Method for synchronous installation of a cross structure and equipment of a converter
By dividing the charging span structure into three installation zones and carrying out simultaneous construction, the problem of extended installation time for the converter charging span and equipment was solved, achieving efficient construction of the converter project.
Patent Information
- Application Number
- CN202311179855.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-09-13
- Publication Date
- 2026-01-13
- Estimated Expiration
- 2043-09-13
AI Technical Summary
The installation sequence of the converter charging structure and equipment leads to extended construction time, is severely limited by construction space, and affects the project installation cycle.
The charging span structure is divided into three installation zones. Installation Zone 1 and Installation Zone 2 are constructed simultaneously. The overhead crane in Installation Zone 1 is used to install the furnace front platform and equipment simultaneously. A temporary placement area is set up on the furnace front platform, and cable corridors and tilting reducers are installed in advance to achieve parallel construction of the charging span and equipment.
By using a synchronous installation method, the installation and commissioning of the converter equipment can be completed ahead of schedule, shortening the installation cycle of the converter project and improving construction efficiency.
Smart Images

Figure CN117418702B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the technical field of converter steelmaking equipment installation, and in particular relates to a method for synchronously installing the converter charging span structure and equipment. Background Technology
[0002] Metallurgical converter steelmaking projects, as complex large-scale metallurgical engineering projects, are characterized by complex three-dimensional structures, high structural installation difficulty, equipment installation within confined spaces, and long construction periods. The converter charging span is located between the converter furnace span and the converter electrical room. Installation work can only proceed along the column line to one side. Structurally, the roof beams and part of the trolley beams of the charging span are installed on the high-rise frame columns of the furnace span. An elevated furnace front platform is located directly in front of the furnace span to connect the furnace span and the converter electrical room. This platform, as the main working platform for converter equipment installation, is crucial, especially the cable corridor installed below it, which is used to lay cables connecting the converter equipment and the electrical cabinets, directly affecting the installation and commissioning of the equipment. Figure 1 As shown, the current installation of the charging span structure and equipment involves constructing the charging span steel structure sequentially from line 1 to line 7 in a front-to-back direction. Only after the charging span steel structure is completed is the furnace platform and equipment installed. This results in a late start time for equipment installation and severe limitations due to construction space constraints, which is the main reason for the long installation cycle in converter projects. Therefore, optimizing the converter process and developing a method for simultaneous installation of the converter charging span structure and equipment to solve the problem of long installation cycles in converter projects is of great significance for promoting project construction and improving construction efficiency. Summary of the Invention
[0003] The main objective of this invention is to propose a method for synchronously installing the converter charging cross structure and equipment, which can effectively solve the problems in the background art.
[0004] To achieve the above objectives, the present invention provides the following technical solution:
[0005] A method for synchronously installing converter charging across the structure and equipment includes the following steps:
[0006] S1, Material feeding across work areas
[0007] The charging span is divided into three sections: installation zone 1, installation zone 2, and installation zone 3, with the converter high-rise frame column as the dividing point. The steel structure and equipment of the charging span are constructed in sections. The area from the converter high-rise frame column to the end of the front column is installation zone 1, the area containing the converter high-rise frame column is installation zone 2, and the area from the converter high-rise frame column to the end of the rear column is installation zone 3.
[0008] S2. Installation of the steel structure and overhead crane in Zone 1.
[0009] S21. From the high-rise frame column of the converter to the end of the front column row, the feeding span column, the crane beam, and the roof beam are constructed in sequence, and the roof purlins are laid and installed on the top between the roof beams. A reserved span is set at the end of the front column row, and the roof purlins are not installed in the reserved span.
[0010] S22. Install the first main beam and the second main beam on the front and rear sides of the reserved mid-span trolley beam respectively, and install end beams at both ends of the first main beam. Then install the first secondary beam between the two end beams. Leave enough hoisting space between the first secondary beam and the second main beam. Then hoist the trolley vertically between the first secondary beam and the second main beam. When the lowest part of the trolley exceeds the top of the first main beam and the second main beam, install the second secondary beam between the two end beams. Then move the first main beam to the second main beam. The two are connected and fixed through the end beams. Finally, lower the trolley to the first main beam and the second main beam.
[0011] S23. Install roof purlins with reserved spans;
[0012] S3. During the installation process in step S2, the installation of the steel structure and equipment in Zone 2 shall be carried out simultaneously.
