A non-capping assembled bridge pier and construction method for conventional areas
By adopting the prefabricated bridge pier method without caps in the bridge project and using the steel-concrete connecting components of the prefabricated pier columns and cast-in-place pile foundations, the problem of difficult construction under conventional regional geological conditions has been solved, and the rapid docking and assembly of the bridge piers has been achieved. Efficient construction adapts to the geological and topographical conditions of conventional areas, improving the economic benefits and seismic performance of the project.
Patent Information
- Application Number
- CN202410102400.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-25
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-01-25
AI Technical Summary
In existing bridge projects, it is difficult to construct prefabricated piers in conventional areas, especially when the geological conditions are unstable. Prefabricated pile foundations are difficult to adapt to, and the setting of cast-in-place caps is inconsistent with the concept of prefabricated bridges, resulting in low construction efficiency and economical Poor efficiency.
The prefabricated pier method is adopted, and the first steel-concrete connection component between the prefabricated pier column and the cast-in-situ pile foundation is used, including the first butt barrel, the annular butt plate and the external cast barrel to form ultra-high performance concrete The structural layer is grouted to achieve rapid docking and assembly of cap beams, prefabricated piers and cast-in-place pile foundations.
It realizes the rapid docking and assembly of bridge piers under the cap-less structure, has the advantages of strong nodes and weak components, adapts to the geological and terrain conditions of conventional areas, reduces the difficulty of construction, and improves the economic benefits and seismic performance of the project.
Smart Images

Figure CN117646384B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of bridge engineering, and in particular to a prefabricated bridge pier without a cap for use in conventional areas and a construction method thereof. Background Art
[0002] The prefabrication and assembly of existing bridges began with the superstructure, forming a relatively complete standardization system for the design and construction of prefabricated superstructures; the prefabrication and assembly of the lower supporting structure started relatively late, with a relatively low assembly rate, mainly including prefabricated pipe piles, prefabricated piers, prefabricated cap beams, and a combination of one or more of them. The prefabrication and assembly of the lower supporting structure of the bridge is conducive to improving construction quality, accelerating construction progress, and reducing environmental impact.
[0003] At present, there are two main forms of conventional prefabricated bridge piers. One is a fully prefabricated pier structure, that is, the pile foundation, pier column, and cap beam are all prefabricated structures. The construction of prefabricated pile foundations requires the use of hammering, vibration or implantation methods to sink piles, which has high requirements on geological stability and uniformity. However, for conventional areas where there are certain changes in the rock and soil layers underground along the bridge project, the soil layer distribution is relatively random, and the terrain has certain undulations, prefabricated pile foundations are difficult to adapt to the geological conditions of conventional areas, the construction is difficult, and it is difficult to standardize, which reduces the economic benefits of the project and is difficult to promote and apply in engineering practice.
[0004] Another form is to use cast-in-place or prefabricated pile groups to connect cast-in-place caps. However, the on-site cap cast-in-place formwork engineering and foundation pit excavation work are large, the material consumption is high, and the post-cast concrete takes a long time to strengthen. The setting of cast-in-place caps is contrary to the concept of prefabricated bridges.
[0005] Cast-in-place pile foundation technology is mature, the structure is reliable, and the pile length and diameter can be adjusted according to needs. It is a foundation form suitable for most bridges. If cast-in-place pile foundation is used in the existing technology, it is necessary to cast piers after the cast-in-place cap to ensure the connection strength of the piers. If prefabricated piers are directly placed on top of the cast-in-place pile foundation, the requirements of strong nodes and weak components cannot be met, the connection strength between piles and columns cannot be guaranteed, and the safety and stability of the bridge cannot be guaranteed.
[0006] In view of this, it is necessary to propose a prefabricated bridge pier without a cap for use in conventional areas and a construction method to solve or at least alleviate the above-mentioned defects. Summary of the invention
[0007] The main purpose of the present application is to provide a prefabricated bridge pier without a cap and a construction method for use in conventional areas, so as to solve the technical problems that if a prefabricated bridge pier is connected with a cast-in-place cap and a prefabricated pile group, there will be a large workload of on-site cast-in-place cap formwork and cap foundation pit excavation and a long time to strengthen the cap, and if a fully prefabricated bridge pier is used, there will be technical problems such as limited geological conditions and great construction difficulty.
[0008] To achieve the above-mentioned purpose, the present application provides a prefabricated bridge pier without a cap for use in conventional areas, comprising a cap beam and a cap beam support unit for supporting the cap beam, wherein the cap beam support unit comprises a prefabricated pier column and a cast-in-place pile foundation arranged in sequence from top to bottom, wherein the prefabricated pier column and the cast-in-place pile foundation are connected by a first steel-concrete connection assembly, and the outer diameter of the prefabricated pier column is smaller than the outer diameter of the cast-in-place pile foundation; wherein:
[0009] The first steel-concrete connection assembly includes a first butt joint cylinder, an annular butt joint plate, and an external casting cylinder located outside the prefabricated pier column; wherein:
[0010] The annular butt joint plate is connected to the middle part of the outer peripheral wall of the first butt joint cylinder, and the top surface of the annular butt joint plate is in contact with the bottom surface of the prefabricated pier column;
[0011] The inner cavity of the first docking cylinder is filled with a first concrete core, and the annular docking plate divides the first docking cylinder into an upper docking cylinder section and a lower embedded cylinder section in the height direction; wherein a first docking space for docking of the upper docking cylinder section is formed at the bottom of the prefabricated pier, and the upper docking cylinder section extends into the first docking space to dock the prefabricated pier with the top of the cast-in-place pile foundation; the lower embedded cylinder section is cast in the cast-in-place pile foundation;
[0012] The external casting cylinder is fixed on the top of the cast-in-place pile foundation, a concrete casting space is formed between the external casting cylinder and the prefabricated pier, and ultra-high performance concrete is cast in the concrete casting space to form a grouting structure layer.
[0013] Preferably, the cap beam and the cap beam supporting unit are connected by a second steel-concrete connecting assembly; wherein, the second steel-concrete connecting assembly includes a second docking cylinder, the inner cavity of the second docking cylinder is filled with a second concrete core, the second docking cylinder includes an upper embedded cylinder section cast inside the cap beam and a lower docking cylinder section protruding downward from the bottom surface of the cap beam, a second docking space for docking of the lower docking cylinder section is formed on the top of the prefabricated pier, and the lower docking cylinder section extends into the second docking space to dock the cap beam support to the top of the prefabricated pier.
[0014] Preferably, the second steel-concrete connection assembly also includes a plurality of vertical butt tubes arranged at intervals around the second butt tube body; the prefabricated pier includes a pier body and a plurality of pier longitudinal main reinforcements arranged in the pier body and distributed at intervals around the central axis of the pier body; the pier longitudinal main reinforcements are arranged in a one-to-one correspondence with the vertical butt tubes; after the pier longitudinal main reinforcements extend into the vertical butt tubes, the vertical butt tubes are grouted to connect the pier longitudinal main reinforcements to the interior of the cap beam.
