A method for constructing equipment pipe networks in ultra-high structures and narrow spaces
Through systematic in-depth design and process interleaving, combined with the scaffolding installation drawings during structural construction, the piping and cable penetration of mechanical and electrical equipment and pipe networks are completed in ultra-high structures and narrow spaces, and are prefabricated and assembled on the ground to solve the problem of safety in high-altitude operations. Hidden hazards are eliminated and construction efficiency and quality are improved.
Patent Information
- Application Number
- CN202311534783.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-17
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2043-11-17
AI Technical Summary
In ultra-high structures and narrow spaces, late-stage high-altitude operations on electromechanical equipment and pipe networks have safety and quality hazards that are difficult to effectively solve.
Through system in-depth design and process interleaving, combined with the scaffolding installation drawings during the structural construction, the piping and cable penetration of the mechanical and electrical equipment and pipe network are completed, and installation and debugging are carried out during the dismantling stage of the scaffolding in the hall, reducing the content of high-altitude operations, and on the ground Complete the prefabricated assembly of pipelines and supports and hangers.
It eliminates high-altitude operations in the later installation of mechanical and electrical equipment, improves construction safety and efficiency, reduces construction difficulty, and speeds up construction progress and quality.
Smart Images

Figure CN117526172B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of building construction, and more specifically, to a method for constructing equipment pipe networks in ultra-high structures and narrow spaces. Background Art
[0002] With the improvement of people's living standards, the wine consumption market is getting bigger and bigger, the liquor industry is booming, the production and storage volume of large liquor companies has increased dramatically, and the country has begun to expand and transform modern wineries. The traditional method of storing wine in ceramic jars is difficult to meet the demand for the sharp increase in storage volume, and the disadvantage of setting up stainless steel wine storage tanks outdoors is that they are prone to environmental impacts. The method of setting up stainless steel wine storage tanks in indoor warehouses has been rapidly promoted and applied.
[0003] Although the indoor stainless steel wine storage tank warehouse can meet the storage requirements of the enterprise, there are also some problems: compared with the outdoor wine storage tanks, the indoor tank wine storage tanks are installed inside the frame structure, the mass of a single tank is large, and the quality requirements of the tank foundation construction are high. The tank foundation construction is completed simultaneously with the pile foundation construction. The explosion-proof walls on both sides of the single-row tank are also super-high structure construction. The explosion-proof walls are completed simultaneously during the structural construction. Wine is stored as flammable and explosive liquids. Fire protection systems, three-band flame detectors and roof rainwater pipes are installed in the fire protection zone. The mechanical and electrical equipment and pipeline network in the storage area do not have the conditions for high-altitude machinery construction, and the space is narrow. There are great safety and quality risks in construction. Summary of the invention
[0004] One purpose of this application is to solve the technical problems of difficulties in the later high-altitude operations of electromechanical equipment and pipelines in current buildings with ultra-high structures and narrow spaces, and great safety and quality risks in construction. Other advantages of this application will be explained later.
[0005] In order to achieve these objectives, the present application provides a method for constructing a super-high structure and narrow space equipment pipe network, including electromechanical equipment installation and pipe network installation, the steps are as follows:
[0006] S10: System deepening of pipelines and specialized pipelines of electromechanical equipment to be installed;
[0007] S20: Based on the mechanical and electrical equipment pipelines and professional pipelines after the system deepening in S10, combined with the scaffolding installation drawings during the structural construction, the professional pipelines and mechanical and electrical equipment piping and cable threading are completed through interleaving of processes during the structural construction;
[0008] S30: Based on the results of the in-depth study of the electromechanical equipment pipeline system and combined with the scaffolding installation drawings during the structural construction, when the scaffolding is dismantled to 0.5m to 1.5m below the detection equipment, the electromechanical equipment is immediately installed and the equipment angle is adjusted to prevent high-altitude work during the subsequent electromechanical installation.
