Adaptive configuration method and system for injection production line based on production work order

Through the adaptive configuration method and system of the injection production line based on production work orders, the work order completion rate and delay rate are identified, and the configuration parameters are optimized, which solves the problems of low work order completion rate and insufficient fault tolerance caused by production line failures, and improves production efficiency and product quality.

CN118195097BActive Publication Date: 2024-10-29BEIJING YONGKANG PHARM FACTORY
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202410496677.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-24
Publication Date
2024-10-29
Estimated Expiration
2044-04-24

AI Technical Summary

Technical Problem

The injection production line often encounters failures, resulting in the work order completion rate not reaching the expected level, and the fault tolerance is low, making it impossible to timely feedback the work order delay rate and optimize it.

Method used

Provide an adaptive configuration method and system for injection production lines based on production work orders. By receiving work order queues, identifying work order completion rates, collecting historical failure probabilities of production line nodes, calculating work order delay rates, and in adaptive optimization memory Optimize configuration parameters in the library to improve work order completion rate.

Benefits of technology

It improves the fault tolerance performance of the production line, ensures that the work order completion rate reaches the preset level, reduces the impact of faults, and improves production efficiency and product quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118195097B_ABST
    Figure CN118195097B_ABST
Patent Text Reader

Abstract

The present application provides an adaptive configuration method for an injection production line based on a production work order, and relates to the technical field of production line configuration. The method includes: receiving an injection production work order queue, then identifying and obtaining the work order completion rate, collecting the historical failure rate corresponding to each production line node, and then obtaining the work order delay rate, adjusting feedback according to the work order completion rate, and obtaining the work order completion rate after feedback. When the preset completion rate is not met, the completion rate is used as an adaptive target, and optimization is performed in the adaptive optimization memory library, and the optimized configuration parameters are output, and production operations are performed according to the optimized configuration parameters. The present application mainly solves the problem that the production line often encounters failures, resulting in the actual work order completion rate failing to reach the expected level, and its fault tolerance is low, and the work order delay rate cannot be fed back in time and optimized. The work order completion situation is optimized according to historical failure situations, which improves the fault tolerance performance of the production line.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of production line configuration, and in particular to a method and system for adaptively configuring an injection production line based on a production work order. Background Art

[0002] With the diversification and personalization of market demand, the manufacturing industry needs to be able to respond quickly and adapt to the production needs of different products. As a common drug dosage form, the production process of injections needs to strictly comply with relevant regulations and quality standards, and it also faces the challenges of diversified product demand and production efficiency. In the pharmaceutical industry, the injection production line is a highly complex system involving multiple links and equipment. Due to the particularity of pharmaceutical products, there are extremely high requirements for quality and safety in the production process. Therefore, any sudden failure may have a serious impact on production, resulting in a decrease in the completion rate of work orders, and may even affect product quality and patient life safety. Therefore, it is of great practical significance to develop an adaptive configuration method for injection production lines based on production work orders.

[0003] However, in the process of implementing the technical solution of the invention in the embodiment of the present application, it is found that the above technology has at least the following technical problems:

[0004] The production line often encounters failures, resulting in the actual work order completion rate failing to reach the expected level. In addition, its fault tolerance is low and it is unable to promptly provide feedback on the work order delay rate and make optimizations. Summary of the invention

[0005] This application mainly solves the problem that it is impossible to achieve reasonable allocation of resources, resulting in excessive use of certain resources or repeated use of resources with higher failure rates, affecting production efficiency and failing to timely feedback on work order delay rates and optimize them.

[0006] In view of the above problems, the present application provides an injection production line adaptive configuration method and system based on production work orders. In the first aspect, the present application provides an injection production line adaptive configuration method based on production work orders, the method comprising: receiving an injection production work order queue, the injection production work order queue being a work order set table based on the timing of the injection production line; identifying the injection production work order queue according to the current configuration parameters of the injection production line, and obtaining the work order completion rate of the injection production work order queue; collecting the historical failure probabilities corresponding to each production line node in the injection production line; identifying the injection production work order queue according to the historical failure probabilities, and obtaining the work order delay rate; adjusting and feeding back the work order completion rate according to the work order delay rate to obtain the work order completion rate after feedback; when the work order completion rate after feedback does not meet the preset work order completion rate, taking the preset work order completion rate as the adaptive target, taking the current configuration parameters of the injection production line as the input variables, performing optimization in the adaptive optimization memory library, and outputting the optimized configuration parameters of the injection production line; and performing production operations on the injection production line according to the optimized configuration parameters.

[0007] In the second aspect, the present application provides an injection production line adaptive configuration system based on production work orders, the system comprising: a work order queue receiving module, the work order queue receiving module is used to receive the injection production work order queue, the injection production work order queue is a work order collection table based on the injection production line timing reception; a work order completion rate acquisition module, the work order completion rate acquisition module is used to identify the injection production work order queue according to the current configuration parameters of the injection production line, and obtain the work order completion rate of the injection production work order queue; collect the corresponding information of each production line node in the injection production line historical failure probability; identifying the injection production work order queue according to the historical failure probability to obtain the work order delay rate; adjusting and feeding back the work order completion rate according to the work order delay rate to obtain the work order completion rate after feedback; when the work order completion rate after feedback does not meet the preset work order completion rate, taking the preset work order completion rate as the adaptive target and the current configuration parameters of the injection production line as the input variables, performing optimization in the adaptive optimization memory library to output the optimized configuration parameters of the injection production line; performing production operations on the injection production line according to the optimized configuration parameters.

[0008] One or more technical solutions provided in this application have at least the following technical effects or advantages:

[0009] The present application provides an adaptive configuration method for an injection production line based on a production work order, and relates to the technical field of production line configuration. The method comprises: receiving an injection production work order queue, and then identifying and obtaining a work order completion rate, collecting historical failure rates corresponding to each production line node, and then obtaining a work order delay rate, and adjusting feedback according to the work order completion rate to obtain the work order completion rate after feedback. When the preset completion rate is not met, the completion rate is used as an adaptive target, and optimization is performed in an adaptive optimization memory library, and optimized configuration parameters are outputted, and production operations are performed according to the optimized configuration parameters.

