A rapid construction method for large-volume piers at docks

Through the method of layered concrete pouring and reserved PVC pipes, combined with the use of tensioning and form removal devices, the problem of difficulty in dismantling the bottom form support structure caused by insufficient cranes has been solved, and the construction efficiency and safety of large-volume piers at the wharf have been improved. It is suitable for on-site construction with limited resources.

CN118223417BActive Publication Date: 2024-10-18THE FIRST CONSTRUCTION COMPANY OF CCCC SECOND HARBOR ENGINEERING CO LTD +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410515306.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-26
Publication Date
2024-10-18
Estimated Expiration
2044-04-26

AI Technical Summary

Technical Problem

In the case of insufficient crane resources, it is difficult to quickly dismantle the bottom form support structure of the large-volume pier of the wharf with existing technology, resulting in low construction efficiency, high safety risks, and inability to meet the construction schedule requirements.

Method used

Adopt the concrete layered pouring method, reserve vertical PVC pipes, install tensioning devices on the pipes, cut off the steel corbels, and use the form removal device to gradually dismantle the bottom form support structure, including extracting distribution beams, secondary beams and main beams. until completely removed.

Benefits of technology

It achieves efficient dismantling of the bottom formwork support structure, reduces the frequency of underwater operations, and improves construction safety and efficiency. It is suitable for large-volume pier construction, can be completed by a single person on site, and adapts to the arrangements of different construction cycles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118223417B_ABST
    Figure CN118223417B_ABST
Patent Text Reader

Abstract

The present invention provides a method for rapid construction of large-volume piers at a dock. The method has high construction efficiency, and the second layer of concrete can be directly constructed without removing the bottom formwork, so the pier body can be quickly formed. The operation is convenient, and the elevation of the bottom formwork support structure is lowered compared to the traditional unloading sand box. There are fewer underwater operations and good safety. The method is particularly suitable for the construction of large-volume piers, and solves the problem of difficulty in removing the bottom formwork support structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of rapid construction of large-volume piers, and in particular to a rapid construction method for large-volume piers at a wharf. Background Art

[0002] With the vigorous development of water transport engineering in my country, cast-in-place solid piers are widely used in the construction of docks. The piers are large in size and the bottom formwork support structure is difficult to dismantle. The traditional pier construction platform erection process is the corbel, transverse and longitudinal beam load-bearing bottom formwork method. For projects with pier design elevations that are too low, the welded corbels are seriously affected by the tide and cannot meet the owner's construction period requirements.

[0003] At present, unloading sand boxes are mostly used for dismantling the pier bottom formwork, which involves a lot of underwater operations, high safety risks and low construction efficiency. Therefore, a fast construction method is needed that can quickly dismantle the bottom formwork support structure under limited resources, so as to improve construction efficiency, shorten the construction period and meet the owner's construction period requirements. Summary of the invention

[0004] The main purpose of the present invention is to provide a method for rapid construction of large-volume piers at a wharf, which solves the problem that the bottom formwork support structure cannot be quickly dismantled when crane resources are insufficient.

[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: a method for rapid construction of large-volume piers of a wharf, the method comprising:

[0006] S1. Pour concrete in layers and calculate the load of each pouring;

[0007] S2. Set up the bottom formwork support structure and reserve vertical PVC pipes;

[0008] S3, pouring the first layer of concrete;

[0009] S4, extend the PVC pipe and pour the next layer of concrete;

[0010] S5, repeat step S4 until the pier pouring is completed;

[0011] S6. Install the tensioning device on the PVC pipe and fix it;

[0012] S7, cut off the steel bull leg;

[0013] S8. Use the demoulding device to lower the bottom mold support structure, pull out the distribution beam and secondary beam, pull out the main beam, and remove the panel.

