Sliding conductor rail device and its construction method applicable to large-span gantry cranes
By using a spatial cable structure system consisting of pylons, horizontal cables, wind cables, and back cables, combined with the dynamic connection of hubs, brackets, telescopic rods, and rollers, the problems of long construction cycle, high cost, and difficulty in adjusting the alignment of the power supply sliding contact line for large-span gantry cranes have been solved, achieving lightweighting and improved stability.
Patent Information
- Application Number
- CN202311505071.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-13
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-11-13
AI Technical Summary
Traditional column-beam structure has problems such as long construction period, high cost and difficulty in adjusting the alignment when installing power supply sliding contact line for large-span gantry cranes. It also has high requirements for the control of the beam centerline and the deviation of the column axis.
A spatial cable structure system consisting of cable towers, horizontal cables, wind cables, and back cables is adopted. Combined with the dynamic connection between the hub, bracket, telescopic rod, and rollers, the stress state is judged by monitoring the displacement of the telescopic rod, thereby achieving lightweighting and improved stability of the sliding contact line.
It greatly saves material usage, shortens the installation cycle, improves the flexibility and stability of linear control, and reduces construction difficulty and cost.
Smart Images

Figure CN117566592B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of sliding conductor rail installation, and in particular to a sliding conductor rail device and its construction method suitable for large-span gantry cranes. Background Technology
[0002] Gantry cranes are a type of portal crane with features such as high site utilization, large operating range, wide adaptability, and strong versatility. They are widely used in loading and unloading at freight yards and material yards.
[0003] Common power supply methods for gantry cranes include cable reel power supply, single-stage combined sliding conductor power supply, and overhead power supply. Among these, overhead power supply is required when the gantry crane crosses roads or needs to transport large loads. Overhead power supply typically uses concrete poles or steel pipes as supports, with the sliding conductor rails elevated and arranged using brackets. The spacing between the supports is generally 2-3 meters. When the distance to be crossed exceeds 6 meters, crossbeams must be added between the supports to ensure the smoothness of the sliding conductor rail.
[0004] However, as the distances that need to be crossed increase further, such as when crossing extremely long spaces, the traditional method of fixing the conductor rail requires the use of columns and beams with larger cross sections, resulting in problems such as high material consumption, long construction periods, and high construction costs. In addition, since the conductor rail is fixed under the beam, the adjustment range for adjusting the installation alignment of the conductor rail by relying solely on hangers and suspension clamps is small, and the requirements for controlling the center line of the beam and positioning the deviation of the column axis are high. Summary of the Invention
[0005] This invention provides a sliding contact line device and its construction method suitable for large-span gantry cranes, which solves the problems of long construction period, high construction cost and great difficulty in adjusting the alignment when installing the power supply sliding contact line of large-span gantry cranes using the traditional column-beam structure.
[0006] To solve the above-mentioned technical problems, the technical solution adopted by the present invention is: a sliding contact line device suitable for large-span gantry cranes, including at least two cable towers provided on one side of the gantry crane legs, at least two horizontal cables arranged parallel to the gantry crane travel track between the two cable towers, multiple crossbars provided along the length of the horizontal cables, multiple sliding contact lines arranged parallel to the horizontal cables on the crossbars, and a cable collector provided, with each sliding contact of the cable collector sliding within each sliding contact line, and a cable collector bracket provided on one side of the gantry crane legs, with the cable collector connected to the cable collector bracket.
[0007] In the preferred embodiment, the horizontal cable is further provided with guy cables on both the upper and lower sides, which are connected to the horizontal cable, and the two ends of the guy cables are connected to each cable tower respectively.
[0008] In the preferred embodiment, the tower is provided with a transverse upper crossbeam, a middle crossbeam, and a lower crossbeam. Each of the upper, middle, and lower crossbeams is provided with a rotatable tensioner. Anchor bolts are provided at both ends of the horizontal cable and the guy cable, and each anchor bolt is threadedly connected to each tensioner.
[0009] In the preferred embodiment, a back cable is provided on the side of the tower away from the horizontal cable, and the lower end of the back cable is connected to the anchor.
[0010] In the preferred embodiment, the crossbar is provided with lugs at both ends, and cable clamps are provided on both sides of both ends of the crossbar. The cable clamps are connected to the horizontal cable, and the lugs are connected to the guy cable.
