Moisture-proof wiring equipment and method for tunnel construction
By designing a moisture-proof wiring equipment for tunnel construction and using a mechanized method to hang cables from the ground to the tunnel wall, the problems of cable wear and insufficient length are solved, and the safety of the cables and the service life of the equipment are improved.
Patent Information
- Application Number
- CN202410059345.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-16
- Publication Date
- 2024-10-08
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During tunnel construction, cables are easily worn by gravel when being dragged, leading to leakage, and when the cable length is insufficient, it cannot be hung effectively, posing safety risks.
A moisture-proof wiring equipment including a car body, a lifting assembly, an L-shaped plate, a pulling roller set, a clamping claw and a mechanical clamp is designed. The cable is hung from the ground to the tunnel wall in a mechanized manner, using the clamping claw and Use sandpaper to clean debris on the cable surface to avoid crossing and friction, and adjust the cable length through telescopic plates and linear drives.
It realizes the safe hanging of cables, avoids cable damage and cross friction, extends the service life of the equipment, and solves the problem of insufficient cable length.
Smart Images

Figure CN118040546B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of construction wiring, and in particular to moisture-proof wiring equipment and method for tunnel construction. Background Art
[0002] During the tunnel construction process, construction equipment, lighting, etc. all require the use of electricity, so it is necessary to temporarily lay cables in the tunnel. The temporary cables laid by the prior art will be dragged according to the movement of the construction equipment. Due to the presence of gravel on the ground, the gravel will cause wear to the cable during the dragging process, resulting in the protective layer on the surface of the cable being cut, causing the cable to leak electricity and become dangerous. Therefore, the cable needs to be hung on the tunnel wall. The prior art is for workers to pick up the cable from the ground and hang it on a hook on the side wall of the tunnel. However, when the worker pulls the cable from the ground to hang it on the tunnel wall, the cable will be pulled upwards, and the cable may be insufficient in length, resulting in the cable being unable to be hung on the hook. Summary of the invention
[0003] In order to overcome the shortcomings of the above-mentioned background technology, the present invention provides a moisture-proof wiring device and method for tunnel construction.
[0004] The technical implementation scheme of the present invention is: a moisture-proof wiring equipment for tunnel construction, including a car body, a lifting assembly, an L-shaped plate and a pulling roller group; a lifting assembly is installed on the car body; an L-shaped plate for hanging the cable is connected to the lifting assembly; the lifting assembly is used to drive the L-shaped plate to lift and lower; a pulling roller group for guiding and pulling the cable is fixed to the car body; the pulling roller group is located on the right side of the L-shaped plate; it also includes a clamping claw, a first connecting plate, a connecting frame and a translation assembly; a translation assembly is installed on the car body; the translation assembly is located on the right side of the pulling roller group; the translation assembly is connected to the connecting frame; the translation assembly is used to drive the connecting frame to translate; the connecting frame is located on the right side of the translation assembly; a first connecting plate is rotatably connected to the connecting frame, and the first connecting plate is driven to rotate by a motor; the front and rear sides of the first connecting plate are rotatably connected to clamping claws for clamping cables, and the clamps are driven to rotate by a motor.
[0005] Furthermore, it also includes a first telescopic plate, a first linear drive member and a second linear drive member; the second linear drive member is fixedly connected to the connecting frame; the telescopic end of the second linear drive member is rotatably connected to the first telescopic plate, and the first telescopic plate is driven to rotate by a motor; a first linear drive member is fixedly connected to the upper and lower sides of the first telescopic plate; each first linear drive member output end is fixedly connected to the L-shaped telescopic portion of the adjacent first telescopic plate.
[0006] Furthermore, it also includes a wedge plate and a third linear drive member; the third linear drive member is fixedly connected to the first telescopic plate; and the output end of the third linear drive member is fixedly connected to a wedge plate for determining the cross relationship of the cables.
[0007] Furthermore, it also includes sandpaper; the inner side of the clamping jaw is provided with sandpaper for rubbing the cement block on the surface of the cable.
