A construction technology of underground continuous wall
By using sodium sulfonate modified nanosilica particles as retarder in underground continuous wall construction, the setting time and strength of concrete are adjusted, and the problems of discomfort and low strength during construction are solved, which significantly improves construction stability and safety, achieving improved impermeability and durability.
Patent Information
- Application Number
- CN202311288599.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Priority Date
- 2023-07-06
- Filing Date
- 2023-10-07
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2043-10-07
AI Technical Summary
In the construction of underground continuous walls, the existing technology is difficult to effectively solve the problems of concrete settling time adjustment, low strength and high leakage probability, especially in complex underground conditions, which affects construction stability and quality safety.
Using sodium sulfonate modified nanosilica particles as retarder, by adjusting the addition amount of γ-mercaptopropyl trimethoxysilane, the concrete settling time is extended, and its later strength and permeability are enhanced, combining with specific Underwater concrete formulation and construction technology ensure the stability and durability of concrete.
It effectively avoids landslides and leakage problems in underground continuous wall construction, significantly improves the later strength and durability of concrete, is suitable for construction under complex conditions, and improves construction efficiency and quality safety.
Smart Images

Figure CN117344714B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of building construction, and in particular to an underground continuous wall construction process. Background Art
[0002] Underground continuous wall construction refers to the use of special trenching machinery to dig a narrow and deep trench in sections along the designed position on the ground of the proposed underground building, clear the foundation, sink a steel cage in the trench and pour underwater concrete to build a section of reinforced concrete wall. Connect several wall sections into a whole to form a continuous underground wall. Due to the complex underground conditions, the surrounding soil will be disturbed during the trenching construction of the continuous wall, which may cause the trench wall to collapse and affect the overall stability of the subsequent continuous wall. Therefore, it is necessary to design a reasonable underground continuous wall construction process to reduce the occurrence of the above problems.
[0003] During the construction of underground continuous walls, the impact of groundwater on building materials should be fully evaluated. According to the classification of groundwater corrosiveness to building materials by the environment and soil permeability, the groundwater environment type is Class II and the ground permeability is Class A. Site soil is slightly corrosive to both concrete structures and steel bars in reinforced concrete structures, and groundwater is slightly corrosive to concrete structures and steel bars in reinforced concrete structures. Therefore, in the construction of underground continuous walls, the strength requirements for underwater concrete are relatively high.
[0004] In addition, in the process of pouring underwater concrete during the construction of underground continuous walls, it is necessary to ensure the appropriate setting time. If the setting time is too short, the hydration heat will be too high due to too fast hydration, the connection of special parts is not dense, and plastic cracks will appear. A series of problems will affect the later strength and durability of concrete and cause quality and safety hazards. Moreover, too short a setting time is not conducive to the overall pouring and construction of underground continuous walls.
[0005] The application of retarder can effectively prolong the initial setting time of concrete. Retarder is a common admixture used to prolong the setting time of concrete. In the summer construction process, adding a proper amount of retarder can make the newly mixed concrete maintain good plasticity for a long time, facilitate construction, and improve work efficiency. Especially in the construction process of large-volume concrete, in order to prevent the concrete from producing temperature cracks due to excessive concentration of hydration heat, adding retarder becomes one of its important means; and for high temperature seasons, a proper amount of retarder can prevent the concrete from collapsing too quickly and losing workability. Currently, commonly used retarders mainly include organic retarders such as molasses, wood sulfonates, carboxyl acids and their salts, and inorganic retarders such as phosphates, borax, etc. However, although organic retarders can achieve good retarding effects, they have adverse effects on the strength and workability of concrete; and inorganic retarders are not easy to control the adjustment of setting time, and cannot meet the requirements of underground continuous wall construction projects for concrete retarding time. Therefore, it is of great significance to develop a retarder material suitable for underground continuous wall construction technology, which has convenient adjustment of the retarding time and can enhance the later strength, durability and impermeability of concrete. Summary of the invention
[0006] In view of the deficiencies of the prior art, the present invention provides an underground continuous wall construction method capable of reducing the probability of leakage of the underground continuous wall, thereby solving the problems of cracks, low strength and high probability of leakage of the existing underground continuous wall.
