Segmental cast-in-place construction method of arch-beam composite bridge based on hanging basket with lifting function

By using the technology of a hanging basket with a lifting function in the construction of arch-beam composite bridges, the span capacity and safety issues in the construction of large-span bridges spanning V-shaped valleys have been solved, and efficient and safe construction of the lower chord arch section has been achieved, which avoids The potential safety hazards of cantilever supports and platform erection are eliminated.

CN118422597BActive Publication Date: 2024-10-18贵州交通建设集团有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410900327.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-05
Publication Date
2024-10-18
Estimated Expiration
2044-07-05

AI Technical Summary

Technical Problem

In the construction of long-span bridges across V-shaped river valleys, the existing technology has limited span capacity and low structural load-bearing efficiency. Moreover, due to the lack of working space in mountainous construction sites, there are potential safety hazards and time waste in building construction platforms.

Method used

The cast-in-place construction method of arch-girder composite bridge segments based on hanging baskets with lifting functions is adopted. Through the combined use of upper hanging baskets and lower hanging baskets, the lifting system and suspension system are used to realize the movement and conversion of the bottom basket system, providing stability. Support the platform to avoid overhanging supports and improve construction safety and efficiency.

Benefits of technology

It realizes the safe and efficient construction of the lower chord arch section in the mountainous construction site, reduces the construction time and space requirements, avoids the collision between the upper chord hanging basket and the lower chord hanging basket, and improves the construction efficiency and safety.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118422597B_ABST
    Figure CN118422597B_ABST
Patent Text Reader

Abstract

The invention relates to the field of arch-beam combination bridges, and discloses a cast-in-place construction method for arch-beam combination bridge segments based on a hanging basket with a lifting function, comprising the following steps: step 1, completing the construction of bridge piers, casting a 0# segment of an upper chord beam on the top of the bridge piers, installing an upper chord hanging basket on the 0# segment of the upper chord beam, using the upper chord hanging basket to cast a 1# segment of the upper chord beam, and installing a lifting system on a main truss system of the upper chord hanging basket; step 2, the lifting system drives a bottom basket system to move downward, extends an upper end of a suspension system, connects the upper end of the suspension system with a main truss system of an upper chord hanging basket, and casts a 1# segment of a lower chord arch with the bottom basket system as support; step 3, the upper chord hanging basket moves forward, and casts a 2# segment of a lower chord arch with the bottom basket system as support; step 4, installing a walking system and a main truss system of a lower chord hanging basket on the lower chord arch, connecting the main truss system of the lower chord hanging basket with the upper end of a suspension system of the upper chord hanging basket, and converting the suspension system and the bottom basket system of the upper chord hanging basket into the suspension system and the bottom basket system of the lower chord hanging basket.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of arch-beam combination bridges, and in particular to a segment cast-in-place construction method of an arch-beam combination bridge based on a hanging basket with a lifting function. Background Art

[0002] With the continuous construction and extension of western expressways, expressway construction has entered areas with high mountains, canyon rivers and more complex geological conditions. Large-span bridges across V-shaped river valleys have become key projects for expressways in the western region and a controlling factor in the entire project construction period and cost.

[0003] However, the existing technology has limited spanning capacity and cannot meet the needs of spans above 300m; the structural load-bearing efficiency is not high, and the engineering economy deteriorates rapidly when the span is greater than 200m; due to the construction site and hoisting restrictions in mountainous areas, prefabricated beam bridges with large spans are not used in principle due to the heavy hoisting weight and difficulty in transportation.

[0004] The arch-beam composite bridge adopts a combination of an upper chord beam and a lower chord arch. The lower chord arch provides support for the upper chord beam, reducing the phenomenon of mid-span deflection, increasing the maximum span, while reducing the deadweight and improving economy.

[0005] However, at the location where the arch foot of the lower chord is connected to the pier, due to the lack of working space, it is necessary to temporarily build a construction platform and provide sufficient support to cast the lower chord arch section 1#; however, this requires the pier to be used as a support to build a cantilevered construction platform. During the process of building the platform, there is a lack of footholds, which is very dangerous and requires sufficient stability. Building a construction platform will consume a lot of time. Summary of the invention

[0006] The present invention aims to provide a cast-in-place construction method for an arch-beam composite bridge segment based on a hanging basket with a lifting function, which can safely and efficiently construct a lower chord arch 1# segment.