[0008] Furthermore, it also includes a mechanical gripper, a fourth linear drive component and a buffer component; two fourth linear drives are fixedly connected to the vehicle body; each fourth linear drive component is fixedly connected to a buffer component; a mechanical gripper for cleaning cement powder on the cable surface is fixedly connected to the lower side of each buffer component, and a sponge is provided inside the mechanical gripper.
[0009] Furthermore, the lifting assembly includes a first electric slide rail, a first slider and a second slider; the first electric slide rail is fixedly connected to the vehicle body; the first slider and the second slider are slidably connected to the first electric slide rail; the first slider and the second slider are both fixedly connected to an L-shaped plate; the L-shaped plate is driven up and down by the first slider and the second slider, and the position between the L-shaped plate and the cable hook is adjusted so that the L-shaped plate passes through the cable hook and the cable is mounted on the hook.
[0010] Furthermore, the translation assembly includes a second electric slide rail and a third slider; the second electric slide rail is fixedly connected to the right side of the vehicle body; the third slider is slidably connected to the second electric slide rail; the third slider is fixedly connected to a connecting frame; the third slider drives the connecting frame and other parts to move forward and backward along the second electric slide rail to adapt to the position of the cable.
[0011] Furthermore, it also includes a second telescopic plate; two second telescopic plates symmetrically connected to the right side of the vehicle body for placing preset cables; the second telescopic plates are located on the right side of the vehicle body and on the left side of the pulling roller group; a U-shaped buckle of a limiting cable is fixed to the telescopic part of each second telescopic plate.
[0012] Furthermore, it also includes a second connecting plate, a sixth linear driving member and an extrusion plate; each second telescopic plate fixing portion is fixedly connected to a second connecting plate; each second connecting plate is fixedly connected to a sixth linear driving member; each sixth linear driving member output end is fixedly connected to an extrusion plate for limiting the cable.
[0013] A moisture-proof wiring method for tunnel construction, comprising the following steps: 1. inserting a cable from the ground into a moisture-proof wiring device for tunnel construction; 2. removing debris from the surface of the cable by using the moisture-proof wiring device for tunnel construction; 3. guiding the cable to a hook on the tunnel wall by using the moisture-proof wiring device for tunnel construction; and 4. lowering the cable into the hook.
[0014] The beneficial effects of the present invention are as follows: the present invention realizes the work of transferring the cable from the ground to the hook, and at the same time overcomes the problem of the cable being stuck by the soil, and will not damage the cable.
[0015] The present invention drives the clamping claw to rotate by the first connecting plate to untie the cables so that they no longer cross each other, thereby preventing the crossing part of the cables from moving rightward all the time during the hanging process of the cables, increasing the friction between the cables and between the cables and the gravel, and improving the safety of the cables when in use.
[0016] The present invention uses machinery to replace workers to hang up cables for tunnel construction, and at the same time cleans cement blocks on the surface of the cables, thereby increasing the service life of moisture-proof wiring equipment for tunnel construction; at the same time, crossed cables can be de-crossed to avoid damage caused by mutual friction between the cables.
[0017] The invention overcomes the problem that the cable cannot be hung due to insufficient cable length during the process of hanging the cable. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 It is a schematic diagram of the three-dimensional structure of the moisture-proof wiring equipment for tunnel construction of the present invention;
[0019] Figure 2 It is a schematic diagram of the three-dimensional structure of the second telescopic plate of the present invention;
[0020] Figure 3 For the present invention Figure 2 A magnified image of the area in the middle;
[0021] Figure 4 It is a schematic diagram of the combined three-dimensional structure of the partial structure of the present invention;
[0022] Figure 5 For the present invention Figure 4 A magnified image of the area at B in the middle;
[0023] Figure 6 It is a schematic diagram of the three-dimensional structure of the mechanical gripper of the present invention;
[0024] Figure 7 It is a schematic diagram of the three-dimensional structure of the clamping jaw and sandpaper combination of the present invention;
[0025] Figure 8 It is a schematic diagram of the three-dimensional structure of the wedge plate of the present invention;
[0026] Fig. 9 A diagram showing a state in which a cable is hung on an L-shaped plate of the present invention;
[0027] Fig.10 This is a state diagram of the first telescopic plate of the present invention lifting the cable upward.
