Roof cutting and pressure relief method and support for gob-side entry retention

By drilling holes underground and using high-pressure water injection to form a gob-side lane cutting and pressure relief method that penetrates the fissure zone, the problem of coal dust and gas risks caused by limited underground space is solved, and safe production and cost reduction are achieved.

CN117145475BActive Publication Date: 2024-10-01YUNNAN DIANDONG YUWANG ENERGY CO LTD
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202311174032.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-09-12
Publication Date
2024-10-01
Estimated Expiration
2043-09-12

AI Technical Summary

Technical Problem

The existing roof cutting and pressure relief and gob-side lane retention technology produces a large amount of coal dust when the underground space is limited, and there are flammable gases such as gas underground, which poses a huge threat to the safe production of mines.

Method used

The method of roof cutting and pressure relief is adopted to retain tunnels along the gob. Drill holes at an angle of 15° between the drill holes, and use high-pressure water injection to form a through-going crack zone to achieve directional cutting of the roof, reduce tunnel stress and deformation, and design brackets to support and regulating the high-pressure water injection system to avoid noise and vibration.

Benefits of technology

It achieves underground safe production, reduces the risks of coal dust and gas, reduces tunnel support and maintenance costs, and improves cracking efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117145475B_ABST
    Figure CN117145475B_ABST
Patent Text Reader

Abstract

The invention discloses a method and a support for unloading pressure during roof cutting of goaf-retained lanes, and belongs to the technical field of non-coal pillar mining in coal mines. The method comprises the following steps: determining a roof fracturing position and drilling holes, wherein a spacing between adjacent boreholes is reserved between 450-500 mm and forms an angle of 15° with the vertical direction; sealing the boreholes, and injecting high-pressure water into the boreholes through a booster, while observing the pressure at the sealed holes; after fracturing once, closing the booster and stopping the water injection, and waiting for the pressure to recover to 0 MPa, and then continuing to open the booster to slowly increase the pressure, thereby further expanding the cracks; forming a through fracture zone between adjacent boreholes, thereby realizing directional cutting of the roof of goaf-retained lanes; during the operation of the high-pressure water injection pump, continuously pressurizing an external water source and delivering it to a high-pressure water injection rod and spraying it out from a water spray hole; the high-pressure water flow forms a through fracture zone between adjacent boreholes, thereby realizing directional cutting of the roof of goaf-retained lanes, reducing the pressure and deformation of goaf-retained lanes, and reducing the cost of lane support and maintenance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of non-coal pillar mining in coal mines, in particular to a method and a support for top cutting and pressure relief along a gob-side lane retaining. Background Art

[0002] Green mining is a development direction of coal mining in my country, and coal-pillar-free mining belongs to green mining. Coal-pillar-free mining includes gob-side tunneling and gob-side tunneling. Gob-side tunneling is more commonly used due to its superiority. Gob-side tunneling can recover coal pillars, reduce tunneling volume, achieve Y-type ventilation, and ease the tension between mining and excavation. Gob-side tunneling technology is to use different methods to retain the original drift after the working face is mined, to serve the next working face, and realize dual use of one tunnel. The key to gob-side tunneling is to control the surrounding rock, reduce tunnel stress and deformation, and reduce the cost of tunneling so that it can meet the use requirements.

[0003] The existing technology of top cutting and pressure relief along the goaf retaining tunnel carries out advance pre-splitting blasting on the rock layer on the top of the working face and performs top cutting along a specific direction. However, the underground space is limited and the blasting produces a large amount of coal dust. In addition, there are flammable gases such as gas underground. The blasting process poses a huge threat to the safe production of mines to a certain extent. Therefore, it is necessary to develop a top cutting and pressure relief method and support for goaf retaining tunnel that does not require explosives or blasting personnel. Summary of the invention

[0004] The purpose of the present invention is to solve the problem in the prior art that the limited underground space blasting produces a large amount of coal dust, and there are combustible gases such as gas underground, and the blasting process poses a huge threat to the safe production of the mine to a certain extent, and a method and support for unloading pressure by cutting the top of the goaf-retaining lane are proposed.

[0005] In order to achieve the above object, the present invention adopts the following technical solutions:

[0006] The method of removing pressure by cutting the top of the gob-side entry mainly includes the following steps:

[0007] Step 1: Determine the top plate fracturing position and drill holes. The spacing between adjacent holes is reserved between 450-500mm and at an angle of 15° to the vertical direction.

