A TBM excavation parameter optimization system and optimization method
Through the TBM boring parameter optimization system, the Monte Carlo model and simulation curve comparison technology are used to solve the problem of experience in adjusting the TBM boring parameter, improve construction efficiency and accuracy, and ensure the smooth progress of tunnel boring.
Patent Information
- Application Number
- CN202410277552.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-12
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-03-12
AI Technical Summary
TBM excavation parameters adjustment depends on experience, resulting in uneven construction efficiency and the inability to reasonably determine the optimization timing, affecting the excavation speed and accuracy.
A TBM excavation parameter optimization system was designed, including the engineer terminal interaction module, rock mass excavation data acquisition module and edge computing gateway control module. The Monte Carlo model is used to calculate the optimal efficiency, and determine whether it is done through real-time and ideal efficiency simulation curve comparison. It is necessary to optimize the excavation parameters and adjust the cutting wheel speed and torque to improve the excavation efficiency.
The efficiency and accuracy of TBM excavation parameter optimization are improved, the smooth progress of the excavation process is ensured, and the data processing volume is reduced, which enhances the accuracy of parameter optimization.
Smart Images

Figure CN118223903B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of tunnel TBM excavation parameter optimization, and in particular to a TBM excavation parameter optimization system and an optimization method thereof. Background Art
[0002] Full-face tunnel boring machines (TBMs) have been increasingly widely used in tunnel engineering. However, the conditions of the surrounding rock in the excavation strata are relatively sensitive to changes. When the rock conditions in front of the excavation face change, it is necessary to adjust the corresponding TBM excavation control parameters (cutterhead thrust, TBM penetration, cutterhead speed, etc.) in time to achieve the best TBM excavation state. At present, the adjustment of excavation parameters during TBM construction has the following main shortcomings:
[0003] (1) Tunnel excavation geological conditions are complex, and TBM operators mainly adjust excavation parameters based on experience. TBM construction efficiency depends largely on the driver's operating level;
[0004] (2) The existing TBM excavation mode does not take into account the impact of the selection of TBN excavation control parameters on the equipment torque, resulting in uneven excavation speed.
[0005] In view of the above-mentioned deficiencies, the present invention patent proposes a TBM excavation parameter optimization system and an optimization method thereof. Summary of the invention
[0006] The present invention aims to solve at least one of the technical problems existing in the prior art; to this end, the present invention proposes a TBM excavation parameter optimization system and method, which are used to solve the technical problems that the prior art needs to perform a large amount of data processing when optimizing TBM excavation parameters, and cannot reasonably determine the timing of TBM excavation parameter optimization, resulting in the inability to balance the efficiency and accuracy of TBM excavation parameter optimization.
[0007] To achieve the above-mentioned purpose, the first aspect of the present invention provides a TBM excavation parameter optimization system, including an engineer terminal interaction module, and a rock excavation data acquisition module and an edge computing gateway control module connected thereto; and the rock excavation data acquisition module is connected to an excavation distance control module of different geological types;
[0008] Rock excavation data collection module: During the normal implementation of the cutter head speed of different geological types, the rock excavation process data per unit time of the TBM excavation parameters of each rock layer structure is collected through the rock excavation distance connected to it, and transmitted to the engineer terminal interaction module;
[0009] Engineer terminal interaction module: The Monte Carlo model unit is used to calculate the optimal efficiency of the excavation cutter head speed of different geological types, and the real-time rock excavation efficiency is determined according to the engineering project management information. The optimal efficiency and the real-time rock excavation efficiency are compared to determine whether TBM excavation parameter optimization is required; if parameter optimization is required, the rock excavation process data per unit time of the TBM excavation parameters of each rock layer structure are collected, and if parameter optimization is not required, rock excavation is continued according to the rock excavation distance; and the mining efficiency of the TBM excavation parameters per unit time of the TBM excavation parameters of each rock layer structure is calculated based on the rock excavation process data per unit time; a real-time efficiency simulation curve is drawn for the mining efficiency of different TBM excavation parameters, and the real-time efficiency simulation curve is compared and analyzed with the ideal efficiency simulation curve to determine the optimized rock layer structure TBM excavation parameters; wherein, the ideal efficiency simulation curve is calculated using the Monte Carlo model unit.
