An automated steel structure welding production line

By designing an automated steel structure welding production line, the automated welding of tubular support beams is achieved using a walking track and robotic arms, solving the problem of insufficient welding equipment for multiple sets of tubular support beams and improving welding efficiency and forming quality.

CN118204608BActive Publication Date: 2026-11-17SHANDONG SHENGTIAN STEEL STRUCTURE CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311765739.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-12-21
Publication Date
2026-11-17
Estimated Expiration
2043-12-21

AI Technical Summary

Technical Problem

The lack of automated welding equipment suitable for multiple sets of tubular support beams in the existing technology results in a low level of automation, making it difficult to cut and weld the entire long tubular support beam at different positions of the tubular main beam.

Method used

An automated steel structure welding production line was designed, including a main circular tube fixing frame and a traveling track. A branch tube cutting and welding device is installed on the traveling trolley. The relative position adjustment between the tubular support beam and the tubular main beam is achieved through gear and rack meshing. Automatic welding and cutting are performed using a robotic arm and a cutting gun head.

Benefits of technology

The automated welding of multiple sets of tubular support beams was achieved, which improved production efficiency, reduced labor intensity and manufacturing costs, and enhanced the forming quality of steel structures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118204608B_ABST
    Figure CN118204608B_ABST
Patent Text Reader

Abstract

This invention relates to an automated steel structure welding production line, belonging to the field of automated welding technology. It includes a main circular pipe fixing frame installed on the ground and two sets of traveling tracks. The two sets of traveling tracks are located on the same side of the main circular pipe fixing frame, and the main circular pipe fixing frame and traveling tracks are parallel to each other and have the same length direction. A traveling trolley is installed on each traveling track, moving along the length direction of the two sets of traveling tracks. A branch pipe cutting and welding device is installed on the traveling trolley. This invention has the following beneficial effects: this welding production line can upgrade traditional labor-intensive operations to automated factory operations, reduce construction workers, lower the manufacturing cost of steel structures, improve production efficiency, improve the overall forming quality of steel structures, and reduce labor intensity. Controlling the traveling trolley to move along the length direction of the tubular main beam to the next welding position further improves welding efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to an automatic welding production line for steel structures, belonging to the field of automatic welding technology. Background Technology

[0002] Saddle-shaped automatic welding technology is a very common automatic welding technology for steel structures. Saddle-shaped automatic welding mainly follows the principle of saddle-shaped curve motion. During the connection of two cylinders, there will be an intersection line, with their central axes perpendicular to each other, and the intersection lines are parallel. To effectively improve the application effect of automatic welding technology, scientific work principles should be followed, and effective measures should be adopted to improve the quality and level of related welding operations to meet current work requirements.

[0003] Patent application number 201410183768.7 discloses a method for automatic submerged arc saddle-shaped welding of pipe joints with small cylinder diameter ratios. The method is characterized by the following steps: the pipe joint is vertically fixed to the cylinder body using manual argon arc welding for the root pass; a flux protection fixture is placed on the cylinder body surface to support the flux required for welding; a balance crane is used to place the automatic submerged arc saddle-shaped welding machine on the pipe joint; the three-jaw chuck of the automatic submerged arc saddle-shaped welding machine extends into the pipe joint to fix the machine in place; and the different drop and weld bead arrangement are adjusted sequentially by adjusting the saddle drop adjuster and the welding torch angle adjustment valve to complete the automatic submerged arc saddle-shaped welding. This method successfully achieves automatic submerged arc saddle-shaped welding of pipe joints with small cylinder diameter ratios, resulting in aesthetically pleasing weld formation.

[0004] Although the aforementioned patent can achieve the welding function, the current technology is not comprehensive and has the following drawbacks: For the welding production of multiple sets of tubular support beams vertically welded on the tubular main beam, there is currently no welding equipment suitable for multiple sets of tubular support beams, and the level of automation is low.