[0008] Step 2: Seal the borehole and inject water into the borehole at high pressure through the booster, while observing the pressure at the sealed hole;

[0009] Step 3: After the crack is induced once, close the booster and stop injecting water, wait until the pressure returns to 0 MPa, then continue to open the booster to slowly increase the pressure and further expand the crack;

[0010] Step 4: A continuous fracture zone is formed between adjacent boreholes, realizing directional cutting at the top of the gob-retained tunnel.

[0011] The top cutting and pressure relief support along the empty tunnel comprises a top plate, a supporting plate is arranged on the top plate, a side guard plate is rotatably mounted on one side of the supporting plate, and an adjustment frame is rotatably mounted on both sides of the top plate along the length direction, and also includes: a pressure cylinder rotatably mounted on the bottom surface of the supporting plate, a pressure rod is slidably mounted in the pressure cylinder, and the pressure rod is rotatably connected to the side guard plate; a high-pressure water injection assembly, the high-pressure water injection assembly is fixedly mounted on the top plate, a first water inlet pipe is fixedly connected between the pressure cylinder and the high-pressure water injection assembly, and the high-pressure water injection assembly is used for directionally cutting the top plate of the empty tunnel.

[0012] In order to form a through fracture zone between adjacent boreholes and realize directional cutting of the roof of the empty tunnel, preferably, the high-pressure water injection assembly includes: a fixed frame, on which a high-pressure water injection pump is installed, one end of the high-pressure water injection pump is connected to a water source, and the other end of the high-pressure water injection pump is connected to a second water inlet pipe, a high-pressure water injection rod is threadedly installed on the second water inlet pipe, and water spray holes are opened on the high-pressure water injection rod in a circumferential direction; a sealing air bag is fixedly installed on the high-pressure water injection rod, and a manual pump is connected to the sealing air bag through an air inlet pipe; a water injection valve and a pressure gauge are fixedly installed on the second water inlet pipe.

[0013] In order to provide pressure safety reminders to the staff, further, a pressure sensor is fixedly installed on the top of the high-pressure water injection rod, a pressure sensing plate is slidably installed in the high-pressure water injection rod, and a spring is fixedly connected between the pressure sensing plate and the pressure sensor; an alarm is fixedly installed on the fixed frame, and the alarm and the pressure sensor are connected through a signal.

[0014] In order to reduce the noise generated by the high-pressure water injection pump, further, a cover is fixedly installed on the fixing frame, sound insulation cotton is pasted on the inner wall of the cover, and the high-pressure water injection pump is placed in the cover.

[0015] In order to avoid the problem of uneven cracking or water leakage caused by excessive pressure in the high-pressure water injection pump, the invention further includes: a rheostat fixedly mounted on the fixed frame, the rheostat is equipped with a motor, the output end of the motor is connected to a screw rod through a coupling, a speed regulating block is threadedly mounted on the screw rod, the speed regulating block is slidably mounted in the rheostat at the same time, and the rheostat is electrically connected to the high-pressure water injection pump through a wire.

[0016] In order to improve the fracturing efficiency, it further includes: a disturbance tube fixedly connected between the pressure cylinder and the high-pressure water injection rod, the cross-section of one end of the disturbance tube located in the high-pressure water injection rod is smaller than the other end; both the disturbance tube and the first water inlet pipe are fixedly installed with a one-way valve, and the working surfaces of the two one-way valves are opposite.

[0017] In order to protect the high-pressure water injection rod, a rectangular slot is further provided on the top plate, the inner side wall of the rectangular slot is hinged with a rectangular plate that matches the rectangular slot, and a torsion spring is installed at the hinge, a fixing seat is fixedly installed on the rectangular plate, and the high-pressure water injection rod is clamped in the fixing seat.

[0018] In order to facilitate the adjustment of the height and width of the device, preferably, the adjustment frame includes: a width adjustment plate, a length adjustment plate is rotatably installed on the side of the width adjustment plate away from the top plate, a first hydraulic cylinder is rotatably installed on the width adjustment plate, an extended end of the first hydraulic cylinder is rotatably installed at the connection between the width adjustment plate and the length adjustment plate, a second hydraulic cylinder is fixedly installed on the length adjustment plate, and a foot is fixedly installed on the extended end of the second hydraulic cylinder; a slide rail is fixedly installed on the length adjustment plate, movable support legs are symmetrically installed on the slide rail, and a third hydraulic cylinder is connected between the slide rail and the movable support leg.

