Pile foundation construction method of segmented casing on demand in vertical string karst cave area

By setting up protective tubes and protective nets in sections as needed in karst areas, combined with geological survey and construction technology, the problem of unpredictability and danger in karst cave treatment is solved, the efficiency and quality of pile foundation construction are improved, and the safety of the bridge structure is ensured. Security.

CN116220090BActive Publication Date: 2024-10-11THE FIRST ENGINEERING COMPANY OF CCCC FOURTH HARBOUR ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310420240.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-04-18
Publication Date
2024-10-11
Estimated Expiration
2043-04-18

AI Technical Summary

Technical Problem

When constructing large-diameter pile foundations in karst areas, the treatment of caves is unpredictable and dangerous. Especially the construction of pile foundations in string-shaped caves can easily lead to accidents such as slurry leakage, hammer jamming, buried hammers, broken piles, etc., affecting the bridge structure. Safety.

Method used

The pile foundation construction method of segmenting the casing as needed in the vertical string cave area is adopted. By identifying the type of cave and the mechanical properties of the rock strata, the inner casing and protective net are set up in segments as needed, combined with the use of crawler cranes and vibrating hammers, to ensure The protective tube should be installed vertically, and a cave treatment plan should be formulated based on geological survey data before construction, using steel cages and underwater concrete for pouring.

Benefits of technology

It improves the pile forming efficiency and pile forming quality of the pile foundation, ensures the smooth formation of pile holes and piles, meets the bearing capacity requirements, reduces construction risks, and ensures the safety of the bridge structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116220090B_ABST
    Figure CN116220090B_ABST
Patent Text Reader

Abstract

The invention discloses a pile foundation construction method of segmented casing as required in a vertical string karst cave area, which is applicable to the technical field of pile foundation construction of bridge buildings. The method comprises the steps of construction preparation, positioning of an impact pile drill, burying of an open-hole casing, segmented follow-up construction of an inner casing and a protective net as required, manufacturing and installing a steel cage, and pouring underwater concrete. The segmented follow-up construction of the inner casing and a protective net as required specifically comprises the following steps: identifying the type of karst cave and the follow-up of the inner casing and a protective net, arranging a plurality of segments of inner casing as required for the corresponding karst cave type under the main pier pile foundation, and overlapping a protective net tube between two segments of inner casing, so as to solve the construction difficulties caused by adverse geological conditions such as multi-layer karst caves, improve the pile formation efficiency and pile formation quality of the pile foundation, ensure that the pile hole is smoothly drilled and piled and meets the bearing capacity requirements, so as to ensure the structural safety of the bridge.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge building pile foundation construction, and in particular to a pile foundation construction method of a vertical string-shaped karst cave area with segmented casings as required. Background Art

[0002] This application is based on the construction of the main pier pile foundation of the Liuxi River Bridge. The site of the Liuxi River Bridge reveals that the Carboniferous bedrock is mainly limestone, which is a typical karst geological area with strongly developed caves and complex dissolution fissures. The difficulty of carrying out large-diameter pile foundation construction in such a complex and changeable karst area is self-evident. Cave treatment is the primary technical risk in the main pier pile foundation construction. There are many soil caves and karst caves in the strata within the bridge location area of ​​this project. The distribution space and depth of the karst caves are somewhat random, the rock surface is buried at different depths and the strength is uneven. A series of string-like karst caves are formed by karst action. The pile foundation construction of string-like karst cave piles in karst areas has always been the focus and difficulty of pile foundation construction in karst areas. The pile foundation construction of karst caves is unpredictable and dangerous, especially the pile foundation construction of string-like karst caves. Compared with traditional pile foundation construction, more attention should be paid to the bearing capacity of the pile foundation to ensure the overall bearing capacity of the highway or bridge and avoid settlement problems in the later period. If the karst cave treatment method is improper, it will often cause accidents such as drill drop, hammer jam, buried hammer, slurry leakage, hole collapse, and pile breakage, and even seriously affect the structural safety of the bridge.

