Intelligent construction method, system, equipment and medium for modular integrated building
By using BIM models and inspection robots to collect data in real time in modular integrated building construction, dynamically adjusting construction plans and personnel scheduling, the problem of relying on manual experience in construction is solved, construction efficiency and safety are improved, and modern intelligent construction is realized need.
Patent Information
- Application Number
- CN202410523063.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-28
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2044-04-28
AI Technical Summary
The existing modular integrated building construction process relies on manual experience, lack of dynamic monitoring and reasonable construction plan formulation, resulting in poor construction efficiency and quality and inability to meet the requirements of modern intelligent construction.
By establishing a BIM model of the construction site, determining the inspection route and construction plan of the inspection robot, collecting construction images and environmental parameters in real time, performing feature extraction and error evaluation, optimizing construction strategies, dynamically adjusting construction plans and personnel scheduling, and improving construction efficiency and security.
Real-time monitoring and optimization of the construction process is achieved, construction efficiency and safety are improved, energy efficiency of construction projects is enhanced, construction errors are corrected in a timely manner, and construction risks are reduced.
Smart Images

Figure CN118350593B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of intelligent construction technology, and in particular to an intelligent construction method, system, equipment and medium for modular integrated buildings. Background Art
[0002] Modular integrated construction is a modern construction technology that breaks down buildings into modular "units". These units complete the construction processes such as structure, decoration, water and electricity, equipment pipelines, and sanitary facilities in the factory, and are quickly assembled into the whole building through reliable connection technology at the construction site. This technology moves the building from the construction site into the factory, greatly shortens the construction period, and reduces the difficulty of construction. It is a green construction method with a high degree of building industrialization.
[0003] At present, modular integrated buildings mainly rely on manual experience to carry out construction work during the construction process. For example, the basic plan is determined in the early project planning, including personnel allocation, construction process, etc. When an abnormality occurs during the construction process, an alarm is usually triggered, and improvement measures based on historical experience are combined to intervene in emergency problems, thereby reducing construction risks. However, this method of relying on manual experience still has many shortcomings: for example, there is a lack of dynamic monitoring of the construction process and progress, and manual intervention is only carried out when an abnormality occurs, which has a large lag. In addition, the rationality of relying solely on manual experience to formulate construction plans and personnel scheduling plans also needs to be considered. Therefore, the current construction process for modular integrated buildings cannot meet the requirements of modern intelligent construction, and the construction effect is not ideal. Summary of the invention
[0004] In order to solve at least one of the technical problems mentioned above, the present invention provides an intelligent construction method, system, equipment and medium for modular integrated buildings.
[0005] In a first aspect, the present invention provides an intelligent construction method for a modular integrated building, the method comprising:
[0006] Establish a BIM model of the construction site based on the basic data of the construction site, and determine the construction plan and the inspection route of the inspection robot based on the BIM model;
[0007] Control the inspection robot to perform inspection tasks, with one inspection route as one cycle, and receive the construction images and environmental parameters of different construction areas collected by the inspection robot in real time;
[0008] Extract features from construction images, determine the construction errors of each construction area based on the extracted features, and evaluate the corresponding error levels. Re-rank the priorities of construction areas in the next inspection cycle according to the error levels to update the inspection routes.
[0009] The construction images and environmental parameters are input into the preset construction detection model, the construction optimization strategy is generated, and the construction plan is updated using the construction optimization strategy.
[0010] Preferably, after extracting features from the construction image, the method further includes:
[0011] Determine the actual construction progress of each construction area based on the extracted features, and calculate the time difference between the actual construction progress and the target construction progress planned in the construction plan;
[0012] When the time difference is greater than the preset threshold and the actual construction progress is faster than the target construction progress, the corresponding construction area is marked as a key construction quality focus area;
[0013] When the time difference is greater than the preset threshold and the actual construction progress is slower than the target construction progress, the corresponding construction area is marked as a key construction progress focus area;
[0014] Update inspection tasks according to construction quality focus areas and construction progress focus areas;
[0015] Among them, the inspection duration, inspection frequency and number of construction images collected by the inspection robots in the key construction quality areas or construction progress areas are greater than those in other construction areas.
[0016] Preferably, after marking the corresponding construction area as a construction progress focus area, the method further includes:
[0017] Obtaining the personnel allocation and personnel operation status in the key focus areas of the construction progress; the personnel allocation status includes the number of personnel, personnel qualifications and personnel physical conditions; the personnel operation status includes the number of times leaving the construction site within a preset time and the construction efficiency;
[0018] Determine the factors affecting the construction progress;
[0019] When the influencing factor is determined to be a personnel allocation problem, update the personnel allocation plan for the key areas of the construction progress;
[0020] When it is determined that the influencing factor is a personnel operation problem, the corresponding construction personnel will be notified and reminded.