[0013] S31. Install the charging cross columns and converter high-rise frame columns in the second installation zone. The converter high-rise frame columns are divided into two sections by the elevation of the crane beam rail surface. First, install the lower column of the converter high-rise frame, and then install the upper column of the converter high-rise frame.
[0014] S32. Install trolley beams on the charging cross column and the lower column of the converter high-rise frame respectively, so that the trolley beams of the second installation zone are connected to the trolley beams of the first installation zone, and the trolleys of the first installation zone can run to the second installation zone for subsequent furnace front platform and equipment installation.
[0015] S33. Install the roof beam. One end of the roof beam is connected to the feeding cross column, and the other end is connected to the upper column of the converter high-rise frame.
[0016] S34. Arrange the hoisting machinery in the third installation area, use the hoisting machinery to hoist the fume hood and suspend it at the bottom of the roof beam. After installation, lay the roof purlins on the roof beam. Finally, use the hoisting machinery to hoist the pipe and fix it to the top of the roof beam.
[0017] S4. Installation of steel structure and equipment for furnace front platform
[0018] S41. Install the first and second platform columns on one side of the installation zone 2 by means of overhead crane hoisting operation, and install the third and fourth platform columns on the other side. Install platform beams on the first, second, third and fourth platform columns to form a furnace front platform. At the same time, reserve multiple platform beams between the second and third platform columns near the converter foundation as a temporary placement area for converter equipment.
[0019] S42. The converter equipment is hoisted to the temporary placement area by a crane, and then the converter equipment is pushed to the middle of the furnace span by a trolley for installation. Finally, the platform beam of the temporary placement area is installed.
[0020] S43. Assemble the cable corridor on the ground between the first platform column and the second platform column. After assembly, suspend the cable corridor under the furnace front platform.
[0021] S44. Install temporary supports on the third and fourth platform columns on the side closest to the converter foundation, and set up temporary columns on the converter foundation. Then lay roadbed boxes on the temporary supports and temporary columns, and make the top elevation of the roadbed boxes level with the top elevation of the tilting reducer stop seat on the converter foundation. Finally, place the tilting reducer on the roadbed boxes and push it to the middle of the furnace span to install it on the tilting reducer stop seat.
[0022] S5. While installing the steel structure and equipment on the furnace front platform, complete the installation of the steel structure and overhead crane in the third installation zone according to step S2.
[0023] Preferably, in step S1, the charging span is composed of multiple column structures consisting of two columns, A-axis and B-axis, including lines 1 to 7. Lines 4 to 5 of the B-axis are provided with the converter high-rise frame columns of the furnace span. Therefore, lines 1 to 4 are the first installation zone, lines 4 to 5 are the second installation zone, and lines 5 to 7 are the third installation zone.
[0024] Preferably, in step S21, the reserved span is 1 to 2 lines.
[0025] Preferably, in step S22, the first main beam, the second main beam, the first secondary beam, the second secondary beam, and the trolley beam together form a trolley that can move on the trolley beam for hoisting the steel structure and equipment of the furnace front platform.
[0026] Preferably, in step S31, the feeding cross column is located on axis A, and the converter high-rise frame column is located on axis B.
[0027] Preferably, in step S34, a suspension device is provided at the bottom of the roof beam for installing a smoke hood, and a bracket is provided at the top of the roof beam for installing pipes.
[0028] Preferably, in step S41, the converter foundation has been poured before the construction of the charging span, and a tilting reducer stop seat is installed on the converter foundation.
[0029] Preferably, in step S44, after the converter tilting reducer is installed, the roadbed box, temporary column and temporary support are removed.
[0030] Preferably, in step S5, the three-zone crane is installed on the crane beam of line 6 to line 7 according to the construction method in step S2.