[0011] In the preferred embodiment, the hub bracket is provided with an upper support plate, and a connecting frame is provided between the upper support plate and the hub. The connecting frame is provided with a vertical plate, which is arranged perpendicular to the sliding contact line. The upper support plate is provided with at least two telescopic rods that can be adjusted vertically. One end of the telescopic rod is provided with a connecting frame, and the connecting frame is provided with a rotatable roller. The vertical plate is provided with an arc-shaped groove, and the roller is engaged in the arc-shaped groove and rolls.
[0012] In the preferred embodiment, a damping sleeve is provided inside the upper support plate, and a sliding rod is provided in the middle of the telescopic rod. The sliding rod slides inside the damping sleeve, and stop plates are provided at both ends of the sliding rod. Springs are respectively fitted on both sides of the upper support plate on the telescopic rod, and the two ends of the springs abut against the stop plates and the upper support plate respectively.
[0013] In a preferred embodiment, an extension rod parallel to the telescopic rod is provided on one side of the telescopic rod, a sliding seat is fitted on the extension rod, a contact assembly is provided on one side of the sliding seat, a screw part is provided at the end of the telescopic rod away from the connecting frame, multiple turns of resistance wire are wound along the thread of the screw part, an insulating layer is provided on the outside of the resistance wire, and a leakage core is provided on the side of each turn of the resistance wire facing the contact assembly. The leakage core is used to contact the end of the contact assembly. A resistance meter is also provided, and one end of the resistance wire and the contact assembly are electrically connected to the resistance meter.
[0014] Construction methods including conductor rails and fixing structures: S1. Carry out column foundation and anchorage construction, and fabricate the steel structure of the cable tower; S2. The tower and column base are connected and fixed by high-strength bolts. The back cable is installed and 1 / 3 to 1 / 2 of the design cable force is applied to initially counter-tension the tower to avoid tower anchorage failure due to excessive unbalanced load on both sides when tensioning the horizontal cable. S3. Install a pair of horizontal cables and tension them to the design cable force; S4. Anchor the suspension clamp to the lower part of the crossbar in advance, place the crossbars at intervals on the horizontal cable, and fix the crossbars on the horizontal cable with the cable clamp; S5. Install the main cable of the upper cable and connect the main cable to the lug at the end of the crossbar with the secondary cable. Secure the connection with a cable buckle. After connecting the anchor rod to the end of the main cable, anchor it to the upper crossbeam and tension it to the design cable force. S6. Install the main cable of the lower cable wind cable, and connect the main cable wind cable to the end lug of the crossbar with the secondary cable wind cable. Secure the connection with a lock. After the end of the main cable wind cable is connected to the anchor rod, it is anchored to the lower crossbeam and tensioned to the design cable force. S7. Use the aerial work platform to install the conductor rail into the suspension clamp. After the conductor rail is suspended, install the end tensioner to tension the conductor rail. S8. Using the downward or upward deformation of the middle of the sliding conductor line as the control amount, adjust the cable tension of the guy cable, horizontal cable, and back cable until the maximum deformation of the middle of the sliding conductor line is less than 10cm. S9. During operation, the deflection deformation of the middle part of the conductor rail shall be monitored regularly. When the deflection or arching exceeds 10cm, the cable force shall be finely adjusted to meet the limit requirements.
[0015] The beneficial effects of this invention are as follows: Based on the cable-bearing method, the fixing device for large-span applications of sliding conductor lines is made extremely lightweight. Compared with the traditional "column + beam" sliding conductor line fixing structure, under the same span, the method proposed in this patent requires similar amounts of column foundation excavation and concrete usage as the traditional method. However, due to the reduction in the number of columns and the elimination of beams, the steel usage is only 35% to 55% of the traditional method, greatly saving material usage. The number of columns is reduced, and the cable structure construction is fast, effectively shortening the installation cycle. A stable spatial cable structure system is formed by horizontal cables, upper and lower guy cables, and back cables. Furthermore, the cable force can be easily adjusted, which facilitates the control of the sliding conductor line's shape. The cable collector and cable collector bracket are dynamically connected using a spring telescopic rod and roller structure, which improves the problems of weak cable structure rigidity and significant thermal expansion and contraction. Moreover, the stress state of the horizontal cable can be determined by monitoring the displacement of multiple telescopic rods. Attached Figure Description
[0016] The present invention will be further described below with reference to the accompanying drawings and embodiments.
