A deep sea bridge pier structure and construction method
By adopting the design of space truss systems and protective components in deep-sea bridge piers, the horizontal thrust problem of tidal current on the bridge piers is solved, structural stability and construction efficiency are improved, cost and difficulty are reduced, and the use of cofferdam measures is reduced.
Patent Information
- Application Number
- CN202410491780.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-23
- Publication Date
- 2024-11-05
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The horizontal thrust generated by the tidal water flow of the deep-sea bridge piers leads to uneven structural stress, high resistance, and difficult construction of the cofferdam, high cost and high difficulty.
Adopt a space truss architecture, including base piles, trusses and protective components. The truss consists of a main rod, an oblique connecting rod and a transverse connecting rod. The main rod is hollow inside, a fixed steel bracket, and the locking parts include an electric jack and a movable hook, rubber The water stop hood is used to reduce the thrust of tidal water flow on the pier body, and protective components surround the base piles and trusses to reduce the impact of the ocean currents.
The horizontal thrust of the ocean current on the pier body is reduced, the bending moment is reduced, the structural stability and safety is improved, the construction difficulty and cost is reduced, the use of cofferdam measures is reduced, the steel plate material is saved and the construction period is shortened.
Smart Images

Figure CN118360859B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of bridge piers, in particular to a deep-sea bridge pier structure and a construction method. Background Art
[0002] Bridge piers are buildings that support the span structure and transfer the dead load and vehicle live load to the foundation. Bridge abutments are located on both sides of the bridge. The bridge piers are located between the two abutments. The function of the bridge piers is to support the span structure, while the abutments not only support the span structure, but also connect with the embankment and prevent the embankment from sliding. In order to protect the abutments and embankment fill, some protection and diversion projects are often carried out on both sides of the abutments.
[0003] The current problem is that due to the tides in the ocean, the bridge piers in the deep sea are generally solid, and their force-bearing area is large, which will block the tidal current and generate horizontal thrust on the bridge piers. The higher the bridge pier is, the greater the resistance is, and the greater the horizontal thrust torque is. In order to reduce the horizontal thrust generated by the ocean current on the pier body, a deep-sea bridge pier structure and construction method are urgently needed to solve the above problems. Summary of the invention
[0004] In view of the above-mentioned technical problems existing in the prior art, a deep-sea pier structure and construction method are provided, which can effectively solve the construction difficulties of deep-sea pier cofferdams. The new structure is adopted to reduce the horizontal thrust of tidal water flow on the piers.
[0005] The purpose and effect of the present invention are achieved by the following specific technical means:
[0006] A deep-sea bridge pier structure, comprising: foundation piles, trusses and protective components, wherein a plurality of the foundation piles and trusses are provided, the lower ends of the plurality of the foundation piles and protective components are fixed to the seabed, a plurality of the trusses are longitudinally spliced and fixed to form a pier body and are fixed to the plurality of the foundation piles, and the protective components surround the plurality of the foundation piles and the plurality of trusses;
[0007] The truss comprises a main rod, an oblique connecting rod and a transverse connecting rod. The main rods are provided in a plurality and are distributed in a ring shape, and are arranged in an inclined manner. A conical limiting tube is provided at the upper end of each main rod. The oblique connecting rods and the transverse connecting rods are provided in a plurality and are respectively welded between two adjacent main rods. The main rods, the oblique connecting rods and the transverse connecting rods form a plurality of triangles.
[0008] The main rod is hollow inside, and a steel bracket is fixed inside the main rod, and a locking piece is installed between two adjacent steel brackets.
[0009] Preferably, a plurality of the trusses are in a tower shape that is larger at the bottom and smaller at the top and gradually shrinks, and a polymer anti-corrosion material is provided on the outside of the trusses.
[0010] Preferably, the locking member includes an electric jack, a movable hook and a fixed hook, the electric jack and the fixed hook are respectively fixed on two upper and lower adjacent steel brackets, and the movable hook is installed on the movable end of the electric jack and is buckled with the fixed hook.
[0011] Preferably, a conical rubber water-stop sleeve is fixed to the lower end of the main rod, the rubber water-stop sleeve is buckled in the limiting tube and forms a glue injection cavity, and a grouting pipe connected to the interior of the rubber water-stop sleeve is fixed on the rubber water-stop sleeve, and drainage holes symmetrically distributed with the grouting pipe are opened on the rubber water-stop sleeve, the glue injection cavity is filled with epoxy resin glue through the grouting pipe, and underwater fiber concrete is injected into the main rod.