[0010] Furthermore, the engineer terminal interaction module is respectively connected to the rock excavation data acquisition module and the edge computing gateway control module in communication; and the edge computing gateway control module includes a cloud server;
[0011] The rock excavation data acquisition module is in communication connection with the rock excavation distance at the rotation speed of the excavation cutter head of different geological types; and the rock excavation distance matches the different rock excavation stages of the TBM excavation parameters of each rock layer structure.
[0012] Furthermore, the engineer terminal interaction module uses Monte Carlo model unit matching to obtain the optimal efficiency of the cutter head rotation speed of different geological types, and uses the optimal efficiency to determine whether TBM excavation parameter optimization is required, including:
[0013] The Monte Carlo model unit is connected, and the step-shaped excavation efficiency per unit time of the standard rock tunneling cutter head speed is calculated therefrom; wherein the tunneling cutter head speeds of different geological types have the same energy consumption as the standard rock tunneling cutter head speed or the rock layer structure TBM excavation parameters included;
[0014] The median of the rock excavation efficiency at different stages of the step excavation efficiency is obtained, which is recorded as the optimal efficiency; the step excavation efficiency of the excavation cutter head speed of different geological types is obtained, which is recorded as the real-time rock excavation efficiency; wherein the median of the rock excavation efficiency at different stages includes the efficiency affected by human factors or natural environmental factors;
[0015] When the real-time rock excavation efficiency is weaker than the optimal efficiency, it is determined that the TBM excavation parameters need to be optimized for the excavation cutter head speeds of the different geological types; otherwise, it is determined that the TBM excavation parameters do not need to be optimized for the excavation cutter head speeds of the different geological types.
[0016] Further, when it is determined that the TBM excavation parameters need to be optimized for the excavation cutter head speeds of the different geological types, the rock excavation progress data per unit time is acquired by collecting the rock excavation distance set on the excavation cutter head speeds of the different geological types; and
[0017] The rock excavation progress data per unit time is screened and then transmitted to the engineer terminal interaction module; wherein the rock excavation progress data per unit time includes rock excavation energy consumption data and torque size data.
[0018] Furthermore, the engineer terminal interaction module extracts the TBM excavation parameter mining efficiency corresponding to each rock layer structure TBM excavation parameter from the rock excavation process data per unit time, and draws the real-time efficiency simulation curve based on the different TBM excavation parameter mining efficiencies, including:
[0019] Extracting torque size data of TBM excavation parameters of each rock structure from the rock excavation process data per unit time, and calculating the excavation efficiency of the TBM excavation parameters of each rock structure per unit time using the torque size data;
[0020] For the excavation efficiency of different TBM excavation parameters, an independent variable is established according to the rock excavation time, and the real-time efficiency simulation curve is drawn by fitting with the excavation efficiency of TBM excavation parameters as the dependent variable.
[0021] Furthermore, the engineer terminal interaction module obtains the ideal efficiency simulation curve based on the rock excavation process data per unit time corresponding to the rock excavation cutter head speeds of different standards when the step-shaped excavation efficiency is achieved, including:
[0022] The step-shaped excavation efficiency is used to preferentially screen out a standard rock mass excavation cutter head speed from different standard rock mass excavation cutter head speeds, and the corresponding unit time rock mass excavation process data is calibrated as the preset rock mass excavation process data;
[0023] The TBM excavation parameter excavation efficiency of the TBM excavation parameters of each rock layer structure is obtained from the preset rock excavation process data and calibrated as the preset excavation efficiency; the horizontal axis is plotted per unit time for different preset excavation efficiencies to obtain the ideal efficiency simulation curve.