[0009] Preferably, the in-depth design of electromechanical equipment pipelines and professional pipelines in S10 includes the following steps:
[0010] S11: According to the design drawings of electromechanical equipment pipelines, professional pipelines, and civil engineering, construct equipment pipeline BIM models, pipeline BIM models, and building BIM models respectively;
[0011] S12: Integrate the equipment pipeline BIM model and the pipeline BIM model constructed in S11, and optimize and arrange the conflicting and colliding parts in the pipeline BIM model and the pipeline BIM model to obtain a comprehensive pipeline BIM model;
[0012] S13: Integrate the integrated pipeline BIM model with the building BIM model, optimize and arrange the conflicting and colliding parts of the integrated pipeline BIM model and the building BIM model, obtain the integrated pipeline model after in-depth design, and issue in-depth design drawings of the integrated pipeline.
[0013] Preferably, after the comprehensive pipeline detailed design drawings are issued, the support and hanger details are drawn based on the comprehensive pipeline detailed design drawings.
[0014] Preferably, after drawing the support and hanger general drawing, construct the support and hanger BIM model according to the drawn support and hanger general drawing, integrate the support and hanger BIM model with the comprehensive pipeline model and building BIM model after in-depth design, optimize and arrange the conflicting and colliding parts of each model, clarify the support and hanger shaping plan, and issue the support and hanger in-depth design drawings.
[0015] Preferably, after issuing the detailed design drawings of supports and hangers, according to the main structure construction plan, the detailed design drawings of integrated pipelines, the detailed design drawings of supports and hangers, the full-floor scaffolding installation drawings during the structural construction, and the on-site transportation conditions of the storage area, the comprehensive pipeline pipes and supports and hangers are reasonably structurally split and component decomposition drawings are issued.
[0016] Preferably, the support and hanger is a pipeline integrated support and hanger.
[0017] Preferably, the disassembled integrated pipeline pipes and supports and hangers are pre-processed in a prefabrication factory according to the component disassembly drawings; and the pipeline pipes and supports and hangers are prefabricated and assembled on the ground before installation according to the construction procedures and construction and installation planning.
[0018] Preferably, in step S30, after the electromechanical equipment is debugged, a bubble protective cover is provided outside the electromechanical equipment for protection, and a wire is reserved, one end of which is connected to the bubble protective cover and the other end of which extends to the ground.
[0019] Preferably, the bubble protective cover can be removed by traction with a wire on the ground during fire debugging to prevent high-altitude work in the subsequent electromechanical installation.
[0020] By adopting the above technology, compared with the prior art, the beneficial effects of the present invention are:
[0021] 1. The method of the present invention systematically deepens the electromechanical equipment and pipeline network in super-high structures and narrow spaces, combines the full-floor scaffolding installation drawing during the structural construction period, uses the process interspersed during the structural construction period to complete the professional pipeline and mechanical equipment piping and cable threading, and completes the electromechanical installation and debugging during the full-floor scaffolding dismantling stage, thereby eliminating the high-altitude work content of the later electromechanical equipment installation.
[0022] 2. The method of the present invention, according to the transportation conditions of the construction site, combined with the in-depth design drawings of the pipelines and the in-depth design drawings of the supports and hangers, separates the pipelines and supports and hangers into components, and completes the prefabrication and assembly of the pipelines and supports and hangers on the ground before installation, thereby reducing the high-altitude work content and construction difficulty of the pipeline network construction, speeding up the installation of the pipelines and supports and hangers, and improving the installation efficiency and quality.
[0023] 3. The method of the present invention, by deepening the pipelines and supports and hangers and utilizing integrated supports, concentrates the construction on the same working surface, speeds up the construction progress, and can complete the installation and commissioning of electromechanical equipment more quickly during the scaffolding removal stage with higher safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings used in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without creative work.