[0005] To solve one of the above problems, there is an urgent need for an automated steel structure welding production line. Summary of the Invention

[0006] In view of the shortcomings of the prior art, the technical problem to be solved by the present invention is: how to realize the cutting and welding of the entire long tubular support beam by the support pipe cutting and welding device, and automatically weld it at different positions of the tubular main beam, and to this end, an automatic welding production line for steel structure is provided.

[0007] The automatic steel structure welding production line of the present invention is characterized in that it includes a main circular pipe fixing frame and two sets of walking tracks installed on the ground. The two sets of walking tracks are located on the same side of the main circular pipe fixing frame, and the main circular pipe fixing frame and the walking tracks are parallel to each other and have the same length direction. A walking trolley is provided on the walking track to travel along the length direction of the two sets of walking tracks. A branch pipe cutting and welding device is installed on the walking trolley.

[0008] Preferably, the two sets of travel tracks are a first travel track and a second travel track. The traveling trolley includes an upper slide rail, with both ends of the upper slide rail supported on the first track trolley and the second track trolley, respectively. The first track trolley includes a trolley frame A connected to the upper slide rail. A set of traveling wheels A is provided at the four corners of the bottom of the trolley frame A. A travel reduction motor A is provided in the middle of the trolley frame A. A main drive gear A is installed on the power output shaft of the travel reduction motor A. Track steel A is provided on both sides of the first travel track along its length direction to cooperate with the corresponding traveling wheels A. A rack A is provided between the two sets of track steel A to mesh with the main drive gear A. The rack A is provided along the length direction of the first travel track. The length direction of the upper slide rail is perpendicular to the length direction of the first travel track. A second upper slide table and a second drive device for driving the first upper slide table to travel along the length direction of the upper slide rail are installed on the upper slide rail.

[0009] By cooperating with the first and second traveling tracks and the first and second track trolleys, the relative positions of the tubular support beam and the tubular main beam can be changed, so that the tubular support beam is welded to the outer wall at different positions along the length of the tubular main beam.

[0010] Preferably, the second track trolley includes a trolley traveling frame B connected to the upper slide rail. A set of traveling wheels B is respectively provided at the four corners of the bottom of the trolley traveling frame B. A traveling reduction motor B is provided in the middle of the trolley traveling frame B. A main drive gear B is installed on the power output shaft of the traveling reduction motor B. Track steels B are provided on both sides of the second traveling track along its length direction, cooperating with the corresponding traveling wheels B. A rack B that meshes with the main drive gear B is provided between the two sets of track steels B. The rack B is arranged along the length direction of the first traveling track. The traveling reduction motor A moves synchronously with the traveling reduction motor B. A second upper slide table and a third drive device for driving the second upper slide table to move along the length direction of the upper slide rail are installed on the upper slide rail.

[0011] The movement of the first and second track trolleys is achieved by the meshing of the main drive gear and rack, powered by a geared motor.

[0012] Preferably, the two ends of the upper slide rail are fixed to the trolley traveling frame A and the trolley traveling frame B, respectively.

[0013] Preferably, the second drive device includes a travel reduction motor C mounted on the first upper slide, a main drive gear C mounted on the power output shaft of the travel reduction motor C, and a rack C meshing with the main drive gear C on the upper slide rail. The second drive device and the third drive device have the same structure.

[0014] Preferably, the branch pipe cutting and welding device includes a branch pipe welding structure and a steel pipe cutting structure installed on the upper surface of the second upper slide, and a steel pipe pushing mechanism is installed on the second upper slide.

[0015] Preferably, the branch pipe welding structure includes a guide pipe, a telescopic outer sleeve A is slidably sleeved on the left end of the guide pipe, a tailstock A is integrally provided on the right end of the telescopic outer sleeve A, a push-pull cylinder A is installed on the guide pipe to push the tailstock A to move along the length direction of the guide pipe, the rotating outer sleeve A is rotatably mounted on the telescopic outer sleeve A through a rotary bearing A, an external gear ring A is provided on the right end of the rotating outer sleeve A, a rotary drive reduction motor C is provided at the end of the telescopic outer sleeve A near the tailstock A, a drive gear D that meshes with the external gear ring A is provided on the power output shaft of the rotary drive reduction motor C, a second manipulator is installed on the rotating outer sleeve A, and a welding gun is installed at the execution end of the second manipulator.