[0014] In the preferred embodiment, in step S1, the initial concrete pouring layer height is 0.6-1m;

[0015] In step S1, a finite element model of the pile and the first pouring of concrete is established, and the pouring layer thickness is determined by calculation and analysis; the load of the second pouring of concrete is loaded on the top surface of the first pouring of concrete; if the calculation result shows that there is a large-area tensile stress, and the value is large, the thickness of the first pouring of concrete is increased, or the thickness of the second pouring of concrete is reduced;

[0016] If the calculation results show no tensile stress, or the tensile stress distribution range is very small, and the value is much smaller than the designed tensile strength, the thickness of the first concrete pouring should be reduced, or the thickness of the second concrete pouring should be increased; if the calculation results show that the tensile stress within 1MPa exists only near the top of the concrete above the pile top, a steel mesh should be installed in the pier concrete above the pile top;

[0017] In the preferred embodiment, in step S2, the bottom mold support structure includes a steel bracket, a main beam, a secondary beam, a distribution beam, and a panel; during installation, the steel bracket is first welded, and then the main beam, the secondary beam, the distribution beam, and the panel are installed in sequence;

[0018] In step S2, a hole is opened in the panel corresponding to the PVC pipe, the bottom of the pipe passes through the bottom mold support structure, and the top is 10 cm higher than the initial concrete pouring;

[0019] In step S6, the fine-rolled threaded steel bar passes through the main beam and a pad and bolts are arranged at the bottom. After the steel corbel is cut off, the fine-rolled threaded steel bar bears the deadweight of the bottom mold support structure.

[0020] In the preferred embodiment, the bottom formwork support structure includes a plurality of hoops, which are arranged on the piers, a bottom formwork support plate is provided above the hoops, a plurality of steel corbels are provided above the bottom formwork support plate, a casting bottom formwork is provided above the steel corbels, and side formwork support plates and casting side formworks are symmetrically provided on both sides of the casting bottom formwork.

[0021] In a preferred embodiment, the tensioning device in step S6 comprises a finely rolled threaded steel bar, the finely rolled threaded steel bar penetrates the PVC pipe, an upper threaded sleeve is provided above the finely rolled threaded steel bar, and a lower threaded sleeve is provided below the finely rolled threaded steel bar;

[0022] A weighing pad is also provided between the upper screw sleeve and the PVC pipe. The upper screw sleeve is arranged above the concrete, and the lower screw sleeve is arranged below the concrete. The tensioning device is used to tighten the bottom formwork support plate.

[0023] In the preferred embodiment, a detachable lifting buckle is also provided on the top of the fine-rolled threaded steel bar.

[0024] In a preferred embodiment, the demoulding device in step S8 comprises a base, a plurality of guide holes are provided on an upper surface of the base, and slidable guide rods are coaxially arranged in the guide holes;

[0025] A top plate is arranged on the top of the guide rod, a jack is arranged between the top plate and the base, a notch is arranged on one side of the base, a roller is arranged on the other side, and a handle is arranged above the roller.

[0026] In the preferred embodiment, a clamping plate is provided on one side of the top plate near the notch, and relatively movable clamping plates are provided between the clamping plates;

[0027] A clamping groove is arranged on one side opposite to the clamping plate, and a guide column is arranged between the clamping plate and the clamping vertical plate.

[0028] In the preferred embodiment, a screw is further provided between the clamping plate and the clamping vertical plate, and the clamping plate is arranged on the screw. When the screw is rotated, the clamping plate moves relatively on the screw at the same time;

[0029] The screw rod passes through the clamping upright plates at both sides, the screw rod is rotatably connected with the clamping upright plates at both sides, and rotating rings are arranged at both ends of the screw rod.

[0030] In the preferred embodiment, a detachable extension sleeve is also provided in the notch, and the extension sleeve is used to facilitate the operator to remove the upper screw sleeve;

[0031] A plurality of anti-skid grooves are arranged in the clamping groove, the anti-skid grooves are semicircular, and the groove walls are perpendicular to the axial direction of the precision-rolled threaded steel bar.