[0031] This invention provides a method for synchronously installing the converter charging structure and equipment, which has the following beneficial effects;
[0032] This invention changes the existing sequential construction of the charging span and equipment to parallel construction. The charging span structure is divided into three installation zones. Installation Zone 1 and Installation Zone 2 are constructed simultaneously. The steel structure and equipment of Installation Zone 2 are installed simultaneously with the steel structure and overhead crane installation in Installation Zone 1. Then, the overhead crane delivered first in Installation Zone 1 is used to install the steel structure and equipment of the furnace front platform. Specifically, a temporary placement area is set up on the furnace front platform for the converter installation in advance. The cable corridor is suspended and installed under the furnace front platform in advance, and the tilting reducer is installed in advance through temporary supports, temporary columns, and roadbed boxes. All construction operations are carried out simultaneously, which can complete the installation and commissioning of the converter equipment as early as possible. Moreover, the steel structure and overhead crane installation of Installation Zone 3 are completed at the same time as the steel structure and equipment installation of the furnace front platform. This invention makes reasonable deployment and interleaving of the construction of the charging span and equipment, which can improve construction efficiency and greatly shorten the installation cycle of the converter project. Attached Figure Description
[0033] Figure 1 This is a schematic diagram of the cross-zone feeding structure of the present invention;
[0034] Figure 2 This is a schematic diagram of the installation structure of the first installation area of the present invention;
[0035] Figure 3 This is a schematic diagram of the installation structure of the second installation zone of the present invention;
[0036] Figure 4 This is a schematic diagram of the installation structure of the furnace front platform and equipment of the present invention.
[0037] In the diagram: 1. Charging span; 2. Furnace span; 3. Installation zone 1; 4. Installation zone 2; 5. Installation zone 3; 6. Charging span column; 7. Crane beam; 8. Roof beam; 9. High-rise frame column; 9.1. Lower column; 9.2. Upper column; 10. Furnace front platform; 10.1. First platform column; 10.2. Second platform column; 10.3. Third platform column; 10.4. Fourth platform column; 10.5. Platform 11. Beams; 11.1. First main beam; 11.2. Second main beam; 11.3. End beams; 11.4. First secondary beam; 11.5. Second secondary beam; 11.6. Main trolley of the crane; 12. Roof purlins; 13. Fume hood; 14. Pipelines; 15. Cable corridor; 16. Converter foundation; 17. Temporary supports; 18. Roadbed box; 19. Tilting reducer stop seat; 20. Lifting machinery. Detailed Implementation
[0038] To make the objectives, technical solutions, and advantages of the present invention clearer, the technical solutions of the present invention will be clearly and completely described below with reference to the accompanying drawings.
[0039] The technical solution of the present invention will be clearly and completely described below with reference to the embodiments. Obviously, the described embodiments are only some embodiments of the present invention, and not all embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative effort are within the scope of protection of the present invention.
[0040] In the description of this invention, it should be understood that the terms "center," "longitudinal," "lateral," "length," "width," "thickness," "upper," "lower," "front," "rear," "left," "right," "vertical," "horizontal," "top," "bottom," "inner," "outer," "clockwise," and "counterclockwise," etc., indicate the orientation or positional relationship based on the orientation or positional relationship shown in the accompanying drawings. They are used only for the convenience of describing this invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, or be constructed and operated in a specific orientation. Therefore, they should not be construed as limiting this invention.
[0041] Furthermore, the terms "first" and "second" are used for descriptive purposes only and should not be construed as indicating or implying relative importance or implicitly specifying the number of indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the stated features. In the description of this invention, "a plurality of" means two or more, unless otherwise explicitly specified. Furthermore, the terms "installed," "connected," and "linked" should be interpreted broadly; for example, they may refer to a fixed connection, a detachable connection, or an integral connection; they may refer to a mechanical connection or an electrical connection; they may refer to a direct connection or an indirect connection through an intermediate medium; and they may refer to the internal connection of two components. Those skilled in the art can understand the specific meaning of the above terms in this invention based on the specific circumstances.
[0042] An embodiment of a method for synchronously installing converter charging structures and equipment includes the following steps:
[0043] S1, For the setting of feeding across work area 1, please refer to... Figure 1
[0044] Using the converter high-rise frame column 9 of furnace span 2 as the dividing point, the charging span 1 is divided into three sections: installation zone 1 3, installation zone 2 4, and installation zone 3 5. The steel structure and equipment of the charging span 1 are constructed in sections. The area from the converter high-rise frame column 9 to the end of the front column is installation zone 1 3, the area containing the converter high-rise frame column 9 is installation zone 2 4, and the area from the converter high-rise frame column 9 to the end of the rear column is installation zone 3 5.
[0045] In this embodiment, the charging span 1 is composed of two columns, A and B, including lines 1 to 7. Lines 4 to 5 of the B axis are provided with the converter high-rise frame columns 9 of the furnace span 2. Therefore, lines 1 to 4 are for installation zone 1 3, lines 4 to 5 are for installation zone 2 4, and lines 5 to 7 are for installation zone 3 5.
