System and method for measuring gas content in shale cuttings

By designing a shale shale debris gas content measurement system, using gas configuration and adsorption and desorption technology, the accuracy and construction difficulty in shale gas content measurement are solved, and accurate evaluation and reserve calculation of shale gas resources are achieved.

CN116519533BActive Publication Date: 2024-11-05CHINA UNIV OF GEOSCIENCES (BEIJING)
View PDF 11 Cites 0 Cited by

Patent Information

Application Number
CN202310559173.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-05-17
Publication Date
2024-11-05
Estimated Expiration
2043-05-17

AI Technical Summary

Technical Problem

It is difficult to accurately determine the gas content of shale in the entire well section and even the entire area, and the on-site desorption test has problems such as high construction difficulty, high cost and inaccurate gas dissipation.

Method used

A shale rock chip gas content measurement system is designed, including a gas configuration unit, an adsorption and desorption unit and a gas measurement unit. Through the combination of adsorbent gas and non-adsorbent gas, gas in shale rock chips is adsorbed and desorbed. The gas volume is measured using a tunable laser meter to achieve accurate determination of the gas content of shale rock chips.

Benefits of technology

The system can accurately measure the gas content of shale debris, overcome the problems of gas dissipation and inaccurate fitting regression during on-site desorption measurement, reduce construction difficulty and cost, and realize shale gas for all well sections and even the entire area Comprehensive evaluation of resources and calculation of reserves.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116519533B_ABST
    Figure CN116519533B_ABST
Patent Text Reader

Abstract

The present application is applicable to the field of shale exploration technology, and provides a system and method for measuring the gas content of shale cuttings, the system comprising: a gas configuration unit, an adsorption and desorption unit, and a gas volume measurement unit connected in sequence; the gas configuration unit transmits adsorbed gas and non-adsorbed gas to the adsorption and desorption unit, the adsorbed gas can be adsorbed in the pores of the shale cuttings, and the non-adsorbed gas is used to displace the adsorbed gas that is not adsorbed by the shale cuttings; the adsorption and desorption unit can make the shale cuttings adsorbed gas, crush the shale cuttings, desorb the adsorbed gas adsorbed by the shale cuttings, and transmit the adsorbed gas generated by desorption to the gas volume measurement unit; the gas volume measurement unit receives the adsorbed gas generated by desorption, determines and displays the gas volume of the adsorbed gas generated by desorption, and the gas volume represents the gas content of the shale cuttings. The present application can obtain shale gas content data for the entire well section or even the entire region by accurately measuring the gas content of shale cuttings.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of shale exploration, and in particular, relates to a system and method for determining the gas content of shale cuttings. Background Art

[0002] With the growing demand for natural gas, shale gas is considered an important energy source to replace conventional oil and gas. As one of the key parameters for shale gas resource evaluation and reserve calculation, accurate determination of gas content is an indispensable part of shale gas exploration and development.

[0003] At present, there are many ways to determine the gas content of shale, including field desorption test, isothermal adsorption experiment and logging interpretation prediction. Among them, field desorption test has been widely used because it can directly and quickly obtain the gas content of shale.

[0004] The gas content of shale can be composed of three parts: desorbed gas volume, residual gas volume and lost gas volume. The desorbed gas volume is the gas volume obtained by desorbing the extracted shale, the residual gas volume is the gas volume obtained by crushing and grinding the desorbed shale, and the lost gas volume is the gas volume that escaped during the core extraction process calculated by fitting and regressing the desorption data.

[0005] However, shale cores need to be extracted before on-site desorption testing, and core extraction is restricted by objective factors such as complex construction technology, low construction efficiency, and high construction costs, resulting in only cores from a specific shale layer, and the shale gas content of the entire well section or even the entire region cannot be obtained. At the same time, different shale layers are affected by multiple factors such as burial depth and formation pressure, and the amount of gas released during core extraction varies greatly. The loss gas volume calculated by desorption data fitting regression often cannot reflect the actual amount of gas released, resulting in a large deviation in the measured shale gas content.

[0006] Therefore, there is an urgent need for a method that can obtain shale gas content data for the entire well section or even the entire region and can accurately determine the shale gas content. Summary of the invention

[0007] In order to overcome the problems existing in the related art, the embodiments of the present application provide a shale cuttings gas content determination system and method, which can obtain shale gas content data for the entire well section and even the entire region by accurately determining the gas content of shale cuttings.

[0008] This application is implemented through the following technical solutions:

[0009] In a first aspect, an embodiment of the present application provides a shale cuttings gas content determination system, comprising: a gas configuration unit, an adsorption and desorption unit and a gas volume determination unit connected in sequence; the gas configuration unit transmits adsorbed gas and non-adsorbed gas to the adsorption and desorption unit, the adsorbed gas can be adsorbed in the pores of the shale cuttings, and the non-adsorbed gas cannot be adsorbed in the voids of the shale cuttings, and the non-adsorbed gas is used to displace the adsorbed gas that is not adsorbed by the shale cuttings; the adsorption and desorption unit can make the shale cuttings adsorbed gas, crush the shale cuttings, desorb the adsorbed gas adsorbed by the shale cuttings, and transmit the adsorbed gas generated by desorption to the gas volume determination unit; the gas volume determination unit receives the adsorbed gas generated by desorption, determines and displays the gas volume of the adsorbed gas generated by desorption, and the gas volume characterizes the gas content of the shale cuttings.

