Pile foundation tooling for rotary drilling construction in water-rich karst areas

By introducing an electric scraper assembly and a cutting auger into the pile foundation tooling for rotary drill construction, the problem of cleaning and clogging of attachments on the inner wall of the injection hopper is solved, and the efficiency and quality of pile foundation construction are improved.

CN117488859BActive Publication Date: 2024-10-18CHINA CONSTR THIRD ENG BUREAU GRP CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311601019.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-11-28
Publication Date
2024-10-18
Estimated Expiration
2043-11-28

AI Technical Summary

Technical Problem

During the construction of pile foundations in water-rich karst areas, the concrete in the injection hopper easily adheres to the inner wall, causing waste and blockage, affecting pouring efficiency and construction progress.

Method used

A pile foundation tooling for rotary drilling construction including an electric scraper assembly, a centering positioning assembly, a hand-operated control assembly and a guide assembly is designed. The electric scraper assembly is used to clean the concrete attached to the inner wall of the injection hopper, and the lower part of the transmission shaft The unloading auger speeds up concrete unloading, and the positioning assembly and locking structure improve the fixing strength of the steel casing and injection hopper to avoid shaking and clogging.

Benefits of technology

It effectively reduces concrete waste and blockage, improves pouring efficiency and construction progress, and ensures pile quality and disassembly and assembly efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure HDA0004574105730000011
    Figure HDA0004574105730000011
  • Figure HDA0004574105730000012
    Figure HDA0004574105730000012
  • Figure HDA0004574105730000021
    Figure HDA0004574105730000021
Patent Text Reader

Abstract

The present invention discloses a pile foundation tooling for rotary drilling construction in water-rich karst areas, and relates to the technical field of pile foundation construction in water-rich karst areas. The tooling includes a base with a through hole at the center, a steel casing that is arranged in the through hole, an electric scraper assembly, a centering and positioning assembly, a hand-cranked control assembly, and a guide assembly, and a hopper is fixed to the top of the steel casing through a locking structure. The present invention is designed with an electric scraper assembly, which can facilitate the effective cleaning of concrete attached to the inner wall of the hopper during the pile foundation construction process, thereby reducing the waste of concrete raw materials; the present invention can make the two V-shaped positioning blocks fixed on the two centering rods align and approach to each other through the coordinated cooperation of the centering and positioning assembly, the hand-cranked control assembly, and the guide assembly, so as to facilitate the effective positioning of steel casings of different specifications, and adopt a double locking method to increase the locking force, thereby avoiding shaking during the pile foundation construction process and ensuring the quality of pile formation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of pile foundation construction in water-rich karst areas, in particular to pile foundation tooling for rotary drilling construction in water-rich karst areas. Background Art

[0002] In the process of pile foundation construction in water-rich karst areas, the mechanical hole-making technology of bored piles is generally adopted, especially the rotary drilling hole-making technology. The supporting tooling for the follow-up of the steel casing with the rotary drilling construction can realize the hole expansion at the bottom of the casing, and then the steel casing is driven down with a vibrating hammer to drill the hole.

[0003] Currently, during the construction process, it is necessary to connect a hopper to the top of the steel casing to pour concrete into the steel casing. However, the concrete in the hopper tends to adhere to the inner wall of the hopper in large quantities, causing waste of raw materials, and subsequent cleaning is more troublesome. At the same time, the hopper is prone to blockage, which affects the efficiency of concrete pouring and delays the progress of pile foundation construction. Summary of the invention

[0004] In view of the shortcomings of the prior art, the present invention provides a pile foundation tooling for rotary drilling construction in water-rich karst areas. In order to achieve the above-mentioned purpose, the present invention adopts the following technical solutions:

[0005] A pile foundation tooling for rotary drilling construction in a water-rich karst area, comprising a base with a through hole opened at the center and a steel casing penetrating the through hole;

[0006] It also includes an electric scraper assembly, a centering and positioning assembly, a hand-operated control assembly and a guide assembly, and a filling hopper is fixed on the top of the steel casing through a locking structure;

[0007] The electric scraper assembly includes a support rod welded to the top outer wall of the filling hopper, a drive motor fixed to the top outer wall of the support rod, a transmission shaft coaxially connected to the output shaft of the drive motor through a coupling, a connecting rod fixedly connected to the transmission shaft and a scraper bevel welded to the outer wall of one end of the connecting rod, and a feeding auger is welded to the lower outer wall of the transmission shaft.