[0024] Furthermore, the engineer terminal interaction module compares the real-time efficiency simulation curve with the ideal efficiency simulation curve, and optimizes the TBM excavation parameters of each rock structure according to the comparison result, including:
[0025] Comparing the real-time efficiency simulation curve with the ideal efficiency simulation curve, determining the rock structure TBM excavation parameters corresponding to the parts of the two simulation curves where the horizontal and vertical coordinates are completely consistent, and calibrating them as the TBM excavation parameters to be optimized;
[0026] The influence of excavation efficiency noise of the TBM excavation parameters to be optimized is determined according to the real-time efficiency simulation curve and the ideal efficiency simulation curve; and the torque size data of the TBM excavation parameters to be optimized is adjusted within the rock excavation energy consumption data to reduce the influence of excavation efficiency noise.
[0027] A second aspect of the present invention provides a TBM excavation parameter optimization method, comprising:
[0028] Using the cutterhead speeds of various standard rock mass excavation records and the corresponding stepped excavation efficiencies recorded in the Monte Carlo model unit, the optimal efficiency is obtained based on the median of the rock mass excavation stage efficiency with different stepped excavation efficiencies;
[0029] Obtain the real-time rock excavation efficiency of the cutterhead speed for different geological types; compare the real-time rock excavation efficiency with the optimal efficiency to determine whether to optimize the TBM excavation parameters for the cutterhead speed for different geological types;
[0030] The TBM excavation parameter excavation efficiency of each rock structure TBM excavation parameter is calculated based on the collected rock excavation process data per unit time, and then the real-time efficiency simulation curve is obtained; the real-time efficiency simulation curve is compared with the ideal efficiency simulation curve to determine and optimize the rock structure TBM excavation parameters. Beneficial Effects
[0031] The present invention first determines the optimal efficiency according to the standard rock tunneling cutter head speed, and determines whether it is necessary to optimize the TBM tunneling parameters based on the optimal efficiency; obtains the excavation efficiency of different TBM tunneling parameters by analyzing the rock tunneling process data per unit time of the tunneling cutter head speed of different geological types, and then sorts out and obtains the real-time efficiency simulation curve; compares the real-time efficiency simulation curve with the ideal efficiency simulation curve obtained by the standard rock tunneling cutter head speed to determine the TBM tunneling parameters to be optimized and the optimization value; while ensuring the accuracy of TBM tunneling parameter optimization, the data processing amount is reduced, thereby improving the TBM tunneling parameter optimization efficiency. By comparing the real-time efficiency simulation curve and the ideal efficiency simulation curve, the present invention can not only determine which rock layer structure TBM tunneling parameters need to be optimized, and determine the optimization range, and after completing the TBM tunneling parameters at the tunneling cutter head speeds of different geological types, the relevant data can also be uploaded to the Monte Carlo model unit to adjust the standard rock tunneling cutter head speed, which is helpful to improve the accuracy of TBM tunneling parameter optimization, make the parameters of tunnel rock tunneling more reasonable, and thus smoothly carry out tunneling. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 It is a schematic diagram of the system module composition of the present invention;
[0033] Figure 2 The present invention is a schematic diagram of the process flow of the method. DETAILED DESCRIPTION
[0034] The technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0035] like Figure 1 As shown, the first embodiment of the present invention provides a TBM excavation parameter optimization system, including an engineer terminal interaction module, and a rock excavation data acquisition module and an edge computing gateway control module connected thereto; and the rock excavation data acquisition module is connected to an excavation distance control module of different geological types;
[0036] Rock excavation data collection module: During the normal implementation of the cutter head speed of different geological types, the rock excavation process data per unit time of the TBM excavation parameters of each rock layer structure is collected through the rock excavation distance connected to it, and transmitted to the engineer terminal interaction module;
[0037] Engineer terminal interactive module: Use Monte Carlo model units to calculate the optimal efficiency of the cutter head speed for different geological types, determine the real-time rock excavation efficiency based on the project management information, and compare the optimal efficiency with the real-time rock excavation efficiency to determine whether TBM excavation parameter optimization is needed; if parameter optimization is needed, collect the rock excavation process data per unit time of the TBM excavation parameters of each rock layer structure; if parameter optimization is not needed, continue rock excavation according to the rock excavation distance; and
[0038] The excavation efficiency of TBM excavation parameters per unit time of each rock structure is calculated based on the rock excavation process data per unit time; a real-time efficiency simulation curve is drawn for the excavation efficiency of different TBM excavation parameters, and the real-time efficiency simulation curve is compared and analyzed with the ideal efficiency simulation curve to determine the optimized rock structure TBM excavation parameters; among which, the ideal efficiency simulation curve is calculated using the Monte Carlo model unit.