[0028] The meanings of the reference numerals in the figure are: 1-car body, 2-L-shaped plate, 3-pulling roller group, 4-clamping claw, 5-first telescopic plate, 101-first electric slide rail, 102-first slider, 103-second slider, 104-first linear drive member, 105-second linear drive member, 106-first connecting plate, 107-connecting frame, 108-second electric slide rail, 109-third slider, 201-wedge plate, 202-third linear drive member, 203-sandpaper, 204-mechanical clamp, 205-fourth linear drive member, 206-buffer, 301-second telescopic plate, 302-second connecting plate, 303-sixth linear drive member, 304-extrusion plate. DETAILED DESCRIPTION
[0029] Hereinafter, embodiments of the present invention will be described with reference to the drawings.
[0030] Example 1
[0031] like Figure 1-Figure 10 As shown, a moisture-proof wiring equipment for tunnel construction includes a vehicle body 1, a lifting assembly, an L-shaped plate 2 and a pulling roller group 3; the vehicle body 1 is equipped with a lifting assembly; the L-shaped plate 2 is connected to the lifting assembly; the lifting assembly is used to drive the L-shaped plate 2 to rise and fall; the pulling roller group 3 is fixedly connected to the vehicle body 1; the pulling roller group 3 is located on the right side of the L-shaped plate 2;
[0032] It also includes a clamping jaw 4, a first connecting plate 106, a connecting frame 107 and a translation assembly; a translation assembly is installed on the vehicle body 1; the translation assembly is located on the right side of the pulling roller group 3; a connecting frame 107 is connected to the translation assembly; the translation assembly is used to drive the connecting frame 107 to translate; the connecting frame 107 is located on the right side of the translation assembly; the connecting frame 107 is rotatably connected to the first connecting plate 106, and the first connecting plate 106 is driven to rotate by a motor; the front and rear sides of the first connecting plate 106 are rotatably connected to the clamping jaw 4, and the clamping jaw 4 is driven to rotate by a motor; the cable is driven to swing up and down by driving the clamping jaw 4 with the connecting axis between the first connecting plate 106 and the clamping jaw 4 as the rotation center.
[0033] It also includes a first telescopic plate 5, a first linear drive member 104 and a second linear drive member 105; the second linear drive member 105 is bolted to the connecting frame 107; the telescopic end of the second linear drive member 105 is rotatably connected to the first telescopic plate 5, and the first telescopic plate 5 is driven to rotate by a motor; a first linear drive member 104 is bolted to the upper and lower sides of the first telescopic plate 5; the output end of each first linear drive member 104 is fixedly connected to the L-shaped telescopic portion of the adjacent first telescopic plate 5; the first linear drive member 104 is an electric push rod; the second linear drive member 105 is an electric push rod.
[0034] It also includes a wedge plate 201 and a third linear drive member 202 ; the third linear drive member 202 is bolted to the first telescopic plate 5 , and the third linear drive member 202 is an electric push rod; the output end of the third linear drive member 202 is fixedly connected to the wedge plate 201 .
[0035] It also includes sandpaper 203; sandpaper 203 is arranged inside the clamping jaw 4. It also includes a mechanical gripper 204, a fourth linear drive member 205 and a buffer member 206; two fourth linear drives 205 symmetrically connected to the vehicle body 1 are bolted; each fourth linear drive member 205 is fixedly connected to a buffer member 206; a mechanical gripper 204 is fixedly connected to the lower side of each buffer member 206, and a sponge is arranged inside the mechanical gripper 204; the fourth linear drive member 205 is an electric push rod or a telescopic rod.
[0036] The lifting assembly includes a first electric slide rail 101, a first slider 102 and a second slider 103; the first electric slide rail 101 is bolted to the vehicle body 1; the first slider 102 and the second slider 103 are slidably connected to the first electric slide rail 101; the first slider 102 and the second slider 103 are both fixedly connected to an L-shaped plate 2; the L-shaped plate 2 is driven up and down by the first slider 102 and the second slider 103, the position between the L-shaped plate 2 and the cable hook is adjusted, the L-shaped plate 2 passes through the cable hook, and the cable is mounted on the hook.