[0046] S2, Installation of Zone 1, Steel Structure 3 and Crane 11, please refer to... Figure 1 and Figure 2
[0047] S21. From the high-rise frame column 9 of the converter to the end of the front column, the feeding span column 6, the crane beam 7, and the roof beam 8 are constructed in sequence, and the roof purlins 12 are laid and installed on the top between the roof beams 8. A reserved span is set at the end of the front column. The roof purlins 12 are not installed in the reserved span. The reserved span is line 1 to line 2.
[0048] S22. Install the first main beam 11.1 and the second main beam 11.2 on the front and rear sides of the reserved mid-span gantry beam 7 respectively, and install end beams 11.3 at both ends of the first main beam 11.1. Then install the first secondary beam 11.4 between the two end beams 11.3. Leave sufficient hoisting space between the first secondary beam 11.4 and the second main beam 11.2. Then vertically hoist the gantry crane 11.6 between the first secondary beam 11.4 and the second main beam 11.2. When the lowest part of the gantry crane 11.6 exceeds the top of the first main beam 11.1 and the second main beam 11.2, install the second secondary beam 11.5 between the two end beams 11.3. Then move the first main beam 11.1 toward the second main beam 11.2. The two are connected and fixed through the end beams 11.3. Finally, lower the gantry crane 11.6 to be located on the first main beam 11.1 and the second main beam 11.2.
[0049] The first main beam 11.1, the second main beam 11.2, the end beam 11.3, the first secondary beam 11.4, the second secondary beam 11.5, and the overhead crane 11.6 together form the overhead crane 11, which can move on the overhead crane beam 7 and is used to hoist the steel structure and equipment of the furnace front platform 10.
[0050] S23. Install roof purlins 12 with reserved spans;
[0051] S3. During the installation process in step S2, the installation of the steel structure and equipment in Zone 4 shall be carried out simultaneously. Please refer to... Figure 3
[0052] S31. Install the charging span column 6 and the converter high-rise frame column 9 in Zone 2 4. The converter high-rise frame column 9 is divided into two sections by the rail surface elevation of the traveling beam 7. First, install the lower column 9.1 of the converter high-rise frame, and then install the upper column 9.2 of the converter high-rise frame. The charging span column 6 is located on axis A, and the converter high-rise frame column 9 is located on axis B.
[0053] S32. Install trolley beams 7 on the charging cross column 6 and the lower column 9.1 of the converter high-rise frame respectively, so that the trolley beam 7 of the second installation zone 4 is connected to the trolley beam 7 of the first installation zone 3, and the trolley 11 of the first installation zone 3 can run to the second installation zone 4 to install the subsequent furnace front platform 10 and equipment.
[0054] S33. Install roof beam 8. One end of roof beam 8 is connected to the feeding cross column 6, and the other end is connected to the upper column 9.2 of the converter high-rise frame.
[0055] S34. The hoisting machine 20 is arranged in the installation zone 5. The hoisting machine 20 is used to hoist the fume hood 13 and suspend it at the bottom of the roof beam 8. After installation, the roof purlins 12 are laid on the roof beam 8. Finally, the hoisting machine 20 is used to hoist the pipe 14 and fix it at the top of the roof beam 8.
[0056] In this embodiment, a suspension device is provided at the bottom of the roof beam 8 for installing the smoke hood 13, and a bracket is provided at the top of the roof beam 8 for installing the pipe 14.
[0057] S4. For the installation of the steel structure and equipment of the furnace front platform 10, please refer to... Figure 4
[0058] S41. Using the hoisting operation of the overhead crane 11, install the first platform column 10.1 and the second platform column 10.2 on one side of the installation zone 4, specifically at line 4. On the other side, install the third platform column 10.3 and the fourth platform column 10.4, specifically at line 5. Install platform beams 10.5 on the first platform column 10.1, the second platform column 10.2, the third platform column 10.3 and the fourth platform column 10.4 to form the furnace front platform 10. At the same time, reserve multiple platform beams 10.5 between the second platform column 10.2 and the third platform column 10.3 on the side close to the converter foundation 16. These beams will not be installed as a temporary placement area for the converter equipment.
[0059] The converter foundation 16 was poured before the construction of the charging span 1, and the tilting reducer stop seat 19 is installed on the converter foundation 16.
[0060] S42. The converter equipment is hoisted to the temporary placement area by the overhead crane 11, and then the converter equipment is pushed to the furnace span 2 by the trolley for installation. Finally, the platform beam 10.5 of the temporary placement area is installed.