[0010] In a possible implementation of the first aspect, the gas configuration unit includes a first gas tank and a second gas tank, the first gas tank stores adsorbed gas, and the second gas tank stores non-adsorbed gas; the first gas tank and the second gas tank are both connected to the adsorption and desorption unit, the first gas tank transmits the adsorbed gas to the adsorption and desorption unit, and the second gas tank transmits the non-adsorbed gas to the adsorption and desorption unit.

[0011] In a possible implementation of the first aspect, the adsorption and desorption unit includes a third gas tank and an electromagnetic crushing device, the electromagnetic crushing device includes a material pipe; the third gas tank is arranged in the cavity of the electromagnetic crushing device, the first gas tank and the second gas tank are both connected to the third gas tank, the connection point between the second gas tank and the third gas tank and the connection point between the first gas tank and the third gas tank are not in the same horizontal plane, the third gas tank is connected to the gas volume measuring unit, and the third gas tank is connected to the external space; the material pipe is arranged in the third gas tank, and the material pipe is used to crush shale cuttings.

[0012] In a possible implementation of the first aspect, the gas volume measuring unit includes a tunable laser and a display device; the tunable laser is electrically connected to the display device, and the tunable laser is connected to a third gas tank; the tunable laser receives the adsorbed gas generated by desorption, measures the gas volume data of the adsorbed gas generated by desorption, and transmits the gas volume data to the display device; the display device receives the gas volume data and displays the gas volume data as gas volume.

[0013] In a possible implementation of the first aspect, the tunable laser includes a laser cavity and a laser; the laser cavity is capable of storing adsorbed gas generated by desorption transmitted by a third gas tank, and the laser is a laser for measuring gas volume data of the adsorbed gas.

[0014] In a possible implementation of the first aspect, the system also includes a gas regulating unit; the gas regulating unit connects the gas configuration unit with the adsorption and desorption unit, connects the adsorption and desorption unit with the gas measuring unit, and connects the adsorption and desorption unit with the external space; the gas regulating unit is capable of adjusting the gas volume and gas pressure of gas transmitted from the first gas tank to the third gas tank, adjusting the gas volume and gas pressure of gas transmitted from the second gas tank to the third gas tank, and adjusting the gas volume of gas transmitted from the third gas tank to the tunable laser, and adjusting the gas volume of gas transmitted from the third gas tank to the external space.

[0015] In a possible implementation of the first aspect, the gas regulating unit includes a first pipeline, a second pipeline, a third pipeline, a fourth pipeline, a first air pump, a second air pump, a third air pump, a first valve, a second valve, a third valve and a fourth valve; the first pipeline is used to connect the first gas tank and the third gas tank, the second pipeline is used to connect the second gas tank and the third gas tank, the third pipeline is used to connect the third gas tank and the tunable laser, and the fourth pipeline is used to connect the third gas tank and the external space; the first air pump is arranged on the first pipeline, and is used to drive the adsorbed gas of the first gas tank into the third gas tank, so that the pressure in the third gas tank is a preset pressure; the second air pump is arranged on the second pipeline, and is used to The invention is used to drive the non-adsorbed gas in the second gas tank into the third gas tank, so that the pressure in the third gas tank is a preset pressure; the third air pump is arranged on the third pipeline, and is used to drive the adsorbed gas generated by the desorption of the third gas tank into the tunable laser instrument; the first valve is arranged on the first pipeline, and is used to control the on-off of the gas transmission between the first gas tank and the third gas tank; the second valve is arranged on the second pipeline, and is used to control the on-off of the gas transmission between the second gas tank and the third gas tank; the third valve is arranged on the third pipeline, and is used to control the on-off of the gas transmission between the third gas tank and the tunable laser instrument; the fourth valve is arranged on the third gas tank, and is used to control the on-off of the gas transmission between the third gas tank and the external space.

[0016] Compared with the prior art, the embodiments of the present invention have the following beneficial effects:

[0017] The shale cuttings gas content determination system provided in the embodiment of the present application includes a gas configuration unit, an adsorption and desorption unit, and a gas volume determination unit connected in sequence. The gas configuration unit can transmit adsorbed gas and non-adsorbed gas to the adsorption and desorption unit, and perform adsorption and desorption operations in the adsorption and desorption unit respectively: first, the voids of the shale cuttings are filled with adsorbed gas, and then the adsorbed gas is displaced with non-adsorbed gas, so that the adsorbed gas in the adsorption and desorption unit is only retained in the pores of the shale cuttings, and then the shale cuttings are desorbed in a crushing manner to obtain the full amount of adsorbed gas in the pores of the shale cuttings, and finally the gas volume of the adsorbed gas in the pores of the shale cuttings is measured by the gas determination unit, and the gas volume can accurately characterize the gas content of the shale cuttings.

[0018] The shale cuttings gas content determination system disclosed in the embodiment of the present application is targeted at the adsorption characteristics of shale cuttings, and can accurately determine the true gas content of shale cuttings through adsorption and desorption of shale cuttings. It overcomes the drawbacks of the prior art that the escaped gas cannot be estimated and the fitting regression calculation is not accurate enough when the core is desorbed on site; at the same time, the construction difficulty and construction cost of extracting cuttings are greatly reduced compared with extracting cores, and the extraction of cuttings is no longer limited to specific shale faults and shale areas. By extracting cuttings from the entire well section or even the entire area, shale gas exploration can be carried out in a comprehensive and complete manner in the shale area, thereby accurately obtaining key parameters such as shale gas resource evaluation and reserve calculation.