[0021] Preferably, the updating of the personnel allocation plan for the key areas of the construction progress includes:
[0022] Obtaining basic scheduling data, including the actual current construction progress and personnel allocation plan of the key construction progress area, the target construction progress, and information on the dispatchable personnel in other construction areas;
[0023] The basic scheduling data is input into a preset scheduling analysis model to generate a personnel scheduling strategy, and the personnel scheduling strategy is used to update the current personnel allocation plan for the construction.
[0024] Preferably, determining the information of dispatchable personnel in other construction areas includes:
[0025] Calculate the correlation index f between the key construction progress area and other construction areas:
[0026]
[0027] Where, X 0 Indicates the key areas of construction progress, X i Indicates other construction areas, N(X 0 ∩X i ) represents the number of elements contained in the intersection of the construction progress focus area and other construction areas; N(X 0 ∪X i ) indicates the number of elements included in the construction data information of the construction progress focus area and other construction areas;
[0028] The priority of dispatching personnel in other construction areas is sorted according to the size of the correlation index.
[0029] Preferably, after extracting features from the construction image, the method further includes:
[0030] Identify construction behaviors that do not meet the preset conditions, synchronously feed back the corresponding construction behavior data to the monitoring platform, and trigger an alarm prompt; among them, construction behaviors that do not meet the preset conditions include construction size parameters or material parameters that do not meet the operating standards, not wearing a safety helmet, and not wearing protective clothing.
[0031] Preferably, after determining the construction error of each construction area according to the extracted features, the method further comprises:
[0032] Conduct simulation based on construction errors and visualize the simulation results on the monitoring platform;
[0033] The risk level caused by construction errors is evaluated based on the simulation results, and different degrees of alarm prompts are matched according to different risk levels to provide risk warnings for different construction areas.
[0034] In a second aspect, the present invention further provides an intelligent construction system for modular integrated buildings, the system comprising:
[0035] A BIM model building unit is used to build a BIM model of the construction site based on the basic data of the construction site, and determine the construction plan and the inspection route of the inspection robot based on the BIM model;
[0036] The data acquisition unit is used to control the inspection robot to perform inspection tasks, with one inspection route completed as one cycle, and to receive the construction images and environmental parameters of different construction areas collected by the inspection robot in real time;
[0037] The inspection route updating unit is used to extract features from the construction image, determine the construction error of each construction area according to the extracted features, evaluate the corresponding error level, and re-order the priority of the construction area in the next inspection cycle according to the error level to update the inspection route;
[0038] The construction plan updating unit is used to input the construction image and environmental parameters into a preset construction detection model, generate a construction optimization strategy, and use the construction optimization strategy to update the construction plan.
[0039] In a third aspect, the present invention further provides an electronic device comprising: a processor and a memory, wherein the memory is used to store computer program code, and the computer program code comprises computer instructions. When the processor executes the computer instructions, the electronic device executes the intelligent construction method of modular integrated buildings as described in the first aspect and any one of the preferred embodiments thereof.
[0040] In a fourth aspect, the present invention further provides a computer-readable storage medium, wherein a computer program is stored in the computer-readable storage medium, wherein the computer program includes program instructions, and when the program instructions are executed by a processor of an electronic device, the processor executes the intelligent construction method for modular integrated buildings as described in the first aspect and any preferred embodiment thereof.
[0041] Compared with the prior art, the present invention has the following beneficial effects:
[0042] The present invention provides an intelligent construction method for modular integrated buildings, including establishing a BIM model of a construction site according to basic data of the construction site, and determining a construction plan and an inspection route of an inspection robot according to the BIM model. By establishing a BIM model, the initial construction plan and inspection route can be reasonably planned. Then, the inspection robot is controlled to perform the inspection task, with the completion of one inspection route as one cycle, and the construction images and environmental parameters of different construction areas collected by the inspection robot are received in real time; then, feature extraction is performed on the construction image, the construction error of each construction area is determined according to the extracted features, and the corresponding error level is evaluated, and the priority of the construction area in the next inspection cycle is reordered according to the size of the error level to update the inspection route; by analyzing the error levels of different construction areas, the priority order of the next inspection route can be changed in time, that is, the area with a high error level can be inspected first, so that the construction error situation can be intervened and corrected in time, which is conducive to the stable development of construction operations. In addition, the present invention also inputs the acquired construction images and environmental parameters into a preset construction detection model, generates a construction optimization strategy, and uses the construction optimization strategy to update the construction plan. By considering environmental factors and real-time construction status on site, combined with the construction detection model, the initial construction plan can be quickly optimized, thereby adjusting and carrying out construction work in a more scientific and reasonable manner, which is conducive to speeding up the progress of construction work and improving the safety of the construction process, greatly enhancing the energy efficiency of the construction project.
[0043] It is to be understood that both the foregoing general description and the following detailed description are exemplary and explanatory only and are not restrictive of the present disclosure. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the background technology, the drawings required for use in the embodiments of the present invention or the background technology will be described below.
