A method for physiological health monitoring and environmental monitoring early warning of deep foundation pit construction workers

Through multi-source information fusion monitoring of deep foundation pit construction personnel and environment, the target threshold of physiological health index and environmental indicators is established, and the problem of untimely early warning in the existing technology is solved, and the construction environment and workers' status of deep foundation pits is realized. Comprehensive monitoring and safety alerts have improved construction safety.

CN118141342BActive Publication Date: 2024-11-26SHENZHEN UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410114920.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-01-25
Publication Date
2024-11-26
Estimated Expiration
2044-01-25

AI Technical Summary

Technical Problem

The existing technology cannot achieve comprehensive and accurate and intelligent monitoring of the construction environment and workers' status of deep foundation pits, resulting in untimely warning of abnormal conditions, affecting construction safety.

Method used

By obtaining the historical physiological index information of construction workers and the historical environmental information of deep foundation pits, the factor analysis method is used to process it, the target threshold range of the overall physiological health index and environmental indicators is constructed, the current data is monitored in real time, and if abnormal, a safety alarm prompt is issued.

Benefits of technology

It realizes dynamic linkage monitoring of workers, environment and structures, responds quickly and warns, improves the safety management level of construction sites, and ensures the normal progress of deep foundation pit construction and the life safety of construction workers.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118141342B_ABST
    Figure CN118141342B_ABST
Patent Text Reader

Abstract

The present invention discloses a physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers, the method comprising: obtaining historical physiological index information, historical air index data and historical foundation pit enclosure structure data, and pre-processing the historical physiological index information according to preset requirements to obtain historical physiological parameter data; performing data processing on the historical physiological parameter data according to the factor analysis method to obtain the overall physiological health index of the construction personnel; performing linear analysis processing on the historical air index data according to the overall physiological health index to obtain the target threshold range of the historical air index data; obtaining the current physiological parameter data and the current environmental data, if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm prompt is given. The present invention effectively ensures the normal construction of the deep foundation pit and the personal safety of the construction personnel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of data monitoring technology, and in particular to a method, system, terminal and computer-readable storage medium for physiological health monitoring and environmental monitoring and early warning of deep foundation pit construction workers. Background Art

[0002] Deep foundation pit excavation is extremely risky. In order to ensure that all work related to deep foundation pit excavation is carried out in an orderly manner, it is necessary to do a good job in safety risk management of on-site construction, starting from multiple aspects such as the physiological indicators of construction personnel and the on-site environment.

[0003] However, traditional deep foundation pit construction safety monitoring technology uses simple video surveillance and a small number of sensors, such as wearable devices for workers to collect various physiological data of workers, environmental monitoring systems can detect specific environmental parameters or various structural deformation indicators through structural health detection systems. However, the above-mentioned technical monitoring functions are relatively independent and single, and cannot achieve comprehensive and accurate intelligent monitoring of the construction environment and worker status, resulting in untimely warning of abnormal conditions occurring during deep foundation pit excavation, affecting the normal excavation work of the deep foundation pit and the life safety of construction workers.

[0004] Therefore, the prior art still needs to be improved and developed. Summary of the invention

[0005] The main purpose of the present invention is to provide a method, system, terminal and computer-readable storage medium for physiological health monitoring and environmental monitoring early warning of deep foundation pit construction workers, aiming to solve the problem that the prior art cannot realize comprehensive and accurate intelligent monitoring of the deep foundation pit construction environment and worker status, resulting in untimely early warning of abnormal conditions occurring during deep foundation pit excavation, affecting the normal excavation work of the deep foundation pit and the life safety of construction workers.

[0006] To achieve the above object, the present invention provides a method for physiological health monitoring and environmental monitoring early warning of deep foundation pit construction workers, the method comprising the following steps:

[0007] Acquire historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and pre-process the historical physiological index information according to preset requirements to obtain historical physiological parameter data, wherein the historical environmental information includes historical air index data and historical foundation pit retaining structure data;

[0008] Processing the historical physiological parameter data according to factor analysis to obtain the overall physiological health index of the construction personnel;

[0009] Performing linear analysis on the historical air index data according to the overall physiological health index to obtain target threshold ranges for the historical air index data;

[0010] The current physiological parameter data and the current environmental data are obtained, and if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm is issued.

[0011] Optionally, the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers, wherein the historical physiological index information of the construction workers and the historical environmental information of the deep foundation pit are obtained, and the historical physiological index information is preprocessed according to preset requirements to obtain historical physiological parameter data, specifically including:

[0012] Acquire historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and set preset physiological parameter thresholds corresponding to each physiological parameter in the historical physiological index information;

[0013] Each physiological parameter in the historical physiological index information is compared with the corresponding preset physiological parameter threshold, and the physiological parameters in the historical physiological index information that exceed the preset physiological parameter threshold are deleted to obtain the historical physiological parameter data.

[0014] Optionally, the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers, wherein the historical physiological parameter data is processed according to the factor analysis method to obtain the overall physiological health index of the construction workers, specifically includes:

[0015] Performing data standardization processing on the historical physiological parameter data to obtain standardized physiological parameter data, wherein the calculation formula for the data standardization processing is: (x-μ) / σ, x is the historical physiological parameter data corresponding to each construction worker, μ is the mean value of all construction workers in the historical physiological parameter data under any physiological indicator, and σ is the standard deviation of all construction workers in the historical physiological parameter data under any physiological indicator;

[0016] Constructing a standardized matrix according to the standardized physiological parameter data, and obtaining a corresponding correlation coefficient matrix according to the standardized matrix;

[0017] Acquire multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and determine the number of common factors in the historical physiological parameter data and the multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the multiple eigenvalues ​​and the multiple eigenvectors;

[0018] The numerical value corresponding to the common factor is determined according to the historical physiological parameter data and the multivariate linear relationship equation, and the overall physiological health index is calculated according to the numerical value corresponding to the common factor and the distribution weight of the common factor in the historical physiological parameter data.