[0019] In order to improve the stability of the high-pressure water injection rod in a working state, further, a rotating plate is installed on the inner wall of the high-pressure water injection rod for rotation along the circumferential direction, a rubber cover is connected between the rotating plate and the inner wall of the high-pressure water injection rod, a V-shaped spring is fixedly installed on the inner wall of the high-pressure water injection rod, the V-shaped spring is located in the rubber cover, and the two ends of the V-shaped spring are respectively abutted against the inner wall of the high-pressure water injection rod and the rotating plate; a staple is fixedly installed on the rotating plate, and a staple groove matching the staple is opened on the high-pressure water injection rod.

[0020] Compared with the prior art, the present invention provides a method and support for pressure relief of roof cutting in gob-side tunnel retaining, which has the following beneficial effects:

[0021] 1. The pressure relief bracket for cutting the roof of the gob-side tunnel extends the high-pressure water injection rod into the reserved borehole, and injects air into the sealing airbag through a manual pump to expand it and seal the borehole. During the operation of the high-pressure water injection pump, the external water source is continuously pressurized and transported to the high-pressure water injection rod and sprayed out from the water spray hole. The high-pressure water flow forms a through fracture zone between adjacent boreholes, realizing the directional cutting of the roof of the gob-side tunnel, reducing the pressure and deformation of the gob-side tunnel, and reducing the cost of tunnel support and maintenance. At the same time, the sound insulation cotton absorbs part of the noise generated by the high-pressure water injection pump to avoid vibration of the fixed frame, which may cause the high-pressure water injection rod to loosen in the borehole;

[0022] 2. For the pressure relief support for cutting the top of the gob-side tunnel, when a through fracture zone is formed between adjacent boreholes, the pressure in the high-pressure water injection rod decreases, and the pressure sensing plate slides and resets accordingly, and transmits the force to the pressure sensor through the spring. The pressure sensor sends a signal to activate the alarm, reminding the staff to shut down the high-pressure water injection pump;

[0023] 3. The motor of the gob-side tunnel cutting and pressure relief support also works during the operation of the high-pressure water injection pump. The motor drives the screw to rotate. Since the speed regulating block is constrained by the rheostat, the speed regulating block can move linearly on the screw. The resistance in the rheostat is changed by the movement of the speed regulating block, thereby changing the current of the high-pressure water injection pump, so that the high-pressure water injection pump can slowly increase the pressure.

[0024] 4. The top cutting and pressure relief support for gob-side tunnel retaining, during the operation of the high-pressure water injection pump, part of the water enters the pressure cylinder through the first water inlet pipe and pushes the pressure rod to slide, lifting the side guard plate to support the tunnel. When gravel falls from the top, the side guard plate shakes and squeezes the pressure rod, so that part of the water flows quickly from the disturbance pipe into the high-pressure water injection rod. Since the cross-section of the water outlet pipe of the disturbance pipe becomes smaller, the flow rate increases, which can drive the water in the high-pressure water injection rod to quickly impact the borehole, thereby improving the fracturing efficiency.

[0025] 5. When the top-cutting pressure-relieving bracket along the gob-retained tunnel is not in use, the high-pressure water injection rod is fixed in the fixed seat. When the gravel on the top passes over the support plate and hits the top plate, the rectangular plate is flipped under the force, and the high-pressure water injection rod is stored at the bottom of the top plate to avoid deformation of the high-pressure water injection rod. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] Figure 1 This is a schematic structural diagram of the roof cutting and pressure relief support for gob-side tunnel retaining proposed by the present invention;

[0027] Figure 2 A second perspective structural schematic diagram of the gob-side entry retaining roof cutting and pressure relief support proposed by the present invention;

[0028] Figure 3 A schematic diagram of the internal structure of the pressure cylinder of the gob-side entry retaining roof cutting and pressure relief support proposed by the present invention;

[0029] Figure 4 A schematic diagram of the internal structure of the cover of the gob-side tunnel retaining roof cutting and pressure relief support proposed by the present invention;

[0030] Figure 5 This is a schematic diagram of the high-pressure water injection rod structure of the roof cutting and pressure relief support for gob-side tunnel retention proposed by the present invention;