[0010] This application mainly solves the problem that the production line often encounters failures, resulting in the actual work order completion rate failing to reach the expected level, and its fault tolerance is low, and the work order delay rate cannot be fed back in time and optimized. The work order completion status is optimized based on historical failure conditions, which improves the fault tolerance performance of the production line.

[0011] The above description is only an overview of the technical solution of the present application. In order to more clearly understand the technical means of the present application, it can be implemented in accordance with the contents of the specification. In order to make the above and other purposes, features and advantages of the present application more obvious and easy to understand, the specific implementation methods of the present application are listed below. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] In order to more clearly illustrate the technical solutions in the present application or the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other drawings can be obtained based on the provided drawings without paying any creative work.

[0013] Figure 1 A schematic diagram of a method for adaptively configuring an injection production line based on a production work order is provided for an embodiment of the present application;

[0014] Figure 2 A schematic flow chart of a method for obtaining a work order delay rate in a method for adaptively configuring an injection production line based on a production work order is provided for an embodiment of the present application;

[0015] Figure 3 A schematic diagram of a method flow for outputting optimized configuration parameters of an injection production line in an injection production line adaptive configuration method based on a production work order is provided for an embodiment of the present application;

[0016] Figure 4 A structural schematic diagram of an injection production line adaptive configuration system based on a production work order is provided for an embodiment of the present application.

[0017] Explanation of the reference numerals: work order queue receiving module 10 , work order completion rate acquisition module 20 , historical fault probability collection module 30 , work order delay rate acquisition module 40 , work order completion rate acquisition module 50 , optimized configuration parameter output module 60 , production operation module 70 . DETAILED DESCRIPTION

[0018] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0019] This application mainly solves the problem that the production line often encounters failures, resulting in the actual work order completion rate failing to reach the expected level, and its fault tolerance is low, and the work order delay rate cannot be fed back in time and optimized. The work order completion status is optimized based on historical failure conditions, which improves the fault tolerance performance of the production line.

[0020] In order to better understand the above technical solution, the above solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods:

[0021] Embodiment 1

[0022] like Figure 1 The method for adaptively configuring an injection production line based on a production work order is shown, and the method comprises:

[0023] Receive an injection production work order queue, where the injection production work order queue is a collection table of work orders received based on the injection production line time sequence;

[0024] Specifically, first, receive a queue of injection production work orders. This queue is a collection table of work orders received based on the timing of the injection production line. Each work order contains information such as specific production requirements, specifications, quantities, etc. Analyze each work order in detail to understand its characteristics, such as production type, required raw materials, production time, etc. Based on the characteristics of the work order, the system will evaluate whether the existing resources meet the production needs and make reasonable allocations based on resource usage. According to the characteristics of the work order and the results of the resource evaluation, the system will perform dynamic configuration, including adjusting equipment parameters, scheduling production processes, etc., to meet production needs. Through this adaptive configuration method of injection production lines based on production work orders, it is possible to achieve automation and intelligence of production, improve production efficiency, meet the needs of different work orders, and ensure the rational use of resources.

[0025] Identify the injection production work order queue according to the current configuration parameters of the injection production line, and obtain the work order completion rate of the injection production work order queue;

[0026] Specifically, first, collect data on current configuration parameters from various devices, sensors, and systems in the injection production line. These data may include equipment status, operating parameters, material inventory, etc. Analyze the collected configuration parameters to identify the changing trends and abnormalities of key parameters. This includes cleaning, classification, and preliminary analysis of the data, matching and analyzing according to the characteristics of the current configuration parameters and the production work order queue. For example, some work orders may have specific requirements for equipment parameters, and whether the current configuration parameters meet these requirements needs to be judged. Calculate the work order completion rate based on the number of completed work orders and the total number of work orders. This can be done through an automated system or manual statistics. At the same time, it is necessary to analyze the reasons for unfinished work orders, such as equipment failure, insufficient materials, etc. Feedback the work order completion rate and related analysis results to production management personnel. Continuous monitoring and adjustment: During the production process, the work order completion rate and changes in configuration parameters should be continuously monitored. If abnormalities are found or adjustments are required, timely measures should be taken, such as adjusting equipment parameters, scheduling production processes, etc. Through the above steps, the real-time status of the production line can be better understood, providing strong support for optimizing production and improving efficiency. At the same time, it also helps to reduce risks and waste in the production process and improve the competitiveness of enterprises.

[0027] Collecting the historical failure probabilities corresponding to each production line node in the injection production line;

[0028] Specifically, first, identify the various nodes in the injection production line, which may include different equipment, machines or production stages. For each production line node, collect its historical failure data. This data should include information such as the time, cause, impact and repair measures of the failure. Based on the historical failure data, analyze and identify the common failure modes and causes of each node. This helps to understand why each node is prone to failure and the possible consequences when the failure occurs. Based on the historical data, calculate the failure probability for each production line node. This can be done by counting the number of failures of each node within a certain period of time. Based on the failure probability of each node, formulate corresponding preventive measures. For example, for nodes with a high probability of failure, the frequency of inspection and maintenance can be increased, or other preventive measures can be taken to reduce the possibility of failure. By collecting and using the historical failure probabilities corresponding to each production line node in the injection production line, the operating status and potential problems of the production line can be better understood. This not only helps to improve production efficiency, but also effectively reduces the possibility of failure and ensures the stability and continuity of production.

[0029] Identify the injection production work order queue according to the historical failure probability and obtain the work order delay rate;

[0030] Specifically, first, establish a database containing the historical failure probability of each production line node. This data should be classified by node, and the time, cause and duration of the failure should be recorded in chronological order. Perform a detailed analysis of the received injection production work order queue to understand the urgency of each work order, the required products and the expected completion time. Match each work order in the work order queue with the historical failure probability in the database. This can be done by querying the failure records of similar products, production conditions and time ranges. Based on the historical failure probability, conduct a risk assessment on the work order queue. High-risk work orders may require more attention and resource allocation, while low-risk work orders can be handled according to the normal process. According to the risk assessment results, the resource allocation is dynamically adjusted. For example, for high-risk work orders, more equipment resources, manpower and technical support can be allocated preferentially to ensure that they are completed on time. Real-time monitoring and feedback: During the production process, continuously monitor the progress of the work order and the operating status of the node. If it is found that the actual progress deviates greatly from the expected, immediately investigate and take necessary adjustment measures. Calculate the delay rate of each work order based on the actual completion time and the expected completion time. The delay rate can be calculated by the formula delay time / estimated completion time. Through the above steps, historical fault data can be better utilized to identify and manage the injection production work order queue, reduce the work order delay rate, and improve production efficiency and product quality.