[0012] Preferably, the protective component includes a plurality of steel pipes, the lower ends of the steel pipes are driven into the seabed, the upper ends extend to the sea surface, and connecting rods are welded between adjacent steel pipes.
[0013] Preferably, the foundation piles are made of steel cages and underwater concrete casting, and a pile foundation cap steel sleeve is sleeved between the lower end of the main rod at the bottom and the upper end of the foundation pile. The pile foundation cap steel sleeve is filled with underwater fiber concrete to consolidate the main rod at the bottom and the foundation pile.
[0014] The present invention also provides a deep-sea pier structure construction method, comprising the following steps:
[0015] S1: driving a protective component for pier protection into the seabed, the protective component comprising a plurality of steel pipes, with connecting rods welded between two adjacent steel pipes. The protective component is used as an operating platform during the construction phase and is used for pier protection after the construction is completed;
[0016] S2: Install a drilling rig on the protective component, set up several foundation pile sites on the seabed, arrange steel pipe casings for foundation pile construction at the foundation pile sites, use the drilling rig to drill holes at the foundation pile sites, make several steel cages on the water, lower the made steel cages into several pile holes, then install the steel cages at the locations, use the conduit to pour underwater concrete into the pile holes, complete the production of foundation piles, and use an underwater excavator to clean the pile foundation and the seabed to meet the bearing capacity requirements of the bridge piers;
[0017] S3: A number of tower-shaped trusses that can be longitudinally spliced and gradually shrink from the bottom to the top are manufactured in the factory. A number of hollow main rods are arranged on the periphery of the trusses. The steel sleeves of the pile foundation cap are sleeved at the lower ends of the main rods. Disassembled locking parts are arranged in the two main rods adjacent to each other;
[0018] A conical rubber water-stop sleeve is fixed at the lower end of the main rod, the rubber water-stop sleeve is buckled in the limit tube and forms a glue injection cavity, and a grouting pipe communicating with the inside of the rubber water-stop sleeve is fixed on the rubber water-stop sleeve, and drainage holes symmetrically distributed with the grouting pipe are opened on the rubber water-stop sleeve;
[0019] S4: The finished trusses are transported by sea to the pier fabrication site, and a steel wire rope group for truss unloading is installed on the protective component. The steel wire rope group is provided with an automatic detachment device. Then, the bottom trusses are hoisted and lowered to the seabed by the steel wire rope group, and the pile foundation cap steel sleeves at the lower ends of several main rods are respectively sleeved on several foundation piles. The underwater fiber concrete is injected into the pile foundation cap steel sleeves by the guide tube to consolidate the main rods and the foundation piles, and then the automatic detachment device is activated to retract the steel wire rope group;
[0020] S5: When the underwater fiber concrete curing period in S4 is reached and the strength meets the requirements, the surface of the underwater fiber concrete is roughened by underwater construction equipment;
[0021] S6: Use an external conduit to inject underwater fiber concrete into the main rod. During this process, the seawater in the main rod is discharged from the upper end. After the main rod is fully filled, the upper end of the locking piece protrudes from the main rod.
[0022] S7: When the underwater fiber concrete in the main pole reaches the curing period and the strength meets the requirements, the next truss is hoisted and lowered into the sea to be spliced with the bottom truss, and then the locking piece in the upper main pole is locked with the locking piece in the lower main pole, and then S6 is repeated;
[0023] S8: Repeat S7 until all trusses are assembled and fastened together.
[0024] Preferably, a steel support is fixed inside the main rod, and the locking member includes an electric jack, a movable hook and a fixed hook. The electric jack and the fixed hook are respectively fixed on two adjacent steel supports above and below, and the movable hook is connected with the fixed hook below it by starting the electric jack with electricity.
