Construction project progress management system and its optimization method
By introducing risk assessment and quality management modules into the construction project management system, the problem of the existing system's failure to effectively assess risk and quality is solved, the safety and quality assurance of task progress is achieved, and management efficiency and overall progress quality are improved. .
Patent Information
- Application Number
- CN202410322965.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-21
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-03-21
AI Technical Summary
The existing construction project management system fails to effectively assess risks and quality when tracking task progress, resulting in potential risks not being discovered and dealt with in a timely manner, affecting project safety and efficiency.
A system including project planning module, task management module, resource management module, progress monitoring module, risk assessment module, quality management module and reporting module is designed. By tracking task progress, identifying and assessing risks, and recording quality control activities in real time, and generate various reports to support administrator decision-making.
The system can effectively track task progress, identify and assess risks, ensure the safety and quality of task progress, provide comprehensive quality analysis, and improve the management efficiency of administrators and the overall progress quality of engineering projects.
Smart Images

Figure CN117933947B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of engineering progress management, and in particular to a construction engineering project progress management system and an optimization method thereof. Background Art
[0002] Construction projects are usually large-scale, involve multiple professional fields, and contain a large number of work tasks, which makes project schedule planning and management complicated. A systematic approach is needed to ensure that each stage and task is completed on time. Construction projects usually involve cooperation in many professional fields, such as architectural design, structural engineering, mechanical and electrical engineering, etc. These different fields of work need to be carried out in coordination, and the project schedule management system can help all parties work together better to ensure that various tasks are carried out as planned;
[0003] In the field of construction engineering, the success of a project often depends on reasonable progress management. Since construction projects usually involve complex processes, the participation of multiple parties and huge resource investment, the management system is an information tool designed to effectively plan, monitor and control the progress of construction projects.
[0004] The prior art has the following deficiencies:
[0005] 1. When tracking the progress of project tasks, the existing management system does not assess and handle the risks in the construction process of project tasks, resulting in the failure to timely discover and handle potential risks during the project progress, posing safety hazards;
[0006] 2. The existing management system does not perform quality analysis on project tasks when tracking the progress of project tasks, which makes it impossible for administrators to understand the quality of project tasks and manage them in advance, reducing the efficiency of administrators in managing engineering projects. Summary of the invention
[0007] The purpose of the present invention is to provide a construction project progress management system and an optimization method thereof to solve the deficiencies in the background technology.
[0008] In order to achieve the above-mentioned purpose, the present invention provides the following technical solutions: a construction project progress management system, including a project planning module, a task management module, a resource management module, a progress monitoring module, a risk assessment module, a collaboration module, a quality management module, and a reporting module:
[0009] Project planning module: used by administrators to develop overall project plans;
[0010] Task management module: refine the project plan and divide it into multiple tasks;
[0011] Resource management module: manage the resources required for different tasks based on project plan information division;
[0012] Progress monitoring module: real-time tracking of task progress and detection of whether different tasks are proceeding as planned;
[0013] Risk Assessment Module: used to identify and assess risks associated with task progress as different project tasks progress;
[0014] Collaboration module: Generates corresponding collaborative work based on project progress information;
[0015] Quality management module: record the quality control activities of different project tasks as they progress, and analyze the progress quality of the project by combining the construction quality of different project tasks after the project is completed;
[0016] Reporting module: used to generate various reports and analyses and present them to administrators.
[0017] In a preferred embodiment, the risk assessment module is used to identify and assess the risks associated with the progress of different project tasks, including the following steps:
[0018] Identify various anomalies that affect task progress, which will increase the probability of various risks occurring;
[0019] Assign corresponding classification labels to each risk, including technical risk, financial risk, and market risk;
[0020] Conduct quantitative or qualitative assessments of identified risks, including the probability of risk occurrence and the extent of impact;
[0021] Establish a risk register to record all identified risk information and develop a corresponding risk response plan for each risk. The response plan includes preventive measures and response plans.
[0022] In a preferred embodiment, the risk assessment module identifies various anomalies that affect the progress of the task, including groundwater level anomalies, foundation settlement anomalies, precipitation anomalies, and equipment anomalies. After quantitative analysis of groundwater level anomalies, foundation settlement anomalies, precipitation anomalies, and equipment anomalies, a risk index is generated for the task as the task progresses. , the calculation expression is:
[0023] ;
[0024] In the formula, It is the real-time change of the probability of risk occurring during the task progress. The period for groundwater level warning is The period for foundation settlement warning is The period for precipitation warning is The time period for equipment downtime warning;
[0025] The risk index generated Compared with the risk threshold, if the risk index If the risk index is greater than the risk threshold, the predicted task progress will be at risk. If it is less than or equal to the risk threshold, there will be no risk in predicting the task progress.
[0026] In a preferred embodiment, the time period for the groundwater level warning is the time period when the real-time groundwater level is not within the stable water level range; the time period for the foundation settlement warning is the time period when the foundation settlement exceeds the settlement threshold; the time period for the precipitation warning is the time period when the precipitation exceeds the precipitation threshold; the time period for the equipment shutdown warning is the time period when the shutdown duration of the corresponding equipment exceeds the duration threshold during the task progress.