[0003] Conventional string-shaped karst pile foundation construction usually adopts the method of lowering steel casing, using rotary drilling to dig the guide hole, and finally pouring concrete to form the pile. If pressurized water is encountered during the pile foundation construction, no measures will be taken at the location of the construction process, which is easy to cause water gushing. Other common problems include leakage, deflection, stuck drill, broken piles, etc. Therefore, in order to ensure that there is no leakage during the construction of the main pier pile foundation of Liuxi River Bridge, or that there is no collapse in the event of leakage, and to ensure that the pile hole is smoothly formed and piles are formed and meet the bearing capacity requirements, the geological survey data is used before construction to determine the karst stratum conditions, karst cavity size, karst fillings, etc., and a karst cave treatment plan is formulated for each pile, and casing and net are set up in sections as needed to solve the above construction problems and improve the pile foundation efficiency and pile quality. Summary of the invention

[0004] The purpose of the present invention is to provide a pile foundation construction method with segmented casings as needed in vertical string cave areas, to solve the construction difficulties caused by unfavorable geology such as multi-layer caves, to improve the pile foundation efficiency and pile quality, to ensure that pile holes are drilled and piles are formed smoothly and meet the bearing capacity requirements, so as to ensure the structural safety of the bridge.

[0005] To achieve the above object, the present invention provides the following technical solutions:

[0006] The pile foundation construction method of the vertical string karst cave area with segmented casing on demand includes the following steps: construction preparation, positioning of the impact pile drilling machine, burying of the hole casing, segmented follow-up construction of the inner casing and protective net on demand, production and installation of the steel cage, and pouring of underwater concrete. The segmented follow-up construction of the inner casing and protective net on demand specifically includes the following steps:

[0007] Step 1) Identify the types of caves. According to geological survey data, the types of caves include small caves, medium caves, large caves, easily collapsed soil layers and soil caves;

[0008] Step 2) Follow-up of inner casing and protective net: according to the corresponding cave type under the main pier pile foundation, several sections of inner casing are set up in sections as needed, and a protective net tube is overlapped between two sections of the inner casing;

[0009] Step 3) Casing installation: The inner casing and protective net are followed up by a crawler crane and a vibrating hammer to be driven into place. During the vibration sinking process, two total stations are used to observe from two directions to ensure the verticality of the casing installation.

[0010] As a preferred technical solution of the present invention, the type of cave is identified by judging the type of cave according to the formation conditions, cavity size and fillings of the cave. The specific judgment method is:

[0011] The small karst caves are divided into small karst caves close to buildings, small karst caves with easily collapsed soil layers in the overlying layer, and small string-shaped karst caves;

[0012] The medium-sized caves include fully filled caves or pre-treated medium-sized caves far away from structures, medium-sized caves with half-filled or no filling and cave roof rock thickness ≤ 1m, medium-sized caves with full filling and cave roof rock thickness > 1m adjacent to structures, and medium-sized string-shaped caves;

[0013] The large karst caves include large karst caves with a cave top rock layer thickness of ≤1m, large karst caves with a cave top rock layer thickness of >1m, and large string-shaped karst caves;

[0014] Soil layers and soil holes prone to collapse: soft plastic and fluid plastic silty clay.

[0015] As a preferred technical solution of the present invention, the inner diameter of the inner casing is made of a steel plate 20 cm larger than the pile diameter and with a wall thickness of 8 to 20 mm; the protective net tube is made of a steel wire mesh, and the diameter of the steel wire mesh is 3 to 8 mm;

[0016] The judgment method of the small series of caves is that the height of a single cave is H≤3m, or multiple caves, the height of a single cave is <3m, they are not filled caves and the interval distance is >3m, collectively referred to as Class I caves, the Class I caves use an inner casing with a wall thickness of 8 to 12mm, and the protective net tube is made of a steel wire mesh made of steel wire with a diameter of 3 to 5mm;

[0017] The determination method for the medium-sized string-shaped karst caves is that the height of a single cave is 3m < H < 10m, or the spacing between multiple karst caves is small, and the cumulative height of the karst caves > 3m, which are collectively referred to as type II karst caves; for the type II karst caves, an inner casing with a wall thickness of 10 - 14mm is used, and the casing net is made of a wire mesh rolled from steel wires with a diameter of 4 - 6mm;

[0018] The determination method for the large-sized string-shaped karst caves: the height of a single cave is H ≥ 10m, or the spacing between multiple karst caves is small, and the cumulative height of the karst caves ≥ 10m, which are collectively referred to as type III karst caves; for the type III karst caves, an inner casing with a wall thickness of 12 - 20mm is used, and the casing net is made of a wire mesh rolled from steel wires with a diameter of 5 - 8mm;

[0019] The above-mentioned large, medium, and small-sized string-shaped karst caves are fully filled or semi-filled, and the filling material is fluid plastic silty clay.

