Railroad tie production system and method
By introducing concrete and steel bar transportation mechanisms into the track slab production system, multiple track slab production lines can operate simultaneously, solving the problem of low production efficiency in existing technologies and enabling efficient production of multiple track slab models.
Patent Information
- Application Number
- CN202211671420.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-12-26
- Publication Date
- 2025-11-21
- Estimated Expiration
- 2042-12-26
AI Technical Summary
The existing technology has low production efficiency for track slabs and cannot produce different models of track slabs at the same time, requiring the production line to be cleared and the production model to be changed.
The system employs one steel reinforcement production line and one concrete production line. Through concrete transport mechanisms and steel reinforcement transport mechanisms, steel mesh and concrete are transported to multiple track slab production lines, enabling the simultaneous production of various track slab models.
It improves track slab production efficiency, enabling the simultaneous production of multiple track slab models, saving costs and reducing the frequency of production line changes.
Smart Images

Figure CN116100664B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application belongs to the technical field of track slab production, and particularly relates to a track slab production system and method. BACKGROUND
[0002] The track slab refers to a new type of track component in a plate body structure type, used to support and fix the steel rail, and distribute the load transmitted by the steel rail to the base under the plate.
[0003] In the prior art, the production of the track slab is achieved by connecting the steel bars to form a steel mesh, pouring the concrete on the steel mesh, and waiting for the concrete to solidify. However, this method can only produce one type of track slab at a time, and when the type of the track slab to be produced needs to be changed, the production line needs to be emptied and re-injected, which is extremely low in production efficiency. SUMMARY
[0004] In view of the deficiencies in the related art, the present application provides a track slab production system and method, which provides steel mesh for track slab production lines of different types through a steel bar production line, and transports concrete to each track slab production line through a concrete transportation mechanism to pour the track slab, which can simultaneously produce multiple types of track slabs to solve the technical problem of low production efficiency of track slabs in the prior art.
[0005] The present application provides a track slab production system and method, comprising:
[0006] A concrete production line, the concrete production line comprising a mixing station;
[0007] A steel bar production line, the steel bar production line comprising a steel bar storage area, a steel bar processing area, and a steel bar binding area;
[0008] A plurality of track slab production lines, at least one of the plurality of track slab production lines produces a type different from the types produced by the remaining track slab production lines; the track slab production line comprises a concrete pouring area, a steel mesh storage area, a water curing area, a tensioning and anchoring area, and a curing area; all the track slab production lines are located between the concrete production line and the steel bar production line;
[0009] A concrete transportation mechanism, the concrete transportation mechanism being used to transport the concrete mixed by the mixing station to the concrete pouring area of each steel bar production line;
[0010] A steel bar transportation mechanism, the steel bar transportation mechanism being used to transport the bound steel mesh to the steel mesh storage area.
[0011] In the technical scheme, the same steel bar production line can produce different types of steel mesh, and the steel mesh is transported to the corresponding steel mesh storage area in the track plate production line. The steel mesh is moved to the corresponding concrete pouring area, and the concrete is transported to the corresponding concrete pouring area by the concrete transportation mechanism to form the track plate. It can utilize one steel bar production line and one concrete production line to supply multiple track plate production lines, and multiple track plate production lines can produce simultaneously to improve production efficiency.
[0012] In some embodiments, the concrete transportation mechanism includes a concrete transportation channel, a first track arranged in the concrete transportation channel, and a transportation hopper slidably connected to the first track. The concrete pouring areas in all the track production lines are close to the concrete transportation channel.
[0013] In the technical scheme, when pouring concrete, the transportation hopper is moved to the mixing station through the first track, the concrete output by the mixing station enters the transportation hopper, and the transportation hopper moves on the first track to the corresponding track plate production line. The transportation is convenient and fast, and the efficiency is improved.
[0014] In some embodiments, the concrete pouring area, the steel mesh storage area, the water curing area, the tensioning and anchoring area, and the curing area in the track plate production line are arranged in a single direction, and the direction from the concrete pouring area to the curing area is the production direction. Multiple track plate production lines are arranged on both sides of the concrete transportation channel, and the production direction of each track plate is away from the concrete transportation channel.