[0045] The drawings herein are incorporated into the specification and constitute a part of the specification. These drawings illustrate embodiments consistent with the present disclosure and are used to illustrate the technical solutions of the present disclosure together with the specification.
[0046] Figure 1 A schematic diagram of a flow chart of an intelligent construction method for a modular integrated building provided by an embodiment of the present invention;
[0047] Figure 2 A schematic structural diagram of an intelligent construction system for a modular integrated building provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0048] In order to enable those skilled in the art to better understand the scheme of the present invention, the technical scheme in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0049] The terms "first", "second", etc. in the specification and claims of the present invention and the above-mentioned drawings are used to distinguish different objects, rather than to describe a specific order. In addition, the terms "including" and "having" and any variations thereof are intended to cover non-exclusive inclusions. For example, a process, method, system, product or device that includes a series of steps or units is not limited to the listed steps or units, but may optionally include steps or units that are not listed, or may optionally include other steps or units that are inherent to these processes, methods, products or devices.
[0050] The term "and / or" herein is only a description of the association relationship of the associated objects, indicating that there may be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the term "at least one" herein represents any combination of at least two of any one or more of a plurality of. For example, including at least one of A, B, and C can represent including any one or more elements selected from the set consisting of A, B, and C.
[0051] Reference to "embodiments" herein means that a particular feature, structure, or characteristic described in conjunction with the embodiments may be included in at least one embodiment of the present invention. The appearance of the phrase in various places in the specification does not necessarily refer to the same embodiment, nor is it an independent or alternative embodiment that is mutually exclusive with other embodiments. It is explicitly and implicitly understood by those skilled in the art that the embodiments described herein may be combined with other embodiments.
[0052] In addition, in order to better illustrate the present invention, numerous specific details are provided in the following specific embodiments. It should be understood by those skilled in the art that the present invention can be implemented without certain specific details. In some examples, methods, means, components and circuits well known to those skilled in the art are not described in detail in order to highlight the subject matter of the present invention.
[0053] During the construction process of current modular integrated buildings, construction plans are mainly planned based on manual experience, and their construction efficiency and effect are not ideal. To this end, the present invention provides an intelligent construction method for modular integrated buildings, which can update inspection routes and construction plans according to construction images and environmental parameters, thereby improving construction safety while ensuring construction progress and quality.
[0054] See also Figure 1 , Figure 1 The following is a flow chart of an intelligent construction method for a modular integrated building provided by an embodiment of the present invention. Figure 1 As shown, a smart construction method for modular integrated buildings includes the following steps:
[0055] S10. Establish a BIM model of the construction site based on the basic data of the construction site, and determine the construction plan and the inspection route of the inspection robot based on the BIM model;
[0056] BIM model, or building information model, is a three-dimensional digital model that integrates all relevant information of a construction project. It contains the building's geometric shape, geographic coordinates, spatial relationships, attribute information, and non-geometric information, such as cost, time, manufacturing, and construction methods. In this embodiment, by establishing a BIM model of the construction site, the initial construction plan and the inspection route of the inspection robot can be reasonably planned based on the model.
[0057] In a preferred embodiment, constructing a BIM model may include:
[0058] 1) Collect the scope, shape and terrain characteristics of the construction site, plan the flight route and coverage area of the remote sensing equipment, and obtain remote sensing planning data;
[0059] 2) Use remote sensing equipment to perform high-precision three-dimensional scanning of the construction site based on remote sensing planning data to obtain image data, then perform feature point correction and matching on the image data, and obtain stereoscopic image stitching data through multi-view integration and stitching;
[0060] 3) Perform three-dimensional reconstruction on the stereo image stitching data to obtain a three-dimensional BIM model.
[0061] S20, controlling the inspection robot to perform the inspection task, taking the completion of one inspection route as one cycle, and receiving in real time the construction images and environmental parameters of different construction areas collected by the inspection robot.
[0062] After the inspection route is generated, it will be imported into the inspection robot, and the inspection robot will be controlled to perform the inspection task along the route. In the first designed inspection route, the inspection order is usually set according to the location relationship of the construction area. For example, there are 5 construction areas, and these 5 construction areas need to be covered at the same time in one inspection cycle. First, multiple inspection routes are generated by traversing these 5 construction areas, and then the distance between the two areas is calculated. Finally, the route with the shortest sum of all distances is used as the inspection route and imported into the inspection robot.
[0063] During the inspection process, the inspection robot will inspect the construction area in turn according to the inspection route, including collecting environmental parameters and construction images of the corresponding construction area. The environmental parameters are mainly collected by sensors installed in the inspection robot, such as wind speed sensors, temperature and humidity sensors, etc. The construction image is obtained by the inspection robot through the camera in the construction area it inspects.