[0019] In a second aspect, an embodiment of the present application provides a method for determining the gas content of shale cuttings, which is applied to a shale cuttings gas content determination system as described in any one of the first aspects, including: gas adsorption: controlling a gas configuration unit to transmit adsorbed gas and non-adsorbed gas to an adsorption and desorption unit, so that the pores of the shale cuttings adsorbed gas, and the non-adsorbed gas displaces the adsorbed gas not adsorbed by the shale cuttings; gas desorption: controlling the adsorption and desorption unit to crush the shale cuttings, desorb the adsorbed gas adsorbed by the shale cuttings, and transmitting the adsorbed gas generated by desorption to a gas volume determination unit; gas measurement: controlling the gas volume determination unit to receive the adsorbed gas generated by desorption, and measuring and displaying the gas volume of the adsorbed gas generated by desorption, wherein the gas volume characterizes the gas content of the shale cuttings.

[0020] In a possible implementation of the second aspect, the gas configuration unit is controlled to transmit adsorbed gas and non-adsorbed gas to the adsorption and desorption unit, so that the pores of the shale cuttings adsorbed gas and the non-adsorbed gas displaces the adsorbed gas that is not adsorbed by the shale cuttings, including: placing the shale cuttings in a third gas tank; controlling the first valve to open, controlling the first air pump to drive the adsorbed gas in the first gas tank into the third gas tank, so that the pressure in the third gas tank reaches a preset first pressure value, controlling the first valve to close, and maintaining the preset time, the preset first pressure value is a pressure value determined according to the burial depth of the shale cuttings and the formation pressure, and the preset time is the time when the shale cuttings can fully adsorb the adsorbed gas; controlling the second valve to open, controlling the second air pump to drive the non-adsorbed gas in the second gas tank into the third gas tank, controlling the opening of the fourth valve based on the operating power of the second air pump, maintaining the preset first pressure value unchanged, so that the non-adsorbed gas displaces the adsorbed gas in the third gas tank that is not adsorbed by the shale cuttings and is discharged from the fourth valve, and controlling the second valve and the fourth valve to close.

[0021] In a possible implementation of the second aspect, the adsorption and desorption unit is controlled to crush shale cuttings, desorb the adsorbed gas adsorbed by the shale cuttings, and transmit the adsorbed gas generated by the desorption to the gas volume measuring unit, including: controlling the electromagnetic crushing device to crush the shale cuttings into shale particles, the diameter of the shale particles is less than or equal to 200 mesh; controlling the third valve to open, controlling the third air pump to drive the adsorbed gas generated by desorption in the third gas tank to enter the laser cavity, and after the pressure in the third gas tank reaches a preset second pressure value, controlling the third valve to close, the preset second pressure value representing the amount of gas remaining in the third gas tank.

[0022] Compared with the prior art, the embodiments of the present invention have the following beneficial effects:

[0023] The method for determining the gas content of shale cuttings provided in the embodiment of the present application mainly includes three stages: gas adsorption, gas desorption and gas determination. Gas adsorption allows the shale cuttings to fully adsorb the adsorbed gas, gas desorption accurately obtains the amount of adsorbed gas adsorbed by the shale cuttings, and the gas determination unit can accurately determine the amount of trace adsorbed gas and present it in the form of data.

[0024] The determination method disclosed in the embodiment of the present application uses rock cuttings instead of cores to determine the gas content of shale. First, it is not subject to time constraints and does not have to be measured on site; second, it overcomes the drawbacks of the inability to estimate the escaped gas and the inaccurate fitting regression calculation when the core is subjected to on-site desorption determination; third, it reduces the construction difficulty and construction cost of extraction, improves construction efficiency, and can realize the extraction of rock cuttings for the entire well section or even the entire region, thereby obtaining accurate key parameters such as overall resource evaluation and reserve calculation of shale gas.

[0025] It is to be understood that the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present specification. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0027] Figure 1 It is a structural schematic diagram of a shale cuttings gas content determination system provided in one embodiment of the present application;

[0028] Figure 2 It is a structural schematic diagram of a shale cuttings gas content determination system provided in one embodiment of the present application;

[0029] Figure 3 It is a structural schematic diagram of a shale cuttings gas content determination system provided in one embodiment of the present application;

[0030] Figure 4 It is a schematic flow chart of a method for determining gas content in shale cuttings provided in one embodiment of the present application.

[0031] In the figure: 10 gas configuration unit, 11 first gas tank, 12 second gas tank, 20 adsorption and desorption unit, 21 third gas tank, 22 electromagnetic pulverization device, 221, electromagnetic pulverization device cavity, 222 material pipe, 30 gas volume measurement unit, 31 tunable laser instrument, 311, laser instrument cavity, 312 laser, 32 display terminal, 411 first pipeline, 412 second pipeline, 413 third pipeline, 414 fourth pipeline, 421 first air pump, 422 second air pump, 423 third air pump, 431 first valve, 432 second valve, 433 third valve, 434 fourth valve. DETAILED DESCRIPTION

[0032] In the following description, specific details such as specific system structures, technologies, etc. are provided for the purpose of illustration rather than limitation, so as to provide a thorough understanding of the embodiments of the present application. However, it should be clear to those skilled in the art that the present application may also be implemented in other embodiments without these specific details. In other cases, detailed descriptions of well-known systems, devices, circuits, and methods are omitted to prevent unnecessary details from obstructing the description of the present application.