[0015] Preferably, the second steel-concrete connection assembly further comprises a third docking cylinder arranged coaxially with the second docking cylinder and arranged outside the second docking cylinder, the third docking cylinder comprising an upper connecting section cast inside the cap beam and a lower guiding docking section protruding downwardly from the bottom surface of the cap beam, and a third docking space for docking the prefabricated pier is formed between the third docking cylinder and the second docking cylinder;
[0016] The prefabricated pier column adopts a cylindrical hollow structure, the upper end of the prefabricated pier column extends into the third docking space, and the second docking cylinder extends into the inner cavity of the prefabricated pier column to dock the cap beam support to the top of the prefabricated pier column.
[0017] Preferably, the top of the cast-in-place pile foundation is stepped, including a first mounting surface for fixedly installing the external casting cylinder and a second mounting surface flush with the top surface of the annular docking plate, the first mounting surface is lower in height than the second mounting surface, and the external casting cylinder is installed on the outside of the first mounting surface and extends upward so that the longitudinal cross-section of the concrete pouring space is in a Γ shape.
[0018] Preferably, the longitudinal main reinforcement of the cast-in-place pile foundation is distributed in a "J" shape in the range of the pile top, and cooperates with local annular stirrups to form a local steel mesh in the grouting structure layer. The length of the outer limb of the longitudinal main reinforcement of the pile foundation is smaller than the length of the inner limb, and the length of the outer limb of the longitudinal main reinforcement of the pile foundation pre-buried downward in the cast-in-place pile foundation is not less than the anchoring length of the steel bar.
[0019] Preferably, the inner diameter of the annular docking plate is equal to the outer diameter of the first docking cylinder, the outer diameter of the annular docking plate is smaller than the outer diameter corresponding to the second mounting surface of the cast-in-place pile foundation, and the outer diameter of the annular docking plate is larger than the outer diameter of the prefabricated pier; the annular docking plate is provided with a plurality of steel bar positioning grooves arranged at intervals along the circumferential direction, and the steel bar positioning grooves and the longitudinal main reinforcements of the pile foundation are arranged one by one.
[0020] Preferably, a plurality of docking guide blocks arranged at intervals around the first docking cylinder body are provided on the upper portion of the outer wall of the first docking cylinder body, and the cross-sectional size of the docking guide blocks gradually increases from top to bottom; and / or a plurality of stiffening plates arranged at intervals around the first docking cylinder body are provided on the outer wall of the first docking cylinder body below the annular docking plate, and the radial width of the stiffening plates along the first docking cylinder body is smaller than the radial width of the annular docking plate.
[0021] The present application also provides a construction method for a prefabricated bridge pier without a cap for conventional areas, which is applied to the above-mentioned prefabricated bridge pier without a cap for conventional areas, and comprises the following steps:
[0022] S100, after burying the steel casing at the target position, the pile foundation is bored, the first docking cylinder body and the annular docking plate fixed thereon are processed, the annular docking plate is used as a part of the steel bar frame to bind the pile foundation steel cage, and the first docking cylinder body is welded and fixed to the top of the pile foundation steel cage through the annular docking plate and the longitudinal main reinforcement of the pile foundation, and then an isolation agent is applied to the inner wall of the steel casing; wherein the top of the steel casing exceeds the top of the cast-in-place pile foundation by 0.3-1m, and the top elevation of the steel casing is 0-0.2m higher than the first docking cylinder body;
[0023] S101, pouring concrete into the pile foundation steel cage and pouring it over to the top of the steel casing, so that the concrete covers the top of the first docking cylinder body, so that the interior of the first docking cylinder body is filled with concrete, and after the strength of the pile foundation concrete reaches 80% of the design strength, the steel casing is removed and recovered;
[0024] S102, breaking the pile head concrete to the designed elevation of the pile top, cleaning the concrete surface of the pile top, exposing the upper docking cylinder section, the annular docking plate and the longitudinal main reinforcement of the pile top;
[0025] S103, hoisting the prefabricated pier column, applying epoxy mortar or structural adhesive on the outer side of the upper butt-jointed cylinder section, inserting the bottom of the prefabricated pier column into the outer side of the upper butt-jointed cylinder section, and then welding the bottom surface of the prefabricated pier column and the annular butt-jointed plate;
[0026] S104, installing and fixing the external casting cylinder, and applying a release agent on the inner side of the external casting cylinder;
[0027] S105, tying the joint steel mesh, pouring ultra-high performance concrete into the concrete pouring space to obtain a grouting structure layer and maintaining it;
[0028] S106, when the strength of the grouting structure layer reaches above 60 MPa, demoulding and recycling the external casting cylinder; and then hoisting the cap beam to the top of the prefabricated pier.
[0029] The present application also provides a construction method for a prefabricated bridge pier without a cap for conventional areas, which is applied to the above-mentioned prefabricated bridge pier without a cap for conventional areas, and comprises the following steps:
[0030] S111, after burying the steel casing at the target position, the pile foundation is bored, the first docking cylinder body and the annular docking plate fixed thereon are processed, the annular docking plate is used as a part of the steel frame to bind the pile foundation steel cage, and the first docking cylinder body is welded and fixed to the top of the pile foundation steel cage through the annular docking plate and the longitudinal main reinforcement of the pile foundation, and then an isolation agent is applied to the inner wall of the steel casing; wherein the top of the steel casing exceeds the top of the cast-in-place pile foundation by 0.3-1m, and the top elevation of the steel casing is 0-0.2m higher than the first docking cylinder body;
[0031] S112, pouring concrete into the pile foundation steel cage and pouring it over to the top of the steel casing, so that the concrete covers the top of the first docking cylinder body, so that the interior of the first docking cylinder body is filled with concrete, and after the strength of the pile foundation concrete reaches 80% of the design strength, the steel casing is removed and recovered;
[0032] S113, breaking the pile head concrete to the designed elevation of the pile top, cleaning the concrete surface of the pile top, exposing the upper docking cylinder section, the annular docking plate and the longitudinal main reinforcement of the pile top;
[0033] S114, installing and fixing the external casting cylinder, and applying a release agent on the inner side of the external casting cylinder;
[0034] S115, tying the joint steel mesh, and first pouring ultra-high performance concrete into the concrete pouring space to obtain a grouting structure layer;
[0035] S116, immediately hoist the prefabricated pier column, insert the upper docking cylinder section into the first docking space at the bottom of the prefabricated pier column; temporarily fix it after hoisting it into place, and then perform grouting structural layer maintenance;
[0036] S117, when the strength of the grouting structure layer reaches above 60MPa, demoulding and recycling the external casting cylinder; and then hoisting the cap beam to the top of the prefabricated pier.