[0027] In a preferred embodiment, the quality management module analyzes the progress quality of the project in combination with the construction quality of different project tasks, including the following steps:
[0028] The risk index The number of times greater than the risk threshold is marked as , the risk index When the risk threshold is greater than the risk threshold, the number of times the construction party manages is marked as , and then calculate the construction party's task risk management rate, the expression is: , where Risk management rate for the mission;
[0029] Calculate the average value of the task risk management rate of the engineering project and mission risk management dispersion ;
[0030] If the average value of the task risk management rate Greater than or equal to the management rate threshold, and the task risk management dispersion Less than or equal to the discrete threshold, the overall progress quality of the project is good;
[0031] If the average value of the task risk management rate Greater than or equal to the management rate threshold, and the task risk management dispersion If it is greater than the discrete threshold, the overall progress quality of the project is good, indicating that the progress quality of some tasks is poor;
[0032] If the average value of the task risk management rate Less than the management rate threshold, and the task risk management dispersion If it is greater than the discrete threshold, the overall progress quality of the project is medium, indicating that the progress quality of some tasks is good;
[0033] If the average value of the task risk management rate Less than the management rate threshold, and the task risk management dispersion Less than or equal to the discrete threshold, the overall progress quality of the project is poor.
[0034] In a preferred embodiment, the progress monitoring module is used to track the progress of the task in real time and includes the following steps:
[0035] Update the progress information of the task, including the start time, completion time, and actual completion percentage;
[0036] Automatically generate key performance indicator reports to show task completion and delays;
[0037] Provides Gantt chart and timeline views to show the overall timeline of the project and the relationship between tasks;
[0038] When the task progress is abnormal or delayed, reminders are automatically sent to the administrator.
[0039] In a preferred embodiment, the progress monitoring module automatically sends a reminder to the administrator when the task progress is abnormal or delayed, including the following steps:
[0040] In the progress monitoring module, set warning rules for abnormal or delayed task progress. The warning rules include the planned completion time, actual completion time, and completion percentage of the task.
[0041] Monitor the progress of tasks regularly or in real time, check the difference between the actual progress of tasks and the planned progress, and determine whether the set warning rules are met;
[0042] Detecting abnormalities or delays in task progress triggers an early warning mechanism, which includes sending automatic notifications, generating alarms, or triggering related workflows;
[0043] Reminder information is generated according to the early warning rules, and the reminder information includes task name, planned completion time, actual completion time, and delay information.
[0044] The present invention also provides a method for optimizing the progress of a construction project, the method comprising the following steps:
[0045] S1: Divide the project plan into multiple tasks, including engineering quantity analysis and process division;
[0046] S2: Divide the resources required for different information management tasks based on the project plan, including human resources, materials, and equipment;
[0047] S3: Track the progress of tasks in real time and check whether different tasks are proceeding as planned;
[0048] S4: Evaluate the importance of all tasks. When a task is not up to standard, determine whether the construction progress of the task needs to be optimized based on the importance of the task.
[0049] S5: When it is determined that construction progress optimization is necessary, corresponding decision suggestions are generated and sent to the administrator.
[0050] In a preferred embodiment, in step S4, the importance of all tasks is evaluated. When the progress of a task does not meet the target, judging whether the construction progress of the task needs to be optimized based on the importance of the task includes the following steps:
[0051] S4.1: Obtain the critical path index, relevance index, and estimated cost index of the task;
[0052] S4.2: Normalize the critical path index, correlation index and estimated cost index and calculate the importance coefficient ;
[0053] S4.3: Obtaining importance coefficient After the importance coefficient The value is compared with the preset importance threshold;
[0054] S4.4: If the task importance coefficient If the value is greater than or equal to the importance threshold, the importance of the analysis task is high;
[0055] S4.5: If the task importance coefficient The value is less than the importance threshold, and the importance of the analysis task is small;
[0056] S4.6: When the progress of a task does not meet the target and the analysis result of the task is of high importance, generate suggestions for optimizing the construction progress of the task.
[0057] In a preferred embodiment, the calculation logic of the critical path index is:
[0058] Use the Bellman-Ford algorithm to calculate the earliest start time and earliest finish time of the task. Based on the calculation of the earliest start time and earliest finish time, perform the reverse Bellman-Ford algorithm to calculate the latest start time and latest finish time of the task, and calculate the critical path index of each task. The expression is: , where is the critical path index, is the latest start time, The earliest start time.
[0059] In the above technical solution, the technical effects and advantages provided by the present invention are:
[0060] 1. The present invention uses a progress monitoring module to track the progress of tasks in real time and detect whether different tasks are carried out as planned. The risk assessment module is used to identify and assess the risks related to the progress of tasks when different project tasks are in progress. The quality management module records the quality control activities of different project tasks when different project tasks are in progress, and after the project is completed, analyzes the progress quality of the project in combination with the construction quality of different project tasks. The reporting module generates various reports and analyses and displays them to the administrator. This management system can effectively track the progress of different project tasks, and conduct risk and quality assessments on tasks in the process of tracking progress to ensure the safety and quality of task progress. Moreover, after the completion of the project, the overall progress quality of the project is comprehensively analyzed based on the quality analysis results of each task. The analysis is more comprehensive and convenient for the administrator to carry out corresponding management.
[0061] 2. The present invention monitors the construction progress of each task of the project, normalizes the critical path index, the correlation index and the estimated cost index, and then calculates the importance coefficient. , importance coefficient The larger the task is, the more important it is in the project. If the value is greater than or equal to the importance threshold, the importance of the analysis task is high. When the progress of a task does not meet the standard and the analysis result of the task is high in importance, a construction progress optimization suggestion for the task is generated, so that the administrator can optimize the construction progress. BRIEF DESCRIPTION OF THE DRAWINGS
[0062] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can also be obtained based on these drawings.
[0063] Figure 1 It is a system module diagram of the present invention.
