A prefabricated box-type fan foundation and its application method

By combining prefabricated panels and connectors, the complexity of connections and fatigue resistance of prefabricated box-type wind turbine foundations are solved, enabling efficient and stable wind turbine foundation construction, which is suitable for large wind turbine units.

CN118148174BActive Publication Date: 2026-11-10NORTHWEST ELECTRIC POWER DESIGN INST OF CHINA POWER ENG CONSULTING GRP +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410352227.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-03-26
Publication Date
2026-11-10
Estimated Expiration
2044-03-26

AI Technical Summary

Technical Problem

The existing prefabricated panel connection method of the prefabricated box-type wind turbine foundation is complicated, it is difficult to ensure strength, the construction speed is slow, and the fatigue resistance is insufficient, which makes it difficult to meet the needs of large wind turbine units.

Method used

The structure adopts a combination of prefabricated panels and connectors, including prefabricated panels, prefabricated corner connectors, longitudinal reinforcement, transverse reinforcement, sleeve connectors and grouting material, which are connected by tenon and groove, angle steel embedded parts and other methods to form a stable wind turbine foundation structure.

Benefits of technology

It improves the strength and fatigue resistance of prefabricated box-type wind turbine foundations, simplifies the construction process, shortens the construction period, and reduces construction costs, making it suitable for wind power projects in remote areas.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118148174B_ABST
    Figure CN118148174B_ABST
Patent Text Reader

Abstract

This invention belongs to the field of wind power engineering and discloses a prefabricated box-type wind turbine foundation and its usage method. The invention includes a column and several prefabricated units; the prefabricated units are arranged circumferentially along the column to form the foundation structure; the column is located at the center of the foundation structure; the column is connected to the prefabricated units; adjacent prefabricated units are connected by connectors; the prefabricated units have a cavity structure. This invention solves the problems of complex connection structure and difficulty in ensuring strength of prefabricated panels in prefabricated box-type wind turbine foundations, possesses good strength and fatigue resistance, and has high installation efficiency, significantly saving construction time and showing broad engineering application prospects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of wind power generation engineering, specifically to a prefabricated box-type wind turbine foundation and its usage method. Background Technology

[0002] The wind turbine foundation is the fixed end of the wind turbine generator set. Together with the tower, it erects the turbine at a height of 90-150 meters and is a crucial component ensuring the normal power generation of the wind turbine. Wind turbine foundations are typically reinforced concrete structures, designed in different forms according to local geological conditions. They are constructed primarily based on the tower load and the climate environment in which the turbine is located, in accordance with high-rise building construction standards.

[0003] With the increasing size of wind turbine units and the rising cost of construction labor, traditional cast-in-place reinforced concrete wind turbine foundations are unable to meet the needs of some remote wind power projects due to high project costs, inconvenient material transportation, low construction efficiency, environmentally unfriendly on-site concrete pouring, and difficulty in controlling concrete pouring quality.

[0004] With the widespread application of industrialized construction, the advantages of prefabricated construction are becoming increasingly apparent. Prefabricated box-type wind turbine foundations can be prefabricated in the factory and assembled on-site, solving the difficulties of material transportation; they can also effectively shorten the construction period, reduce labor costs, and address the problems of low construction efficiency and difficulty in ensuring pouring quality in on-site concrete pouring. However, the connection points of prefabricated box-type wind turbine foundation panels are generally constructed using cast-in-place concrete sections, resulting in slow construction speed and difficulty in ensuring concrete pouring quality. Wind turbine units bear not only enormous wind loads but also alternating and random characteristics. The strength, stiffness, and fatigue issues of the foundation structure are primary considerations. The connection strength and fatigue resistance between prefabricated components determine the overall load-bearing performance of the box-type wind turbine foundation, requiring a focused and rational solution to the connection schemes between the various prefabricated components.

[0005] Therefore, a connection scheme for assembling prefabricated panels of box-type wind turbine foundations is provided, which has the characteristics of good stress performance, simple structure and easy construction, so as to solve the key technical problems in this field. Summary of the Invention

[0006] The purpose of this invention is to provide a fatigue-resistant connection method for prefabricated box-type wind turbine foundation plates, which solves the problems of complex assembly and connection methods for prefabricated box-type wind turbine foundation plates, avoids on-site concrete pouring, and greatly improves the splicing construction efficiency of prefabricated components.

[0007] To achieve the above objectives, the present invention provides the following technical solution.

[0008] A prefabricated box-type wind turbine foundation includes a column and several prefabricated units; the several prefabricated units are arranged circumferentially along the column to form a foundation structure; the column is located at the center of the foundation structure.