[0037] Compared with the prior art, this application has the following beneficial effects:
[0038] The present invention provides a prefabricated bridge pier without a cap for conventional areas and a construction method, including a cap beam and a cap beam support unit, the cap beam support unit including a prefabricated pier column and a cast-in-place pile foundation, the prefabricated pier column and the cast-in-place pile foundation are connected by a first steel-concrete connection assembly, the first steel-concrete connection assembly including a first docking cylinder, an annular docking plate and an external casting cylinder, the inner cavity of the first docking cylinder is filled with a first concrete core, the external casting cylinder is fixed on the top of the cast-in-place pile foundation, a concrete pouring space is formed between the external casting cylinder and the prefabricated pier column, and ultra-high performance concrete is poured in the concrete pouring space to form a grouting structure layer. The present application can realize the rapid docking and assembly between the cap beam, prefabricated pier column and cast-in-place pile foundation under the non-capped structure, has the advantages of strong nodes and weak components, and avoids the limitation of the promotion and application of prefabricated bridge pier without a cap due to geological and topographical conditions. The present application can realize the rapid docking and assembly between the cap beam, prefabricated pier column and cast-in-place pile foundation under the non-capped structure, and avoids the limitation of the promotion and application of prefabricated bridge pier without a cap due to geological and topographical conditions.
[0039] Specifically, the salient features of the present application are that there is no need to set up a large pedestal, and there is no need to cast a large pedestal on site. The pile-column connection structure is pre-buried in the top of the cast-in-place pile foundation, and the force transmission path of the connection structure is smooth, which can ensure the effective use of the bearing capacity; steel end plates can be set at the upper and lower ends of the prefabricated piers to be opposite to the top of the cast-in-place pile foundation and the bottom of the cap beam, and steel hoops can be provided near the ends of the prefabricated piers, which can effectively reduce the adverse effects on the seismic bearing capacity and post-disaster recoverability of the structure caused by local concrete crushing under the action of earthquake swing, and can adapt to the seismic bearing capacity requirements of conventional areas; the present application adopts mature cast-in-place pile foundation technology, reliable structure, and the pile length and diameter can be adjusted as needed, with low construction difficulty. Standardized construction can be achieved within conventional areas, which greatly expands the use of prefabricated bridge piers and has high economic benefits.
[0040] Secondly, the lower embedded cylinder section pre-embedded in the cast-in-place pile foundation and the first concrete core filled in the inner cavity of the first docking cylinder can greatly improve the seismic ductility of the pier structure. By filling the first docking cylinder with concrete to form a CFST tenon, as an important component of the connection joint, the ductility and shear resistance of the joint are greatly increased, and the brittle failure of the joint can be prevented.
[0041] Furthermore, by using ultra-high performance concrete, that is, UHPC, to form a UHPC tubular grouting layer in the concrete pouring space, the initial strength growth rate of the UHPC tubular grouting layer is fast, which can effectively improve the construction efficiency. The UHPC tubular grouting layer is only used between the prefabricated pier column and the external casting cylinder, with small dosage, high efficiency and good economy. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying any creative work.
[0043] Figure 1 This is a schematic diagram of the overall structure of an embodiment of the present application;
[0044] Figure 2 for Figure 1 A schematic diagram of the combined structure of the cap beam and the second steel-concrete connection assembly;
[0045] Figure 3 This is a schematic diagram of the overall structure of another embodiment of the present application;
[0046] Figure 4 for Figure 3A schematic diagram of the combined structure of the cap beam and the second steel-concrete connection assembly;
[0047] Figure 5 This is a schematic diagram of the structure after the prefabricated pier column and the cast-in-place pile foundation are connected in one embodiment of the present application;
[0048] Figure 6 for Figure 5 A is an enlarged schematic diagram;
[0049] Figure 7 It is a partial enlarged schematic diagram of the joint between the prefabricated pier column and the cast-in-place pile foundation in another embodiment of the present application;
[0050] Figure 8 It is a structural schematic diagram of a prefabricated pier in one embodiment of the present application;
[0051] Fig. 9 It is a structural schematic diagram of a prefabricated pier in another embodiment of the present application;
[0052] Fig.10 This is a schematic diagram of the combined structure of the first docking cylinder and the annular docking plate in one embodiment of the present application;
[0053] Fig.11 It is a top view of the prefabricated pier and the cast-in-place pile foundation after docking in one embodiment of the present application.
[0054] The purpose, features and advantages of this application will be further described in conjunction with the embodiments and with reference to the accompanying drawings.
[0055] Description of Figure Numbers:
[0056] 10. Cap beam; 20. Prefabricated pier; 210. First docking space; 220. Second docking space; 230. Pier body; 240. Pier longitudinal main reinforcement; 30. Cast-in-place pile foundation; 310. First installation surface; 320. Second installation surface; 330. Pile longitudinal main reinforcement; 331. Outer limb of pile longitudinal main reinforcement; 332. Inner limb of pile longitudinal main reinforcement; 340. Local annular stirrups; 40. First steel-concrete connection assembly; 410. First docking cylinder; 411. Upper docking cylinder section; 412. Lower embedded cylinder Segment; 420, first concrete core filling; 430, docking guide block; 440, stiffening plate; 450, annular docking plate; 451, steel bar positioning groove; 460, external cast cylinder; 470, grouting structure layer; 480, docking cone; 50, second steel-concrete connection assembly; 510, second docking cylinder; 511, upper embedded cylinder section; 512, lower docking cylinder section; 513, second concrete core filling; 520, vertical docking pipe; 530, third docking cylinder; 531, upper connection section; 532, lower guide docking section. DETAILED DESCRIPTION
[0057] It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.
[0058] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0059] It should be noted that all directional indications in the embodiments of the present application (such as up, down, left, right, front, back, etc.) are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.
[0060] In addition, the descriptions of "right part", "middle part" and the like in this application are only for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of technical features indicated. Therefore, the features defined as "right part" and "middle part" may explicitly or implicitly include at least one such feature. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in this field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such combination of technical solutions does not exist and is not within the scope of protection required by this application.
[0061] It is important for those skilled in the art to know that the design of bridge pile foundations is greatly affected by geological conditions. In many cases, prefabricated pile foundations do not meet the construction conditions or are difficult to standardize. The application of prefabricated piles increases the construction difficulty to a certain extent, reduces the economic benefits of the project, and has great difficulties in promoting and applying them in engineering practice. Specifically, the size of prefabricated piles is usually small (diameter 0.4~0.8m), and a single pile cannot meet the force requirements of the bridge structure; the pile group foundation is limited by the minimum pile clearance, and conventional bridge piers usually use cast-in-place caps to connect with prefabricated pile groups. The on-site cap cast-in-place formwork and cap foundation pit excavation work is large and takes a long time to be strengthened, which is contrary to the concept of prefabricated bridges. In the prior art, prefabricated piles are usually driven by diesel hammers or heavy hammers. The pile driving construction equipment is huge and is restricted by traffic conditions. Prefabricated pile foundations cannot be used in bridges in mountainous areas, areas with thin overburden, and areas with large stratum fluctuations. Therefore, they are greatly affected by topography and geology. At present, the pile foundation of pile-column bridge piers is connected to the piers. Except for the cast-in-place pier column structure which does not need a cap or a conversion block, the prefabricated piers are all connected to the pile foundation in the form of a cap or a conversion block.