[0019] Optionally, the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers, wherein the step of constructing a standardized matrix according to the standardized physiological parameter data and obtaining a corresponding correlation coefficient matrix according to the standardized matrix, specifically includes:

[0020] Obtaining the number of construction workers corresponding to the historical physiological parameter data, and constructing a standardized matrix according to the number of construction workers and the standardized physiological parameter data;

[0021] Calculate the covariance and standard deviation corresponding to different physiological index parameters in the standardized matrix, and obtain the correlation coefficient matrix based on the covariance and the standard deviation, wherein the calculation formula of the correlation coefficient matrix is: ρ(X1, X2)=COV(X1, X2) / (σX1σX2), wherein X1 and X2 represent different physiological index parameters, ρ(X1, X2) is the correlation coefficient matrix, COV(X1, X2) is the covariance of different physiological index parameters, and σX1σX2 is the standard deviation of different physiological index parameters.

[0022] Optionally, the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers, wherein the obtaining of multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and determining the number of common factors in the historical physiological parameter data and the multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the multiple eigenvalues ​​and the multiple eigenvectors, specifically includes:

[0023] Acquire multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and arrange the multiple eigenvalues ​​in descending order, and when the multiple eigenvalues ​​meet a preset condition, obtain the target number of the common factors;

[0024] The target number of eigenvalues ​​are extracted from the plurality of eigenvalues ​​in order from large to small, a load matrix is ​​constructed according to the target number of eigenvalues, and the multivariate linear relationship equation between each common factor and the historical physiological parameter data is obtained according to the load matrix.

[0025] Optionally, the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers, wherein the linear analysis and processing of the historical air index data according to the overall physiological health index to obtain the target threshold range of the historical air index data specifically includes:

[0026] According to the overall physiological health index, the historical air index data are subjected to linear analysis and processing to obtain a functional relationship between the historical air index data and the overall physiological health index, wherein the expression of the functional relationship is: Yi=kθ+b, wherein Yi is any air index data in the historical air index data, θ is the overall physiological health parameter corresponding to each construction worker, and k and b are constants in the functional relationship;

[0027] The target threshold range corresponding to each of the historical air index data is determined according to the overall physiological health index and the functional relationship.

[0028] Optionally, in the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers, the current environmental data includes current air index data and current foundation pit retaining structure data; the current physiological parameter data and current environmental data are obtained, and if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm prompt is issued, specifically including:

[0029] Acquire the current physiological parameter data, the current air index data and the current foundation pit retaining structure data, and set a preset foundation pit retaining structure threshold according to the historical foundation pit retaining structure data;

[0030] If any one of the physiological parameters in the current physiological parameter data is greater than the corresponding preset physiological parameter threshold, the current physiological parameter data is determined to be abnormal, and a safety alarm is issued;

[0031] If any of the current air index data is greater than the corresponding target threshold range, the current air index data is determined to be abnormal, and a safety alarm is issued;

[0032] If any foundation pit retaining structure parameter in the current foundation pit retaining structure data is greater than the corresponding preset foundation pit retaining structure threshold, the current foundation pit retaining structure data is determined to be abnormal, and a safety alarm is issued.

[0033] In addition, to achieve the above-mentioned purpose, the present invention also provides a deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning system, wherein the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning system comprises:

[0034] A historical data collection module is used to obtain historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and pre-process the historical physiological index information according to preset requirements to obtain historical physiological parameter data, wherein the historical environmental information includes historical air index data and historical foundation pit retaining structure data;

[0035] A historical data processing module, used for processing the historical physiological parameter data according to a factor analysis method to obtain the overall physiological health index of the construction personnel;

[0036] An air index range determination module, used to perform linear analysis on the historical air index data according to the overall physiological health index to obtain a target threshold range for the historical air index data;

[0037] The data abnormality alarm module is used to obtain current physiological parameter data and current environmental data. If the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm prompt is issued.

[0038] In addition, to achieve the above-mentioned purpose, the present invention also provides a terminal, wherein the terminal includes: a memory, a processor, and a deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning program stored in the memory and runnable on the processor, and the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning program, when executed by the processor, implements the steps of the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning method as described above.

[0039] In addition, to achieve the above-mentioned purpose, the present invention also provides a computer-readable storage medium, wherein the computer-readable storage medium stores a deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning program, and when the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning program is executed by the processor, the steps of the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning method as described above are implemented.

[0040] In the present invention, the historical physiological index information of the construction personnel and the historical environmental information of the deep foundation pit are obtained, and the historical physiological index information is preprocessed according to the preset requirements to obtain the historical physiological parameter data, wherein the historical environmental information includes the historical air index data and the historical foundation pit enclosure structure data; the historical physiological parameter data is processed according to the factor analysis method to obtain the overall physiological health index of the construction personnel; the historical air index data is linearly analyzed according to the overall physiological health index to obtain the target threshold range of the historical air index data; the current physiological parameter data and the current environmental data are obtained, and if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm prompt is given. The present invention obtains the physiological index data and environmental data of the construction personnel during the deep foundation pit excavation process, and combines the physiological index data and the environmental data to construct a linear relationship between the two, thereby realizing dynamic linkage monitoring of workers, environment, and structure. It can monitor the generation of abnormal data more quickly and accurately, and give early warning prompts in time, effectively ensuring the normal construction of the deep foundation pit and the personal safety of the construction personnel. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] Figure 1 It is a flow chart of a preferred embodiment of the method for physiological health monitoring and environmental monitoring and early warning of deep foundation pit construction workers of the present invention;