[0009] The column is connected to several prefabricated units; adjacent prefabricated units are connected by connectors; the prefabricated units have a cavity structure.

[0010] Preferably, the prefabricated unit comprises a plurality of prefabricated panels 3; the plurality of prefabricated panels 3 form the cavity structure.

[0011] Preferably, adjacent precast panels are connected by connectors; the precast panels are divided into several small precast panels, and the several small precast panels are spliced ​​together to form a precast panel.

[0012] Preferably, the connector comprises a plurality of prefabricated corner connectors.

[0013] Preferably, the prefabricated corner connector is an integral prefabricated panel; the prefabricated corner connector includes a first connector, a second connector, a third connector, and a fourth connector; The first connector includes an L-shaped plate and a triangular prism plate with a right angle on its bottom surface connected thereto; The second connector has a T-shaped cross-section and is a T-shaped structural plate. The third connector includes two plates connected at their ends, forming an included angle smaller than a flat angle, thus forming a V-shaped structure. It also includes another plate connected to the connection point of the two plates. The fourth connector includes two first connectors, the ends of which are connected, forming an included angle smaller than a flat angle, thus forming a V-shaped structure. There is also another plate that is connected to the two first connectors at the connection point.

[0014] Preferably, longitudinal steel bars, transverse steel bars, and tie bars are provided inside the precast slab and the precast corner connector.

[0015] Preferably, sleeve connectors are embedded in the precast slab and the precast corner connector respectively; one end of the longitudinal steel bar is connected to the sleeve connector inside the precast slab, and the other end extends out of the precast slab; one end of the longitudinal steel bar is connected to the sleeve connector inside the precast corner connector, and the other end extends out of the precast corner connector.

[0016] Preferably, both the precast panel and the precast corner connector have a tenon at one end and a groove at the other end; the tenon of the precast panel is connected to the groove of the precast corner connector; the groove of the precast panel is connected to the tenon of the precast corner connector; each small precast panel has a tenon and a groove, and adjacent small precast panels are connected by the tenon and the groove; an elastic sealing gasket is provided between the tenon and the groove.

[0017] Preferably, the precast slab and the precast corner connector are connected by an angle steel embedded part.

[0018] A method for using a prefabricated box-type fan foundation, comprising the following steps: S1: Arrange several prefabricated units around the circumference of the column to form a basic structure, with the column placed at the center of the basic structure; S2: Connect two adjacent prefabricated units using connectors; S3: Connect the prefabricated unit to the column, add filling material to the cavity structure inside the prefabricated unit to form the fan foundation.

[0019] Compared with the prior art, the present invention has the following beneficial effects: This invention solves the problems of complex connection structure and difficulty in ensuring strength of prefabricated panels for prefabricated box-type wind turbine foundations by connecting the connectors to the prefabricated panels. It has good strength and fatigue resistance, high installation efficiency, and can significantly save construction time, and has broad engineering application prospects.

[0020] Furthermore, the present invention incorporates steel sleeve connectors and tenon-groove joints in the precast slabs, making the internal connection of the wind turbine foundation more stable and less prone to splitting, thus enhancing the stability of the wind turbine foundation. The precast slabs are disassembled into small precast slabs for easy installation, which has the advantages of convenient transportation and assembly. The sleeve connectors complete the connection of the longitudinal steel bars inside each component to withstand the axial tension and compression between the slabs. The connection is achieved by using tenon 9 and groove 10 or angle steel embedded parts to withstand the transverse shearing between the slabs. Grouting material is used to seal the connection, so that the connected structure has good strength and fatigue resistance. Attached Figure Description

[0021] The accompanying drawings described herein are for illustrative purposes only and are not intended to limit the scope of the invention in any way. Furthermore, the shapes and proportions of the components in the drawings are merely schematic to aid in understanding the invention and do not specifically limit the shapes and proportions of the components. In the drawings: Figure 1 This is a schematic diagram of the internal structure of a prefabricated box-type fan foundation according to the present invention; Figure 2 This is a schematic diagram of the structure of the present invention; Figure 3 for Figure 2 A schematic diagram of the planar structure; Figure 4 for Figure 3 A schematic diagram of the AA cross-section; Figure 5 This is Embodiment 1 of the present invention. Figure 3 BB cross-sectional diagram; Figure 6 This is Embodiment 2 of the present invention. Figure 3 BB cross-sectional diagram; Figure 7 This is a schematic diagram of the structure of the connector of the prefabricated corner connector of the present invention; (a) is the first connector; (b) is the second connector; (c) is the third connector; (d) is the fourth connector; Figure 8 This is a schematic diagram of the sleeve connector of the present invention; Figure 9 This is a numerical analysis model diagram of the sleeve connector of the present invention; Figure 10 The figure shows the fatigue numerical simulation results of the sleeve connector of the present invention.