[0015] In the technical scheme, the layout is reasonable and convenient for concrete transportation. Moreover, the produced track plate in the curing area is close to the edge of the factory building, which facilitates the transportation of the produced track plate.
[0016] In some embodiments, the steel bar transportation mechanism includes a steel bar transportation channel, a second track, and a transportation vehicle. The steel bar transportation mechanism includes two groups and is arranged on both sides of the concrete transportation channel. The steel bar transportation channel passes through between the concrete pouring area and the steel mesh storage area in the track plate production line. The second track is arranged in the steel bar transportation track, and the transportation vehicle is slidably connected to the second track.
[0017] In the technical scheme, multiple track plate production lines located on both sides of the concrete transportation channel can transport steel bars through the transportation vehicle in the corresponding transportation channel. One transportation channel connects multiple track plate production lines to improve work efficiency.
[0018] In some embodiments, at least one mold is arranged in the concrete pouring area; a water curing pool is arranged in the water curing area; a hoisting device is arranged in the track slab production line; and at least one tensioning pedestal is arranged in the tensioning and anchoring area.
[0019] In the technical solution, multiple molds can be used to simultaneously produce multiple track slabs in the track slab production line. The hoisting device is used to transport the steel mesh, the track slab and the transport hopper. The tensioning pedestal is used to place the track slab, and multiple tensioning pedestals can be used to tension multiple track slabs.
[0020] In some embodiments, the length direction of the steel bar production line is the same as the length direction of the track slab production line; and one end of the steel bar production line is further provided with a prestressed steel bar storage area.
[0021] In some embodiments, the concrete transport mechanism, the steel bar transport mechanism, the prestressed steel bar storage area, the steel bar production line and all the track slab production lines are arranged in a factory building, the concrete production line is arranged outside the factory building, and the output end of the mixing station extends into the factory building and corresponds to the concrete transport channel.
[0022] In the technical solution, the layout mode can avoid dust from the mixing station entering the factory building to affect the production of the track slab and the steel bar, and reduce harm to the human body.
[0023] The application further provides a track slab production method, which applies the track slab production system as described above, and the specific steps are as follows:
[0024] Steel mesh manufacturing: moving the steel bars in the steel bar storage area to the steel bar processing area for shearing and bending, and moving the processed steel bars to the steel bar binding area to form a steel mesh by binding;
[0025] Concrete pouring: moving the steel mesh to the mold by using the hoisting device; outputting the concrete output by the mixing station to the transport hopper, lifting the transport hopper by using the hoisting device and moving the transport hopper above the mold in which the steel mesh has been placed, opening the hopper to pour the concrete into the mold;
[0026] Water curing: lifting the track slab by using the hoisting device and immersing the track slab in the water curing pool;
[0027] Track slab tensioning: lifting and moving the track slab to the tensioning and anchoring area by using the hoisting device and placing the track slab on the tensioning pedestal; obtaining the steel bar from the prestressed steel bar area and moving the steel bar to the tensioning and anchoring area, passing the prestressed steel bar through the track slab, tightening the nuts at both ends of the prestressed steel bar, and tightly pressing the nuts against the two sides of the track slab, and continuing to tighten the nuts to stretch the prestressed steel bar.
[0028] In the technical scheme, the rail plate production lines are of different types, so that the multiple rail plate production lines can produce rail plates of different types at the same time. Moreover, the steel bar production line and the concrete production line can simultaneously meet the requirements of the multiple rail plate production lines, thereby maximizing cost saving and improving efficiency.
[0029] In some embodiments, after the pouring of the concrete, the water curing is preceded by a step of steam curing, which is: covering the mold with a tarpaulin, waiting for 18 hours, then removing the tarpaulin and the mold; at this time, the concrete in the mold is solidified to form the rail plate.
[0030] In the technical scheme, the mold is covered with the tarpaulin, steam is generated in the tarpaulin, and the rail plate being formed is cured, so that a reasonable humidity range is provided, and subsequent cracking of the rail plate is avoided.