[0042] Figure 2 It is an overall implementation flow chart of a preferred embodiment of the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning method of the present invention;

[0043] Figure 3 It is a structural diagram of a preferred embodiment of the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning system of the present invention;

[0044] Figure 4 It is a structural diagram of a preferred embodiment of the terminal of the present invention. DETAILED DESCRIPTION

[0045] In order to make the purpose, technical solution and advantages of the present invention clearer and more specific, the present invention is further described in detail below with reference to the accompanying drawings and examples. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0046] Deep foundation pit excavation is extremely risky. In order to ensure that all work of deep foundation pit excavation is carried out in an orderly manner, it is necessary to do a good job in safety risk control of on-site construction, starting from various aspects such as the physiological indicators of construction personnel and the on-site environment. For example, various environmental parameters and structural deformation parameters, etc., form a deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning system with multi-source information fusion. However, traditional deep foundation pit construction safety monitoring technology uses simple video monitoring and a small number of sensors, which cannot achieve comprehensive intelligent monitoring of the construction environment and worker status. There is a lack of effective fusion and utilization of multi-source data, and there are monitoring blind spots.

[0047] Although there are ways to use workers' wearable devices to collect workers' physiological data in the existing technology, there is a lack of an effective utilization method and there are application limitations. However, if it is embedded in the present invention and combined with other on-site environmental data for full utilization, then such equipment will also be greatly promoted and utilized. Existing environmental monitoring systems generally detect specific environmental parameters, but the functions are relatively independent and insufficient to support systematic safety management. Although the existing structural health detection system can also accurately detect various structural deformation indicators, its functions are also relatively independent, and it is not combined with the construction site workers and environmental detection, and the early warning response is not timely enough.

[0048] In view of the above problems, the present invention proposes a multi-source information fusion method for physiological health monitoring and environmental monitoring early warning of deep foundation pit construction workers.

[0049] The physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers described in the preferred embodiment of the present invention is as follows: Figure 1 As shown, the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers includes the following steps:

[0050] Step S10, obtaining historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and preprocessing the historical physiological index information according to preset requirements to obtain historical physiological parameter data, wherein the historical environmental information includes historical air index data and historical foundation pit retaining structure data.

[0051] like Figure 2As shown, the system consists of a worker physiological health monitoring module, an environmental monitoring module, a server and a mobile monitoring terminal. The worker physiological health monitoring module detects and collects various physiological parameters of the workers, and is set to measure indicators such as heart rate, blood pressure, blood oxygen concentration, body temperature, and blood sugar concentration; the environmental monitoring module detects and collects various indicators of the construction site. Because the scenario targeted by the present invention is a deep foundation pit excavation scenario, the space is relatively closed and noisy, so the collected environmental information includes various air indicators and various indicator parameters of the foundation pit retaining structure, among which the various air indicators include air temperature and humidity, toxic gas (for example: methane) concentration, carbon dioxide concentration, noise decibel value, etc., and the various indicator parameters of the foundation pit retaining structure include deformation value and inclination of the retaining structure strain gauge, surface settlement value and water pressure detection, etc.

[0052] Specifically, historical physiological indicator information of construction workers and historical environmental information of deep foundation pits are obtained, and a preset physiological parameter threshold corresponding to each physiological parameter in the historical physiological indicator information is set; each physiological parameter in the historical physiological indicator information is compared with the corresponding preset physiological parameter threshold, and the physiological parameters in the historical physiological indicator information that exceed the preset physiological parameter threshold are deleted to obtain the historical physiological parameter data.

[0053] The above monitoring values ​​are transmitted back to the server via Bluetooth. The server collects information from each detection terminal and processes the collected data according to the set method.

[0054] The data processing method is as follows: In terms of the physiological parameters of workers, the first step is to combine the preset safety thresholds of various physiological parameters of workers. If a physiological parameter exceeds the threshold, the alarm function is immediately triggered, and the worker is notified to take corresponding mitigation measures through voice broadcast of the wearable physiological health detection device. For example, if the blood sugar concentration is too low, the worker is notified to stop and rest immediately and replenish sugar, and the risk is sent to the mobile monitoring terminal to remind the on-site management personnel.

[0055] The present invention is composed of a worker physiological health monitoring module, an environmental monitoring module, a server and a mobile monitoring terminal. The functions of each functional module are as follows:

[0056] Worker physiological health monitoring module: The worker physiological health monitoring module uses wearable devices such as smart bracelets or smart helmets, with built-in heart rate, blood pressure, blood oxygen concentration, body temperature, blood sugar concentration, position and other measurement sensors, which regularly collect various physiological parameters and positioning information of workers and upload them to the server through the wireless network. Since each person's physiological health parameters are different, the safety thresholds set in the server can be adjusted slightly in a personalized manner.

[0057] Environmental monitoring module: The environmental monitoring terminal uses alarms to connect external temperature and humidity detection, toxic gas concentration detection, noise detection sensors, as well as enclosure structure strain gauge deformation value detection, inclination value detection (inclination is measured by sensors), surface settlement value detection and water pressure detection sensors to monitor various environmental parameters and structural deformation in real time. Each sensor has its own location information, which is uploaded back to the server via the wireless network.