[0025] Compared with the prior art, the present invention has the following beneficial effects:
[0026] 1. The pier body adopts a spatial truss system (made of several trusses spliced and fixed longitudinally). It is hollow inside and has a small horizontal area. The ocean current can flow inside, thereby reducing the horizontal thrust of the ocean current on the pier body, thereby reducing the horizontal bending moment of the pier body and making the structure more reasonable;
[0027] 2. Several trusses are prefabricated in the factory. Compared with the deep-sea piers currently built in the sea, the engineering difficulty is greatly reduced, and the quality of the piers is more reliable;
[0028] 3. The truss at the bottom is fixedly connected to the foundation pile, making the pier base larger and more stable;
[0029] 4. The protective components surround the foundation piles and trusses, which can reduce the impact of ocean currents and effectively prevent ships from hitting the foundation piles and trusses, thus providing good protection for the pier body. In addition, during construction, the protective components can be used as an operating platform for building several trusses, thus killing two birds with one stone.
[0030] 5. When the bridge piers are working underwater, cofferdam measures are not used. Since deep-sea cofferdams are expensive and difficult to make, this reduces the construction difficulty and saves more than 10,000 tons of steel plates used for cofferdam measures, greatly saving construction costs and shortening construction period. BRIEF DESCRIPTION OF THE DRAWINGS
[0031] Figure 1 It is a schematic diagram of the three-dimensional structure of the bridge pier of the present invention after the construction is completed;
[0032] Figure 2 It is a schematic diagram of the three-dimensional structure of the truss of the present invention;
[0033] Figure 3 It is a schematic diagram of the three-dimensional structure of the bridge pier during construction of the present invention;
[0034] Figure 4 It is a schematic diagram of the main cross-sectional structure of the foundation pile, main rod and pile foundation cap steel sleeve of the present invention;
[0035] Figure 5 It is a schematic diagram of the front cross-sectional structure of the truss of the present invention;
[0036] Figure 6 It is a schematic diagram of the main structure of the truss of the present invention;
[0037] Figure 7 For the present invention Figure 5 Schematic diagram of the local structure at point A.
[0038] Markings in the figure: truss 1, base pile 2, steel pipe 3, connecting rod 4, main rod 5, grouting pipe 6, oblique connecting rod 7, transverse connecting rod 8, rubber water-stop sleeve 9, limit pipe 10, drainage hole 11, steel support 12, electric jack 13, movable hook 14, fixed hook 15, pile foundation cap steel sleeve 16, glue injection cavity 17. DETAILED DESCRIPTION
[0039] See also Figure 1-7 , further illustrate the embodiments of the present invention;
[0040] A deep-sea bridge pier structure, comprising: a foundation pile 2, a truss 1 and a protective component, wherein a plurality of foundation piles 2 and a plurality of trusses 1 are provided, the lower ends of the plurality of foundation piles 2 and the protective component are fixed to the seabed, a plurality of trusses 1 are longitudinally spliced and fixed to form a pier body and are fixed to the plurality of foundation piles 2, and the protective component surrounds the plurality of foundation piles 2 and the plurality of trusses 1;
[0041] In this solution, the pier body adopts a spatial truss system, which is composed of several trusses 1 spliced and fixed longitudinally. The interior of the trusses is hollow and has a small horizontal area. The ocean current can flow inside, thereby reducing the horizontal thrust of the ocean current on the pier body, thereby reducing the horizontal bending moment of the pier body and making the structure more reasonable.
[0042] It should be noted that the several trusses 1 are all prefabricated in the factory. Compared with the deep-sea piers currently built in the sea, the engineering difficulty is greatly reduced, and the quality of the piers is more reliable.
[0043] The truss 1 at the bottom is fixedly connected to the foundation pile 2, so that the base of the pier is larger and the pier is more stable;
[0044] Since the protective component surrounds a plurality of foundation piles 2 and a plurality of trusses 1, the impact of ocean currents can be reduced, and the collision of ships with the foundation piles 2 and the trusses 1 can be effectively avoided, thereby providing good protection for the pier body. In addition, during the construction period, the protective component can be used as an operating platform for building a plurality of trusses 1. For example, before the truss 1 needs to be lowered into the sea, a steel wire rope group that can move as the truss 1 sinks is arranged on the protective component. The purpose is to adjust the position of the suspended truss 1 so that the truss 1 can be kept horizontally lowered so that the truss 1 can be accurately moved to the installation site.
[0045] When the bridge piers were operated underwater, no cofferdam measures were used, which reduced the construction difficulty and saved more than 10,000 tons of steel plates used for cofferdam measures, greatly saving construction costs and shortening the construction period.