[0033] It should be understood that when used in the present specification and the appended claims, the term "comprising" indicates the presence of described features, wholes, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, wholes, steps, operations, elements, components and / or combinations thereof.

[0034] It should also be understood that the term “and / or” used in the specification and appended claims refers to any and all possible combinations of one or more of the associated listed items, and includes these combinations.

[0035] As used in the specification and appended claims of this application, the term "if" can be interpreted as "when" or "uponce" or "in response to determining" or "in response to detecting", depending on the context. Similarly, the phrase "if it is determined" or "if [described condition or event] is detected" can be interpreted as meaning "uponce it is determined" or "in response to determining" or "uponce [described condition or event] is detected" or "in response to detecting [described condition or event]", depending on the context.

[0036] In addition, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.

[0037] References to "one embodiment" or "some embodiments" etc. described in the specification of this application mean that one or more embodiments of the present application include specific features, structures or characteristics described in conjunction with the embodiment. Therefore, the statements "in one embodiment", "in some embodiments", "in some other embodiments", "in some other embodiments", etc. that appear in different places in this specification do not necessarily refer to the same embodiment, but mean "one or more but not all embodiments", unless otherwise specifically emphasized in other ways. The terms "including", "comprising", "having" and their variations all mean "including but not limited to", unless otherwise specifically emphasized in other ways.

[0038] In order to make readers understand better, the nouns involved in the present invention are explained as follows:

[0039] The so-called core refers to the cylindrical rock sample taken out by the core barrel during the drilling process.

[0040] The so-called rock cuttings refer to the granular rock samples that are broken by the drill bit during the drilling process and returned with the drilling fluid.

[0041] The adsorption refers to the phenomenon that the surface layer of shale ore absorbs gas.

[0042] The desorption refers to the phenomenon that the gas adsorbed by the surface of the shale mine is released.

[0043] In the existing field desorption test, the shale core obtained by drilling needs to be placed in the on-site desorption device for desorption as soon as possible to obtain the desorbed gas volume to prevent shale gas from escaping; after the desorption is completed, the shale core is crushed and the released residual gas volume is collected and measured; and the loss of gas released from the shale core during the drilling process is generally obtained by fitting and regressing the desorption data.

[0044] my country's shale reservoirs generally have a deep burial depth and high formation pressure. In the process of extracting shale cores to the ground, as the pressure on the cores gradually weakens, the gas escape is aggravated. Existing test results show that the proportion of shale gas loss in the gas content can reach more than 80%. In addition, the gas escape causes a significant decrease in the core pore pressure obtained by drilling. The desorption data obtained under this pore pressure cannot represent the desorption behavior under the original formation state, further increasing the error in the prediction of lost gas volume.

[0045] Based on the above problems, the embodiment of the present application provides a shale cuttings gas content determination system. In order to make the purpose, technical solution and advantages of the present application clearer and more specific, the present application is described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described below are only used to explain the present application and are not used to limit the present application.

[0046] The following combination Figure 1 The shale cuttings gas content determination system of the present application is described in detail.

[0047] Figure 1 is a schematic diagram of the structure of a shale cuttings gas content determination system provided in an embodiment of the present application, referring to Figure 1 , the system is described in detail as follows:

[0048] The shale cuttings gas content determination system may include: a gas configuration unit 10, an adsorption and desorption unit 20, and a gas determination unit 30. The gas configuration unit 10, the adsorption and desorption unit 20, and the gas determination unit 30 are sequentially connected through pipelines.

[0049] In some embodiments, the gas configuration unit 10 transmits adsorbed gas and non-adsorbed gas to the adsorption and desorption unit 20 .

[0050] Explanation: Adsorbed gas refers to gas that can remove air from the gaps in shale cuttings and adsorb in the gaps in shale cuttings. Adsorbed gas includes alkane gases such as methane, ethane, butane, and carbon dioxide.

[0051] Explanatory, non-adsorbent gas is the gas that cannot be adsorbed in the voids of shale cuttings, and non-adsorbent gas is mostly inert gas. Among them, non-adsorbent gas can also be used to displace adsorbent gas that is not adsorbed by shale cuttings.

[0052] In some embodiments, the adsorption and desorption unit 20 can make the shale cuttings adsorb the adsorbed gas, desorb the adsorbed gas adsorbed by the shale cuttings by crushing the shale cuttings, and transmit the adsorbed gas generated by the desorption to the gas volume measurement unit 30 .

[0053] Explanatory, the adsorption-desorption unit 20 can accelerate or simulate the adsorption of the adsorbent gas by the shale cuttings by changing conditions such as temperature and pressure.

[0054] Explanatory, the adsorption-desorption unit 20 may crush the shale cuttings by a crushing device, so that the shale cuttings release the adsorbent gas adsorbed therein, thereby achieving the purpose of desorption.

[0055] Explanatoryally, the adsorption and desorption unit 20 may also be connected to the gas measurement unit 30 to transmit all the adsorbed gas generated by desorption to the gas volume measurement unit 30 .

[0056] In some embodiments, the gas volume measurement unit 30 can receive the adsorbed gas generated by desorption transmitted by the adsorption and desorption unit 20, and measure and display the gas volume of the adsorbed gas generated by adsorption. The measured gas volume can represent the gas content of the shale cuttings.

[0057] The above is an overall description of the shale cuttings gas content determination system. The following is a detailed description of the various components of the shale cuttings gas content determination system. Figure 2 , as detailed below:

[0058] Figure 2 It is a structural schematic diagram of a shale cuttings gas content determination system provided in one embodiment of the present application.

