A ground stress testing device and method for hard rock roadway and tunnel
By using a combination of cracking components and test modules in ground stress testing equipment, high-precision measurement of ground stress in tunnels and tunnels is achieved, solving the problems of low measurement accuracy and harsh conditions in the existing technology, simplifying operations and Reduced requirements for surrounding rock integrity.
Patent Information
- Application Number
- CN202311505581.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-13
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2043-11-13
AI Technical Summary
Existing in-situ stress testing technology has shortcomings in measurement accuracy and harsh conditions, especially in hard rock roadways and tunnels. It is difficult for existing equipment to measure in-situ stress with high precision and requires high integrity of the surrounding rock.
The cracking component is used to prop up the hole, and the pointing plate is observed through the camera and level in the test module. Combined with the extrusion force generated by the cracking component, the ground stress data is calculated to achieve high-precision measurement.
This equipment can measure the in-situ stress data of roadways and tunnels with high precision, is simple to operate, has lower requirements on the integrity of surrounding rocks, and improves measurement accuracy and flexibility.
Smart Images

Figure CN117347180B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of geostress testing, and in particular to a geostress testing device and method for hard rock lanes and tunnels. Background Art
[0002] Geostress is the stress existing in the earth's crust. It is the force per unit area inside the medium caused by rock deformation. It generally consists of two parts: (1) stress caused by the weight of the covering rock, which is caused by gravity and the centrifugal force of the earth's rotation inertia; (2) tectonic stress transmitted from adjacent blocks or the bottom. This stress refers to the part that is different from the standard state. In addition to the modern tectonic stress transmitted from the adjacent blocks or the bottom, it also includes the residual stress left over from past tectonic movements that has not yet been completely relaxed, as well as stress changes caused by nearby man-made projects (such as tunnels and mining surfaces). Tectonic stress directly reflects the power source of crustal movement and is an important factor in causing earthquakes. When digging tunnels in areas with strong tectonic stress, the walls of the tunnels become free surfaces and are easily deformed, causing the tunnels to gradually shrink or collapse. Therefore, it is of great significance to study geostress.
[0003] Geostress is the fundamental cause of roadway and tunnel damage. At present, the direction and support design of roadways and tunnels are gradually becoming modernized and digitalized, which puts forward further requirements on the accuracy of geostress data. Existing geostress testing technologies mainly include indirect measurement method and direct measurement method. Among them, the indirect measurement method includes stress relief method, aperture deformation method, hole wall strain method and hollow inclusion method. The core of the indirect measurement method is to destroy the connection between the core and the original rock mass, relieve the stress of the core; measure the elastic recovery deformation of the core; and calculate the original geostress size according to the generalized Hooke's law. The indirect measurement method has the advantages of high measurement accuracy and mature theory, but cracks often appear in the hole wall, resulting in damage to the bonding performance of the strain gauge and the core, affecting the test results. In order to overcome the shortcomings of poor bonding performance of strain gauges, direct measurement method for geostress measurement technology came into being, and derived flat jack method, rigid inclusion stress gauge method, hydraulic fracturing method and acoustic emission method. The direct measurement method is suitable for relatively complete brittle rock mass and has the advantage of economical measurement of deep stress. However, hydraulic fracturing can only measure the maximum and minimum principal stresses in the vertical drilling plane, which is essentially a two-dimensional stress measurement method; and for rocks with pore distribution, liquid is prone to leakage, which directly affects the test accuracy. In summary, the existing ground stress test equipment has low test accuracy and harsh test conditions. Summary of the invention
[0004] In view of the above problems, the purpose of the present invention is to provide a geostress testing device for hard rock lanes and tunnels, in which a fracturing component is provided to prop up a hole, and when the camera in the test module observes the pointing plate pointing to the crack, the relevant angle data of the level meter is combined with the extrusion pressure generated by the fracturing component to calculate the geostress data. The device can measure the relevant data of lanes and tunnels with high precision, is simple to operate, and has low requirements on the integrity of the surrounding rock.