[0058] Server: The server collects information from each monitoring module for centralized information processing, and transmits the processed data to the mobile monitoring terminal in real time. At the same time, it combines the preset safety thresholds of normal physiological health parameters of workers and the safety thresholds of various environmental monitoring indicators to determine whether the physiological parameters of workers are abnormal and whether there are dangerous factors in the environment. Once data abnormalities are detected, an alarm is immediately triggered and sent to the monitoring terminal.

[0059] Mobile monitoring terminal: The mobile monitoring terminal is operated by the on-site management personnel, and can view and call up various workers' physiological health parameters, overall physiological health index and various environmental parameters at any time. When receiving abnormal data, the alarm can be directly triggered to warn on-site. If the worker's physiological parameters exceed the threshold, the mobile monitoring terminal will also display the worker's specific location information, which is convenient for construction site management.

[0060] Step S20: Process the historical physiological parameter data according to factor analysis to obtain the overall physiological health index of the construction workers.

[0061] If the worker's physiological index parameters do not exceed the preset threshold range, further data processing is performed in combination with the factor analysis method in multivariate statistical analysis to obtain the worker's real-time overall physiological health index.

[0062] Specifically, the historical physiological parameter data is subjected to data standardization processing to obtain standardized physiological parameter data, wherein the calculation formula for the data standardization processing is: (x-μ) / σ, x is the historical physiological parameter data corresponding to each construction worker, μ is the mean value of all construction workers in the historical physiological parameter data under any physiological indicator, and σ is the standard deviation of all construction workers in the historical physiological parameter data under any physiological indicator.

[0063] Obtain the number of construction workers corresponding to the historical physiological parameter data, and construct a standardized matrix based on the number of construction workers and the standardized physiological parameter data; calculate the covariance and standard deviation corresponding to different physiological index parameters in the standardized matrix, and obtain the correlation coefficient matrix based on the covariance and the standard deviation, wherein the calculation formula of the correlation coefficient matrix is: ρ(X1, X2)=COV(X1, X2) / (σX1σX2), wherein X1 and X2 represent different physiological index parameters, ρ(X1, X2) is the correlation coefficient matrix, COV(X1, X2) is the covariance of different physiological index parameters, and σX1σX2 is the standard deviation of different physiological index parameters.

[0064] The standardized physiological indicators of each worker are combined into a matrix with the number of workers as the number of rows and the physiological indicators of each worker in each column. ij It represents the value of the jth physiological index of the i-th worker after data standardization, and then the corresponding correlation coefficient matrix can be obtained according to this standardized matrix. At the same time, the covariance of different physiological index parameters satisfies COV(X1, X2) = E[X1-μx1)(X2-μX2)], where E is the expected calculation.

[0065] Acquire multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and arrange the multiple eigenvalues ​​in order from large to small. When the multiple eigenvalues ​​meet the preset conditions, obtain the target number of the common factors; extract the eigenvalues ​​of the target number from the multiple eigenvalues ​​in order from large to small, construct a load matrix according to the eigenvalues ​​of the target number, and obtain the multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the load matrix. Determine the numerical value corresponding to the common factor according to the historical physiological parameter data and the multivariate linear relationship equation, and calculate the overall physiological health index according to the numerical value corresponding to the common factor and the distribution weight of the common factor in the historical physiological parameter data.

[0066] Then calculate the eigenvalues ​​λ of this correlation coefficient matrix i and the corresponding eigenvector e i =[a i1 , a i2 , a i3 , a i4 , a i5 ], sort the calculated eigenvalues ​​from large to small, and calculate when , the value of m is the number of common factors F determined, and the eigenvectors corresponding to the first m eigenvalues ​​are multiplied by The matrix composed of is the load matrix, from which the multivariate linear relationship equation F between each common factor F and each physiological index of the worker can be obtained. i =a i1 X 1 +a i2 X 2 +…+a i5 X 5 , the linear relationship equation can be substituted into the worker's physiological parameters to obtain the common factors F i Since each common factor has a different contribution to the variance of the overall sample and the contribution is the corresponding eigenvalue, the weight allocated to the overall physiological health parameter by each common factor is equal to The final overall physiological health parameters are And through actual measurements by a large number of workers, the value range of θ can also be obtained, which provides a basis for the subsequent air index threshold control.

[0067] Step S30: performing linear analysis on the historical air index data according to the overall physiological health index to obtain target threshold ranges for the historical air index data.

[0068] Specifically, the historical air index data are linearly analyzed and processed according to the overall physiological health index to obtain a functional relationship between the historical air index data and the overall physiological health index, wherein the expression of the functional relationship is: yi=kθ+b, wherein Yi is any air index data in the historical air index data, θ is the overall physiological health parameter corresponding to each construction worker, and k and b are constants in the functional relationship; the target threshold range corresponding to the historical air index data is determined according to the overall physiological health index and the functional relationship.

[0069] The calculated workers' overall physiological health index at multiple moments and the various air indicators in the environmental monitoring module are subjected to univariate linear regression analysis to obtain the functional relationship between various air indicators and the overall physiological health index. Through this functional relationship, combined with the workers' physiological health parameters obtained from the previous data processing, corresponding threshold control range reference values ​​can be proposed for various air indicators in the current construction environment. If an indicator exceeds the corresponding threshold, an alarm will also be triggered and sent to the mobile monitoring terminal to alert on-site managers.

[0070] Step S40, obtaining current physiological parameter data and current environmental data, and if the current physiological parameter data is judged to be abnormal according to the preset requirement or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm is issued.