[0059] In some embodiments, the gas configuration unit 10 may include at least a first gas tank and a second gas tank 20 , wherein the first gas tank 11 is used to store adsorptive gas, and the second gas tank 11 is used to store non-adsorbent gas.

[0060] The first gas tank 11 and the second gas tank 12 are both connected to the adsorption and desorption unit 20 . The first gas tank 10 transmits adsorbed gas to the adsorption and desorption unit 20 , and the second gas tank 12 transmits non-adsorbed gas to the adsorption and desorption unit 20 .

[0061] Explanatory, the first gas tank 11 and the second gas tank 12 are both sealed gas tanks, and the first gas tank 11 and the second gas tank 12 can store high-pressure gas. Exemplarily, the selected first gas tank 11 and the second gas tank 12 can store gas with a pressure value of 15Mpa.

[0062] In some embodiments, the adsorption and desorption unit 20 may include a third gas tank 21 and an electromagnetic pulverization device 22 . The electromagnetic pulverization device 22 includes an electromagnetic pulverization device cavity 221 and a material pipe 222 .

[0063] Optionally, the third gas tank 21 is disposed in the electromagnetic crushing device cavity 221, and the material pipe 222 is disposed in the third gas tank 21. The material pipe 222 is used to crush shale cuttings.

[0064] Optionally, the third gas tank 21 is connected to the first gas tank 11 and the second gas tank 12 respectively, and is used to receive the adsorptive gas transmitted by the first gas tank 11 and the non-adsorbent gas transmitted by the second gas tank 12 .

[0065] Furthermore, the connection point between the third gas tank 21 and the first gas tank 11 and the connection point between the third gas tank 21 and the second gas tank 21 are not in the same horizontal plane. This arrangement is to achieve the purpose of enabling the non-adsorbed gas to displace the non-adsorbed adsorbed gas.

[0066] For example, if the adsorbed gas is methane and the non-adsorbed gas is argon, since the molar mass of the adsorbed gas is less than the molar mass of the non-adsorbed gas, the connection point between the third gas tank 21 and the first gas tank 11 is higher than the connection point between the third gas tank 21 and the second gas tank 21. Figure 2 shown.

[0067] For example, if the adsorbent gas is butane and the non-adsorbent gas is helium, since the molar mass of the adsorbent gas is less than the molar mass of the non-adsorbent gas, the connection point between the third gas tank 21 and the first gas tank 11 is lower than the connection point between the third gas tank 21 and the second gas tank 21.

[0068] Optionally, the third gas tank 21 is in communication with the gas volume measuring unit 30 , and is used to transmit the desorbed adsorbent gas to the gas volume measuring unit 30 .

[0069] Optionally, the third gas tank 21 is communicated with the external space and is used for displacing the non-adsorbed adsorbed gas with the non-adsorbed gas.

[0070] Explanatory note, the third gas tank 21 can adjust the pressure value and temperature value of the third gas tank 21 so that the shale cuttings can fully adsorb the adsorptive gas.

[0071] Furthermore, the third gas tank 21 is a sealed high-pressure gas tank. Exemplarily, the selected third gas tank 21 can store gas with a pressure value not less than 30 MPa.

[0072] Explanatory, the present application adopts an electromagnetic crushing device, not a traditional physical crushing device, in order to ensure the gas pressure in the third gas tank 21 without opening the third gas tank 21 when crushing shale cuttings. Exemplarily, the power of the selected electromagnetic crushing device is 1200W, the loading amount is 40-80g, the crushing time is <2min, and the crushing particle size is ≤200 mesh.

[0073] In some embodiments, the gas measurement unit 30 may include a tunable laser instrument 31 and a display device 32. The tunable laser instrument 31 is electrically connected to the display device 32, and the tunable laser instrument 31 is in pipeline communication with the third gas tank 21.

[0074] Optionally, the tunable laser instrument 31 is used to receive the adsorbed gas generated by desorption, measure the gas volume data of the adsorbed gas generated by desorption, and transmit the gas volume data to the display device 32.

[0075] Explanatory, the tunable laser instrument 31 adopts absorption spectroscopy technology to achieve the gas volume measurement of the adsorbed gas generated by desorption. Exemplarily, the selected tunable laser instrument 31 has a response time of 0.1s, a minimum detection limit of 5ppm, a measurement error of ≤±1%, a long optical path White gas chamber, 17 laser reflection times, and a maximum optical path of 18m.

[0076] Furthermore, the tunable laser instrument 31 may also include a laser instrument inner cavity 311 and a laser 312 .

[0077] The laser cavity 311 is capable of storing the adsorbed gas generated by desorption and transmitted by the third gas tank 21 .

[0078] The laser 312 is a laser specially loaded on the tunable laser instrument 31 for measuring the gas amount data of the adsorbed gas.

[0079] Optionally, the display device 32 is used to receive the gas volume data transmitted by the tunable laser instrument 31, and display the gas volume data as gas volume.

[0080] It should be noted that the display device 32 can be a computer, a wearable device, a vehicle-mounted device, a tablet computer, a laptop computer, a netbook, a personal digital assistant (PDA), an augmented reality (AR) / virtual reality (VR) device, a mobile phone or other terminal device. The embodiment of the present application does not impose any restrictions on the specific type of the display device 32.

[0081] In some embodiments, based on Figure 1 In the illustrated embodiment, the system for determining the gas content in shale cuttings may further include a gas regulating unit.