[0031] Adjusting and feeding back the work order completion rate according to the work order delay rate to obtain the work order completion rate after feedback;

[0032] Specifically, delay rate calculation: Determine the expected completion time for each work order. This is based on the production plan and historical data. Track the actual completion time of each work order and compare it with the expected completion time. Calculate the delay rate of each work order using the formula delay time / estimated completion time. Completion rate calculation: Count the number of completed and uncompleted work orders. Calculate the preliminary work order completion rate using the formula number of completed work orders / total number of work orders. Adjustment feedback: Determine the cause of the delay, such as equipment failure, material shortage, staff absence, etc. Adjust the work order completion rate according to the cause of the delay: For delays caused by force majeure factors (such as equipment failure, external supply problems), maintain or appropriately reduce the completion rate. For predictable and controllable factors, such as production process adjustments or planned maintenance, the completion rate can be appropriately adjusted upward, as these are usually planned and controllable. For delays caused by unknown or unexpected factors, special attention should be paid and consideration should be given to reducing the completion rate. Feedback result output: Feedback the adjusted work order completion rate to relevant production managers. Provide analytical reports on the causes and effects of delays to help managers better understand the health of the production line. Optimization and improvement: Based on the feedback on completion rate and delay reasons, evaluate the efficiency of existing production processes, equipment maintenance plans and staffing. Develop targeted improvement measures, such as optimizing production processes, strengthening equipment maintenance, improving staff training, etc. Implement improvement measures and continuously monitor their effects.

[0033] When the work order completion rate after feedback does not meet the preset work order completion rate, the preset work order completion rate is used as the adaptive target, the current configuration parameters of the injection production line are used as input variables, and the optimization is performed in the adaptive optimization memory library to output the optimized configuration parameters of the injection production line;

[0034] Specifically, first, set the preset work order completion rate as the goal of adaptive optimization. This goal should be formulated based on the actual needs and production capacity of the enterprise. Collect the current configuration parameters of the injection production line, including equipment parameters, production process parameters, personnel configuration, etc. These parameters will be used as input variables for the optimization process. Establish an adaptive optimization memory library, which contains historical optimization configuration parameters, corresponding work order completion rates and other related information. This memory library will provide data support for the optimization process. Select appropriate optimization algorithms, such as genetic algorithms, particle swarm optimization algorithms, etc. These algorithms will be used to find the optimal configuration parameters in the memory library. With the preset work order completion rate as the goal and the current configuration parameters as input, the selected optimization algorithm is used to optimize in the adaptive optimization memory library. This process will be iterated continuously until the optimal configuration parameters that meet the preset work order completion rate are found. According to the output optimized configuration parameters, formulate implementation plans, including equipment adjustment, production process optimization, personnel training, etc. Ensure that these plans can be implemented in actual production. Implement the implementation plan in place and continuously monitor the operation of the production line and the completion of the work order. Adjust and optimize the implementation plan according to the actual situation. Compare the work order completion rate after implementation with the preset work order completion rate to evaluate the optimization effect. If the expected goal is achieved, the optimization process ends; otherwise, it is necessary to search for the best and optimize again. Through the above steps, when the preset work order completion rate is not met, the configuration parameters of the injection production line can be optimized with the preset work order completion rate as the adaptive target. This will help improve the stability and efficiency of the production line, reduce production costs, and enhance the competitiveness of the enterprise.

[0035] The injection production line is operated according to the optimized configuration parameters.

[0036] Specifically, parameter adjustment plan formulation: formulate parameter adjustment plan, including adjustment time, adjustment steps, responsible person, etc. Equipment parameter adjustment: set parameters for equipment in the production line according to the equipment parameter adjustment plan. Test and verify the equipment to ensure that the equipment operates normally and meets production requirements. Record the equipment parameter adjustment results and archive them. Production process optimization: analyze the optimization content of production process parameters and determine the production links and processes that need to be improved. Adjust the existing production process, introduce new processes or improve the original processes. Conduct production simulation or small batch tests to verify the feasibility of the optimized production process. Continuously monitor the actual production situation and further optimize the production process based on the feedback results. Personnel configuration adjustment: adjust and train the personnel in the production line according to the personnel configuration requirements. Ensure that the personnel understand the new configuration parameters and production requirements, and conduct necessary training. Establish a personnel assessment mechanism, conduct regular assessments on personnel, and ensure that the personnel capabilities match the new configuration. Production operation implementation: start production operations according to the adjusted equipment parameters, production process and personnel configuration. Develop a production plan for the initial stage to ensure a smooth transition to the new configuration. Monitor the overall operation of the production line and record production data. Real-time monitoring and adjustment: During the production process, regularly check the equipment operation status, production process execution and product quality. According to the real-time monitoring results, timely adjust the relevant parameters or production plan to ensure stable production. Establish a rapid response mechanism to deal with sudden problems or abnormal situations. Through the above steps, scientific and systematic production operations can be carried out on the injection production line according to the optimized configuration parameters to improve production efficiency and product quality.

[0037] Furthermore, the method of the present application collects the historical failure probabilities corresponding to each production line node in the injection production line, and the method includes:

[0038] Acquire multiple production line nodes of the injection production line;

[0039] Collecting the operating equipment corresponding to the multiple production line nodes, and collecting historical fault information of the operating equipment corresponding to each production line node to obtain a set of historical fault probabilities of the equipment;

[0040] After the equipment historical failure probability set is regularized, the regularized weighted calculation result is output as the historical failure probability corresponding to each production line node.