[0022] In the figure, 1-column, 2-precast unit, 3-precast slab, 4-precast corner connector, 5-longitudinal reinforcement, 6-transverse reinforcement, 7-tie bar, 8-sleeve connector, 9-tenon, 10-groove, 11-elastic sealing gasket, 12-angle steel embedded part, 13-grouting material. Detailed Implementation

[0023] To enable those skilled in the art to better understand the technical solutions of this invention, the technical solutions of the embodiments of this invention will be clearly and completely described below with reference to the accompanying drawings. Obviously, the described embodiments are only some embodiments of this invention, and not all embodiments. Based on the embodiments of this invention, all other embodiments obtained by those skilled in the art without creative effort should fall within the scope of protection of this invention.

[0024] It should be noted that when a component is said to be "set on" another component, it can be directly on the other component or there may be an intervening component. When a component is said to be "connected to" another component, it can be directly connected to the other component or there may be an intervening component.

[0025] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this invention pertains. The terminology used herein in the description of the invention is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention.

[0026] This invention provides a prefabricated box-type fan foundation including a column 1 and a prefabricated unit 2; a fatigue-resistant connection device for the prefabricated box-type fan foundation plate includes a prefabricated plate 3, a prefabricated corner connector 4, longitudinal steel bars 5, transverse steel bars 6, tie bars 7, a sleeve connector 8, sealing grout 13, and an angle steel embedded part 12; or the angle steel embedded part 12 can be replaced with a tenon 9, a groove 10, and an elastic sealing gasket 11.

[0027] like Figure 1 and Figure 2 As shown, a prefabricated box-type wind turbine foundation includes a column 1 and several prefabricated units 2. The several prefabricated units 2 are arranged around the circumference of the column 1 to form a foundation structure. The column 1 is located at the center of the foundation structure. The prefabricated unit 2 includes several prefabricated panels 3. The several prefabricated panels 3 form a cavity structure. The cavity structure can be filled with filling material, preferably concrete or soil excavated from the wind turbine foundation site, which can ensure the stability of the wind turbine foundation and allow for the secondary use of the excavated soil without wasting resources.

[0028] The column 1 is connected to several prefabricated units 2; adjacent prefabricated units 2 are connected by connectors. Preferably, the connector is a prefabricated corner connector 4. Since the overall size of the wind turbine foundation is large, for ease of transportation and assembly, the prefabricated panels 3 can be disassembled into smaller prefabricated panels for easy installation, and multiple smaller prefabricated panels can be spliced ​​together to form the prefabricated panel 3. Preferably, since the prefabricated panels 3 are all planar structures, the connection between the smaller prefabricated panels is a direct splicing. The splicing connection of straight sections between the smaller prefabricated panels and the connection between the prefabricated corner connector 4 and the straight section prefabricated panel 3 can both be achieved.

[0029] like Figure 3 and Figure 4 As shown, precast slab 3 and precast corner connector 4 are formed by concrete pouring and curing in the factory. All reinforcement is completed during factory prefabrication, eliminating the need for on-site tying. Both precast slab 3 and precast corner connector 4 are internally equipped with longitudinal reinforcement 5, transverse reinforcement 6, and tie bars 7. The longitudinal reinforcement 5 and transverse reinforcement 6 are arranged at intervals, and the tie bars 7 connect one end to the longitudinal reinforcement 5 and the other end to the transverse reinforcement 6, serving a tying function. The reinforcement arrangement makes the connection between precast slab 3 and precast corner connector 4 more stable and less prone to splitting, enhancing the stability of the wind turbine foundation. Furthermore, each small precast component also contains longitudinal reinforcement 5, transverse reinforcement 6, and tie bars 7, resulting in very high strength for the precast slab 3 formed after the small precast components are connected. The tie bars 7 improve the overall integrity of the reinforcement cage and serve a tying function.