[0031] In some embodiments, after the tensioning of the rail plate, the step further includes a step of rail plate curing, which is: using hoisting equipment to hoist and move the rail plate to a curing area.
[0032] In the technical scheme, the rail plate is placed in the curing area for curing, so that problems such as cracking of the rail plate caused by large temperature changes of the outside weather are avoided, and the quality of the rail plate is improved.
[0033] Based on the above technical scheme, in the embodiments of the present application, the same steel bar production line can produce steel bar meshes of different types, and the steel bar meshes are transported to the corresponding steel bar mesh storage areas in the rail plate production lines. The steel bar meshes are moved to the corresponding concrete pouring areas, and the concrete is transported to the corresponding concrete pouring areas by the concrete transportation mechanism to pour and form the rail plates. The steel bar production line and the concrete production line can be used to produce and supply multiple rail plate production lines, and the multiple rail plate production lines can produce at the same time, thereby improving the production efficiency. BRIEF DESCRIPTION OF DRAWINGS
[0034] The accompanying drawings, which are included to provide a further understanding of the present application and are incorporated in and constitute a part of this application, illustrate embodiments of the present application and serve to explain the present application. In the drawings:
[0035] Figure 1 It is a whole schematic view of an embodiment of the rail plate production system of the present application;
[0036] Figure 2 It is a schematic view of the rail plate production line in the rail plate production system of the present application;
[0037] Figure 3 It is a flow chart of the rail plate production method of the present application.
[0038] In the drawings:
[0039] 100, concrete production line; 101, sand and stone storage area; 102, feeding conveyor belt; 103, mixing station; 200, track slab production line; 201, concrete pouring area; 2011, mold; 202, steel mesh storage area; 203, water curing area; 2031, water curing pool; 204, tensioning and anchoring area; 205, curing area; 300, steel bar production line; 301, first steel bar storage area; 302, second steel bar storage area; 303, steel bar processing area; 3031, steel bar shearing and bending equipment; 304, first steel bar binding area; 305, second steel bar binding area; 400, longitudinal prestressed steel bar storage area; 500, transverse prestressed steel bar storage area; 600, concrete transportation mechanism; 601, concrete transportation channel; 602, first track; 603, transportation hopper; 700, steel bar transportation mechanism; 701, common transportation channel; 702, steel bar transportation channel; 703, second track; 704, transportation vehicle; 800, outdoor storage area; 900, boiler room; 110, office; 120, warehouse; 130, mechanical processing area. DETAILED DESCRIPTION
[0040] The technical solutions in the embodiments will be described clearly and completely below with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments. Based on the embodiments of the present application, all other embodiments obtained by those skilled in the art without creative work fall within the scope of protection of the present application.
[0041] In the description of the present application, it should be understood that the terms "center", "transverse", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer" and the like indicate the orientation or positional relationship based on the orientation or positional relationship shown in the drawings, and are only for the purpose of facilitating the description of the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a particular orientation, be constructed and operated in a particular orientation, and therefore cannot be understood as a limitation of the present application.
[0042] The terms "first", "second", "third" are only for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of the technical features indicated. Therefore, the features defined with "first", "second", "third" can explicitly or implicitly include one or more of the features.
[0043] In the description of the present application, it should be noted that unless otherwise explicitly specified and limited, the terms "mounting", "connection", "linking" should be understood in a broad sense, for example, it can be fixed connection, or detachable connection, or integrally connected; it can be directly connected, or indirectly connected through intermediate medium, or internal communication of two elements. For those skilled in the art, the specific meaning of the above terms in the present application can be understood according to the specific circumstances.