[0064] It is understandable that sensors can usually be installed at the construction site, but due to the large scope of the construction site, if the environmental parameters of each construction area are to be accurately measured, it is usually necessary to set up corresponding sensors in each construction area, which will increase the cost. In addition, since the fluctuation of environmental parameters within a patrol cycle is usually small, there is no need to install sensors on site for real-time monitoring. In summary, this embodiment gives priority to setting sensors on the patrol robot, so that environmental parameters can be accurately and timely collected when passing through each construction area, which can reduce the equipment cost of the construction site.
[0065] When shooting construction images, it is usually necessary to shoot from various angles to cover every part of the construction site as much as possible, so as to extract status information such as the stacking and quantity of construction materials, the appearance of the building construction, and the progress from the images. Preferably, dynamic videos can also be shot by patrolling around the construction area to better extract construction information.
[0066] S30, extracting features from the construction image, determining the construction error of each construction area based on the extracted features, and evaluating the corresponding error level, re-ranking the priority of the construction areas in the next inspection cycle according to the error level, so as to update the inspection route.
[0067] Before feature extraction, the acquired image usually needs to be preprocessed, including image correction, dedistortion, noise reduction, image enhancement, etc., in order to improve the image quality.
[0068] Specifically, when extracting image features, we mainly focus on the image's texture features, contour features, including edges and corners, and color features. We match the extracted features with known construction standards or templates, and combine them with actual construction conditions to determine construction errors, including but not limited to size deviation, position offset, angle deviation, etc. The size of the error is used as an indicator to measure construction quality.
[0069] In some embodiments, the model used to extract image features is mainly a neural network model. For example, any one of a convolutional neural network, a recurrent neural network, a deep residual network, a generative adversarial network, and a Transformer model can be used to train a construction image recognition model. The model can extract features from construction images to identify construction data and further determine construction error data.
[0070] Furthermore, after obtaining the construction error, it is necessary to evaluate the corresponding error level, and then re-order the priority of the construction area in the next inspection cycle according to the error level to update the inspection route. Construction errors will affect the subsequent construction quality and progress, and are crucial to construction safety. Therefore, this embodiment will mark the construction area in combination with the error level to optimize the inspection route for the next cycle.
[0071] For example, among the five construction areas, the error levels of areas A, B, and C decrease in sequence. In the initial inspection route, the inspection robot will inspect areas B, C, and A in sequence according to the principle of the shortest route. However, after the error levels are ranked, since area A has the highest error level and the greatest safety hazard, it should first be inspected in the next inspection cycle to monitor the construction status and quality in a timely manner, so that timely intervention can be made when abnormalities occur, reducing the probability of dangerous consequences due to untimely inspections.
[0072] S40: Input the construction image and environmental parameters into a preset construction detection model, generate a construction optimization strategy, and use the construction optimization strategy to update the construction plan.
[0073] Optimizing inspection routes is to conduct hierarchical monitoring of areas with different construction levels, and the construction plan is the main factor affecting the entire construction process. Therefore, in this embodiment, after obtaining the construction image and environmental parameters, they will be input into the preset construction detection model to quickly generate a construction optimization strategy, and then use the construction optimization strategy to update the initial construction plan, so as to improve the energy efficiency of the construction operation.
[0074] It should be noted that the construction detection model of this embodiment also needs to be obtained based on neural network training, including but not limited to convolutional neural network, random forest algorithm, recurrent neural network, SVM algorithm, etc. When training the model, a large number of data samples in the historical construction process, including construction images, environmental parameters and construction strategies, are obtained, and the basic network is trained with construction images and environmental parameters as inputs and construction strategies as outputs, and the construction detection model is obtained when the training accuracy meets the preset value. The reason why environmental parameters are considered is that in some special environments, the construction quality will have a greater impact. For example, compared with a sunny day of more than 20 degrees, the probability of construction errors in stormy and snowy weather is greater, and the level of construction errors is also likely to be higher. Preferably, as the construction data increases, the model can also be allowed to self-learn to achieve the process of adaptively optimizing network parameters to improve the accuracy and generalization ability of the model.
[0075] In summary, this embodiment can timely change the priority order of the next inspection route by analyzing the error levels of different construction areas, that is, the areas with high error levels can be inspected first, so that the construction error situation can be intervened and corrected in time, which is conducive to the stable development of construction operations. In addition, the present invention also inputs the acquired construction images and environmental parameters into a preset construction detection model, generates a construction optimization strategy, and uses the construction optimization strategy to update the construction plan. By considering environmental factors and the real-time construction status on site, combined with the construction detection model, the initial construction plan can be quickly optimized, so as to adjust and carry out construction operations more scientifically and reasonably, which is conducive to speeding up the progress of construction operations and improving the safety of the construction process, and greatly enhancing the energy efficiency of the construction project.