[0030] A sleeve connector 8 is provided at one end of the precast slab 3, and the longitudinal steel bars 5 inside the precast slab 3 are connected to the sleeve connector 8 and located inside the sleeve connector 8; the longitudinal steel bars 5 inside the precast corner connector 4 extend out of the precast corner connector 4 and are exposed on the outside; the protruding end of the longitudinal steel bars 5 of the precast corner connector 4 is inserted into the sleeve connector 8 of the precast slab 3, so that the sleeve connector 8 of the precast slab 3 is connected to the longitudinal steel bars 5 of the precast corner connector 4, so that the precast slab 3 and the precast corner connector 4 are connected; additionally, it is feasible to provide a sleeve at one end of the precast corner connector 4. The longitudinal reinforcing bars 5 inside the precast corner connector 4 are connected to the sleeve connector 8 and located inside the sleeve connector 8; the longitudinal reinforcing bars 5 inside the precast slab 3 extend out of the precast slab 3 and are exposed on the outside; the protruding ends of the longitudinal reinforcing bars 5 of the precast slab 3 are inserted into the sleeve connector 8 of the precast corner connector 4, so that the sleeve connector 8 of the precast corner connector 4 is connected to the longitudinal reinforcing bars 5 of the precast slab 3, so that the precast slab 3 and the precast corner connector 4 are connected; the transverse reinforcing bars 6 at the connection end of the precast slab 3 are densified within a range of 3 times the slab thickness, so that the end of the precast slab 3 is more solid. The gap at the interface between the precast slab 3 and the precast corner connector 4 is sealed with high-strength grout 13, so that the splicing is more solid and reliable.

[0031] Secondly, a small precast component is equipped with a sleeve connector 8. The longitudinal reinforcing bars 5 inside the small precast component are connected to the sleeve connector 8 and located inside the sleeve connector 8. The longitudinal reinforcing bars 5 inside another small precast component adjacent to the first small precast component extend out of the other small precast component and are exposed. The protruding end of the longitudinal reinforcing bars 5 of the other small precast component is inserted into the sleeve connector 8 of the first small precast component, so that the sleeve connector 8 of the first small precast component is connected to the longitudinal reinforcing bars 5 of the other small precast component, thereby connecting the adjacent small precast components and splicing them to form several precast slabs 3. The transverse reinforcing bars 6 at the connection ends of the precast slabs 3 are denser within a range of 3 times the slab thickness. The gaps at the interfaces between adjacent small precast components are sealed with high-strength grout 13, making the splicing more firm and reliable.

[0032] The transverse reinforcing bars 6 inside each component are connected by sleeve connectors 8 to withstand the transverse tensile and compressive forces between the plates, so that the connected structure has good strength and fatigue resistance.

[0033] like Figure 5 and Figure 6As shown, a tenon 9 is provided at one end of the precast panel 3, and a groove 10 is provided at one end of the precast corner connector 4. The precast panel 3 and the precast corner connector 4 are connected by inserting the tenon 9 into the groove 10. This connection method gives the connected components advantages such as high strength and good seismic performance. An elastic sealing gasket 11 is provided at the connection between the tenon 9 and the groove 10. The elastic sealing gasket 11 can tightly fit the two contact surfaces, providing a good sealing effect and absorbing impact and vibration, reducing friction and wear between the precast components. Alternatively, a tenon 9 can be provided at one end of the precast corner connector 4, and a groove 10 can be provided at one end of the precast panel 3. The precast panel 3 and the precast corner connector 4 are connected by inserting the tenon 9 into the groove 10. An elastic sealing gasket 11 is provided at the connection between the tenon 9 and the groove 10. The elastic sealing gasket 11 can tightly fit the two contact surfaces, providing a good sealing effect and absorbing impact and vibration, reducing friction and wear between the precast components.

[0034] Secondly, between adjacent precast blocks, tenons 9 and grooves 10 are respectively provided. The tenons 9 are inserted into the grooves 10, and an elastic sealing gasket 11 is provided at the connection between the tenons 9 and the grooves 10 to complete the connection between adjacent precast blocks.

[0035] Another implementation involves setting angle steel embedded parts 12 at one end of the precast slab 3 and one end of the precast corner connector 4 or at the end of an adjacent small precast piece. The connection between the precast pieces is completed by connecting the angle steel embedded parts 12 at both ends. The advantages of the angle steel embedded parts 12 connection are that it can enhance the stability of the structure, improve seismic performance, improve corrosion resistance, and increase load-bearing capacity.

[0036] Finally, high-strength grout 13 is used to seal and protect the connecting parts at the connection between the tenon 9 and the groove 10 and the connection between the angle steel embedded part 12, thus completing the assembly. The lateral shearing action between the precast panels is resisted by the connection between the tenon 9 and the groove 10 or by the welding of the angle steel embedded part 12.

[0037] like Figure 7 As shown in (a), (b), (c), and (d), the prefabricated corner connector 4 includes a first connector, a second connector, a third connector, and a fourth connector. The prefabricated panels 3 at the top and bottom of adjacent prefabricated units 2 are connected by the corner connector 4; the prefabricated panels 3 on the outer walls of adjacent prefabricated units 2 are connected by the prefabricated corner connector 4; adjacent prefabricated panels 3 within a prefabricated unit 2 are connected by the prefabricated corner connector 4; the connection between the prefabricated panels 3 and the prefabricated corner connector 4 makes the wind turbine foundation structure more stable and reliable.