[0020] As a preferred technical solution of the present invention, according to the mechanical properties of the rock strata between the vertical string-shaped karst caves, they are divided into weakly weathered, moderately weathered, and strongly weathered rock strata. When encountering the weakly weathered rock strata, the embedding depth of the inner casing into the rock strata is 0.1m < D ≤ 0.3m; when encountering the moderately weathered rock strata, the embedding depth of the inner casing into the rock strata is 0.2m < D ≤ 0.4m, and when encountering the strongly weathered rock strata, the embedding depth of the inner casing into the rock strata is 0.3m < D ≤ 0.5m.

[0021] As a preferred technical solution of the present invention, for the follow-up of the inner casing and casing net of the main pier pile foundation, at least one section of inner casing is set according to the corresponding karst cave type under the main pier pile foundation. The inner casing follows up to the bottom surface of the karst cavity of the karst cave. When there are multiple layers of karst caves vertically distributed within the range of the main pier pile foundation, after the inner casing passes through the bottom surface of the karst cavity of the first layer of karst cave, a section of casing net is welded and lapped, and a second section of inner casing is continuously lapped below the casing net and follows up to the bottom surface of the karst cavity of the next layer of karst cave, and so on until the wall construction of all the karst cavities of multiple layers of karst caves is completed. A casing net is lapped between every two inner casings.

[0022] Further preferably, during the follow-up process of the inner casing and casing net, a single-layer casing or a double-layer casing is set. A single-layer casing is set for all karst cave types;

[0023] For the string-shaped karst caves: when setting a double-layer casing, the outer casing follows up to the rock strata, and the inner casing follows up to the bottom of the lowest layer of karst cave; when setting a single-layer casing, the single-layer casing follows up to the bottom of the lowest layer of karst cave; at least one section of inner casing is set for the inner casing of the single-layer casing or the double-layer casing, and a casing net is lapped between every two inner casings.

[0024] As a preferred technical solution of the present invention, when setting a single-layer casing for the karst cave type without string-shaped karst caves,

[0025] For small karst caves, inner casing and protective net are used to follow up to 2.5m below the prone-to-collapse layer;

[0026] For medium and large caves, inner casing and net are used to follow up to the rock layer;

[0027] The soil cave uses an inner casing to follow up to 1.0m below the bottom of the soil cave, but does not enter the rock layer;

[0028] In addition, for the cave types without string-like caves, single-layer casing is set, and the wall of each pile cave is completed in conjunction with the backfill wall building method. A three-phase mixture of stone flakes, clay, and bagged cement (weight ratio: 6.5:3:0.5) is used for backfill wall building.

[0029] Further preferably, the inner diameter of the single-layer casing or the inner diameter of the inner casing of the double-layer casing is rolled from a steel plate 20 cm larger than the pile diameter and with a wall thickness of 8 to 20 mm; the outer casing of the double-layer casing is rolled from a steel plate 40 cm larger than the pile diameter and with a wall thickness of 8 to 20 mm.

[0030] As a preferred technical solution of the present invention, in the step of burying the perforated casing, when the perforated casing is buried, the deviation between the center of the top surface of the perforated casing and the designed pile position shall not be greater than 5 cm, and the inclination shall not be greater than 0.5% (1 / 200), so as to meet the process requirements of following up the inner casing and protective net when treating the cave in the next step.

[0031] To sum up, compared with the prior art, the beneficial effects of the present invention are as follows: before construction, the present invention determines the karst stratum conditions, karst cavity size, karst cave fillings, etc. according to the detailed geological survey data, formulates a karst cave treatment plan for each pile, and sets up casing and protective nets in sections as needed. First, the karst cave type is identified, and the vertical string karst caves are divided into Class I, Class II and Class III karst caves. Then, according to the mechanical properties of the rock strata between the vertical string karst caves, they are divided into weakly weathered, moderately weathered and strongly weathered rock strata, and then the wall thickness and overlap depth of the inner casing are determined. This on-demand segmented setting method can complete the pier pile foundation construction in a simple, fast, low-cost and high-quality manner, solve the construction difficulties caused by adverse geology such as multi-layer karst caves, improve the pile foundation efficiency and pile quality, ensure that the pile holes are drilled and piled smoothly and meet the bearing capacity requirements, so as to ensure the structural safety of the bridge. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 This is a process flow chart of the pile foundation construction hole-forming process of the present invention;

[0033] Figure 2 This is a schematic diagram of a double-layer casing follow-up structure for three-layer vertical string-shaped caves according to Example 1 of the present invention;

[0034] Figure 3 It is a partial enlarged view of A of Example 1 of the present invention;