[0064] Figure 2 The figure is a flow chart of the method of the present invention. DETAILED DESCRIPTION
[0065] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0066] Example 1: Please refer to Figure 1 As shown, the construction project progress management system described in this embodiment includes a project planning module, a task management module, a resource management module, a progress monitoring module, a risk assessment module, a collaboration module, a quality management module, and a reporting module:
[0067] Project planning module: This module is used by administrators to develop an overall project plan, including the project's phased tasks, schedule, resource allocation, etc. The project planning module provides the basis for the entire system and defines the project's time frame. The project plan information is sent to the task management module, specifically:
[0068] Provide an area for administrators to fill in the overview, objectives and key requirements of the project. Administrators enter the overall information of the project in this area, including the project's objectives, scope, expected results, etc., allowing administrators to divide the entire project into different stages or phased tasks. Administrators create project stages in the system and set specific goals, deliverables and deadlines for each stage. Provide a calendar view or timetable for setting the duration and deadlines of the project and each stage. Administrators specify the start date of the project, the start and end dates of each stage in the timetable to ensure that the project is completed on time;
[0069] Allows administrators to allocate resources required for the project, including human, technical and financial resources. The system specifies the resources required for each task or stage, including team members, equipment, funds, etc. Allows administrators to set dependencies between tasks to ensure that tasks are executed in the correct order. The system specifies the order and dependencies of tasks to ensure the consistency of the entire project process. It provides a critical path analysis tool to help administrators identify critical paths and key tasks in the project. The system automatically generates critical paths based on task duration, dependencies and other information, which administrators can view and analyze in the system.
[0070] Provides a graphical project plan view to help team members and stakeholders understand the overall timeline of the project. Generates project Gantt charts or other visual charts in the system to show the timing and dependencies of tasks. Allows the system to send notifications and reminders to ensure that team members are aware of changes in the project plan and task deadlines. Set notification rules in the system to send reminders to administrators based on project progress and task completion.
[0071] Task management module: used to refine the project plan and divide the project plan into multiple tasks, including engineering quantity analysis and process division. The project plan division information is sent to the resource management module, progress monitoring module, risk assessment module and reporting module. Specifically:
[0072] Administrators are allowed to create specific tasks and refine the work content, engineering quantity and process of the tasks according to the project plan. Administrators create tasks in the system and enter detailed information about the tasks, including the name, description, and estimated workload of the tasks. Engineering quantity analysis tools are provided to evaluate the resources, time and cost required for each task. Engineering quantity analysis is performed in the system to estimate the manpower, materials, equipment and other resources required for the tasks, as well as the time and cost required to complete the tasks. Administrators are allowed to further divide tasks into processes and set the workflow of the tasks. Task workflows are created in the system to define the execution order and conditions of each process.
[0073] Administrators are allowed to assign tasks to specific team members and perform resource management to ensure that each task has sufficient resource support. They can specify task executors in the system, allocate required resources, coordinate the scheduling of manpower, materials and equipment, and send the resource information required for the task to the resource management module to ensure effective allocation of resources. The task management module integrates data with the resource management module to ensure that the resource requirements of the task are met.
[0074] Resource management module: This module effectively manages various resources required for different tasks based on project plan division information, including human resources, materials, equipment, etc. The resource management module can help the project team to reasonably allocate resources to ensure their full utilization at all stages of the project. The resource allocation results are sent to the reporting module, specifically:
[0075] Manage the human resources required for the project, including the skills, roles and work assignments of team members, record the information of team members in the system, including skills, experience, work roles, etc., designate the executors of tasks, and ensure the balanced use of human resources, manage the materials required for the project, including raw materials, engineering materials, etc., record the inventory of materials in the system, purchase and allocate materials according to the needs of the project plan, and ensure that the supply of materials meets the project requirements, manage the equipment required for the project, including mechanical equipment, tools, etc., record the status and availability of equipment in the system, schedule and allocate equipment to different tasks, and ensure the effective use of equipment;
[0076] According to the requirements of the project plan and task management modules, reasonably dispatch and allocate human, material and equipment resources, dispatch and allocate resources in the system, ensure that each task has sufficient resource support, avoid excessive or insufficient resources, monitor and report the utilization of project resources, ensure that resources are fully utilized at all stages of the project, generate resource utilization reports in the system, analyze resource usage, adjust and optimize resource allocation in a timely manner, manage project resource costs, including human cost, material procurement cost, equipment rental cost, etc., record resource cost information in the system, conduct cost control and budget management, and ensure effective use of resources within the budget;
[0077] Receive and process resource requirement information sent by the task management module, ensure that resource allocation meets the requirements of project plans and tasks, realize data integration with the task management module, obtain the resource requirements of tasks in a timely manner, and perform corresponding resource scheduling and allocation.