[0008] As a preferred technical solution, the transmission shaft is concentrically arranged with the injection hopper, and the scraper bevel knife contacts the inner wall of the injection hopper.

[0009] As a preferred technical solution, the centering and positioning assembly includes a first U-shaped bracket welded to the top outer wall of the base, a bidirectional screw rotatably installed on the first U-shaped bracket, two centering rods symmetrically threaded on two opposite threaded ends of the bidirectional screw, and two V-shaped positioning blocks symmetrically fixed to the outer walls of adjacent sides of the two centering rods.

[0010] As an optimal technical solution, the hand-cranked control assembly includes a worm gear fixedly mounted on a bidirectional screw, a bearing seat fixedly mounted on the top outer wall of the base, a control vertical shaft whose bottom end is connected to the top inner wall of the bearing seat through a bearing, a worm fixedly mounted on the control vertical shaft and meshing with the worm gear, and a control handwheel fixedly connected to the top outer wall of the control vertical shaft.

[0011] As a preferred technical solution, the guide assembly includes a second U-shaped bracket welded to the top outer wall of the base, a guide transverse axis welded to the second U-shaped bracket, and two linear bearings fixedly embedded in two centering rods, and both linear bearings are movably connected to the guide transverse axis.

[0012] As a preferred technical solution, the locking structure includes an adjustment ring sleeved on the upper part of the steel casing, four annularly distributed positioning beads installed on the inner outer wall of the adjustment ring, and four annularly distributed locking assemblies.

[0013] As a preferred technical solution, the positioning bead is a press-in ball plunger, and the surface of the steel casing is provided with three positioning bead limiting components distributed at equal distances.

[0014] As an optimal technical solution, the locking assembly includes an articulated oblique rod hinged on an adjusting ring, a slider hinged to the upper part of the articulated oblique rod, an arc-shaped locking block welded to the top outer wall of the slider, and a T-shaped guide rod welded to the upper outer wall of the steel casing, and the slider is slidably connected to the T-shaped guide rod.

[0015] As a preferred technical solution, the limiting component includes four positioning holes opened on the surface of the steel casing, and the positioning holes are adapted to the positioning beads.

[0016] The beneficial effects of the present invention are:

[0017] 1. The present invention is designed with an electric scraper assembly, which drives the transmission shaft to rotate through a driving motor, and then the scraper blade connected to one end of the connecting rod will make a circular motion on the inner wall of the injection hopper, so that during the pile foundation construction, it is convenient to effectively clean the concrete attached to the inner wall of the injection hopper, reducing the waste of concrete raw materials and the subsequent cleaning workload;

[0018] 2. The unloading auger fixed at the lower part of the transmission shaft of the present invention can accelerate the unloading rate of concrete during high-speed rotation, effectively reduce the blockage in the hopper, and is conducive to improving the pouring efficiency of concrete and accelerating the progress of pile foundation construction;

[0019] 3. The present invention can make the two V-shaped positioning blocks fixed on the two centering rods align and move closer together through the coordinated cooperation of the centering positioning assembly, the hand-cranked control assembly and the guide assembly, so as to facilitate the effective positioning of steel casings of different specifications, and adopt a double locking method to improve the locking force, thus avoiding shaking during the pile foundation construction process and ensuring the quality of pile formation;

[0020] 4. The top of the steel casing of the present invention is fixed with a filling hopper by a locking structure, and the filling hopper is locked and locked by four arc-shaped locking blocks, which is convenient for effectively locking and fixing the filling hopper, and the locking is released by moving the four arc-shaped locking blocks away from each other, which is convenient for quickly removing the filling hopper, thereby improving the disassembly and assembly efficiency of the filling hopper during the pile foundation construction process, and helping to improve the construction efficiency of the pile foundation construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the overall front-view three-dimensional structure of the present invention;

[0022] Figure 2 It is a front view structural schematic diagram of the electric scraper assembly in the present invention;

[0023] Figure 3 It is a three-dimensional structural schematic diagram of the centering positioning component, the hand-cranked control component and the guide component in the present invention;

[0024] Figure 4 It is a three-dimensional enlarged structural schematic diagram of the hand-cranked control assembly in the present invention;

[0025] Figure 5 It is a schematic diagram of the three-dimensional structure of the connection between the injection hopper and the steel casing in the present invention;

[0026] Figure 6 It is a three-dimensional enlarged structural schematic diagram of the locking structure in the present invention;

[0027] Figure 7 It is a schematic diagram of the three-dimensional structure of the positioning hole in the present invention.