[0007] To achieve the above object, the present invention adopts the following technical solution: a cast-in-place construction method for arch-beam composite bridge segments based on a hanging basket with a lifting function,

[0008] The arch-beam composite bridge includes an upper chord beam and a lower chord arch. One end of the upper chord beam and the arch foot of the lower chord arch are connected to the bridge pier, and the other end of the upper chord beam is closed with the arch top of the lower chord arch. The upper chord beam and the lower chord arch are cast in several sections.

[0009] The arch-beam composite bridge adopts hanging basket construction, which is cantilevered from the top of the pier to both sides. The hanging basket is divided into upper chord hanging basket and lower chord hanging basket. Both upper chord hanging basket and lower chord hanging basket include walking system, main truss system, suspension system and bottom basket system. The walking system is installed on the upper surface of the upper chord beam or the lower chord arch. The main truss system is installed on the walking system and extends to the cantilever end. The upper end of the suspension system is detachably connected to the main truss system, and the lower end of the suspension system is connected to the bottom basket system. The bottom basket system serves as a supporting platform to bear the construction load.

[0010] The following steps are involved:

[0011] Step 1: Complete the construction of the bridge piers, cast the 0# section of the upper chord beam on the top of the piers, install the upper chord hanging basket on the 0# section of the upper chord beam, use the upper chord hanging basket to cast the 1# section of the upper chord beam, install the lifting system on the main truss system of the upper chord hanging basket, the lifting system can drive the bottom basket system to move downward, and remove the connection between the upper end of the suspension system and the main truss system;

[0012] Step 2: The lifting system drives the bottom basket system to move downward to the arch foot of the lower chord arch, and the upper end of the suspension system is extended to connect the upper end of the suspension system with the main truss system of the upper chord hanging basket, and the lower chord arch 1# section is cast with the bottom basket system as support;

[0013] Step 3: The walking system of the upper chord hanging basket drives the main truss system, the lifting system, the suspension system and the bottom basket system to move forward together, and the lower chord arch section 2# is cast with the bottom basket system as support;

[0014] Step 4: Install the walking system and main truss system of the lower chord hanging basket on the lower chord arch sections 1# and 2#, connect the main truss system of the lower chord hanging basket with the upper end of the suspension system of the upper chord hanging basket, and convert the suspension system and bottom basket system of the upper chord hanging basket into the suspension system and bottom basket system of the lower chord hanging basket;

[0015] Step 5: Cast the lower chord arch section 3#, remove the upper chord hanging basket, set up brackets on the lower chord arch sections 1# and 2# as support for the upper chord beam, and cast the upper chord beam section 2#;

[0016] Step 6: Repeat step 5 until the upper chord beam and the lower chord arch are poured to the closed position.

[0017] The beneficial effects of this program are:

[0018] In this solution, the upper chord hanging basket moves in the direction of the cantilever end of the upper chord beam. The upper chord hanging basket is set up on the 0# section of the upper chord beam, and then the bottom basket of the upper chord hanging basket is lowered to the arch foot position of the lower chord arch through the lifting system to provide a platform for the pouring of the 1# section of the lower chord arch. Compared with the prior art that directly sets up a platform at the arch foot position, this solution sets up the upper chord hanging basket on the 0# section of the upper chord beam, which has sufficient operating space and footholds, and there is no need to worry about stepping on empty space and falling, which makes the operation safer, so as to more safely construct the 1# section of the lower chord arch. The top of the pier can provide sufficient support for the upper chord hanging basket. Compared with the prior art, there is no need to set up a cantilever platform, and the construction process is safer and faster, so as to efficiently construct the 1# section of the lower chord arch. After pouring the lower chord arch section 2#, the lower chord hanging basket is set up, and the main truss system of the lower chord hanging basket provides support for the bottom basket system, so that the bottom basket system of the upper chord hanging basket is transferred to the lower chord hanging basket, eliminating the tedious steps of reinstalling the bottom basket system of the lower chord hanging basket, and improving the construction efficiency. The lower chord arch is constructed first, and then a bracket is set up on the lower chord arch to provide support for the upper chord beam. Compared with the cantilever construction of the upper chord beam, the way of setting up the bracket is more traditional and safer, and the lower chord arch below is used as support to avoid the situation of cantilever support; at the same time, the upper chord beam does not need to use a hanging basket for construction, which saves the time of moving the hanging basket and improves the construction efficiency. As the construction progresses, the upper chord beam and the lower chord arch gradually approach each other to facilitate the final closure; if the arch-beam composite bridge is constructed by a hanging basket, the upper chord hanging basket and the lower chord hanging basket are prone to collision due to their close distance, thus affecting the efficiency of construction; in this scheme, after the upper chord beam completes the construction of Section 1, the upper chord hanging basket is cancelled and supported by brackets, which greatly saves construction space and avoids the collision between the upper chord hanging basket and the lower chord hanging basket. Furthermore, the lifting system includes several electric hoists;