[0017] Figure 1 This is a front view of the present invention.
[0018] Figure 2 This is a top view of the present invention.
[0019] Figure 3 This is a side view of the present invention.
[0020] Figure 4 This is a top view of the crossbar of the present invention.
[0021] Figure 5 This is a front view of the crossbar of the present invention.
[0022] Figure 6 This is an enlarged view of the anchor bolt structure of the present invention.
[0023] Figure 7 This is a schematic diagram of the dynamic connection structure of the hub of the present invention.
[0024] Figure 8 This is a structural diagram of the connecting frame of the present invention.
[0025] Figure 9 This is a diagram showing the torsion state of the crossbar of the present invention.
[0026] Figure 10 This is a diagram showing the downward movement of the crossbar according to the present invention.
[0027] Figure 11 This is a schematic diagram of the cable state monitoring structure of the present invention.
[0028] Figure 12 This is a contact diagram of the contact component and the resistance wire of the present invention.
[0029] Figure 13 This is a diagram of a traditional column-beam type sliding conductor rail fixing structure.
[0030] In the diagram: 1. Cable tower; 101. Upper crossbeam; 102. Middle crossbeam; 103. Lower crossbeam; 104. Back cable; 2. Horizontal cable; 201. Cable clamp; 202. Guy cable; 203. Anchor bolt; 204. Tensioner; 3. Crossbar; 301. Hanging lug; 4. Sliding conductor line; 401. Hanging wire clamp; 5. Gantry crane outrigger; 501. Gantry crane traveling track; 6. Hub bracket; 601. Upper support plate; 602. Damping sleeve; 7. Hub; 8. Connecting frame; 801. Vertical plate; 802. Arc-shaped slide groove; 9. Telescopic rod; 901. Roller; 902. Connecting frame; 903. Telescopic rod connecting column; 904. Stop plate; 905. Screw part; 906. Outrigger; 10. Sliding seat; 1001. Contact assembly; 11. Resistance wire; 12. Insulation layer; 1202. Leaking core part; 13. Resistance meter. Detailed Implementation
[0031] like Figure 1-13 In this invention, a sliding contact line device suitable for a large-span gantry crane is provided, including at least two pylons 1 on one side of the gantry crane outrigger 5, at least two horizontal cables 2 arranged parallel to the gantry crane travel track 501 between the two pylons 1, a plurality of crossbars 3 along the length of the horizontal cables 2, a plurality of sliding contact lines 4 arranged parallel to the horizontal cables 2 on the crossbars 3, and a cable collector 7, each sliding contact of the cable collector 7 sliding within each sliding contact line 4, and a cable collector bracket 6 on one side of the gantry crane outrigger 5, the cable collector 7 being connected to the cable collector bracket 6.
[0032] The horizontal bar 3 is installed perpendicular to the horizontal cable 2. The horizontal cable 2 is provided with multiple suspension clamps 401 along its length. Each sliding contact line 4 is clamped in each suspension clamp 401. The horizontal cable 2, the sliding contact line 4 and the gantry crane travel track 501 are parallel. When the gantry crane outrigger 5 travels along the gantry crane travel track 501, it drives the hub 7 to move through the hub bracket 6. The sliding contact of the hub 7 is always in contact with the sliding contact line 4 and draws power in real time.
[0033] In the preferred embodiment, the horizontal cable 2 is further provided with guy cables 202 connected to the horizontal cable 2 on both the upper and lower sides, and the two ends of the guy cables 202 are respectively connected to each cable tower 1.
[0034] In the preferred embodiment, the tower 1 is provided with a transverse upper crossbeam 101, a middle crossbeam 102 and a lower crossbeam 103. The upper crossbeam 101, the middle crossbeam 102 and the lower crossbeam 103 are respectively provided with rotatable tensioners 204. The horizontal cable 2 and the guy cable 202 are respectively provided with anchor rods 203 at both ends. Each anchor rod 203 is threadedly connected to each tensioner 204.
[0035] In the preferred embodiment, a back cable 104 is provided on the side of the tower 1 away from the horizontal cable 2, and the lower end of the back cable 104 is connected to the anchor.