[0082] Optionally, the gas regulating unit is used to connect the gas configuration unit 10 with the adsorption and desorption unit 20, connect the adsorption and desorption unit 20 with the gas measuring unit 30, and connect the adsorption and desorption unit 20 with the external space.

[0083] Specifically, the gas regulating unit can adjust the gas quantity and gas pressure of the gas transmitted from the first gas tank 11 to the third gas tank 21, adjust the gas quantity and gas pressure of the gas transmitted from the second gas tank 12 to the third gas tank 21, adjust the gas quantity of the gas transmitted from the third gas tank 21 to the laser instrument inner cavity 311, and adjust the gas quantity of the gas transmitted from the third gas tank 21 to the external space.

[0084] In some embodiments, see Figure 3 The gas regulating unit may include a first pipeline 411, a second pipeline 412, a third pipeline 413, a fourth pipeline 414, a first air pump 421, a second air pump 422, a third air pump 423, a first valve 431, a second valve 432, a third valve 433 and a fourth valve 434.

[0085] Specifically, the first pipeline 411 is used to connect the first gas tank 11 and the third gas tank 21, the second pipeline 412 is used to connect the second gas tank 12 and the third gas tank 21, the third pipeline 413 is used to connect the third gas tank 21 and the laser instrument cavity 311, and the fourth pipeline 414 is used to connect the third gas tank 21 and the external space.

[0086] Specifically, the first air pump 421 is disposed on the first pipeline 411, and is used to drive the adsorptive gas in the first gas tank 11 into the third gas tank 21, so that the pressure in the third gas tank 21 is a preset pressure.

[0087] Explanatory, the preset pressure is determined based on the burial depth of the shale cuttings and the formation pressure corresponding to the burial depth.

[0088] Explanatory note: In the actual drilling process, shale cuttings are continuously discharged, and they are discharged while drilling. Therefore, the burial depth of shale cuttings can be known. Generally, shale cuttings obtained from the drilling site are packed into bags of two meters according to the burial depth. The formation pressure corresponding to the burial depth can also be detected or calculated according to the existing technology, and this application will not elaborate in detail.

[0089] Specifically, the second air pump 422 is disposed on the second pipeline 412, and is used to drive the non-adsorbent gas in the second gas tank 12 into the third gas tank 21, so that the pressure in the third gas tank 21 is a preset pressure.

[0090] Specifically, the third air pump 423 is disposed on the third pipeline 413 , and is used to drive the adsorbed gas generated by desorption of the third gas tank 21 to enter the laser instrument inner cavity 311 .

[0091] Specifically, the first valve 431 is disposed on the first pipeline 411 to control the on / off of gas transmission between the first gas tank 11 and the third gas tank 21 .

[0092] Specifically, the second valve 432 is disposed on the second pipeline 412 to control the on / off of gas transmission between the second gas tank 12 and the third gas tank 21 .

[0093] Specifically, the third valve 433 is disposed on the third pipeline 413 to control the on-off of gas transmission between the third gas tank 21 and the inner cavity 311 of the laser instrument.

[0094] Specifically, the fourth valve 434 is disposed on the third gas tank 21, and is used to control the on-off of gas transmission between the third gas tank 21 and the external space.

[0095] The shale cuttings gas content determination system disclosed in the embodiment of the present application is targeted at the adsorption characteristics of shale cuttings, and can accurately determine the true gas content of shale cuttings through adsorption and desorption of shale cuttings. It overcomes the drawbacks of the prior art that the escaped gas cannot be estimated and the fitting regression calculation is not accurate enough when the core is desorbed on site; at the same time, the construction difficulty and construction cost of extracting cuttings are greatly reduced compared with extracting cores, and the extraction of cuttings is no longer limited to specific shale faults and shale areas. By extracting cuttings from the entire well section or even the entire area, shale gas exploration can be carried out in a comprehensive and complete manner in the shale area, thereby accurately obtaining key parameters such as shale gas resource evaluation and reserve calculation.

[0096] The above is a detailed description of the shale cuttings gas content determination system provided by the present application. The present application also discloses a shale cuttings gas content determination method, which is applied to the shale cuttings gas content determination system.

[0097] Below, refer to Figure 4 , the method for determining the gas content of shale cuttings is described in detail. This method can be implemented by executing steps 501 to 503, as described in detail as follows:

[0098] In step 501, gas adsorption: controlling the gas configuration unit to transmit adsorbent gas and non-adsorbent gas to the adsorption and desorption unit, so that the pores of the shale cuttings adsorbent gas and the non-adsorbent gas displaces the adsorbent gas not adsorbed by the shale cuttings.

[0099] In some embodiments, step 501 may be implemented by executing steps 5011 to 5013, as follows:

[0100] In step 5011, shale cuttings are placed in a third gas tank.

[0101] In step 5012, the first valve is controlled to open, and the first air pump is controlled to drive the adsorptive gas in the first gas tank to enter the third gas tank, so that the pressure in the third gas tank reaches a preset first pressure value, and the first valve is controlled to close and maintain a preset time.

[0102] Explanatory note, the preset first pressure value is a pressure value determined according to the burial depth of the shale cuttings and the formation pressure.

[0103] Explanatory, the preset time is the time when the shale cuttings can fully adsorb the adsorbed gas.