[0019] In step 1, during the construction of the bridge pier, a horizontally set lower chord arch 0# section is reserved, the upper ends of the electric hoists are connected to the main truss system of the upper chord hanging basket, and the lower ends of the electric hoists are hung on the bottom basket system;

[0020] In step 2, while the electric hoist drives the bottom basket system to move downward, the upper end of the suspension system is temporarily fixed on the steel cable of the electric hoist; after the electric hoist drives the bottom basket system to move downward, a template of the lower chord arch section 1# is set up on the bottom basket system, the bottom basket system and the template of the lower chord arch section 1# are detachably connected, and the template of the lower chord arch section 1# is connected to the lower chord arch section 0#.

[0021] Furthermore, the suspension system of the upper chord hanging basket includes a plurality of suspension units, each of which includes a suspension rod and an extension rod, an upper connecting piece and a lower connecting piece are respectively provided at the upper and lower ends of the suspension rod, the upper end of the suspension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connecting piece, and the upper connecting piece is supported on the main truss system;

[0022] In step two, the upper connector is removed, and the steel cables of the boom and the electric hoist are temporarily fixed by iron wire. The electric hoist drives the bottom basket system to move downward, and the upper end of the extension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connector. The upper connector is supported on the main truss system, and the extension connector is threadedly connected at the lower end of the extension rod. The lower end of the extension connector is threadedly connected to the upper end of the boom, and the iron wire on the steel cables of the boom and the electric hoist is removed.

[0023] Furthermore, the thread directions of the suspension rod and the extension rod are the same, a conversion pad is welded at the lower end of the extension connector, and the upper end of the suspension rod can pass through the conversion pad; the front crossbeam or the rear crossbeam is composed of two parallel I-beams, and the distance between the two I-beams is less than the width of the conversion pad;

[0024] In step 4, the method of converting the suspension system and bottom basket system of the upper string hanging basket into the suspension system and bottom basket system of the lower string hanging basket is as follows:

[0025] Step 4.1, during the installation of the main truss system of the lower chord hanging basket, make the suspension rod of the upper chord hanging basket pass through the front beam or rear beam of the lower chord hanging basket, hang the upper end of the electric hoist on the front beam or rear beam, and hang the lower end of the electric hoist on the front cantilever beam or rear cantilever beam;

[0026] Step 4.2, rotate the extension connector so that the conversion pad at the lower end of the extension connector is supported on the main truss system of the lower chord hanging basket, remove the upper connector at the upper end of the extension rod, rotate the extension rod to separate the lower end of the extension rod from the extension connector, and remove the extension rod and the electric hoist.

[0027] Furthermore, one ends of several longitudinal beams are hinged to the front cantilever beam, and several horizontally arranged support tubes are provided on the rear cantilever beam. The other ends of the longitudinal beams are supported on the support tubes, and the other ends of the longitudinal beams can slide on the support tubes.

[0028] Furthermore, the conversion pad is provided with four strip-shaped bolt holes, each of which can be equipped with a limiting bolt;

[0029] In step 4.2, the conversion pad is supported on the front beam or rear beam of the main truss system of the lower chord hanging basket, and four limit bolts are installed on the conversion pad. The four limit bolts are evenly distributed and fit on both sides of the front beam or rear beam, thereby limiting the distance between the two I-beams constituting the front beam or rear beam.

[0030] Furthermore, taking the center line of the pier as the axis of symmetry, the upper chord beam and the lower chord arch on both sides of the pier are constructed synchronously and symmetrically; a number of temporary cables are set on the pier, and the temporary cables all pass through the pier. The two ends of the temporary cables are anchored in the lower chord arch on both sides of the pier. Starting from the 2# section of the lower chord arch, each section is cast and a temporary cable is constructed;

[0031] In step 3, two ends of a temporary cable are anchored in the 2# section of the lower chord arch on both sides of the bridge pier;

[0032] In step five, the two ends of a temporary cable are anchored in the 3# section of the lower chord arch on both sides of the pier.