[0025] Figure 1 Flow chart of the construction method of super-high structure and narrow space equipment pipe network provided for this application;
[0026] Figure 2 A schematic diagram of the plan structure of a wine storage warehouse provided in Example 1 of the present application;
[0027] Figure 3 A schematic diagram of the structure of one implementation of the equipment bracket provided in the embodiment of the present application;
[0028] Figure 4 A schematic diagram of the structure of one implementation of the pipe support provided in the embodiment of the present application;
[0029] Figure 5 A schematic structural diagram of another implementation scheme of the pipe support provided in the embodiment of the present application;
[0030] Figure 6 A schematic diagram of the structure of one implementation of the integrated bracket provided in the embodiment of the present application;
[0031] Figure 7 A schematic structural diagram of another implementation scheme of the pipe support provided in the embodiment of the present application;
[0032] Markings in the figure: 1-tank body, 2-explosion-proof wall, 3-exterior wall, 4-first connecting piece, 5-second connecting piece, 6-third connecting piece, 7-three-band flame detector, 8-rainwater pipe, 9-reinforcement rib, 10-pipe clamp a, 11 pipe clamp b. DETAILED DESCRIPTION
[0033] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.
[0034] In the description of the present invention, it is explained that the orientations or positional relationships indicated by terms such as "center", "up", "down", "left", "right", "vertical", "horizontal", "inside" and "outside" are based on the orientations or positional relationships shown in the accompanying drawings, or are the orientations or positional relationships in which the inventive product is usually placed when used. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0035] In addition, the terms "horizontal", "vertical" and the like do not mean that the components are required to be absolutely horizontal or suspended, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.
[0036] In the description of the present invention, it is also explained that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0037] Example 1
[0038] See also Figure 1~Figure 2This embodiment provides a method for constructing a super-high structure and narrow space equipment pipe network. The construction site is a wine storage warehouse in a certain place. The foundation form of the wine storage warehouse is a pile foundation and an independent foundation. The main structure adopts a frame structure. Please refer to Figure 1 The diameter of a single wine tank 1 is 4m-10m, and the height of the tank is 16m-18m. Explosion-proof walls 2 are set on both sides of the single-row tank 1. The mechanical and electrical equipment and pipe network installation and construction in the storage area do not have the conditions for high-altitude mechanical construction, and the space is narrow. The later high-altitude construction content of the storage area mainly includes the installation of three-band flame detectors and roof rainwater pipes. The three-band flame detectors and rainwater pipes are set on the explosion-proof wall 2 and / or the outer wall 3 along the fire partition in the storage area;
[0039] The following is a detailed description of this application plan, including:
[0040] Step 1: System deepening of the three-band flame detector pipeline and rainwater pipeline;
[0041] Specifically, in one embodiment of the present application, the system deepening in step 1 includes:
[0042] S11. According to the design drawings of the rainwater pipe, the three-band flame detector and the warehouse, construct the rainwater pipe BIM model, the three-band flame detector pipeline BIM model and the warehouse BIM model respectively;
[0043] S12. Perform collision detection on the constructed rainwater pipe BIM model and the three-band flame detector pipeline BIM model. According to the optimization principles of "large pipes first", "separate strong and weak electricity", "pressure gives way to non-pressure", and "electricity avoids heat and water", the collision parts of the rainwater pipe BIM model and the three-band flame detector pipeline BIM model are optimized and reasonably arranged to obtain a comprehensive pipeline BIM model.
[0044] S13. Perform collision detection on the integrated pipeline BIM model and the building BIM model, optimize and reasonably arrange the conflicting and colliding parts of the integrated pipeline BIM model and the building BIM model, complete the system deepening of the three-band flame detector pipeline and the rainwater pipeline, and export the integrated pipeline deepening design drawings;
[0045] Step 2: Develop support and hanger schemes based on the comprehensive pipeline design drawings;
[0046] Specifically, in one embodiment of the present application, after issuing the comprehensive pipeline in-depth design drawings, a support and hanger drawing is drawn based on the comprehensive pipeline in-depth design drawings, and a support and hanger BIM model is constructed according to the drawn support and hanger drawing, and the support and hanger BIM model is integrated and deepened with the comprehensive pipeline model and warehouse BIM model after in-depth design, and then according to the current construction specifications of each profession, according to the calculated pipeline load and direction based on multiple professions or multiple pipelines, according to the pipeline load information, size information, material information, the support and hanger arrangement spacing, form and material are clarified, and a support and hanger in-depth design drawing is issued.