[0044] As shown in the accompanying drawings Figure 1 and Figure 2 In one illustrative embodiment of the track slab production system of the present application, the track slab production system comprises a concrete production line 100, a steel bar production line 300, a plurality of track slab production lines 200, a concrete transportation mechanism 600 and a steel bar transportation mechanism 700. The concrete production line 100 comprises a mixing station 103. The steel bar production line 300 comprises a steel bar storage area, a steel bar processing area 303 and a steel bar binding area. In the plurality of track slab production lines 200, at least one production line produces a different model from the rest of the track slab production lines 200. The track slab production line 200 comprises a concrete pouring area 201, a steel bar mesh storage area 202, a water curing area 203, a tensioning and anchoring area 204 and a curing area 205. All track slab production lines 200 are located between the concrete production line 100 and the steel bar production line 300. The concrete transportation mechanism 600 is used to transport the mixed concrete from the mixing station 103 to the concrete pouring area 201 of each steel bar production line 300. The steel bar transportation mechanism 700 is used to transport the bound steel bar mesh to the steel bar mesh storage area 202. The same steel bar production line 300 can produce different models of steel bar mesh, which are transported to the corresponding steel bar mesh storage area 202 in the track slab production line 200. The steel bar mesh is moved to the corresponding concrete pouring area 201, and the concrete is transported to the corresponding concrete pouring area 201 by the concrete transportation mechanism 600 to form a track slab. It can utilize one steel bar production line 300 and one concrete production line 100 to produce and supply multiple track slab production lines 200, and multiple track slab production lines 200 can produce simultaneously to improve production efficiency.
[0045] Specifically, the concrete production line 100 further comprises a sand and stone storage area 101 and a feeding conveyor 102, and the output end of the feeding conveyor 102 corresponds to the input end of the mixing station 103. The input end of the feeding conveyor 102 is close to the sand and stone storage area 101.
[0046] In an embodiment, the concrete transportation mechanism 600 comprises a concrete transportation channel 601, a first track 602 arranged in the concrete transportation channel 601, and a transportation hopper 603 slidably connected to the first track 602. The concrete pouring area 201 in each track slab production line is close to the concrete transportation channel 601. When pouring concrete, the transportation hopper 603 is moved to the mixing station 103 through the first track 602, the concrete output by the mixing station 103 enters the transportation hopper 603, and the transportation hopper 603 moves on the first track 602 to the corresponding track slab production line 200, which is convenient and fast for transportation and improves efficiency.
[0047] Specifically, the concrete transportation channel 601 and the first track 602 are in a straight line. When there are only two production lines, the two production lines are symmetrically arranged on the two sides of the concrete transportation channel 601.
[0048] In an embodiment, the concrete pouring area 201, the steel mesh storage area 202, the water curing area 203, the tensioning and anchoring area 204, and the curing area 205 in the track slab production line 200 are arranged in a single direction, and the direction from the concrete pouring area 201 to the curing area 205 is the production direction; a plurality of track slab production lines 200 are arranged on the two sides of the concrete transportation channel 601, and the production direction of each track slab production line 200 is towards the side away from the concrete transportation channel 601. This layout is reasonable and facilitates the transportation of concrete. Moreover, the produced track slab in the curing area 205 is close to the edge of the factory building, which facilitates the transportation of the produced track slab out of the factory.
[0049] Specifically, the production direction of the track slab production line 200 is arranged along the length direction of the track slab production line 200. The length directions of the track slab production lines 200 are parallel to each other. The length direction of the track slab production line 200 is perpendicular to the length direction of the concrete transportation channel 601.
[0050] Preferably, the number of track slab production lines 200 on the two sides of the concrete transportation channel 601 is the same or the difference in number is 1.
[0051] Specifically, four track slab production lines 200 are arranged, and two of the track slab production lines 200 are arranged on the two sides of the concrete transportation channel 601.
[0052] Further, at least one of the track slab production lines 200 can produce two types of track slabs.
[0053] As shown in FIG. 1, the track slab production line 200 comprises a concrete pouring area 201, a steel mesh storage area 202, a water curing area 203, a tensioning and anchoring area 204, and a curing area 205. Figure 1 and Figure 2As shown, in one embodiment, the rebar storage area includes a first rebar storage area 301 and a second rebar storage area 302, and the rebars stored in the first rebar storage area 301 and the second rebar storage area 302 are of different types. The corresponding rebar type can be selected according to different models of track slabs.
[0054] Preferably, the first steel bar storage area 301 is an epoxy-coated steel bar storage area, and the second steel bar storage area 302 is a regular steel bar storage area.
