Construction method of inclined wall and stairs
By using a method of integral casting of the sloping wall and the staircase, the problem of low efficiency in casting the wall and the staircase in stages was solved, and the sloping wall and the staircase were formed as a whole, which improved the construction efficiency and the casting quality.
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-31
- Publication Date
- 2026-03-24
AI Technical Summary
In existing technologies, the walls and stairs need to be poured in two separate pours, resulting in low construction efficiency.
The method of casting-in-place sloping walls and stairs is adopted. The sloping wall baffle and the staircase casting box are built at the construction site of the sloping wall. The main connecting steel bars are used to form a rectangular frame structure, and the sloping wall and stairs are cast in one pouring process.
This method enables the sloping wall and staircase to be formed simultaneously in a single pouring operation, improving construction efficiency, reducing installation difficulty and voids during construction, and enhancing pouring quality and structural stability.
Smart Images

Figure CN117344924B_ABST
Abstract
Description
TECHNICAL FIELD
[0001] The present application relates to a construction method for pouring a wall and a staircase integrally, and belongs to the technical field of building construction. BACKGROUND
[0002] In a conventional construction process, the pouring of a wall and a staircase is separated, and generally, the wall is poured first, then a platform beam for bearing the staircase is poured on the wall, and then the staircase is built between the platform beam and the ground. In this process, the wall and the staircase need to be poured twice, which makes the conventional construction process inefficient. SUMMARY
[0003] The technical problem to be solved by the present application is to provide a construction method for pouring a wall and a staircase integrally, which solves the problem of inefficient conventional construction process caused by the need to pour the wall and the staircase twice.
[0004] The technical problem to be solved by the present application is solved by the following technical solution: a construction method for pouring a wall and a staircase integrally, the construction method comprising
[0005] S1: erecting two inclined wall stop plates side by side at the construction site of the inclined wall, the space between the two inclined wall stop plates being an inclined wall pouring space;
[0006] S2: horizontally inserting a plurality of main connecting steel bars into the inclined wall stop plate, the main connecting steel bars being rigidly fixed to the inclined wall stop plate, one end of the main connecting steel bars extending into the inclined wall pouring space, and the other end of the main connecting steel bars extending away from the inclined wall stop plate;
[0007] S3: arranging two side stop plates side by side, fixing a front stop plate to one end of the two side stop plates, and fixing a rear connecting plate to the other end of the two side stop plates, so that the two side stop plates, the front stop plate, and the rear connecting plate form a rectangular frame structure,
[0008] S4: aligning the reserved holes on the two side stop plates of the rectangular frame structure with the end portions of the main connecting steel bars, inserting the side stop plates into the main connecting steel bars away from the inclined wall stop plate, and abutting the side stop plates against the inclined wall stop plate;
[0009] S5: fixedly installing a staircase upper formwork on the upper side of the rectangular frame structure, and fixedly installing a staircase lower formwork on the lower side of the rectangular frame structure, so that the staircase upper formwork, the staircase lower formwork, and the rectangular frame structure form a staircase pouring box;
[0010] S6: arranging a plurality of staircase pouring boxes side by side along the horizontal extension direction of the inclined wall stop plate, and fixedly assembling the front stop plate and the rear connecting plate on adjacent staircase pouring boxes, and inserting the main connecting steel bars through the reserved holes to form the state in S2;
[0011] S7: A connecting slot is arranged at the joint of the back connecting plate and the upper template of the stair, and the connecting slot and the stair pouring box form a stair pouring cavity,
[0012] S8: The concrete mortar is poured into the grouting hole on the upper end of the side wall baffle and the upper template of the stair, and the concrete mortar fully fills the stair pouring cavity and the side wall pouring space, and forms the pouring stair and the pouring wall respectively.
[0013] By adopting the above technical scheme, the side wall and the stair can be poured at the same time in one pouring operation, and the side wall and the stair are integrally formed after pouring, so that the side wall and the stair do not need to be constructed separately, and the construction efficiency is greatly improved.