[0104] In step 5013, the second valve is controlled to open, and the second air pump is controlled to drive the non-adsorbed gas in the second gas tank to enter the third gas tank. The opening of the fourth valve is controlled based on the operating power of the second air pump, and the preset first pressure value is kept unchanged, so that the non-adsorbed gas displaces the adsorbed gas in the third gas tank that is not adsorbed by the shale cuttings and is discharged from the fourth valve, and the second valve and the fourth valve are controlled to be closed.

[0105] In step 502, gas desorption: controlling the adsorption and desorption unit to crush the shale cuttings, desorbing the adsorbed gas adsorbed by the shale cuttings, and transmitting the adsorbed gas generated by the desorption to the gas volume measuring unit.

[0106] In some embodiments, step 502 may be implemented by executing steps 5021 to 5022, as follows:

[0107] In step 5021, the electromagnetic crushing device is controlled to crush the shale cuttings into shale particles, and the diameter of the shale particles is less than or equal to 200 mesh.

[0108] In step 5022, the third valve is controlled to open, and the third air pump is controlled to drive the adsorbed gas generated by desorption in the third gas tank to enter the laser cavity. After the pressure in the third gas tank reaches a preset second pressure value, the third valve is controlled to close.

[0109] Explanatory, it is unrealistic for the third gas tank to reach a completely vacuum state, so a preset second pressure value is set, and the preset second pressure value is used to represent the amount of gas remaining in the third gas tank. When the preset second pressure value is less than a certain value, it can be approximated that the third gas tank reaches a vacuum state.

[0110] In step 503, gas measurement: the gas volume measurement unit is controlled to receive the adsorbed gas generated by desorption, and the gas volume of the adsorbed gas generated by desorption is measured and displayed.

[0111] In some embodiments, step 502 may be implemented by executing steps 5031 to 5032, as follows:

[0112] In step 5031, the tunable laser is controlled to start, the laser measures the gas volume data of the adsorbed gas, and transmits the gas volume data to the display device.

[0113] In step 5032, the display device receives the gas volume data and displays the gas volume data as gas volume, where the gas volume represents the gas content of the shale cuttings.

[0114] The above-mentioned method for determining the gas content of shale cuttings uses cuttings instead of cores to determine the gas content of shale. First, it is not subject to time constraints and does not have to be measured on site; second, it overcomes the drawbacks of the inability to estimate the escaped gas and the inaccurate fitting regression calculation when the core is desorbed on site; third, it reduces the construction difficulty and construction cost of extraction, improves construction efficiency, and can realize the extraction of cuttings for the entire well section or even the entire region, thereby obtaining accurate key parameters such as overall resource evaluation and reserve calculation of shale gas.

[0115] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.

[0116] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0117] The above-described embodiments are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application is described in detail with reference to the aforementioned embodiments, a person of ordinary skill in the art should understand that the technical solutions described in the aforementioned embodiments can still be modified, or some of the technical features can be replaced by equivalents. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should be included in the protection scope of the present application.