[0076] In some embodiments, after extracting features from the construction image, the method further includes:
[0077] 3.1) Determine the actual construction progress of each construction area based on the extracted features, and calculate the time difference between the actual construction progress and the target construction progress planned in the construction plan;
[0078] 3.2) When the time difference is greater than the preset threshold and the actual construction progress is faster than the target construction progress, the corresponding construction area is marked as a key construction quality focus area;
[0079] 3.3) When the time difference is greater than the preset threshold and the actual construction progress is slower than the target construction progress, the corresponding construction area is marked as a key construction progress focus area;
[0080] 3.4) Update inspection tasks according to construction quality focus areas and construction progress focus areas;
[0081] Among them, the inspection duration, inspection frequency and number of construction images collected by the inspection robots in the key construction quality areas or construction progress areas are greater than those in other construction areas.
[0082] It is understandable that the construction progress is also very important for the entire construction process. When planning the construction plan in the early stage of the construction project, the allocation of personnel and the development of the construction task process are all to ensure that the construction progress is close to the ideal value. In this embodiment, the actual construction progress will be calculated based on the extracted image features. For example, the stacking of construction materials at the construction site and the structure of the completed construction building can be extracted to judge the construction progress. After obtaining the actual construction progress, the time difference between the actual construction progress and the target construction progress planned in the construction plan is calculated. If the difference between the two is large and greater than a preset threshold, it proves that there may be problems in the construction process.
[0083] Specifically, if the actual construction progress is much faster than the target construction progress, the possible reason is that the construction personnel cut corners in the construction process and ignored the construction quality issues in order to reduce the work tasks and improve efficiency. In this case, the construction area needs to be marked as a key area for construction quality. In the next inspection cycle, the inspection time, inspection frequency and number of construction images collected in this area will be increased compared to other areas. If the actual construction progress is slower than the target construction progress for a long period of time, there may be serious problems with the construction efficiency of this area. In this case, the area is marked as a key area for construction progress. In the next inspection process, the inspection time, inspection frequency and number of construction images collected also need to be increased.
[0084] This embodiment analyzes the construction progress to determine possible abnormal situations under different construction progresses, and marks them respectively, so that the updated inspection tasks are more targeted.
[0085] In some embodiments, after marking the corresponding construction area as a construction progress focus area, the process further includes:
[0086] Obtaining the personnel allocation and personnel operation status in the key focus areas of the construction progress; the personnel allocation status includes the number of personnel, personnel qualifications and personnel physical conditions; the personnel operation status includes the number of times leaving the construction site within a preset time and the construction efficiency;
[0087] Determine the factors affecting the construction progress;
[0088] When the influencing factor is determined to be a personnel allocation problem, update the personnel allocation plan for the key areas of the construction progress;
[0089] When it is determined that the influencing factor is a personnel operation problem, the corresponding construction personnel will be notified and reminded.
[0090] Since there are more than one reason that affects the construction progress, it may be unreasonable personnel allocation or personnel's own laziness. This embodiment aims to analyze different reasons and formulate targeted strategies to ensure the rationality of the construction progress.
[0091] Specifically, when it is determined that the influencing factor is a personnel allocation problem, it is necessary to update the personnel allocation plan for the key construction progress area to ensure that the construction progress in this area can catch up. When it is determined that the influencing factor is a personnel operation problem, the corresponding construction personnel will be notified and prompted, and the current personnel's physical status will be paid attention to to confirm whether to dispatch the personnel, such as arranging easier work, or giving the personnel a holiday to rest and stop working.
[0092] In one embodiment, the updating of the personnel allocation plan for the key areas of the construction progress includes:
[0093] Obtaining basic scheduling data, including the actual current construction progress and personnel allocation plan of the key construction progress area, the target construction progress, and information on the dispatchable personnel in other construction areas;
[0094] The basic scheduling data is input into a preset scheduling analysis model to generate a personnel scheduling strategy, and the personnel scheduling strategy is used to update the current personnel allocation plan for the construction.
[0095] Preferably, determining the information of dispatchable personnel in other construction areas includes:
[0096] Calculate the correlation index f between the key construction progress area and other construction areas:
[0097]
[0098] Where, X 0 Indicates the key areas of construction progress, X i Indicates other construction areas, N(X 0 ∩X i ) represents the number of elements contained in the intersection of the construction progress focus area and other construction areas; N(X 0 ∪X i ) indicates the number of elements included in the construction data information of the construction progress focus area and other construction areas;
[0099] The priority of dispatching personnel in other construction areas is sorted according to the size of the correlation index.