[0078] Progress Monitoring Module: It is used to track the progress of tasks in real time and detect whether different tasks are progressing as planned. It can provide key performance indicators and charts to help project managers detect potential delays or problems in a timely manner. Project progress information is sent to the risk assessment module, collaboration module, quality management module and reporting module. Specifically:
[0079] Update the progress information of the task, including the start time, completion time, actual completion percentage, etc., automatically generate key performance indicator reports, display the completion status and delay status of the task, etc., provide intuitive Gantt chart and timeline views, and show the overall timeline of the project and the relationship between the tasks. Project managers can view the Gantt chart and timeline in the system to intuitively understand the scheduling and progress of the tasks, set early warning rules, and automatically send reminders to the administrators when the task progress is abnormal or delayed. The system monitors the progress of the task according to the set rules, and sends early warning notifications when abnormal situations are found. It records historical progress data to facilitate historical performance comparison and trend analysis. The system saves the historical progress data of the task for reference and analysis by the project administrator;
[0080] Send project progress information to the risk assessment module to help identify potential risks related to the progress, achieve data integration with the risk assessment module to ensure the effective association between project progress and potential risks, share project progress information to the collaboration module to promote real-time communication and collaboration among team members, achieve data integration with the collaboration module to ensure that team members share project progress information, send project progress information to the quality management module to ensure the consistency of task progress and quality standards, achieve data integration with the quality management module, and coordinate the relationship between task progress and quality management;
[0081] When the task progress is abnormal or delayed, automatically sending reminders to the administrator includes the following steps:
[0082] Set warning rules for abnormal or delayed task progress in the system. These rules can be set based on factors such as the planned completion time, actual completion time, and completion percentage of the task. Monitor the progress of the task regularly or in real time. The system needs to regularly check the difference between the actual progress of the task and the planned progress to determine whether the set warning rules are met. The system detects abnormal or delayed task progress, such as when the task is not completed as planned or the actual completion time exceeds expectations.
[0083] Once the system detects an abnormality or delay in task progress, it triggers an early warning mechanism, which may include sending automatic notifications, generating alarms, or triggering related workflows. The system generates detailed reminder information based on the early warning rules, including key information such as task name, planned completion time, actual completion time, and delays. The system selects the appropriate notification method based on the administrator's settings, such as email, text message, internal system message, etc., and automatically sends reminder information to the administrator. The reminder information should include key information about the task so that the administrator can quickly understand the problem and take appropriate actions.
[0084] The system records the history of reminders sent, including the time of the reminder, task information, and which administrators were sent to. This helps track the history of problems and analyze trends. As needed, the system can set the frequency of reminders to ensure that administrators can obtain timely information about abnormal or delayed task progress. If the system supports it, administrators can provide feedback on reminders or take some basic response measures directly in the reminders, such as adjusting task plans, allocating more resources, etc.
[0085] Risk Assessment Module: This module is used to identify and assess the risks associated with the progress of different project tasks. It can help the project team take preventive and responsive measures to reduce the impact of risks on the project progress. The risk assessment results are sent to the reporting module.
[0086] Collaboration module: Generates corresponding collaborative work based on project progress information, which helps effective communication and information sharing among project team members. This includes tasks assignment, team collaboration, progress update and other functions to promote team collaboration, specifically:
[0087] Allow project administrators to assign tasks to specific team members and designate responsible persons. Project administrators select tasks in the system and designate responsible persons to ensure that each task has a clear responsible person. Provide a team collaboration space so that team members can collaborate in real time on a shared platform. Team members can access shared documents, discussion areas, notifications and other functions in the system to promote team collaboration;
[0088] Integrate real-time communication tools, such as chat and instant messaging, to facilitate timely communication between team members. Team members can communicate instantly through the real-time communication tools within the system to solve problems, exchange progress, etc. Provide task discussion and message board functions to facilitate team members to discuss and leave messages on task-related matters. Set up a discussion area or message board for each task in the system, where members can exchange opinions and make suggestions, etc.;
[0089] Allow team members to share files in the system and provide version control functions to ensure that the team always uses the latest files. Team members can upload, download and edit files, and the system automatically tracks file versions to prevent confusion and errors. Allow team members to update the progress of tasks and share progress reports to ensure that the entire team understands the real-time status of the project. Team members update the progress of tasks in the system and generate corresponding progress reports to share the latest developments of the project with the team;
[0090] Set reminder and notification rules to ensure that team members can receive important information such as task assignments and progress updates in a timely manner. The system automatically sends reminders and notifications according to the set rules to help team members stay focused on the project. Integrate collaboration information with the progress monitoring module to ensure that collaborative work is closely related to task progress. Implement data integration with the progress monitoring module to ensure that the collaborative information of the task is reflected in the overall progress monitoring.
[0091] Quality management module: When different project tasks are progressing, the quality of the bridge construction project is one of the key factors. It is used to supervise and record the quality control activities of different project tasks. After the project is completed, the progress quality of the project is analyzed in combination with the construction quality of different project tasks to ensure that the project meets relevant standards and specifications. The analysis results are sent to the report module.
[0092] Reporting module: This module is used to generate various reports and analyses so that project managers can have a comprehensive understanding of the status of the project. This may include progress reports, resource utilization reports, risk analysis reports, etc. Specifically:
[0093] Generate project progress reports, summarize task completion, key performance indicators and overall project progress, select corresponding parameters and time ranges in the system, generate project progress reports, provide visual charts and data, generate resource utilization reports, analyze the utilization and efficiency of human, material, equipment and other resources, select resource management data in the system, generate resource utilization reports, and help administrators optimize resource allocation;
[0094] Generate risk analysis reports, summarize potential risks in the project, countermeasures taken and risk impact assessments, obtain data from the risk assessment module in the system, generate risk analysis reports, help project managers respond to risks in a timely manner, analyze task completion trends, identify possible problems and improvement points, use the system's task completion history data to generate trend analysis reports for project managers to refer to, generate cost reports, summarize the actual cost, budget and cost control of project resources, obtain cost data from the resource management module in the system, generate cost reports, and support project economic decision-making;
[0095] Generate quality analysis reports, summarize the quality assessment results of tasks and possible improvement measures, use the data of the quality management module to generate quality analysis reports, help project managers improve project quality, analyze the critical path of the project, identify key tasks and potential project delay points, use the data of the progress monitoring module to generate critical path analysis reports, provide key decision support for project managers, provide customized reports and visualization tools to meet the specific needs of different project managers, and allow users to select report content, format and visualization methods according to their own needs to generate personalized reports;
[0096] Integrate data with other modules to ensure that the information in the report is comprehensive and accurate, consistent with the actual situation of the project, and integrate data with modules such as task management, resource management, progress monitoring, and risk assessment to improve the accuracy and practicality of the report. Set regular automatic report generation rules to ensure that project managers regularly obtain the latest project information. The system automatically generates reports at specific times according to the set rules and sends them to administrators.