[0041] Specifically, obtain multiple production line nodes of the injection production line: determine the layout of the injection production line and clarify the location and function of each production line node. This information can be obtained through field visits or using a production monitoring system. Sort and classify the obtained production line node information, and collect the operating equipment corresponding to the production line node: for each production line node, determine the operating equipment related to it, including but not limited to mechanical, electrical, and automation equipment. Use sensors, data acquisition systems, or other technical means to collect the operating data, status information, etc. of these equipment. Collect historical equipment failure information: Combine equipment maintenance records, production logs, and other information to collect historical failure information of each operating equipment. Record the time, cause, impact, and treatment method of the failure to provide a data basis for subsequent analysis. Calculate the historical failure probability set of equipment: Sort and classify the collected historical failure data, and count the frequency of various types of failures. Calculate the failure probability of each device based on the failure frequency to form a historical failure probability set of equipment. Regularize the historical failure probability set of equipment: In order to eliminate the influence of factors such as scale and importance between different equipment, regularization is required. Normalization and standardization can be used to convert the failure probability into a relative value to make it comparable. Calculate the regularized weighted results: According to the regularized failure probability set, perform weighted calculations on the equipment corresponding to each production line node. Factors such as the equipment's operating time, load, and maintenance records can be considered for a comprehensive weighted analysis. Output the historical failure probability corresponding to each production line node: Output the results of the regularized weighted calculation as the historical failure probability corresponding to each production line node. Reports, charts, or other visualizations can be generated to facilitate analysis and decision-making. Through the above steps, multiple production line nodes of the injection production line can be obtained, the corresponding operating equipment can be collected, and the historical failure probability of each device can be calculated. These data can help companies understand the operating status and potential risks of the equipment, so as to formulate targeted maintenance and preventive measures to ensure the stability and continuity of production.

[0042] Furthermore, if Figure 2 As shown, the method of the present application identifies the injection production work order queue according to the historical failure probability and obtains the work order delay rate, and the method includes:

[0043] Collecting historical delay time samples corresponding to each production line node when a failure occurs;

[0044] Performing average settlement based on the historical delay time samples to obtain the average delay time of each production line node when a failure occurs;

[0045] When the historical failure probability of any production line node is greater than the preset failure probability, it is marked as an abnormal production line node. The injection production work order queue is identified by the average delay time corresponding to the abnormal production line node to obtain the work order delay rate.

[0046] Specifically, collect the historical delay time samples corresponding to each production line node in the event of a failure: collect the time required from the occurrence of the failure to the restoration of normal production when each production line node fails. These data can be obtained through production monitoring systems, maintenance records, etc. These time samples are sorted and classified to form historical delay time samples for each production line node. Calculate the mean delay time of each production line node in the event of a failure: calculate the mean of the historical delay time samples of each production line node. Simple arithmetic mean or weighted average methods can be used. The calculated mean delay time is used as the delay characteristic of the production line node in the event of a failure. Identify abnormal production line nodes: According to the historical failure probability set, check whether the failure probability of each production line node is greater than the preset failure probability threshold. If the failure probability of a production line node is greater than the preset threshold, it is identified as an abnormal production line node. Identify the injection production work order queue by the mean delay time corresponding to the abnormal production line node: obtain the injection production work order queue currently waiting or being processed. For each abnormal production line node, analyze its impact on the work order queue based on its corresponding mean delay duration. Identify work orders that are greatly affected by abnormal production line nodes, which may face a higher risk of delay. Calculate the work order delay rate: For work orders affected by abnormal production line nodes, calculate the delay rate of the work order based on its estimated completion time and actual delay duration. Summarize the delay rates of all affected work orders to obtain the delay rate of the overall work order queue. Through the above steps, it is possible to identify abnormal production line nodes in the injection production process and analyze their impact on the work order queue. This helps companies to promptly identify potential problems, take corresponding measures, reduce the risk of production delays, and improve production efficiency and product quality.

[0047] Furthermore, the present application method also includes:

[0048] Determining whether the abnormal production line node includes a backup device;

[0049] If the abnormal production line node includes a backup device, a first elimination instruction is triggered, wherein the first elimination instruction is used to eliminate the work order delay caused by the abnormal production line node.

[0050] Specifically, obtain the backup equipment information: determine whether each production line node is equipped with a backup equipment, and record the model, specification, location and other information of the backup equipment. Obtain the status information of the backup equipment, such as whether it is in an available state, whether it has been activated, etc. Determine whether the abnormal production line node contains a backup equipment: compare the information of the abnormal production line node with the backup equipment information to determine whether the abnormal production line node contains a backup equipment. If the abnormal production line node contains a backup equipment, proceed to the next step, otherwise, perform other processing or analysis. Trigger the first elimination instruction: When the abnormal production line node contains a backup equipment, generate the first elimination instruction. The first elimination instruction is used to eliminate the work order delay caused by the abnormal production line node. For example: automatically activate the backup equipment, adjust the production plan, reallocate the work order, etc. Execute the first elimination instruction: Activate the backup equipment: If the backup equipment is not activated, first perform the corresponding startup operation to ensure that it can work normally. Check the status and performance of the backup equipment to ensure that it can meet production needs. Adjust the production plan: Adjust the production plan according to the situation of the work order queue. Reallocate the affected work orders to other normal or activated backup equipment to reduce work order delays. Strengthen monitoring and maintenance: Strengthen monitoring of abnormal production line nodes and spare equipment, and continuously monitor their operating status and performance. Perform necessary maintenance and care to ensure the stability and reliability of the equipment. Emergency repair: If the abnormal production line node cannot quickly resume normal operation, emergency repair should be considered. Through the above steps, the first elimination instruction can be effectively executed to eliminate the work order delay caused by the abnormal production line node. This helps to improve the stability and efficiency of the production process and ensure the smooth execution of the production plan.

[0051] Furthermore, the present application method also includes:

[0052] Establishing an adaptive optimization memory library, wherein, by calling the historical configuration parameter sample library of the injection production line and performing an acceleration stability evaluation on the historical configuration parameter sample library, a configuration parameter sample whose acceleration stability is greater than a preset stability is obtained and configured as the adaptive optimization memory library;

[0053] The preset work order completion rate is used as an adaptive target, and the current configuration parameters of the injection production line are used as input variables to perform optimization in the adaptive optimization memory library.