[0028] In the figure: 1. base; 2. through hole; 3. steel casing; 4. injection hopper; 5. support rod; 6. drive motor; 7. transmission shaft; 8. connecting rod; 9. scraper bevel knife; 10. unloading auger; 11. first U-shaped bracket; 12. bidirectional screw; 13. centering rod; 14. V-shaped positioning block; 15. worm gear; 16. bearing seat; 17. control vertical axis; 18. worm; 19. control hand wheel; 20. second U-shaped bracket; 21. guide horizontal axis; 22. linear bearing; 23. adjustment ring; 24. positioning bead; 25. positioning hole; 26. hinged oblique rod; 27. slider; 28. arc locking block; 29. ​​T-shaped guide rod. DETAILED DESCRIPTION

[0029] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.

[0030] Example 1, reference Figure 1-2 , a pile foundation tooling for rotary drilling construction in water-rich karst areas, comprising a base 1 with a through hole 2 opened at the center, a steel casing 3 penetrating the through hole 2, an electric scraper assembly and a material injection hopper 4;

[0031] The electric scraper assembly includes a support rod 5, a drive motor 6, a transmission shaft 7, a connecting rod 8 and a scraper bevel knife 9;

[0032] Specifically, the support rod 5 is welded to the top outer wall of the injection hopper 4, the drive motor 6 is fixed to the top outer wall of the support rod 5 by bolts, the top end of the transmission shaft 7 is coaxially connected to the output shaft of the drive motor 6 through a coupling, the transmission shaft 7 is concentrically arranged with the injection hopper 4, the connecting rod 8 is fixedly connected to the transmission shaft 7, the scraper bevel 9 is welded to the outer wall of one end of the connecting rod 8, and the scraper bevel 9 contacts the inner wall of the injection hopper 4;

[0033] When in use, the transmission shaft 7 is controlled to rotate by the driving motor 6, and then the scraper 9 connected to one end of the connecting rod 8 will make a circular motion on the inner wall of the injection hopper 4, so that during the pile foundation construction, it is convenient to effectively clean the concrete attached to the inner wall of the injection hopper 4, reducing the waste of concrete raw materials and the subsequent cleaning workload;

[0034] In addition, a feeding auger 10 is welded to the lower outer wall of the transmission shaft 7. The feeding auger 10 fixed at the lower part of the transmission shaft 7 can accelerate the feeding rate of concrete during high-speed rotation, effectively reducing the blockage in the filling hopper 4, which is beneficial to improving the concrete pouring efficiency and accelerating the progress of pile foundation construction.

[0035] Example 2, reference Figure 1 and Figure 3-4 , This embodiment is optimized on the basis of embodiment 1, specifically: the pile foundation tooling for rotary drilling construction in water-rich karst areas also includes a centering positioning component, a hand-cranked control component and a guide component;

[0036] The centering and positioning assembly includes a first U-shaped bracket 11, a bidirectional screw 12, two centering rods 13 and two V-shaped positioning blocks 14;

[0037] Specifically, the first U-shaped bracket 11 is welded to the top outer wall of the base 1, the bidirectional screw 12 is connected to the inner walls of both sides of the first U-shaped bracket 11 through two bearings, the two centering rods 13 are symmetrically screwed to the two opposite threaded ends of the bidirectional screw 12, and the two V-shaped positioning blocks 14 are symmetrically fixed to the outer walls of one side adjacent to the two centering rods 13;

[0038] When in use, the rotation of the bidirectional screw 12 will control the two V-shaped positioning blocks 14 fixed on the two centering rods 13 to be centered and close together, so as to facilitate the effective positioning of steel casings 3 of different specifications;

[0039] The hand-operated control assembly includes a worm gear 15, a bearing seat 16, a control vertical shaft 17, a worm 18 and a control hand wheel 19;

[0040] Specifically, the worm gear 15 is fixedly mounted on the bidirectional screw 12, the bearing seat 16 is fixedly mounted on the top outer wall of the base 1 by bolts, the bottom end of the control vertical shaft 17 is connected to the top inner wall of the bearing seat 16 by a bearing, the worm 18 is fixedly mounted on the control vertical shaft 17 and meshes with the worm gear 15, and the control hand wheel 19 is fixedly connected to the top outer wall of the control vertical shaft 17;