[0005] The technical solution adopted by the present invention is as follows:
[0006] A ground stress testing device for hard rock lanes and tunnels, comprising a fracturing assembly for expanding outward and cracking holes, a testing module being arranged on one side of the fracturing assembly, the testing module comprising a mounting plate and a driving mechanism for driving the mounting plate to rotate around the axis of the fracturing assembly, a camera, a level and a pointing plate being mounted on the mounting plate, and the length direction of the pointing plate being perpendicular to the axis direction of the fracturing assembly.
[0007] Preferably, at least two fracturing assemblies are provided, and the test module is located between the two fracturing assemblies.
[0008] Preferably, the fracturing assembly comprises a hydraulic cylinder, the hydraulic cylinder is connected to a plurality of hydraulic telescopic rods arranged along the circumference of the hydraulic cylinder, and the top ends of the hydraulic telescopic rods are connected to arc-shaped top plates.
[0009] Preferably, the axis of the hydraulic cylinder is connected with a connecting pipe, a valve is provided in the connecting pipe, and the connecting pipe is connected to a high-pressure oil pump.
[0010] Preferably, the connecting pipe is connected to a pressure gauge.
[0011] Preferably, the driving mechanism comprises a fixing ring sleeved on the connecting pipe, the fixing ring is provided with a slide groove along the circumferential direction, and a slide rail motor connected to the mounting plate is arranged in the slide groove.
[0012] Preferably, the fixing ring is elastic, and is provided with a notch for disconnecting the fixing ring. Both ends of the fixing ring are connected with connecting plates protruding from the fixing ring. A screw rod movably penetrates the connecting plate, and a nut is threadedly sleeved on the screw rod.
[0013] A method for testing ground stress of hard rock tunnels and tunnels, using the ground stress testing device to perform the test, the testing method comprising the following steps:
[0014] S1: Drill hole No. 1, select a suitable test location, use a drilling rig to drill holes, and the hole depth should not be less than 3 times the tunnel section to eliminate the influence of tunnel stress concentration on the ground stress test;
[0015] S2: Equipment assembly: assemble the ground stress test equipment in the order of fracturing assembly, test module, fracturing assembly, pressure gauge and high-pressure oil pump, and push the test equipment into the hole using a drilling rig;
[0016] S3: Pressurize, turn on the high-pressure oil pump and pressure gauge, open the valve to release the high-pressure oil, and the high-pressure oil enters the hydraulic cylinder through the connecting pipe, so that the hydraulic telescopic rod drives the arc-shaped top plate to extend outward, and continue to pressurize until the pressure change of the hydraulic oil tends to be smooth. Record the hydraulic oil pressure value of the whole process. The calculation formula of the maximum principal stress and the minimum principal stress of the plane is:
[0017]
[0018] Among them, P min is the minimum principal stress, MPa; P max is the maximum principal stress, P r is the peak stress in the stable stage, MPa; P b is the first peak stress, MPa; T is the rock tensile strength, MPa;
[0019] S4: Unload the pressure, turn off the high-pressure oil pump, and recycle the hydraulic oil in the equipment into the high-pressure oil pump. When the value in the pressure gauge is close to 0, close the valve and the pressure gauge;
[0020] S5: Leveling, control the test module, adjust the slide motor to make the level meter in the camera observation level, and record the angle γ 1 ;
[0021] S6: Measure the cracking angle, adjust the slide motor so that the pointing plate in the camera observation points to the crack, and record the angle γ 2 , the crack angle formula is:
[0022] γ=γ 2 -γ 1
[0023] S7: dismantle the equipment and use a drilling rig to pull out the entire equipment. The ground stress test process of hole 1 is completed;
[0024] S8: Calculate the plane stress of the hole. Take the hole axis direction as the x direction and use the right-hand rule to establish the coordinate system xyz. The calculation formula for the stress is:
[0025]
[0026] Among them, σ is the normal stress, MPa, τ is the shear stress, MPa;
[0027] S9: Change the vertical inclination angle α of the drilling rig and perform drilling operation of hole No. 2 at the test point;
[0028] Repeat steps S2 to S7 to obtain the stress calculation formula for hole No. 2:
[0029]
[0030] S10: changing the horizontal rotation angle β of the drilling machine, and performing the drilling operation of the No. 3 hole at the test point;
[0031] Repeat steps S2 to S7 to obtain the stress calculation formula for hole 3:
[0032]
[0033] S11: Integrating the above formulas, we can get all the stress components.