[0054] Specifically, establish an adaptive optimization memory library: create a memory library to store historical configuration parameter samples of the injection production line. Ensure that the memory library can quickly retrieve and call the required configuration parameter samples. Call the historical configuration parameter sample library of the injection production line: extract relevant configuration parameter samples from the historical configuration parameter sample library. These samples should include the configuration parameters of the injection production line under different conditions. Perform accelerated stability evaluation on the historical configuration parameter sample library: perform stability evaluation on each historical configuration parameter sample. Use appropriate accelerated test methods, such as accelerated life tests, to evaluate the stability of the configuration parameters. Screen out configuration parameter samples with accelerated stability greater than the preset stability: Based on the evaluation results, screen out configuration parameter samples with accelerated stability greater than the preset stability. The preset stability can be determined based on production requirements and industry standards. Configure the configuration parameter samples that meet the conditions as the adaptive optimization memory library: store the screened configuration parameter samples in the adaptive optimization memory library. Ensure that the memory library can quickly retrieve and call these configuration parameter samples that meet the conditions. Set a preset work order completion rate as an adaptive target: set a preset work order completion rate as the target for optimizing configuration parameters. The preset work order completion rate can be determined according to the production goals and market demand of the enterprise. Take the current configuration parameters of the injection production line as input variables: collect the configuration parameters of the current injection production line as input variables for the optimization process. These configuration parameters can include equipment parameters, process parameters, etc. Optimize in the adaptive optimization memory library: select a suitable adaptive optimization algorithm, such as genetic algorithm, particle swarm optimization algorithm, etc. Set the parameters and number of iterations of the algorithm to search for the optimal configuration parameter combination in the memory library. Through continuous iteration and optimization, gradually approach the optimal solution. During the optimization process, the performance and convergence of the algorithm can be monitored in real time, and necessary adjustments and improvements can be made. When the preset number of iterations is reached or other termination conditions are met, the optimization process ends. The final optimal configuration parameter combination is extracted from the memory library for optimizing the production process of the injection production line. Using the adaptive optimization algorithm, the best configuration parameter combination is searched in the adaptive optimization memory library. The algorithm can perform iterative optimization according to the input variables and adaptive objectives to find the optimal solution that meets the conditions. During the optimization process, the parameters and optimization objectives of the algorithm can be adjusted as needed to obtain better optimization results. Through the above steps, an adaptive optimization memory library can be established to store historical configuration parameter samples of the injection production line. By performing accelerated stability evaluation on historical configuration parameters, configuration parameter samples that meet the conditions can be screened out and stored in the adaptive optimization memory library. Then, with the preset work order completion rate as the adaptive target, the adaptive optimization algorithm is used to search in the memory library to find the optimal configuration parameter combination, thereby improving the production efficiency and stability of the injection production line.

[0055] Furthermore, if Figure 3As shown, the method of the present application performs optimization in the adaptive optimization memory library and outputs the optimized configuration parameters of the injection production line, and also includes:

[0056] Identify the equipment coordination relationship of each production line node in the injection production line, and obtain the equipment coordination index of each production line node;

[0057] Selecting an initial optimization device in the injection production line, wherein the initial optimization device is a device randomly selected based on each production line node, and each production line node includes at least one device;

[0058] Performing optimization in the adaptive optimization memory base according to the initial optimization device to obtain the optimized configuration parameters of the initial optimization device;

[0059] Then, according to the equipment coordination index of each production line node and the optimization configuration parameters of the initial optimization equipment, the remaining optimization equipment is coordinated and adapted to obtain the optimization configuration parameters of the remaining optimization equipment;

[0060] According to the optimized configuration parameters of the initial optimization equipment and the optimized configuration parameters of the remaining optimization equipment, the optimized configuration parameters of the injection production line are output.

[0061] Specifically, determine the target of equipment coordination relationship identification: clarify the scope and type of equipment coordination relationship to be identified, such as communication, data transmission, and action coordination between equipment. Determine the target of identifying equipment coordination relationship, such as improving production efficiency, reducing energy consumption, and reducing failures. Collect production line node equipment information: collect detailed information on each production line node equipment, including equipment type, function, performance parameters, etc. Understand the connection method and communication protocol between equipment, as well as data transmission and processing flow. Analyze equipment coordination relationship: identify the coordination relationship between each production line node equipment, such as which equipment needs to cooperate with each other to complete a task. Analyze the communication and data transmission between equipment, including communication frequency, data volume, transmission speed, etc. Determine equipment coordination index: determine the index used to evaluate equipment coordination performance based on the analysis results of equipment coordination relationship. These indicators can include communication success rate, data transmission delay, action coordination accuracy, etc. Collect and calculate equipment coordination index data: process and analyze the collected data to obtain the equipment coordination index value of each production line node. Evaluate and optimize equipment coordination performance: evaluate the equipment coordination performance of each production line node based on the equipment coordination index value. Randomly select initial optimization equipment: Randomly select some equipment from each production line node as the initial optimization equipment. Ensure that each production line node contains at least one selected equipment. Priority sorting: Prioritize the selected equipment and determine the priority based on the synergy relationship. Analyze the data of the initial optimization equipment: Collect historical data, operating parameters, fault records and other related information of the initial optimization equipment. Analyze these data to understand the performance, failure mode and optimization potential of the equipment. Determine the optimization goal: Clarify the optimization goal, such as improving equipment operation efficiency, reducing failure rate, saving energy, etc. Retrieve relevant information in the adaptive optimization memory: Use the adaptive optimization memory to retrieve optimization cases, historical configuration parameters and optimization experience related to the initial optimization equipment. Analyze this information to understand possible optimization paths and methods. Perform optimization operation: Use appropriate optimization algorithms (such as genetic algorithms, simulated annealing algorithms, etc.) to perform optimization operations on the initial optimization equipment. Through iteration and evaluation, continuously adjust the configuration parameters of the equipment to approach the optimization goal. Obtain optimized configuration parameters: After the optimization operation is completed, select appropriate configuration parameters as optimized configuration parameters based on the optimization results and evaluation criteria. Ensure that these parameters can effectively improve the performance of the equipment and meet the optimization goals. Output optimized configuration parameters: Organize the optimized configuration parameters into a report or data format, detailing the adjustment of each parameter and the optimization effect. Provide the report or data to relevant personnel for implementation and adjustment in actual production. Analyze equipment collaboration relationships: Analyze equipment collaboration indicators, such as communication delay, data consistency, etc., to evaluate the collaborative performance between devices. Determine collaborative adaptation goals: Based on the optimized configuration parameters and equipment collaboration indicators of the initial optimization equipment, clarify the collaborative adaptation goals of the remaining optimization equipment.These goals may include improving the efficiency of coordination between devices, reducing communication delays, and enhancing data consistency. Perform collaborative adaptation operations: Obtain optimized configuration parameters: Based on the results of the collaborative adaptation operations, determine the optimized configuration parameters for each remaining optimization device. These parameters should be able to promote collaborative work between devices and meet the preset adaptation goals. Output optimized configuration parameters: Organize the optimized configuration parameters into a report or data format, detailing the adjustment of each parameter and the optimization effect. Integrate optimized configuration parameters: Integrate the optimized configuration parameters of the initial optimization device and the remaining optimization devices. Ensure the consistency and coordination of the parameters to achieve the optimization goals of the entire injection production line. Analyze the overall performance of the production line: Evaluate the impact of the integrated optimized configuration parameters on the performance of the entire injection production line. Analyze changes in the production efficiency, stability, energy consumption, etc. of the production line. Adjust optimized configuration parameters: Fine-tune the optimized configuration parameters based on the analysis results of the overall performance of the production line. Optimization goals include improving production efficiency, reducing energy consumption, and enhancing production line stability. Verify the effectiveness of the optimized configuration parameters: Output optimized configuration parameter report: Generate an optimized configuration parameter report, detailing the configuration parameters, optimization reasons, and expected results of each device. After implementing the optimized configuration parameters, the operating status and performance of the entire injection production line are continuously monitored.