[0055] In one embodiment, a steel bar shearing and bending device 3031 is provided in the steel bar processing area 303. The steel bars are sheared or bent by the steel bar shearing and bending device 3031.
[0056] In one embodiment, the rebar production line 300 further includes a finished rebar storage area. A first rebar storage area 301, a second rebar storage area 302, a rebar processing area 303, a finished rebar storage area, and a rebar binding area are arranged in a single direction to form the rebar production line 300. Finished rebar processed by the rebar shearing and bending equipment 3031 is transported to the finished rebar storage area, and then moved from the finished rebar storage area to the rebar binding area for manual binding to form a rebar mesh.
[0057] In one embodiment, the rebar tying area includes a first rebar tying area 304 and a second rebar tying area 305. The first rebar tying area 304 is used to tie rebars of the corresponding type in the first rebar storage area 301, and the second rebar tying area 305 is used to tie rebars of the corresponding type in the second rebar storage area 302. Multiple first rebar tying areas 304 and multiple second rebar tying areas 305 are provided at intervals.
[0058] As attached Figure 1 and Figure 2 As shown, in one embodiment, the rebar transport mechanism 700 includes a rebar transport channel 702, a second track 703, and a transport vehicle 704. The rebar transport mechanism 700 includes two sets, respectively located on both sides of the concrete transport channel 601. The rebar transport channel 702 passes through the concrete pouring area 201 and the rebar mesh storage area 202 of the track slab production line 200. The second track 703 is located within the rebar transport track, and the transport vehicle 704 is slidably connected to the second track 703. Multiple track slab production lines 200 located on both sides of the concrete transport channel 601 can transport rebar via the transport vehicle 704 in their respective transport channels. One transport channel connects multiple track slab production lines 200, improving work efficiency.
[0059] Specifically, the length direction of the steel bar production line 300 is the same as that of the track slab production line 200. The length direction of the steel bar binding area is the same as that of the track slab production line 200. The steel bar transportation mechanism 700 further includes a common transportation passage 701. The length direction of the common transportation passage 701 is the same as that of the steel bar binding area, and the common transportation passage 701 is adjacent to the steel bar binding area. The common transportation passage 701 is arranged on one side of the steel bar binding area close to the track slab production line 200. Two steel bar transportation passages 702 are respectively communicated with both ends of the common transportation passage 701, and the transport vehicle 704 can enter the common transportation passage 701. The tied steel bar mesh can select any one of the steel bar transportation passages 702 through the common transportation passage 701.
[0060] As shown in the appendix Figure 1 and Figure 2 In an embodiment, as shown, at least one mold 2011 is arranged in the concrete pouring area 201; a water curing pool 2031 is arranged in the water curing area 203; a hoisting device is arranged in the track slab production line 200; at least one tensioning pedestal is arranged in the tensioning and anchoring area 204. In the track slab production line 200, multiple track slabs can be produced simultaneously through multiple molds 2011. The hoisting device is used to transport steel bar meshes, track slabs and the transport hopper 603. The tensioning pedestal is used to place track slabs, and multiple tensioning pedestals can perform tensioning work on multiple track slabs.
[0061] Specifically, the track slab production line 200 for producing different types of track slabs mainly lies in the different molds 2011 and / or steel bar meshes. The models of the molds 2011 in the same track slab production line 200 are the same.
[0062] More specifically, the hoisting device is selected as a gantry crane.
[0063] In an embodiment, in a track slab production line 200, four water curing pools 2031 are arranged. The four water curing pools 2031 are adjacent to each other in pairs to form a "field" shape. During the track slab production process, three water curing pools 2031 are used, and the remaining one water curing pool 2031 is used as a spare. An overflow channel is arranged between the water curing pools 2031, so that the curing water in the water curing pools 2031 can flow and circulate with each other, without being pumped by a water pump, thus saving water.
[0064] In an embodiment, a prestressed steel bar storage area is further arranged at one end of the steel bar production line 300.
[0065] Specifically, the prestressed steel bar storage area includes a longitudinal prestressed steel bar storage area 400 and a transverse prestressed steel bar storage area 500.