[0031] Figure 6 This is a schematic diagram of the structure of a rheostat for the roof cutting and pressure relief support for gob-side tunnel retaining proposed by the present invention;

[0032] Figure 7 The invention provides a pressure relief support for cutting the top of the gob-side tunnel. Figure 1 A schematic diagram of the structure enlargement in the middle;

[0033] Figure 8 This is a schematic diagram of the nail installation structure of the top cutting and pressure relief support for gob-side tunnel retaining proposed by the present invention;

[0034] Fig. 9 This is a schematic diagram of the internal structure of the high-pressure water injection rod of the gob-side tunnel retaining top cutting and pressure relief support proposed by the present invention.

[0035] In the figure: 1, top plate; 101, rectangular notch; 102, rectangular plate; 103, fixed seat; 2, width adjustment plate; 3, length adjustment plate; 4, first hydraulic cylinder; 5, second hydraulic cylinder; 6, foot pad; 7, side guard plate; 8, pressure cylinder; 9, pressure rod; 10, first water inlet pipe; 11, fixed frame; 12, high-pressure water injection pump; 13, second water inlet pipe; 14, high-pressure water injection rod; 1401, water spray hole; 1402, sealing air bag; 1403, Manual pump; 15. Water injection valve; 16. Pressure gauge; 17. Pressure sensor; 18. Pressure sensing plate; 19. Spring; 20. Disturbance tube; 21. Support plate; 22. Cover; 23. Rheostat; 24. Motor; 25. Screw; 26. Speed ​​regulating block; 27. Slide rail; 28. Moving support leg; 29. ​​Third hydraulic cylinder; 30. Alarm; 31. Fourth hydraulic cylinder; 32. Rotating plate; 33. V-shaped spring; 34. Pin; 35. Rubber cover. DETAILED DESCRIPTION

[0036] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0037] In the description of the present invention, it is necessary to understand that the terms "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0038] Embodiment 1:

[0039] Reference Figure 1-Figure 9 The method of removing pressure by cutting the top of the gob-side entry mainly includes the following steps:

[0040] Step 1: Determine the top plate fracturing position and drill holes. The spacing between adjacent holes is reserved between 450-500 mm, preferably 500 mm, and at an angle of 15° to the vertical direction;

[0041] Step 2: Seal the borehole and inject water into the borehole at high pressure through the booster, while observing the pressure at the sealed hole;

[0042] Step 3: After the crack is induced once, close the booster and stop injecting water, wait until the pressure returns to 0 MPa, then continue to open the booster to slowly increase the pressure and further expand the crack;

[0043] Step 4: A through fracture zone is formed between adjacent boreholes, realizing directional cutting of the roof of the gob-side tunnel.

[0044] In the above-mentioned method steps, the rock mass crushing and swelling characteristics formed by the mine pressure and the roof rock are mainly utilized. By injecting high-pressure water flow inward, a through fracture zone is formed between adjacent boreholes, thereby realizing directional cutting of the roof of the goaf-retained lane, reducing the pressure and deformation of the goaf-retained lane, and reducing the cost of lane support and maintenance. It can effectively solve the problems of stress concentration during mining of the comprehensive mining face, thereby damaging the roof and low utilization rate of protective coal pillars.

[0045] Embodiment 2:

[0046] See also Figure 1-Figure 9 , a top cutting and pressure relief support along the goaf-retaining tunnel comprises a top plate 1, a support plate 21 is arranged on the top plate 1, a side guard plate 7 is rotatably installed on one side of the support plate 21, a fourth hydraulic cylinder 31 is fixedly installed between the rectangular frame and the top plate 1, and adjustment frames are rotatably installed on both sides of the top plate 1 along the length direction, and also includes: a pressure cylinder 8 rotatably installed on the bottom surface of the support plate 21, a pressure rod 9 is slidably installed in the pressure cylinder 8, and the pressure rod 9 is rotatably connected to the side guard plate 7; a high-pressure water injection assembly, the high-pressure water injection assembly is fixedly installed on the top plate 1, a first water inlet pipe 10 is fixedly connected between the pressure cylinder 8 and the high-pressure water injection assembly, and the high-pressure water injection assembly is used for directional cutting of the top of the goaf-retaining tunnel.