[0097] This application uses the progress monitoring module to track the progress of tasks in real time and detect whether different tasks are progressing as planned. The risk assessment module is used to identify and assess the risks associated with the progress of tasks when different project tasks are progressing. The quality management module records the quality control activities of different project tasks when different project tasks are progressing, and after the project is completed, it analyzes the progress quality of the project in combination with the construction quality of different project tasks. The reporting module generates various reports and analyses and displays them to the administrator. This management system can effectively track the progress of different project tasks, and conduct risk and quality assessments on tasks in the process of tracking progress to ensure the safety and quality of task progress. Moreover, after the completion of the project, the overall progress quality of the project is comprehensively analyzed based on the quality analysis results of each task. The analysis is more comprehensive and convenient for the administrator to manage accordingly.
[0098] Example 2: The risk assessment module is used to identify and assess the risks associated with the progress of different project tasks. It can help the project team take preventive and responsive measures to reduce the impact of risks on the project progress, including the following steps:
[0099] Identify various anomalies that may affect the progress of tasks. Various anomalies may increase the probability of various risks. Assign corresponding classification labels to each risk in the system, such as technical risk, financial risk, market risk, etc., conduct quantitative or qualitative assessments of identified risks, including the possibility of risks, the degree of impact, etc., establish a risk register, record all identified risk information, formulate corresponding risk response plans for each risk in the system, including preventive measures and response plans, designate a person in charge for each risk, and set up a reminder mechanism to ensure timely risk management. The team regularly updates risk information through the system, including the progress, changes, and measures taken of risks;
[0100] Identify various anomalies that may affect the progress of the task, including abnormal groundwater level, abnormal foundation settlement, abnormal precipitation, and abnormal equipment. After quantitative analysis of abnormal groundwater level, abnormal foundation settlement, abnormal precipitation, and abnormal equipment, generate a risk index for the task as the task progresses. ,The quality index is used to reflect the quality of task progress, and the calculation expression is:
[0101] ;
[0102] In the formula, It is the real-time change of the probability of risk occurring during the task progress. The period for groundwater level warning is The period for foundation settlement warning is The period for precipitation warning is The time period for equipment downtime warning;
[0103] Risk index as the task progresses The larger the value, the greater the probability of risk when the task progresses. Therefore, the risk index generated Compared with the risk threshold, if the risk index If the risk index is greater than the risk threshold, the predicted task progress will be at risk. If the value is less than or equal to the risk threshold, there will be no risk in the prediction task progress. When the prediction task progresses and there is a risk, an early warning signal is sent to the administrator, who is required to perform corresponding management.
[0104] in:
[0105] The period of groundwater level warning is the period when the real-time groundwater level is not within the stable water level range. When the groundwater level is too high, it may lead to reduced foundation stability and increase the risk of bridge structure settlement. Excessive groundwater may exert additional water pressure on bridge piers and abutments, increasing the bearing burden of the structure. High water level may cause the water depth to increase at the construction site, increasing the safety risk of construction personnel and equipment. When the groundwater level is too low, it may lead to foundation water shortage, affecting the stability of the bridge structure, causing soil cracking, affecting the bearing capacity of the soil around the bridge, and increasing the difficulty of construction, such as mixing and pouring of concrete.
[0106] The period of foundation settlement warning is the period when the foundation settlement exceeds the settlement threshold. When the foundation settlement exceeds the settlement threshold, it will cause excessive foundation settlement. Excessive foundation settlement may cause uneven settlement of the bridge structure, causing cracks, deformation and other structural damage. Large-scale foundation settlement may cause the entire or partial tilt of the bridge, affecting the normal use and safety of the bridge. Differences in foundation settlement in different parts may cause uneven settlement of the bridge structure, increasing the deformation and uneven force of the bridge. Under certain geological conditions, foundation settlement may trigger foundation liquefaction, causing the soil to lose its bearing capacity and aggravate the settlement of the structure. Foundation settlement may make it impossible to use construction equipment and materials normally, increasing the difficulty of construction. Large-scale foundation settlement may hinder the progress of the project and delay the construction period of the bridge.
[0107] The period of precipitation warning is the period when the precipitation exceeds the precipitation threshold. At this time, the precipitation in the mission environment is too large. Heavy rainfall may cause the river water level to rise, triggering floods, and impacting the bridge structure and foundation. Heavy rain may cause geological disasters such as landslides and mudslides, affecting the geological environment around the bridge. Heavy rain may cause soil softening and liquefaction, reducing the soil's bearing capacity and increasing the risk of bridge foundation settlement. Floods may wash the bottom of the bridge, causing the bridge foundation to become unstable. Continuous rainfall may cause water and mud to accumulate at the construction site, increasing the difficulty of construction. Heavy rainfall may hinder the construction progress and delay the bridge construction period. Long-term rainfall may have an adverse effect on bridge materials, especially concrete, and affect the quality of the bridge.