[0037] The translation assembly includes a second electric slide rail 108 and a third slider 109; the second electric slide rail 108 is bolted to the right side of the vehicle body 1; the third slider 109 is slidably connected to the second electric slide rail 108; the third slider 109 is fixedly connected to the connecting frame 107; the third slider 109 drives the connecting frame 107 and other parts to move forward and backward along the second electric slide rail 108 to adapt to the position of the cable.
[0038] During tunnel construction, workers need to hang up construction cables;
[0039] Before the present invention works, the cable is manually passed through the L-shaped plate 2, the pulling roller group 3 and other parts, such as Figure 1 Status shown;
[0040] When the present invention is working, during the process of the vehicle body 1 moving to the right, the pulling roller group 3 pulls the cable to move to the left, and at the same time the clamping claw 4 straightens the cable, and then the first slider 102 and the second slider 103 drive the L-shaped plate 2 to adjust the height, so that the L-shaped plate 2 passes through the hook. After the L-shaped plate 2 moves through the hook, the cable automatically falls on the hook. Fig. 9As shown, the vehicle body 1 drives the clamping jaw 4 to move rightward to straighten the cable. When workers clean the tunnel, they sweep debris and soil to both sides of the road, so that part of the cable is buried. The clamping jaw 4 may bend the cable in the process of straightening the cable. Therefore, the motor connected to the first connecting plate 106 drives the clamping jaw 4 to swing up and down, and further drives the cable to swing up and down, so as to pull out the buried cable, thereby avoiding bending of the cable in the process of straightening the cable by the clamping jaw 4. At the same time, part of the soil on the surface of the cable is pulled off, so as to reduce the friction of the cable on the moisture-proof wiring equipment for tunnel construction.
[0041] When the cable is buried in the soil, the soil becomes compacted due to workers' trampling and equipment rolling, and the clamp 4 cannot pull the cable out of the soil, the motor on the first telescopic plate 5 drives the first telescopic plate 5 to rotate ninety degrees clockwise from right to left, so that the first telescopic plate 5 is in a horizontal state, and then the first telescopic plate 5 is driven by the second linear drive 105 to move downward to the lower side of the cable, and further driven by the first linear drive 104 to move the L-shaped telescopic portion of the first telescopic plate 5 to the front and rear sides, as shown in FIG. Fig.10 As shown, the first telescopic plate 5 is then driven upward by the second linear drive member 105 to pull the cable out of the soil, and at the same time the two clamping claws 4 provide support on the left side; the above-mentioned work of the present invention realizes the work of transferring the cable from the ground to the hook, and at the same time overcomes the problem of the cable being stuck in the soil, and will not damage the cable.
[0042] Since two cables cross each other when the cables are in use, the wedge plate 201 is driven to move rightward by the third linear drive member 202, and the cable is pushed by the wedge plate 201. The cross position relationship of the cables is determined by observation by workers or by installing an identification camera, and then the first connecting plate 106 is rotated, and then the clamping claw 4 is driven to rotate by the first connecting plate 106 to untie the cables so that they no longer cross. At this time, the first connecting plate 106 is inclined, and the heights of the two cables are different, so as to avoid the crossover of the cables from moving to the right all the time during the hanging process, thereby increasing the friction between the cables and the cables and the cables and the gravel, and improving the safety of the cables when in use;
[0043] During the construction of the tunnel, cement will drip onto the cable. In the process of straightening the cable by swinging the clamp 4, the cable surface is polished by sandpaper 203, and the small cement blocks on the cable surface are polished. Then, the fourth linear drive 205 drives the mechanical gripper 204 to move left and right, and the cement powder rubbed on the cable surface is wiped off by sponge. At the same time, the buffer 206 is used to adapt the swinging range of the clamp 4 to the cable, so that part of the cement powder on the cable surface is removed by the sponge inside the mechanical gripper 204. Furthermore, the mechanical gripper 204 can be controlled to open at a small angle to make the cement powder inside the mechanical gripper 204 fall off, thereby increasing the cleaning effect on the cable.