[0100] Because when dispatching personnel, the types of construction work of personnel in different construction areas vary greatly, and they are different in complexity and professionalism. For example, the qualifications of transport workers and workers who splice modules are different, and the integrated modules of splicing buildings require more professional technical workers to complete. Therefore, in order to achieve reasonable scheduling, while ensuring the construction progress, the completion of the construction work is considered. When determining the information of the dispatchable personnel, this embodiment considers the correlation between other construction areas and the areas of focus of the construction progress. This correlation can be obtained from the construction data information. For example, if there are many types of building materials and many types of construction work in two areas, then it is considered that the two are parallel construction areas with strong correlation. At this time, the dispatch will give priority to dispatching personnel from other construction areas with high correlation. When the area with the greatest correlation cannot provide dispatching personnel, it will be dispatched from the area with the second highest correlation strength until the personnel dispatch is completed. In this way, reasonable resource allocation and personnel dispatch can be guaranteed, and while ensuring the improvement of construction progress, the construction quality is also taken into account.
[0101] In some embodiments, if it is a problem with the personnel's own work, then the personnel's vital sign data can be obtained at this time. This data can be detected by wearing smart helmets, smart protective clothing and other smart wearable devices. After the vital sign data is obtained, it will be compared with the standard vital sign data to determine whether the person has physical abnormalities; if so, the person will be dispatched, such as letting him rest and recover, or sent to the hospital for treatment. If the overall situation is normal, it is due to the laziness of the personnel themselves that the construction progress is delayed, then the personnel will be criticized and criticized, and as a key focus, if it is found that there are multiple absences, they may be dismissed or fined.
[0102] In summary, after obtaining the construction progress information, this embodiment analyzes the main reasons affecting the construction progress and provides different response strategies for different reasons. It can improve the construction progress while taking into account the construction quality, thereby greatly improving the energy efficiency of the construction project.
[0103] In some embodiments, after extracting features from the construction image, the method further includes:
[0104] Identify construction behaviors that do not meet the preset conditions, synchronously feed back the corresponding construction behavior data to the monitoring platform, and trigger an alarm prompt; among them, construction behaviors that do not meet the preset conditions include construction size parameters or material parameters that do not meet the operating standards, not wearing a safety helmet, and not wearing protective clothing.
[0105] By monitoring unqualified and dangerous behaviors during the construction process, construction workers can be reminded to correct their behaviors in a timely manner, thereby improving construction safety.
[0106] In some embodiments, after determining the construction error of each construction area according to the extracted features, the method further includes:
[0107] Conduct simulation based on construction errors and visualize the simulation results on the monitoring platform;
[0108] The risk level caused by construction errors is evaluated based on the simulation results, and different degrees of alarm prompts are matched according to different risk levels to provide risk warnings for different construction areas.
[0109] By simulating and extrapolating construction errors, we can evaluate the risk levels brought about by different construction errors, thereby providing more targeted alarm prompts and improving construction safety.
[0110] See also Figure 2 In some embodiments, the present invention further provides an intelligent construction system for modular integrated buildings, the system comprising:
[0111] The BIM model building unit 100 is used to build a BIM model of the construction site according to the basic data of the construction site, and determine the construction plan and the inspection route of the inspection robot according to the BIM model;
[0112] The data acquisition unit 200 is used to control the inspection robot to perform the inspection task, with one inspection route completed as one cycle, and to receive the construction images and environmental parameters of different construction areas collected by the inspection robot in real time;
[0113] The inspection route updating unit 300 is used to extract features from the construction image, determine the construction error of each construction area according to the extracted features, evaluate the corresponding error level, and re-order the priority of the construction area in the next inspection cycle according to the error level to update the inspection route;
[0114] The construction plan updating unit 400 is used to input the construction image and environmental parameters into a preset construction detection model, generate a construction optimization strategy, and update the construction plan using the construction optimization strategy.
[0115] It can be understood that the functions or modules included in the system provided in this embodiment can be used to execute the method described in the above method embodiment. Its specific implementation can refer to the description of the above method embodiment. For the sake of brevity, it will not be repeated here.
[0116] The present invention also provides an electronic device, including a processor and a memory, wherein the memory is used to store computer program code, and the computer program code includes computer instructions. When the processor executes the computer instructions, the electronic device executes the intelligent construction method of modular integrated buildings as described in any one of the above embodiments.
[0117] The present invention also provides a computer-readable storage medium, in which a computer program is stored. The computer program includes program instructions. When the program instructions are executed by a processor of an electronic device, the processor executes the intelligent construction method of a modular integrated building as described in any one of the above embodiments.
[0118] Those skilled in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of the present invention.
[0119] Those skilled in the art can clearly understand that, for the convenience and brevity of description, the specific working processes of the systems, devices and units described above can refer to the corresponding processes in the aforementioned method embodiments, and will not be repeated here. Those skilled in the art can also clearly understand that the descriptions of the various embodiments of the present invention have different focuses. For the convenience and brevity of description, the same or similar parts may not be repeated in different embodiments. Therefore, for parts not described or not described in detail in a certain embodiment, refer to the records of other embodiments.
[0120] In the several embodiments provided by the present invention, it should be understood that the disclosed systems, devices and methods can be implemented in other ways. For example, the device embodiments described above are only schematic. For example, the division of the units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.