[0039] The TBM excavation parameter optimization in the prior art mainly optimizes the various parameters of the TBM excavation parameters, generally by comparing the torque size data of the TBM excavation parameters with the optimal implementation parameters for comparison and adjustment. However, this method is only effective for optimizing a single TBM excavation parameter, and the effect is not good when multiple TBM excavation parameters need to be implemented in coordination. A Gray Wolf optimization algorithm can also be established based on a combination of optimal parameters of the TBM excavation parameters, and the Gray Wolf optimization algorithm is used to search in the constructed search space to complete the optimization of multiple TBM excavation parameters. This method requires a lot of data preparation work, which affects the efficiency and accuracy of TBM excavation parameter optimization.
[0040] The present invention first determines the optimal efficiency according to the standard rock tunneling cutter head speed, and determines whether it is necessary to optimize the TBM tunneling parameters based on the optimal efficiency; obtains the excavation efficiency of different TBM tunneling parameters by analyzing the rock tunneling process data per unit time of the tunneling cutter head speed of different geological types, and then obtains the real-time efficiency simulation curve; compares the real-time efficiency simulation curve with the ideal efficiency simulation curve obtained by the standard rock tunneling cutter head speed to determine the TBM tunneling parameters to be optimized and the optimization value; reduces the data processing amount while ensuring the accuracy of TBM tunneling parameter optimization, thereby improving the TBM tunneling parameter optimization efficiency.
[0041] In the application of the present invention, the engineer terminal interaction module is communicated with the rock excavation data acquisition module and the edge computing gateway control module respectively; and the edge computing gateway control module includes a cloud server; the rock excavation data acquisition module is communicated with the rock excavation distance at the rotation speed of the excavation cutter head of different geological types; and the rock excavation distance matches the different rock excavation stages of the TBM excavation parameters of each rock structure.
[0042] The engineer terminal interaction module mainly performs data processing and interacts with the rock excavation data acquisition module and the edge computing gateway control module. The edge computing gateway control module is used to display the TBM excavation parameter optimization process and present the optimization suggestions to the staff. The rock excavation data acquisition module is mainly used to collect the rock excavation process data per unit time of the excavation cutter head speed of different geological types, and interacts with the rock excavation distance and the engineer terminal interaction module. It should be noted that the rock excavation distance includes cameras, efficiency sensors, etc., which can be set next to the rock structure TBM excavation parameters, and can be installed inside the rock structure TBM excavation parameters if necessary.
[0043] The Monte Carlo model unit mainly stores different standard rock cutting disc speeds and corresponding rock cutting process data, including torque size data of each TBM cutting parameter under the step-shaped excavation efficiency state. And the relevant data in the Monte Carlo model unit will be updated in time to ensure the reliability of the Monte Carlo model unit. It is understandable that after the TBM excavation parameters of each rock layer structure of the cutting disc speed of different geological types are optimized and the step-shaped excavation efficiency is achieved, the cutting disc speed of different geological types and related data can also be uploaded to the Monte Carlo model unit as the standard rock cutting disc speed.