[0014] The application further provides that: the reserved holes are arranged on the side baffle, and the reserved holes are arranged at equal intervals along the extension direction of the side baffle.
[0015] By adopting the above technical scheme, the main connecting steel bar is arranged in alignment with the reserved hole when inserted into the side wall baffle, the rectangular frame structure is hoisted and connected with the main connecting steel bar after the rectangular frame structure is hoisted and connected with the main connecting steel bar, and the main connecting steel bar provides support for the rectangular frame structure, thereby facilitating the installation of the frame structure and reducing the installation difficulty in the construction process.
[0016] The application further provides that: the grouting hole is arranged at the upper end of the upper template of the stair in the installed position, and two grouting holes are arranged, and the two grouting holes are respectively located on the two sides of the extension direction of the upper template of the stair towards the side wall baffle.
[0017] By adopting the above technical scheme, when the concrete mortar is poured, it is poured through one grouting hole, and when the concrete in the stair pouring cavity is full, the excess concrete mortar will overflow from the other grouting hole, at which time it can be considered that the stair pouring cavity is full and pouring is stopped, and the air in the stair pouring cavity can overflow through the grouting hole during pouring, achieving the purpose of exhausting air and reducing the phenomenon of cavities after pouring concrete mortar in the stair pouring cavity.
[0018] The application further provides that: an observation channel is arranged at the horizontal plane outside the upper template of the stair and is communicated with the stair pouring cavity, and a transparent observation plate is detachably and fixedly installed on the observation channel.
[0019] By adopting the above technical scheme, the grouting condition in the stair pouring cavity can be directly observed through the transparent observation plate, and since the inside of the upper template of the stair is arranged in a stair shape, cavities may be generated at the right angles of the stair shape inside the upper template of the stair during grouting, at which time the transparent observation plate can be used to observe whether cavities are generated, and if many cavities are generated, the transparent observation plate is removed after grouting is completed, and then the cavities are manually filled, which is beneficial to improve the pouring quality of the stair.
[0020] The present application is further provided that a connecting slot is formed on the rear connecting plate, the inner profile of the connecting slot is matched with the outer profile of the end of the front baffle away from the stepped formwork, and the front baffle is fixed with the rear connecting plate after being connected with the connecting slot.
[0021] By adopting the above technical scheme, the rear connecting plate and the front baffle are fixed by connecting the front baffle with the connecting slot, thereby limiting the relative movement of the rear connecting plate and the front baffle in the horizontal direction, and ensuring that the front baffle will not move upward under the restriction of gravity and the main connecting steel bar, thereby improving the stability of the multiple stair pouring box after splicing, and when the error after splicing of the two stair pouring boxes is too large or other special conditions occur, the stair pouring box can be quickly disassembled by being vertically lifted before the main connecting steel bar is inserted into the reserved hole, thereby improving the convenience of construction.
[0022] The present application is further provided that a reserved insertion slot is formed on the rear baffle, the opening of the reserved insertion slot faces the stair pouring cavity, a reinforcing steel bar is inserted into the reserved insertion slot, and the other end of the reinforcing steel bar extends into the front baffle and is fixedly connected with the front baffle.
[0023] By adopting the above technical scheme, the reinforcing steel bar can improve the connection strength between the rear baffle and the poured stair and between the front baffle and the poured stair after the concrete mortar is poured and solidified, thereby greatly strengthening the load-bearing capacity of the completed stair.
[0024] The present application is further provided that a second supporting plate is detachably fixed below the rear baffle, and a first supporting plate is detachably fixed below the rear connecting plate.
[0025] By adopting the above technical scheme, the second supporting plate is fixed below the rear baffle and the first supporting plate is fixed below the rear connecting plate, which can provide the stair pouring box with pressure resistance, thereby improving the stability of the stair pouring box during the installation and construction process of the stair pouring box and the concrete mortar pouring process.
[0026] The present application is further provided that a fence is fixedly installed on the upper surface of the side baffle close to the side of the inclined wall baffle.