[0032] The present invention provides a method for rapid construction of large-volume piers at a wharf, which has the following beneficial effects:

[0033] 1. This construction method has high construction efficiency. The second layer of concrete can be directly constructed without removing the bottom formwork, which can quickly form the main body of the pier. It is easy to operate. Compared with the traditional unloading sand box, the elevation of the bottom formwork support structure is lowered, there are fewer underwater operations, and the safety is good. It is particularly suitable for large-volume pier construction;

[0034] 2. In the demolding stage of this construction method, the bottom formwork support structure can be dismantled without a crane on site. The entire bottom formwork support structure can be dismantled by a single person, which has better practicality. The construction personnel can be reasonably arranged and the construction progress can be adjusted according to the actual construction period. BRIEF DESCRIPTION OF THE DRAWINGS

[0035] The present invention will be further described below in conjunction with the accompanying drawings and embodiments:

[0036] Figure 1 is a schematic diagram of pouring concrete for the first time according to the present invention;

[0037] Figure 2 It is a schematic diagram of the installation of the tensioning device of the present invention;

[0038] Figure 3 is an enlarged view of the tensioning device of the present invention;

[0039] Figure 4is a cross-sectional view of the mold removal device of the present invention;

[0040] Figure 5 It is a schematic diagram of the axial layout of the demoulding device of the present invention;

[0041] Figure 6 is an isometric view of the mold removal device of the present invention;

[0042] Figure 7 is a cross-sectional view of the clamping vertical plate of the present invention;

[0043] Figure 8 It is a front view of the demoulding device of the present invention.

[0044] In the figure: pier 1; bottom form support plate 2; side form support plate 3; concrete 4; tensioning device 5; precision-rolled threaded steel 501; upper screw sleeve 502; load-bearing pad 503; lower screw sleeve 504; lifting buckle 505; PVC pipe 6; demoulding device 7; base 701; top plate 702; jack 703; handle 704; guide rod 705; roller 706; clamping plate 707; guide hole 708; guide column 709; notch 710; clamping vertical plate 711; screw 712; rotating ring 713; extension sleeve 714; clamping groove 715; hoop 8. DETAILED DESCRIPTION

[0045] Example 1

[0046] like Figure 1-8 As shown, a method for rapid construction of a large-volume pier at a wharf comprises:

[0047] S1. Pour concrete in 4 layers and calculate the load of each pouring;

[0048] S2. Set up the bottom formwork support structure and reserve the vertical PVC pipe 6;

[0049] S3, pouring the first layer of concrete 4;

[0050] S4, extend the PVC pipe 6 and pour the next layer of concrete 4;

[0051] S5, repeat step S4 until the pier pouring is completed;

[0052] S6, install the tensioning device 5 at the PVC pipe 6 and fix it;

[0053] S7, cut off the steel bull leg;

[0054] S8. Use the demoulding device 7 to lower the bottom mold support structure, pull out the distribution beam and secondary beam, pull out the main beam, and remove the panel.

[0055] In the preferred embodiment, in step S1, the initial pouring of concrete 4 has a layer height of 0.6 to 1 m;

[0056] In step S1, a finite element model of the pile and the first pouring of concrete 4 is established, and the pouring layer thickness is determined by calculation and analysis; the load of the second pouring of concrete 4 is loaded on the top surface of the first pouring of concrete 4; if the calculation result shows that there is a large-area tensile stress, and the value is large, the thickness of the first pouring of concrete 4 is increased, or the thickness of the second pouring of concrete 4 is reduced;

[0057] If the force of the bottom formwork support system is not fully exerted, the thickness of the initial concrete pouring will be increased; if the force of the bottom formwork support system is close to the limit, the concrete pouring layers will be increased and the thickness of the second concrete pouring will be reduced;