[0066] In an embodiment, the concrete transport mechanism 600, the steel bar transport mechanism 700, the prestressed steel bar storage area, the steel bar production line 300 and the whole track slab production line 200 are arranged in the factory building, the concrete production line 100 is arranged outside the factory building, and the output end of the mixing station 103 extends into the factory building and corresponds to the concrete transport channel 601. This layout can avoid the dust of the mixing station 103 from entering the factory building to affect the production of the track slab and the steel bar, and reduce the harm to the human body.
[0067] As shown in FIGS. 1 to 3, in an embodiment, the factory building is provided with an outdoor storage area 800 and a travelling crane channel outside the factory building. Figure 1 Figure 2 As shown in FIGS. 1 to 3, in an embodiment, the factory building is provided with an outdoor storage area 800 and a travelling crane channel outside the factory building.
[0068] In an embodiment, the factory building is further provided with a boiler room 900 outside the factory building. When steam curing is performed, the boiler room 900 is used for boiling water and heat preservation in winter construction
[0069] In an embodiment, the factory building is further provided with a company office, a warehouse 120 and a mechanical processing area 130 on the side of the factory building far away from the steel bar storage area.
[0070] As shown in FIGS. 1 to 3, in an embodiment, the factory building is provided with an outdoor storage area 800 and a travelling crane channel outside the factory building. Figure 3 The application further provides a track slab production method, which applies the track slab production system as described above, and the specific steps are as follows:
[0071] S100: Steel bar mesh manufacturing: moving the steel bars in the steel bar storage area to the steel bar processing area 303 for shearing and bending, and moving the processed steel bars to the steel bar binding area to form a steel bar mesh by binding;
[0072] S300: Pouring concrete: moving the steel bar mesh to the mold 2011 by using the hoisting equipment; the concrete output from the mixing station 103 is output to the transport hopper 603, the hoisting equipment is used to hoist the transport hopper 603 and move it to the top of the mold 2011 in which the steel bar mesh has been placed, the hopper is opened to pour the concrete into the mold 2011;
[0073] S500: Water curing: hoisting the track slab by using the hoisting equipment and immersing it into the water curing pool 2031;
[0074] S600: Track slab tensioning: hoisting the track slab by using the hoisting equipment and placing it on the tensioning anchor area 204; obtaining the steel bar from the prestressed steel bar area and moving it to the tensioning anchor area 204, passing the prestressed steel bar through the track slab, tightening the nuts at both ends of the prestressed steel bar, the nuts abutting against the two sides of the track slab, and continuing to tighten the nuts to stretch the prestressed steel bar.
[0075] The track slab production lines 200 are of different models, so that multiple track slab production lines 200 can simultaneously produce track slabs of different models. Moreover, the steel bar production line 300 and the concrete production line 100 can simultaneously meet the needs of multiple track slab production lines 200, thereby maximizing cost savings while improving efficiency.
[0076] In an embodiment, the S100 steel bar mesh manufacturing: moving the steel bars in the steel bar storage area to the steel bar processing area 303 for shearing and bending, and moving the processed steel bars to the steel bar binding area to manually bind the steel bars into a steel bar mesh. The specific steps are as follows: according to the production requirements, obtaining steel bars from the first steel bar storage area 301 and / or the second steel bar storage area 302 and transporting them to the steel bar processing area 303, shearing or bending the steel bars by the steel bar shearing and bending equipment 3031 in the steel bar processing area 303. Transporting the finished steel bars processed by the steel bar shearing and bending equipment 3031 to the finished steel bar storage area, and manually binding the finished steel bars from the finished steel bar storage area to the steel bar binding area to form a steel bar mesh.
[0077] In an embodiment, before the step S300 of pouring concrete, there is a step S200 of concrete production, the steps of which are as follows: inputting the sand and gravel in the sand and gravel storage area 101 from the input end of the feeding conveyor 102, and inputting the sand and gravel into the input end of the mixing station 103 by the feeding conveyor 102.