[0027] By adopting the above technical scheme, the fence can be directly installed on the side baffle without damaging the poured stair during installation, thereby ensuring the structural integrity of the poured stair and improving the structural strength of the poured stair during use.
[0028] The beneficial effects of the present application are:
[0029] 1. The inclined wall and the stair can be poured simultaneously in one pouring operation, and the inclined wall and the stair are integrally formed after pouring, thereby eliminating the need for separate construction of the inclined wall and the stair, and greatly improving the construction efficiency.
[0030] 2. By setting pre-reserved holes at equal intervals, the main connecting steel bars are aligned with the pre-reserved holes when inserted into the inclined wall baffle. After the rectangular frame structure is hoisted and connected to the main connecting steel bars, the main connecting steel bars provide support for the rectangular frame structure, which facilitates the installation of the frame structure and reduces the installation difficulty during construction.
[0031] 3. The transparent observation board allows direct observation of the grouting process inside the staircase pouring cavity. Since the inner side of the upper formwork of the staircase is stepped, voids may be generated at the right angles of the stepped formwork during the grouting process. The transparent observation board can be used to check whether voids have been generated. If there are many voids, the transparent observation board can be removed after the grouting is completed, and the voids can be manually filled, which helps to improve the pouring quality of the staircase. Attached Figure Description
[0032] Figure 1 This is a structural schematic diagram of the staircase casting box and inclined wall baffle of the present invention in the installation position;
[0033] Figure 2 This is a schematic diagram of the structure of the staircase casting box after installation according to the present invention;
[0034] Figure 3 This is a cross-sectional view of the structure of the present invention;
[0035] Figure 4 This is a schematic diagram of the structure of the present invention after casting is completed and supported by the first and second support plates;
[0036] Figure 5 This is a schematic diagram of the structure of the present invention after casting without the use of the first and second support plates.
[0037] In the diagram: 10. Side baffle; 11. Front baffle; 12. Upper formwork of the staircase; 13. Rear connecting plate; 14. Rear baffle; 15. Connecting slot; 16. Lower formwork of the staircase; 20. Grouting hole; 21. Reserved hole; 22. Transparent observation plate; 23. First support plate; 24. Second support plate; 30. Sloping wall baffle; 31. Main connecting reinforcement; 32. Reserved slot; 33. Reinforcing reinforcement; 40. Staircase pouring cavity; 41. Pouring wall; 42. Pouring staircase. Detailed Implementation
[0038] To facilitate a clear understanding of the technical means, creative features, objectives, and effects of this invention, the invention will be further described below in conjunction with specific illustrations.
[0039] like Figures 1-5 As shown, the integrated cast-in-place construction equipment for the inclined wall and stairs includes several staircase casting boxes and inclined wall baffles 30.
[0040] The inclined wall and the stairs are integrally casted by the construction method, and the construction method comprises
[0041] Firstly, the inclined wall baffle 30 is erected side by side at the inclined wall construction position, the end of the inclined wall baffle 30 is inserted into the ground and fixedly connected with the ground, the two inclined wall baffles 30 are shielded in the horizontal direction by the baffles, and the space between the two inclined wall baffles 30 is the inclined wall casting space, wherein the side inclined wall baffle 30 of the construction stairs is provided with a prefabricated concrete wall plate. Then, when the first stair casting box is installed, a plurality of main connecting steel bars 31 are inserted horizontally into the inclined wall baffle 30, the main connecting steel bars 31 are prefabricated on the inclined wall baffle 30 when the prefabricated concrete wall is used, the main connecting steel bars 31 are rigidly fixedly connected with the inclined wall baffle 30, one end of the main connecting steel bars 31 extends to the inclined wall casting space, and the other end of the main connecting steel bars 31 extends away from the inclined wall baffle 30 and is used for cooperating with the stair casting box.
