Photovoltaic inverter MPPT efficiency field test device and test method
By designing a photovoltaic inverter MPPT efficiency on-site test device, using intelligent converters and irradiation probes to complete the test of the maximum power and actual power of the photovoltaic string in a short time, it solves the problem in the existing technology that the MPPT efficiency cannot be tested on-site. Achieving high-accuracy test results and improving intelligence.
Patent Information
- Application Number
- CN202310276965.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-21
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2043-03-21
AI Technical Summary
The maximum power point tracking (MPPT) efficiency of existing photovoltaic inverters cannot be obtained through on-site testing. The test environment requires high requirements, the results are highly uncertain, and the degree of intelligence is low.
A photovoltaic inverter MPPT efficiency on-site test device is designed, including an intelligent converter, an irradiation probe and a test device. It realizes real-time power and maximum power testing through intelligent switches and current sensors, using the deviation of the two test irradiation values. Perform retest command output to ensure the accuracy of test results.
Complete the test and collection of the maximum power and actual power of the photovoltaic string in a short time, obtain the maximum power point tracking efficiency of the photovoltaic inverter, reduce the impact of radiation fluctuations, and improve the accuracy and intelligence of the test results.
Smart Images

Figure CN116317944B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of photovoltaic inverter efficiency testing, and in particular relates to a photovoltaic inverter MPPT efficiency on-site testing device and a testing method. Background Art
[0002] In photovoltaic power generation systems, the inverter is one of the decisive factors in power generation efficiency. When other components are exactly the same, choosing different inverters will result in a 5% to 10% difference in the total power generation of the system. The maximum power point tracking (MPPT) efficiency of photovoltaic inverters is a key factor in determining the power generation of photovoltaic inverters. Its importance even exceeds the efficiency of the photovoltaic inverters themselves. Since this efficiency cannot be obtained through field testing at this stage, it is easily overlooked.
[0003] The maximum power point tracking (MPPT) efficiency of a photovoltaic inverter refers to the ability of the inverter to adjust the output power of the photovoltaic system according to different external ambient temperature, light intensity and other characteristics, so that the photovoltaic system always outputs maximum power. It is equal to the hardware efficiency multiplied by the software efficiency. The hardware efficiency is mainly determined by the accuracy of the sampling circuit, the MPPT voltage range, and the number of MPPT paths, while the software efficiency is mainly determined by the control algorithm.
[0004] The maximum power point tracking (MPPT) efficiency of photovoltaic inverters needs to be obtained by testing the maximum power and actual power of the photovoltaic strings connected to the inverter. However, due to the influence of irradiation changes, two tests must be completed in a short time, and the two tests need to be measured in the disconnected and connected states respectively. Therefore, there is a lack of technology that can be tested on site at this stage. The existing test standards use a simulated power supply with known output power instead of the photovoltaic strings. Only the input power of the photovoltaic inverter needs to be tested, and it is mostly used in laboratory tests.
[0005] The Chinese invention patent application with publication number CN106597151A discloses a method and system for testing the tracking efficiency of an inverter in operation in a photovoltaic power station. The testing method includes the following steps: Step 1: selecting an appropriate test time; Step 2: obtaining the initial and final IV curves and the irradiance and temperature data at the corresponding moments; Step 3: recording the DC voltage, DC current, irradiance and temperature during the test period; Step 4: obtaining the theoretical power value of the photovoltaic array at each sampling moment during the test period; Step 5: calculating the inverter tracking efficiency to complete the test.
[0006] The above-mentioned invention patent application scheme attempts to solve the problem that the tracking efficiency of the inverters in the photovoltaic power station cannot be tested on site, and proposes a method for obtaining the maximum theoretical power of the photovoltaic array during the test. However, the above-mentioned invention patent application scheme has the following shortcomings: 1. It has high requirements for the test environment, requiring the irradiation to be relatively stable and slowly changing; 2. The maximum theoretical power of the photovoltaic array at each sampling point is calculated by combining the IV curve of the photovoltaic array at the beginning and end of the test with an algorithm, and the test results have a large uncertainty; 3. The degree of intelligence is low. Summary of the invention
[0007] Aiming at the shortcomings of the existing photovoltaic inverter MPPT efficiency, such as high requirements on the test environment, large uncertainty of the test results, and low intelligence, the present invention provides a photovoltaic inverter MPPT efficiency field test device, which can complete the test collection of the maximum power of the photovoltaic string and the actual power of the photovoltaic string in a short time, thereby obtaining the maximum power point tracking (MPPT) efficiency of the photovoltaic inverter. The present invention also provides a photovoltaic inverter MPPT efficiency field test method.