[0035] Figure 4 This is a schematic diagram of a single-layer casing follow-up structure for a small karst cave without a string-like karst cave according to Embodiment 2 of the present invention;

[0036] Figure 5 This is a schematic diagram of a single-layer casing follow-up structure for a medium-sized cave without a string-like cave according to Example 3 of the present invention;

[0037] Figure 6 This is a schematic diagram of a single-layer casing follow-up structure for a soil cave without a string-like karst cave according to Embodiment 4 of the present invention;

[0038] In the figure: 1-opening casing, 2-outer casing, 3-inner casing, 31-first section inner casing, 32-second section inner casing, 33-third section inner casing, 4-net protection tube, 41-first section net protection tube, 42-second section net protection tube, 5-inner casing wall thickness, 6-lap depth. DETAILED DESCRIPTION

[0039] The specific embodiments of the present invention are further described below in conjunction with the accompanying drawings. It should be noted that the description of these embodiments is used to help understand the present invention, but does not constitute a limitation of the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0040] like Figure 1 As shown, the pile foundation construction method of the vertical string karst cave area with segmented casing as required includes the following steps: construction preparation, positioning of the impact drilling pile driver, burying of the hole casing, segmented follow-up construction of the inner casing and protective net as required, production and installation of the steel cage, and pouring of underwater concrete. The segmented follow-up construction of the inner casing and protective net as required specifically includes the following steps:

[0041] Step 1) Identify the types of caves. According to geological survey data, the types of caves include small caves, medium caves, large caves, easily collapsed soil layers and soil caves;

[0042] Step 2) Follow-up of inner casing and protective net: according to the corresponding cave type under the main pier pile foundation, several sections of inner casing are set up in sections as needed, and a protective net tube is overlapped between two sections of the inner casing;

[0043] Step 3) Casing installation: The inner casing and protective net are followed up by a crawler crane and a vibrating hammer to be driven into place. During the vibration sinking process, two total stations are used to observe from two directions to ensure the verticality of the casing installation.

[0044] As a preferred implementation of the embodiment, the type of cave is identified by judging the type of cave according to the formation conditions, cavity size and fillings of the cave. The specific judgment method is:

[0045] The small karst caves are divided into small karst caves adjacent to buildings, small karst caves with collapsible soil layers in the overburden layer, and small string-shaped karst caves;

[0046] The medium karst caves include fully filled karst caves or medium karst caves that have been pre-treated and are far from the buildings and structures, medium karst caves that are semi-filled or unfilled and the thickness of the rock layer on the top of the karst cave is ≤ 1m, fully filled medium karst caves adjacent to the buildings and structures and the thickness of the rock layer on the top of the karst cave is > 1m, and medium string-shaped karst caves;

[0047] The large karst caves include large karst caves with the thickness of the rock layer on the top of the karst cave ≤ 1m, large karst caves with the thickness of the rock layer on the top of the karst cave > 1m, and large string-shaped karst caves;

[0048] Collapsible soil layer and soil cave: Soft plastic and flowing plastic silty clay.

[0049] As a preferred implementation manner of the embodiment, the inner casing has an inner diameter that is 20 cm larger than the pile diameter and is made of a steel plate with a wall thickness of 8 - 20 mm; the wire mesh casing is made of a wire mesh rolled up, and the wire diameter of the wire mesh is 3 - 8 mm;

[0050] The judgment method for the small string-shaped karst cave is that the height of a single cave H ≤ 3m, or for multiple karst caves, each single karst cave is < 3m, which does not belong to the filled karst cave and the spacing distance is > 3m, and they are collectively referred to as type I karst caves. The inner casing of type I karst caves has a wall thickness of 8 - 12 mm, and the wire mesh casing is made of a wire mesh rolled up with wires with a diameter of 3 - 5 mm;

[0051] The judgment method for the medium string-shaped karst cave is that the height of a single cave 3m < H < 10m, or the spacing of multiple karst caves is small, and the cumulative height of the karst caves > 3m, and they are collectively referred to as type II karst caves; the inner casing of type II karst caves has a wall thickness of 10 - 14 mm, and the wire mesh casing is made of a wire mesh rolled up with wires with a diameter of 4 - 6 mm;

[0052] The judgment method for the large string-shaped karst cave: the height of a single cave H ≥ 10m, or the spacing of multiple karst caves is small, and the cumulative height of the karst caves ≥ 10m, and they are collectively referred to as type III karst caves; the inner casing of type III karst caves has a wall thickness of 12 - 20 mm, and the wire mesh casing is made of a wire mesh rolled up with wires with a diameter of 5 - 8 mm;

[0053] The above-mentioned large, medium and small string-shaped karst caves are fully filled or semi-filled, and the filling material is flowing plastic silty clay.