[0042] The installation process of the stair casting box is as follows: firstly, the two side baffles 10 are arranged side by side, the front baffle 11 is fixedly installed at one end of the two side baffles 10 by bolts or screws, and the rear connecting plate 13 is fixedly installed at the other end of the two side baffles 10 by bolts or screws, so that the two side baffles 10, the front baffle 11 and the rear connecting plate 13 form a rectangular frame structure. Then, the reserved holes 21 on the two side baffles 10 of the rectangular frame structure are aligned with the end of the main connecting steel bars 31, the reserved holes 21 are arranged on the side baffles 10, and the reserved holes 21 are arranged at equal intervals along the extension direction of the side baffles 10. The side baffles 10 are installed through the end of the main connecting steel bars 31 away from the inclined wall baffle 30, so that the side baffles 10 abut against the inclined wall baffle 30. Then, the stair upper formwork 12 is fixedly installed on the upper side of the rectangular frame structure, the stair upper formwork 12 is arranged on the side baffles 10, the side baffles 10 and the stair upper formwork 12 are fixedly connected by bolts or screws, and the stair lower formwork 16 is fixedly installed on the lower side of the rectangular frame structure, the stair lower formwork 16 abuts against the lower end of the side baffles 10, and the stair lower formwork 16 and the side baffles 10 are fixedly connected by bolts or screws, so that the stair upper formwork 12, the stair lower formwork 16 and the rectangular frame structure form the stair casting box.
[0043] In the installation of the second stair pouring box, the two stair pouring boxes are spliced, a plurality of stair pouring boxes are arranged side by side along the horizontal extension direction of the inclined wall baffle 30, and the front baffle 11 and the rear connecting plate 13 on the adjacent stair pouring boxes are assembled and fixed. The rear connecting plate 13 is provided with a connecting clamping groove 15, the inner contour of the connecting clamping groove 15 is matched with the outer contour of the end of the front baffle 11 away from the stair upper formwork 12, and the front baffle 11 and the rear connecting plate 13 are fixed after the mortise and tenon connection of the front baffle 11 and the connecting clamping groove 15. After assembly, the main connecting steel bars 31 are inserted into the inclined wall baffle 30. When the inclined wall baffle 30 is a prefabricated concrete wall plate, the main connecting steel bars 31 are inserted into the through holes reserved in the inclined wall baffle 30, and then the connection state of the stair pouring box in S2 and the main connecting steel bars 31 is formed. The connecting clamping groove 15 provided with the connecting clamping groove 15 is inserted into the connecting part of the rear connecting plate 13 and the stair upper formwork 12, the connecting clamping groove 15 and the stair pouring box form a stair pouring cavity 40, and the splicing joint is sealed by sealing material, so that the stair pouring cavity 40 remains in a closed state.
[0044] Finally, the concrete mortar is poured into the grouting holes 20 on the upper end of the inclined wall baffle 30 and the stair upper formwork 12. The grouting holes 20 are arranged at the upper end of the stair upper formwork 12 in the installed position, and two grouting holes 20 are arranged on both sides of the stair upper formwork 12 in the extension direction of the inclined wall baffle 30. The concrete mortar fully fills the stair pouring cavity 40 and the inclined wall pouring space, and forms a poured stair 42 and a poured wall 41 respectively.
[0045] After pouring, the bolts or screws for fixedly connecting the stair upper formwork 12 and the stair lower formwork 16 with the side baffle 10 are disassembled, and then the side baffle 10 is disconnected from the stair upper formwork 12 and the stair lower formwork 16 by using a hard object such as a crowbar, so that the stair upper formwork 12 and the stair lower formwork 16 are disassembled, and the inclined wall baffle 30 away from the side baffle 10 is also disassembled. At this time, the poured wall 41 can be used independently.
[0046] The joint between the connecting clamping groove 15 and the front baffle 11 is filled with grouting mortar or adhesive to further improve the structural strength of the joint. After the stair upper formwork 12 and the stair lower formwork 16 are disassembled, the length of the end of the front baffle 11 and the rear connecting plate 13 away from the inclined wall baffle 30 is greater than that of the poured stair 42. At this time, a falling prevention net can be fixed between the front baffle 11 and the rear connecting plate 13 by using fasteners such as bolts and screws or welding, so as to avoid falling from the side away from the poured wall 41 when a person walks on the poured stair 42.