[0008] To achieve the above purpose, the present invention adopts the following technical solution: a photovoltaic inverter MPPT efficiency field test device, the photovoltaic inverter MPPT efficiency field test device comprises:
[0009] An intelligent converter, comprising an input terminal connected to a photovoltaic string, an output terminal connected to a photovoltaic inverter, a test terminal connected to a test line, an intelligent switch arranged between the input terminal and the output terminal, a current sensor arranged between the photovoltaic string and the intelligent switch, a current sensor data transmission terminal connected to the current sensor, and an intelligent switch control terminal connected to the intelligent switch;
[0010] Irradiation probe;
[0011] The test device comprises a voltage port connected to a test line, a test port connected to the test line, a current port connected to a data transmission end of a current sensor, an intelligent switch control port connected to an intelligent switch control end, an irradiation port connected to an irradiation probe, an acquisition module, a real-time power test module, an IV test module, a program control module, an operation display module, and a battery. The acquisition module is connected to the voltage port, the current port, the real-time power test module, and the IV test module, and the test port is connected to the IV test module.
[0012] Among them, the program control module controls the closing and opening of the intelligent switch, and controls the real-time power test module and the IV test module to test the real-time output power and maximum output power of the photovoltaic string respectively. The program control module uses the deviation of the irradiation values of the two tests as the basis to output the test results or retest instructions.
[0013] The photovoltaic inverter MPPT efficiency field test device of the present invention can complete the test collection of the maximum power and the actual power of the photovoltaic string in a short time by arranging an intelligent converter, an irradiation probe and a test device, so as to obtain the maximum power point tracking (MPPT) efficiency of the photovoltaic inverter; and the deviation of the irradiation values of two tests is used as a basis to realize the output of the test result or the retest instruction, that is, when the deviation of the irradiation values of two tests is within the allowable range, the test result is output, and when the deviation is outside the allowable range, the test is re-performed, thereby reducing the influence of the irradiation fluctuation, realizing the on-site actual measurement of all data, and thus ensuring the accuracy of the test result; and the test environment requirement is low.
[0014] As an improvement, when the smart switch is disconnected, the connection between the photovoltaic string and the photovoltaic inverter is disconnected, and when the smart switch is closed, the connection between the photovoltaic string and the photovoltaic inverter is connected.
[0015] As an improvement, the intelligent switch is in a normally closed state. When the IV test module performs a maximum power test, the intelligent switch synchronously receives instructions and opens; when the test is completed, the intelligent switch receives instructions and closes.
[0016] As an improvement, the intelligent switch is connected to the programmable control module of the test device via Bluetooth or wired mode.
[0017] As an improvement, the current sensor is connected to the test device via a signal line.
[0018] As an improvement, the smart converter is connected to the photovoltaic inverter and the photovoltaic string using a dedicated MC4 connector, and the connector type for connecting the smart converter to the test device is determined by the port of the test device.
[0019] As an improvement, the test line is divided into two test lines, one of which is connected to the test port of the test device to form an IV test loop, and the other is connected to the voltage port of the test device for voltage measurement.
[0020] As an improvement, the IV test module includes an electronic variable resistor, which can complete the acquisition of current and voltage when the electronic variable resistor changes from 0Ω to infinity within 1s and obtain the maximum power point.
[0021] As an improvement, the program control module determines the deviation of the two input irradiation values G1 and G2. If (G1-G2) / G2×100 is not greater than 1%, the output result P / Pmax×100% is sent to the display module to obtain the instantaneous maximum power point tracking (MPPT) efficiency. If the deviation between the two irradiation values is greater than 1%, it is prompted that the irradiation deviation is large, and retesting is started until the irradiation deviation meets the requirements.