[0016] A bevel is machined at the end of the tubular support beam to fit the outer wall of the tubular main beam. The tubular support beam is pushed into the guide tube by a steel pipe pushing mechanism and abuts against the outer wall of the tubular main beam. The position of the first upper slide is adjusted, and the position of the rotating outer sleeve A is finely adjusted by the push-pull cylinder A. The welding gun is turned on to weld the connection. The rotating outer sleeve A is driven by the rotary drive reduction motor C to drive the second robot arm and the welding gun to rotate and weld. The welding will undulate with the shape of the bevel after one round. The distance between the welding gun and the tubular main beam is controlled by the extension and retraction of the push-pull cylinder A, so as to realize the automatic welding of the tubular support beam to the tubular main beam.

[0017] Preferably, the steel pipe cutting structure includes a first robotic arm, a telescopic outer sleeve B slidably sleeved on the right end of the guide tube, a tailstock B integrally formed on the left end of the telescopic outer sleeve B, a push-pull cylinder B mounted on the guide tube to push the tailstock B to move along the length of the guide tube, a rotating outer sleeve B rotatably mounted on the telescopic outer sleeve B via a rotary bearing B, an external gear ring B provided on the left end of the rotating outer sleeve B, a rotary drive reduction motor D provided on the end of the telescopic outer sleeve B near the tailstock B, a drive gear E meshing with the external gear ring B provided on the power output shaft of the rotary drive reduction motor D, a first robotic arm mounted on the rotating outer sleeve B, a cutting head mounted on the execution end of the first robotic arm, the cutting head being a plasma cutting head, and a cutting nozzle provided at the lower end of the plasma cutting head. After the tubular support beam and the tubular main beam are welded together, the tubular support beam is first cut off using a cutting gun head, and then a bevel that matches the tubular main beam is machined. The external gear ring B works with the rotary drive reduction motor D to realize the circumferential cutting of the tubular support beam by the cutting gun head. At the same time, the push-pull cylinder B controls the movement of the cutting gun head to achieve the cutting of the bevel shape.

[0018] After the tubular support beam is cut, the second upper slide and the first upper slide are simultaneously controlled to move away from the tubular main beam. The tubular support beam to be welded is moved out of the guide tube. Then the traveling trolley is controlled to move along the length of the tubular main beam to the next welding position.

[0019] Preferably, the steel pipe pushing mechanism includes a frame fixed on a first upper slide, on which an upper wheel set and a lower wheel set are provided. The tubular support beam passes through the upper wheel set and the lower wheel set. The drive wheels of the upper wheel set and the lower wheel set are directly connected by a reduction motor F. The upper wheel set and the lower wheel set rotate in opposite directions, driving the tubular support beam to move.

[0020] Preferably, the guide tube is fixed to the first upper slide by a support column. Both the first and second robotic arms are multi-joint robotic arms, which is existing technology.

[0021] Compared with the prior art, the present invention has the following beneficial effects: The automatic steel structure welding production line of the present invention is used to vertically weld multiple sets of tubular support beams on a tubular main beam. The multiple sets of tubular support beams are at the same height and parallel to each other, and their center lines all pass through the center line of the tubular main beam. The tubular main beam is hoisted onto the main circular pipe fixing frame using a lifting device. The entire long tubular support beam is cut off by a support pipe cutting and welding device and welded to different positions of the tubular main beam.

[0022] The automatic steel structure welding production line described in this invention can upgrade traditional labor-intensive operations to automated factory operations, reduce construction workers, lower steel structure manufacturing costs, improve production efficiency, enhance the overall forming quality of steel structures, and reduce labor intensity. The automatic steel structure welding production line of the present invention, after the tubular support beam is cut, simultaneously controls the second upper slide and the first upper slide to move away from the tubular main beam, so that the tubular support beam to be welded is moved out of the guide tube, and then controls the traveling trolley to move along the length of the tubular main beam to the next welding position, thereby further improving the welding efficiency. Attached Figure Description

[0023] To more clearly illustrate the specific embodiments of the present invention or the technical solutions in the prior art, the accompanying drawings used in the description of the specific embodiments or the prior art will be briefly introduced below. In all the drawings, similar elements or parts are generally identified by similar reference numerals. In the drawings, the elements or parts are not necessarily drawn to scale.