[0062] Furthermore, the method of the present application, performing optimization in the adaptive optimization memory library and outputting the optimized configuration parameters of the injection production line also includes:

[0063] By identifying the process complexity of each production line node in the injection production line, the node complexity index of each production line node is obtained;

[0064] According to the node complexity index, an initial optimal production line is selected from the injection production line, wherein the initial optimal production line is a production line whose node complexity index is greater than a preset node complexity index;

[0065] Optimizing the initial optimization production line in the adaptive optimization memory library to obtain the optimal configuration parameters of the initial optimization production line;

[0066] Then, optimizing the remaining optimal production lines according to the optimal configuration parameters of the initial optimal production line, to obtain the optimal configuration parameters of the remaining optimal production lines;

[0067] According to the optimized configuration parameters of the initial optimized production line and the optimized configuration parameters of the remaining optimized production lines, the optimized configuration parameters of the injection production line are output.

[0068] Specifically, determine the process complexity identification method: select an appropriate process complexity identification method, such as process flow-based analysis, equipment operation complexity assessment, etc. Ensure that the selected method can fully reflect the process complexity of the production line nodes. Collect process data of production line nodes: collect relevant data such as process flow, equipment parameters, operation steps, etc. of each production line node. Ensure the accuracy and completeness of the data for subsequent analysis. Analyze process complexity: Analyze the process complexity of each production line node based on the collected data. Identify key factors such as process steps, operation difficulty, and material conversion complexity involved in the node. Determine node complexity index: Based on the analysis results, determine the index used to evaluate node complexity. These indicators can include the number of process steps, operation difficulty coefficient, material conversion frequency, etc. Assign node complexity index value: According to the determined node complexity index, assign the corresponding index value to each production line node. Ensure that the allocation of index values ​​is reasonable and can reflect the actual process complexity of the node. Set a preset node complexity index value as the standard for selecting the initial optimization production line. This value can be determined based on production needs, historical data or industry standards. Screening the initial optimization production lines: Based on the node complexity index, screen out the production lines whose node complexity is greater than the preset value. These production lines are considered to be the initial optimization production lines with greater optimization potential. Priority sorting: Prioritize the selected initial optimization production lines. The priority can be determined based on the size of the node complexity index, the degree of impact on production, and other factors. Analyze the causes and identify the problems: Analyze each initial optimization production line to understand the reasons for its high node complexity. Identify the specific process flow, equipment, or operation steps that lead to high complexity. Formulate an optimization plan: Based on the analysis results, formulate a specific optimization plan for each initial optimization production line. The optimization plan should include improvement measures, expected results, and an implementation schedule. Implement the optimization plan: According to the optimization plan, gradually implement the improvement measures. Analyze the historical data and operating parameters of the initial optimization production line: Collect the historical data, operating parameters, fault records, and other related information of the initial optimization production line. Analyze these data to understand the performance, failure mode, and optimization potential of the production line. Determine the optimization goal: According to the optimization requirements, clarify the optimization goal, such as improving the operating efficiency of the production line, reducing the failure rate, and saving energy. According to the goal, select appropriate optimization indicators and evaluation criteria. Retrieve relevant information in the adaptive optimization memory: Use the adaptive optimization memory to retrieve optimization cases, historical configuration parameters, and optimization experience related to the initial optimization production line. Perform optimization operations: Use appropriate optimization algorithms (such as genetic algorithms, simulated annealing algorithms, etc.) to perform optimization operations on the initial optimization production line. Through iteration and evaluation, continuously adjust the configuration parameters of the production line to approach the optimization goal. Obtain optimized configuration parameters: After the optimization operation is completed, select appropriate configuration parameters as the optimized configuration parameters based on the optimization results and evaluation criteria. Ensure that these parameters can effectively improve the performance of the production line and meet the optimization goals.Output optimized configuration parameters: Organize the optimized configuration parameters into a report or data format, detailing the adjustment of each parameter and the optimization effect. Analyze the performance and configuration of the remaining optimization lines: Evaluate the performance, configuration parameters and current status of the remaining optimization lines. Understand the optimization potential of the remaining lines and the differences with the initial optimization lines. Determine optimization goals and evaluation criteria: Determine optimization goals for the remaining optimization lines based on optimization requirements, such as improving production efficiency and reducing energy consumption. Establish evaluation criteria to evaluate the effectiveness of optimization results and the degree of performance improvement. Apply the optimized configuration parameters of the initial optimization line: Apply the optimized configuration parameters of the initial optimization line to the remaining optimization lines. Analyze the impact of these parameters on the performance of the remaining lines and make preliminary adjustments. Retrieve relevant optimization experience in the adaptive optimization memory: Use the adaptive optimization memory to retrieve optimization cases and experience related to the remaining optimization lines. Learn from the optimization results of other similar lines to provide optimization guidance for the remaining lines. Perform optimization operations: Perform optimization operations on the remaining optimization lines based on the optimized configuration parameters of the initial optimization line and the retrieved optimization experience. Through iteration and evaluation, the configuration parameters are continuously adjusted to achieve the optimal solution. Obtain the optimized configuration parameters: According to the results of the optimization operation, determine the final optimized configuration parameters for the remaining optimization production lines. Ensure that these parameters can meet the optimization objectives and evaluation criteria. Output the optimized configuration parameter report: Organize the optimized configuration parameters into a report or data form. Integrate the optimized configuration parameters: Integrate the optimized configuration parameters of the initial optimization production line and the remaining optimization production lines. Ensure the consistency and coordination of the parameters to achieve the optimization goals of the entire injection production line. Analyze the overall performance of the production line: Evaluate the impact of the integrated optimized configuration parameters on the performance of the entire injection production line. Analyze changes in the production efficiency, stability, energy consumption, etc. of the production line. Adjust the optimized configuration parameters: Fine-tune the optimized configuration parameters based on the analysis results of the overall performance of the production line. Optimization goals include improving production efficiency, reducing energy consumption, and enhancing production line stability. Verify the effectiveness of the optimized configuration parameters:.