[0046] Several trusses 1 are in the shape of a tower that is larger at the bottom and smaller at the top and gradually shrinks. The purpose of this design is: first, it helps to improve the overall stability of the structure. The center of gravity is lower, the structure is more stable, and it can better resist external loads such as ocean currents; second, the design of larger at the bottom and smaller at the top helps to reduce ocean current resistance and improve the safety of the structure; third, according to the stress conditions, the stress performance of the pier body can be fully utilized. The outside of the truss 1 is provided with a polymer anti-corrosion material, such as polyethylene, which has an anti-corrosion effect on the truss 1 and can also reduce water friction.
[0047] The truss 1 includes a main rod 5, an oblique connecting rod 7 and a transverse connecting rod 8. The main rods 5 are provided with a plurality of rods and are distributed in a ring shape. The main rods 5 are arranged obliquely. A conical limiting tube 10 is provided at the upper end of each main rod 5. The oblique connecting rods 7 and the transverse connecting rods 8 are provided with a plurality of rods and are respectively welded between two adjacent main rods 5. The main rods 5, the oblique connecting rods 7 and the transverse connecting rods 8 form a plurality of triangles.
[0048] It should be noted that the limit tube 10 is made of steel and has high hardness; the main rod 5 is the main force-bearing foot of the truss 1. During the splicing process of two adjacent trusses 1, the limit tube 10 can limit the main rod 5 above it, which is conducive to the rapid splicing of the upper main rod 5 and the lower main rod 5. The reason why the upper and lower adjacent main rods 5 in this application do not adopt the concave-convex splicing method is that the weight of the truss 1 is at least thousands of tons. After the truss 1 is stressed, the concave-convex part of the main rod 5 is prone to deformation, which is not conducive to the later splicing of the two main rods 5. Since the diagonal connecting rods 7 and the transverse connecting rods 8 are each provided with a plurality of them and are respectively welded between two adjacent main rods 5, the main rods 5, the diagonal connecting rods 7 and the transverse connecting rods 8 form a plurality of triangles, so the truss 1 is stably stressed and has high safety.
[0049] The main rod 5 is hollow inside, and a steel bracket 12 is fixed inside the main rod 5, and a locking piece is installed between two adjacent steel brackets 12;
[0050] The hollow interior of the main rod 5 is designed to install a locking piece. After the two upper and lower adjacent trusses 1 are spliced, the two upper and lower adjacent main rods 5 are tightened by the locking piece. On the one hand, the connection strength between the two upper and lower adjacent main rods 5 can be strengthened, and on the other hand, the force transmission performance of several trusses 1 can be strengthened.
[0051] The locking member includes an electric jack 13, a movable hook 14 and a fixed hook 15. The electric jack 13 and the fixed hook 15 are respectively fixed to two adjacent steel brackets 12 above and below. The movable hook 14 is installed at the movable end of the electric jack 13 and is buckled with the fixed hook 15.
[0052] It should be noted that if Figure 5 and Figure 7As shown, a fixing hook 15 is arranged at the lower end of the locking member, and the fixing hook 15 is fixed on the steel bracket 12 inside the bottom main rod 5, and ensures that the hook portion of the fixing hook 15 protrudes from the bottom main rod 5, the purpose is to prevent the fixing hook 15 from being buried by grouting of the main rod 5 in the later stage, and an electric jack 13 is arranged at the upper end of the locking member, and the electric jack 13 is fixed on the internal steel bracket 12 connected to the bottom main rod 5, so that after the next truss 1 is installed, an external power supply is connected to directly start the electric jack 13 to drive the movable hook 14 to hook the fixing hook 15, and when the upper and lower trusses 1 are spliced, the movable hook 14 is in an open state, and after the movable hook 14 is aligned with the fixing hook 15, the top of the fixing hook 15 will touch the mechanism in the movable hook 14, so that the movable hook 14 and the fixing hook 15 are locked.