[0058] If the calculation results show that there is no tensile stress, or the tensile stress distribution range is very small, and the value is much smaller than the designed tensile strength, then the thickness of the first pouring of concrete 4 is reduced, or the thickness of the second pouring of concrete 4 is increased; if the calculation results show that there is a tensile stress of less than 1MPa only near the top of the concrete 4 above the pile top, then a steel mesh is installed at the pier concrete 4 above the pile top;

[0059] In the preferred embodiment, in step S2, the bottom mold support structure includes a steel bracket, a main beam, a secondary beam, a distribution beam, and a panel; during installation, the steel bracket is first welded, and then the main beam, the secondary beam, the distribution beam, and the panel are installed in sequence;

[0060] In step S2, a hole is opened in the panel corresponding to the PVC pipe 6, the bottom of the pipe passes through the bottom mold support structure, and the top is 10 cm higher than the initial pouring of concrete 4;

[0061] In step S6, the fine-rolled threaded steel 501 passes through the main beam and a pad and bolts are set at the bottom. After the steel corbel is cut off, the fine-rolled threaded steel 501 bears the deadweight of the bottom mold support structure.

[0062] In the preferred embodiment, the bottom formwork support structure includes a plurality of hoops 8, which are arranged on the pier 1. A bottom formwork support plate 2 is provided above the hoops 8, a plurality of steel corbels are provided above the bottom formwork support plate 2, a casting bottom formwork is provided above the steel corbels, and side formwork support plates 3 and casting side formworks are symmetrically provided on both sides of the casting bottom formwork.

[0063] In the preferred embodiment, the tensioning device 5 in step S6 includes a finely rolled threaded steel bar 501, the finely rolled threaded steel bar 501 penetrates the PVC pipe 6, an upper threaded sleeve 502 is provided above the finely rolled threaded steel bar 501, and a lower threaded sleeve 504 is provided below the finely rolled threaded steel bar 501;

[0064] A weighing pad 503 is also provided between the upper screw sleeve 502 and the PVC pipe 6 . The upper screw sleeve 502 is arranged above the concrete 4 , and the lower screw sleeve 504 is arranged below the concrete 4 . The tensioning device 5 is used to tighten the bottom mold support plate 2 .

[0065] In the preferred embodiment, a detachable lifting buckle 505 is also provided on the top of the fine-rolled threaded steel bar 501 .

[0066] In the preferred embodiment, the demoulding device 7 in step S8 comprises a base 701, a plurality of guide holes 708 are provided on an upper surface of the base 701, and slidable guide rods 705 are coaxially arranged in the guide holes 708;

[0067] A top plate 702 is provided on the top of the guide rod 705 , and a jack 703 is provided between the top plate 702 and the base 701 . A notch 710 is provided on one side of the base 701 , and a roller 706 is provided on the other side. A handle 704 is provided above the roller 706 .

[0068] In the preferred embodiment, a clamping plate 711 is provided on one side of the top plate 702 near the notch 710, and a relatively movable clamping plate 707 is provided between the clamping plates 711;

[0069] A clamping groove 715 is provided on one side opposite to the clamping plate 707 , and a guide column 709 is provided between the clamping plate 707 and the clamping vertical plate 711 .

[0070] In the preferred embodiment, a screw 712 is further provided between the clamping plate 707 and the clamping vertical plate 711, and the clamping plate 707 is arranged on the screw 712. When the screw 712 is rotated, the clamping plate 707 moves relatively on the screw 712 at the same time;

[0071] The screw rod 712 passes through the clamping upright plates 711 on both sides. The screw rod 712 is rotatably connected to the clamping upright plates 711 on both sides. Rotating rings 713 are provided at both ends of the screw rod 712 .

[0072] In the preferred embodiment, a detachable extension sleeve 714 is further provided in the notch 710, and the extension sleeve 714 is used to facilitate the operator to remove the upper screw sleeve 502;

[0073] A plurality of anti-skid grooves are provided in the clamping groove 715 . The anti-skid grooves are semicircular in shape, and the groove walls are perpendicular to the axial direction of the precision-rolled threaded steel bar 501 .