[0062] The cast-in-place pile foundation 30 has mature technology, reliable structure, and the pile length and diameter can be adjusted according to needs. It is a foundation form suitable for most bridges. In addition, if the cast-in-place pile foundation 30 is adopted in the prior art, it is necessary to cast piers after the cast-in-place cap to ensure the connection strength of the piers. If the prefabricated piers 20 are directly mounted on the cast-in-place pile foundation 30, the requirements of strong nodes and weak components cannot be met, the connection strength between the piles and columns cannot be guaranteed, and the safety and stability of the bridge cannot be guaranteed.
[0063] Please see attached Figures 1 to 11 In one embodiment provided in the present application, a prefabricated bridge pier without a cap for use in conventional areas comprises a cap beam 10 and a cap beam support unit (not shown) for supporting the cap beam 10, wherein the cap beam support unit comprises a prefabricated pier column 20 and a cast-in-place pile foundation 30 arranged in sequence from top to bottom, wherein the prefabricated pier column 20 and the cast-in-place pile foundation 30 are connected via a first steel-concrete connection assembly 40, wherein the outer diameter of the prefabricated pier column 20 is smaller than the outer diameter of the cast-in-place pile foundation 30, and the prefabricated pier column 20 and the cast-in-place pile foundation 30 are connected as a whole via the first steel-concrete connection assembly 40; wherein the cap beam support unit is used to support the cap beam 10, and the top of the cap beam 10 is used to lay the bridge deck and other ancillary structures, and the number of the cap beam support units needs to be set according to the actual situation of the cap beam 10, such as the width of the cap beam 10, and in a specific example, one cap beam 10 corresponds to two cap beam support units, and the two cap beam support units are arranged at intervals along the width direction of the cap beam 10, for example Figure 1 or Figure 3 The structure shown.
[0064] Among them, the cast-in-place pile foundation 30 adopts ordinary concrete or ordinary underwater concrete structure, and is provided with longitudinal main reinforcement 330 of the pile foundation and annular stirrups according to the force requirements. The longitudinal main reinforcement 330 of the pile foundation extends a certain length from the top of the pile foundation, and the end of the longitudinal main reinforcement 330 of the pile foundation can be provided with a pier head or welded with a small end plate to reduce the anchoring length of the longitudinal main reinforcement 330 of the pile foundation in the joint.
[0065] The prefabricated pier 20 can be centrifugally formed and autoclaved to have a high concrete strength (C60-C100). Fig. 9 As shown, the upper and lower ends of the prefabricated pier 20 are provided with steel end plates (not shown in the figure), and a plurality of pier longitudinal main reinforcements 240 and stirrups are arranged inside the prefabricated pier 20. The steel end plates are provided with anchoring structures of the pier longitudinal main reinforcements 240, and the pier longitudinal main reinforcements 240 are partially or fully pre-tensioned with prestress.
[0066] For further information, see Appendix Figure 8-9 The prefabricated pier 20 is provided with a ribbed steel hoop (not shown) on the outside of the joint area to enhance the structural strength of the connection.
[0067] The first steel-concrete connection assembly 40 includes a first docking cylinder 410, an annular docking plate 450, and an external cast cylinder 460 located outside the prefabricated pier 20; wherein the first docking cylinder 410 can be in the form of a steel pipe, the annular docking plate 450 can be in the form of an annular steel plate, and the external cast cylinder 460 can be in the form of a corrugated sleeve or a UHPC shell.
[0068] The annular docking plate 450 is connected to the middle of the outer peripheral wall of the first docking cylinder 410, and the top surface of the annular docking plate 450 is in contact with the bottom surface of the prefabricated pier 20;
[0069] The inner cavity of the first docking cylinder 410 is filled with a first concrete core 420, and the annular docking plate 450 separates the first docking cylinder 410 into an upper docking cylinder section 411 and a lower embedded cylinder section 412 in the height direction; wherein, a first docking space 210 for docking of the upper docking cylinder section 411 is formed at the bottom of the prefabricated pier 20, and the upper docking cylinder section 411 extends into the first docking space 210 to dock the prefabricated pier 20 to the cast-in-place pile foundation 30; the lower embedded cylinder section 412 is cast in the cast-in-place pile foundation 30 and is tightly embedded and connected with the cast-in-place pile foundation 30; in a preferred example, the first docking space 210 is a circular or hollow structure, preferably a circular hollow structure, the diameter of the upper docking cylinder section 411 is smaller than the cavity diameter of the prefabricated pier 20, and the centers are aligned, and the gap size on each side is 0.2~3cm, so that epoxy mortar or structural adhesive can be applied on the outer side of the upper docking cylinder section 411 to increase the connection strength.
[0070] The external casting cylinder 460 is fixed on the top of the cast-in-place pile foundation 30, and a concrete casting space is formed between the external casting cylinder 460 and the prefabricated pier 20. Ultra-high performance concrete is cast in the concrete casting space to form a grouting structure layer 470. In a specific example, Figure 6 As shown, the outer casting cylinder 460 adopts a corrugated sleeve, the lower end of which can be fixed on the outside of the cast-in-place pile foundation 30, and the inner diameter of the corrugated sleeve is the same as the outer diameter of the top of the cast-in-place pile foundation 30. The outer corrugated sleeve is composed of two half-tubes, one side of which is connected by a hinge or other rotating mechanism, and the other side is provided with a fixed locking device. The inner side of the outer corrugated sleeve is coated with an isolation agent to facilitate later demoulding and reuse.
[0071] Furthermore, ultra-high performance concrete, namely UHPC, may be provided with a partial steel mesh in the UHPC grouting structure layer 470, and the lower end of the partial steel mesh may be pre-buried in the concrete of the cast-in-place pile foundation 30 or only provided inside the UHPC.
[0072] The notable feature of the present application is that there is no need to set up a large pedestal, and the pile-column connection structure is pre-buried in the top of the cast-in-place pile foundation 30. The force transmission path of the connection structure is smooth, which can ensure the effective use of the bearing capacity; steel end plates can be set at the upper and lower ends of the prefabricated pier 20 to be opposite to the top of the cast-in-place pile foundation 30 and the bottom of the cap beam 10, and steel hoops (not shown in the figure) can be provided near the ends of the prefabricated pier 20, which can effectively reduce the adverse effects on the seismic bearing capacity and post-disaster recoverability of the structure caused by local concrete crushing under the action of earthquake shaking.