[0038] like Figure 8 As shown, the prefabricated slab 3 of the assembled wind turbine foundation of the present invention is connected to the connecting parts by a sleeve connector 8.

[0039] like Figure 9 The figure shown is a numerical analysis model diagram of the sleeve connector of the present invention.

[0040] like Figure 10 The figure shown is a numerical simulation result of the fatigue of the sleeve connector of the present invention.

[0041] In summary, this connection method can effectively solve the problems of complex connection structure and difficulty in ensuring strength of prefabricated panels for prefabricated box-type wind turbine foundations. It has good strength and fatigue resistance, high installation efficiency, and can significantly save construction time, thus having broad prospects for engineering applications.

[0042] Furthermore, the connection of the precast panel 3 described in this invention can also be used for the connection of precast components of other structures, not limited to wind turbine foundations.

[0043] The present invention discloses a method for using a prefabricated box-type fan foundation, comprising the following steps: S1: Connect the small prefabricated pieces of prefabricated panel 3 together to form several prefabricated panels 3; S2: The longitudinal steel bars 5 at the protruding end of the precast slab 3 are inserted into the sleeve connector 8 inside the precast corner connector 4 and connected; the longitudinal steel bars at the protruding end of the precast corner connector 4 are inserted into the sleeve connector 8 inside the precast slab 3 and connected; the connection between the longitudinal steel bars 5 and the sleeve connector 8 is sealed with high-strength grout 13. S3: Connect the tenon 9 of the precast panel to the groove 10 of the precast corner connector; connect the groove 10 of the precast panel 3 to the tenon 9 of the precast corner connector 4; Alternatively, the precast panel 3 can be connected to the precast corner connector 4 via the angle steel embedded part 12; S4: The precast slab 3 is connected to the precast corner connector 4 to form several precast units 2. Each precast unit 2 includes six faces, which form a cavity structure, and filler is added into the cavity structure. S5: Arrange the prefabricated unit 2 around the circumference of the column 1 to form the foundation structure, with the column 1 located at the center of the foundation structure; S6: Connect the prefabricated unit 2 to the column 1 to form the wind turbine foundation.

[0044] Example 1 A prefabricated box-type wind turbine foundation includes a column 1 and several prefabricated units 2. The prefabricated units 2 are arranged around the circumference of the column 1 to form a foundation structure. The column 1 is located at the center of the foundation structure. Each prefabricated unit 2 has six faces, including five planes and one curved surface. The five planes are prefabricated panels 3, and the curved surface is the one connected to the column 1. The six faces together form a cavity structure, and the cavity structure can be filled with a filling material, preferably concrete or soil excavated from the foundation of the wind turbine.

[0045] The column 1 is connected to several prefabricated units 2; adjacent prefabricated units 2 are connected by prefabricated corner connectors 4. The prefabricated panel 3 can be disassembled into small prefabricated panels for easy installation, and multiple small prefabricated panels can be spliced ​​together to form the prefabricated panel 3; since the prefabricated panel 3 is a planar structure, the connection between the small prefabricated panels is a direct splicing.

[0046] Precast slabs 3 and precast corner connectors 4 are formed and cured in the factory using formwork, concrete, and curing. All reinforcing bars are installed during factory prefabrication, eliminating the need for on-site tying. Both precast slabs 3 and precast corner connectors 4 have longitudinal reinforcing bars 5, transverse reinforcing bars 6, and tie bars 7 inside. The longitudinal reinforcing bars 5 and transverse reinforcing bars 6 are arranged alternately, and the tie bars 7 are connected at one end to the longitudinal reinforcing bars 5 and at the other end to the transverse reinforcing bars 6. Furthermore, each small precast component also has longitudinal reinforcing bars 5, transverse reinforcing bars 6, and tie bars 7 inside.

[0047] One end of the precast slab 3 is provided with a sleeve connector 8, and the longitudinal steel bar 5 inside the precast slab 3 is connected to the sleeve connector 8 and located inside the sleeve connector 8; the longitudinal steel bar 5 inside the precast corner connector 4 extends out of the precast corner connector 4 and is exposed on the outside; the extended end of the longitudinal steel bar 5 of the precast corner connector 4 is inserted into the sleeve connector 8 of the precast slab 3, so that the sleeve connector 8 of the precast slab 3 is connected to the longitudinal steel bar 5 of the precast corner connector 4, so that the precast slab 3 and the precast corner connector 4 are connected; Alternatively, one end of the precast corner connector 4 is provided with a sleeve connector 8, and the longitudinal steel bars 5 inside the precast corner connector 4 are connected to the sleeve connector 8 and located inside the sleeve connector 8; the longitudinal steel bars 5 inside the precast slab 3 extend out of the precast slab 3 and are exposed on the outside; the protruding ends of the longitudinal steel bars 5 of the precast slab 3 are inserted into the sleeve connector 8 of the precast corner connector 4, so that the sleeve connector 8 of the precast corner connector 4 is connected to the longitudinal steel bars 5 of the precast slab 3, thus connecting the precast slab 3 and the precast corner connector 4; the transverse steel bars 6 at the connection end of the precast slab 3 are denser within a range of 3 times the slab thickness. The gap at the interface between the precast slab 3 and the precast corner connector 4 is sealed with high-strength grout 13.