[0078] In the step S300 of pouring concrete, after moving the steel bar mesh into the mold 2011 by the hoisting equipment, the subsequent steps are as follows: manually spraying release agent in the mold 2011, and installing sleeves and spiral bars at designated positions. After the installation is completed, the hoisting equipment is used to lift and transport the hopper 603 to above the mold 2011 in which the steel bar mesh has been placed, the hopper is opened, and the concrete is poured into the mold 2011.
[0079] In an embodiment, in the step S300 of pouring concrete, after the hopper is opened to pour the concrete into the mold 2011, the subsequent steps are as follows: manually leveling the upper surface of the concrete in the mold 2011.
[0080] In an embodiment, after pouring the concrete, before curing, there is a step S400 of steam curing, the steps of which are as follows: installing a curing shed frame on the mold 2011, covering the mold 2011 with a tarpaulin on the curing shed frame, and setting a temperature measuring probe inside the tarpaulin. After waiting for 18 hours, the tarpaulin is removed, and the mold 2011 is removed; at this time, the concrete in the mold 2011 is solidified to form a track slab. By covering the mold 2011 with the tarpaulin, steam appears inside the tarpaulin, which cures the track slab being formed, provides a reasonable humidity range, and avoids subsequent cracking of the track slab.
[0081] In an embodiment, the specific steps of lifting the track slab by the lifting device and immersing the track slab into the water curing pool 2031 in step S500 of water curing are as follows: manually removing the mold 2011, lifting the track slab upward, lifting the track slab by the lifting device, and moving above the water curing pool 2031, and lowering the track slab to immerse the track slab into the water curing pool 2031.
[0082] In an embodiment, the specific steps of obtaining the steel bars from the prestressed steel bar area and moving to the tensioning anchorage area 204, and inserting the prestressed steel bars through the track slab in step S600 of track slab tensioning are as follows: moving the plurality of longitudinal prestressed steel bars and the plurality of transverse prestressed steel bars close to the tensioning anchorage area 204 by the lifting device from the longitudinal prestressed steel bar area and the transverse prestressed steel bar area. The longitudinal prestressed steel bars and the transverse prestressed steel bars are inserted into the corresponding anchoring holes on the track slab. It is worth noting that the anchoring holes are formed by the mold 2011 in step S300 of pouring concrete.
[0083] In an embodiment, the specific steps of tightening the nuts at both ends of the prestressed steel bar, abutting the nuts against both sides of the track slab, and continuing to tighten the nuts to stretch the prestressed steel bar in step S600 of track slab tensioning are as follows: tightening the nuts by the tensioning device. The tensioning force can be accurately controlled.
[0084] In an embodiment, the steps after tightening the nuts by the tensioning device in step S600 of track slab tensioning are as follows: mixing the anchoring mortar, and filling the anchoring holes with the anchoring mortar.
[0085] In an embodiment, the steps after step S600 of track slab tensioning further include step S700 of track slab curing, which is as follows: lifting the track slab by the lifting device and moving to the curing area 205. The track slab is placed in the curing area 205 for curing, which avoids large temperature changes in the outside weather from causing the track slab to crack and improves the quality of the track slab.
[0086] After step S700 of track slab curing, step S800 of track slab storage is further included, which is as follows: after the track slab is stored in the curing area 205 for 24 days, the track slab is transported to the outdoor storage area 800 for storage.
[0087] Finally, it should be noted that: the embodiments in the specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts of each embodiment can be referred to each other.
[0088] The above examples are only used to illustrate the technical solutions of the present application but not to limit the present application; although the present application has been described in detail with reference to the preferred embodiments, it is understood by the person of ordinary skill in the art that the specific embodiments of the present application can be modified or some technical features can be replaced by equivalent ones without departing from the spirit of the technical solutions of the present application, and all of them should be covered in the technical solution range of the present application claimed.