[0108] The period of equipment downtime warning is the period during the progress of the task when the downtime of the corresponding equipment exceeds the time threshold. If the equipment suddenly stops during construction and the downtime is too long, it will bring the following risks to the bridge project: Some steps in the project may require specific processes or conditions. Equipment downtime may cause quality risks, such as solidification of materials or other problems during construction. Equipment downtime may cause chaos at the construction site and increase safety risks, such as accidents due to failure to operate equipment normally.
[0109] The quality management module is used to analyze the quality control activities of different project tasks as they progress. After the project is completed, it is used to analyze the progress quality of the project in combination with the construction quality of different project tasks to ensure that the project meets relevant standards and specifications. The analysis results are sent to the report module.
[0110] From the above scheme, it can be seen that when various anomalies occur during the progress of a task, not only will the probability of risk in the progress of the task increase, but also the quality of the progress of the task will decrease. However, in the actual process, when anomalies occur in the progress of a task, corresponding measures are usually formulated to manage the anomalies to ensure the quality of the progress of the task;
[0111] However, in actual management, due to human negligence, exceptions may not be properly managed. Therefore, this application monitors the construction party's management of exceptions to judge the progress quality of the task. The specific plan is as follows:
[0112] As the task progresses, the risk index The number of times greater than the risk threshold is marked as , the risk index When the risk threshold is greater than the risk threshold, the number of times the construction party manages is marked as , and then calculate the construction party's task risk management rate, the expression is: , where is the task risk management rate. The larger the task risk management rate is, the better the management effect of the construction party is. When the task risk management rate is lower than the management rate threshold, it is judged that when the probability of task progress risk is high, the management effect of the construction party is poor, which also indicates that the progress quality of the task is poor.
[0113] Finally, after the completion of the project, a comprehensive analysis of the overall project progress quality is conducted, as follows:
[0114] Calculate the average value of the task risk management rate of the engineering project and mission risk management dispersion ; Average value of mission risk management rate The larger the value, the better the overall progress quality of the project and the higher the degree of dispersion of task risk management. The larger the value, the greater the fluctuation in the quality of progress of different tasks in the project, and the greater the degree of dispersion of task risk management. The smaller it is, the smaller the fluctuation in the progress quality of different tasks in the project is;
[0115] Mission Risk Management Discreteness The calculation expression is:
[0116] In the formula, , Indicates the number of tasks divided in the project. is a positive integer, represents the task risk management rate of the i-th task, represents the average value of the mission risk management rate;
[0117] Average mission risk management rate The calculation expression is: ; In the formula, , Indicates the number of tasks divided in the project. is a positive integer, represents the task risk management rate of the i-th task.
[0118] Therefore, if the average mission risk management rate is Greater than or equal to the management rate threshold, and the task risk management dispersion Less than or equal to the discrete threshold, the overall progress quality of the project is good;
[0119] If the average value of the task risk management rate Greater than or equal to the management rate threshold, and the task risk management dispersion If it is greater than the discrete threshold, the overall progress quality of the project is good, indicating that the progress quality of some tasks is poor;
[0120] If the average value of the task risk management rate Less than the management rate threshold, and the task risk management dispersion If it is greater than the discrete threshold, the overall progress quality of the project is medium, indicating that the progress quality of some tasks is good;
[0121] If the average value of the task risk management rate Less than the management rate threshold, and the task risk management dispersion Less than or equal to the discrete threshold, the overall progress quality of the project analysis is poor;
[0122] This application obtains the progress quality of each task in the project, and then evaluates the overall progress quality of the project by comprehensively analyzing the progress quality of each task, and then displays it to the administrator, so that the administrator can understand the construction progress quality of the construction party and facilitate subsequent management. For example, when the construction party's progress quality is poor, you can choose to terminate the cooperation with the construction party. When the construction party's progress quality is good, you can reward it, etc.
[0123] Example 3: Please refer to Figure 1 As shown, the construction project schedule optimization method described in this embodiment includes the following steps:
[0124] The project plan is divided into multiple tasks, including engineering quantity analysis and process division. Based on the project plan division information, various resources required for different tasks, including human resources, materials, equipment, etc., are effectively managed. The progress of tasks is tracked in real time to detect whether different tasks are proceeding as planned. It can provide key performance indicators and charts to help project managers discover potential delays or problems in a timely manner and evaluate the importance of all tasks. When the progress of a task is not up to standard, it is determined whether the construction progress of the task needs to be optimized based on the importance of the task. When it is determined that the construction progress needs to be optimized, the corresponding decision suggestions are generated and sent to the administrator. The decision suggestions include increasing the economic and human investment in the task, and appropriately reducing the economic and human investment in tasks with low importance to ensure the overall construction progress.
[0125] Evaluate the importance of all tasks. When a task is not up to standard, determine whether the construction progress of the task needs to be optimized based on the importance of the task. The following steps are included:
[0126] Get the critical path index, relevance index and estimated cost index of the task;
[0127] The critical path index, correlation index and estimated cost index are normalized and then comprehensively calculated to obtain the importance coefficient , the expression is: , where is the critical path index, is the estimated cost index, is the correlation index, are the proportional coefficients of the critical path index, the estimated cost index, and the correlation index, respectively, and Both are greater than 0.
[0128] Importance coefficient The larger the value, the greater the importance of the task in the project. Therefore, the importance coefficient is obtained. After the importance coefficient The value is compared with the preset importance threshold. If the importance coefficient of the task The value is greater than or equal to the importance threshold, and the importance of the analysis task is large. If the importance coefficient of the task If the value is less than the importance threshold, the importance of the analysis task is small. When the progress of a task does not meet the standard and the analysis result of the task is high in importance, a construction progress optimization suggestion for the task is generated.