[0053] A conical rubber water-stop sleeve 9 is fixed at the lower end of the main rod 5, the rubber water-stop sleeve 9 is buckled in the limit tube 10 and forms a glue injection cavity 17, and a grouting pipe 6 communicating with the inside of the rubber water-stop sleeve 9 is fixed, and a drainage hole 11 symmetrically distributed with the grouting pipe 6 is opened on the rubber water-stop sleeve 9, and the glue injection cavity 17 is filled with epoxy resin glue through the grouting pipe 6, and underwater fiber concrete is injected into the main rod 5;
[0054] The underwater fiber concrete is filled from the bottom to the inside of the main rod 5 by using an external conduit, and the seawater in the main rod 5 is discharged from the top during the process. After the underwater fiber concrete solidifies and reaches the required strength, the next truss 1 can be lowered into the seawater for further splicing, and the truss 1 just lowered is locked with the truss 1 spliced with it by using a locking piece, and then the main rod 5 in the truss 1 just lowered is grouted. All trusses 1 can be spliced and fixed according to the above method. The reason for grouting the truss 1 first and then splicing the next truss 1 is that the weight of the truss 1 is at least thousands of tons, and the truss 1 after grouting has a strong load-bearing capacity, which can ensure that it will not deform when splicing the next truss 1. The reason for casting underwater fiber concrete is that the concrete has high compressive strength, and the tensile strength is also higher than that of ordinary concrete, which provides force protection for the truss 1.
[0055] When the two main rods 5 adjacent to each other are spliced, the rubber water-stop sleeve 9 on the upper main rod 5 will be buckled into the limiting tube 10 below. At this time, a closed glue injection cavity 17 is formed between the rubber water-stop sleeve 9 and the limiting tube 10. The grouting pipe 6 is used to guide the epoxy resin glue on the water into the glue injection cavity 17. During this process, the seawater in the glue injection cavity 17 will be discharged through the drainage hole 11, so that the connection between the two main rods 5 is sealed, which can strengthen the connection strength of the two main rods 5, so that the two main rods 5 adjacent to each other can form a whole and achieve force transmission performance.
[0056] The protection component includes a plurality of steel pipes 3, the lower ends of the steel pipes 3 are driven into the seabed, and the upper ends extend to the sea surface, and connecting rods 4 are welded between adjacent steel pipes 3;
[0057] Since the truss 1 and steel pipe 3 in the present invention are large in size, the truss 1 and steel pipe 3 are both rolled from steel plates. The diameter of the steel pipe 3 is 1-2m, and the hardness of the steel pipe 3 is high. After a number of steel pipes 3 surround the truss 1 and the foundation pile 2, the impact of ocean currents can be reduced, and at the same time, the ship can be effectively prevented from hitting the foundation pile 2 and the truss 1, which plays a good protective role on the pier body; during construction, a number of steel pipes 3 can be used as an operating platform for building a number of trusses 1. For example, before the truss 1 needs to be lowered to the sea, a steel wire rope group that can move with the sinking of the truss 1 is set on the several steel pipes 3, in order to adjust the position of the hanging truss 1 so that the truss 1 can be accurately moved to the installation site. The welding of the connecting rod 4 is done after the construction of the pier is completed, and a number of steel pipes 3 are no longer needed as an operating platform for the construction of the pier.
[0058] The foundation pile 2 is made of a steel cage and underwater concrete pouring to ensure the hardness and strength of the foundation pile 2.
[0059] A pile foundation cap steel sleeve 16 is sleeved between the lower end of the lowest main rod 5 and the upper end of the foundation pile 2. The pile foundation cap steel sleeve 16 is filled with underwater fiber concrete, so that the lowest main rod 5 and the foundation pile 2 are consolidated, similar to the current bridge pier pile foundation cap, to ensure the stability of the pier bottom.
[0060] The present invention also provides a deep-sea pier structure construction method, comprising the following steps:
[0061] S1: driving a protective component for pier protection into the seabed, the protective component comprising a plurality of steel pipes 3, a connecting rod 4 being welded between two adjacent steel pipes 3, the protective component being used as an operating platform during the construction phase, and being used for pier protection after the construction is completed;
[0062] S2: Install a drilling rig on the protective component, set up several foundation pile 2 locations on the seabed, arrange steel pipe casings for foundation pile 2 construction at the foundation pile 2 locations, use the drilling rig to drill holes at the foundation pile 2 locations, make several steel cages on the water, lower the made steel cages into several pile holes, then install the steel cages at the locations, use a conduit to pour underwater concrete into the pile holes, complete the production of foundation pile 2, and use an underwater excavator to clean the pile foundation and the seabed so that they meet the bearing capacity requirements of the bridge piers;
[0063] Since the protective components surround several foundation piles 2 and several trusses 1, the impact of ocean currents can be reduced, and the collision of ships with foundation piles 2 and trusses 1 can be effectively prevented, which plays a good protective role on the pier body; in addition, during the construction period, the protective components can be used as an operating platform for building several trusses 1, for example: drilling holes at the foundation pile 2 site, installing and fixing the foundation pile 2, and before the truss 1 needs to be lowered into the sea, a steel wire rope group that can move with the truss 1 is set on the protective component, in order to adjust the position of the hanging truss 1 so that the truss 1 can be accurately moved to the installation site. The welding of the connecting rod 4 is to strengthen the connection strength between several steel pipes 3 after the construction of the bridge pier is completed. At this time, several steel pipes 3 are not needed as an operating platform for the construction of the bridge pier.