[0022] As an improvement, a sampling period T is set for the test device, and N groups of data including the real-time power and maximum power of the photovoltaic strings are tested and collected within the period T. The accumulated power and theoretical maximum output power of the photovoltaic strings within the period T are obtained through an integration algorithm to obtain the maximum power point tracking efficiency.
[0023] The photovoltaic inverter MPPT efficiency field test method is applied to the aforementioned photovoltaic inverter MPPT efficiency field test device. The photovoltaic inverter MPPT efficiency field test method includes:
[0024] Step S1: At a photovoltaic power generation site, a photovoltaic inverter MPPT efficiency field test device, an intelligent converter, a photovoltaic inverter, and a photovoltaic string are connected;
[0025] Step S2, start the test device to perform real-time power test, record the irradiation value G1, current I, voltage V obtained when the intelligent switch is turned on, calculate the real-time power P, and output it to the program control module;
[0026] Step S3, perform a maximum power test. Before the test, send a command to the intelligent switch to disconnect it, collect the irradiation value G2, the maximum current Imax, and the voltage Vmax when the intelligent switch is disconnected, and calculate the maximum output power Pmax, which is output to the program control module. After the test, send a command to the intelligent switch again to close it.
[0027] Step S4, the program control module determines the deviation of the two input irradiation values G1 and G2. If (G1-G2) / G2×100 is not greater than 1%, the output result P / Pmax×100% is sent to the operation display module. If the deviation of the two irradiation values is greater than 1%, it indicates that the irradiation deviation is large and starts retesting until the irradiation deviation meets the requirements.
[0028] As an improvement, the on-site test method for the MPPT efficiency of a photovoltaic inverter also includes: setting a sampling period T, testing and collecting N groups of data including the real-time power and maximum power of photovoltaic strings within the period T, obtaining the cumulative power and theoretical maximum output power of the photovoltaic strings within the period T through an integration algorithm, and obtaining the maximum power point tracking efficiency.
[0029] The photovoltaic inverter MPPT efficiency field test device of the present invention has the following beneficial effects: by setting up an intelligent converter, an irradiation probe and a test device, the test collection of the maximum power and the actual power of the photovoltaic string can be completed in a short time, thereby obtaining the maximum power point tracking (MPPT) efficiency of the photovoltaic inverter; based on the deviation of the irradiation values of two tests, the output of the test result or the retest instruction is realized, that is, when the deviation of the irradiation values of two tests is within the allowable range, the test result is output, and when the deviation is outside the allowable range, the test is re-performed, thereby ensuring the accuracy of the test result.
[0030] The beneficial effect of the photovoltaic inverter MPPT efficiency on-site testing method of the present invention is that the maximum power point tracking (MPPT) efficiency of the photovoltaic inverter can be tested at the photovoltaic power generation site, all data are measured data, and the test results are accurate and reliable. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a connection diagram of a photovoltaic inverter MPPT efficiency field test device according to the first embodiment of the present invention.
[0032] Figure 2 It is a structural block diagram of an intelligent converter of a photovoltaic inverter MPPT efficiency field test device according to a first embodiment of the present invention.
[0033] Figure 3 It is a structural block diagram of a testing device of a photovoltaic inverter MPPT efficiency field testing device according to the first embodiment of the present invention.
[0034] Figure 4 It is a flow chart of a photovoltaic inverter MPPT efficiency on-site testing method according to the first embodiment of the present invention. DETAILED DESCRIPTION
[0035] The following is an explanation and description of the technical solutions of the embodiments of the present invention in conjunction with the accompanying drawings of the embodiments of the present invention, but the following embodiments are only preferred embodiments of the present invention, not all. Based on the embodiments in the implementation mode, other embodiments obtained by those skilled in the art without creative work are all within the protection scope of the present invention.