[0007] To this end, the technical solution provided by the present invention is as follows:
[0008] An underground continuous wall construction process comprises the following steps in sequence:
[0009] 1) Preliminary preparation work, leveling the site;
[0010] 2) Construction of guide walls;
[0011] 3) Excavated underground continuous wall trench;
[0012] 3.1) Use hydraulic grab bucket trenching machine to excavate the soil layer;
[0013] 3.2) Use pile drivers with round and square hammers to excavate the rock sections;
[0014] 4) Hanging the steel cage;
[0015] According to the law of moment balance and the principle that the moment deformation is minimal when the positive and negative moments are equal, the main and auxiliary hanging points are calculated and the steel cage is placed;
[0016] 5) Pouring underwater concrete;
[0017] Underwater concrete is poured into a steel cage, wherein the underwater concrete comprises cement, coarse and fine aggregates, a water reducing agent and a retarder; wherein the retarder is sodium sulfonate modified nano-silicon dioxide particles, which are prepared by the following method:
[0018] Add γ-mercaptopropyltrimethoxysilane and ammonia water to the silica sol and stir to mix evenly, then heat to 20-60°C and stir to react for 1-6 hours, add hydrogen peroxide solution and stir to react for 2-10 hours after the reaction is completed, add sodium hydroxide solution to adjust the pH value of the system to 8-10 after the reaction is completed, centrifuge, wash, dry and crush the product to obtain sodium sulfonate modified nano silica particles.
[0019] The amount of γ-mercaptopropyltrimethoxysilane added is 8% to 35% of the mass of silicon dioxide in the silica sol. The retarder of the present invention can simply adjust the retarding time by adding the amount of γ-mercaptopropyltrimethoxysilane to meet the requirements of different construction projects for the retarding time of concrete, and can enhance the later strength, durability and impermeability of concrete.
[0020] Furthermore, in the above-mentioned underground continuous wall construction process, the guide wall type is adopted type.
[0021] Furthermore, in the above-mentioned underground continuous wall construction process, the guide wall construction process is as follows: the guide wall construction is carried out in sections, each section is about 20 to 30 meters long, and during the guide wall construction, the guide wall is first excavated, the guide wall steel bars are tied, the formwork is erected, and the guide wall concrete is poured; after the cast-in-place reinforced concrete guide wall is demolded, supports are immediately set up between the two guide walls at a spacing of 2m, and maintenance is carried out; when the concrete strength of the guide wall reaches 80% of the design strength, trenching construction can be carried out.
[0022] Furthermore, in the above-mentioned underground continuous wall construction process, the cement is ordinary Portland cement; the coarse and fine aggregates are crushed stone with a particle size of 5 to 40 mm and natural sand, artificial sand, bentonite, clay, alumina, and barite with a particle size of 0.15 to 5 mm; the water reducer is a polycarboxylic acid-based high-performance water reducer; and the underwater concrete is composed of the following components in percentage by mass:
[0023] Cement: 10%~35%, coarse and fine aggregate: 30%~65%, water reducer: 0.5%~2%, retarder: 0.2%~2%, water: balance.
[0024] Furthermore, in the above-mentioned underground continuous wall construction process, during the trenching process of the soil layer, when the verticality of the grab and the deviation of the X and Y axis directions of the plane position exceed the allowable value, correction is immediately carried out and mud is added in time to maintain the stability of the mud liquid level in the guide wall.
[0025] Furthermore, in the above-mentioned underground continuous wall construction process, in the rock-embedded slot section, the grab stops when it reaches the rock surface, and the bottom of the slot is basically level. When the rotary drilling rig and pile driver are accurately positioned and the mud is prepared to the required standard, rock flushing begins. The standard slot section is 6.0m. The rotary drilling rig and pile driver should complete the flushing work of 5 main holes. After flushing, the pile driver needs to use a square hammer to repair the slot and remove the corners that the round hammer cannot impact, and then lower the steel cage.