[0061] S43. Assemble the cable corridor 15 on the ground between the first platform column 10.1 and the second platform column 10.2. After the assembly is completed, suspend the cable corridor 15 under the furnace front platform 10.
[0062] S44. Install temporary supports 17 on the third platform column 10.3 and the fourth platform column 10.4 on the side of the converter foundation 16. At the same time, set up temporary columns on the converter foundation 16. Then, lay the roadbed box 18 on the temporary supports 17 and the temporary columns. The thickness of the temporary supports 17, the temporary columns and the roadbed box 18 is set according to the height of the tilting reducer stop seat 19. Make the top elevation of the roadbed box 18 flush with the top elevation of the tilting reducer stop seat 19 on the converter foundation 16. Finally, place the tilting reducer on the roadbed box 18 and push it into the furnace span 2 to install it on the tilting reducer stop seat 19. After the converter tilting reducer is installed, remove the roadbed box 18, the temporary columns and the temporary supports 17.
[0063] S5. While installing the steel structure and equipment of the furnace front platform 10, complete the installation of the steel structure and overhead crane 11 of installation zone 5 according to step S2. Please refer to... Figure 1 Specifically, the crane 11 in zone 5 is installed on the crane beam 7 of lines 6 to 7 according to the construction method in step S2.
[0064] This invention changes the sequential construction of the existing charging span 1 and equipment to parallel construction. The structure of the charging span 1 is divided into three installation areas. Installation area 1 (3) and installation area 2 (4) are constructed simultaneously. The steel structure and equipment of installation area 2 (4) are installed simultaneously while the steel structure and overhead crane 11 of installation area 1 (3) are being installed. Then, the steel structure and equipment of the furnace front platform 10 are installed using the overhead crane 11, which is delivered first in installation area 1 (3). Specifically, a temporary placement area is set up on the furnace front platform 10 for the converter installation in advance. The cable corridor 15 is suspended and installed under the furnace front platform 10 in advance, and the tilting reducer is installed in advance through temporary supports 17, temporary columns, and roadbed boxes 18. All construction operations are carried out simultaneously, which can complete the installation and commissioning of the converter equipment as early as possible. Moreover, the steel structure and overhead crane 11 of installation area 3 (5) are installed at the same time as the steel structure and equipment of the furnace front platform 10. This invention makes reasonable deployment and interleaving of the construction of the charging span 1 and equipment, which can improve construction efficiency and greatly shorten the installation cycle of the converter project.
[0065] The above embodiments are only used to illustrate the technical solutions of the present invention, and are not intended to limit it. Although the present invention has been described in detail with reference to the foregoing embodiments, those skilled in the art should understand that modifications can still be made to the technical solutions described in the foregoing embodiments, or equivalent substitutions can be made to some of the technical features. Such modifications or substitutions do not cause the essence of the corresponding technical solutions to deviate from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A method for synchronously installing the converter charging span structure and equipment, characterized in that, Includes the following steps: S1, Material feeding across work areas The charging span is divided into three sections: installation zone 1, installation zone 2, and installation zone 3, with the converter high-rise frame column as the dividing point. The steel structure and equipment of the charging span are constructed in sections. The area from the converter high-rise frame column to the end of the front column is installation zone 1, the area containing the converter high-rise frame column is installation zone 2, and the area from the converter high-rise frame column to the end of the rear column is installation zone 3. S2. Installation of the steel structure and overhead crane in Zone 1. S21. From the high-rise frame column of the converter to the end of the front column row, the feeding span column, the crane beam, and the roof beam are constructed in sequence, and the roof purlins are laid and installed on the top between the roof beams. A reserved span is set at the end of the front column row, and the roof purlins are not installed in the reserved span. S22. Install the first main beam and the second main beam on the front and rear sides of the reserved mid-span trolley beam respectively, and install end beams at both ends of the first main beam. Then install the first secondary beam between the two end beams. Leave enough hoisting space between the first secondary beam and the second main beam. Then hoist the trolley vertically between the first secondary beam and the second main beam. When the lowest part of the trolley exceeds the top of the first main beam and the second main beam, install the second secondary beam between the two end beams. Then move the first main beam to the second main beam. The two are connected and fixed through the end beams. Finally, lower the trolley to the first main beam and the second main beam. S23. Install roof purlins with reserved spans; S3. During the installation process in step S2, the installation of the steel structure and equipment in Zone 2 shall be carried out