[0036] The lower end of the pylon 1 is provided with a column base. The pylon 1 is installed on the sides of both ends of the gantry crane travel track 501. The two ends of the horizontal cable 2 are installed on the middle crossbeam 102 through the anchor rods 203 and tensioned so that the horizontal cable 2 is as parallel as possible to the gantry crane travel track 501. In order to improve the stress structure, the horizontal cable 2 is suspended and tensioned through the guy cable 202.
[0037] The upper end of the back cable 104 is equipped with an anchor rod and is threadedly connected to the tensioner on the cable tower 1. The tensioner can be a threaded sleeve, which can tighten each cable when rotated.
[0038] In the preferred embodiment, the crossbar 3 is provided with lugs 301 at both ends, and cable clips 201 are provided on both sides of the crossbar 3. The cable clips 201 are connected to the horizontal cable 2, and the lugs 301 are connected to the wind cable 202.
[0039] The crossbar 3 is the core connecting component. It is connected and fixed to the horizontal cable 2 via the cable clamp 201, connected and fixed to the wind cable 202 via the hanging lug 301, and connected and fixed to the sliding contact line 4 via the suspension clamp 401.
[0040] Since horizontal cables 2 are generally made of steel cables, their requirements for ground support are less than those for steel frames, but their rigidity is weaker. Compared to the larger mass of a steel frame, the thermal expansion and contraction of steel cables are also more pronounced. However, the hub bracket 6 is a steel frame structure, so the distance between the crossbar 3 and the hub bracket 6 is more prone to change. Furthermore, when using double horizontal cables off the shore and at both ends of the crossbar 3, there is actually a positional deviation in the direction of the two horizontal cables 2. Therefore, the crossbar 3 also experiences torsion in certain lengths of the horizontal cables 2. In summary, there may be problems with poor contact or excessive contact force causing severe wear between the sliding contact head and the sliding contact line 4 of the hub 7.
[0041] In the preferred embodiment, the hub bracket 6 is provided with an upper support plate 601, and a connecting frame 8 is provided between the upper support plate 601 and the hub 7. The connecting frame 8 is provided with a vertical plate 801, which is arranged perpendicular to the sliding contact line 4. The upper support plate 601 is provided with at least two telescopic rods 9 that are adjustable in height. One end of the telescopic rod 9 is provided with a connecting frame 902, and the connecting frame 902 is provided with a rotatable roller 901. The vertical plate 801 is provided with an arc-shaped sliding groove 802, and the roller 901 is engaged in the arc-shaped sliding groove 802 and rolls.
[0042] The lower end of the connecting frame 902 is provided with multiple telescopic rod connecting columns 903 arranged side by side. Each telescopic rod connecting column 903 can be equipped with a telescopic rod 9, thereby improving the structural strength.
[0043] In the preferred embodiment, a damping sleeve 602 is provided inside the upper support plate 601, and a sliding rod part is provided in the middle of the telescopic rod 9. The sliding rod part slides inside the damping sleeve 602. Stop plates 904 are provided at both ends of the sliding rod part. Springs 905 are respectively sleeved on both sides of the upper support plate 601 on the telescopic rod 9, and the two ends of the springs 905 abut against the stop plates 904 and the upper support plate 601 respectively.
[0044] Spring 905 maintains the height position of telescopic rod 9 and bears the weight of connecting frame 8, reducing the vertical tension of sliding contact head on sliding contact line 4.
[0045] The damping sleeve 602 has appropriate friction with the outer wall of the telescopic rod 9, ensuring that the telescopic rod 9 can slide, but the sliding will not be too fast, thus reducing oscillation.
[0046] In a preferred embodiment, an extension rod 10 parallel to the telescopic rod 9 is provided on one side of the telescopic rod 9. A sliding seat 1001 is fitted on the extension rod 10. A contact assembly 11 is provided on one side of the sliding seat 1001. A screw part 906 is provided at the end of the telescopic rod 9 away from the connecting frame 8. Multiple turns of resistance wire 12 are wound along the thread of the screw part 906. An insulating layer 1201 is provided on the outside of the resistance wire 12. Each turn of the resistance wire 12 has a leakage core on the side facing the contact assembly 11. The leakage core is used to contact the end of the contact assembly 11. A resistance meter 13 is also provided. One end of the resistance wire 12 and the contact assembly 11 are electrically connected to the resistance meter 13.