[0026] Furthermore, in the above-mentioned underground continuous wall construction process, the trench depth should be measured and checked after the trench is formed. After verification, the first trench cleaning should be carried out; first, the remaining soil and sediment at the bottom of the trench should be grabbed with a grab bucket, and then the hole should be cleaned with reverse circulation. In order to ensure the effective removal of sediment at the bottom of the trench, the bottom should be cleaned with a grab bucket and mud circulation in time during the trenching process to replace the high-density mud; after the trench reaches the designed elevation, a grab bucket should be used for secondary bottom cleaning to ensure that the sediment thickness after the hole cleaning is less than 5cm, the mud density within 500mm of the trench bottom is less than 1.15, and the top slag and the super-high concrete should be chiseled out before pouring the crown beam. After the steel mesh is placed in the trench, the second round of slag cleaning should be carried out. After the sediment at the bottom of the trench is cleaned, the underwater concrete should be poured immediately.
[0027] Furthermore, the above-mentioned underground continuous wall construction process also includes pre-embedded plastic foam at the location where the holes are set in the underground continuous wall and on the outer side of the embedded connecting parts.
[0028] Furthermore, in the above-mentioned underground continuous wall construction process, before pouring underwater concrete, there must be a concrete storage volume in the storage hopper that is sufficient to bury the bottom end of the conduit in the concrete to a depth of more than 0.8m at one time; when pouring concrete, an inflatable bladder is used as a water stop, and the concrete tank truck directly delivers the concrete to the funnel on the conduit, and the pouring speed is controlled at 3 to 5 meters per hour; when pouring, each conduit must be carried out synchronously, keeping the concrete surface rising in a horizontal state, and the height difference of the concrete surface must not be greater than 300 mm; during the pouring process, the rising height of the concrete surface must be measured frequently, and the buried depth of the conduit must be controlled at 2.0 to 4.0 m. The pouring process must be carried out continuously, and the interruption time must not exceed 30 minutes. When pouring to the top of the wall, it must be over-poured by 500 mm.
[0029] Furthermore, in the above-mentioned underground continuous wall construction process, in order to prevent the steel mesh from irreversible deformation during the lifting and assembly process, various shapes of steel mesh are equipped with longitudinal trusses, including two lifting main trusses and one or two reinforcing trusses for each steel mesh. In order to strengthen its integrity, "X"-shaped scissor bars are set on the upper and lower meshes; the main truss is composed of "W"-shaped steel bars. The transverse truss is arranged every 1.25m and strengthened at the lifting point; and additional diagonal rods are added for reinforcement.
[0030] Compared with the prior art, the underground continuous wall construction process of the present invention has the following beneficial effects:
[0031] (1) The technical solution provided by the present invention can be constructed under various complex conditions, effectively avoiding landslides and having good stability.
[0032] (2) The underwater concrete in the construction process of the present invention uses specific sodium sulfonate modified nano-silica particles as a retarder, which has the advantage of convenient adjustment of the retarding time and can significantly enhance the later strength, durability and impermeability of concrete compared with conventional organic retarders and inorganic retarders. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 A process flow chart of underground continuous wall construction provided in Example 1. DETAILED DESCRIPTION
[0034] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0035] The present invention provides an underground continuous wall construction process, the process flow chart is shown in Figure 1 , comprising the following steps in sequence:
[0036] 1) Preliminary preparation work, leveling the site;
[0037] 2) Construction Type guide wall;
[0038] The guide wall construction process is as follows: the guide wall construction is carried out in sections, each section is about 20 to 30 meters long. During the guide wall construction, the guide wall is first excavated, the guide wall steel bars are tied, the formwork is erected, and the guide wall concrete is poured; after the cast-in-place reinforced concrete guide wall is demolded, supports are immediately set at a spacing of 2m between the two guide walls, and maintenance is carried out; when the concrete strength of the guide wall reaches 80% of the design strength, trenching construction can be carried out.
[0039] 3) Excavated underground continuous wall trench;
[0040] 3.1) Use hydraulic grab bucket trenching machine to excavate the soil layer;
[0041] During the trenching process of the soil layer, if the verticality of the grab and the deviation of the X and Y axis directions of the plane position exceed the allowable value, correct the deviation immediately and add mud in time to maintain the stability of the mud liquid level in the guide wall.