[0044] The engineer terminal interaction module in the present invention uses Monte Carlo model unit matching to obtain the optimal efficiency of the cutter head speed of different geological types, and determines whether TBM excavation parameter optimization is required based on the optimal efficiency, including:
[0045] The Monte Carlo model unit is connected, and the step excavation efficiency per unit time of the standard rock tunneling cutterhead speed is calculated therefrom; the median of the rock tunneling stage efficiency of different step excavation efficiencies is obtained, which is recorded as the optimal efficiency; the step excavation efficiency of the tunneling cutterhead speed of different geological types is obtained, which is recorded as the real-time rock tunneling efficiency; when the real-time rock tunneling efficiency is weaker than the optimal efficiency, it is determined that the TBM tunneling parameters need to be optimized for the tunneling cutterhead speeds of different geological types; otherwise, it is determined that the TBM tunneling parameters do not need to be optimized for the tunneling cutterhead speeds of different geological types.
[0046] After connecting the Monte Carlo model unit, the stepped excavation efficiency corresponding to the cutterhead speed of different standard rock masses is obtained, and the optimal efficiency is determined based on the distribution characteristics of each stepped excavation efficiency. If the real-time rock excavation efficiency of the cutterhead speed of different geological types is weaker than the optimal efficiency, it can be understood that the overall excavation efficiency of the cutterhead speed of different geological types is lower than the average level, or is not in the optimal state. At this time, TBM excavation parameter optimization is required.
[0047] The speed of the excavation cutterhead of different geological types is consistent with the energy consumption of the standard rock excavation cutterhead speed or the rock structure TBM excavation parameters included are consistent. It is generally believed that the speed of the excavation cutterhead of different geological types is completely consistent with the speed of the standard rock excavation cutterhead, that is, the speed of the different rock excavation cutterheads of a tunnel, and the Monte Carlo model unit can also immediately establish a data service platform for the manufacturer. It should be understood that after obtaining the stepped excavation efficiency of the different standard rock excavation cutterhead speeds, the reasonable median of the rock excavation stage efficiency should be used to determine the optimal efficiency to avoid the influence of extreme values on the rationality of the optimal efficiency.
[0048] When determining that the TBM excavation parameters need to be optimized for the excavation cutter head speeds of different geological types, the present invention application acquires the rock excavation progress data per unit time by collecting the rock excavation distance set at the excavation cutter head speeds of different geological types; and transmits the rock excavation progress data per unit time to the engineer terminal interaction module after screening.
[0049] The screening of the rock excavation process data per unit time mentioned here is mainly to remove abnormal values. The rock excavation process data per unit time includes rock excavation energy consumption data and torque size data. The standard implementation limit is the limit value of the rock structure TBM excavation parameter operation, such as the speed limit value; and the torque size data is the actual parameter of the excavation cutter head speed of different geological types during the implementation process, such as the actual speed value. The torque size data should be within the range of the implementation limit, otherwise it is determined that the rock excavation distance or the rock structure TBM excavation parameter is abnormal, and a timely warning is issued.
[0050] The engineer terminal interaction module in the present invention extracts the TBM excavation parameter mining efficiency corresponding to the TBM excavation parameters of each rock structure from the rock excavation process data per unit time, and obtains a real-time efficiency simulation curve based on the mining efficiency of different TBM excavation parameters, including:
[0051] The torque size data of TBM excavation parameters of each rock structure is extracted from the rock excavation process data per unit time, and the TBM excavation parameter excavation efficiency of each rock structure per unit time is calculated based on the torque size data; the excavation efficiency of different TBM excavation parameters is established as an independent variable according to the rock excavation time, and the real-time efficiency simulation curve is obtained by fitting with the TBM excavation parameter excavation efficiency as the dependent variable.
[0052] The excavation parameters of TBMs with different rock structures are obtained by dividing the speed of the excavation cutter discs of different geological types. The excavation parameters of TBMs with rock structures are preferably TBM excavation parameters with automatically adjustable parameters, so as to realize the automatic optimization of TBM excavation parameters through the engineer terminal interaction module. The excavation efficiency of TBM excavation parameters of each rock structure TBM is calculated through the torque size data, and the excavation parameters are numbered after being sorted from large to small, and then fitted to obtain the real-time efficiency simulation curve. It should be understood that there is a linear or nonlinear relationship between the excavation efficiency of TBM excavation parameters of rock structure TBMs at the same rock excavation cutter disc speed.