[0033] Furthermore, in step 1, a longitudinal temporary prestress is applied to the upper side of the upper chord beam 1# segment;

[0034] In step five, after the support is erected, the temporary prestress applied to the upper chord beam section 1# is removed.

[0035] This solution also has the following effects:

[0036] 1. During the construction of the bridge pier, a horizontally set lower chord arch section 0# is reserved to reserve a connection position for the template of the lower chord arch section 1#.

[0037] 2. Compared with using a jack to drive the boom to move downward, this solution uses an electric hoist to drive the bottom basket system to move downward, which is faster and more convenient;

[0038] In addition, when constructing on high bridge piers, the wind load is large, the lower end of the hanger is in a free state, and it shakes violently; when the bottom basket system moves downward, the wind load on the hanger gradually increases, the hanger shakes more violently, and it is easy to deform and damage; in this solution, the steel cable of the electric hoist is more flexible than the hanger, and it can recover even if it is deformed under wind load. The upper end of the hanger is no longer fixed, and the hanger shakes with the steel cable, so it is not easy to deform; when the bottom basket system reaches the arch foot position of the lower chord arch and is connected to the 0# section of the lower chord arch through the template, the bottom basket system tends to be stable under the support of the 0# section of the lower chord arch. At this time, the shaking of the lower end of the hanger affected by the wind load is reduced. At this time, an extension rod is used to extend the hanger, and the hanger is not easy to deform.

[0039] 3. In step 4, since the boom is the main load-bearing component, if the connection between the boom and the extension rod is suddenly disconnected, the steel cable of the electric hoist becomes the main load-bearing component, and the steel cable is subjected to increased force and becomes longer, which can easily cause the electric hoist to be impacted and damaged; if the main truss system of the boom and the lower chord hanging basket is to be fixed first, the connection between the boom and the extension rod still needs to be disconnected first, so as to connect the upper connector to the upper end of the boom;

[0040] In this solution, the bottom basket system of the upper-chord basket is transferred to the lower-chord basket without disconnecting the boom and the extension rod, and this function is achieved through a specially designed extension connector. The extension connector can connect the boom and the extension rod, and can also serve as a nut and a pad to support the lower-chord basket.

[0041] Specifically, in this solution, since the front crossbeam or the rear crossbeam is composed of two I-beams, when welding the front crossbeam, the hanger is located between the two I-beams, so that the hanger passes through the front crossbeam or the rear crossbeam without disconnecting the hanger and the extension rod; then, the extension connector is rotated to move the extension connector downward until the conversion pad at the lower end of the extension connector is supported on the front crossbeam or the rear crossbeam of the lower chord hanging basket. At this time, the hanger and the extension rod are still connected through the extension connector, and the conversion of the load-bearing part is realized in advance. At this time, if the connection between the hanger and the extension rod is disconnected, the electric hoist or other parts that can bear force will not be greatly impacted due to the conversion of the load-bearing part.

[0042] The extension connector in this solution is not a simple combination of nuts and pads. The extension connector needs to be long enough to not only connect the suspension rod and the extension rod at the same time, but also to move one end downward to allow the conversion pad to contact the front beam or the rear beam while maintaining the connection with the extension rod. Finally, the lower end of the extension rod is disengaged from the extension connector by rotating the extension rod.

[0043] 4. Balance the gravity of the lower chord arch on both sides of the pier through temporary cables, and transfer the load to the pier through the middle of the temporary cables.

[0044] 5. After constructing the upper chord beam section 1# and installing the upper chord hanging basket on the upper chord beam section 1#, the upper chord beam section 1# is in a cantilever state, and the end portion sinks and deforms due to gravity. Therefore, it is necessary to apply a longitudinal temporary prestress on the upper side of the upper chord beam section 1#, and the temporary prestress is used to make the end portion of the upper chord beam section 1# warp to reduce this deformation. After the bracket is erected, the upper chord beam section 1# is no longer in a cantilever state, and the end portion no longer sinks and deforms. Therefore, the temporary prestress is cancelled to prevent the end portion of the upper chord beam section 1# from warping.