[0042] 3.2) Use pile drivers with round and square hammers to excavate the rock sections;
[0043] In the rock-embedded slot section, the grab stops when it reaches the rock surface and makes the bottom of the slot basically level. When the rotary drilling rig and pile driver are accurately positioned and the mud is prepared to the standard, rock flushing begins. The standard slot section is 6.0m. The rotary drilling rig and pile driver should complete the flushing work of 5 main holes. After flushing, the pile driver needs to use a square hammer to repair the slot and remove the corners that the round hammer cannot impact, and then lower the steel cage.
[0044] 4) Hanging the steel cage;
[0045] According to the law of moment equilibrium, the bending deformation is minimal when the positive and negative moments are equal.
[0046] It was concluded that the main hanging point should be set at the end of the steel mesh and 12 meters away from the end of the steel mesh, and the auxiliary hanging point should be set at about 5 meters away from the end of the steel mesh.
[0047] 5) Pouring underwater concrete;
[0048] Before pouring underwater concrete, there must be enough concrete storage in the storage hopper to bury the bottom end of the conduit in the concrete to a depth of more than 0.8m at one time; when pouring concrete, use an inflatable ball as a water stop, and the concrete tanker directly delivers the concrete to the funnel on the conduit. The pouring speed is controlled at 3-5 meters per hour; when pouring, each conduit must be carried out synchronously to keep the concrete surface rising in a horizontal state, and the height difference of the concrete surface must not be greater than 300 mm; during the pouring process, the rising height of the concrete surface must be measured frequently, and the buried depth of the conduit must be controlled at 2.0-4.0m. The pouring process must be carried out continuously, and the interruption time must not exceed 30 minutes. When pouring to the top of the wall, it must be over-poured by 500mm.
[0049] The underwater concrete is composed of the following components in percentage by mass:
[0050] Ordinary Portland cement: 14.5%, crushed stone with a particle size of 5 to 40 mm: 24%, natural sand with a particle size of 0.15 to 5 mm, bentonite, clay, alumina and barite: 38.5%, polycarboxylic acid-based high-performance water reducer: 1.2%, retarder: 0.8%, water: 21%. The retarder is sodium sulfonate modified nano-silica particles, which are prepared by the following method:
[0051] Add γ-mercaptopropyltrimethoxysilane and ammonia water to the silica sol and stir to mix evenly, then heat to 40°C and stir to react for 3 hours, add hydrogen peroxide solution and stir to react for 5 hours after the reaction is completed (the amount of hydrogen peroxide solution added is based on the total oxidation of mercaptopropyl groups to sulfonic acid groups, generally 2 to 5 times the molar amount of γ-mercaptopropyltrimethoxysilane in terms of hydrogen peroxide molar amount), add sodium hydroxide solution after the reaction is completed to adjust the pH value of the system to 9 to 10, and the product is centrifuged, washed, dried, and crushed to obtain sodium sulfonate modified nano-silica particles.
[0052] In order to prevent the steel mesh from irreversible deformation during the lifting and assembly process, longitudinal trusses are set for steel meshes of various shapes, including two main lifting trusses and one or two reinforcing trusses for each steel mesh. In order to strengthen its integrity, "X"-shaped scissor bars are set on the upper and lower meshes; the main truss is composed of "W"-shaped steel bars. One transverse truss is arranged every 1.25m, and the lifting point is strengthened; additional inclined rods are added for reinforcement. Plastic foam is embedded in the location where the holes are set in the ground-connected wall and on the outside of the embedded connectors.
[0053] It should be noted that after the trench is formed, the depth of the trench should be measured and checked. After verification, the first trench cleaning should be carried out; first, the remaining soil and sediment at the bottom of the trench should be grabbed with a grab bucket, and then the hole should be cleaned with reverse circulation. In order to ensure the effective removal of sediment at the bottom of the trench, the bottom should be cleaned with a grab bucket and mud circulation in time during the trench forming process to replace the high-density mud; after the trench reaches the designed elevation, the grab bucket should be used for secondary bottom cleaning to ensure that the sediment thickness after the hole cleaning is less than 5cm, the mud density within 500mm of the trench bottom is less than 1.15, and the top scum and the super-high concrete should be chiseled out before pouring the crown beam. After the steel mesh is placed in the trench, the second round of slag cleaning should be carried out. After the sediment at the bottom of the trench is cleaned, the underwater concrete should be poured immediately.