[0047] See also Figure 1 and Figure 2 The adjustment frame includes: a width adjustment plate 2, a length adjustment plate 3 is rotatably installed on the side of the width adjustment plate 2 away from the top plate 1, a first hydraulic cylinder 4 is rotatably installed on the width adjustment plate 2, an extended end of the first hydraulic cylinder 4 is rotatably installed at the connection between the width adjustment plate 2 and the length adjustment plate 3, a second hydraulic cylinder 5 is fixedly installed on the length adjustment plate 3, and a pad 6 is fixedly installed on the extended end of the second hydraulic cylinder 5.

[0048] A slide rail 27 is fixedly mounted on the length adjustment plate 3 , and movable support legs 28 are symmetrically mounted on the slide rail 27 . A third hydraulic cylinder 29 is connected between the slide rail 27 and the movable support legs 28 .

[0049] Through the arrangement of the above structure, the second hydraulic cylinder 5 on the length adjustment plate 3 is adjusted to adjust the height of the device as a whole to the lane, and the first hydraulic cylinder 4 on the width adjustment plate 2 is adjusted to adjust the width of the lane as a whole. The support plate 21 is abutted against and supported by the top surface of the lane through the fine adjustment of the fourth hydraulic cylinder 31.

[0050] After the pressure in this area is relieved, the third hydraulic cylinder 29 on the slide rail 27 is adjusted to extend and retract to push the movable support leg 28 to change the support position in the tunnel, thereby achieving advancement to the working surface.

[0051] See also Figure 1 and Figure 2 and Figure 4 and Figure 5 The high-pressure water injection assembly includes: a fixed frame 11, on which a high-pressure water injection pump 12 is mounted, the input end of the high-pressure water injection pump 12 is externally connected to a water source, the output end of the high-pressure water injection pump 12 is connected to a second water inlet pipe 13, a high-pressure water injection rod 14 is threadedly mounted on the second water inlet pipe 13, and a water spray hole 1401 is opened on the high-pressure water injection rod 14 along the circumferential direction; a sealing air bag 1402 is fixedly mounted on the high-pressure water injection rod 14, and a manual pump 1403 is connected to the sealing air bag 1402 through an air inlet pipe; a water injection valve 15 and a pressure gauge 16 are fixedly mounted on the second water inlet pipe 13.

[0052] Both ends of the first water inlet pipe 10 are connected to the pressure cylinder 8 and the output end of the high-pressure water injection pump 12 respectively.

[0053] A cover shell 22 is fixedly mounted on the fixing frame 11 , sound insulation cotton is pasted on the inner wall of the cover shell 22 , and the high-pressure water injection pump 12 is placed in the cover shell 22 .

[0054] Through the arrangement of the above structure, the high-pressure water injection rod 14 is extended into the reserved borehole, and air is injected into the sealing airbag 1402 through the manual pump 1403 to expand it and seal the borehole. During the operation of the high-pressure water injection pump 12, the external water source is continuously pressurized and transported to the high-pressure water injection rod 14 and sprayed out from the water spray hole 1401. The high-pressure water flow forms a through fracture zone between adjacent boreholes, realizes directional cutting of the top of the goaf-retained tunnel, reduces the pressure and deformation of the goaf-retained tunnel, and reduces the tunnel support and maintenance costs.

[0055] At the same time, the sound insulation cotton absorbs part of the noise generated by the high-pressure water injection pump 12, avoiding vibration of the fixing frame 11 and causing the high-pressure water injection rod 14 to loosen in the borehole.

[0056] It should be noted that when the reading of the pressure gauge 16 is 10% lower than the peak value, it means that the top has been fractured once, and it is necessary to shut down the high-pressure water injection pump 12, wait for the pressure to return to 0 MPa, and then restart the high-pressure water injection pump 12 to slowly increase the pressure to further expand the cracks. At the same time, record the pressure changes of the high-pressure water injection pump 12, and cycle fracturing 2-3 times.

[0057] Embodiment 3:

[0058] See also Figure 1-Figure 9 , which is basically the same as Example 2. On the basis of Example 2, the entire technical solution is further optimized.

[0059] See also Figure 2 and Figure 5 , a specific implementation plan for safety reminders for staff has been added. A pressure sensor 17 is fixedly installed on the top of the high-pressure water injection rod 14, and a pressure sensing plate 18 is slidably installed in the high-pressure water injection rod 14. A spring 19 is fixedly connected between the pressure sensing plate 18 and the pressure sensor 17; an alarm 30 is fixedly installed on the fixed frame 11, and the alarm 30 is connected to the pressure sensor 17 through a signal.