[0047] The observation passage is communicated with the stair pouring cavity 40 and is provided with a transparent observation plate 22. The pouring condition in the stair pouring cavity 40 can be directly observed through the transparent observation plate 22. Since the inner side of the stair upper formwork 12 is arranged in a stair shape, cavities are likely to be formed at the inner side of the stair upper formwork 12 in a stair shape during the pouring process. At this time, the transparent observation plate 22 can be used to observe whether cavities are formed. If cavities are formed, the transparent observation plate 22 is removed after the pouring is completed, and the cavities are manually filled, which is beneficial to improving the pouring quality of the stair.
[0048] The rear baffle 14 is provided with a reserved slot 32 with an opening facing the stair pouring cavity 40. A reinforcing steel bar 33 is inserted into the reserved slot 32. The other end of the reinforcing steel bar 33 extends through the stair pouring cavity 40 and is fixedly connected with the front baffle 11. The second support plate 24 is fixedly arranged below the rear baffle 14, and the first support plate 23 is fixedly arranged below the rear connecting plate 13. The second support plate 24 fixed below the rear baffle 14 and the first support plate 23 fixed below the rear connecting plate 13 can provide pressure resistance for the stair pouring box, thereby improving the stability of the stair pouring box during the installation and construction process of the stair pouring box and the pouring process of the concrete mortar. After the concrete mortar is poured and solidified, the reinforcing steel bar 33 can improve the connection strength between the rear baffle 14 and the poured stair 42 and between the front baffle 11 and the poured stair 42, thereby greatly improving the load-bearing capacity of the completed stair.
[0049] After the inclined wall and the stair are poured and dried, a fence is fixedly arranged on the upper surface of the side baffle 10 near the inclined wall baffle 30 to protect the poured wall. The fence can be directly installed on the side baffle 10 without damaging the poured stair 42, thereby ensuring the structural integrity of the poured stair 42 and improving the structural strength of the poured stair 42 during use.
[0050] The inclined wall and the stair can be simultaneously poured in one pouring operation, and the inclined wall and the stair are integrally formed after the pouring is completed, thereby eliminating the need for separate construction of the inclined wall and the stair and greatly improving the construction efficiency. The reserved holes 21 are arranged at equal intervals, the main connecting steel bar 31 is arranged in alignment with the reserved holes 21 when the main connecting steel bar 31 is inserted into the inclined wall baffle 30, the rectangular frame structure is hoisted and inserted into the main connecting steel bar 31, and the main connecting steel bar 31 provides support for the rectangular frame structure, thereby facilitating the installation of the frame structure and reducing the installation difficulty during the construction process.
[0051] When the concrete mortar is injected, the injection is through one grouting hole 20, when the concrete in the stair pouring cavity 40 is full, the excess concrete mortar will overflow from another grouting hole 20, at this time, it can be considered that the stair pouring cavity 40 is full and the injection is stopped, and the air in the stair pouring cavity 40 can overflow through the grouting hole 20 during the injection, the purpose of exhausting is achieved, and the phenomenon of cavity after the concrete mortar is injected in the stair pouring cavity 40 is reduced.
[0052] The front baffle 11 is connected with the connecting clamping groove 15 through the mortise and tenon connection, and then the rear connecting plate 13 and the front baffle 11 are fixed, so that the relative movement of the rear connecting plate 13 and the front baffle 11 in the horizontal direction is limited, and under the restriction of gravity and the main connecting steel bars 31, it is ensured that the front baffle 11 will not move upward, thereby the stability of the multiple stair pouring box bodies after splicing is improved, and when the error after splicing of two stair pouring box bodies is too large or other special conditions occur, the stair pouring box bodies can also be vertically lifted for quick disassembly before the main connecting steel bars 31 are inserted into the reserved holes 21, and the convenience of construction is improved.
[0053] The basic principle, main features and advantages of the present application are shown and described above. It should be understood by those skilled in the art that the present application is not limited by the above embodiments, and various changes and improvements can be made without departing from the spirit and scope of the present application, and these changes and improvements all fall within the scope of the present application. The scope of protection of the present application is defined by the appended claims and their equivalents.