[0024] Figure 1 This is a schematic diagram of the structure of the present invention; Figure 2 This is a schematic diagram of the external structure of the walking vehicle of the present invention; Figure 3 This is a schematic diagram of the external structure of the branch pipe welding structure of the present invention; In the diagram: 1. Main circular tube fixing frame; 2. Traveling track; 3. Traveling trolley; 3.1. Trolley traveling frame A; 3.2. Traveling wheel A; 3.3. Traveling reduction motor A; 3.4. Main drive gear A; 3.5. Rack A; 3.6. Upper slide rail; 3.7. First upper slide table; 4. Track steel A; 5. Branch pipe welding structure; 5.1. Guide tube; 5.2. Telescopic outer sleeve A; 5.3. Tailstock A; 5.4. Push-pull cylinder A; 5.5. External gear ring A; 5.6. Rotating outer sleeve A; 5.7. Rotary drive reduction motor C; 6. Steel pipe cutting structure; 6.1. First robotic arm; 6.2. Cutting gun head; 7. Steel pipe pushing mechanism; 8. Tubular main beam; 9. Tubular support beam. Detailed Implementation

[0025] The present invention will be further described below with reference to the accompanying drawings. The present invention will be further illustrated by specific embodiments, but it is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.

[0026] Example 1, as Figure 1-2 As shown, the automatic steel structure welding production line includes a main circular tube fixing frame 1 and two sets of traveling tracks 2 installed on the ground. The two sets of traveling tracks 2 are located on the same side of the main circular tube fixing frame 1, and the main circular tube fixing frame 1 and the traveling tracks 2 are parallel to each other and have the same length direction. The invention is characterized in that: a traveling trolley 3 is provided on the traveling track 2, traveling along the length direction of the two sets of traveling tracks 2, and a branch pipe cutting and welding device is installed on the traveling trolley 3. This invention is used to vertically weld multiple sets of tubular support beams on a tubular main beam. The multiple sets of tubular support beams are at the same height and are parallel to each other, with their center lines all passing through the center line of the tubular main beam. The tubular main beam 8 is hoisted onto the main circular tube fixing frame 1 using a lifting device. The entire long tubular support beam 9 is cut by the branch pipe cutting and welding device and welded at different positions on the tubular main beam 8. Example 2, as... Figure 1-3 As shown, the automatic steel structure welding production line includes a main circular pipe fixing frame 1 and two sets of walking tracks 2 installed on the ground. The two sets of walking tracks 2 are located on the same side of the main circular pipe fixing frame 1, and the main circular pipe fixing frame 1 and the walking tracks 2 are parallel to each other and have the same length direction. A walking trolley 3 is provided on the walking track 2 to travel along the length direction of the two sets of walking tracks 2. A branch pipe cutting and welding device is installed on the walking trolley 3.

[0027] Furthermore, the two sets of traveling tracks 2 are respectively the first traveling track and the second traveling track. The traveling trolley 3 includes an upper slide rail 3.6, with both ends of the upper slide rail 3.6 supported on the first track trolley and the second track trolley, respectively. The first track trolley includes a trolley frame A3.1 connected to the upper slide rail 3.6. A set of traveling wheels A3.2 is respectively provided at the four corners of the bottom of the trolley frame A3.1. A traveling reduction motor A3.3 is provided in the middle of the trolley frame A3.1, and a power output shaft of the traveling reduction motor A3.3 is mounted on... The system includes a main drive gear A3.4. Track steel A4, which meshes with corresponding traveling wheels A3.2, is provided on both sides of the first traveling track along its length. A rack A3.5, meshing with the main drive gear A3.4, is positioned between the two sets of track steel A4. The rack A3.5 is positioned along the length of the first traveling track. The upper slide rail 3.6 is perpendicular to the length of the first traveling track. A second upper slide table 3.8 and a second drive device that drives the first upper slide table 3.7 to travel along the length of the upper slide rail 3.6 are mounted on the upper slide rail 3.6. Through the interaction of the first and second traveling tracks with the first and second track trolleys, the relative positions of the tubular support beam 9 and the tubular main beam 8 can be changed, allowing the tubular support beam 9 to be welded to the outer wall at different positions along the length of the tubular main beam 8.