[0047] Step 3. Installation of rainwater pipes and three-band flame detector pipelines: Based on the above-mentioned comprehensive pipeline in-depth design plan and support and hanger in-depth design drawings, combined with the full-floor scaffolding installation drawings during the structural construction period, the rainwater pipes and three-band flame detector piping and cable threading are completed during the structural construction period by using interspersed processes, and the pipeline installation quality and safety are strictly controlled according to requirements during the construction process.
[0048] Specifically, in one embodiment of the present application, in step three, before the rainwater pipe and the three-band flame detector are installed, it also includes:
[0049] S31. According to the comprehensive pipeline detailed drawings, the support and hanger finalization plan, the full-floor scaffolding installation drawings during the structural construction period, and the on-site transportation conditions of the storage area, the pipelines and supports and hangers are reasonably divided into structures, and component decomposition drawings are issued;
[0050] S32. According to the component decomposition drawings, the disassembled pipelines and supports are processed into prefabricated components in the prefabricated parts processing plant. After the prefabricated components are transported to the storage area, according to the construction process and installation planning, the pipelines and supports are prefabricated and assembled on the ground before installation, so as to reduce the work content and construction difficulty of the pipelines and supports in the high-altitude environment and improve the installation efficiency and quality.
[0051] Step 4. Installation of three-band flame detector: After completing the equipment piping and cable threading, clarify the specific location of the three-band flame detector according to the electromechanical equipment construction drawing and the full-floor scaffolding installation drawing during the structural construction. When the full-floor scaffolding is dismantled, the finished product protection is controlled through technical briefing. After the full-floor scaffolding is dismantled to within 1m under the detection equipment, the three-band flame detector is immediately installed and the equipment angle is debugged. After the three-band flame detector is debugged, a bubble protective cover is set outside the three-band flame detector for protection, and a wire is reserved. One end of the wire is connected to the bubble protective cover, and the other end of the wire extends to the ground. During fire debugging, the bubble protective cover can be removed by traction of the wire on the ground to prevent high-altitude operations in the later electromechanical installation.
[0052] Through the above method, this application utilizes in-depth design combined with the full-floor scaffolding installation drawing during the structural construction period, completes equipment pipeline piping and cable threading during the structural construction period through interspersed processes, and completes the installation and commissioning of electromechanical equipment such as three-band flame detectors during the full-floor scaffolding dismantling stage, thereby eliminating high-altitude operations during the later installation of electromechanical equipment.
[0053] Example 2
[0054] The present embodiment provides a method for constructing equipment pipe networks in super-high structures and narrow spaces. On the basis of Embodiment 1, further, the supports and hangers are supports and hangers for metal pipes for building drainage. The supports and hangers for metal pipes for building drainage are metal parts, and their form, material, size, quality and anti-corrosion requirements shall comply with the provisions of the relevant national standards in force; the piers may be cast with concrete having a strength not less than C15; the brackets, hangers and piers shall not be arranged in the cross-section of the interface.
[0055] More specifically, the brackets and hangers of the building drainage metal pipes should be able to bear the loads generated by the vertical pipes or horizontal pipes in the layer, and their supporting strength should be greater than the sum of the self-weight of the vertical pipes and horizontal pipes in the layer and the maximum water weight in the pipes.
[0056] More specifically, the setting and installation of the brackets and hangers of the building drainage metal pipes should meet the requirements of the verticality of the riser, the bending of the horizontal pipe and the designed slope respectively; they should be installed firmly, correctly positioned, in close contact with the pipes, and should not damage the outer surface of the pipes.
[0057] More specifically, the brackets of the vertical pipes and the brackets of the horizontal pipes of the building drainage metal pipes must be fixed or pre-buried on the load-bearing components; the hangers of the horizontal pipes should be fixed on the floor slabs, beams and roof trusses. When the vertical pipes of the building drainage pass through the floor slabs, they should be fixed with pipe clamps. When there is a pipe well, they should be fixed directly on the floor slabs; when there is no pipe well or there is a suspended ceiling, the pipe clamps should be fixed under the floor slabs.