[0054] The performance of underwater concrete in this embodiment was tested:
[0055] (1) The amount of γ-mercaptopropyltrimethoxysilane added was adjusted to 4%, 8%, 15%, 25%, 35% and 45% of the mass of silica in the silica sol. The underwater concretes obtained were respectively counted as T-4, T-8, T-15, T-25, T-35 and T-45. The setting time (GB / T 50080-2016), strength (GB / T 50081-2019) and durable impermeability (GB / T50082-2009) tests were carried out on different underwater concretes. The same amount of sodium lignosulfonate and sodium tripolyphosphate was added as the control group, and no retarder was added as the blank group. The results are shown in Table 1 below.
[0056] Table 1
[0057] Test Group / Performance Initial setting time Final setting time 28d compressive strength Anti-seepage pressure T-4 6.5h 9.2h 33.4Mpa 0.69MPa T-8 24.6h 30.7h 42.3Mpa 0.84MPa T-15 36.2h 41.9h 48.6Mpa 0.92Mpa T-25 45.7h 53.1h 52.2Mpa 1.05Mpa T-35 55.0h 63.8h 55.9Mpa 1.16Mpa T-45 56.4h 65.1h 56.6Mpa 1.16Mpa Sodium lignosulfonate 38.0h 45.6h 32.6Mpa 0.87MPa Sodium tripolyphosphate 12.2h 17.5h 33.5Mpa 0.76MPa Blank group 3.8h 8.9h 32.9Mpa 0.67MPa
[0058] It can be seen from the results in Table 1 that the sodium sulfonate modified nano-silica particle retarder used in the present invention can significantly improve the late strength and durable impermeability of concrete compared with the existing sodium wood sulfonate or sodium tripolyphosphate retarder; and the retarding time can be flexibly adjusted, which is very suitable for underwater concrete pouring in the underground continuous wall construction process.
[0059] (2) Taking underwater concrete T-35 as the test sample, the mass percentage of retarder added was adjusted to 0.1%, 0.2%, 0.4%, 0.8%, 1.5% and 2.0% respectively, and the corresponding setting time, strength and durable impermeability test were tested. The results are shown in Table 2 below.
[0060] Table 2
[0061]
[0062]
[0063] It can be seen from the results in Table 2 that the retarder of the present invention can effectively prolong the setting time of concrete and significantly enhance the late strength and durable impermeability of concrete when the addition amount is within the range of 0.2% to 2%.
[0064] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A construction process for underground continuous wall, It is characterized in that The steps are as follows: 1) Preliminary preparation work, leveling the site; 2) Construction of guide walls; 3) Excavation of underground continuous wall trench; 3.1) Use hydraulic grab bucket trenching machine to excavate the soil layer; 3.2) Use pile drivers with round and square hammers to excavate the rock sections; 4) Hanging the steel cage; According to the law of moment balance and the principle that the moment deformation is minimal when the positive and negative moments are equal, the main and auxiliary hanging points are calculated and the steel cage is placed; 5) Pouring underwater concrete; Underwater concrete is poured into a steel cage, wherein the underwater concrete comprises cement, coarse and fine aggregates, a water reducing agent and a retarder; wherein the retarder is sodium sulfonate modified nano-silicon dioxide particles, which are prepared by the following method: Add γ-mercaptopropyltrimethoxysilane and ammonia water to the silica sol and stir to mix evenly, then heat to 20-60°C and stir to react for 1-6 hours, add hydrogen peroxide solution and stir to react for 2-10 hours after the reaction is completed, add sodium hydroxide solution to adjust the pH value of the system to 8-10 after the reaction is completed, centrifuge, wash, dry and crush the product to obtain sodium sulfonate modified nano-silica particles.
2. The underground continuous wall construction process according to claim 1, It is characterized in that The added amount of the γ-mercaptopropyltrimethoxysilane is 8% to 35% of the mass of silicon dioxide in the silica sol.