[0048] Secondly, a small precast component is equipped with a sleeve connector 8. The longitudinal steel bars 5 inside the small precast component are connected to the sleeve connector 8 and located inside the sleeve connector 8. The longitudinal steel bars 5 inside another small precast component adjacent to the first small precast component extend out of the other small precast component and are exposed. The protruding end of the longitudinal steel bars 5 of the other small precast component is inserted into the sleeve connector 8 of the first small precast component, so that the sleeve connector 8 of the first small precast component is connected to the longitudinal steel bars 5 of the other small precast component, thereby connecting the adjacent small precast components and splicing them to form several precast slabs 3. The transverse steel bars 6 at the connection ends of the precast slabs 3 are denser within a range of 3 times the slab thickness. The gaps at the interfaces between adjacent small precast components are sealed with high-strength grout 13 to complete the assembly.

[0049] One end of the precast panel 3 is provided with a tenon 9, and one end of the precast corner connector 4 is provided with a groove 10. The precast panel 3 and the precast corner connector 4 are connected by inserting the tenon 9 into the groove 10, and an elastic sealing gasket 11 is provided at the connection between the tenon 9 and the groove 10. Alternatively, one end of the precast corner connector 4 is provided with a tenon 9, and one end of the precast panel 3 is provided with a groove 10. The precast panel 3 and the precast corner connector 4 are connected by inserting the tenon 9 into the groove 10, and an elastic sealing gasket 11 is provided at the connection between the tenon 9 and the groove 10.

[0050] Secondly, between adjacent precast blocks, tenons 9 and grooves 10 are respectively provided. The tenons 9 are inserted into the grooves 10, and an elastic sealing gasket 11 is provided at the connection between the tenons 9 and the grooves 10 to complete the connection between adjacent precast blocks.

[0051] Finally, high-strength grout 13 is used to seal and protect the connecting parts at the connection between the tenon 9 and the groove 10.

[0052] In this embodiment, experimental examples are provided to verify the connection effect of the grouting sleeve connector 8, and real performance test data are provided. The specific parameters of the specimens are shown in Table 1 below, and the parameters of the high-strength grouting material are shown in Table 2 below.

[0053] Table 1 Main Technical Parameters of Fully Grouted Sleeve Connectors

[0054] Table 2 Main Technical Parameters of High-Strength Grouting Material

[0055] In this embodiment, the fatigue performance of the grouting sleeve connector was numerically simulated and analyzed using finite element software. The numerical analysis results are shown in Table 3.

[0056]

[0057] Specifically, as shown in Table 3, the stress amplitude range for the steel reinforcement connection stress ratio R = 0.4~0.8 is 113~55 MPa, and the fatigue life range is 2.05×10⁻⁶. 6 ~4.14×10 6 .

[0058] In this embodiment, a uniaxial tensile test was conducted on the grouting sleeve connector 8. The uniaxial tensile test data are shown in Table 4.

[0059]

[0060] Specifically, as shown in Table 4, the tensile strength of the three specimens of the grouting sleeve connector at the final failure point under uniaxial tension was greater than the ultimate tensile strength of the connecting steel bar HRB400.

[0061] In this embodiment, fatigue tests were conducted on the grouting sleeve connectors. The fatigue test results of the specimens at a steel reinforcement connection stress ratio R=0.7 are shown in Table 5.

[0062]

[0063] In the experimental example, the grouting sleeve connector 8 remained in the elastic stage until it reached its fatigue life. The failure mode upon reaching fatigue life was the breakage of the outer reinforcing bar of the sleeve connector 8; neither the sleeve connector 8 nor the grouting material was damaged. As shown in Table 5, when the reinforcing bar connection stress ratio R = 0.7, and the stress amplitude is 60 MPa, the fatigue life is 1.0 × 10⁻⁶. 7 When the stress amplitude is 70 MPa, the fatigue life is 2.77 × 10⁻⁶. 6 Second-rate.