[0045] 6. In step 1, mark the connection position between the upper end of the boom and the front beam or rear beam of the upper string hanging basket;

[0046] In step 2, the connection position between the extension rod and the front crossbeam or rear crossbeam of the upper chord hanging basket is also at the positioning mark. When installing the extension rod, a tower crane is used to fix the upper end of the extension rod. At this time, the extension rod remains vertical under the action of gravity. Only when there is no wind, the boom will also remain vertical, and the lower end of the extension rod can be aligned and connected with the upper end of the boom. Then, check whether the boom and the extension rod are in the same straight line, and adjust them in time. Since the connection position between the lower end of the boom and the front cantilever beam or the rear cantilever beam of the bottom basket system remains unchanged, the extension rod and the boom are always kept in a vertical state in a windless state. The force direction in a windless state is always the axial direction of the rod, and there is no eccentric force, thereby ensuring the load-bearing capacity of the extension rod and the boom.

[0047] The higher the height of the bridge pier, the greater the wind load. Since the length of the hanger plus the extension rod is longer, it is more affected by the wind load. The verticality described in this plan can only ensure verticality in a windless state, and it is impossible to be vertical at all times. Therefore, it is impossible to wait until the wind stops to check the verticality every time. It can only ensure that the upper end of the hanger is always in a fixed state so that the verticality remains unchanged.

[0048] In step 4 of the present scheme, before the upper end of the boom and the front crossbeam of the lower line hanging basket are fixed, the boom and the extended boom are always kept connected to prevent the upper end of the boom from changing its verticality due to loss of connection, thereby ensuring the vertical alignment of the central axes of the upper chord hanging basket and the lower chord hanging basket, and then ensuring the vertical alignment of the central axes of the cast upper chord beam and the lower chord arch, preventing the load of the upper chord beam from generating eccentric force on the lower chord arch.

[0049] 7. In step 2, when the hoisting system drives the bottom rail system to move downward, due to the inclination of the bottom of the lower arch, the longitudinal beam in the bottom rail system needs to be tilted as well, and the template of the lower arch is supported on the longitudinal beam.

[0050] If the two connection positions of the longitudinal beam and the front and rear cantilever beams are fixed, after the longitudinal beam is tilted, the horizontal distance between the front and rear cantilever beams is reduced, resulting in a reduction in the distance between the lower ends of the suspension rods connected to the front and rear cantilever beams, causing the suspension rods to tilt. No matter how the operator makes adjustments, it is impossible to keep all the suspension rods vertical at the same time, which will lead to the following adverse effects:

[0051] a. At this time, the operator cannot judge whether there is wind by whether the suspension rod is vertical, and thus cannot adjust the construction progress of the lower chord arch formwork on the bottom rail system in time according to whether there is wind, thereby reducing the construction accuracy of the lower chord arch formwork.

[0052] b. In step 4, when installing the main truss of the lower chord hanging basket, the two I-beams on the front and rear crossbeams on the main truss clamp the boom to prevent it from shaking. However, when the boom is no longer vertical, the two I-beams clamping the boom will pull the upper end of the boom back to a vertical state, while the lower end of the boom is still tilted, causing the boom to deform and a large internal force to exist, thereby reducing the durability of the boom.

[0053] In this solution, one end of the longitudinal beam is hinged to the front beam, and the other end is slidably connected to the rear beam (sliding can be ensured by applying lubricating oil on the contact surface), so that the horizontal distance between the front beam and the rear beam will not change when the longitudinal beam is tilted, and the suspension rod can still remain vertical under the action of gravity;

[0054] For adverse effect a, the operator can judge whether there is wind by whether the hanger is vertical, thereby ensuring the construction accuracy of the lower chord arch formwork; for adverse effect b, the hanger can be prevented from generating internal force, thereby ensuring the durability of the hanger.