[0064] S3: A plurality of tower-shaped trusses 1 that can be longitudinally spliced and are gradually contracted from the bottom to the top are manufactured in a factory. A plurality of hollow main rods 5 are arranged on the periphery of the trusses 1. The pile foundation cap steel sleeves 16 are sleeved on the lower ends of the main rods 5. Disassembled locking parts are arranged inside two upper and lower adjacent main rods 5.
[0065] A conical rubber water-stop sleeve 9 is fixed at the lower end of the main rod 5, the rubber water-stop sleeve 9 is buckled in the limit tube 10 and forms a glue injection cavity 17, and a grouting pipe 6 communicating with the inside of the rubber water-stop sleeve 9 is fixed on the rubber water-stop sleeve 9, and drainage holes 11 symmetrically distributed with the grouting pipe 6 are opened on the rubber water-stop sleeve 9;
[0066] The purpose of the tower-shaped design of the pier is: first, it helps to improve the overall stability of the structure, with a lower center of gravity, a more stable structure, and better resistance to external loads such as ocean currents; second, the design of a larger bottom and smaller top helps to reduce ocean current resistance and improve the safety of the structure; third, according to the stress conditions, the stress performance of the pier can be fully utilized. The main rod 5 is designed to be hollow inside on the one hand to facilitate the accommodation of the locking piece so that the two adjacent main rods 5 can be locked after splicing in the later stage, and on the other hand to enable grouting. After grouting, the main rod 5 is stronger and the load-bearing capacity of the truss 1 is improved.
[0067] S4: The finished truss 1 is shipped by sea to the pier manufacturing site, and a steel wire rope group for unloading the truss 1 is installed on the protective component. The steel wire rope group is provided with an automatic detachment device, and then the bottom truss 1 is hoisted and lowered to the seabed by the steel wire rope group, and the pile foundation cap steel sleeves 16 at the lower ends of several main rods 5 are respectively sleeved on several foundation piles 2, and underwater fiber concrete is injected into the pile foundation cap steel sleeves 16 by using a catheter to consolidate the main rods 5 and the foundation piles 2, and then the automatic detachment device is activated to retract the steel wire rope group;
[0068] Before the truss 1 is lowered into the sea, a steel wire rope group that can move with the truss 1 is set on the protective component, in order to adjust the position of the truss 1, and keep the truss 1 horizontally lowered so that the truss 1 can be accurately moved to the installation site. The underwater fiber concrete is injected into the pile foundation cap steel sleeve 16 to consolidate the main rod 5 and the foundation pile 2. This design is similar to the current bridge pier pile foundation cap, ensuring the stability of the pier bottom.
[0069] When the two main rods 5 adjacent to each other are spliced, the rubber water-stop sleeve 9 on the upper main rod 5 will be buckled into the limiting tube 10 below. At this time, a closed glue injection cavity 17 is formed between the rubber water-stop sleeve 9 and the limiting tube 10. The grouting pipe 6 is used to guide the epoxy resin glue on the water into the glue injection cavity 17. During this process, the seawater in the glue injection cavity 17 will be discharged through the drainage hole 11, so that the connection between the two main rods 5 is sealed, which can strengthen the connection strength of the two main rods 5, so that the two main rods 5 adjacent to each other can form a whole and achieve force transmission performance.
[0070] S5: When the underwater fiber concrete curing period in S4 is reached and the strength meets the requirements, the surface of the underwater fiber concrete is roughened by underwater construction equipment;
[0071] When the underwater fiber concrete curing period is reached and the strength meets the requirements, the steel wire rope groups fixing the truss 1 horizontally and vertically are withdrawn and moved to the water surface. The underwater fiber concrete surface is roughened by underwater construction equipment to ensure the quality of its coagulation with the underwater fiber concrete in the main rod 5 at a later stage.