Claims
1. A method for integral cast-in-place construction of sloping walls and stairs, characterized by: The construction method includes S1: Build inclined wall baffles (30) side by side at the construction site of the inclined wall, and the space between the two inclined wall baffles (30) is the inclined wall pouring space; S2: Several main connecting steel bars (31) are horizontally inserted into the inclined wall baffle (30). The main connecting steel bars (31) are rigidly fixed to the inclined wall baffle (30). One end of the main connecting steel bar (31) extends to the inclined wall pouring space, and the other end of the main connecting steel bar (31) extends away from the inclined wall baffle (30). S3: Two side panels (10) are arranged side by side. A front baffle (11) is fixedly installed at one end of the two side panels (10), and a rear connecting plate (13) is fixedly installed at the other end of the two side panels (10), so that the two side panels (10), the front baffle (11), and the rear connecting plate (13) form a rectangular frame structure. S4: Align the reserved holes (21) on the two side baffles (10) of the rectangular frame structure with the ends of the main connecting steel bars (31), so that the side baffles (10) are inserted through the end of the main connecting steel bars (31) away from the inclined wall baffles (30), so that the side baffles (10) and the inclined wall baffles (30) abut against each other. S5: Install the upper formwork (12) of the steps on the upper side of the rectangular frame structure, and at the same time install the lower formwork (16) of the steps on the lower side of the rectangular frame structure. The upper formwork (12), the lower formwork (16) of the steps and the rectangular frame structure form a staircase casting box. S6: Several stair casting boxes are arranged side by side along the horizontal extension direction of the inclined wall baffle (30), and the front baffle (11) and rear connecting plate (13) on the adjacent stair casting boxes are assembled and fixed. After assembly, the main connecting steel bar (31) is inserted through the reserved hole (21) so that the main connecting steel bar (31) forms the state in S2. S7: A connecting slot (15) is inserted at the connection between the rear connecting plate (13) and the upper template (12) of the staircase. The connecting slot (15) and the staircase casting box are closed to form a staircase casting cavity (40). S8: Concrete mortar is introduced into the opening at the top of the parallel inclined wall baffle (30) and the grouting hole (20) on the template (12) of the step, and the concrete mortar fully fills the stair pouring cavity (40) and the inclined wall pouring space and forms the pouring staircase (42) and the pouring wall (41) respectively.
2. The method for integral cast-in-place construction of inclined wall and staircase according to claim 1, characterized in that: The reserved holes (21) are opened on the side baffle (10), and the reserved holes (21) are arranged at equal intervals along the extension direction of the side baffle (10).
3. The method for integral cast-in-place construction of inclined wall and staircase according to claim 1, characterized in that: Grouting holes (20) are opened at the upper end of the upper formwork (12) of the step, where the formwork is installed. There are two grouting holes (20), which are located on both sides of the upper formwork (12) of the step, extending towards the inclined wall baffle (30).
4. The method for integral cast-in-place construction of inclined wall and staircase according to claim 1, characterized in that: An observation channel communicating with the stair pouring cavity (40) is provided on the horizontal surface outside the template (12) of the staircase. A transparent observation plate (22) is detachably and fixedly installed on the observation channel.
5. The method for integral cast-in-place construction of inclined wall and staircase according to claim 1, characterized in that: A connecting slot (15) is provided on the rear connecting plate (13). The inner contour of the connecting slot (15) matches the outer contour of the end of the front baffle (11) away from the upper template (12) of the step. After the front baffle (11) and the connecting slot (15) are mortised and tenoned, the front baffle (11) and the rear connecting plate (13) are fixed.
6. The method for integral cast-in-place construction of inclined wall and staircase according to claim 1, characterized in that: A fence is fixedly installed on the upper surface of the side panel (10) near the inclined wall panel (30).
Citation Information
Patent Citations
A steel stair template for building stairwell is once pour shapingly
CN204626965U
Precast concrete stair
CN208533893U