[0071] Specifically, the current physiological parameter data, the current air index data and the current foundation pit retaining structure data are obtained, and a preset foundation pit retaining structure threshold is set according to the historical foundation pit retaining structure data; if any one of the physiological parameters in the current physiological parameter data is greater than the corresponding preset physiological parameter threshold, the current physiological parameter data is determined to be abnormal, and a safety alarm is issued; if any one of the air indexes in the current air index data is greater than the corresponding target threshold range, the current air index data is determined to be abnormal, and a safety alarm is issued; if any one of the foundation pit retaining structure parameters in the current foundation pit retaining structure data is greater than the corresponding preset foundation pit retaining structure threshold, the current foundation pit retaining structure data is determined to be abnormal, and a safety alarm is issued.

[0072] At the same time, various thresholds are set for various indicator parameters of the foundation pit retaining structure according to the safety needs of the project. If an indicator exceeds the corresponding threshold, an alarm will also be triggered and sent to the mobile monitoring terminal to remind on-site management personnel.

[0073] In addition, the thresholds of various parameters set in the present invention are not fixed, but can be adjusted dynamically; in the setting of various thresholds, the present invention can make the following personalized adjustments according to different scenarios and individuals:

[0074] 1. Adjustment of the thresholds of workers' physiological health parameters: Through investigation and research, the normal physiological parameter ranges of workers of different age groups and genders under various labor intensities are determined, so that the thresholds of workers' physiological parameters set in the system are more scientific and reasonable.

[0075] 2. Adjustment of the threshold values ​​of various air index parameters: The present invention assumes that the environment is in a deep foundation pit excavation environment, so the appropriate environmental parameter safety threshold standards should be selected based on the temperature, humidity, noise, toxic gases and other parameter characteristics of this construction environment, combined with the predictive air index parameters obtained after data processing, and the adjustment tolerance range should be considered.

[0076] 3. Adjustment of structural deformation thresholds: Based on the soil conditions of foundation pits in different construction projects (for example, the soil conditions of each deep foundation pit excavation project are different. The soil layer of this project may be clay, while that of other projects may be sandy soil, etc., and the corresponding support designs for different situations are also different), support structure design and other factors, combined with the requirements of the design drawings, professional engineering and technical personnel shall determine (the design drawings will contain the allowable force values ​​of the support structure, and different thresholds will be set according to the design requirements of the drawings) reasonable allowable values ​​of structural deformation and alarm thresholds that vary from project to project.

[0077] 4. Adjustment of the adjustable parameter setting interface: Provide an adjustable parameter setting interface in the monitoring software, allowing the thresholds of various parameters to be adjusted within a certain range, facilitating personalized settings according to different project requirements.

[0078] Finally, professional technicians are regularly organized to maintain and calibrate the parameter thresholds in the system, promptly identify indicators that need to be adjusted and optimized, and ensure the rationality of parameter settings.

[0079] Compared with the existing technology, the present invention adopts a more systematic and intelligent design concept, which can better meet the safety supervision needs of complex construction environments.

[0080] Technical effect:

[0081] 1. The present invention adopts the deep integration of multi-source data to build a more comprehensive and three-dimensional construction safety monitoring system.

[0082] 2. The present invention arranges real-time intelligent analysis and processing to realize dynamic linkage monitoring of workers, environment and structure.

[0083] 3. The present invention is configured to quickly respond and issue an early warning when monitoring data is abnormal, thereby improving the safety management level of the construction site.

[0084] 4. The present invention is versatile and easily expandable, and can be applied to safety monitoring in various high-risk construction environments.

[0085] Furthermore, if Figure 3 As shown, based on the above-mentioned deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning method, the present invention also provides a deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning system, wherein the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning system includes:

[0086] The historical data collection module 51 is used to obtain the historical physiological index information of the construction personnel and the historical environmental information of the deep foundation pit, and pre-process the historical physiological index information according to the preset requirements to obtain the historical physiological parameter data, wherein the historical environmental information includes the historical air index data and the historical foundation pit retaining structure data;

[0087] A historical data processing module 52 is used to process the historical physiological parameter data according to a factor analysis method to obtain the overall physiological health index of the construction personnel;

[0088] The air index range determination module 53 is used to perform linear analysis on the historical air index data according to the overall physiological health index to obtain the target threshold range of the historical air index data;

[0089] The data abnormality alarm module 54 is used to obtain current physiological parameter data and current environmental data, and if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm prompt is issued.

[0090] Furthermore, if Figure 4 As shown, based on the above-mentioned deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning method and system, the present invention also provides a terminal accordingly, and the terminal includes a processor 10, a memory 20 and a display 30. Figure 4 Only some components of the terminal are shown, but it should be understood that it is not required to implement all of the components shown, and more or fewer components may be implemented instead.

[0091] In some embodiments, the memory 20 may be an internal storage unit of the terminal, such as a hard disk or memory of the terminal. In other embodiments, the memory 20 may also be an external storage device of the terminal, such as a plug-in hard disk, a smart memory card (Smart Media Card, SMC), a secure digital (SecureDigital, SD) card, a flash card (Flash Card), etc. equipped on the terminal. Further, the memory 20 may also include both an internal storage unit of the terminal and an external storage device. The memory 20 is used to store application software and various types of data installed on the terminal, such as the program code of the installation terminal. The memory 20 may also be used to temporarily store data that has been output or is to be output. In one embodiment, the memory 20 stores a deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning program 40, which can be executed by the processor 10, thereby realizing the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning method in this application.

[0092] In some embodiments, the processor 10 can be a central processing unit (CPU), a microprocessor or other data processing chip, used to run the program code or process data stored in the memory 20, such as executing the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers.

[0093] In some embodiments, the display 30 may be an LED display, a liquid crystal display, a touch-sensitive liquid crystal display, an OLED (Organic Light-Emitting Diode) touch device, etc. The display 30 is used to display information on the terminal and to display a visual user interface. The components 10-30 of the terminal communicate with each other via a system bus.