[0054] As a preferred embodiment of the example, the rock formations between the vertical string - shaped karsts are divided into weakly weathered, moderately weathered, and strongly weathered rock formations according to their mechanical properties. When encountering the weakly weathered rock formation, the embedding depth of the inner casing into the rock formation is 0.1m < D ≤ 0.3m; when encountering the moderately weathered rock formation, the embedding depth of the inner casing into the rock formation is 0.2m < D ≤ 0.4m; when encountering the strongly weathered rock formation, the embedding depth of the inner casing into the rock formation is 0.3m < D ≤ 0.5m.

[0055] As a preferred embodiment of the example, for the follow - up of the inner casing protection net, at least one section of the inner casing is set according to the corresponding karst type under the main pier pile foundation. The inner casing is followed up to the bottom surface of the karst cavity. When there are multiple layers of karsts vertically distributed within the range of the main pier pile foundation, after the inner casing passes through the bottom surface of the karst cavity of the first layer, a section of the protection net cylinder is welded and overlapped, and the second section of the inner casing is continuously overlapped below the protection net cylinder and followed up to the bottom surface of the karst cavity of the next layer, and so on until the wall construction of all karst cavities of multiple layers of karsts is completed. One protection net cylinder is overlapped between every two inner casings.

[0056] In a further preferred embodiment, a single - layer casing or a double - layer casing is set during the follow - up process of the inner casing protection net, and a single - layer casing is set for all karst types;

[0057] For string - shaped karsts: when setting a double - layer casing, the outer casing is followed up to the rock formation, and the inner casing is followed up to the bottom of the lowest - layer karst; when setting a single - layer casing, the single - layer casing is followed up to the bottom of the lowest - layer karst; at least one section of the inner casing is set for the inner casing of the single - layer casing or the double - layer casing, and one protection net cylinder is overlapped between every two inner casings.

[0058] As a preferred technical solution of the present invention, as Figures 4 to 6 shown, when setting a single - layer casing for karst types without string - shaped karsts,

[0059] For small karsts, the inner casing protection net is followed up to 2.5m below the bottom of the easily collapsible layer;

[0060] For medium - sized and large - sized karsts, the inner casing protection net is followed up to the rock formation;

[0061] For soil caves, the inner casing is followed up to 1.0m below the bottom of the soil cave but does not enter the rock formation;

[0062] In addition, for those karst types without string - shaped karsts where a single - layer casing is set, the wall construction of each pile karst is completed by cooperating with the backfill wall - construction method, and a three - phase mixture of rubble, clay, and bagged cement (weight ratio: 6.5:3:0.5) is used for backfill wall - construction treatment.

[0063] In a further preferred embodiment, the inner diameter of the single-layer casing or the inner diameter of the inner casing of the double-layer casing is rolled from a steel plate 20 cm larger than the pile diameter and with a wall thickness of 8 to 20 mm; the outer casing of the double-layer casing is rolled from a steel plate 40 cm larger than the pile diameter and with a wall thickness of 8 to 20 mm.

[0064] Finally, as a preferred implementation of the embodiment, in the step of burying the perforated casing, when the perforated casing is buried, the deviation between the center of the top surface of the perforated casing and the designed pile position shall not be greater than 5 cm, and the inclination shall not be greater than 0.5% (1 / 200), so as to meet the process requirements of the follow-up of the inner casing net during the next step of cave treatment. Before installing the inner casing, a pile hammer slightly larger than the outer diameter of the inner casing should be used to punch it to the buried elevation of the perforated casing. The diameter of the pile hammer should be about 5 cm larger than the outer diameter of the inner casing. A stiffening plate should be provided at the bottom of the casing to prevent the bottom from curling during the installation of the perforated casing, which will affect the lowering of the inner casing and the jamming of the hammer. After the casing is buried, clay, mudstone and bagged cement should be backfilled to compact the bottom of the casing to avoid vibration during the punching process, which may cause slurry to flow through the bottom of the casing.

[0065] In order to enable those skilled in the art to better understand the present technical solution, the following examples are provided for a more detailed explanation.