[0041] When in use, the worm 18 on the vertical shaft 17 is driven to rotate by operating the hand wheel 19, and then the worm wheel 15 meshing with the worm 18 drives the bidirectional screw 12 to rotate. Since the bidirectional screw 12 is threadedly connected with the two centering rods 13, it has a thread locking effect, and the worm 18 and the worm wheel 15 also have a self-locking performance after meshing, so the double locking method is used to improve the locking strength;

[0042] The guide assembly includes a second U-shaped bracket 20, a guide transverse axis 21 and two linear bearings 22;

[0043] Specifically, the second U-shaped bracket 20 is welded to the top outer wall of the base 1, the guide transverse shaft 21 is welded to the second U-shaped bracket 20, and two linear bearings 22 are fixedly embedded in the two centering rods 13 in sequence, and the two linear bearings 22 are movably connected to the guide transverse shaft 21;

[0044] When in use, the cooperation between the two linear bearings 22 and the guide horizontal shaft 21 can ensure that the two centering rods 13 move in a straight line, and the friction force is small, and the movement is smoother;

[0045] To sum up: this embodiment, through the coordinated cooperation of the centering positioning component, the hand-cranked control component and the guide component, can make the two V-shaped positioning blocks 14 fixed on the two centering rods 13 centered and close to each other, which is convenient for effectively positioning the steel casings 3 of different specifications, and adopts a double locking method to increase the locking force, thus avoiding shaking during the pile foundation construction process and ensuring the quality of the pile.

[0046] Example 3, reference Figure 1 and Figure 5-7 , This embodiment is optimized on the basis of embodiment 1, specifically: the pile foundation tooling for rotary drilling construction in water-rich karst areas also includes a locking structure;

[0047] The locking structure includes an adjusting ring 23 sleeved on the upper part of the steel casing 3, four annularly distributed positioning beads 24 installed on the inner and outer walls of the adjusting ring 23, and four annularly distributed locking components. The positioning beads 24 are press-fit ball plungers. The surface of the steel casing 3 is provided with three equally spaced positioning beads 24 limiting components.

[0048] The locking assembly includes an articulated oblique rod 26 articulated on the adjusting ring 23, a slider 27 articulated on the upper part of the articulated oblique rod 26, an arc-shaped locking block 28 welded to the outer wall of the top of the slider 27, and a T-shaped guide rod 29 welded to the outer wall of the upper part of the steel casing 3, and the slider 27 is slidably connected to the T-shaped guide rod 29;

[0049] The limiting component includes four positioning holes 25 opened on the surface of the steel casing 3, and the positioning holes 25 are adapted to the positioning beads 24;

[0050] In this embodiment, the injection hopper 4 is locked and locked by four arc-shaped locking blocks 28, so that the injection hopper 4 can be effectively locked and fixed, and the locking is released by moving the four arc-shaped locking blocks 28 away from each other, so that the injection hopper 4 can be quickly removed, which improves the disassembly and assembly efficiency of the injection hopper 4 during the pile foundation construction, and helps to improve the construction efficiency of the pile foundation construction.

[0051] The working mode of the present invention is:

[0052] First, the worm 18 on the vertical shaft 17 is driven to rotate by the control hand wheel 19, and then the worm wheel 15 meshing with the worm 18 drives the bidirectional screw 12 to rotate. Under the guidance of the guide assembly, the rotation of the bidirectional screw 12 controls the two V-shaped positioning blocks 14 fixed on the two centering rods 13 to center and move closer, which is convenient for effectively positioning the steel casings 3 of different specifications, thus avoiding the shaking of the steel casing 3 during the pile foundation construction process, and ensuring the quality of the pile;

[0053] Secondly, put the injection hopper 4 into the top of the steel casing 3, and then push the adjusting ring 23 downward. The downward movement of the adjusting ring 23 will make the four hinged inclined rods 26 move together. Under the guidance of the T-shaped guide rod 29, the movement of the four hinged inclined rods 26 will pull the arc-shaped locking blocks 28 fixed on the top of the four sliders 27 to lock and lock the injection hopper 4, which is convenient for effectively locking and fixing the injection hopper 4, improving the installation efficiency. In addition, since the inner and outer walls of the adjusting ring 23 are equipped with four positioning beads 24 and the surface of the steel casing 3 is provided with positioning holes 25 adapted thereto, the position of the adjusting ring 23 can be automatically fixed and locked after the movement is completed.