3. The underground continuous wall construction process according to claim 1, It is characterized in that The guide wall adopts the "┓┏" type; the guide wall construction is carried out in sections, each section is 20 to 30 meters long. During the guide wall construction, the guide wall is first excavated, the guide wall steel bars are tied, the formwork is erected, and the guide wall concrete is poured; after the cast-in-place reinforced concrete guide wall is demolded, supports are immediately set up between the two guide walls at a spacing of 2m, and maintenance is carried out; when the concrete strength of the guide wall reaches 80% of the design strength, trenching construction can be carried out.
4. The underground continuous wall construction process according to claim 2, It is characterized in that The cement is ordinary Portland cement; the coarse and fine aggregates are crushed stone with a particle size of 5 to 40 mm and natural sand, artificial sand, bentonite, clay, alumina, and barite with a particle size of 0.15 to 5 mm; the water reducer is a polycarboxylic acid high-performance water reducer; the underwater concrete is composed of the following components in percentage by mass: composition: Cement: 10%~35%, coarse and fine aggregate: 20%~65%, water reducer: 0.5%~2%, retarder: 0.2%~2%, water: balance.
5. The underground continuous wall construction process according to claim 1, It is characterized in that During the trenching process of the soil layer, if the verticality of the grab and the deviation of the X and Y axis directions of the plane position exceed the allowable value, correct the deviation immediately and add mud in time to maintain the stability of the mud liquid level in the guide wall.
6. The underground continuous wall construction process according to claim 1, It is characterized in that In the rock-embedded slot section, the grab stops when it reaches the rock surface and makes the bottom of the slot basically level. When the rotary drilling rig and pile driver are accurately positioned and the mud is prepared to the standard, rock flushing begins. The standard slot section is 6.0m. The rotary drilling rig and pile driver should complete the flushing work of 5 main holes. After flushing, the pile driver needs to use a square hammer to repair the slot and remove the corners that the round hammer cannot impact, and then lower the steel cage.
7. The underground continuous wall construction process according to claim 1, It is characterized in that After the trench is formed, the trench depth should be measured and checked. After verification, the first trench cleaning should be carried out; first, use a grab bucket to grab the remaining soil and sediment at the bottom of the trench, and then use reverse circulation to clean the hole; in order to ensure the effective removal of sediment at the bottom of the trench, use a grab bucket and mud circulation to clean the bottom in time during the trench forming process and replace the high-density mud; after the trench reaches the designed elevation, use a grab bucket to carry out a second bottom cleaning to ensure that the sediment thickness after cleaning the hole is less than 5cm, and the mud density within 500mm height of the trench bottom is less than 1.15, and the top slag and the super-high part of the concrete should be chiseled out before pouring the crown beam; after the steel mesh is lowered into the trench, the second round of slag cleaning should be carried out. After the sediment at the bottom of the trench is cleaned, underwater concrete should be poured immediately.
8. The underground continuous wall construction process according to claim 1, It is characterized in that It also includes pre-embedded plastic foam at the locations where holes are set in the ground-connected wall and at the outer sides of the embedded connecting parts.
9. The underground continuous wall construction process according to claim 1, It is characterized in that Before pouring underwater concrete, there must be enough concrete storage in the storage hopper to bury the bottom end of the conduit in the concrete to a depth of more than 0.8m at one time; when pouring concrete, use an inflatable ball as a water stop, and the concrete tank truck directly delivers the concrete to the funnel on the conduit. The pouring speed is controlled at 3-5 meters per hour; when pouring, each conduit must be carried out synchronously to keep the concrete surface rising in a horizontal state, and the height difference of the concrete surface must not be greater than 300 mm; during the pouring process, the rising height of the concrete surface must be measured frequently, and the buried depth of the conduit must be controlled at 2.0-4.0m. The pouring process must be carried out continuously, and the interruption time must not exceed 30 minutes. When pouring to the top of the wall, it must be over-poured by 500mm.
10. The underground continuous wall construction process according to claim 1, It is characterized in that In order to prevent the steel mesh from irreversible deformation during the lifting and assembly process, longitudinal trusses are set up for steel meshes of various shapes, including two main lifting trusses and one or two reinforcing trusses for each steel mesh. In order to strengthen its integrity, "X"-shaped scissors bars are set up on the upper and lower meshes; the main truss is composed of "W"-shaped steel bars; the transverse trusses are arranged every 1.25m and reinforced at the lifting points; and additional diagonal rods are required for reinforcement.