[0121] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.
[0122] In addition, each functional unit in each embodiment of the present invention may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit.
[0123] In the above embodiments, it can be implemented in whole or in part by software, hardware, firmware or any combination thereof. When implemented by software, it can be implemented in whole or in part in the form of a computer program product. The computer program product includes one or more computer instructions. When the computer program instructions are loaded and executed on a computer, the process or function described in the embodiment of the present invention is generated in whole or in part. The computer can be a general-purpose computer, a special-purpose computer, a computer network, or other programmable device. The computer instructions can be stored in a computer-readable storage medium or transmitted through the computer-readable storage medium. The computer instructions can be transmitted from a website site, computer, server or data center to another website site, computer, server or data center by wired (e.g., coaxial cable, optical fiber, digital subscriber line (digital subscriber line, DSL)) or wireless (e.g., infrared, wireless, microwave, etc.) mode. The computer-readable storage medium can be any available medium that can be accessed by a computer or a data storage device such as a server or data center that includes one or more available media integrated. The available medium may be a magnetic medium (eg, a floppy disk, a hard disk, a magnetic tape), an optical medium (eg, a digital versatile disc (DVD)), or a semiconductor medium (eg, a solid state disk (SSD)).
[0124] A person skilled in the art can understand that to implement all or part of the processes in the above-mentioned embodiments, the processes can be completed by a computer program to instruct the relevant hardware, and the program can be stored in a computer-readable storage medium. When the program is executed, it can include the processes of the above-mentioned method embodiments. The aforementioned storage medium includes: a read-only memory (ROM) or a random access memory (RAM), a magnetic disk or an optical disk, and other media that can store program codes.
Claims
1. An intelligent construction method for modular integrated buildings, characterized in that: The method comprises: A BIM model of the construction site is established based on the basic data of the construction site. The construction plan and the inspection route of the inspection robot are determined based on the BIM model. Multiple inspection routes are generated by traversing all construction areas, and then the distance between two areas is calculated. Finally, the route with the shortest sum of all distances is used as the initial inspection route. Control the inspection robot to perform inspection tasks, with one inspection route as one cycle, and receive the construction images and environmental parameters of different construction areas collected by the inspection robot in real time; Extract features from construction images, determine the construction errors of each construction area based on the extracted features, evaluate the corresponding error levels, and re-rank the priorities of construction areas in the next inspection cycle from large to small according to the error levels to update the inspection routes; After extracting features from the construction image, the method further includes: Determine the actual construction progress of each construction area based on the extracted features, and calculate the time difference between the actual construction progress and the target construction progress planned in the construction plan; When the time difference is greater than the preset threshold and the actual construction progress is faster than the target construction progress, the corresponding construction area is marked as a key construction quality focus area; When the time difference is greater than the preset threshold and the actual construction progress is slower than the target construction progress, the corresponding construction area is marked as a key construction progress focus area; Update inspection tasks according to construction quality focus areas and construction progress focus areas; Among them, the inspection duration, inspection frequency and number of construction images collected by the inspection robot in the key construction quality areas or the key construction progress areas are greater than those in other construction areas; After marking the corresponding construction area as a construction progress focus area, the method further includes: Obtaining the personnel allocation and personnel operation status in the key focus areas of the construction progress; the personnel allocation status includes the number of personnel, personnel qualifications and personnel physical conditions; the personnel operation status includes the number of times leaving the construction site within a preset time and the construction efficiency; Determine the factors affecting the construction progress; When the influencing factor is determined to be a personnel allocation problem, update the personnel allocation plan for the key areas of the construction progress; When it is determined that the influencing factor is a personnel operation problem, the corresponding construction personnel will be notified and reminded; The updated construction schedule focuses on the staffing allocation plan for the area, including: Obtaining basic scheduling data, including the actual current construction progress and personnel allocation plan of the key construction progress area, the target construction progress, and information on the dispatchable personnel in other construction areas; Input the basic scheduling data into a preset scheduling analysis model to generate a personnel scheduling strategy, and use the personnel scheduling strategy to update the current personnel allocation plan for the construction; Determine the information of the dispatchable personnel in the other construction areas, including: Calculate the correlation index between the construction progress focus area and other construction areas : In the formula, Indicates the key areas of construction progress. Indicates other construction areas. It indicates the number of elements contained in the intersection of the construction data information of the key focus area of the construction progress and other construction areas; Indicates the construction progress focus area and the number of elements included in the construction data information of other construction areas; The priorities for dispatching personnel from other construction areas are sorted according to the correlation index from large to small. Personnel are dispatched from the construction area with the largest correlation first. When the area with the largest correlation cannot provide dispatched personnel, dispatch from the area with the second largest correlation strength until the personnel dispatch is completed; The construction images and environmental parameters are input into the preset construction detection model to generate the construction optimization strategy, and the construction plan is updated using the construction optimization strategy.