[0053] The engineer terminal interactive module in the present invention obtains an ideal efficiency simulation curve based on the rock excavation process data per unit time corresponding to the rock excavation cutter head speed of different standard rock excavation efficiencies when the step-shaped excavation efficiency is achieved, including:
[0054] Based on the stepped excavation efficiency, the standard rock excavation cutter head speed is preferentially screened out from different standard rock excavation cutter head speeds, and the corresponding rock excavation process data per unit time is calibrated as the preset rock excavation process data; the TBM excavation parameter excavation efficiency of the TBM excavation parameters of each rock layer structure is obtained from the preset rock excavation process data, and calibrated as the preset excavation efficiency; the horizontal coordinates of different preset excavation efficiencies are plotted per unit time to obtain the ideal efficiency simulation curve.
[0055] In order to improve the overall excavation efficiency of the cutterhead speed of different geological types, it is necessary to provide data reference for the optimization of TBM excavation parameters, that is, to reasonably select a stepped excavation efficiency from the Monte Carlo model unit (generally better than the real-time rock excavation efficiency of the cutterhead speed of different geological types), and calibrate the corresponding rock excavation process data per unit time to the preset rock excavation process data, so that the ideal efficiency simulation curve can be obtained accordingly.
[0056] It is worth noting that by reasonably selecting the preset rock excavation process data, not only can the implementation efficiency of the TBM excavation parameters of different geological types and rock formation structures be improved, but also the implementation efficiency of the TBM excavation parameters of different geological types and rock formation structures can be reasonably reduced when necessary; this adjustment method is suitable for scenarios where the cutter head speed of different geological types needs to be adjusted at any time.
[0057] The engineer terminal interactive module in the present invention compares the real-time efficiency simulation curve and the ideal efficiency simulation curve, and optimizes the TBM excavation parameters of each rock structure according to the comparison results, including:
[0058] By comparing the real-time efficiency simulation curve and the ideal efficiency simulation curve, the TBM excavation parameters of the rock structure corresponding to the parts where the horizontal and vertical coordinates of the two simulation curves are completely consistent are determined, and calibrated as the TBM excavation parameters to be optimized; the influence of excavation efficiency noise on the TBM excavation parameters to be optimized is determined according to the real-time efficiency simulation curve and the ideal efficiency simulation curve; the torque size data of the TBM excavation parameters to be optimized is adjusted within the rock excavation energy consumption data to reduce the influence of excavation efficiency noise.
[0059] When comparing the real-time efficiency simulation curve and the ideal efficiency simulation curve, first determine which positions do not overlap between the two. The corresponding rock structure TBM excavation parameters can be determined by the numbers of these positions. These rock structure TBM excavation parameters are the TBM excavation parameters to be optimized. The specific degree of adjustment of the TBM excavation parameters to be optimized depends on the noise influence between the two simulation curves.
[0060] like Figure 2 As shown, the second embodiment of the present invention provides a TBM excavation parameter optimization method, comprising:
[0061] Step S100, using the cutter head rotation speeds of various standard rock mass excavation units and the corresponding stepped excavation efficiencies recorded in the Monte Carlo model unit, and obtaining the optimal efficiency based on the median of the rock mass excavation staged efficiencies of different stepped excavation efficiencies;
[0062] Step S200, obtaining the real-time rock excavation efficiency of the excavation cutter head speed of different geological types; comparing the real-time rock excavation efficiency with the optimal efficiency to determine whether to optimize the TBM excavation parameters for the excavation cutter head speed of different geological types; if parameter optimization is required, proceed to the next step; if parameter optimization is not required, continue rock excavation according to the rock excavation distance;
[0063] Step S300, calculate and obtain the TBM excavation parameter excavation efficiency of each rock structure TBM excavation parameter based on the collected rock excavation process data per unit time, and then obtain a real-time efficiency simulation curve; compare the real-time efficiency simulation curve with the ideal efficiency simulation curve to determine and optimize the rock structure TBM excavation parameters.