[0047] The sliding seat 1001 can be threadedly connected to the extension rod 10. A set screw is provided in the sliding seat 1001, which can press against the outer wall of the extension rod 10, and can adjust and lock the initial height position of the sliding seat 1001.
[0048] The top of the insulating layer 1201 facing the contact assembly 11 is peeled off, and the core portion 1202 of each turn forms a straight conductive area. The tip of the contact assembly 11 contacts the conductive area, and as the telescopic rod 9 moves up and down, it slides relative to the conductive area to change the position of the contact resistance wire 12.
[0049] The contact component 11 has a conductive head at its tip, which leads out a terminal through a wire and connects to one pole of the resistance meter 13. One end of the resistance wire 12 is insulated, and the other end is connected to the other pole of the resistance meter 13.
[0050] The resistance meter 13 is an existing resistance monitoring instrument, such as a ohmmeter or a multimeter. Since the sliding seat 1001 is fixed, the telescopic rod 9 slides up and down. The conductive head of the contact component 11 is in different positions on the resistance wire 12. According to the resistance value monitored by the resistance meter 13, the up and down position of the telescopic rod 9 can be measured, thereby monitoring the state of the horizontal cable 2.
[0051] If the two telescopic poles 9 are found to be at different heights, it indicates that the crossbar 3 has an angle relative to the horizontal plane. It can then be inferred that in the absence of wind, the two horizontal cables 2 are likely to twist relative to the reference position on the same length section. If the two telescopic poles 9 are found to be descending at the same time, it indicates that the two horizontal cables 2 are below the theoretical value on that length section, and the tension is reduced.
[0052] By remotely monitoring the values of the resistance meter 13, analyzing the state of the horizontal cable 2 and its position relative to the upper support plate 601, potential hazards can be detected and repaired in a timely manner.
[0053] Example 2: A fixed structure for the sliding contact line of a large-span gantry crane is mainly composed of components such as cable towers, column bases, crossbars and auxiliary facilities, and tensioning systems.
[0054] The pylon is the main vertical load-bearing structure supporting the elevated system, and consists of the pylon, upper crossbeam, middle crossbeam, and lower crossbeam.
[0055] The pylon is a steel pylon with a circular or rectangular cross-section, and its height is determined by the required height of the conductor rail. When the span is large, the pylon can be filled with concrete to form a steel-concrete composite structure to improve its bending resistance.
[0056] The multiple cable towers are interconnected by three crossbeams: an upper crossbeam, a middle crossbeam, and a lower crossbeam. These crossbeams serve two purposes: they connect the towers into a unified structure for shared load-bearing and also act as anchorages for the tensioning system. The upper crossbeam is used for anchoring the upper guy cables, the middle crossbeam for anchoring the horizontal cables, tensioners, and back cables, and the lower crossbeam for anchoring the lower guy cables.
[0057] The column base is an enlarged reinforced concrete column base to distribute the vertical forces and bending moments transmitted by the tower. Protruding bolts are pre-installed on the top surface of the column base, and a flange is provided at the bottom of the tower; the two are connected quickly and reliably using high-strength bolts.
[0058] Crossbars and ancillary facilities are the main carriers supporting the conductor rail, and are arranged at equal intervals between two or more towers, with a spacing of 2-3 meters. Ancillary facilities include cable clamps, lugs, and suspension clamps.
[0059] The crossbars are made of metal tubing, ranging from 0.4 to 1.0 meters in length. Each crossbar has a cable clamp and a lug at its end for stability. The cable clamps secure the crossbar to the horizontal cables, preventing slippage and controlling the distance between adjacent crossbars. The lugs connect the upper and lower guy cables to the crossbars, improving horizontal and vertical stiffness and preventing significant swaying under wind loads.
[0060] The suspension clamps are devices for securing the sliding contact line, and are arranged in three or four rows at equal intervals at the bottom of the crossbar. The suspension clamps are made of fiberglass to ensure insulation from the sliding contact line. The clamps are connected via threaded holes at the bottom of the crossbar and tightened with nuts to prevent loosening.
[0061] The gantry crane supports the hub via a hub bracket. The hub is fixed in the sliding contact line groove. The gantry crane can achieve sliding power supply by moving on the track.
[0062] The tensioning system consists of horizontal cables, back cables, guy cables, anchor bolts, anchor seats, and tensioners. The tensioning system is used to tighten the conductor rail and to adjust its shape, ensuring it remains straight.