[0058] More specifically, gravity flow drainage risers of building drainage metal pipes should be fixed with brackets on each floor in addition to pipe clamps. The spacing between brackets should not be greater than 3m. When the floor height is less than 4m, one bracket can be installed on each floor. The connection between the bottom of the riser and the end of the discharge pipe should be fixed with piers. The bottom turning point of the flexible interface drainage cast iron riser can be supported by duckfoot elbows, and piers or steel sections can be set for fixing.
[0059] More specifically, for the gravity flow cast iron horizontal pipe of the building drainage metal pipe, each straight pipe must be installed with one or more hangers, and the distance between two hangers shall not be greater than 2m. The connection between the horizontal pipe and each pipe fitting shall be installed with a support hanger, and the distance between the support hanger and the interface section should not be greater than 300mm.
[0060] More specifically, when the length of the gravity flow cast iron horizontal pipe of the building drainage metal pipe is greater than 12m, a diagonal brace to prevent horizontal displacement or a bracket fixed with a pipe clamp must be set every 12m.
[0061] Example 3
[0062] This embodiment provides a method for constructing a super-high structure and narrow space equipment pipe network. On the basis of Embodiment 1, further, the support and hanger is an electrical engineering support and hanger, and the electrical engineering support and hanger includes a bridge, a wire trough support, and a closed busbar support, wherein:
[0063] The bridge frame and cable trough bracket are hoisted along the bottom of the beam or installed against the wall in places without suspended ceilings, and are hoisted inside the suspended ceiling or installed against the wall in places with suspended ceilings. In public places without suspended ceilings, they are combined with structural components and take into account the aesthetics of the building and the convenience of maintenance. They are installed against the wall, column brackets or on the lower chord components of the roof truss.
[0064] When the bridge is installed horizontally, the bracket should be installed at a distance of 1.5m; a fixed bracket should be installed 0.5m away from the bridge elbow at bridge bends, tees, crosses, climbing bends, etc.
[0065] When the bridge is installed vertically, the distance between the brackets shall not exceed 2m. Two, three, four and two brackets shall be respectively set at 0.5m away from the bridge bends, three-way, four-way and climbing bends. The vertically installed brackets shall be fixed on the load-bearing wall of the structure. If installed on the load-bearing brick wall, two 12-diameter galvanized screws with opposite penetration and tension must be set at the bracket installation position, and the roots shall be horizontally connected through L50 galvanized flat steel.
[0066] The bracket must be installed firmly to ensure that it is horizontal and vertical. When installing the bracket on a sloped ground, the bracket must remain parallel to the slope of the ramp.
[0067] The material used for the bracket must be straight, without obvious distortion or rust. The length deviation after cutting must be within 5mm, and there should be no curling or burrs at the cut.
[0068] The bracket welding should be firm, without significant deformation, the weld should be full, the weld length should meet the load requirements, and there should be no cracks, undercuts, pores, dents, leaks, etc. Special cutting machines and bench drills should be used for bracket cutting and drilling. Gas cutting is prohibited.
[0069] All bridge frames are equipped with fixed brackets on the structural columns or beams every 20m. Additional fixed brackets are installed when the distance is less than 20m. The model of the fixed bracket is the same as the model of the bracket cross arm.
[0070] The construction method of ordinary distribution pipe support and hanger refers to 03D301-3 steel conduit wiring installation.
[0071] The direction of the enclosed busbar support and busbar duct shall be determined comprehensively according to the design drawings and the actual project. The principle is that it shall not conflict with large-diameter pipelines and bridges. It shall be laid as far as possible along the shortest straight line, and the distance from the horizontal elevation to the ground shall not be less than 2.5m. The minimum clearance distance from the building surface, other electrical lines and various pipelines shall comply with the current national standards.