[0060] Through the setting of the above structure, when a through fracture zone is formed between adjacent boreholes, the pressure in the high-pressure water injection rod 14 decreases, and the pressure sensing plate 18 slides and resets accordingly, and transmits the force to the pressure sensor 17 through the spring 19. The pressure sensor 17 sends a signal to activate the alarm 30, reminding the staff to shut down the high-pressure water injection pump 12.

[0061] Embodiment 4:

[0062] See also Figure 1-Figure 9 , which is basically the same as Example 3. On the basis of Example 3, the entire technical solution is further optimized.

[0063] See also Figure 2 and Figure 6 , a specific implementation scheme for avoiding the problem that the pressure of the high-pressure water injection pump 12 is directly too high, which is easy to cause uneven cracking or leakage, is added, and also includes: a rheostat 23 fixedly mounted on the fixed frame 11, a motor 24 is mounted on the rheostat 23, the output end of the motor 24 is connected to a screw rod 25 through a coupling, a speed regulating block 26 is threadedly mounted on the screw rod 25, and the speed regulating block 26 is slidably mounted in the rheostat 23 at the same time, and the rheostat 23 and the high-pressure water injection pump 12 are electrically connected through a wire.

[0064] Through the arrangement of the above-mentioned structure, during the operation of the high-pressure water injection pump 12, the motor 24 also works at the same time, and the motor 24 drives the screw rod 25 to rotate. Since the rotation degree of the speed regulating block 26 is constrained by the rheostat 23, the speed regulating block 26 can move linearly on the screw rod 25. The movement of the speed regulating block 26 changes the resistance size in the rheostat 23, thereby changing the current of the high-pressure water injection pump 12, so that the high-pressure water injection pump 12 can slowly increase the pressure.

[0065] Embodiment 5:

[0066] See also Figure 1-Figure 9 , which is basically the same as Example 4. On the basis of Example 4, the entire technical solution is further optimized.

[0067] See also Figure 1 and Figure 2 and Figure 3, a specific implementation scheme for improving the fracturing efficiency is added, and also includes: a disturbance tube 20 fixedly connected between the pressure cylinder 8 and the high-pressure water injection rod 14, the cross-section of one end of the disturbance tube 20 located in the high-pressure water injection rod 14 is smaller than that of the other end; a one-way valve is fixedly installed in the disturbance tube 20 and the first water inlet pipe 10, and the working surfaces of the two one-way valves are opposite.

[0068] Through the arrangement of the above-mentioned structure, during the operation of the high-pressure water injection pump 12, part of the water enters the pressure cylinder 8 through the first water inlet pipe 10 and pushes the pressure rod 9 to slide, lifting the side guard plate 7 to support the tunnel. When gravel falls from the top, the side guard plate 7 shakes and squeezes the pressure rod 9, causing part of the water flow to quickly enter the high-pressure water injection rod 14 from the disturbance pipe 20. Since the cross-section of the water outlet pipe of the disturbance pipe 20 becomes smaller, the flow rate increases, which can drive the water in the high-pressure water injection rod 14 to quickly impact the borehole, thereby improving the fracturing efficiency.

[0069] Embodiment 6:

[0070] See also Figure 1-Figure 9 , which is basically the same as Example 5. On the basis of Example 5, the entire technical solution is further optimized.

[0071] See also Figure 1 and Figure 2 and Figure 7 A specific implementation scheme for protecting the high-pressure water injection rod 14 is added. A rectangular slot 101 is opened on the top plate 1. A rectangular plate 102 matching the rectangular slot 101 is hinged on the inner side wall of the rectangular slot 101, and a torsion spring is installed at the hinge. A fixing seat 103 is fixedly installed on the rectangular plate 102, and the high-pressure water injection rod 14 is clamped in the fixing seat 103.

[0072] Through the arrangement of the above structure, when not in use, the high-pressure water injection rod 14 is fixed in the fixing seat 103. When the gravel on the top passes over the supporting plate 21 and hits the top plate 1, the rectangular plate 102 is flipped by the force, and the high-pressure water injection rod 14 is stored at the bottom of the top plate 1, thereby avoiding deformation of the high-pressure water injection rod 14.