[0074] A method for rapid construction of large-volume piers at a wharf is specifically implemented as follows:

[0075] S1. Concrete layering, calculate the load of the divided pouring, the initial pouring concrete layer height is 0.6~1m; establish the finite element model of the pile and the first pouring concrete, and determine the pouring layer thickness through calculation and analysis; load the second pouring concrete on the top surface of the first pouring concrete; if the calculation result shows a large area tensile stress, and the value is large, increase the thickness of the first pouring concrete, or reduce the thickness of the second pouring concrete;

[0076] If the calculation results show no tensile stress, or the tensile stress distribution range is very small, and the value is much smaller than the designed tensile strength, the thickness of the first concrete pouring should be reduced, or the thickness of the second concrete pouring should be increased; if the calculation results show that the tensile stress within 1MPa exists only near the top of the concrete above the pile top, a steel mesh should be installed in the pier concrete above the pile top;

[0077] S2. Use a clamp 8 to clamp onto the pier column 1, and set up a bottom formwork support plate structure above the clamp 8. The bottom formwork support structure includes a steel corbel, a main beam, a secondary beam, a distribution beam, and a panel. During installation, the steel corbel is first welded, and then the main beam, the secondary beam, the distribution beam, and the panel are installed in sequence. A bottom formwork support plate 2 is provided below the steel corbel, and the bottom formwork support plate 2 is arranged above the pier column 1. A clamp 8 is provided between the bottom formwork support plate 2 and the pier column 1.

[0078] A casting bottom formwork is arranged above the steel corbel, and side formwork support plates 3 and casting side formwork are symmetrically arranged on both sides of the casting bottom formwork. A vertical PVC pipe 6 is reserved, and a panel opening is made at the corresponding position of the PVC pipe 6. The bottom of the pipe passes through the bottom formwork support structure, and the top is 10 cm higher than the initial pouring of concrete.

[0079] S3, pour the first layer of concrete 4. Pay attention to evenly pouring when pouring, and do not pour a large amount of concrete in a concentrated manner to avoid stress concentration;

[0080] S4, after the first layer of concrete 4 has initially set, the PVC pipe 6 is extended, and then the next layer of concrete 4 is poured;

[0081] S5, repeat step S4 until the pier pouring is completed;

[0082] S6, first install the load-bearing pad 503 above the PVC pipe 6, the load-bearing pad can prevent the upper screw sleeve 502 from directly crushing the concrete 4, and then install the tensioning device 5 and fix it. The installation process is as follows: first make the fine-rolled threaded steel 501 pass through the PVC pipe 6 and the load-bearing pad 503, install the lower screw sleeve 504 at its bottom, and install the upper screw sleeve 502 above the load-bearing pad 503;

[0083] S7. After each tensioning device 5 is installed, cut off the steel corbel at the bottom and remove the clamp 8 on the bottom pier 1. The cutting of the steel corbel and the removal of the clamp 8 should comply with the principle of uniform force. Cut from the middle to both sides to avoid stress concentration on one side. After the steel corbel is cut off, the fine-rolled threaded steel 501 bears the deadweight of the bottom mold support structure.

[0084] S8. When removing the formwork, use the demoulding device 7 to lower the bottom formwork support structure, pull out the distribution beam and the secondary beam, pull out the main beam, and remove the panel. The demoulding device 7 is small and flexible, and the demoulding method is also relatively flexible.

[0085] The method is as follows: the demoulding device 7 is moved to the tensioning device 5, and the handle 704 in the demoulding device 7 is pressed downward to form a lever at the roller 706, so that the roller 706 can roll above the concrete 4, making it easier for the operator to move the demoulding device 7;

[0086] The rotating ring 713 is rotated to open the clamping plate 707. A steel bar or other rod-shaped object can be inserted into the rotating ring 713 to facilitate clamping the fine-rolled threaded steel 501. The extension sleeve 714 is first sleeved on the tensioning device 5 to be removed. After the clamping plate 707 is opened, the demolding device 7 is pushed to make the notch 710 face the extension sleeve 714, so that the fine-rolled threaded steel 501 is just located between the clamping grooves 715. The rotating ring 713 is rotated to make the clamping grooves 715 clamp the fine-rolled threaded steel 501.