[0094] In one embodiment, when the processor 10 executes the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning program 40 in the memory 20, the following steps are implemented:

[0095] Acquire historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and pre-process the historical physiological index information according to preset requirements to obtain historical physiological parameter data, wherein the historical environmental information includes historical air index data and historical foundation pit retaining structure data;

[0096] Processing the historical physiological parameter data according to factor analysis to obtain the overall physiological health index of the construction personnel;

[0097] Performing linear analysis on the historical air index data according to the overall physiological health index to obtain target threshold ranges for the historical air index data;

[0098] The current physiological parameter data and the current environmental data are obtained, and if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm is issued.

[0099] The acquisition of historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and preprocessing of the historical physiological index information according to preset requirements to obtain historical physiological parameter data specifically include:

[0100] Acquire historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and set preset physiological parameter thresholds corresponding to each physiological parameter in the historical physiological index information;

[0101] Each physiological parameter in the historical physiological index information is compared with the corresponding preset physiological parameter threshold, and the physiological parameters in the historical physiological index information that exceed the preset physiological parameter threshold are deleted to obtain the historical physiological parameter data.

[0102] The process of processing the historical physiological parameter data according to the factor analysis method to obtain the overall physiological health index of the construction workers specifically includes:

[0103] Performing data standardization processing on the historical physiological parameter data to obtain standardized physiological parameter data, wherein the calculation formula for the data standardization processing is: (x-μ) / σ, x is the historical physiological parameter data corresponding to each construction worker, μ is the mean value of all construction workers in the historical physiological parameter data under any physiological indicator, and σ is the standard deviation of all construction workers in the historical physiological parameter data under any physiological indicator;

[0104] Constructing a standardized matrix according to the standardized physiological parameter data, and obtaining a corresponding correlation coefficient matrix according to the standardized matrix;

[0105] Acquire multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and determine the number of common factors in the historical physiological parameter data and the multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the multiple eigenvalues ​​and the multiple eigenvectors;

[0106] The numerical value corresponding to the common factor is determined according to the historical physiological parameter data and the multivariate linear relationship equation, and the overall physiological health index is calculated according to the numerical value corresponding to the common factor and the distribution weight of the common factor in the historical physiological parameter data.

[0107] The step of constructing a standardized matrix according to the standardized physiological parameter data and obtaining a corresponding correlation coefficient matrix according to the standardized matrix specifically includes:

[0108] Obtaining the number of construction workers corresponding to the historical physiological parameter data, and constructing a standardized matrix according to the number of construction workers and the standardized physiological parameter data;

[0109] Calculate the covariance and standard deviation corresponding to different physiological index parameters in the standardized matrix, and obtain the correlation coefficient matrix based on the covariance and the standard deviation, wherein the calculation formula of the correlation coefficient matrix is: ρ(X1, X2)=COV(X1, X2) / (σX1σX2), wherein X1 and X2 represent different physiological index parameters, ρ(X1, X2) is the correlation coefficient matrix, COV(X1, X2) is the covariance of different physiological index parameters, and σX1σX2 is the standard deviation of different physiological index parameters.

[0110] The step of obtaining a plurality of eigenvalues ​​and corresponding eigenvectors in the correlation coefficient matrix, and determining the number of common factors in the historical physiological parameter data and the multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the plurality of eigenvalues ​​and the plurality of eigenvectors, specifically includes:

[0111] Acquire multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and arrange the multiple eigenvalues ​​in descending order, and when the multiple eigenvalues ​​meet a preset condition, obtain the target number of the common factors;

[0112] The target number of eigenvalues ​​are extracted from the plurality of eigenvalues ​​in order from large to small, a load matrix is ​​constructed according to the target number of eigenvalues, and the multivariate linear relationship equation between each common factor and the historical physiological parameter data is obtained according to the load matrix.

[0113] The linear analysis of the historical air index data according to the overall physiological health index to obtain the target threshold range of the historical air index data specifically includes:

[0114] According to the overall physiological health index, the historical air index data are subjected to linear analysis and processing to obtain a functional relationship between the historical air index data and the overall physiological health index, wherein the expression of the functional relationship is: Yi=kθ+b, wherein Yi is any air index data in the historical air index data, θ is the overall physiological health parameter corresponding to each construction worker, and k and b are constants in the functional relationship;

[0115] The target threshold range corresponding to each of the historical air index data is determined according to the overall physiological health index and the functional relationship.

[0116] The current environmental data includes current air index data and current foundation pit retaining structure data; the current physiological parameter data and current environmental data are obtained, and if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm prompt is issued, specifically including:

[0117] Acquire the current physiological parameter data, the current air index data and the current foundation pit retaining structure data, and set a preset foundation pit retaining structure threshold according to the historical foundation pit retaining structure data;

[0118] If any one of the physiological parameters in the current physiological parameter data is greater than the corresponding preset physiological parameter threshold, the current physiological parameter data is determined to be abnormal, and a safety alarm is issued;

[0119] If any of the current air index data is greater than the corresponding target threshold range, the current air index data is determined to be abnormal, and a safety alarm is issued;

[0120] If any foundation pit retaining structure parameter in the current foundation pit retaining structure data is greater than the corresponding preset foundation pit retaining structure threshold, the current foundation pit retaining structure data is determined to be abnormal, and a safety alarm is issued.

[0121] The present invention also provides a computer-readable storage medium, wherein the computer-readable storage medium stores a physiological health monitoring and environmental monitoring early warning program for deep foundation pit construction workers, and when the physiological health monitoring and environmental monitoring early warning program for deep foundation pit construction workers is executed by a processor, the steps of the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers as described above are implemented.