[0066] Example 1: Double casing follow-up for vertical string caves with three layers of caves

[0067] This application is based on the construction of the main pier pile foundation of Liuxi River Bridge, which has two main piers, 5# and 6#. The total number of pile foundations of 5# and 6# main piers is 52. According to the cave treatment plan, there are 50 pile foundations that need to be treated with caves, accounting for 96.2%, which is a very high proportion. The maximum height of the cave in the 5# main pier is 8.1m, which is revealed in piles 5-3# and 5-4#; the maximum height of the cave in the 6# main pier is 12.6m, which is revealed in pile 6-2#. Many beaded caves have been revealed, such as the 5# main pier has up to 5 layers of caves connected in series, which is revealed in pile 5-24#; the 6# main pier has up to 5 layers of caves connected in series, which is revealed in pile 6-23#. The following is an example of a beaded cave with three vertical layers of caves revealed by a pile of the 6# main pier, and the preparation before follow-up: the vertical string-like cave is a large-scale string-like cave, and the total height of the multi-layer cave is greater than 10m. Therefore, the wall thickness 5 of the inner casing 3 is 14mm (in other embodiments, 12mm, 16mm, 18mm, 20mm can be used according to actual working conditions), and the first and second sections of the protective net tube are both made of steel wire with a diameter of 5mm (in other embodiments, 5mm, 6mm, 7mm, 8mm can be used according to actual working conditions). The inner diameters of the first section inner casing, the second section inner casing, and the third section inner casing are all 2.65m, and the inner diameter of the outer casing of the double-layer casing is 2.85m.

[0068] like Figure 2 and Figure 3 As shown, at the location where the opening casing 1 is buried, the outer inner casing 2 is firstly used to follow up to the cave roof (rock layer top surface), and the first section of the outer casing 31 is followed to the bottom surface of the karst cavity of the first layer of the string-shaped karst cave ( Figure 2 The depth of embedding in the rock layer is the overlap depth 6. According to the mechanical properties of the medium weathered rock layer, the overlap depth (DJ) 6 is selected as 0.3m. Therefore, the bottom of the first section of the inner casing 31 is embedded in the medium weathered rock layer by 0.3m. The wall thickness of the first section of the inner casing 31 is overlapped by welding after the inner casing 2 passes through the bottom of the karst cavity of the first layer of the karst cave, and then the second section of the inner casing 32 is overlapped below the first section of the karst cavity to follow up to the bottom of the karst cavity of the second layer of the karst cave ( Figure 2 The bottom of the second section inner casing 32 is embedded in the slightly weathered rock layer by 0.4m, the second section inner casing 32 is overlapped with the second section protective net tube 42, and the second section protective net tube 42 is further overlapped with the third section inner casing 33 to follow up to the bottom of the third layer of karst cave ( Figure 2 The third section of the inner casing 33 is embedded in the slightly weathered rock layer by 0.5m. Figure 2 As shown, there are three layers of vertical string caves. After being followed up with double-layer casing, it was rushed to the designed final hole elevation (designed pile bottom elevation), the steel cage was lowered, and concrete was poured to complete the pile foundation construction. After ultrasonic testing by a third-party testing agency, the pile body was found to be intact and rated as a Class I pile.

[0069] Example 2: For small caves, no string caves

[0070] like Figure 4 As shown in the figure, for small karst caves, an inner casing is used to follow up to 2.5m below the prone-to-collapse layer, and a 2.7m diameter pile hammer is used to punch to the location of the casing burial at the opening, and then an inner casing with an inner diameter of 2.65m is buried. After the casing is buried, a 2.5m diameter pile hammer is replaced to continue punching. Small karst caves are backfilled with a three-phase mixture of flake stone, clay, and bagged cement (weight ratio: 6.5:3:0.5) for wall construction. The inner casing is made of rolled steel plates with an inner diameter of Φ2.65m and a wall thickness of 14mm.

[0071] Example 3: For medium-sized caves, no string-like caves

[0072] For medium or large caves, an inner casing is used to follow up to the top of the rock layer, and a 2.7m diameter pile hammer is used to drive to the rock surface, and then an inner casing with an inner diameter of 2.65m is buried. After the casing is buried, a 2.5m diameter pile hammer is replaced to continue driving. The cave is backfilled with a three-phase mixture of stone, clay, and bagged cement (weight ratio: 6.5:3:0.5) for wall construction.

[0073] Example 4: For soil caves, no string-like caves

[0074] like Figure 5 As shown in the figure, for pile foundations with soil holes within the scope of the pile foundation, first use a 2.7m diameter pile hammer to drive in to about 0.5m from the top of the soil hole, then bury an inner casing with an inner diameter of 2.65m, and use a vibrating hammer to drive the inner casing to 1m below the bottom of the soil hole. After the casing is buried, replace the 2.5m diameter pile hammer and continue to drive in.