[0036] See also Figures 1 to 4 , Photovoltaic inverter MPPT efficiency field test device, Photovoltaic inverter MPPT efficiency field test device includes:
[0037] An intelligent converter, comprising an input terminal connected to a photovoltaic string, an output terminal connected to a photovoltaic inverter, a test terminal connected to a test line, an intelligent switch arranged between the input terminal and the output terminal, a current sensor arranged between the photovoltaic string and the intelligent switch, a current sensor data transmission terminal connected to the current sensor, and an intelligent switch control terminal connected to the intelligent switch;
[0038] Irradiation probe;
[0039] The test device comprises a voltage port connected to a test line, a test port connected to the test line, a current port connected to a data transmission end of a current sensor, an intelligent switch control port connected to an intelligent switch control end, an irradiation port connected to an irradiation probe, an acquisition module, a real-time power test module, an IV test module, a program control module, an operation display module, and a battery. The acquisition module is connected to the voltage port, the current port, the real-time power test module, and the IV test module, and the test port is connected to the IV test module.
[0040] Among them, the program control module controls the closing and opening of the intelligent switch, the real-time power test module and the IV test module test the real-time output power and maximum output power of the photovoltaic string respectively, and the program control module uses the deviation of the two test irradiation values as the basis to output the test results or retest instructions.
[0041] The photovoltaic inverter MPPT efficiency field test device of the present invention can complete the test collection of the maximum power and the actual power of the photovoltaic string in a short time by arranging an intelligent converter, an irradiation probe and a test device, so as to obtain the maximum power point tracking (MPPT) efficiency of the photovoltaic inverter; the deviation of the irradiation values of two tests is used as a basis to realize the output of the test result or the retest instruction, that is, when the deviation of the irradiation values of two tests is within the allowable range, the test result is output, and when the deviation is outside the allowable range, the test is re-performed, thereby reducing the influence of the irradiation fluctuation, realizing the on-site actual measurement of all data, and thus ensuring the accuracy of the test result.
[0042] Embodiment 1
[0043] See also Figures 1 to 4 , Photovoltaic inverter MPPT efficiency field test device, Photovoltaic inverter MPPT efficiency field test device includes:
[0044] An intelligent converter, comprising an input terminal connected to a photovoltaic string, an output terminal connected to a photovoltaic inverter, a test terminal connected to a test line, an intelligent switch arranged between the input terminal and the output terminal, a current sensor arranged between the photovoltaic string and the intelligent switch, a current sensor data transmission terminal connected to the current sensor, and an intelligent switch control terminal connected to the intelligent switch;
[0045] Irradiation probe;
[0046] The test device comprises a voltage port connected to a test line, a test port connected to the test line, a current port connected to a data transmission end of a current sensor, an intelligent switch control port connected to an intelligent switch control end, an irradiation port connected to an irradiation probe, an acquisition module, a real-time power test module, an IV test module, a program control module, an operation display module, and a battery. The acquisition module is connected to the voltage port, the current port, the real-time power test module, and the IV test module, and the test port is connected to the IV test module.
[0047] Among them, the program control module controls the closing and opening of the intelligent switch, the real-time power test module and the IV test module test the real-time output power and maximum output power of the photovoltaic string respectively, and the program control module uses the deviation of the two test irradiation values as the basis to output the test results or retest instructions.
[0048] In this embodiment, when the smart switch is turned off, the connection between the photovoltaic string and the photovoltaic inverter is disconnected, and when the smart switch is turned on, the connection between the photovoltaic string and the photovoltaic inverter is turned on.
[0049] In this embodiment, the intelligent switch is in a normally closed state. When the maximum power test is performed in the IV test module, the intelligent switch synchronously receives the instruction and opens; when the test is completed, the intelligent switch receives the instruction and closes.
[0050] In this embodiment, the intelligent switch is connected to the program control module of the testing device via Bluetooth or wired connection.
[0051] In this embodiment, the current sensor is connected to the testing device through a signal line.
[0052] In this embodiment, the intelligent converter is connected to the photovoltaic inverter and the photovoltaic string using a dedicated MC4 connector, and the connector type for connecting the intelligent converter to the test device is determined according to the port of the test device.
[0053] In this embodiment, the test line is divided into two test lines, one of which is connected to the test port of the test device for IV testing, and the other is connected to the voltage port of the test device for voltage measurement.
[0054] In this embodiment, the IV test module includes an electronic variable resistor, which can complete the acquisition of current and voltage when the electronic variable resistor changes from 0Ω to infinity within 1 second and obtain the maximum power point.