[0069] Embodiment 2

[0070] Based on the same inventive concept as the method for adaptively configuring an injection production line based on a production work order in the aforementioned embodiment, Figure 4 As shown, the present application provides an injection production line adaptive configuration system based on a production work order, the system comprising:

[0071] A work order queue receiving module 10, wherein the work order queue receiving module 10 is used to receive an injection production work order queue, wherein the injection production work order queue is a work order collection table based on the injection production line timing reception;

[0072] A work order completion rate acquisition module 20, which is used to identify the injection production work order queue according to the current configuration parameters of the injection production line and obtain the work order completion rate of the injection production work order queue;

[0073] A historical failure probability collection module 30, which is used to collect the historical failure probability corresponding to each production line node in the injection production line;

[0074] A work order delay rate acquisition module 40, the work order delay rate acquisition module 40 is used to identify the injection production work order queue according to the historical failure probability and obtain the work order delay rate;

[0075] A work order completion rate acquisition module 50, the work order completion rate acquisition module 50 is used to adjust and feedback the work order completion rate according to the work order delay rate to obtain the work order completion rate after feedback;

[0076] An optimized configuration parameter output module 60 is used to, when the work order completion rate after feedback does not meet the preset work order completion rate, use the preset work order completion rate as an adaptive target and the current configuration parameters of the injection production line as input variables, perform optimization in the adaptive optimization memory library, and output the optimized configuration parameters of the injection production line;

[0077] The production operation module 70 is used to perform production operations on the injection production line according to the optimized configuration parameters.

[0078] Furthermore, the system also includes:

[0079] A weighted calculation module is used to obtain multiple production line nodes of the injection production line; collect the operating equipment corresponding to the multiple production line nodes, and collect historical fault information of the operating equipment corresponding to each production line node to obtain a set of historical failure probabilities of the equipment; after regularizing the set of historical failure probabilities of the equipment, the regularized weighted calculation result is output as the historical failure probability corresponding to each production line node.

[0080] Furthermore, the system also includes:

[0081] The production work order identification module is used to collect historical delay time samples corresponding to each production line node in the event of a failure; perform mean settlement based on the historical delay time samples to obtain the mean delay time of each production line node in the event of a failure; when the historical failure probability of any production line node is greater than the preset failure probability, it is marked as an abnormal production line node, and the injection production work order queue is identified with the mean delay time corresponding to the abnormal production line node to obtain the work order delay rate.

[0082] Furthermore, the system also includes:

[0083] The first elimination instruction acquisition module is used to determine whether the abnormal production line node includes a backup device; if the abnormal production line node includes a backup device, the first elimination instruction is triggered, wherein the first elimination instruction is used to eliminate the work order delay caused by the abnormal production line node.

[0084] Furthermore, the system also includes:

[0085] An optimization module is used to establish an adaptive optimization memory library, wherein the adaptive optimization memory library is configured by calling the historical configuration parameter sample library of the injection production line and performing an accelerated stability evaluation on the historical configuration parameter sample library to obtain a configuration parameter sample whose accelerated stability is greater than a preset stability; and the adaptive optimization memory library is configured with the preset work order completion rate as an adaptive target and the current configuration parameters of the injection production line as input variables.

[0086] Furthermore, the system also includes:

[0087] A configuration parameter optimization module is used to identify the equipment coordination relationship of each production line node in the injection production line and obtain the equipment coordination index of each production line node; select the initial optimization equipment in the injection production line, wherein the initial optimization equipment is a device randomly selected based on each production line node, and each production line node includes at least one device; optimize the initial optimization equipment in the adaptive optimization memory library to obtain the optimized configuration parameters of the initial optimization equipment; then, according to the equipment coordination index of each production line node and the optimized configuration parameters of the initial optimization equipment, coordinately adapt the remaining optimization equipment to obtain the optimized configuration parameters of the remaining optimization equipment; output the optimized configuration parameters of the injection production line based on the optimized configuration parameters of the initial optimization equipment and the optimized configuration parameters of the remaining optimization equipment.

[0088] Furthermore, the system also includes:

[0089] The module for outputting the optimized configuration parameters of the remaining optimized production lines is used to obtain the node complexity index of each production line node by identifying the process complexity of each production line node in the injection production line; according to the node complexity index, the initial optimized production line in the injection production line is selected, wherein the initial optimized production line is a production line whose node complexity index is greater than the preset node complexity index; the initial optimized production line is optimized in the adaptive optimization memory library to obtain the optimized configuration parameters of the initial optimized production line; the remaining optimized production lines are then optimized according to the optimized configuration parameters of the initial optimized production line to obtain the optimized configuration parameters of the remaining optimized production lines; according to the optimized configuration parameters of the initial optimized production line and the optimized configuration parameters of the remaining optimized production lines, the optimized configuration parameters of the injection production line are output.