[0028] Furthermore, the second track trolley includes a trolley frame B connected to the upper slide rail 3.6. A set of traveling wheels B is respectively provided at the four corners of the bottom of the trolley frame B. A traveling reduction motor B is provided in the middle of the trolley frame B. A main drive gear B is mounted on the power output shaft of the traveling reduction motor B. Track steels B are provided on both sides of the second track along its length direction, cooperating with the corresponding traveling wheels B. A rack B is provided between the two sets of track steels B, meshing with the main drive gear B. The rack B is arranged along the length direction of the first track. The traveling reduction motor A3.3 moves synchronously with the traveling reduction motor B. A second upper slide 3.8 and a third drive device for driving the second upper slide 3.8 to move along the length direction of the upper slide rail 3.6 are mounted on the upper slide rail 3.6. The movement of the first track trolley and the second track trolley is achieved by the meshing of the main drive gear and the rack, powered by the reduction motor.

[0029] Furthermore, the two ends of the upper slide rail 3.6 are respectively fixed to the trolley traveling frame A3.1 and the trolley traveling frame B.

[0030] Furthermore, the second drive device includes a travel reduction motor C mounted on the first upper slide 3.7, a main drive gear C mounted on the power output shaft of the travel reduction motor C, and a rack C meshing with the main drive gear C on the upper slide rail 3.6. The second drive device and the third drive device have the same structure.

[0031] Furthermore, the branch pipe cutting and welding device includes a branch pipe welding structure 5 and a steel pipe cutting structure 6 installed on the upper surface of the second upper slide 3.8, and a steel pipe pushing mechanism 7 is installed on the second upper slide 3.8.

[0032] Further, the branch pipe welding structure 5 includes a guide pipe 5.1, a telescopic outer sleeve A5.2 is slidably sleeved on the left end of the guide pipe 5.1, a tailstock A5.3 is integrally provided on the right end of the telescopic outer sleeve A5.2, a push-pull cylinder A5.4 is installed on the guide pipe 5.1 to push the tailstock A5.3 to move along the length direction of the guide pipe 5.1, a rotating outer sleeve A5.6 is rotatably mounted on the telescopic outer sleeve A5.2 through a rotating bearing A, an external gear ring A5.5 is provided on the right end of the rotating outer sleeve A5.2 near the tailstock A5.3, a rotary drive reduction motor C5.7 is provided, a drive gear D that meshes with the external gear ring A5.5 is provided on the power output shaft of the rotary drive reduction motor C5.7, and a second robot arm 5.8 is installed on the rotating outer sleeve A5.6, and a welding gun 5.9 is installed at the execution end of the second robot arm 5.8.

[0033] A bevel is machined at the end of the tubular support beam 9 to fit the outer wall of the tubular main beam 8. The tubular support beam 9 is pushed into the guide tube 5.1 by the steel pipe pushing mechanism 7 and abuts against the outer wall of the tubular main beam 8. The position of the first upper slide 3.7 is adjusted, and the position of the rotating outer sleeve A5.6 is finely adjusted by the push-pull cylinder A5.4. The welding gun 5.9 is turned on to weld the connection. The rotating outer sleeve A5.6 is driven by the rotary drive reduction motor C5.7 to drive the second robot arm 5.8 and the welding gun 5.9 to rotate and weld. The welding will undulate with the shape of the bevel after one round. The distance between the welding gun 5.9 and the tubular main beam 8 is controlled by the extension and retraction of the push-pull cylinder A5.4, so that the tubular support beam 9 can be automatically welded to the tubular main beam 8.