[0055] In this embodiment, the program control module determines the deviation of the two input irradiation values G1 and G2. If (G1-G2) / G2×100 is not greater than 1%, the output result P / Pmax×100% is sent to the display module. If the deviation between the two irradiation values is greater than 1%, it indicates that the irradiation deviation is large and starts retesting until the irradiation deviation meets the requirements.
[0056] The beneficial effects of the photovoltaic inverter MPPT efficiency field test device of the first embodiment of the present invention are: by setting up an intelligent converter, an irradiation probe and a test device, the test collection of the maximum power and the actual power of the photovoltaic string can be completed in a short time, thereby obtaining the maximum power point tracking (MPPT) efficiency of the photovoltaic inverter; based on the deviation of the irradiation values of two tests, the output of the test result or the re-test instruction is realized, that is, when the deviation of the irradiation values of the two tests is within the allowable range, the test result is output, and when the deviation is outside the allowable range, the test is re-performed, thereby reducing the impact of irradiation fluctuations, realizing on-site measurement of all data, and thus ensuring the accuracy of the test results.
[0057] See also Figure 4 The present invention also provides a photovoltaic inverter MPPT efficiency on-site testing method, which is applied to Figures 1 to 3 The photovoltaic inverter MPPT efficiency field test device and photovoltaic inverter MPPT efficiency field test method include:
[0058] Step S1: At a photovoltaic power generation site, a photovoltaic inverter MPPT efficiency field test device, an intelligent converter, a photovoltaic inverter, and a photovoltaic string are connected;
[0059] Step S2, start the test device to perform real-time power test, record the radiation value G1, current I, voltage V when the intelligent switch is turned on, calculate the real-time power P, and output it to the program control module;
[0060] Step S3, perform a maximum power test. Before the test, send a command to the intelligent switch to disconnect it, record the irradiation value G2, the maximum current Imax, and the voltage Vmax when the intelligent switch is disconnected, and calculate the maximum output power Pmax, which is output to the program control module. After the test, send a command to the intelligent switch to close it.
[0061] Step S4, the program control module determines the deviation of the two input irradiation values G1 and G2. If (G1-G2) / G2×100 is not greater than 1%, the output result P / Pmax×100% is sent to the operation display module. If the deviation of the two irradiation values is greater than 1%, it indicates that the irradiation deviation is large and starts retesting until the irradiation deviation meets the requirements.
[0062] The on-site test method for the MPPT efficiency of a photovoltaic inverter also includes: setting a sampling period T of the test device, and testing and collecting relevant data such as the real-time power and maximum power of N groups of photovoltaic strings within the period T, and obtaining the cumulative power and theoretical maximum output power of the photovoltaic strings within the period T through an integration algorithm to obtain the maximum power point tracking (MPPT) efficiency.
[0063] The above are only specific embodiments of the invention, but the protection scope of the invention is not limited thereto. Those skilled in the art should understand that the invention includes but is not limited to the contents described in the above specific embodiments. Any modification that does not deviate from the functional and structural principles of the invention will be included in the scope of the claims.
Claims
1. Photovoltaic inverter MPPT efficiency field test device, characterized by: The photovoltaic inverter MPPT efficiency field test device includes: An intelligent converter, comprising an input terminal connected to a photovoltaic string, an output terminal connected to a photovoltaic inverter, a test terminal connected to a test line, an intelligent switch arranged between the input terminal and the output terminal, a current sensor arranged between the photovoltaic string and the intelligent switch, a current sensor data transmission terminal connected to the current sensor, and an intelligent switch control terminal connected to the intelligent switch; Irradiation probe; The test device comprises a voltage port connected to a test line, a test port connected to the test line, a current port connected to a data transmission end of a current sensor, an intelligent switch control port connected to an intelligent switch control end, an irradiation port connected to an irradiation probe, an acquisition module, a real-time power test module, an IV test module, a program control module, an operation display module, and a battery. The acquisition module is connected to the voltage port, the current port, the real-time power test module, and the IV test module, and the test port is connected to the IV test module. Among them, the program control module controls the closing and opening of the intelligent switch, and controls the real-time power test module and the IV test module to test the real-time output power and the maximum output power of the photovoltaic string respectively. The program control module uses the deviation of the two test irradiation values as the basis to realize the output of the test results or retest instructions; The program control module determines the deviation of the two input irradiation values G1 and G2. If (G1-G2) / G2×100 is not greater than 1%, the output result P / Pmax×100% is sent to the display module. If the deviation of the two irradiation values is greater than 1%, it indicates that the irradiation deviation is large and starts retesting until the irradiation deviation meets the requirements.