[0072] The spacing between the support and hanger brackets for horizontal installation of bus duct is 2m. Additional fixed brackets should be installed at the bend of bus duct and the connection of distribution box, 0.5m away from the bend or distribution box.
[0073] The bus duct is installed vertically, using the standardized spring brackets produced by the bus duct manufacturer, with one spring bracket set on each layer.
[0074] An anti-sway bracket is set in the middle of each floor. The anti-sway bracket is made of angle steel, the bracket is in the form of a door-type lower support, and is fixed using special fixing accessories provided by the manufacturer.
[0075] Example 4
[0076] See also Figure 3 , This embodiment provides a method for constructing equipment pipe networks in super-high structures and narrow spaces. On the basis of Embodiment 1, Embodiment 2, and Embodiment 3, further, an equipment bracket is provided for fixing a three-band flame detector 7 and other electromechanical equipment. The equipment bracket includes a first connecting member 4 fixed or pre-buried on an outer wall 3 and / or an explosion-proof wall 2, a second connecting member 5 fixedly connected to the first connecting member 4, and a third connecting member 6 fixed to the second connecting member 5. The three-band flame detector 7 is fixed on the third connecting member 6. In this embodiment, the first connecting member 4 and the second connecting member 5 are both L50*5 angle steel 300mm, and the third connecting member is a 80*60*10 steel plate;
[0077] Preferably, referring to the drawings, in some embodiments of the present application, a pipe clamp is fixed on the second connecting member for fixing the piping of the three-stage flame detector.
[0078] Example 5
[0079] See also Figure 4~Figure 5 This embodiment provides a method for constructing a pipe network for equipment in an ultra-high structure and a narrow space. On the basis of Embodiment 1, Embodiment 2, and Embodiment 3, a pipe bracket is further provided for fixing a rainwater pipe 8 or other water supply and drainage pipes or fire protection system pipes, including a first connecting member 4 fixed or pre-buried on an exterior wall 3 and / or an explosion-proof wall 2, and a second connecting member 5 fixedly connected to the first connecting member 4. A reinforcing rib 9 is provided between the first connecting member 4 and the second connecting member 5, and a pipe clamp a10 is provided on the second connecting member for cooperating with a fixed rainwater horizontal pipe or vertical pipe.
[0080] Example 6
[0081] See also Figure 6~Figure 7 This embodiment provides a method for constructing a pipeline network for super-high structures and narrow space equipment. On the basis of Embodiment 4 and Embodiment 5, a pipeline integrated support and hanger is further provided, including: a first connecting piece 4, one end of which is pre-buried or fixed to the exterior wall or explosion-proof wall by expansion bolts; a second connecting piece 5, which is perpendicular to the first connection, and one end of the second connecting piece 5 is welded or bolted to the first connecting piece; a third connecting piece 6, which is welded or bolted to the end of the second connecting piece 5 away from the first connecting piece; wherein a reinforcing rib 9 is provided between the first connecting piece 4 and the second connecting piece 5, and the second connecting piece 5 is respectively provided with a pipe clamp a10 and a pipe clamp b11 that cooperate with the piping of the rainwater pipe 8 and the three-band flame detector 7, and the three-band flame detector 7 is fixed on the third connecting piece 6.
[0082] In the present application, after the pipelines and professional pipelines of the electromechanical equipment are systematically deepened, combined with the scaffolding installation diagram during the structural construction, the piping and cable threading of professional pipelines and electromechanical equipment are completed through interspersed processes during the structural construction to avoid high-altitude operations in the later stage. In this embodiment, the electromechanical equipment (three-band flame detector 7), equipment piping, and professional pipelines (rainwater pipelines 8) are concentrated on the same working surface or concentrated on the same node for construction through an integrated bracket, which is more convenient for construction; moreover, the installation and commissioning of the electromechanical equipment of the present application are carried out during the dismantling stage of the full-hall scaffolding. Although this can eliminate the high-altitude operations in the later stage, it is well known to those skilled in the art that the dismantling of the full-hall scaffolding in one area is generally completed in two days at a time, and the long dismantling time has a greater safety hazard. In this embodiment, the electromechanical equipment, equipment piping and professional pipelines are all concentrated on the same working surface, and the installation and commissioning of the electromechanical equipment can be completed faster during the scaffolding dismantling stage, which is safer.