[0034] Furthermore, the steel pipe cutting structure 6 includes a first robotic arm 6.1. A telescopic outer sleeve B is slidably fitted on the right end of the guide tube 5.1. A tailstock B is integrally provided on the left end of the telescopic outer sleeve B. A push-pull cylinder B is installed on the guide tube 5.1 to push the tailstock B to move along the length direction of the guide tube 5.1. The rotating outer sleeve B is rotatably mounted on the telescopic outer sleeve B through a rotary bearing B. An external gear ring B is provided on the left end of the rotating outer sleeve B. A rotary drive reduction motor D is provided at the end of the telescopic outer sleeve B near the tailstock B. An active gear E that meshes with the external gear ring B is provided on the power output shaft of the rotary drive reduction motor D. The first robotic arm 6.1 is installed on the rotating outer sleeve B. A cutting head 6.2 is installed at the execution end of the first robotic arm 6.1. The cutting head 6.2 is a plasma cutting head, and a cutting nozzle is provided at the lower end of the plasma cutting head. After the tubular support beam 9 and the tubular main beam 8 are welded together, the tubular support beam 9 is first cut off using the cutting gun head 6.2, and then a bevel that matches the tubular main beam 8 is machined. The external gear ring B works with the rotary drive reduction motor D to realize the circumferential cutting of the tubular support beam 9 by the cutting gun head 6.2. At the same time, the push-pull cylinder B controls the movement of the cutting gun head 6.2 to realize the cutting of the bevel shape.

[0035] After the tubular support beam 9 is cut, the second upper slide 3.8 and the first upper slide 3.7 are simultaneously controlled to move away from the tubular main beam 8, and the welded tubular support beam 9 is moved out of the guide tube 5.1. Then the traveling trolley 3 is controlled to move along the length of the tubular main beam 8 to the next welding position.

[0036] Furthermore, the steel pipe pushing mechanism 7 includes a frame fixed on the first upper slide 3.7, on which an upper wheel set and a lower wheel set are provided. The tubular support beam 9 passes through the upper wheel set and the lower wheel set. The drive wheels of the upper wheel set and the lower wheel set are directly connected by a reduction motor F. The upper wheel set and the lower wheel set rotate in opposite directions, driving the tubular support beam 9 to move.

[0037] Furthermore, the guide tube 5.1 is fixed to the first upper slide 3.7 by a support column. Both the first robotic arm 6.1 and the second robotic arm are multi-joint robotic arms, which is existing technology.

[0038] Compared with the prior art, the present invention has the following beneficial effects: The automatic steel structure welding production line of the present invention is used to vertically weld multiple sets of tubular support beams on a tubular main beam. The multiple sets of tubular support beams are at the same height and parallel to each other, and their center lines all pass through the center line of the tubular main beam. The tubular main beam is hoisted onto the main circular pipe fixing frame using a lifting device. The entire long tubular support beam is cut off by a support pipe cutting and welding device and welded to different positions of the tubular main beam.

[0039] The automatic steel structure welding production line described in this invention can upgrade traditional labor-intensive operations to automated factory operations, reduce construction workers, lower steel structure manufacturing costs, improve production efficiency, enhance the overall forming quality of steel structures, and reduce labor intensity. The automatic steel structure welding production line of the present invention, after the tubular support beam is cut, simultaneously controls the second upper slide and the first upper slide to move away from the tubular main beam, so that the tubular support beam to be welded is moved out of the guide tube, and then controls the traveling trolley to move along the length of the tubular main beam to the next welding position, thereby further improving the welding efficiency.

[0040] The foregoing has shown and described the basic principles, main features, and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The embodiments and descriptions in the specification are merely illustrative of the principles of the invention. Various changes and modifications can be made to the invention without departing from its spirit and scope, and all such changes and modifications fall within the scope of the present invention as claimed. The scope of protection of the present invention is defined by the appended claims and their equivalents.

[0041] Any aspects of this invention not described in detail are well-known to those skilled in the art.