[0075] The inner casings of Examples 2, 3 and 4 are all rolled from steel plates with an inner diameter of Φ2.65m and a wall thickness of 14mm.

[0076] The inner casing is followed up by a crawler crane and a vibrating hammer to be driven into place. Two total stations are used to observe from two directions during the vibration sinking process to ensure the verticality of the casing installation. The above-mentioned cave backfill materials are transported by dump trucks and excavators. When rushing to the vicinity of the cave, sufficient backfill materials and mud are prepared on site, and sufficient mud pumps are equipped near the pile hole. When the cave leaks seriously and the mud is not replenished in time, river water can be pumped into the pile to maintain the water head pressure inside and outside the pile to prevent the hole from collapsing.

[0077] In summary, when encountering a small karst cave or soil cave without a string of karst caves, a whole section of inner casing can be used to follow up directly, or a whole section of inner casing can be used to pass through a small karst cave or soil cave and then overlap a section of protective net tube; when encountering a medium-sized or large string of karst caves, several sections of casing units and several sections of protective net tubes are overlapped. The inner casing and protective net follow-up pile foundation construction technology is studied, discussed and practiced for the problems of difficult drilling of hollow karst caves, many karst cave fillings, and underwater concrete pouring. According to the inspection of a third-party organization commissioned by the project construction unit, all 52 pile foundations of the main pier are Class I piles, and the proportion of Class I piles is 100%. The main pier pile foundation can be completed safely, with high quality, high efficiency and environmental protection, and has successfully passed the high-standard pile foundation inspection. At present, it has gradually formed a set of mature treatment plans for this type of pile foundation construction, and at the same time, it can accurately estimate the construction period and cost investment of this type of pile foundation, providing valuable construction experience for future super-large karst cave pile foundation projects.

[0078] The embodiments of the present invention are described in detail above with reference to the accompanying drawings, but the present invention is not limited to the described embodiments. For those skilled in the art, various changes, modifications, substitutions and variations of these embodiments are made without departing from the principles and spirit of the present invention, and still fall within the scope of protection of the present invention.

Claims

1. A pile foundation construction method with segmented casing as required in a vertical string-shaped karst cave area comprises the following steps: Construction preparation, positioning of impact drill rig, embedding of open-hole casing, segmented follow-up construction of inner casing protection net as required, fabrication and installation of steel cage, and pouring of underwater concrete. It is characterized in that the segmented follow-up construction of the inner casing protection net as required specifically includes the following steps: Step 1) Identify the types of karst caves. According to geological exploration data, the types of karst caves include small karst caves, medium karst caves, large karst caves, easily collapsible soil layers and soil caves; Step 2) Follow-up of the inner casing protection net. For the corresponding karst cave types under the main pier pile foundation, a number of inner casings are segmented as required, and a protection net cylinder is lapped between two adjacent inner casings; Step 3) Casing installation: The inner casing protection net is all installed by using a crawler crane in cooperation with a vibratory hammer. During the vibratory sinking process, two total stations are used to observe from two directions to ensure the verticality of the casing installation; The identification of the types of karst caves is to judge the types of karst caves through the formation conditions, cavity sizes and filling materials of the karst caves. The specific judgment method is: The small karst caves are divided into small karst caves adjacent to buildings, small karst caves with easily collapsible soil layers in the overburden layer, and small string-shaped karst caves; The medium karst caves include fully filled karst caves or medium karst caves that have been pre-treated and are far from buildings, semi-filled or unfilled karst caves with a rock layer thickness of ≤1m at the top of the karst cave, fully filled karst caves adjacent to buildings with a rock layer thickness of >1m at the top of the karst cave, and medium string-shaped karst caves; The large karst caves include large karst caves with a rock layer thickness of ≤1m at the top of the karst cave, large karst caves with a rock layer thickness of >1m at the top of the karst cave, and large string-shaped karst caves; Easily collapsible soil layers and soil caves: soft plastic and flowing plastic silty clay; The inner casing is made of steel plates with an inner diameter 20cm larger than the pile diameter and a wall thickness of 8 - 20mm; the protection net cylinder is made of wire mesh rolled up, and the wire diameter of the wire mesh is 3 - 8mm; The judgment method for small string-shaped karst caves is that the height of a single cave H≤3m, or for multiple karst caves, the height of each single karst cave is <3m, which do not belong to filled karst caves and the interval distance >3m. They are collectively called type I karst caves. The inner casing with a wall thickness of 8 - 12mm is used for type I karst caves, and the protection net cylinder is made of wire mesh rolled up with wires with a diameter of 3 - 5mm; The judgment method for medium string-shaped karst caves is that the height of a single cave 3m < H < 10m, or the spacing of multiple karst caves is small, and the cumulative height of the karst caves >3m. They are collectively called type II karst caves; the inner casing with a wall thickness of 10 - 14mm is used for type II karst caves, and the protection net cylinder is made of wire mesh rolled up with wires with a diameter of 4 - 6mm; The judgment method for large string-shaped karst caves: the height of a single cave H≥10m, or the spacing of multiple karst caves is small, and the cumulative height of the karst caves ≥10m. They are collectively called type III karst caves; the inner casing with a wall thickness of 12 - 20mm is used for type III karst caves, and the protection net cylinder is made of wire mesh rolled up with wires with a diameter of 5 - 8mm; The above-mentioned large, medium and small string-shaped karst caves are fully filled or semi-filled, and the main filling material is flowing plastic silty clay; It is divided into slightly weathered, moderately weathered and highly weathered rock formations according to the mechanical properties of the rock formations between the vertical string-shaped karsts. When encountering the slightly weathered rock formation, the embedding depth of the inner casing into the rock formation is 0.1m < D ≤ 0.3m; when encountering the moderately weathered rock formation, the embedding depth of the inner casing into the rock formation is 0.2m < D ≤ 0.4m, and when encountering the highly weathered rock formation, the embedding depth of the inner casing into the rock formation is 0.3m < D ≤ 0.5m.