[0044] The present invention uses machinery to replace workers to hang up cables for tunnel construction, and at the same time cleans cement blocks on the surface of the cables, thereby increasing the service life of moisture-proof wiring equipment for tunnel construction; at the same time, crossed cables can be de-crossed to avoid damage caused by mutual friction between the cables.
[0045] Example 2
[0046] On the basis of Example 1, Figure 1 , Figure 2 and Figure 3 As shown, it also includes a second telescopic plate 301; two second telescopic plates 301 symmetrically connected to the right side of the vehicle body 1; the second telescopic plates 301 are located on the right side of the vehicle body 1 and on the left side of the pulling roller group 3; a U-shaped buckle of a limiting cable is fixed to the telescopic part of each second telescopic plate 301.
[0047] It also includes a second connecting plate 302, a sixth linear drive member 303 and an extrusion plate 304; each second telescopic plate 301 fixing portion is fixedly connected to a second connecting plate 302; each second connecting plate 302 is bolted to a sixth linear drive member 303, and the sixth linear drive member 303 is an electric push rod; each sixth linear drive member 303 output end is fixedly connected to an extrusion plate 304.
[0048] In the process of hanging the cable, the cable length is insufficient and the cable cannot be hung. Therefore, before construction, the present invention passes the cable through the U-shaped buckle of the second telescopic plate 301, such as Figure 1 As shown, the cable is limited by the second connecting plate 302 at the same time. When the cable length is insufficient, the L-shaped plate 2 drives the cable to pass through the hook to hang the cable, which will pull the cable to shrink the second telescopic plate 301, pull out the preset cable on the second telescopic plate 301, increase the cable length, and hang the cable through the L-shaped plate 2;
[0049] When the present invention stops moving, the sixth linear drive member 303 controls the squeezing plate 304 to move downward to limit the cable, thereby preventing the cable from being affected by gravity and being dragged to the left.
[0050] A moisture-proof wiring method for tunnel construction, comprising the following steps: 1. inserting a cable from the ground into a moisture-proof wiring device for tunnel construction; 2. removing debris from the surface of the cable by using the moisture-proof wiring device for tunnel construction; 3. guiding the cable to a hook on the tunnel wall by using the moisture-proof wiring device for tunnel construction; and 4. lowering the cable into the hook.
[0051] The above description is only an example of the present invention and is not intended to limit the present invention. Any equivalent substitutions made within the principles of the present invention should be included in the protection scope of the present invention. The contents not elaborated in detail in the present invention belong to the existing technologies known to those skilled in the art.
Claims
1. A moisture-proof wiring device for tunnel construction, characterized in that: The invention comprises a vehicle body (1), a lifting assembly, an L-shaped plate (2) and a pulling roller group (3); the lifting assembly is installed on the vehicle body (1); the lifting assembly is connected to the L-shaped plate (2) for hanging the cable; the lifting assembly is used to drive the L-shaped plate (2) to rise and fall; the pulling roller group (3) for guiding and pulling the cable is fixedly connected to the vehicle body (1); the pulling roller group (3) is located on the right side of the L-shaped plate (2); It also includes a clamping claw (4), a first connecting plate (106), a connecting frame (107) and a translation assembly; the translation assembly is installed on the vehicle body (1); the translation assembly is located on the right side of the pulling roller group (3); the translation assembly is connected to the connecting frame (107); the translation assembly is used to drive the connecting frame (107) to translate; the connecting frame (107) is located on the right side of the translation assembly; the connecting frame (107) is rotatably connected to the first connecting plate (106), and the first connecting plate (106) is driven to rotate by a motor; the front and rear sides of the first connecting plate (106) are both rotatably connected to clamping claws (4) for clamping cables, and the clamping claws (4) are driven to rotate by a motor; The invention also comprises a first telescopic plate (5), a first linear drive member (104) and a second linear drive member (105); the second linear drive member (105) is fixedly connected to the connecting frame (107); the telescopic end of the second linear drive member (105) is rotatably connected to the first telescopic plate (5), and the first telescopic plate (5) is driven to rotate by a motor; a first linear drive member (104) is fixedly connected to the upper side and the lower side of the first telescopic plate (5); the output end of each first linear drive member (104) is fixedly connected to the L-shaped telescopic portion of the adjacent first telescopic plate (5); and the invention also comprises a wedge plate (201) and a third linear drive member (202); the third linear drive member (202) is fixedly connected to the first telescopic plate (5); the output end of the third linear drive member (202) is fixedly connected to the wedge plate (201) for determining the cross relationship of the cables.