Claims
1. A track panel production system, characterized by, include: A concrete production line, wherein the concrete production line includes a batching plant; A steel bar production line, comprising a steel bar storage area, a steel bar processing area, and a steel bar binding area; Multiple track slab production lines are provided, and at least one of these production lines produces a different model of track slab than the others. Each track slab production line includes a concrete pouring area, a steel mesh storage area, a water curing area, a tensioning and anchoring area, and a maintenance area. All of the track slab production lines are located between the concrete production line and the steel mesh production line. A concrete transport mechanism is used to transport the concrete mixed at the batching plant to the concrete pouring area of each of the steel reinforcement production lines. A steel bar transport mechanism, used to transport the tied steel bar mesh to the steel bar mesh storage area; The concrete transport mechanism includes a concrete transport channel, a first track, and a transport hopper. The first track is disposed within the concrete transport channel, and the transport hopper is slidably connected to the first track. All concrete pouring areas in the aforementioned track slab production lines are located close to the concrete transport channel; In the track slab production line, the concrete pouring area, the steel mesh storage area, the water curing area, the tensioning and anchoring area, and the curing area are arranged in a single direction, and the direction from the concrete pouring area to the curing area is the production direction; multiple track slab production lines are arranged on both sides of the concrete transport channel, and the production direction of each track slab is towards the side away from the concrete transport channel. The steel bar transportation mechanism includes a steel bar transportation channel, a second track, and a transportation vehicle; the steel bar transportation mechanism includes two sets, which are respectively arranged on both sides of the concrete transportation channel; the steel bar transportation channel runs through the concrete pouring area and the steel bar mesh storage area in the track slab production line, the second track is arranged in the steel bar transportation channel, and the transportation vehicle is slidably connected to the second track.
2. The track panel production system of claim 1, wherein, At least one mold is provided in the concrete pouring area; a water curing pool is provided in the water curing area; lifting equipment is provided in the track slab production line; and at least one tensioning platform is provided in the tensioning and anchoring area.
3. The track panel production system of claim 2, wherein, The length direction of the steel bar production line is the same as that of the track slab production line; a prestressed steel bar storage area is also provided at one end of the steel bar production line.
4. The track panel production system of claim 3, wherein, The concrete transport mechanism, the steel bar transport mechanism, the prestressed steel bar storage area, the steel bar production line, and all track slab production lines are located inside the plant. The concrete production line is located outside the plant. The output end of the mixing plant extends into the plant and corresponds to the concrete transport channel.
5. A method of producing a track slab, characterized by, It utilizes the track slab production system as described in claim 4, and its specific steps are as follows: Steel mesh manufacturing: The steel bars in the steel bar storage area are moved to the steel bar processing area for cutting and bending. The processed steel bars are then moved to the steel bar binding area and bound to form a steel mesh. Pouring concrete: using lifting equipment to move the steel mesh into the mold; the output of the concrete output by the mixing station is output to the transport hopper, and the lifting equipment is used to lift the transport hopper and move it above the mold into which the steel mesh has been placed, the hopper is opened to pour the concrete into the mold; Watering: using lifting equipment to lift the track plate and immerse it in the water tank; Track plate tensioning: using lifting equipment to lift the track plate and move it to the tensioning anchorage area and place it on the tensioning pedestal; obtaining a steel rod from the pre-stressed steel rod area and moving it to the tensioning anchorage area, threading the pre-stressed steel rod through the track plate, tightening the nuts on both ends of the pre-stressed steel rod, the nuts abutting against both sides of the track plate, and continuing to tighten the nuts to stretch the pre-stressed steel rod.
6. The track plate production method according to claim 5, wherein After the pouring of concrete, the water curing step before the track plate tensioning step includes a steam curing step, which is: covering the mold with a tarpaulin, waiting for 18 hours, removing the tarpaulin, and removing the mold; at this time, the concrete in the mold has solidified to form a track plate.
7. The track plate production method according to claim 6, wherein The track plate tensioning step is followed by a track plate curing step, which is: using lifting equipment to lift the track plate and move it to the curing area.
Citation Information
Patent Citations
Parallel PC component production system
CN110355866A
Continuous production line for manufacturing pre-stressed concrete track slabs applied to high-speed railway
CN204278213U
Pedestal method production line for high-speed railway assembled bridge deck accessory structure prefabricated member
CN212795365U