2. The photovoltaic inverter MPPT efficiency field test device according to claim 1, characterized in that: When the smart switch is turned off, the connection between the photovoltaic string and the photovoltaic inverter is disconnected, and when the smart switch is turned on, the connection between the photovoltaic string and the photovoltaic inverter is turned on.
3. The photovoltaic inverter MPPT efficiency field test device according to claim 1, characterized in that: The intelligent switch is in a normally closed state. When the IV test module performs a maximum power test, the intelligent switch synchronously receives instructions and opens; when the test is completed, the intelligent switch receives instructions and closes.
4. The photovoltaic inverter MPPT efficiency on-site test device according to claim 1, characterized in that: The smart switch is connected to the programmable module of the test device via Bluetooth or wired mode; the current sensor is connected to the test device via a signal line; the smart converter is connected to the photovoltaic inverter and photovoltaic strings using a dedicated MC4 connector, and the connector type for connecting the smart converter to the test device is determined by the port of the test device.
5. The photovoltaic inverter MPPT efficiency on-site test device according to claim 1, characterized in that: The test line is divided into two test lines, one of which is connected to the test port of the test device to form an IV test loop, and the other is connected to the voltage port of the test device to measure voltage.
6. The photovoltaic inverter MPPT efficiency on-site test device according to claim 1, characterized in that: The IV test module includes an electronic variable resistor, which can complete the acquisition of current and voltage when the electronic variable resistor changes from 0Ω to infinity within 1s and obtain the maximum power point.
7. The photovoltaic inverter MPPT efficiency on-site test device according to claim 1, characterized in that: The sampling period T of the test device is set, and N groups of data including the real-time power and maximum power of the photovoltaic strings are tested and collected within the period T. The cumulative power and theoretical maximum output power of the photovoltaic strings within the period T are obtained through the integration algorithm to obtain the maximum power point tracking efficiency.
8. The on-site test method for the MPPT efficiency of photovoltaic inverters is characterized by: The photovoltaic inverter MPPT efficiency field test device applied to any one of claims 1 to 7, and the photovoltaic inverter MPPT efficiency field test method include: Step S1: At a photovoltaic power generation site, a photovoltaic inverter MPPT efficiency field test device, an intelligent converter, a photovoltaic inverter, and a photovoltaic string are connected; Step S2, start the test device to perform real-time power test, record the radiation value G1, current I, voltage V when the intelligent switch is turned on, calculate the real-time power P, and output it to the program control module; Step S3, perform a maximum power test. Before the maximum power test, send a command to the intelligent switch to disconnect it, record the irradiation value G2, the maximum current Imax, and the voltage Vmax when the intelligent switch is disconnected, and calculate the maximum output power Pmax, which is output to the program control module. After the test, send a command to the intelligent switch again to close it. Step S4, the program control module determines the deviation of the two input irradiation values G1 and G2. If (G1-G2) / G2×100 is not greater than 1%, the output result P / Pmax×100% is sent to the operation display module. If the deviation of the two irradiation values is greater than 1%, it indicates that the irradiation deviation is large and starts retesting until the irradiation deviation meets the requirements.
9. The method for testing the MPPT efficiency of a 10V inverter on-site according to claim 8, characterized in that: The on-site test method for PV inverter MPPT efficiency also includes: The sampling period T is set, and N groups of data including the real-time power and maximum power of the photovoltaic strings are tested and collected within the period T. The cumulative power and theoretical maximum output power of the photovoltaic strings within the period T are obtained through the integration algorithm to obtain the maximum power point tracking efficiency.
Citation Information
Patent Citations
Method and system for testing photovoltaic plant already-operating inverter tracking efficiency
CN106597151A
Photovoltaic module array monitoring system and monitoring method
CN108551330A