[0073] Embodiment 7:

[0074] See also Figure 1-Figure 9 , which is basically the same as Example 6. On the basis of Example 6, the entire technical solution is further optimized.

[0075] See also Figure 8-Figure 9 The stability of the high-pressure water injection rod 14 in working state is increased to avoid the high-pressure water injection rod 14 being rushed out of the drill hole under the action of water pressure during operation, and the technical scheme of the high-pressure water injection rod 14 is further refined.

[0076] A rotating plate 32 is installed on the inner wall of the high-pressure water injection rod 14 for rotation along the circumferential direction, and a rubber cover 35 is connected between the side wall of the rotating plate 32 and the inner wall of the high-pressure water injection rod 14. A V-shaped spring 33 is fixedly installed on the inner wall of the high-pressure water injection rod 14, and the V-shaped spring 33 is located in the rubber cover 35. The two ends of the V-shaped spring 33 are respectively abutted against the inner wall of the high-pressure water injection rod 14 and the rotating plate 32; a staple 34 is fixedly installed on the rotating plate 32, and a staple groove matched with the staple 34 is opened on the high-pressure water injection rod 14, and the staple 34 is slidably connected to the side wall of the high-pressure water injection rod 14.

[0077] Through the arrangement of the above structure, during operation, when water is pumped into the high-pressure water injection rod 14, a pressure difference is formed between the sealing state inside the rubber cover 35 and the outside, the rotating plate 32 is squeezed by the water and rotates, the V-shaped spring 33 is compressed, and the staple 34 is pushed out of the staple groove by the rotating plate 32 and extends into the top rock. In cooperation with the sealing airbag 1402, the stability and firmness of the high-pressure water injection rod 14 in the borehole are further improved, thereby preventing the high-pressure water injection rod 14 from rushing out of the borehole under the action of water pressure.

[0078] After the water pumping is finished, the V-shaped spring 33 which loses the pressure is reset and pushes the rotating plate 32 to rotate and pull back the clamping nail 34, thereby releasing the fixation of the high-pressure water injection rod 14.

[0079] In this case, all pipes are hoses.

[0080] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. Cutting roof pressure relief support along gob retaining tunnel, It is characterized in that The gob-side tunnel retaining roof cutting and pressure relief support adopts the gob-side tunnel retaining roof cutting and pressure relief method, which mainly includes the following steps: Step 1: Determine the top plate fracturing position and drill holes. The spacing between adjacent holes is reserved between 450-500mm and at an angle of 15° to the vertical direction. Step 2: Seal the borehole and inject water into the borehole at high pressure through the booster, while observing the pressure at the sealed hole; Step 3: After the crack is induced once, close the booster and stop injecting water, wait until the pressure returns to 0 MPa, then continue to open the booster to slowly increase the pressure and further expand the crack; Step 4: A continuous fracture zone is formed between adjacent boreholes, achieving directional cutting of the top of the gob-side entry; The gob-side entry retaining roof cutting pressure relief support comprises a roof plate (1), a support plate (21) is arranged on the roof plate (1), a side guard plate (7) is rotatably mounted on one side of the support plate (21), and adjustment frames are rotatably mounted on both sides of the roof plate (1) along the length direction, and further comprises: A pressure cylinder (8) is rotatably mounted on the bottom surface of the support plate (21), a pressure rod (9) is slidably mounted in the pressure cylinder (8), and the pressure rod (9) is rotatably connected to the side guard plate (7); A high-pressure water injection assembly, the high-pressure water injection assembly being fixedly mounted on the roof (1), a first water inlet pipe (10) being fixedly connected between the pressure cylinder (8) and the high-pressure water injection assembly, the high-pressure water injection assembly being used for directional cutting of the roof of the gob-side tunnel; The high-pressure water injection assembly comprises: A fixing frame (11), wherein a high-pressure water injection pump (12) is mounted on the fixing frame (11), one end of the high-pressure water injection pump (12) is connected to a water source, the other end of the high-pressure water injection pump (12) is connected to a second water inlet pipe (13), a high-pressure water injection rod (14) is threadedly mounted on the second water inlet pipe (13), and a water spray hole (1401) is formed on the high-pressure water injection rod (14) along a circumferential direction; A sealing air bag (1402) is fixedly mounted on the high-pressure water injection rod (14), and a manual pump (1403) is connected to the sealing air bag (1402) via an air inlet pipe; A water injection valve (15) and a pressure gauge (16) are fixedly mounted on the second water inlet pipe (13); A pressure sensor (17) is fixedly mounted on the top of the high-pressure water injection rod (14), a pressure sensing plate (18) is slidably mounted inside the high-pressure water injection rod (14), and a spring (19) is fixedly connected between the pressure sensing plate (18) and the pressure sensor (17); An alarm (30) is fixedly mounted on the fixing frame (11), and the alarm (30) is connected to the pressure sensor (17) via a signal; A rheostat (23) fixedly mounted on the fixing frame (11), the rheostat (23) being equipped with a motor (24), the output end of the motor (24) being connected to a screw rod (25) via a coupling, a speed regulating block (26) being threadedly mounted on the screw rod (25), the speed regulating block (26) being slidably mounted in the rheostat (23), and the rheostat (23) being electrically connected to the high-pressure water injection pump (12) via a wire; A cover shell (22) is fixedly mounted on the fixing frame (11), sound insulation cotton is pasted on the inner wall of the cover shell (22), and the high-pressure water injection pump (12) is placed in the cover shell (22).