[0034] In summary, due to the adoption of the above technical solution, the beneficial effects of the present invention are:
[0035] A crack hole is formed by setting a fracturing component. When the camera in the test module observes the pointing plate pointing to the crack, the relevant angle data of the level meter is combined with the extrusion pressure generated by the fracturing component to calculate the ground stress data. This equipment can measure the relevant data of lanes and tunnels with high precision, is easy to operate, and has low requirements on the integrity of the surrounding rock. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings required for use in the embodiments are briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.
[0037] Figure 1 A schematic diagram of the overall structure provided for an embodiment of the present invention;
[0038] Figure 2 A schematic diagram of the structure of a fracturing assembly provided in an embodiment of the present invention;
[0039] Figure 3 A schematic diagram of the test module structure provided in an embodiment of the present invention;
[0040] Figure 4 A schematic top view of a test module provided in an embodiment of the present invention.
[0041] Description of the drawings: 1-fracture assembly; 11-hydraulic cylinder; 12-hydraulic telescopic rod; 13-arc top plate; 2-connecting pipe; 3-test module; 31-fixing ring; 32-slide groove; 33-nut; 34-connecting plate; 35-slide motor; 36-level; 37-mounting plate; 38-camera; 39-screw; 310-pointing plate; 4-pressure gauge; 5-valve; 6-high-pressure oil pump. DETAILED DESCRIPTION
[0042] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.
[0043] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0044] In the description of the present invention, it should be noted that if the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside" and the like appear, the orientation or position relationship indicated is based on the orientation or position relationship shown in the accompanying drawings, or is the orientation or position relationship in which the product of the application is usually placed when used. It is only for the convenience of describing the present invention and simplifying the description, and does not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0045] Combine the following Figure 1-Figure 4 The present invention is described in detail.
[0046] Example
[0047] A geostress testing device for hard rock roadways and tunnels, such as Figure 1 , 3 As shown in FIG. 4 , the fracturing assembly 1 includes a fracturing assembly 1 for expanding outward and cracking a hole. A test module 3 is provided on one side of the fracturing assembly 1. The test module 3 includes a mounting plate 37 and a driving mechanism for driving the mounting plate 37 to rotate around the axis of the fracturing assembly 1. A camera 38, a level 36 and a pointing plate 310 are installed on the mounting plate 37, and the length direction of the pointing plate 310 is perpendicular to the axis direction of the fracturing assembly 1.
[0048] The camera 38 is a wide-angle camera that can view the level 36 and the pointing board 310 at the same time.
[0049] At least two fracture-inducing assemblies 1 are provided, and the test module 3 is located between the two fracture-inducing assemblies 1, so that the camera 38 of the test module 3 can observe the crack clearly, which facilitates the pointing plate 310 to point to the crack.
[0050] like Figure 2 As shown, the fracturing assembly 1 includes a hydraulic cylinder 11, which is connected to a plurality of hydraulic telescopic rods 12 arranged circumferentially along the hydraulic cylinder 11, and the top of the hydraulic telescopic rods 12 is connected to an arc-shaped top plate 13. Hydraulic oil enters the hydraulic telescopic rods 12 from the hydraulic cylinder 11, so that the hydraulic telescopic rods 12 extend and push the arc-shaped top plate 13 to expand outward, thereby generating cracks in the top crack hole.
[0051] The axis of the hydraulic cylinder 11 is connected with a connecting pipe 2, a valve 5 is arranged in the connecting pipe 2, and the connecting pipe 2 is connected with a high-pressure oil pump 6. The fracturing assembly 1, the connecting pipe 2 and the high-pressure oil pump 6 are located on the same axis, and the drilling rig can be used to push the device, eliminating the manual pushing operation.
[0052] The connecting pipe 2 is connected with a pressure gauge 4. The pressure gauge 4 monitors the pressure of the hydraulic oil in the connecting pipe 2, so that the extrusion force generated by the fracturing assembly can be obtained.
[0053] The driving mechanism includes a fixing ring 31 sleeved on the connecting pipe 2, the fixing ring 31 is provided with a slide groove 32 along the circumferential direction, and a slide rail motor 35 connected to the mounting plate 37 is arranged in the slide groove 32. The slide rail motor 35 can move along the slide groove 32, thereby driving the mounting plate 37 to rotate around the axis of the fracturing assembly 1.