simultaneously. S31. Install the charging cross columns and converter high-rise frame columns in the second installation zone. The converter high-rise frame columns are divided into two sections by the elevation of the crane beam rail surface. First, install the lower column of the converter high-rise frame, and then install the upper column of the converter high-rise frame. S32. Install trolley beams on the charging cross column and the lower column of the converter high-rise frame respectively, so that the trolley beams of the second installation zone are connected to the trolley beams of the first installation zone, and the trolleys of the first installation zone can run to the second installation zone for subsequent furnace front platform and equipment installation. S33. Install the roof beam. One end of the roof beam is connected to the feeding cross column, and the other end is connected to the upper column of the converter high-rise frame. S34. Arrange the hoisting machinery in the third installation area, use the hoisting machinery to hoist the fume hood and suspend it at the bottom of the roof beam. After installation, lay the roof purlins on the roof beam. Finally, use the hoisting machinery to hoist the pipe and fix it to the top of the roof beam. S4. Installation of steel structure and equipment for furnace front platform S41. Install the first and second platform columns on one side of the installation zone 2 by means of overhead crane hoisting operation, and install the third and fourth platform columns on the other side. Install platform beams on the first, second, third and fourth platform columns to form a furnace front platform. At the same time, reserve multiple platform beams between the second and third platform columns near the converter foundation as a temporary placement area for converter equipment. S42. The converter equipment is hoisted to the temporary placement area by a crane, and then the converter equipment is pushed to the middle of the furnace span by a trolley for installation. Finally, the platform beam of the temporary placement area is installed. S43. Assemble the cable corridor on the ground between the first platform column and the second platform column. After assembly, suspend the cable corridor under the furnace front platform. S44. Install temporary supports on the third and fourth platform columns on the side closest to the converter foundation, and set up temporary columns on the converter foundation. Then lay roadbed boxes on the temporary supports and temporary columns, and make the top elevation of the roadbed boxes level with the top elevation of the tilting reducer stop seat on the converter foundation. Finally, place the tilting reducer on the roadbed boxes and push it to the middle of the furnace span to install it on the tilting reducer stop seat. S5. While installing the steel structure and equipment on the furnace front platform, complete the installation of the steel structure and overhead crane in the third installation zone according to step S2.
2. The method for synchronous installation of converter charging span structure and equipment according to claim 1, characterized in that: In step S1, the charging span is composed of two columns, A and B, including multiple column structures from line 1 to line 7. Lines 4 to 5 of the B axis are provided with the converter high-rise frame columns of the furnace span. Therefore, lines 1 to 4 are the first installation zone, lines 4 to 5 are the second installation zone, and lines 5 to 7 are the third installation zone.
3. The method for synchronously installing the converter charging span structure and equipment according to claim 2, characterized in that: In step S21, the reserved span is from line 1 to line 2.
4. The method for synchronous installation of converter charging span structure and equipment according to claim 1, characterized in that: In step S22, the first main beam, the second main beam, the end beam, the first auxiliary beam, the second auxiliary beam, and the overhead crane together form a crane that can move on the crane beam, used for hoisting the steel structure and equipment of the furnace front platform.
5. The method for synchronous installation of converter charging span structure and equipment according to claim 2, characterized in that: In step S31, the charging cross column is located on axis A, and the converter high-rise frame column is located on axis B.
6. The method for synchronous installation of converter charging span structure and equipment according to claim 1, characterized in that: In step S34, a suspension device is provided at the bottom of the roof beam for installing a smoke hood, and a bracket is provided at the top of the roof beam for installing pipes.
7. The method for synchronous installation of converter charging span structure and equipment according to claim 1, characterized in that: In step S41, the converter foundation has been poured before the construction of the charging span, and a tilting reducer stop seat is installed on the converter foundation.
8. The method for synchronous installation of converter charging span structure and equipment according to claim 1, characterized in that: In step S44, after the converter tilting reducer is installed, the roadbed box, temporary columns and temporary supports are removed.
9. A method for synchronously installing the converter charging span structure and equipment according to claim 2, characterized in that: In step S5, the three-zone crane is installed on the crane beams of lines 6 to 7 according to the construction method in step S2.
Citation Information
Patent Citations
Advance integrated installing method of converter
CN103468850A
Construction method for synchronously carrying out high-rise frame structure and large equipment in steel plant
CN113463953A