[0129] The logic for obtaining the estimated cost index is: obtain the estimated investment cost of each task through the construction party of the project, and then obtain the estimated cost index of the task by dividing the estimated investment cost by the estimated total cost of the project. The expression is: , where is the estimated cost index, To estimate the investment cost, The total cost of the project is estimated. The larger the estimated cost index is, the more important the task is in the project.
[0130] The logic of obtaining the correlation index is: obtain the PERT chart of the project, and obtain the number of post-tasks of the current task through the PERT chart. The meaning of the number of post-tasks is: the post-tasks can only start after the current task is completed. , where is the number of post-tasks, and the correlation index The larger the value, the more important the current task is in the entire project.
[0131] The calculation logic of the critical path index is:
[0132] Use the Bellman-Ford algorithm to calculate the earliest start time and earliest finish time of a task. Based on the earliest start time and earliest finish time, perform a reverse Bellman-Ford algorithm to calculate the latest start time and latest finish time of the task. Calculate the critical path index of each task, that is, the float time, the difference between the latest start time and the earliest start time. The expression is: , where is the critical path index, Start time, The earliest start time. The larger the critical path index, the less important the task is on the critical path. , it indicates that the task is part of the critical path and is of great importance;
[0133] Use the Bellman-Ford algorithm to calculate the earliest start time and earliest finish time of a task. Based on the calculation of the earliest start time and earliest finish time, perform a reverse Bellman-Ford algorithm to calculate the latest start time and latest finish time of a task. The following steps are included:
[0134] Calculate the earliest start time and earliest finish time of the task: set the earliest start time of the starting task to 0, and the earliest start time of other tasks to negative infinity, perform relaxation operations on each task, and update the earliest start time and earliest finish time of the task by comparing the earliest finish time with the earliest start time of other tasks. Iterate until convergence to ensure that the earliest start time and earliest finish time of all tasks are calculated correctly.
[0135] Reverse Bellman-Ford algorithm: Reverse the forward task graph to obtain the reverse task graph, that is, reverse the direction of the arrows, and reinitialize: set the latest completion time of the terminal task to the earliest completion time, and the latest completion time of other tasks to positive infinity, perform reverse relaxation operations on each task, and update the latest start time and latest completion time of the task by comparing the latest start time with the latest completion time of other tasks, iterate until convergence, and ensure that the latest start time and latest completion time of all tasks are calculated correctly;
[0136] Calculate the latest start time and latest finish time of the task: Calculate the latest start time and latest finish time of each task. For each task, the latest start time is equal to the latest finish time minus the task duration.
[0137] This application monitors the construction progress of each task of the project, and obtains the importance coefficient by normalizing the critical path index, correlation index and estimated cost index. , importance coefficient The larger the task is, the more important it is in the project. If the value is greater than or equal to the importance threshold, the importance of the analysis task is high. When the progress of a task does not meet the standard and the analysis result of the task is high in importance, a construction progress optimization suggestion for the task is generated, so that the administrator can optimize the construction progress.
[0138] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters in the formula are set by technicians in this field according to actual conditions.
[0139] It should be understood that the term "and / or" in this article is only a description of the association relationship of associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. A and B can be singular or plural. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship, but it may also indicate an "and / or" relationship. Please refer to the context for specific understanding.
[0140] It should be understood that in the various embodiments of the present application, the size of the serial numbers of the above-mentioned processes does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.
[0141] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application. Those skilled in the art can clearly understand that for the convenience and simplicity of description, the specific working process of the above-described system, device and unit can refer to the corresponding process in the aforementioned method embodiment, and will not be repeated here.
[0142] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.
Claims
1. Construction project progress management system, characterized by: Including project planning module, task management module, resource management module, progress monitoring module, risk assessment module, collaboration module, quality management module, and reporting module: Project planning module: used by administrators to develop overall project plans; Task management module: refine the project plan and divide it into multiple tasks; Resource management module: manage the resources required for different tasks based on project plan information division; Progress monitoring module: real-time tracking of task progress and detection of whether different tasks are proceeding as planned; Risk Assessment Module: used to identify and assess risks associated with task progress as different project tasks progress; Collaboration module: Generates corresponding collaborative work based on project progress information; Quality management module: record the quality control activities of different project tasks as they progress, and analyze the progress quality of the project by combining the construction quality of different project tasks after the project is completed; Reporting module: used to generate various reports and analyses and present them to administrators; The risk assessment module is used to identify and assess the risks associated with the progress of different project tasks, including the following steps: Identify various anomalies that affect task progress, which will increase the probability of various risks occurring; Assign corresponding classification labels to each risk, including technical risk, financial risk, and market risk; Conduct quantitative or qualitative assessments of identified risks, including the probability of risk occurrence and the extent of impact; Establish a risk register to record all identified risk information and formulate a corresponding risk response plan for each risk, which includes preventive measures and response plans; The risk assessment module identifies various anomalies that affect the progress of the task, including groundwater level anomalies, foundation settlement anomalies, precipitation anomalies, and equipment anomalies. After quantitative analysis of groundwater level anomalies, foundation settlement anomalies, precipitation anomalies, and equipment anomalies, a risk index fx is generated for the task as the task progresses. s , the calculation expression is: Where Ft is the real-time change in the probability of risk occurring during task progress, t a , t b is the period of groundwater level warning, t c , t d is the