[0064] Based on the above finite element numerical simulation results and fatigue test results, it can be verified that the fatigue resistance of the precast slab 3 of the prefabricated wind turbine box foundation using the grouting sleeve connector 8 meets the requirements. In this embodiment of the prefabricated wind turbine box foundation, according to the numerical simulation calculation results under fatigue conditions in the experimental example, the fatigue stress amplitude of the reinforcing steel in the middle of the precast slab 3 is approximately distributed between 20MPa and 50MPa. Considering the influence of the soil around the wind turbine foundation, the fatigue life of the foundation can be calculated as 2.0 × 10⁻⁶. 6 Secondary design.

[0065] Example 2 A prefabricated box-type wind turbine foundation includes a column 1 and several prefabricated units 2. The prefabricated units 2 are arranged around the circumference of the column 1 to form a foundation structure. The column 1 is located at the center of the foundation structure. Each prefabricated unit 2 has six faces, including five planes and one curved surface. The five planes are prefabricated panels 3, and the curved surface is the one connected to the column 1. The six faces together form a cavity structure, and the cavity structure can be filled with a filling material, preferably concrete or soil excavated from the foundation of the wind turbine.

[0066] The column 1 is connected to several prefabricated units 2; adjacent prefabricated units 2 are connected by prefabricated corner connectors 4. The prefabricated panel 3 can be disassembled into small prefabricated panels for easy installation, and multiple small prefabricated panels can be spliced ​​together to form the prefabricated panel 3; since the prefabricated panel 3 is a planar structure, the connection between the small prefabricated panels is a direct splicing.

[0067] Precast slabs 3 and precast corner connectors 4 are formed and cured in the factory using formwork, concrete, and curing. All reinforcing bars are installed during factory prefabrication, eliminating the need for on-site tying. Both precast slabs 3 and precast corner connectors 4 have longitudinal reinforcing bars 5, transverse reinforcing bars 6, and tie bars 7 inside. The longitudinal reinforcing bars 5 and transverse reinforcing bars 6 are arranged alternately, and the tie bars 7 are connected at one end to the longitudinal reinforcing bars 5 and at the other end to the transverse reinforcing bars 6. Furthermore, each small precast component also has longitudinal reinforcing bars 5, transverse reinforcing bars 6, and tie bars 7 inside.

[0068] One end of the precast slab 3 is provided with a sleeve connector 8, and the longitudinal steel bar 5 inside the precast slab 3 is connected to the sleeve connector 8 and located inside the sleeve connector 8; the longitudinal steel bar 5 inside the precast corner connector 4 extends out of the precast corner connector 4 and is exposed on the outside; the extended end of the longitudinal steel bar 5 of the precast corner connector 4 is inserted into the sleeve connector 8 of the precast slab 3, so that the sleeve connector 8 of the precast slab 3 is connected to the longitudinal steel bar 5 of the precast corner connector 4, so that the precast slab 3 and the precast corner connector 4 are connected; Alternatively, one end of the precast corner connector 4 is provided with a sleeve connector 8, and the longitudinal steel bars 5 inside the precast corner connector 4 are connected to the sleeve connector 8 and located inside the sleeve connector 8; the longitudinal steel bars 5 inside the precast slab 3 extend out of the precast slab 3 and are exposed on the outside; the protruding ends of the longitudinal steel bars 5 of the precast slab 3 are inserted into the sleeve connector 8 of the precast corner connector 4, so that the sleeve connector 8 of the precast corner connector 4 is connected to the longitudinal steel bars 5 of the precast slab 3, thus connecting the precast slab 3 and the precast corner connector 4; the transverse steel bars 6 at the connection end of the precast slab 3 are denser within a range of 3 times the slab thickness. The gap at the interface between the precast slab 3 and the precast corner connector 4 is sealed with high-strength grout 13.

[0069] Secondly, a small precast component is equipped with a sleeve connector 8. The longitudinal reinforcing bars 5 inside the small precast component are connected to the sleeve connector 8 and located inside the sleeve connector 8. The longitudinal reinforcing bars 5 inside another small precast component adjacent to the first small precast component extend out of the other small precast component and are exposed. The protruding end of the longitudinal reinforcing bars 5 of the other small precast component is inserted into the sleeve connector 8 of the first small precast component, so that the sleeve connector 8 of the first small precast component is connected to the longitudinal reinforcing bars 5 of the other small precast component, thereby connecting the adjacent small precast components and splicing them to form several precast slabs 3. The transverse reinforcing bars 6 at the connection ends of the precast slabs 3 are denser within a range of 3 times the slab thickness. The gaps at the interfaces between adjacent small precast components are sealed with high-strength grout 13.

[0070] Angle steel embedded parts 12 are respectively set at one end of the precast slab 3 and one end of the precast corner connector 4 or the end of the adjacent small precast piece. The connection between each precast piece is completed by connecting the angle steel embedded parts 12 at both ends.