[0064] The working principle of the present invention is as follows: using the cutter head speeds of various standard rock tunneling records in the Monte Carlo model unit and the corresponding stepped excavation efficiencies, the optimal efficiency is obtained based on the median of the staged efficiency of rock tunneling with different stepped excavation efficiencies. The real-time rock tunneling efficiency of the cutter head speeds of different geological types is obtained; the real-time rock tunneling efficiency and the optimal efficiency are compared to determine whether to optimize the TBM tunneling parameters for the cutter head speeds of different geological types; if parameter optimization is required, proceed to the next step; if parameter optimization is not required, continue rock tunneling according to the rock tunneling distance. The TBM tunneling parameter excavation efficiency of each rock structure TBM tunneling parameter is calculated based on the collected rock tunneling process data per unit time, and then the real-time efficiency simulation curve is obtained; the real-time efficiency simulation curve is compared with the ideal efficiency simulation curve to determine and optimize the rock structure TBM tunneling parameters.
[0065] The above embodiments are only used to illustrate the technical method of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical method of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical method of the present invention.
Claims
1. A TBM excavation parameter optimization system, characterized by: The system includes an engineer terminal interaction module, a rock excavation data acquisition module, an edge computing gateway control module, and a control module for excavation distances of different geological types; The rock tunneling data acquisition module is used to collect the rock tunneling process data per unit time of the TBM tunneling parameters of each rock layer structure during the normal implementation of the tunneling cutter head speed of different geological types through the camera and efficiency sensor set on the tunneling cutter head speed of different geological types, and transmit it to the engineer terminal interaction module; The engineer terminal interaction module is used to calculate the optimal efficiency of the cutter head rotation speed of different geological types using the Monte Carlo model unit, determine the real-time rock excavation efficiency according to the engineering project management information, and compare the optimal efficiency with the real-time rock excavation efficiency to determine whether TBM excavation parameter optimization is required; When it is determined that parameter optimization is needed, the rock excavation progress data per unit time of the TBM excavation parameters of each rock layer structure is collected. When it is determined that parameter optimization is not needed, the rock excavation is continued according to the camera and efficiency sensor. And the excavation efficiency of TBM excavation parameters per unit time of each rock structure is calculated based on the rock excavation process data per unit time; A real-time efficiency simulation curve is drawn for the excavation efficiency of different TBM excavation parameters, and the real-time efficiency simulation curve is compared with the ideal efficiency simulation curve to determine the optimized rock structure TBM excavation parameters; wherein the ideal efficiency simulation curve is calculated using the Monte Carlo model unit; The engineer terminal interaction module compares the real-time efficiency simulation curve with the ideal efficiency simulation curve, determines the rock structure TBM excavation parameters corresponding to the parts of the two simulation curves where the horizontal and vertical coordinates are completely consistent, and calibrates them as the TBM excavation parameters to be optimized; The influence of excavation efficiency noise of the TBM excavation parameters to be optimized is determined according to the real-time efficiency simulation curve and the ideal efficiency simulation curve; and the torque size data of the TBM excavation parameters to be optimized is adjusted within the rock excavation energy consumption data to reduce the influence of excavation efficiency noise.
2. A TBM excavation parameter optimization system according to claim 1, characterized in that: The engineer terminal interaction module is respectively connected to the rock excavation data acquisition module and the edge computing gateway control module; and the edge computing gateway control module includes a cloud server; The rock excavation data acquisition module is in communication connection with the camera and efficiency sensor on the excavation cutter head rotation speed of different geological types; and the camera and efficiency sensor match the different rock excavation stages of TBM excavation parameters of each rock layer structure.