2. The moisture-proof wiring equipment for tunnel construction according to claim 1 is characterized in that: The invention also comprises sandpaper (203); the inner side of the clamping jaw (4) is provided with sandpaper (203) for rubbing cement blocks on the surface of the cable.
3. The moisture-proof wiring equipment for tunnel construction according to claim 1 is characterized in that: The invention also comprises a mechanical gripper (204), a fourth linear drive member (205) and a buffer member (206); two fourth linear drive members (205) are fixedly connected to the vehicle body (1); a buffer member (206) is fixedly connected to each fourth linear drive member (205); a mechanical gripper (204) for cleaning cement powder on the surface of the cable is fixedly connected to the lower side of each buffer member (206); a sponge is arranged inside the mechanical gripper (204).
4. A moisture-proof wiring device for tunnel construction according to claim 3, characterized in that: The lifting assembly comprises a first electric slide rail (101), a first slider (102) and a second slider (103); the first electric slide rail (101) is fixedly connected to the vehicle body (1); the first slider (102) and the second slider (103) are slidably connected to the first electric slide rail (101); the first slider (102) and the second slider (103) are both fixedly connected to an L-shaped plate (2); the L-shaped plate (2) is driven to move up and down by the first slider (102) and the second slider (103), the position between the L-shaped plate (2) and the cable hook is adjusted, the L-shaped plate (2) passes through the cable hook, and the cable is mounted on the hook.
5. The moisture-proof wiring equipment for tunnel construction according to claim 4 is characterized in that: The translation assembly comprises a second electric slide rail (108) and a third slider (109); the second electric slide rail (108) is fixedly connected to the right side of the vehicle body (1); the third slider (109) is slidably connected to the second electric slide rail (108); the third slider (109) is fixedly connected to a connecting frame (107); the third slider (109) drives the connecting frame (107) and other parts to move forward and backward along the second electric slide rail (108) to adapt to the position of the cable.
6. A moisture-proof wiring device for tunnel construction according to claim 5, characterized in that: It also includes a second telescopic plate (301); two second telescopic plates (301) symmetrically arranged in the upper and lower parts for placing preset cables are fixedly connected to the right side of the vehicle body (1); the second telescopic plates (301) are located on the right side of the vehicle body (1) and on the left side of the pulling roller group (3); and a U-shaped buckle for limiting the position of the cable is fixedly connected to the telescopic part of each second telescopic plate (301).
7. A moisture-proof wiring device for tunnel construction according to claim 6, characterized in that: It also includes a second connecting plate (302), a sixth linear driving member (303) and an extrusion plate (304); each second telescopic plate (301) fixing portion is fixedly connected to a second connecting plate (302); each second connecting plate (302) is fixedly connected to a sixth linear driving member (303); and each sixth linear driving member (303) output end is fixedly connected to an extrusion plate (304) for limiting the position of the cable.
8. A moisture-proof wiring method for tunnel construction, based on the use of the moisture-proof wiring device for tunnel construction according to claim 7, characterized in that: It includes the following steps:
1. Pass the cable from the ground into the tunnel for moisture-proof wiring equipment; 2. Remove debris from the cable surface using moisture-proof wiring equipment during tunnel construction; 3. Use moisture-proof wiring equipment to guide the cable to the hook on the tunnel wall through tunnel construction; 4. Lower the cable into the hook.