[0072] S6: Use an external conduit to inject underwater fiber concrete into the main rod 5. During this process, the seawater in the main rod 5 is discharged from the upper end thereof. After the main rod 5 is fully filled, the upper end of the locking member protrudes from the main rod 5.
[0073] S7: When the underwater fiber concrete in the main rod 5 reaches the curing period and the strength meets the requirements, the next truss 1 is hoisted and lowered into the sea to be spliced with the bottom truss 1, and then the locking piece in the upper main rod 5 is locked with the locking piece in the lower main rod 5, and then S6 is repeated;
[0074] S8: Repeat S7 until all trusses 1 are assembled and fastened together;
[0075] Underwater fiber concrete is injected into the main rod 5 through an external conduit, and the seawater in the main rod 5 is discharged from its upper end during the process. After the underwater fiber concrete solidifies and reaches the required strength, the next truss 1 can be lowered into the seawater for further splicing, and the truss 1 just lowered is locked with the truss 1 spliced with it by a locking piece, and then the main rod 5 in the truss 1 just lowered is grouted. All trusses 1 can be spliced and fixed according to the above method. The reason for grouting the truss 1 first and then splicing the next truss 1 is that the weight of the truss 1 is at least thousands of tons, and the truss 1 after grouting has a strong load-bearing capacity, which can ensure that it will not deform when splicing the next truss 1. The reason for casting underwater fiber concrete is that the concrete has high compressive strength and higher tensile strength than ordinary concrete, which provides force protection for the truss 1.
[0076] A steel support 12 is fixed inside the main rod 5, and the locking member includes an electric jack 13, a movable hook 14 and a fixed hook 15. The electric jack 13 and the fixed hook 15 are respectively fixed on two adjacent steel supports 12 above and below. The electric jack 13 is activated by electricity to make the movable hook 14 buckle with the fixed hook 15 below it.
[0077] Electricity is used to buckle the movable hook 14 with the fixed hook 15 thereunder, without manual operation. The use of the locking member enhances the connection strength and force transmission performance between the trusses 1 .
[0078] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the present invention, which should be included in the scope of the claims of the present invention.
Claims
1. A deep-sea pier structure, characterized in that: include: Foundation piles (2), trusses (1) and protective components, wherein a plurality of the foundation piles (2) and trusses (1) are provided, the lower ends of the plurality of the foundation piles (2) and protective components are fixed to the seabed, a plurality of the trusses (1) are longitudinally spliced and fixed to form a pier body and are fixed to the plurality of the foundation piles (2), and the protective components surround the plurality of the foundation piles (2) and the plurality of trusses (1); The truss (1) comprises a main rod (5), an oblique connecting rod (7) and a transverse connecting rod (8), wherein a plurality of main rods (5) are provided and are distributed in a ring shape, and the main rods (5) are arranged in an inclined manner, and a conical limiting tube (10) is provided at the upper end of each main rod (5), and a plurality of oblique connecting rods (7) and transverse connecting rods (8) are provided and are respectively welded between two adjacent main rods (5), and the main rods (5), the oblique connecting rods (7) and the transverse connecting rods (8) form a plurality of triangles; The main rod (5) is hollow inside, and a steel support (12) is fixed inside the main rod (5). A locking member is installed between two adjacent steel supports (12). The locking member includes an electric jack (13), a movable hook (14) and a fixed hook (15). The electric jack (13) and the fixed hook (15) are respectively fixed to two upper and lower adjacent steel supports (12). The movable hook (14) is installed at the movable end of the electric jack (13) and is buckled with the fixed hook (15).
2. A deep-sea pier structure according to claim 1, characterized in that: The plurality of trusses (1) are in the shape of a tower that is larger at the bottom and smaller at the top and gradually shrinks. The exterior of the trusses (1) is provided with a polymer anti-corrosion material.
3. A deep-sea pier structure according to claim 1, characterized in that: A conical rubber water-stop sleeve (9) is fixed to the lower end of the main rod (5); the rubber water-stop sleeve (9) is buckled into the limit tube (10) to form a glue injection cavity (17); a grouting pipe (6) communicating with the inside of the rubber water-stop sleeve (9) is fixed to the rubber water-stop sleeve (9); drainage holes (11) symmetrically distributed with the grouting pipe (6) are formed on the rubber water-stop sleeve (9); the glue injection cavity is filled with epoxy resin glue through the grouting pipe (6); and underwater fiber concrete is injected into the main rod (5).