[0073] Secondly, the lower embedded cylinder section 412 pre-embedded in the cast-in-place pile foundation 30 and the first concrete core 420 filled in the inner cavity of the first butt cylinder 410 will greatly improve the seismic ductility of the pier structure. By filling concrete inside the butt cylinder to form a CFST tenon, as an important component of the connection joint, the ductility and shear resistance of the joint are greatly increased, and the brittle failure of the joint can be prevented.
[0074] Furthermore, ultra-high performance concrete, i.e., UHPC, is poured into the concrete pouring space to form a UHPC tubular grouting layer. The initial strength growth rate of the UHPC tubular grouting layer is fast, which can effectively improve the construction efficiency. The UHPC tubular grouting layer is only used between the prefabricated pier 20 and the external casting cylinder 460, with small dosage, high efficiency and good economy.
[0075] As a preferred embodiment, the cap beam 10 and the cap beam supporting unit are connected by a second steel-concrete connection assembly 50; wherein, the second steel-concrete connection assembly 50 includes a second docking cylinder 510, the inner cavity of the second docking cylinder 510 is filled with a second concrete core 513, the second docking cylinder 510 includes an upper embedded cylinder section 511 cast inside the cap beam 10 and a lower docking cylinder section 512 protruding downward from the bottom surface of the cap beam 10, and a second docking space 220 for docking of the lower docking cylinder section 512 is formed on the top of the prefabricated pier 20, and the lower docking cylinder section 512 extends into the second docking space 220 to support the cap beam 10 to be docked at the top of the prefabricated pier 20.
[0076] In this embodiment, the cap beam 10 and the cap beam support unit are connected through the second connection cylinder 510. During the connection process, the cap beam 10 is lifted so that the lower connection cylinder section 512 extends into the second connection space 220 to support the cap beam 10 to be connected to the top of the prefabricated pier 20, thereby completing the connection between the cap beam 10 and the prefabricated pier 20. The CFST tenon is formed by filling the interior of the second connection cylinder 510 with concrete, which is an important component of the connection joint, greatly increasing the ductility and shear resistance of the joint, and preventing the brittle failure of the joint.
[0077] As a preferred embodiment, the second steel-concrete connection assembly 50 also includes a plurality of vertical butt tubes 520 arranged at intervals around the second butt tube body 510; the prefabricated pier 20 includes a pier body 230 and a plurality of pier longitudinal main reinforcements 240 arranged in the pier body 230 and distributed at intervals around the central axis of the pier body 230; the pier longitudinal main reinforcements 240 are arranged one-to-one with the vertical butt tubes 520; after the pier longitudinal main reinforcements 240 extend into the vertical butt tubes 520, the vertical butt tubes 520 are grouted to connect the pier longitudinal main reinforcements 240 to the interior of the cap beam 10.
[0078] In this embodiment, the vertical butt-joint tube 520 can adopt a grouting corrugated pipe, and the number of the grouting corrugated pipe can be set by a technician in this field as needed. In the actual assembly process, after the cap beam 10 is lifted, the butt joint can be completed as long as the longitudinal main reinforcement 240 of the pier column is inserted into the corresponding vertical butt joint tube 520. After the longitudinal main reinforcement 240 of the pier column is inserted into the corresponding vertical butt joint tube 520, grouting is performed to make the two become one. At this time, the second butt joint cylinder 510 is butt jointed in the second butt joint space 220, thereby connecting the longitudinal main reinforcement 240 of the pier column to the inside of the cap beam 10 to complete the assembly between the cap beam 10 and the prefabricated pier column 20.
[0079] As another preferred embodiment, the present application also provides another form, wherein the second steel-concrete connection assembly 50 also includes a third docking cylinder 530 which is arranged coaxially with the second docking cylinder 510 and is arranged on the outside of the second docking cylinder 510, wherein the third docking cylinder 530 includes an upper connecting section 531 cast inside the cap beam 10 and a lower guide docking section 532 protruding downward from the bottom surface of the cap beam 10, and a third docking space (not shown in the figure) for docking the prefabricated pier 20 is formed between the third docking cylinder 530 and the second docking cylinder 510; the prefabricated pier 20 adopts a cylindrical hollow structure, the upper end of the prefabricated pier 20 extends into the third docking space, and the second docking cylinder 510 extends into the inner cavity of the prefabricated pier 20 to support the docking of the cap beam 10 to the top of the prefabricated pier 20.
[0080] Specifically, as another example, a third docking space for docking the prefabricated pier 20 is formed between the third docking cylinder 530 and the second docking cylinder 510. When assembling and docking, it is only necessary to hoist the cap beam 10 above the prefabricated pier 20 so that the upper end of the prefabricated pier 20 can be docked in the third docking space. At this time, the second docking cylinder 510 extends into the inner cavity of the prefabricated pier 20, and the top of the cast-in-place pile foundation 30 and the bottom of the cap beam 10 are connected, so that the cap beam 10 can be supported and docked on the top of the prefabricated pier 20. As a preferred example, the second docking cylinder 510 can be a reinforced concrete structure.
[0081] As a preferred embodiment, the top of the cast-in-place pile foundation 30 is stepped, including a first mounting surface 310 for fixedly mounting the external casting cylinder 460 and a second mounting surface 320 flush with the top surface of the annular docking plate 450, wherein the first mounting surface 310 is lower in height than the second mounting surface 320, and the external casting cylinder 460 is mounted on the outside of the first mounting surface 310 and extends upward so that the longitudinal cross-section of the concrete pouring space is in a Γ shape.
[0082] Specifically, Figure 6 As shown, the top of the cast-in-place pile foundation 30 is stepped, and a notch of a certain height and thickness is provided at the top edge of the cast-in-place pile foundation 30, which is stepped in shape. Ultra-high performance concrete (UHPC) is used for filling later, and the longitudinal section of the UHPC tubular grouting layer formed is Γ-shaped (similar to the shape of a kitchen knife with a handle). It is worth noting that this Γ-shape can move the interface between the UHPC and the ordinary concrete of the cast-in-place pile foundation 30 downward to the lower end face with greater rigidity (there is a height difference between the lower end face and the pile top face), avoiding the fiber discontinuity and shrinkage disharmony of the UHPC and the ordinary concrete interface of the cast-in-place pile foundation 30 at the pile top section of the cast-in-place pile foundation 30. The weakening of the cross section caused by the stress cracking, improves the durability of the pile-column joint. In a specific example, a notch of 20-30 cm in height and 5-10 cm in thickness is provided downward at the top edge of the pile foundation, and the notch interface is roughened. After the prefabricated pier 20 is hoisted in place, the tubular grouting layer of Γ-shaped section is poured using UHPC.