period of foundation settlement warning, t e , t f is the period of precipitation warning, t g , t h The time period for equipment downtime warning; The risk index fx will be generated s Compared with the risk threshold, if the risk index fx s If the risk index fx is greater than the risk threshold, the predicted task progress will be at risk. s Less than or equal to the risk threshold, predicting that the task progress will not be at risk; The period of the groundwater level warning is the period when the real-time groundwater level is not within the stable water level range; the period of the foundation settlement warning is the period when the foundation settlement exceeds the settlement threshold; the period of the precipitation warning is the period when the precipitation exceeds the precipitation threshold; the period of the equipment downtime warning is the period when the downtime of the corresponding equipment exceeds the duration threshold during the task progress; The quality management module analyzes the progress quality of the project in combination with the construction quality of different project tasks, including the following steps: The risk index fx s The number of times greater than the risk threshold is marked as z f , the risk index fx s When it is greater than the risk threshold, the number of times the construction party performs management is marked as z g , and then calculate the construction party's task risk management rate, the expression is: gl = z g z f , where gl is the mission risk management rate; Calculate the average value of the task risk management rate of the engineering project avg and mission risk management discreteness QG; If the average value of the task risk management rate gl avg It is greater than or equal to the management rate threshold, and the discrete degree of task risk management QG is less than or equal to the discrete threshold, and the overall progress quality of the project is good; If the average value of the task risk management rate gl avg If it is greater than or equal to the management rate threshold, and the discrete degree QG of task risk management is greater than the discrete threshold, the overall progress quality of the project is good, indicating that the progress quality of some tasks is poor; If the average value of the task risk management rate gl avg It is less than the management rate threshold, and the discrete degree QG of task risk management is greater than the discrete threshold. The overall progress quality of the project is medium, indicating that the progress quality of some tasks is good; If the average value of the task risk management rate gl avg If the value is less than the management rate threshold and the discrete degree QG of task risk management is less than or equal to the discrete threshold, the overall progress quality of the engineering project is poor.
2. The construction project progress management system according to claim 1, characterized in that: The progress monitoring module is used to track the progress of the task in real time and includes the following steps: Update the progress information of the task, including the start time, completion time, and actual completion percentage; Automatically generate key performance indicator reports to show task completion and delays; Provides Gantt chart and timeline views to show the overall timeline of the project and the relationship between tasks; When the task progress is abnormal or delayed, reminders are automatically sent to the administrator.
3. The construction project progress management system according to claim 2 is characterized by: The progress monitoring module automatically sends a reminder to the administrator when the task progress is abnormal or delayed, including the following steps: In the progress monitoring module, set warning rules for abnormal or delayed task progress. The warning rules include the planned completion time, actual completion time, and completion percentage of the task. Monitor the progress of tasks regularly or in real time, check the difference between the actual progress of tasks and the planned progress, and determine whether the set warning rules are met; Detecting abnormalities or delays in task progress triggers an early warning mechanism, which includes sending automatic notifications, generating alarms, or triggering related workflows; Reminder information is generated according to the early warning rules, and the reminder information includes task name, planned completion time, actual completion time, and delay information.
4. A method for optimizing the progress of a construction project, implemented based on the management system according to any one of claims 1 to 3, characterized in that: The optimization method comprises the following steps: S1: Divide the project plan into multiple tasks, including engineering quantity analysis and process division; S2: Divide the resources required for different information management tasks based on the project plan, including human resources, materials, and equipment; S3: Track the progress of tasks in real time and check whether different tasks are proceeding as planned; S4: Evaluate the importance of all tasks. When a task is not up to standard, determine whether the construction progress of the task needs to be optimized based on the importance of the task. S5: When it is determined that construction progress optimization is necessary, corresponding decision suggestions are generated and sent to the administrator.
5. The method for optimizing the progress of a construction project according to claim 4, characterized in that: In step S4, the importance of all tasks is evaluated. When the progress of a task does not meet the target, it is determined whether the construction progress of the task needs to be optimized based on the importance of the task. The following steps are included: S4.1: Obtain the critical path index, relevance index, and estimated cost index of the task; S4.2: Normalize the critical path index, correlation index and estimated cost index and calculate the importance coefficient zy x ; S4.3: Obtaining importance coefficient zy x After the value is obtained, the importance coefficient zy x The value is compared with the preset importance threshold; S4.4: If the task importance coefficient zy x If the value is greater than or equal to the importance threshold, the importance of the analysis task is high; S4.5: If the task importance coefficient zy x The value is less than the importance threshold, and the importance of the analysis task is small; S4.6: When the progress of a task does not meet the target and the analysis result of the task is of high importance, generate suggestions for optimizing the construction progress of the task.
6. The method for optimizing the progress of a construction project according to claim 5, characterized in that: The calculation logic of the critical path index is: Use the Bellman-Ford algorithm to calculate the earliest start time and earliest finish time of the task. Based on the calculation of the earliest start time and earliest finish time, perform the reverse Bellman-Ford algorithm to calculate the latest start time and latest finish time of the task. Calculate the critical path index of each task. The expression is: TF = |LS-ES|, where TF is the critical path index, LS is the latest start time, and ES is the earliest start time.
Citation Information
Patent Citations
Information system engineering supervision project risk assessment method
CN114037311A
Building engineering progress supervision system based on artificial intelligence
CN116681250A
Fabricated building quality information supervision system based on big data
CN116720752A
Government engineering digital project management system
CN116894648A
Project management method and system based on WBS engineering entity splitting and hooking
CN116934052A