2. The intelligent construction method of modular integrated building according to claim 1, characterized in that: After extracting features from the construction image, the method further includes: Identify construction behaviors that do not meet the preset conditions, synchronously feed back the corresponding construction behavior data to the monitoring platform, and trigger an alarm prompt; among them, construction behaviors that do not meet the preset conditions include construction size parameters or material parameters that do not meet the operating standards, not wearing a safety helmet, and not wearing protective clothing.
3. The intelligent construction method of modular integrated building according to claim 1, characterized in that: After determining the construction error of each construction area according to the extracted features, the method further includes: Conduct simulation based on construction errors and visualize the simulation results on the monitoring platform; The risk level caused by construction errors is evaluated based on the simulation results, and different degrees of alarm prompts are matched according to different risk levels to provide risk warnings for different construction areas.
4. An intelligent construction system for modular integrated buildings, characterized in that: The system comprises: A BIM model building unit is used to build a BIM model of the construction site based on the basic data of the construction site, and determine the construction plan and the inspection route of the inspection robot based on the BIM model. Multiple inspection routes are generated by traversing all construction areas, and then the distance between two areas is calculated. Finally, the route with the shortest sum of all distances is used as the initial inspection route; The data acquisition unit is used to control the inspection robot to perform inspection tasks, with one inspection route completed as one cycle, and to receive the construction images and environmental parameters of different construction areas collected by the inspection robot in real time; The inspection route updating unit is used to extract features from the construction image, determine the construction error of each construction area according to the extracted features, evaluate the corresponding error level, and re-order the priority of the construction areas in the next inspection cycle according to the error level from large to small, so as to update the inspection route; After extracting features from the construction image, the method further includes: Determine the actual construction progress of each construction area based on the extracted features, and calculate the time difference between the actual construction progress and the target construction progress planned in the construction plan; When the time difference is greater than the preset threshold and the actual construction progress is faster than the target construction progress, the corresponding construction area is marked as a key construction quality focus area; When the time difference is greater than the preset threshold and the actual construction progress is slower than the target construction progress, the corresponding construction area is marked as a key construction progress focus area; Update inspection tasks according to construction quality focus areas and construction progress focus areas; Among them, the inspection duration, inspection frequency and number of construction images collected by the inspection robot in the key construction quality areas or the key construction progress areas are greater than those in other construction areas; After marking the corresponding construction area as a construction progress focus area, the method further includes: Obtaining the personnel allocation and personnel operation status in the key focus areas of the construction progress; the personnel allocation status includes the number of personnel, personnel qualifications and personnel physical conditions; the personnel operation status includes the number of times leaving the construction site within a preset time and the construction efficiency; Determine the factors affecting the construction progress; When the influencing factor is determined to be a personnel allocation problem, update the personnel allocation plan for the key areas of the construction progress; When it is determined that the influencing factor is a personnel operation problem, the corresponding construction personnel will be notified and reminded; The updated construction schedule focuses on the staffing allocation plan for the area, including: Obtaining basic scheduling data, including the actual current construction progress and personnel allocation plan of the key construction progress area, the target construction progress, and information on the dispatchable personnel in other construction areas; Input the basic scheduling data into a preset scheduling analysis model to generate a personnel scheduling strategy, and use the personnel scheduling strategy to update the current personnel allocation plan for the construction; Determine the information of the dispatchable personnel in the other construction areas, including: Calculate the correlation index between the construction progress focus area and other construction areas : In the formula, Indicates the key areas of construction progress. Indicates other construction areas. It indicates the number of elements contained in the intersection of the construction data information of the key focus area of the construction progress and other construction areas; Indicates the construction progress focus area and the number of elements included in the construction data information of other construction areas; The priorities for dispatching personnel from other construction areas are sorted according to the correlation index from large to small. Personnel are dispatched from the construction area with the largest correlation first. When the area with the largest correlation cannot provide dispatched personnel, dispatch from the area with the second largest correlation strength until the personnel dispatch is completed; The construction plan updating unit is used to input the construction image and environmental parameters into a preset construction detection model, generate a construction optimization strategy, and update the construction plan using the construction optimization strategy.
5. An electronic device, characterized in that: include: A processor and a memory, wherein the memory is used to store computer program codes, wherein the computer program codes include computer instructions, and when the processor executes the computer instructions, the electronic device executes the intelligent construction method for modular integrated buildings as described in any one of claims 1 to 3.
6. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores a computer program, which includes program instructions. When the program instructions are executed by a processor of an electronic device, the processor executes the intelligent construction method of a modular integrated building as described in any one of claims 1 to 3.
Citation Information
Patent Citations
Inspection route optimization method and device of inspection unit and electronic equipment
CN115509184A
Construction site inspection robot and robot control method
CN117506854A
Cited By
Dynamic integration and construction safety evaluation system for green building modular construction equipment
CN121882565A