[0122] In summary, the present invention provides a method and related equipment for physiological health monitoring and environmental monitoring early warning of deep foundation pit construction workers, the method comprising: obtaining historical physiological index information of construction workers and historical environmental information of deep foundation pits, and preprocessing the historical physiological index information according to preset requirements to obtain historical physiological parameter data, wherein the historical environmental information includes historical air index data and historical foundation pit enclosure structure data; performing data processing on the historical physiological parameter data according to factor analysis to obtain the overall physiological health index of the construction workers; performing linear analysis processing on the historical air index data according to the overall physiological health index to obtain the target threshold range of the historical air index data; obtaining current physiological parameter data and current environmental data, if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm prompt is issued. The present invention obtains the physiological index data and environmental data of construction workers during deep foundation pit excavation, combines the physiological index data and environmental data, and constructs a linear relationship between the two, thereby realizing dynamic linkage monitoring of workers, environment, and structure. It can monitor the generation of abnormal data more quickly and accurately, and issue early warning prompts in a timely manner, effectively ensuring the normal construction of deep foundation pits and the personal safety of construction workers.

[0123] It should be noted that, in this article, the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or terminal including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or terminal. In the absence of further restrictions, an element defined by the sentence "comprises a ..." does not exclude the presence of other identical elements in the process, method, article or terminal including the element.

[0124] Of course, those skilled in the art can understand that all or part of the processes in the above-mentioned embodiments can be implemented by instructing related hardware (such as a processor, a controller, etc.) through a computer program, and the program can be stored in a computer-readable storage medium that can be read by a computer, and the program can include the processes of the above-mentioned method embodiments when executed. The computer-readable storage medium can be a memory, a disk, an optical disk, etc.

[0125] It should be understood that the application of the present invention is not limited to the above examples. For ordinary technicians in this field, improvements or changes can be made based on the above description. All these improvements and changes should fall within the scope of protection of the claims attached to the present invention.

Claims

1. A method for physiological health monitoring and environmental monitoring and early warning of deep foundation pit construction workers. It is characterized in that The physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers includes: Acquire historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and pre-process the historical physiological index information according to preset requirements to obtain historical physiological parameter data, wherein the historical environmental information includes historical air index data and historical foundation pit retaining structure data; Processing the historical physiological parameter data according to factor analysis to obtain the overall physiological health index of the construction personnel; The data processing of the historical physiological parameter data according to the factor analysis method to obtain the overall physiological health index of the construction personnel specifically includes: Performing data standardization processing on the historical physiological parameter data to obtain standardized physiological parameter data, wherein the calculation formula for the data standardization processing is: (x-μ) / σ, x is the historical physiological parameter data corresponding to each construction worker, μ is the mean value of all construction workers in the historical physiological parameter data under any physiological indicator, and σ is the standard deviation of all construction workers in the historical physiological parameter data under any physiological indicator; Constructing a standardized matrix according to the standardized physiological parameter data, and obtaining a corresponding correlation coefficient matrix according to the standardized matrix; Acquire multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and determine the number of common factors in the historical physiological parameter data and the multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the multiple eigenvalues ​​and the multiple eigenvectors; Determine the value corresponding to the common factor according to the historical physiological parameter data and the multivariate linear relationship equation, and calculate the overall physiological health index according to the value corresponding to the common factor and the distribution weight of the common factor in the historical physiological parameter data; The step of obtaining a plurality of eigenvalues ​​and corresponding eigenvectors in the correlation coefficient matrix, and determining the number of common factors in the historical physiological parameter data and a multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the plurality of eigenvalues ​​and the plurality of eigenvectors, specifically includes: Acquire multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and arrange the multiple eigenvalues ​​in descending order, and when the multiple eigenvalues ​​meet a preset condition, obtain the target number of the common factors; Extracting the target number of eigenvalues ​​from the plurality of eigenvalues ​​in descending order, constructing a load matrix according to the target number of eigenvalues, and obtaining the multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the load matrix; Performing linear analysis on the historical air index data according to the overall physiological health index to obtain target threshold ranges for the historical air index data; The linear analysis and processing of the historical air index data according to the overall physiological health index to obtain the target threshold range of the historical air index data specifically includes: According to the overall physiological health index, the historical air index data are subjected to linear analysis and processing to obtain a functional relationship between the historical air index data and the overall physiological health index, wherein the expression of the functional relationship is: Yi=kθ+b, wherein Yi is any air index data in the historical air index data, θ is the overall physiological health parameter corresponding to each construction worker, and k and b are constants in the functional relationship; Determine the target threshold range corresponding to each historical air index data according to the overall physiological health index and the functional relationship; The current physiological parameter data and the current environmental data are obtained, and if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm is issued.

2. The method for physiological health monitoring and environmental monitoring early warning of deep foundation pit construction workers according to claim 1, It is characterized in that The method of obtaining historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and preprocessing the historical physiological index information according to preset requirements to obtain historical physiological parameter data specifically includes: Acquire historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and set preset physiological parameter thresholds corresponding to each physiological parameter in the historical physiological index information; Each physiological parameter in the historical physiological index information is compared with the corresponding preset physiological parameter threshold, and the physiological parameters in the historical physiological index information that exceed the preset physiological parameter threshold are deleted to obtain the historical physiological parameter data.