2. The method for pile foundation construction of vertical string-shaped karst cave areas according to claim 1 is characterized by: For the follow-up of the inner casing protection net, at least one section of inner casing is set according to the corresponding karst type under the main pier pile foundation. The inner casing is followed up to the bottom surface of the karst cavity. When there are multiple layers of karsts vertically distributed within the range of the main pier pile foundation, after the inner casing passes through the bottom surface of the karst cavity of the first layer, a section of protection net cylinder is welded and lapped. The second section of inner casing is continuously lapped below the protection net cylinder and followed up to the bottom surface of the karst cavity of the next layer, and so on until the wall construction of all karst cavities of multiple layers of karsts is completed. One protection net cylinder is lapped between every two inner casings.

3. The method for pile foundation construction of vertical string-shaped karst cave areas according to claim 2 is characterized by: During the follow-up process of the inner casing protection net, a single-layer casing or a double-layer casing is set. A single-layer casing is set for all karst types; For string-shaped karsts: when setting a double-layer casing, the outer casing is followed up to the rock formation, and the inner casing is followed up to the bottom of the lowest-layer karst; when setting a single-layer casing, the single-layer casing is followed up to the bottom of the lowest-layer karst; at least one section of inner casing is set for the inner casing of the single-layer casing or the double-layer casing, and one protection net cylinder is lapped between every two inner casings.

4. The method for pile foundation construction of vertical string-shaped karst cave areas according to claim 3 is characterized by: When setting a single-layer casing for all karst types without string-shaped karsts, For small karsts, the inner casing protection net is followed up to 2.5m below the bottom of the easily collapsible layer; For medium and large karsts, the inner casing protection net is followed up to the rock formation; For soil caves, the inner casing is followed up to 1.0m below the bottom of the soil cave, but does not enter the rock formation; The follow-up of the inner casing protection net is all carried out by using a crawler crane in cooperation with a vibratory hammer for driving and positioning, and two total stations are used for observation from two directions during the vibration sinking process.

5. The method for pile foundation construction with segmented casing on demand in vertical string-like karst cave areas according to claim 3 is characterized by: The inner diameter of the single-layer casing or the inner diameter of the inner casing of the double-layer casing is made of steel plates with a thickness of 8 - 20mm and a diameter 20cm larger than the pile diameter; the outer casing of the double-layer casing is made of steel plates with a thickness of 8 - 20mm and a diameter 40cm larger than the pile diameter.

6. The method for constructing pile foundation with segmented casing as required in vertical string-like karst cave areas according to claim 1 is characterized by: In the step of burying the open-hole casing, when burying the open-hole casing, the deviation of the center of the top surface of the open-hole casing from the designed pile position shall not be greater than 5cm, and the inclination shall not be greater than 0.5%.