[0063] The horizontal cables are made of steel wire rope, and there are two of them. They are used to string together the spaced crossbars. After being connected to the anchor rods, they are anchored to the middle crossbeam. The tension of the horizontal cables can be adjusted by the nuts on the anchor rods.
[0064] Backstays are used to balance the lateral forces on the tower, preventing large bending moments at the tower root that could lead to anchorage failure. One end of the backstay is connected to an anchorage, and the other end is anchored to the central crossbeam via an anchor bolt. The anchorage provides pull-out resistance and can be made of concrete, pull-out piles, rock anchors, or other methods, with the appropriate anchorage type selected based on geological conditions. The backstays are only anchored to the central crossbeam because the tension of the horizontal cables is much greater than that of the guy cables, making it the primary force to be balanced. This also avoids the problem of distributing and adjusting the force among multiple backstays, reducing construction difficulty.
[0065] The guy cables are made of steel wire rope and consist of upper and lower guy cables arranged symmetrically for ease of rope cutting, installation, and construction control. The guy cables are further divided into main guy cables and secondary guy cables. The main guy cables are parabolically and symmetrically arranged on both sides of the horizontal cables. The main guy cables and the horizontal cables are connected by secondary guy cables, which are arranged in a zigzag pattern. The upper guy cables are anchored to the upper crossbeam via end anchor bolts, and the lower guy cables are anchored to the lower crossbeam via anchor bolts. The plane formed by the guy cables is inclined, ensuring that the force exerted on the crossbeam has both horizontal and vertical components, preventing horizontal and vertical swaying of the crossbeam.
[0066] Construction methods including conductor rails and fixing structures: S1. Carry out column foundation and anchorage construction, and fabricate the steel structure of the cable tower; S2. The tower and column base are connected and fixed by high-strength bolts. The back cable is installed and 1 / 3 to 1 / 2 of the design cable force is applied to initially counter-tension the tower to avoid tower anchorage failure due to excessive unbalanced load on both sides when tensioning the horizontal cable. S3. Install a pair of horizontal cables and tension them to the design cable force; S4. Anchor the suspension clamp to the lower part of the crossbar in advance, place the crossbars at intervals on the horizontal cable, and fix the crossbars on the horizontal cable with the cable clamp; S5. Install the main cable of the upper cable and connect the main cable to the lug at the end of the crossbar with the secondary cable. Secure the connection with a cable buckle. After connecting the anchor rod to the end of the main cable, anchor it to the upper crossbeam and tension it to the design cable force. S6. Install the main cable of the lower cable wind cable, and connect the main cable wind cable to the end lug of the crossbar with the secondary cable wind cable. Secure the connection with a lock. After the end of the main cable wind cable is connected to the anchor rod, it is anchored to the lower crossbeam and tensioned to the design cable force. S7. Use the aerial work platform to install the conductor rail into the suspension clamp. After the conductor rail is suspended, install the end tensioner to tension the conductor rail. S8. Using the downward or upward deformation of the middle of the sliding conductor line as the control amount, adjust the cable tension of the guy cable, horizontal cable, and back cable until the maximum deformation of the middle of the sliding conductor line is less than 10cm. S9. During operation, the deflection deformation of the middle part of the conductor rail shall be monitored regularly. When the deflection or arching exceeds 10cm, the cable force shall be finely adjusted to meet the limit requirements.
[0067] The above embodiments are merely preferred technical solutions of the present invention and should not be considered as limitations on the present invention. The scope of protection of the present invention should be limited to the technical solutions described in the claims, including equivalent substitutions of the technical features described in the claims. That is, equivalent substitutions and improvements within this scope are also within the scope of protection of the present invention.