[0083] Furthermore, the longitudinal main reinforcement 330 of the cast-in-place pile foundation 30 is distributed in a "J" shape in the range of the pile top, and cooperates with the local annular stirrups 340 to form a local steel mesh in the grouting structure layer 470. The length of the outer limb 331 of the longitudinal main reinforcement of the pile foundation is less than the length of the inner limb 332 of the longitudinal main reinforcement of the pile foundation, and the length of the outer limb 331 of the longitudinal main reinforcement of the pile foundation pre-buried downward in the cast-in-place pile foundation 30 is not less than the anchoring length of the steel bar.
[0084] Specifically, the longitudinal main reinforcement 330 of the cast-in-place pile foundation 30 is distributed in a "J" shape in the range of the pile top, which can effectively improve the anchoring capacity of the longitudinal main reinforcement 330 of the pile foundation, reduce the steel bar joints and on-site workload, shorten the height of the grouting structure layer 470, and save engineering costs; at the same time, it also strengthens the bearing capacity reserve of the joint section, and the length of the outer limb 331 of the longitudinal main reinforcement of the pile foundation is less than the length of the inner limb 332 of the longitudinal main reinforcement of the pile foundation, that is, the short steel bar is located on the outside of the longitudinal main reinforcement 330 of the pile foundation, and the force efficiency is better than the main reinforcement, while ensuring the effective bonding between the pile foundation concrete and the grouting structure layer 470.
[0085] Furthermore, the inner diameter of the annular docking plate 450 is equal to the outer diameter of the first docking cylinder 410, the outer diameter of the annular docking plate 450 is smaller than the outer diameter corresponding to the second mounting surface 320 of the cast-in-place pile foundation 30, and the outer diameter of the annular docking plate 450 is larger than the outer diameter of the prefabricated pier column 20; the annular docking plate 450 is provided with a plurality of steel bar positioning grooves 451 arranged at intervals along the circumferential direction, and the steel bar positioning grooves 451 and the longitudinal main reinforcement 330 of the pile foundation are arranged one by one. Specifically, the outer diameter of the annular docking plate 450 is smaller than the outer diameter corresponding to the second mounting surface 320 of the cast-in-place pile foundation 30, and the outer diameter of the annular docking plate 450 is larger than the outer diameter of the prefabricated pier column 20, so that the prefabricated pier column 20 can be within the coverage of the annular docking plate 450, thereby improving the stability of the pile column support. By setting the steel bar positioning groove 451 on the circumference of the annular docking plate 450, the longitudinal main reinforcement 330 of the pile foundation is correspondingly embedded in the steel bar positioning groove 451. During the construction process, the longitudinal main reinforcement 330 of the pile foundation can be welded and fixed after being correspondingly embedded in the steel bar positioning groove 451, so as to ensure the embedding stability of the annular docking plate 450. It is also worth noting that the annular docking plate 450 connected to the outer periphery of the first docking cylinder 410 can be used as a steel bar positioning cradle when the steel bar cage is manufactured in the factory, thereby reducing the engineering cost. Since the ultimate goal is to allow the longitudinal main reinforcement 330 of the pile foundation to be correspondingly embedded in the steel bar positioning groove 451, the use of the annular docking plate 450 as a steel bar positioning cradle can also improve the positioning accuracy and quality of the steel bar.
[0086] As a preferred embodiment, a plurality of docking guide blocks 430 are arranged at intervals around the first docking cylinder body 410 on the upper portion of the outer wall of the first docking cylinder body 410, and the cross-sectional size of the docking guide blocks 430 gradually increases from top to bottom; and / or a plurality of stiffening plates 440 are arranged at intervals around the first docking cylinder body 410 on the outer wall of the first docking cylinder body 410 below the annular docking plate 450, and the radial width of the stiffening plates 440 along the first docking cylinder body 410 is smaller than the radial width of the annular docking plate 450.
[0087] Specifically, by setting a docking guide block 430 on the side wall of the first docking cylinder 410, for example, setting the docking guide block 430 at the top position of the outer peripheral wall of the upper docking cylinder section 411, the docking of the upper docking cylinder section 411 and the first docking space 210 can be quickly achieved through the docking guide block 430, and the docking guide block 430 also has a positioning function, for example, a plurality of docking guide blocks 430 are evenly arranged on the outer periphery of the first docking cylinder 410, and when the first docking space 210 is a cylindrical docking space, the first docking cylinder 410 and the prefabricated pier 20 can be arranged coaxially, as long as the first docking cylinder 410 and the cast-in-place pile foundation 30 are arranged coaxially, the cast-in-place pile foundation 30 and the prefabricated pier 20 can be arranged coaxially. In a preferred example, the number of the docking guide blocks 430 is set to 2 to 6 and is evenly arranged around the outer periphery of the first docking cylinder 410. In another embodiment, in order to achieve rapid docking of the cast-in-place pile foundation 30 and the prefabricated pier 20 , the first docking space 210 may also be provided with a docking cone 480 to facilitate guiding the docking insertion of the first docking cylinder 410 .
[0088] By setting the stiffening plates 440, in a preferred example, 4 to 12 stiffening plates 440 are arranged circumferentially along the annular butt joint plate 450, and the stiffening plates 440 can increase its out-of-plane stiffness and improve the local stiffness of the annular butt joint plate 450. In another embodiment, annular stiffening plates 440 can be set between the stiffening plates 440 to further improve the overall structural strength, that is, bidirectional stiffening plates 440 are set under the annular butt joint plate 450 to increase its out-of-plane stiffness. The setting of the annular stiffening plates 440 improves the local stiffness of the annular butt joint plate 450, and is basically aligned with the longitudinal main reinforcement 330 of the pile foundation, so that the structural force transmission is smoother.
[0089] Specifically, the docking guide block 430 and the first docking cylinder body 410 may be welded or integrally formed, and the stiffening plate 440 and the first docking cylinder body 410 may be welded or integrally formed.