[0071] Finally, high-strength grout 13 is used to seal and protect the connecting parts at the connection of the angle steel embedded parts 12, and the assembly is completed.

[0072] Many embodiments and applications beyond the examples provided will be apparent to those skilled in the art upon reading the foregoing description. Therefore, the scope of this teaching should not be determined by reference to the foregoing description, but rather by reference to the foregoing claims and the full scope of their equivalents. For purposes of completeness, all articles and references, including patent applications and publications, are incorporated herein by reference. The omission of any aspect of the subject matter disclosed herein in the foregoing claims is not intended as a waiver of that subject matter, nor should it be construed as an indication that the applicant has not considered that subject matter as part of the disclosed inventive subject matter.

[0073] The above content provides a further detailed description of the present invention. It should not be construed that the specific embodiments of the present invention are limited to this. For those skilled in the art, several simple deductions or substitutions can be made without departing from the concept of the present invention, and all such deductions or substitutions should be considered to fall within the scope of protection of the present invention as defined by the submitted claims.

Claims

1. A prefabricated box-type fan foundation, characterized in that, It includes a pedestal (1) and several prefabricated units (2); the several prefabricated units (2) are arranged circumferentially along the pedestal (1) to form a basic structure; the pedestal (1) is located at the center of the basic structure; The column (1) is connected to several prefabricated units (2); adjacent prefabricated units (2) are connected by connectors; the prefabricated unit (2) is a cavity structure composed of multiple prefabricated panels (3); The prefabricated unit (2) includes a plurality of prefabricated panels (3); the plurality of prefabricated panels (3) form the cavity structure; The adjacent precast panels (3) are connected by connectors; the precast panels (3) are divided into several small precast panels, and the several small precast panels are spliced ​​together to form the precast panels (3). The connector includes several prefabricated corner connectors (4). The prefabricated corner connector (4) is an integral prefabricated panel; the prefabricated corner connector (4) includes a first connector, a second connector, a third connector and a fourth connector; The first connector includes an L-shaped plate and a triangular prism plate with a right angle on its bottom surface connected thereto; The second connector has a T-shaped cross-section and is a T-shaped structural plate. The third connector includes two plates connected at their ends, forming an included angle smaller than a flat angle, thus forming a V-shaped structure. It also includes another plate connected to the connection point of the two plates. The fourth connector includes two first connectors, the ends of which are connected, forming an included angle smaller than a flat angle, thus forming a V-shaped structure. There is also another plate that is connected to the connection point of the two first connectors. The precast slab (3) and the precast corner connector (4) are both provided with longitudinal steel bars (5), transverse steel bars (6) and tie bars (7); The precast slab (3) and the precast corner connector (4) are respectively embedded with sleeve connectors (8); one end of the longitudinal steel bar (5) is connected to the sleeve connector (8) inside the precast slab (3), and the other end extends out of the precast slab (3); one end of the longitudinal steel bar (5) is connected to the sleeve connector (8) inside the precast corner connector (4), and the other end extends out of the precast corner connector (4); the connection between the longitudinal steel bar (5) and the sleeve connector (8) is sealed with grout (13).

2. The prefabricated box-type fan foundation according to claim 1, characterized in that, Both the precast panel (3) and the precast corner connector (4) are provided with a tenon (9) at one end and a groove (10) at the other end; the tenon (9) of the precast panel (3) is connected to the groove (10) of the precast corner connector (4); the groove (10) of the precast panel (3) is connected to the tenon (9) of the precast corner connector (4); each small precast panel is provided with a tenon (9) and a groove (10), and adjacent small precast panels are connected by the tenon (9) and the groove (10); An elastic sealing gasket (11) is provided between the tenon (9) and the groove (10).

3. The prefabricated box-type fan foundation according to claim 1, characterized in that, The precast slab (3) and the precast corner connector (4) are connected by an angle steel embedded part (12).

4. A method for using a prefabricated box-type fan foundation according to any one of claims 1-3, characterized in that the steps are as follows: include: S1: Arrange several prefabricated units (2) around the circumference of the column (1) to form a basic structure, with the column (1) placed at the center of the basic structure; S2: Connect two adjacent prefabricated units (2) together using connectors; S3: Connect the prefabricated unit (2) to the column (1) and add filling material to the cavity structure inside the prefabricated unit (2) to form the fan foundation.

Citation Information

Patent Citations

  • Fabricated box foundation of land wind turbine generator and construction method

    CN115012442A

  • Fabricated box type fan foundation

    CN221989382U

  • modular WIND POWER PLANT FOUNDATION

    RU167022U1