[0090] Through the detailed description of the aforementioned method for adaptive configuration of injection production lines based on production work orders, those skilled in the art can clearly understand the adaptive configuration system for injection production lines based on production work orders in this embodiment. For the system disclosed in the embodiment, since it corresponds to the device disclosed in the embodiment, the description is relatively simple, and the relevant parts can be referred to the description of the method part.

[0091] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present application. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present application. Therefore, the present application will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. Adaptive configuration method of injection production line based on production work order, It is characterized in that The method comprises: Receive an injection production work order queue, where the injection production work order queue is a collection table of work orders received based on the injection production line time sequence; Identify the injection production work order queue according to the current configuration parameters of the injection production line, and obtain the work order completion rate of the injection production work order queue; Collecting the historical failure probabilities corresponding to each production line node in the injection production line; Identify the injection production work order queue according to the historical failure probability and obtain the work order delay rate; Adjusting and feeding back the work order completion rate according to the work order delay rate to obtain the work order completion rate after feedback; When the work order completion rate after feedback does not meet the preset work order completion rate, the preset work order completion rate is used as the adaptive target, the current configuration parameters of the injection production line are used as input variables, and the optimization is performed in the adaptive optimization memory library to output the optimized configuration parameters of the injection production line; Performing production operations on the injection production line according to the optimized configuration parameters; Optimizing in the adaptive optimization memory library and outputting the optimized configuration parameters of the injection production line also includes: Identify the equipment coordination relationship of each production line node in the injection production line, and obtain the equipment coordination index of each production line node; Selecting an initial optimization device in the injection production line, wherein the initial optimization device is a device randomly selected based on each production line node, and each production line node includes at least one device; Performing optimization in the adaptive optimization memory base according to the initial optimization device to obtain the optimized configuration parameters of the initial optimization device; Then, according to the equipment coordination index of each production line node and the optimization configuration parameters of the initial optimization equipment, the remaining optimization equipment is coordinated and adapted to obtain the optimization configuration parameters of the remaining optimization equipment; Outputting the optimized configuration parameters of the injection production line according to the optimized configuration parameters of the initial optimized device and the optimized configuration parameters of the remaining optimized devices; Optimization is performed in the adaptive optimization memory library, and the output of the optimized configuration parameters of the injection production line also includes: By identifying the process complexity of each production line node in the injection production line, the node complexity index of each production line node is obtained; According to the node complexity index, an initial optimal production line is selected from the injection production line, wherein the initial optimal production line is a production line whose node complexity index is greater than a preset node complexity index; Optimizing the initial optimization production line in the adaptive optimization memory library to obtain the optimal configuration parameters of the initial optimization production line; Then, optimizing the remaining optimal production lines according to the optimal configuration parameters of the initial optimal production line, to obtain the optimal configuration parameters of the remaining optimal production lines; According to the optimized configuration parameters of the initial optimized production line and the optimized configuration parameters of the remaining optimized production lines, the optimized configuration parameters of the injection production line are output.

2. The method according to claim 1, It is characterized in that The historical failure probability corresponding to each production line node in the injection production line is collected, and the method includes: Acquire multiple production line nodes of the injection production line; Collecting the operating equipment corresponding to the multiple production line nodes, and collecting historical fault information of the operating equipment corresponding to each production line node to obtain a set of historical fault probabilities of the equipment; After the equipment historical failure probability set is regularized, the regularized weighted calculation result is output as the historical failure probability corresponding to each production line node.

3. The method according to claim 2, It is characterized in that The injection production work order queue is identified according to the historical failure probability to obtain a work order delay rate, and the method includes: Collecting historical delay time samples corresponding to each production line node when a failure occurs; Performing average settlement based on the historical delay time samples to obtain the average delay time of each production line node when a failure occurs; When the historical failure probability of any production line node is greater than the preset failure probability, it is marked as an abnormal production line node. The injection production work order queue is identified by the average delay time corresponding to the abnormal production line node to obtain the work order delay rate.

4. The method according to claim 3, It is characterized in that The method further comprises: Determining whether the abnormal production line node includes a backup device; If the abnormal production line node includes a backup device, a first elimination instruction is triggered, wherein the first elimination instruction is used to eliminate the work order delay caused by the abnormal production line node.

5. The method according to claim 1, It is characterized in that The method further comprises: Establishing an adaptive optimization memory library, wherein, by calling the historical configuration parameter sample library of the injection production line and performing an acceleration stability evaluation on the historical configuration parameter sample library, a configuration parameter sample whose acceleration stability is greater than a preset stability is obtained and configured as the adaptive optimization memory library; The preset work order completion rate is used as an adaptive target, and the current configuration parameters of the injection production line are used as input variables to perform optimization in the adaptive optimization memory library.

6. Adaptive configuration system for injection production line based on production work order, It is characterized in that The system is used to execute the method according to any one of claims 1 to 5, and the system comprises: A work order queue receiving module, the work order queue receiving module is used to receive an injection production work order queue, the injection production work order queue is a work order collection table based on the injection production line timing reception; A work order completion rate acquisition module, which is used to identify the injection production work order queue according to the current configuration parameters of the injection production line and obtain the work order completion rate of the injection production work order queue; A historical failure probability collection module, which is used to collect the historical failure probabilities corresponding to each production line node in the injection production line; A work order delay rate acquisition module, the work order delay rate acquisition module is used to identify the injection production work order queue according to the historical failure probability and obtain the work order delay rate; A work order completion rate acquisition module, the work order completion rate acquisition module is used to adjust and feedback the work order completion rate according to the work order delay rate to obtain the work order completion rate after feedback; An optimized configuration parameter output module, which is used to, when the work order completion rate after feedback does not meet the preset work order completion rate, take the preset work order completion rate as an adaptive target, take the current configuration parameters of the injection production line as input variables, perform optimization in the adaptive optimization memory library, and output the optimized configuration parameters of the injection production line; A production operation module, wherein the production operation module is used to perform production operations on the injection production line according to the optimized configuration parameters.

Citation Information

Patent Citations

  • Intelligent factory production online monitoring and analysis system based on digital twinning

    CN117055494A