[0090] The present application also provides a construction method for a prefabricated bridge pier without a cap for conventional areas, which is applied to the above-mentioned prefabricated bridge pier without a cap for conventional areas, and comprises the following steps:
[0091] S100, after burying a steel casing (not shown) at the target position, the pile foundation is bored, the first docking cylinder body 410 and the annular docking plate 450 fixed thereon are processed, the annular docking plate 450 is used as a part of the steel bar frame to bind the pile foundation steel cage, and the first docking cylinder body 410 is welded and fixed to the top of the pile foundation steel cage through the annular docking plate 450 and the pile foundation longitudinal main reinforcement 330, and then an isolation agent is applied to the inner wall of the steel casing; wherein the top of the steel casing exceeds the top of the cast-in-place pile foundation by 0.3-1m, and the top elevation of the steel casing is higher than the first docking cylinder body by 0-0.2m;
[0092] S101, pouring concrete into the pile foundation steel cage and pouring it over to the top of the steel casing, so that the concrete covers the top of the first docking cylinder 410, so that the interior of the first docking cylinder 410 is filled with concrete, and after the strength of the pile foundation concrete reaches 80% of the design strength, the steel casing is removed and recovered;
[0093] S102, breaking the pile head concrete to the designed elevation of the pile top, cleaning the concrete surface of the pile top, exposing the upper docking cylinder section 411, the annular docking plate 450 and the longitudinal main reinforcement of the pile top;
[0094] S103, hoisting the prefabricated pier column 20, applying epoxy mortar or structural adhesive on the outer side of the upper butt-jointed cylinder section 411, inserting the bottom of the prefabricated pier column 20 into the outer side of the upper butt-jointed cylinder section 411, and then welding the bottom surface of the prefabricated pier column 20 and the annular butt-jointed plate 450;
[0095] S104, installing and fixing the external casting cylinder 460, and applying a release agent on the inner side of the external casting cylinder 460;
[0096] S105, tying the joint steel mesh, and pouring ultra-high performance concrete into the concrete pouring space to obtain a grouting structure layer 470 and curing it (post-grouting UHPC method);
[0097] S106, when the strength of the grouting structure layer 470 reaches above 60 MPa, demoulding and recycling the external casting cylinder 460; and then hoisting the cap beam 10 to the top of the prefabricated pier 20.
[0098] In another embodiment, the present application further provides a construction method for a prefabricated bridge pier without a cap for conventional areas, which is applied to the above-mentioned prefabricated bridge pier without a cap for conventional areas, and comprises the steps of:
[0099] S111, after burying a steel casing (not shown) at the target position, the pile foundation is bored, the first docking cylinder body 410 and the annular docking plate 450 fixed thereon are processed, the annular docking plate 450 is used as a part of the steel bar frame to bind the pile foundation steel cage, and the first docking cylinder body 410 is welded and fixed to the top of the pile foundation steel cage through the annular docking plate 450 and the pile foundation longitudinal main reinforcement 330, and then an isolation agent is applied to the inner wall of the steel casing; wherein the top of the steel casing exceeds the top of the cast-in-place pile foundation by 0.3-1m, and the top elevation of the steel casing is higher than the first docking cylinder body by 0-0.2m;
[0100] S112, pouring concrete into the pile foundation steel cage and pouring it over to the top of the steel casing, so that the concrete covers the top of the first docking cylinder 410, so that the interior of the first docking cylinder 410 is filled with concrete, and after the strength of the pile foundation concrete reaches 80% of the design strength, the steel casing is removed and recovered;
[0101] S113, breaking the pile head concrete to the designed elevation of the pile top, cleaning the concrete surface of the pile top, exposing the upper docking cylinder section 411, the annular docking plate 450 and the longitudinal main reinforcement of the pile top;
[0102] S114, installing and fixing the external casting cylinder 460, and applying a release agent on the inner side of the external casting cylinder 460;
[0103] S115, tying the joint steel mesh, first pouring ultra-high performance concrete into the concrete pouring space to obtain a grouting structure layer 470;
[0104] S116, immediately hoist the prefabricated pier 20, insert the upper docking cylinder section 411 into the first docking space 210 at the bottom of the prefabricated pier 20; temporarily fix it after hoisting it into place, and then perform grouting of the structural layer 470 for maintenance (first grouting UHPC method, similar to seat grouting);
[0105] S117, when the strength of the grouting structure layer 470 reaches above 60 MPa, demoulding and recycling the external casting cylinder 460; and then hoisting the cap beam 10 to the top of the prefabricated pier 20.
[0106] Preferably, when the post-casting UHPC tubular grouting layer method is adopted, the gap between the prefabricated pier column 20 and the first docking cylinder 410 takes a small value; when the pre-casting UHPC tubular grouting layer method is adopted, the gap between the prefabricated pier column 20 and the first docking cylinder 410 takes a large value.
[0107] Preferably, the top of the annular stiffening plate 440 is provided with no less than 4 circular exhaust holes, and the diameter of the exhaust holes is 1-5 cm.
[0108] The above are only preferred embodiments of the present application, and are not intended to limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made using the contents of the present application specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present application.
Claims
1. A prefabricated bridge pier without a cap for use in conventional areas, characterized in that: It comprises a cap beam and a cap beam support unit for supporting the cap beam, the cap beam support unit comprises a prefabricated pier column and a cast-in-place pile foundation arranged in sequence from top to bottom, the prefabricated pier column and the cast-in-place pile foundation are connected by a first steel-concrete connection assembly, and the outer diameter of the prefabricated pier column is smaller than the outer diameter of the cast-in-place pile foundation; wherein: The first steel-concrete connection assembly includes a first butt joint cylinder, an annular butt joint plate, and an external casting cylinder located outside the prefabricated pier column; wherein: The annular butt joint plate is connected to the middle part of the outer peripheral wall of the first butt joint cylinder, and the top surface of the annular butt joint plate is butted against the bottom surface of the prefabricated pier column by circumferential welding; The inner cavity of the first docking cylinder is filled with a first concrete core, and the annular docking plate divides the first docking cylinder into an upper docking cylinder section and a lower embedded cylinder section in the height direction; wherein a first docking space for docking of the upper docking cylinder section is formed at the bottom of the prefabricated pier, and the upper docking cylinder section extends into the first docking space to dock the prefabricated pier with the top of the cast-in-place pile foundation; the lower embedded cylinder section is cast in the cast-in-place pile foundation; The external casting cylinder is fixed on the top of the cast-in-place pile foundation, a concrete casting space is formed between the external casting cylinder and the prefabricated pier column, and ultra-high performance concrete is cast in the concrete casting space to form a grouting structure layer; The longitudinal main reinforcement of the cast-in-place pile foundation is distributed in a "J" shape in the range of the pile top, and cooperates with the local annular stirrups to form a local steel mesh in the grouting structure layer. The length of the outer limb of the longitudinal main reinforcement of the pile foundation is less than the length of the inner limb. The length of the outer limb of the longitudinal main reinforcement of the pile foundation embedded downward in the cast-in-place pile foundation is not less than the anchorage length of the steel bar. The annular butt joint plate is provided with a plurality of steel bar positioning grooves arranged at intervals along the circumferential direction, the steel bar positioning grooves and the longitudinal main bars of the pile foundation are arranged one by one, and the longitudinal main bars of the pile foundation are correspondingly embedded in the steel bar positioning grooves and then welded and fixed to ensure the embedding stability of the annular butt joint plate; The upper part of the outer wall of the first docking cylinder is provided with a plurality of docking guide blocks arranged at intervals around the first docking cylinder, and the cross-sectional size of the docking guide blocks gradually increases from top to bottom; and the outer wall of the first docking cylinder is provided with a plurality of stiffening plates arranged at intervals around the first docking cylinder below the annular docking plate, and the radial width of the stiffening plates along the first docking cylinder is smaller than the radial width of the annular docking plate; annular stiffening plates are arranged between the stiffening plates; The cap beam and the cap beam support unit are connected by a second steel-concrete connection assembly; wherein the second steel-concrete connection assembly comprises a second docking cylinder, the inner cavity of which is filled with a second concrete core, the second docking cylinder comprises an upper embedded cylinder section cast inside the cap beam and a lower docking cylinder section protruding downward from the bottom surface of the cap beam, a second docking space for docking of the lower docking cylinder section is formed on the top of the prefabricated pier column, and the lower docking cylinder section extends into the second docking space to dock the cap beam support to the top of the prefabricated pier column; The second steel-concrete connection assembly further includes a third docking cylinder arranged coaxially with the second docking cylinder and arranged outside the second docking cylinder, the third docking cylinder including an upper connecting section cast inside the cap beam and a lower guiding docking section protruding downwardly from the bottom surface of the cap beam, and a third docking space for docking the prefabricated pier is formed between the third docking cylinder and the second docking cylinder; The prefabricated pier column adopts a cylindrical hollow structure, the upper end of the prefabricated pier column extends into the third docking space, and the second docking cylinder extends into the inner cavity of the prefabricated pier column to dock the cap beam support to the top of the prefabricated pier column; a ribbed steel hoop is provided on the outside of the joint area of the prefabricated pier column.