[0087] After clamping the fine-rolled threaded steel bar 501, rotate the extension sleeve 714 to loosen the upper screw sleeve 502, so that the upper screw sleeve 502 moves upward to the designed distance, and then rotate the rotating ring 713 to loosen the clamping groove 715. At this time, the fine-rolled threaded steel bar 501 will fall down a short distance due to the deadweight of the bottom die support structure below, and then continue to repeat the above-mentioned demoulding operation to the next tensioning device 5 until the bottom die support structure is completely removed;

[0088] This method is mostly used in scenarios where there is a lack of operable equipment on site. If two small jacks are used to support the tensioning device 5 from both sides for removal, there is a risk that the tensioning device 5 will tilt and bend due to the inconsistent descending speed of the jacks on both sides. Therefore, it is safer to use a dedicated demoulding device 7.

[0089] When there is more than one demoulding device 7, the following can be used: Figure 5 The diagonal demoulding method shown in the figure enables point A, point B, point C, and point D to be demolished in pairs, for example, point A and point D are demolished first, and then point B and point D are demolished, so as to ensure that the force on the bottom mold support structure is uniform. If there are four demoulding devices 7, the four points can be demolished at the same time. The demoulding device is simple and easy to operate, and the corresponding number of devices can be arranged according to the actual construction progress, so as to ensure the demoulding speed and improve the overall construction progress.

[0090] A lifting buckle 505 is also provided at the top of the tensioning device 5. When a crane is available on site, the lifting buckle 505 can be directly installed on the top of the finished rolled threaded steel bar 501, and the crane can be used instead of the demolding device 7 for demolding.

[0091] The above embodiments are only preferred technical solutions of the present invention and should not be regarded as limiting the present invention. The protection scope of the present invention shall be the technical solutions recorded in the claims, including equivalent replacement solutions of the technical features in the technical solutions recorded in the claims. That is, equivalent replacement improvements within this scope are also within the protection scope of the present invention.

Claims

1. A method for rapid construction of large-volume piers at a wharf, characterized by: The method includes: S1. Concrete (4) is poured in layers and the load of each pouring is calculated; S2. Set up the bottom formwork support structure and reserve the vertical PVC pipe (6); S3, pouring the first layer of concrete (4); S4, extend the PVC pipe (6) and pour the next layer of concrete (4); S5, repeat step S4 until the pier pouring is completed; S6. Install the tensioning device (5) on the PVC pipe (6) and secure it; S7, cut off the steel bull leg; S8, using the demoulding device (7) to lower the bottom mold support structure, pull out the distribution beam and the secondary beam, pull out the main beam, and remove the panel; The tensioning device (5) in step S6 comprises a finely rolled threaded steel bar (501), the finely rolled threaded steel bar (501) passes through the PVC pipe (6), an upper threaded sleeve (502) is provided above the finely rolled threaded steel bar (501), and a lower threaded sleeve (504) is provided below the finely rolled threaded steel bar (501); A weighing pad (503) is also provided between the upper screw sleeve (502) and the PVC pipe (6); the upper screw sleeve (502) is arranged above the concrete (4); the lower screw sleeve (504) is arranged below the concrete (4); and the tensioning device (5) is used to tighten the bottom formwork support plate (2); The demoulding device (7) in step S8 comprises a base (701), a plurality of guide holes (708) are provided on an upper surface of the base (701), and slidable guide rods (705) are coaxially arranged in the guide holes (708); A top plate (702) is provided on the top of the guide rod (705), a jack (703) is further provided between the top plate (702) and the base (701), a notch (710) is provided on one side of the base (701), a roller (706) is provided on the other side, and a handle (704) is provided above the roller (706); A clamping vertical plate (711) is provided on one side of the top plate (702) close to the notch (710), and relatively movable clamping plates (707) are provided between the clamping vertical plates (711); A clamping groove (715) is provided on one side opposite to the clamping plate (707), and a guide column (709) is provided between the clamping plate (707) and the clamping vertical plate (711); A screw rod (712) is also provided between the clamping plate (707) and the clamping vertical plate (711), and the clamping plate (707) is provided on the screw rod (712). When the screw rod (712) is rotated, the clamping plate (707) and the screw rod (712) move relatively at the same time. The screw rod (712) passes through the clamping vertical plates (711) on both sides, the screw rod (712) is rotatably connected to the clamping vertical plates (711) on both sides, and rotating rings (713) are provided at both ends of the screw rod (712); A detachable extension sleeve (714) is also provided in the notch (710), and the extension sleeve (714) is used to facilitate an operator to remove the upper screw sleeve (502); A plurality of anti-skid grooves are provided in the clamping groove (715), the anti-skid grooves are semicircular, and the groove walls are perpendicular to the axial direction of the fine-rolled threaded steel bar (501).