4. A deep-sea pier structure according to claim 1, characterized in that: The protective component comprises a plurality of steel pipes (3), the lower ends of the steel pipes (3) are driven into the seabed, the upper ends extend to the sea surface, and connecting rods (4) are welded between adjacent steel pipes (3).
5. The deep-sea pier structure according to claim 1, characterized in that: The foundation pile (2) is made of a steel cage and underwater concrete casting, and a pile foundation cap steel sleeve (16) is sleeved between the lower end of the main rod (5) at the bottom and the upper end of the foundation pile (2), and the pile foundation cap steel sleeve (16) is filled with underwater fiber concrete, so that the main rod (5) at the bottom is consolidated with the foundation pile (2).
6. A deep-sea bridge pier structure construction method, characterized in that: The following steps are involved: S1: driving a protective component for bridge pier protection into the seabed, the protective component comprising a plurality of steel pipes (3), a connecting rod (4) being welded between two adjacent steel pipes (3), the protective component being used as an operating platform during the construction phase and being used for bridge pier protection after the construction is completed; S2: installing a drilling rig on the protective component, setting a plurality of foundation pile (2) positions on the seabed, arranging steel pipe casings for the construction of the foundation pile (2) at the foundation pile (2) positions, drilling holes at the foundation pile (2) positions using the drilling rig, making a plurality of steel cages on the water, lowering the made steel cages into a plurality of pile holes, and then installing the steel cages at the positions, pouring underwater concrete into the pile holes using a conduit, completing the production of the foundation pile (2), and using an underwater excavator to clean the pile foundation and the seabed so that they meet the bearing capacity requirements of the bridge pier; S3: A plurality of tower-shaped trusses (1) which can be longitudinally spliced and are gradually contracted in a large lower part and a small upper part are manufactured in a factory. A plurality of hollow main rods (5) are arranged on the periphery of the trusses (1). A pile foundation cap steel sleeve (16) is sleeved on the lower end of the main rods (5). A detachable locking member is arranged inside two upper and lower adjacent main rods (5); A conical rubber water-stop sleeve (9) is fixed to the lower end of the main rod (5); the rubber water-stop sleeve (9) is buckled into the limiting tube (10) and forms a glue injection cavity (17); a grouting pipe (6) communicating with the inside of the rubber water-stop sleeve (9) is fixed to the rubber water-stop sleeve (9); and drainage holes (11) symmetrically distributed with the grouting pipe (6) are formed on the rubber water-stop sleeve (9); S4: The finished truss (1) is shipped by sea to the pier manufacturing site, a steel wire rope group for unloading the truss (1) is installed on the protective component, and an automatic detachment device is provided on the steel wire rope group. Then, the bottom truss (1) is hoisted and lowered to the seabed by the steel wire rope group, and the pile foundation cap steel sleeves (16) at the lower ends of a plurality of main rods (5) are respectively sleeved on a plurality of foundation piles (2). Underwater fiber concrete is injected into the pile foundation cap steel sleeves (16) by a guide tube so that the main rods (5) are consolidated with the foundation piles (2), and then the automatic detachment device is activated to retract the steel wire rope group; S5: When the underwater fiber concrete curing period in S4 is reached and the strength meets the requirements, the surface of the underwater fiber concrete is roughened by underwater construction equipment; S6: using an external conduit to inject underwater fiber concrete into the main rod (5), during which the seawater in the main rod (5) is discharged from its upper end. After the main rod (5) is fully filled, the upper end of the locking member protrudes from the main rod (5); S7: When the underwater fiber concrete in the main rod (5) reaches the curing period and the strength meets the requirements, the next truss (1) is hoisted and lowered into the sea to be spliced with the bottom truss (1), and then the locking piece in the upper main rod (5) is locked with the locking piece in the lower main rod (5), and then S6 is repeated; S8: Repeat S7 until all trusses (1) are assembled and fastened together.
7. A deep-sea pier structure construction method according to claim 6, characterized in that: A steel support (12) is fixed inside the main rod (5), and the locking member includes an electric jack (13), a movable hook (14) and a fixed hook (15). The electric jack (13) and the fixed hook (15) are respectively fixed to two upper and lower adjacent steel supports (12), and the movable hook (14) is locked with the fixed hook (15) below it by starting the electric jack (13) with electricity.