Claims
1. A sliding contact line device suitable for large-span gantry cranes, characterized in that: It includes at least two cable towers (1) located on one side of the gantry crane outrigger (5), and at least two horizontal cables (2) arranged parallel to the gantry crane travel track (501) between the two cable towers (1). Multiple crossbars (3) are provided along the length of the horizontal cables (2), and multiple sliding contact lines (4) arranged parallel to the horizontal cables (2) are provided on the crossbars (3). A cable collector (7) is also provided, and each sliding contact of the cable collector (7) slides within each sliding contact line (4). A cable collector bracket (6) is provided on one side of the gantry crane outrigger (5), and the cable collector (7) is connected to the cable collector bracket (6). The horizontal cable (2) is also provided with guy cables (202) on the upper and lower sides, which are connected to the horizontal cable (2). The two ends of the guy cables (202) are connected to each tower (1); The crossbar (3) is provided with lugs (301) at both ends, and cable clips (201) are also provided on both sides of both ends of the crossbar (3). The cable clips (201) are connected to the horizontal cable (2), and the lugs (301) are connected to the guy cable (202). The hub bracket (6) is provided with an upper support plate (601). A connecting frame (8) is provided between the upper support plate (601) and the hub (7). The connecting frame (8) is provided with a vertical plate (801). The vertical plate (801) is arranged perpendicular to the sliding contact line (4). The upper support plate (601) is provided with at least two telescopic rods (9) that can be adjusted up and down. One end of the telescopic rod (9) is provided with a connecting frame (902). The connecting frame (902) is provided with a rotatable roller (901). The vertical plate (801) is provided with an arc-shaped groove (802). The roller (901) is stuck in the arc-shaped groove (802) and rolls.
2. The sliding contact line device for large-span gantry cranes according to claim 1, characterized in that: The tower (1) is provided with a transverse upper crossbeam (101), a middle crossbeam (102) and a lower crossbeam (103). The upper crossbeam (101), the middle crossbeam (102) and the lower crossbeam (103) are respectively provided with rotatable tensioners (204). The horizontal cable (2) and the guy cable (202) are respectively provided with anchor rods (203) at both ends. Each anchor rod (203) is threadedly connected to each tensioner (204).
3. The sliding contact line device for large-span gantry cranes according to claim 2, characterized in that: The tower (1) is provided with a back cable (104) on the side away from the horizontal cable (2), and the lower end of the back cable (104) is connected to the anchor.
4. The sliding contact line device for large-span gantry cranes according to claim 1, characterized in that: The upper support plate (601) is provided with a damping sleeve (602), and the telescopic rod (9) is provided with a sliding rod in the middle. The sliding rod slides in the damping sleeve (602). The two ends of the sliding rod are provided with stop plates (904). The upper support plate (601) on the telescopic rod (9) is provided with springs (905) on both sides. The two ends of the springs (905) abut against the stop plates (904) and the upper support plate (601) respectively.
5. The sliding contact line device for large-span gantry cranes according to claim 4, characterized in that: A telescopic rod (9) is provided on one side with an extension rod (10) parallel to the telescopic rod (9). A sliding seat (1001) is fitted on the extension rod (10). A contact assembly (11) is provided on one side of the sliding seat (1001). A screw part (906) is provided at one end of the telescopic rod (9) away from the connecting frame (8). Multiple turns of resistance wire (12) are wound along the thread of the screw part (906). An insulating layer (1201) is provided on the outside of the resistance wire (12). Each turn of the resistance wire (12) is provided with a leakage core on the side facing the contact assembly (11). The leakage core is used to contact the end of the contact assembly (11). A resistance meter (13) is also provided. One end of the resistance wire (12) and the contact assembly (11) are electrically connected to the resistance meter (13).
6. The construction method for the sliding contact line device applicable to large-span gantry cranes according to claim 3, characterized in that: S1. Carry out column foundation and anchorage construction, and process the steel structure of the pylon (1). S2. The tower (1) is connected and fixed to the column base, and the back cable (104) is installed to initially reverse the tower (1). S3. Install a pair of horizontal cables (2) and tension them to the design cable force; S4. Anchor the suspension clamp to the lower part of the crossbar (3) in advance, place the crossbar (3) at intervals on the horizontal cable (2), and fix the crossbar (3) on the horizontal cable (2); S5. Install the upper guy cable and connect it to the end of the crossbar (3), and tension it to the design cable force; S6. Install the main cable (202) of the lower cable wind cable and connect it to the end of the crossbar (3), and tension it to the design cable force; S7. Install the sliding contact line (4). After the sliding contact line (4) is suspended, tension the sliding contact line (4). S8. Using the downward or upward deformation of the middle part of the sliding contact line (4) as the control quantity, adjust the cable force of the guy cable (202), horizontal cable (2), and back cable (104); S9. During operation, the flexural deformation of the sliding contact line (4) shall be monitored regularly and the cable force shall be finely adjusted to meet the limiting requirements.