3. The method for physiological health monitoring and environmental monitoring early warning of deep foundation pit construction workers according to claim 1, It is characterized in that The step of constructing a standardized matrix according to the standardized physiological parameter data and obtaining a corresponding correlation coefficient matrix according to the standardized matrix specifically includes: Obtaining the number of construction workers corresponding to the historical physiological parameter data, and constructing a standardized matrix according to the number of construction workers and the standardized physiological parameter data; Calculate the covariance and standard deviation corresponding to different physiological index parameters in the standardized matrix, and obtain the correlation coefficient matrix based on the covariance and the standard deviation, wherein the calculation formula of the correlation coefficient matrix is: ρ(X1, X2)=COV(X1, X2) / (σX1σX2), wherein X1 and X2 represent different physiological index parameters, ρ(X1, X2) is the correlation coefficient matrix, COV(X1, X2) is the covariance of different physiological index parameters, and σX1σX2 is the standard deviation of different physiological index parameters.

4. The method for physiological health monitoring and environmental monitoring early warning of deep foundation pit construction workers according to claim 1, It is characterized in that The current environmental data includes current air index data and current foundation pit retaining structure data; the current physiological parameter data and current environmental data are obtained, and if the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm prompt is issued, specifically including: Acquire the current physiological parameter data, the current air index data and the current foundation pit retaining structure data, and set a preset foundation pit retaining structure threshold according to the historical foundation pit retaining structure data; If any one of the physiological parameters in the current physiological parameter data is greater than the corresponding preset physiological parameter threshold, the current physiological parameter data is determined to be abnormal, and a safety alarm is issued; If any of the current air index data is greater than the corresponding target threshold range, the current air index data is determined to be abnormal, and a safety alarm is issued; If any foundation pit retaining structure parameter in the current foundation pit retaining structure data is greater than the corresponding preset foundation pit retaining structure threshold, the current foundation pit retaining structure data is determined to be abnormal, and a safety alarm is issued.

5. A physiological health monitoring and environmental monitoring early warning system for deep foundation pit construction workers. It is characterized in that The deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning system includes: A historical data collection module is used to obtain historical physiological index information of construction personnel and historical environmental information of deep foundation pits, and pre-process the historical physiological index information according to preset requirements to obtain historical physiological parameter data, wherein the historical environmental information includes historical air index data and historical foundation pit retaining structure data; A historical data processing module, used for processing the historical physiological parameter data according to a factor analysis method to obtain the overall physiological health index of the construction personnel; The data processing of the historical physiological parameter data according to the factor analysis method to obtain the overall physiological health index of the construction personnel specifically includes: Performing data standardization processing on the historical physiological parameter data to obtain standardized physiological parameter data, wherein the calculation formula for the data standardization processing is: (x-μ) / σ, x is the historical physiological parameter data corresponding to each construction worker, μ is the mean value of all construction workers in the historical physiological parameter data under any physiological indicator, and σ is the standard deviation of all construction workers in the historical physiological parameter data under any physiological indicator; Constructing a standardized matrix according to the standardized physiological parameter data, and obtaining a corresponding correlation coefficient matrix according to the standardized matrix; Acquire multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and determine the number of common factors in the historical physiological parameter data and the multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the multiple eigenvalues ​​and the multiple eigenvectors; Determine the value corresponding to the common factor according to the historical physiological parameter data and the multivariate linear relationship equation, and calculate the overall physiological health index according to the value corresponding to the common factor and the distribution weight of the common factor in the historical physiological parameter data; The step of obtaining a plurality of eigenvalues ​​and corresponding eigenvectors in the correlation coefficient matrix, and determining the number of common factors in the historical physiological parameter data and a multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the plurality of eigenvalues ​​and the plurality of eigenvectors, specifically includes: Acquire multiple eigenvalues ​​and corresponding multiple eigenvectors in the correlation coefficient matrix, and arrange the multiple eigenvalues ​​in descending order, and when the multiple eigenvalues ​​meet a preset condition, obtain the target number of the common factors; Extracting the target number of eigenvalues ​​from the plurality of eigenvalues ​​in descending order, constructing a load matrix according to the target number of eigenvalues, and obtaining the multivariate linear relationship equation between each common factor and the historical physiological parameter data according to the load matrix; An air index range determination module, used to perform linear analysis on the historical air index data according to the overall physiological health index to obtain a target threshold range for the historical air index data; The linear analysis and processing of the historical air index data according to the overall physiological health index to obtain the target threshold range of the historical air index data specifically includes: According to the overall physiological health index, the historical air index data are subjected to linear analysis and processing to obtain a functional relationship between the historical air index data and the overall physiological health index, wherein the expression of the functional relationship is: Yi=kθ+b, wherein Yi is any air index data in the historical air index data, θ is the overall physiological health parameter corresponding to each construction worker, and k and b are constants in the functional relationship; Determine the target threshold range corresponding to each of the historical air index data according to the overall physiological health index and the functional relationship; The data abnormality alarm module is used to obtain current physiological parameter data and current environmental data. If the current physiological parameter data is judged to be abnormal according to the preset requirements or the current environmental data is judged to be abnormal according to the target threshold range, a safety alarm prompt is issued.

6. A terminal, It is characterized in that The terminal includes: a memory, a processor, and a deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning program stored in the memory and runnable on the processor. When the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning program is executed by the processor, the steps of the deep foundation pit construction worker physiological health monitoring and environmental monitoring early warning method as described in any one of claims 1-4 are implemented.

7. A computer-readable storage medium, It is characterized in that The computer-readable storage medium stores a physiological health monitoring and environmental monitoring early warning program for deep foundation pit construction workers. When the physiological health monitoring and environmental monitoring early warning program for deep foundation pit construction workers is executed by the processor, the steps of the physiological health monitoring and environmental monitoring early warning method for deep foundation pit construction workers as described in any one of claims 1-4 are implemented.