2. The prefabricated bridge pier without a cap for use in conventional areas according to claim 1, characterized in that: The second steel-concrete connection assembly also includes a plurality of vertical butt tubes arranged at intervals around the second butt tube body; the prefabricated pier includes a pier body and a plurality of pier longitudinal main reinforcements arranged in the pier body and distributed at intervals around the central axis of the pier body; the pier longitudinal main reinforcements are arranged one-to-one in correspondence with the vertical butt tubes; after the pier longitudinal main reinforcements extend into the vertical butt tubes, the vertical butt tubes are grouted to connect the pier longitudinal main reinforcements to the interior of the cap beam.
3. The prefabricated bridge pier without a cap for use in conventional areas according to claim 1, characterized in that: The top of the cast-in-place pile foundation is stepped, including a first mounting surface for fixedly mounting the external casting cylinder and a second mounting surface flush with the top surface of the annular docking plate, the first mounting surface being lower in height than the second mounting surface, the external casting cylinder being mounted on the outside of the first mounting surface and extending upward so that the longitudinal cross-section of the concrete pouring space is in a Γ shape.
4. The prefabricated bridge pier without a cap for use in conventional areas according to claim 3, characterized in that: The inner diameter of the annular docking plate is equal to the outer diameter of the first docking cylinder, the outer diameter of the annular docking plate is smaller than the outer diameter corresponding to the second installation surface of the cast-in-place pile foundation, and the outer diameter of the annular docking plate is larger than the outer diameter of the prefabricated pier.
5. A construction method for a prefabricated bridge pier without a cap for use in conventional areas, applied to the prefabricated bridge pier without a cap for use in conventional areas as claimed in any one of claims 1 to 4, characterized in that: Includes steps: S100, after burying the steel casing at the target position, the pile foundation is bored, the pile foundation steel cage is tied, and the first docking cylinder is fixed on the top of the pile foundation steel cage, and then an isolation agent is applied to the inner wall of the steel casing; wherein the top of the steel casing exceeds the top of the cast-in-place pile foundation by 0.3-1m, and the top elevation of the steel casing is higher than the first docking cylinder by 0-0.2m; S101, pouring concrete into the pile foundation steel cage and pouring it over to the top of the steel casing, so that the concrete covers the top of the first docking cylinder body, so that the interior of the first docking cylinder body is filled with concrete, and after the strength of the pile foundation concrete reaches 80% of the design strength, the steel casing is removed and recovered; S102, breaking the pile head concrete to the designed elevation of the pile top, cleaning the concrete surface of the pile top, exposing the upper docking cylinder section, the annular docking plate and the longitudinal main reinforcement of the pile top; S103, hoisting the prefabricated pier column, applying epoxy mortar or structural adhesive on the outer side of the upper butt-jointed cylinder section, inserting the bottom of the prefabricated pier column into the outer side of the upper butt-jointed cylinder section, and then welding the bottom surface of the prefabricated pier column and the annular butt-jointed plate; S104, installing and fixing the external casting cylinder, and applying a release agent on the inner side of the external casting cylinder; S105, tying the joint steel mesh, pouring ultra-high performance concrete into the concrete pouring space to obtain a grouting structure layer and maintaining it; S106, when the strength of the grouting structure layer reaches above 60 MPa, demoulding and recycling the external casting cylinder; and then hoisting the cap beam to the top of the prefabricated pier.
6. A construction method for a prefabricated bridge pier without a cap for use in conventional areas, applied to the prefabricated bridge pier without a cap for use in conventional areas as claimed in any one of claims 1 to 4, characterized in that: Includes steps: S111, after burying the steel casing at the target position, the pile foundation is bored, the pile foundation steel cage is tied, and the first docking cylinder is fixed on the top of the pile foundation steel cage, and then an isolation agent is applied to the inner wall of the steel casing; wherein the top of the steel casing exceeds the top of the cast-in-place pile foundation by 0.3-1m, and the top elevation of the steel casing is higher than the first docking cylinder by 0-0.2m; S112, pouring concrete into the pile foundation steel cage and pouring it over to the top of the steel casing, so that the concrete covers the top of the first docking cylinder body, so that the interior of the first docking cylinder body is filled with concrete, and after the strength of the pile foundation concrete reaches 80% of the design strength, the steel casing is removed and recovered; S113, breaking the pile head concrete to the designed elevation of the pile top, cleaning the concrete surface of the pile top, exposing the upper docking cylinder section, the annular docking plate and the longitudinal main reinforcement of the pile top; S114, installing and fixing the external casting cylinder, and applying a release agent on the inner side of the external casting cylinder; S115, tying the joint steel mesh, and first pouring ultra-high performance concrete into the concrete pouring space to obtain a grouting structure layer; S116, immediately hoist the prefabricated pier column, insert the upper docking cylinder section into the first docking space at the bottom of the prefabricated pier column; temporarily fix it after hoisting it into place, and then perform grouting structural layer maintenance; S117, when the strength of the grouting structure layer reaches above 60 MPa, demoulding and recycling the external casting cylinder; and then hoisting the cap beam to the top of the prefabricated pier.
Citation Information
Patent Citations
Prefabricated steel reinforced concrete and reinforced concrete assembled pier and construction process
CN110952440A
Pile column type pier assembly structure and construction method
CN111305051A
Prefabricated assembly type railway platform canopy structure in medium-high intensity area and construction method
CN115898118A
Assembly joint structure of cylindrical pier
CN209144637U