2. The roof cutting and pressure relief support for gob-side tunnel retaining according to claim 1, It is characterized in that Also includes: a disturbance tube (20) fixedly connected between the pressure cylinder (8) and the high-pressure water injection rod (14), wherein the cross-section of one end of the disturbance tube (20) located inside the high-pressure water injection rod (14) is smaller than that of the other end; One-way valves are fixedly installed in the disturbance pipe (20) and the first water inlet pipe (10), and the working surfaces of the two one-way valves are opposite.

3. The roof cutting and pressure relief support for gob-side tunnel retaining according to claim 1, It is characterized in that The top plate (1) is provided with a rectangular slot (101), a rectangular plate (102) matching the rectangular slot (101) is hingedly connected to the inner side wall of the rectangular slot (101), and a torsion spring is installed at the hinge, a fixing seat (103) is fixedly installed on the rectangular plate (102), and the high-pressure water injection rod (14) is clamped in the fixing seat (103).

4. The roof cutting and pressure relief support for gob-side tunnel retaining according to claim 1, It is characterized in that The adjustment frame includes: A width adjustment plate (2), a length adjustment plate (3) being rotatably mounted on a side of the width adjustment plate (2) away from the top plate (1), a first hydraulic cylinder (4) being rotatably mounted on the width adjustment plate (2), an extended end of the first hydraulic cylinder (4) being rotatably mounted on a connection between the width adjustment plate (2) and the length adjustment plate (3), a second hydraulic cylinder (5) being fixedly mounted on the length adjustment plate (3), a pad (6) being fixedly mounted on an extended end of the second hydraulic cylinder (5); A slide rail (27) is fixedly mounted on the length adjustment plate (3), a movable support leg (28) is symmetrically mounted on the slide rail (27), and a third hydraulic cylinder (29) is connected between the slide rail (27) and the movable support leg (28).

5. The roof cutting and pressure relief support for gob-side tunnel retaining according to claim 1, It is characterized in that A rotating plate (32) is rotatably mounted on the inner wall of the high-pressure water injection rod (14) in a circumferential direction, a rubber cover (35) is connected between the rotating plate (32) and the inner wall of the high-pressure water injection rod (14), a V-shaped spring (33) is fixedly mounted on the inner wall of the high-pressure water injection rod (14), the V-shaped spring (33) is located in the rubber cover (35), and two ends of the V-shaped spring (33) are respectively in contact with the inner wall of the high-pressure water injection rod (14) and the rotating plate (32); A clamping nail (34) is fixedly mounted on the rotating plate (32), and a nail groove matching the clamping nail (34) is formed on the high-pressure water injection rod (14).

Citation Information

Patent Citations

  • Method for controlling roof caving under condition of hardroof in coal mining

    CN101705821A

  • Topping pressure-relief method for gob-side entry retaining

    CN107191187A

  • Pressure-release anti-impact method for hydraulic cutting of hard and thick top plate

    CN107816352A

  • Reinforced supporting device for roadway

    CN112065474A

  • Visual coal seam water injection two-phase seepage experiment system and method

    CN112098274A