[0054] Then, during the concrete pouring process, the transmission shaft 7 is controlled to rotate by the driving motor 6, and then the scraper bevel 9 connected to one end of the connecting rod 8 will make a circular motion on the inner wall of the injection hopper 4, so that during the pile foundation construction, it is convenient to effectively clean the concrete attached to the inner wall of the injection hopper 4, reducing the waste of concrete raw materials and the subsequent cleaning workload. The unloading auger 10 fixed at the lower part of the transmission shaft 7 can accelerate the unloading rate of concrete during the high-speed rotation process, effectively reducing the blockage in the injection hopper 4, which is beneficial to improving the concrete pouring efficiency and accelerating the progress of pile foundation construction.

[0055] Finally, by pushing the adjustment ring 23 upward, the upward movement of the adjustment ring 23 will cause the four hinged oblique rods 26 to move together. Under the guidance of the T-shaped guide rod 29, the movement of the four hinged oblique rods 26 will drive the four sliders 27 to retreat. At this time, the four arc-shaped locking blocks 28 fixed on the top of the four sliders 27 retreat together, which is convenient for quick removal of the filling hopper 4.

[0056] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A pile foundation tool for rotary drilling construction in a water-rich karst area, comprising a base (1) with a through hole (2) opened at the center and a steel casing (3) penetrating the through hole (2); It is characterized in that It also includes an electric scraper assembly, a centering and positioning assembly, a hand-operated control assembly and a guide assembly, and a material injection hopper (4) is fixed to the top of the steel casing (3) via a locking structure; The electric scraper assembly comprises a support rod (5) welded to the top outer wall of the injection hopper (4), a drive motor (6) fixedly mounted on the top outer wall of the support rod (5), a transmission shaft (7) coaxially connected to the output shaft of the drive motor (6) via a coupling, a connecting rod (8) fixedly connected to the transmission shaft (7), and a scraper bevel (9) welded to the outer wall of one end of the connecting rod (8), and a material unloading auger (10) is welded to the lower outer wall of the transmission shaft (7); The transmission shaft (7) is arranged concentrically with the injection hopper (4), and the scraper blade (9) is in contact with the inner wall of the injection hopper (4); The centering and positioning assembly comprises a first U-shaped bracket (11) welded to the top outer wall of the base (1), a bidirectional screw (12) rotatably mounted on the first U-shaped bracket (11), two centering rods (13) symmetrically screwed to two opposite threaded ends of the bidirectional screw (12), and two V-shaped positioning blocks (14) symmetrically fixed to the outer walls of adjacent sides of the two centering rods (13); The hand-cranked control assembly comprises a worm wheel (15) fixedly mounted on the bidirectional screw (12), a bearing seat (16) fixedly mounted on the top outer wall of the base (1), a control vertical shaft (17) whose bottom end is connected to the top inner wall of the bearing seat (16) via a bearing, a worm (18) fixedly mounted on the control vertical shaft (17) and meshing with the worm wheel (15), and a control hand wheel (19) fixedly connected to the top outer wall of the control vertical shaft (17); The guide assembly comprises a second U-shaped bracket (20) welded to the top outer wall of the base (1), a guide transverse shaft (21) welded to the second U-shaped bracket (20), and two linear bearings (22) fixedly embedded in two centering rods (13), and the two linear bearings (22) are both movably connected to the guide transverse shaft (21); The locking structure comprises an adjusting ring (23) sleeved on the upper part of the steel casing (3), four annularly distributed positioning beads (24) mounted on the inner and outer walls of the adjusting ring (23), and four annularly distributed locking components; The positioning bead (24) is a press-in ball plunger, and the surface of the steel casing (3) is provided with three positioning bead (24) limiting components which are distributed at equal distances; The locking assembly comprises an articulated oblique rod (26) articulated on the adjusting ring (23), a slider (27) articulated on the upper part of the articulated oblique rod (26), an arc-shaped locking block (28) welded to the top outer wall of the slider (27), and a T-shaped guide rod (29) welded to the upper outer wall of the steel casing (3), and the slider (27) is slidably connected to the T-shaped guide rod (29); The limiting component comprises four positioning holes (25) opened on the surface of the steel casing (3), and the positioning holes (25) are matched with the positioning beads (24).

Citation Information

Patent Citations

  • Cast-in-place concrete long pile vibrating device and construction method thereof

    CN111705802A

  • Medicament mixing device for dermatological department

    CN213528339U