[0083] The above description is only a preferred embodiment of the invention and is not intended to limit the technical solution of the invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the technical solution of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for constructing equipment pipe networks in ultra-high structures and narrow spaces, used for the installation of electromechanical equipment and pipe networks, characterized in that: Here are the steps: S10: System deepening of the pipelines and specialized pipelines of the electromechanical equipment to be installed, the electromechanical equipment including the three-band flame detector, and the specialized pipelines including the rainwater pipeline; S20: Based on the mechanical and electrical equipment pipelines and professional pipelines after the system deepening in S10, combined with the scaffolding installation drawings during the structural construction, the professional pipelines and mechanical and electrical equipment piping and cable threading are completed through interleaving of processes during the structural construction; S30: Based on the results of the mechanical and electrical equipment pipeline system deepening and combined with the scaffolding installation drawings during the structural construction, when the scaffolding is removed to 0.5-1.5m below the mechanical and electrical equipment, the mechanical and electrical equipment is immediately installed and the equipment angle is adjusted to prevent the high-altitude work content of the later mechanical and electrical installation; The system deepening of electromechanical equipment pipelines and professional pipelines in S10 includes the following steps: S11: According to the design drawings of electromechanical equipment pipelines, professional pipelines, and civil engineering, construct equipment pipeline BIM models, pipeline BIM models, and building BIM models respectively; S12: Integrate the equipment pipeline BIM model and the pipeline BIM model constructed in S11, and optimize and arrange the conflicting and colliding parts in the pipeline BIM model and the pipeline BIM model to obtain a comprehensive pipeline BIM model; S13: Integrate the integrated pipeline BIM model with the building BIM model, optimize and arrange the conflicting and colliding parts of the integrated pipeline BIM model and the building BIM model, obtain the integrated pipeline model after in-depth design, and issue in-depth design drawings of the integrated pipeline; After the comprehensive pipeline detailed design drawings are issued, the support and hanger details are drawn based on the comprehensive pipeline detailed design drawings; After drawing the support and hanger drawing, build the support and hanger BIM model according to the drawn support and hanger drawing, integrate and deepen the support and hanger BIM model with the comprehensive pipeline model and building BIM model after in-depth design, clarify the support and hanger shaping plan, and issue the support and hanger in-depth design drawings; After the detailed design drawings of the supports and hangers are issued, the comprehensive pipelines and supports and hangers are reasonably split according to the main structure construction plan, the detailed design drawings of the integrated pipelines, the detailed design drawings of the supports and hangers, the installation drawings of the full-floor scaffolding during the structural construction, and the transportation conditions of the construction site, and the component decomposition drawings are issued; According to the component decomposition drawings, the decomposed integrated pipeline pipes and supports and hangers are pre-processed in the prefabricated parts processing plant; according to the construction procedures and construction and installation planning, the pipeline pipes and supports and hangers are prefabricated and assembled on the ground before installation.
2. The method for constructing a super-high structure and narrow space equipment pipe network according to claim 1, characterized in that: The support and hanger is a comprehensive pipeline support and hanger.
3. The method for constructing a super-high structure and narrow space equipment pipe network according to claim 2, characterized in that: In step S30, after the electromechanical equipment is debugged, a bubble protective cover is set outside the electromechanical equipment for protection, and a wire is reserved, one end of the wire is connected to the bubble protective cover, and the other end of the wire extends to the ground.
4. The method for constructing a super-high structure and narrow space equipment pipe network according to claim 3, characterized in that: During firefighting commissioning, the bubble protective cover can be removed by pulling with wires on the ground, thus eliminating the need for high-altitude work during subsequent electromechanical installation.
5. The method for constructing a super-high structure and narrow space equipment pipe network according to claim 4, characterized in that: The protection of the finished products is controlled through technical briefing when the scaffolding is dismantled.