3. A TBM excavation parameter optimization system according to claim 1, characterized in that: The engineer terminal interaction module is connected to the Monte Carlo model unit, and calculates the step-shaped excavation efficiency per unit time of the standard rock tunneling cutter head speed; wherein the tunneling cutter head speeds of different geological types are consistent with the energy consumption of the standard rock tunneling cutter head speed or the rock layer structure TBM excavation parameters included; The median of the rock excavation efficiency at different stages of the step excavation efficiency is obtained, which is recorded as the optimal efficiency; the step excavation efficiency of the excavation cutter head speed of different geological types is obtained, which is recorded as the real-time rock excavation efficiency; wherein the median of the rock excavation efficiency at different stages includes the efficiency affected by human factors or natural environmental factors; When the real-time rock excavation efficiency is weaker than the optimal efficiency, it is determined that the TBM excavation parameters need to be optimized for the excavation cutter head speeds of the different geological types; otherwise, it is determined that the TBM excavation parameters do not need to be optimized for the excavation cutter head speeds of the different geological types.
4. A TBM excavation parameter optimization system according to claim 1, characterized in that: When it is determined that the TBM excavation parameters need to be optimized for the excavation cutter head speeds of the different geological types, the rock excavation process data per unit time is collected and acquired by the camera and efficiency sensor set on the excavation cutter head speeds of the different geological types; and the rock excavation process data per unit time is screened and then transmitted to the engineer terminal interaction module; wherein the rock excavation process data per unit time includes rock excavation energy consumption data and torque size data.
5. A TBM excavation parameter optimization system according to claim 1, characterized in that: The engineer terminal interaction module extracts torque size data of TBM excavation parameters of each rock layer structure from the rock excavation process data per unit time, and uses the torque size data to calculate the excavation efficiency of the TBM excavation parameters of each rock layer structure per unit time.
6. A TBM excavation parameter optimization system according to claim 1, characterized in that: The engineer terminal interaction module compares the real-time efficiency simulation curve with the ideal efficiency simulation curve, and optimizes the TBM excavation parameters of each rock structure according to the comparison result, including: Comparing the real-time efficiency simulation curve with the ideal efficiency simulation curve, determining the rock structure TBM excavation parameters corresponding to the parts of the two simulation curves where the horizontal and vertical coordinates are completely consistent, and calibrating them as the TBM excavation parameters to be optimized; The influence of excavation efficiency noise of the TBM excavation parameters to be optimized is determined according to the real-time efficiency simulation curve and the ideal efficiency simulation curve; and the torque size data of the TBM excavation parameters to be optimized is adjusted within the rock excavation energy consumption data to reduce the influence of excavation efficiency noise.
7. A method for optimizing TBM excavation parameters, characterized in that: include: Using the cutterhead speeds of various standard rock mass excavation records and the corresponding stepped excavation efficiencies recorded in the Monte Carlo model unit, the optimal efficiency is obtained based on the median of the rock mass excavation stage efficiency with different stepped excavation efficiencies; Obtain real-time rock excavation efficiency of the cutterhead speed in different geological types; The real-time rock excavation efficiency and the optimal efficiency are compared to determine whether to optimize the TBM excavation parameters for the cutter head speed of different geological types; if it is determined that parameter optimization is required, the rock excavation process data per unit time of the TBM excavation parameters of each rock layer structure is collected; if it is determined that parameter optimization is not required, the rock excavation is continued according to the camera and efficiency sensor; And the excavation efficiency of TBM excavation parameters per unit time of each rock structure is calculated based on the rock excavation process data per unit time; The TBM excavation parameter excavation efficiency of each rock layer structure is calculated based on the collected rock excavation process data per unit time, and then the real-time efficiency simulation curve is obtained; Compare the real-time efficiency simulation curve with the ideal efficiency simulation curve to determine and optimize the TBM excavation parameters for rock structures; Comparing the real-time efficiency simulation curve with the ideal efficiency simulation curve, determining the rock structure TBM excavation parameters corresponding to the parts of the two simulation curves where the horizontal and vertical coordinates are completely consistent, and calibrating them as the TBM excavation parameters to be optimized; The influence of excavation efficiency noise of the TBM excavation parameters to be optimized is determined according to the real-time efficiency simulation curve and the ideal efficiency simulation curve; and the torque size data of the TBM excavation parameters to be optimized is adjusted within the rock excavation energy consumption data to reduce the influence of excavation efficiency noise.