Claims

1. A method for determining the gas content of shale cuttings, characterized in that: Applicable to a shale rock cuttings gas content determination system, the shale rock cuttings gas content determination system comprises a gas configuration unit, an adsorption and desorption unit and a gas content determination unit which are connected in sequence; The gas configuration unit transmits adsorbent gas and non-adsorbent gas to the adsorption and desorption unit, wherein the adsorbent gas can be adsorbed in the pores of the shale cuttings, and the non-adsorbent gas cannot be adsorbed in the voids of the shale cuttings, and the non-adsorbent gas is used to displace the adsorbent gas that is not adsorbed by the shale cuttings; The adsorption and desorption unit can make the shale cuttings adsorb the adsorbed gas, desorb the adsorbed gas adsorbed by the shale cuttings by crushing the shale cuttings, and transmit the adsorbed gas generated by the desorption to the gas volume measurement unit; The gas volume measuring unit receives the adsorbed gas generated by the desorption, measures and displays the gas volume of the adsorbed gas generated by the desorption, and the gas volume represents the gas content of the shale cuttings; The gas configuration unit includes a first gas tank and a second gas tank, the first gas tank stores the adsorbent gas, and the second gas tank stores the non-adsorbent gas; The first gas tank and the second gas tank are both connected to the adsorption and desorption unit, the first gas tank transmits the adsorbed gas to the adsorption and desorption unit, and the second gas tank transmits the non-adsorbed gas to the adsorption and desorption unit; The adsorption and desorption unit comprises a third gas tank; The first gas tank and the second gas tank are both connected to the third gas tank, and the connection point between the second gas tank and the third gas tank and the connection point between the first gas tank and the third gas tank are not on the same horizontal plane; The gas volume measurement unit includes a tunable laser instrument; The shale cuttings gas content determination system also includes a gas regulating unit; The gas regulating unit is connected to the gas configuration unit and the adsorption and desorption unit, connected to the adsorption and desorption unit and the gas measuring unit, and connected to the adsorption and desorption unit and the external space; The gas regulating unit is capable of regulating the gas amount and gas pressure of the gas transmitted from the first gas tank to the third gas tank, regulating the gas amount and gas pressure of the gas transmitted from the second gas tank to the third gas tank, regulating the gas amount of the gas transmitted from the third gas tank to the tunable laser, and regulating the gas amount of the gas transmitted from the third gas tank to the external space; The gas regulating unit comprises a first pipeline, a second pipeline, a third pipeline, a fourth pipeline, a first air pump, a second air pump, a third air pump, a first valve, a second valve, a third valve and a fourth valve; The first pipeline is used to connect the first gas tank with the third gas tank, the second pipeline is used to connect the second gas tank with the third gas tank, the third pipeline is used to connect the third gas tank with the tunable laser instrument, and the fourth pipeline is used to connect the third gas tank with the external space; The first air pump is disposed on the first pipeline, and is used to drive the adsorptive gas in the first gas tank into the third gas tank, so that the pressure in the third gas tank is a preset pressure; The second air pump is disposed on the second pipeline, and is used to drive the non-adsorbent gas in the second gas tank into the third gas tank, so that the pressure in the third gas tank is a preset pressure; The third gas pump is arranged on the third pipeline, and is used for driving the adsorbed gas generated by the desorption of the third gas tank into the tunable laser instrument; The first valve is disposed on the first pipeline and is used to control the on / off of gas transmission between the first gas tank and the third gas tank; The second valve is disposed on the second pipeline and is used to control the on / off of gas transmission between the second gas tank and the third gas tank; The third valve is arranged on the third pipeline, and is used to control the on-off of gas transmission between the third gas tank and the tunable laser instrument; The fourth valve is disposed on the third gas tank and is used to control the on-off of gas transmission between the third gas tank and the external space. The method comprises: Gas adsorption: controlling the gas configuration unit to transmit adsorbent gas and non-adsorbent gas to the adsorption and desorption unit, so that the pores of the shale cuttings adsorb the adsorbent gas, and the non-adsorbent gas displaces the adsorbent gas that is not adsorbed by the shale cuttings; Gas desorption: controlling the adsorption and desorption unit to crush the shale cuttings, desorbing the adsorbed gas adsorbed by the shale cuttings, and transmitting the adsorbed gas generated by the desorption to the gas volume measuring unit; Gas measurement: controlling the gas volume measurement unit to receive the adsorbed gas generated by the desorption, measuring and displaying the gas volume of the adsorbed gas generated by the desorption, wherein the gas volume represents the gas content of the shale cuttings; The control gas configuration unit transmits the adsorbent gas and the non-adsorbent gas to the adsorption and desorption unit, so that the pores of the shale cuttings adsorb the adsorbent gas, and the non-adsorbent gas displaces the adsorbent gas that is not adsorbed by the shale cuttings, including: Place shale cuttings into the third gas tank; Controlling the first valve to open, controlling the first air pump to drive the adsorbed gas in the first gas tank to enter the third gas tank, so that the pressure in the third gas tank reaches a preset first pressure value, controlling the first valve to close, and maintaining the preset time, wherein the preset first pressure value is a pressure value determined according to the burial depth of the shale cuttings and the formation pressure, and the preset time is the time when the shale cuttings can fully adsorb the adsorbed gas; The second valve is controlled to open, and the second air pump is controlled to drive the non-adsorbent gas in the second gas tank to enter the third gas tank. The opening of the fourth valve is controlled based on the operating power of the second air pump, and the preset first pressure value is kept unchanged, so that the non-adsorbent gas displaces the adsorbent gas in the third gas tank that is not adsorbed by the shale cuttings and is discharged from the fourth valve, and the second valve and the fourth valve are controlled to close.

2. The method for determining the gas content of shale cuttings according to claim 1, characterized in that: The adsorption and desorption unit further comprises an electromagnetic pulverizing device, and the electromagnetic pulverizing device comprises a material pipe; The third gas tank is disposed in the cavity of the electromagnetic pulverizing device, the third gas tank is communicated with the gas volume measuring unit, and the third gas tank is communicated with the external space; The material pipe is arranged in the third gas tank, and the material pipe is used for crushing the shale cuttings.

3. The method for determining the gas content of shale cuttings according to claim 2, characterized in that: The gas volume measurement unit also includes a display device; The tunable laser is electrically connected to the display device, and the tunable laser is in communication with the third gas tank; The tunable laser instrument receives the adsorbed gas generated by the desorption, measures the gas volume data of the adsorbed gas generated by the desorption, and transmits the gas volume data to the display device; A display device receives the gas volume data, and displays the gas volume data as the gas volume.

4. The method for determining the gas content of shale cuttings according to claim 3, characterized in that: The tunable laser instrument comprises a laser instrument cavity and a laser; The laser cavity is capable of storing the adsorbed gas generated by the desorption transmitted by the third gas tank, and the laser is a laser for measuring gas quantity data of the adsorbed gas.

5. The method for determining the gas content of shale cuttings according to claim 1, characterized in that: include: The controlling the adsorption and desorption unit to crush the shale cuttings, desorb the adsorbed gas adsorbed by the shale cuttings, and transmit the adsorbed gas generated by the desorption to the gas volume measuring unit includes: Controlling the electromagnetic crushing device to crush the shale cuttings into shale particles, wherein the diameter of the shale particles is less than or equal to 200 meshes; The third valve is controlled to open, and the third air pump is controlled to drive the adsorbed gas generated by the desorption in the third gas tank to enter the laser cavity. After the pressure in the third gas tank reaches a preset second pressure value, the third valve is controlled to close. The preset second pressure value represents the amount of gas remaining in the third gas tank.

Citation Information

Patent Citations

  • Calculating method and measuring device for shale adsorption gas and free gas

    CN105606703A

  • Integrated whole process airtight gas content measuring instrument based on temperature pressure backtracking principle and application of integrated whole process airtight gas content measuring instrument

    CN107727530A

  • Method for judging content of free gas and adsorbed gas in shale gas

    CN108107182A

  • Rock debris logging method

    CN111175471A

  • Experimental system and experimental method for calibrating coal seam gas content measurement error

    CN113447397A