2. A method for rapid construction of large-volume piers according to claim 1, characterized in that: In step S1, the initial pouring of concrete (4) has a layer height of 0.6-1 m; In step S1, a finite element model of the pile and the first pouring of concrete (4) is established, and the pouring layer thickness is determined by calculation and analysis; the load of the second pouring of concrete (4) is applied to the top surface of the first pouring of concrete (4); if the calculation result shows that there is a large-area tensile stress, and the value is large, the thickness of the first pouring of concrete (4) is increased, or the thickness of the second pouring of concrete (4) is reduced; If the calculation result shows that there is no tensile stress, or the tensile stress distribution range is very small and the value is much smaller than the designed tensile strength, the thickness of the first pouring concrete (4) is reduced, or the thickness of the second pouring concrete (4) is increased; if the calculation result shows that the tensile stress within 1 MPa exists only near the top of the concrete (4) above the pile top, a steel mesh is provided at the pier concrete (4) above the pile top.

3. A method for rapid construction of large-volume piers according to claim 1, characterized in that: In step S2, the bottom mold support structure includes a steel bracket, a main beam, a secondary beam, a distribution beam, and a panel; during installation, the steel bracket is first welded, and then the main beam, the secondary beam, the distribution beam, and the panel are installed in sequence; In step S2, a hole is opened in the panel at a location corresponding to the PVC pipe (6), the bottom of the pipe passes through the bottom formwork support structure, and the top is 10 cm higher than the initial pouring of concrete (4); In step S6, the fine-rolled threaded steel (501) passes through the main beam and a pad and bolts are arranged at the bottom. After the steel corbel is cut off, the fine-rolled threaded steel (501) bears the deadweight of the bottom mold support structure.

4. A method for rapid construction of large-volume piers according to claim 3, characterized in that: The bottom formwork support structure also includes a plurality of hoops (8), the hoops (8) are arranged on the pier (1), a bottom formwork support plate (2) is arranged above the hoops (8), a plurality of steel brackets are arranged above the bottom formwork support plate (2), a casting bottom formwork is arranged above the steel brackets, and side formwork support plates (3) and casting side formworks are symmetrically arranged on both sides of the casting bottom formwork.

5. A method for rapid construction of large-volume piers according to claim 4, characterized in that: The top of the fine-rolled threaded steel bar (501) is also provided with a detachable lifting buckle (505).

Citation Information

Patent Citations

  • Combined type bridge temporary support and construction method for rapidly building continuous beams by virtue of same

    CN105133487A

  • Special construction method for dragging main beam of extra-large bridge

    CN111287095A