[0054] The fixing ring 31 is elastic and has a notch for disconnecting the fixing ring 31. The fixing ring 31 is connected to the head and tail ends of the fixing ring 31 with connecting plates 34 protruding from the fixing ring 31. The connecting plate 34 is movably penetrated by a screw 39, and a nut 33 is threadedly sleeved on the screw 39. The fixing ring 31 is fixed to the connecting pipe 2 by the screw 39 and the nut 33. When necessary, the fixing ring 31 can be disassembled and related parts can be replaced. The mounting plate 37 is also provided with a battery (not shown in the figure), which provides power to the slide motor 35 and the camera 38.
[0055] A method for testing ground stress of hard rock tunnels and tunnels, using the ground stress testing device to perform the test, the testing method comprising the following steps:
[0056] S1: Drill hole No. 1, select a suitable test location, use a drilling rig to drill holes, and the hole depth should not be less than 3 times the tunnel section to eliminate the influence of tunnel stress concentration on the ground stress test;
[0057] S2: Equipment assembly: assemble the ground stress test equipment in the order of the fracturing component 1, the test module 3, the fracturing component 1, the pressure gauge 4 and the high-pressure oil pump 6, and push the test equipment into the hole using a drilling rig;
[0058] S3: Pressurize, turn on the high-pressure oil pump 6 and the pressure gauge 4, open the valve 5 to release the high-pressure oil, and the high-pressure oil enters the hydraulic cylinder 11 through the connecting pipe 2, so that the hydraulic telescopic rod 12 drives the arc-shaped top plate 13 to extend outward, and continue to pressurize until the pressure change law of the hydraulic oil tends to be smooth, and record the hydraulic oil pressure value of the whole process. The calculation formula of the maximum principal stress and the minimum principal stress of the plane is:
[0059]
[0060] Among them, P min is the minimum principal stress, MPa; P max is the maximum principal stress, P r is the peak stress in the stable stage, MPa; P b is the first peak stress, MPa; T is the rock tensile strength, MPa;
[0061] S4: depressurize, close the high-pressure oil pump 6, recover the hydraulic oil in the equipment into the high-pressure oil pump 6, and close the valve 5 and the pressure gauge 4 when the value in the pressure gauge is close to 0;
[0062] S5: Leveling, control the test module 3, adjust the slide motor 35, make the level 36 observed by the camera 38 level, and record the angle γ 1 ;
[0063] S6: Measure the cracking angle, adjust the slide motor 35 so that the pointing plate 310 in the camera 38 points to the crack, and record the angle γ 2 , the crack angle formula is:
[0064] γ=γ 2 -γ 1
[0065] S7: dismantle the equipment and use a drilling rig to pull out the entire equipment. The ground stress test process of hole 1 is completed;
[0066] S8: Calculate the plane stress of the hole. Take the hole axis direction as the x direction and use the right-hand rule to establish the coordinate system xyz. The calculation formula for the stress is:
[0067]
[0068] Among them, σ is the normal stress, MPa, τ is the shear stress, MPa;
[0069] S9: Change the vertical inclination angle α of the drilling rig and perform drilling operation of hole No. 2 at the test point;
[0070] Repeat steps S2 to S7 to obtain the stress calculation formula for hole No. 2:
[0071]
[0072] S10: changing the horizontal rotation angle β of the drilling machine, and performing the drilling operation of the No. 3 hole at the test point;
[0073] Repeat steps S2 to S7 to obtain the stress calculation formula for hole 3:
[0074]
[0075] S11: Integrating the above formulas, we can get all the stress components.