Claims

1. An automatic steel structure welding production line, comprising a main circular tube fixing frame and two sets of traveling tracks installed on the ground, the two sets of traveling tracks being located on the same side of the main circular tube fixing frame, and the main circular tube fixing frame and the traveling tracks being parallel to each other and having the same length direction, characterized in that: The traveling track is equipped with a traveling trolley that travels along the length of two sets of traveling tracks. The traveling trolley is equipped with a branch pipe cutting and welding device. The traveling trolley includes an upper slide rail, the length of which is perpendicular to the length of the traveling track. A first upper slide table and a second upper slide table are installed on the upper slide rail. The branch pipe cutting and welding device includes a branch pipe welding structure and a steel pipe cutting structure installed on the upper surface of the first upper slide table. A steel pipe pushing mechanism is installed on the second upper slide table. The steel pipe cutting structure is located on one end of the guide tube of the branch pipe welding structure and is used to cut the tubular support beam and then process it into a bevel that matches the tubular main beam.

2. The automatic steel structure welding production line according to claim 1, characterized in that, The two sets of travel tracks are a first travel track and a second travel track. The two ends of the upper slide rail are respectively supported on the first track trolley and the second track trolley. The first track trolley includes a trolley frame A connected to the upper slide rail. A set of travel wheels A are respectively provided at the four corners of the bottom of the trolley frame A. A travel reduction motor A is provided in the middle of the trolley frame A. A main drive gear A is installed on the power output shaft of the travel reduction motor A. Track steel A that cooperates with the corresponding travel wheels A is provided on both sides of the first travel track along its length direction. A rack A that meshes with the main drive gear A is provided between the two sets of track steel A. The rack A is provided along the length direction of the first travel track. A second drive device that drives the first upper slide to travel along the length direction of the upper slide rail is also installed on the first upper slide.

3. The automatic steel structure welding production line according to claim 2, characterized in that, The second track trolley includes a trolley frame B connected to the upper slide rail. A set of traveling wheels B is respectively provided at the four corners of the bottom of the trolley frame B. A traveling reduction motor B is provided in the middle of the trolley frame B. A main drive gear B is installed on the power output shaft of the traveling reduction motor B. Track steels B that cooperate with the corresponding traveling wheels B are provided on both sides of the second traveling track along its length direction. A rack B that meshes with the main drive gear B is provided between the two sets of track steels B. The rack B is provided along the length direction of the second traveling track. The traveling reduction motor A moves synchronously with the traveling reduction motor B. A third drive device that drives the second upper slide to move along the length direction of the upper slide rail is also installed on the second upper slide.

4. The automatic steel structure welding production line according to claim 2, characterized in that, The two ends of the upper slide rail are fixed to the trolley traveling frame A and the trolley traveling frame B, respectively.

5. The automatic steel structure welding production line according to claim 3, characterized in that, The second drive device includes a travel reduction motor C mounted on the first upper slide, a main drive gear C mounted on the power output shaft of the travel reduction motor C, and a rack C meshing with the main drive gear C on the upper slide rail. The second drive device and the third drive device have the same structure.

6. The automatic steel structure welding production line according to claim 1, characterized in that, The steel pipe cutting structure includes a first robotic arm.

7. The automatic steel structure welding production line according to claim 1, characterized in that, The steel pipe pushing mechanism includes a frame fixed on the second upper slide, with an upper wheel set and a lower wheel set on the frame. A tubular support beam passes between the upper wheel set and the lower wheel set. The drive wheels of the upper wheel set and the lower wheel set are directly connected by a reduction motor F. The upper wheel set and the lower wheel set rotate in opposite directions, driving the tubular support beam to move.

8. The automatic steel structure welding production line according to claim 1, characterized in that, The guide tube is fixed to the first upper slide by a support column.

Citation Information

Patent Citations

  • Small-cylinder-diameter-ratio pipe connector submerged arc saddle-shaped automatic welding method

    CN103962694A

  • Six-axis intersecting line cutting welding robot and work method

    CN111318826A