[0076] The above are only preferred embodiments of the present invention and are not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A ground stress testing device for hard rock roadways and tunnels, characterized in that: The invention comprises a fracturing assembly (1) for expanding outward and cracking a hole, a test module (3) being arranged on one side of the fracturing assembly (1), the test module (3) comprising a mounting plate (37) and a driving mechanism for driving the mounting plate (37) to rotate around the axis of the fracturing assembly (1), the mounting plate (37) being mounted with a camera (38), a level (36) and a pointing plate (310), and the length direction of the pointing plate (310) is perpendicular to the axis direction of the fracturing assembly (1); at least two fracturing assemblies (1) are arranged, and the test module (3) is located between the two fracturing assemblies (1), the fracturing assembly (1) comprising a hydraulic cylinder (11), the axis of the hydraulic cylinder (11) being connected to a connecting pipe (2 ), a valve (5) is arranged in the connecting pipe (2), the connecting pipe (2) is connected to a high-pressure oil pump (6), the driving mechanism comprises a fixing ring (31) sleeved on the connecting pipe (2), the fixing ring (31) is provided with a slide groove (32) along the circumferential direction, a slide rail motor (35) connected to a mounting plate (37) is arranged in the slide groove (32), the fixing ring (31) is elastic, the fixing ring (31) is provided with a notch for disconnecting the fixing ring (31), the fixing ring (31) is connected to connecting plates (34) protruding from the fixing ring (31) at both ends, a screw rod (39) is movably penetrated on the connecting plate (34), and a nut (33) is threadedly sleeved on the screw rod (39).
2. A ground stress testing device for hard rock roadways and tunnels according to claim 1, characterized in that: The hydraulic cylinder (11) is connected to a plurality of hydraulic telescopic rods (12) arranged along the circumference of the hydraulic cylinder (11), and the top ends of the hydraulic telescopic rods (12) are connected to arc-shaped top plates (13).
3. A ground stress testing device for hard rock roadways and tunnels according to claim 1, characterized in that: The connecting pipe (2) is connected to a pressure gauge (4).
4. A method for testing ground stress in hard rock roadways and tunnels, characterized in that: The test is performed using the ground stress testing device according to any one of claims 1 to 3, wherein the test method comprises the following steps: S1: Drill hole No. 1, select a suitable test location, use a drilling rig to drill holes, and the hole depth should not be less than 3 times the tunnel section to eliminate the influence of tunnel stress concentration on the ground stress test; S2: assembling the equipment, assembling the ground stress test equipment in the order of the fracturing component (1), the test module (3), the fracturing component (1), the pressure gauge (4) and the high-pressure oil pump (6), and pushing the test equipment into the hole using a drilling rig; S3: Pressurize, start the high-pressure oil pump (6) and the pressure gauge (4), open the valve (5) to release the high-pressure oil, and the high-pressure oil enters the hydraulic cylinder (11) through the connecting pipe (2), so that the hydraulic telescopic rod (12) drives the arc-shaped top plate (13) to extend outward, and continue to pressurize until the pressure change of the hydraulic oil tends to be smooth. Record the hydraulic oil pressure value throughout the process. The calculation formula of the maximum principal stress and the minimum principal stress of the plane is: Among them, P min is the minimum principal stress, MPa; P max is the maximum principal stress, P r is the peak stress in the stable stage, MPa; P b is the first peak stress, MPa; T is the rock tensile strength, MPa; S4: depressurize, close the high-pressure oil pump (6), recover the hydraulic oil in the equipment into the high-pressure oil pump (6), and close the valve (5) and the pressure gauge (4) when the value in the pressure gauge is close to 0; S5: Leveling, controlling the test module (3), adjusting the slide motor (35), making the level meter (36) observed by the camera (38) level, and recording the angle γ1; S6: Measure the crack angle, adjust the slide rail motor (35), so that the pointing plate (310) in the camera (38) points to the crack, record the angle γ2, and obtain the crack angle formula: γ=γ2-γ1 S7: dismantle the equipment and use a drilling rig to pull out the entire equipment. The ground stress test process of hole 1 is completed; S8: Calculate the plane stress of the hole. Take the hole axis direction as the x direction and use the right-hand rule to establish the coordinate system xyz. The calculation formula for the stress is: Among them, σ is the normal stress, MPa, τ is the shear stress, MPa; S9: Change the vertical inclination angle α of the drilling rig and perform drilling operation of hole No. 2 at the test point; Repeat steps S2 to S7 to obtain the stress calculation formula for hole No. 2: S10: changing the horizontal rotation angle β of the drilling machine, and performing the drilling operation of the No. 3 hole at the test point; Repeat steps S2 to S7 to obtain the stress calculation formula for hole 3: S11: Integrating the above formulas, we can get all the stress components.