[0055] 8. Regarding effect 7, during the process of adjusting the inclination of the longitudinal beam, if the friction increases and the sliding is abnormal due to insufficient lubricating oil on the contact surface between the longitudinal beam and the rear cantilever beam, or the friction increases and the rotation is abnormal due to rust at the hinge position between the longitudinal beam and the front cantilever beam, or the concrete falls on the connection position between the longitudinal beam and the front cantilever beam or the rear cantilever beam during the previous concrete pouring, the hanger cannot remain vertical. At this time, by clamping the hanger with the two I-beams that form the front cantilever beam or the rear cantilever beam, a reaction force can be provided for the longitudinal beam to overcome the friction; when the hanger connection position is near the end of the I-beam, the end of the I-beam is easily deformed due to the cantilever effect, and the distance between the two I-beams is easily enlarged when the hanger is tilted, and the I-beam cannot clamp the hanger, so that the hanger cannot remain vertical; and this solution uses a limit bolt to limit the distance between the two I-beams, thereby ensuring that the two I-beams can clamp the hanger and the distance is not enlarged as much as possible. BRIEF DESCRIPTION OF THE DRAWINGS

[0056] Figure 1 It is a schematic diagram of the overall structure of Example 1;

[0057] Figure 2 It is a three-dimensional axonometric view of the upper hanging basket of Example 1;

[0058] Figure 3 It is a three-dimensional axonometric diagram when the suspension system and bottom basket system of the upper hanging basket of Example 1 are transferred to the lower hanging basket;

[0059] Figure 4 for Figure 3 A in the enlarged view;

[0060] Figure 5 is a perspective view of the extension connector of Example 1;

[0061] Figure 6 This is a schematic diagram of the structure of step 1 of Example 2;

[0062] Figure 7 This is a schematic diagram of the structure of step 2 of Example 2;

[0063] Figure 8 This is a schematic diagram of the structure of step 3 of Example 2;

[0064] Fig. 9 This is a schematic diagram of the structure of step 4 of Example 2;

[0065] Fig.10 This is a schematic diagram of the structure of step 5 of Example 2;

[0066] Fig.11 This is a schematic diagram of the structure of step 6 of Example 2;

[0067] Fig.12 This is a schematic diagram of the conversion pad in the state of step 4.2 of Example 3;

[0068] Fig.13 Schematic diagram of point P in Example 3. DETAILED DESCRIPTION

[0069] The following is further described in detail through specific implementation methods:

[0070] The figure marks in the drawings of the specification include: pier 1, upper chord beam 2, upper chord beam 0# section 20, upper chord beam 1# section 21, closing section 22, lower chord arch 3, lower chord arch 0# section 30, lower chord arch 1# section 31, lower chord arch 2# section 32, lower chord arch 3# section 33, upper chord hanging basket 41, lower chord hanging basket 42, walking system 50, main truss 51, front cross beam 52, rear cross beam 53, front cantilever beam 61, rear cantilever beam 62, longitudinal beam 63, connecting block 64, rotating shaft 65, electric hoist 7, upper connecting piece 81, upper nut 811, upper pad 812, extension connecting piece 82, conversion pad 83, strip bolt hole 831, limit bolt 832, hanger rod 84, extension rod 85, bracket 9, temporary buckle cable 10.

[0071] Example 1

[0072] Example 1 is basically as Figure 1-Figure 5 As shown: With lifting function hanging basket, it is suitable for arch-beam combination bridges; arch-beam combination bridges such as Figure 1 As shown in FIG. 1 , with the center line of pier 1 as the axis of symmetry, both sides of pier 1 are constructed synchronously and symmetrically. Take the segment on the right side of pier 1 as an example: the segment includes an upper chord beam 2 and a lower chord arch 3. The left end of the upper chord beam 2 and the left arch foot of the lower chord arch 3 are both connected to pier 1. The right end of the upper chord beam 2 and the arch top of the lower chord arch 3 are closed. Figure 1 As shown, the upper chord beam 2 and the lower chord arch 3 are both divided into 13 sections for casting, wherein the thirteenth section is the closing section 22 of the upper chord beam 2 and the lower chord arch 3. The upper chord beam 0# section 20 is above the pier 1, and the upper chord beam 1# section 21 and the upper chord beam 2# section 22 are respectively from near to far from the upper chord beam 0# section 20, and so on; the lower chord arch 0# section 30 is cast together with the pier 1 on both sides of the pier 1, and the lower chord arch 0# section 31 and the lower chord arch 2# section 32 are respectively from near to far from the lower chord arch 0# section 30, and so on; the purpose of casting the lower chord arch 0# section 30 and the pier 1 together is to reserve it in advance so as to be connected with the lower chord arch 1# section 31; a number of temporary cables 10 are set on the pier 1, and the temporary cables 10 all pass through the pier 1, and the two ends of the temporary cables 10 are respectively anchored in the lower chord arch 3 on both sides of the pier 1, and from the lower chord arch 2# section 32, each segment is cast and a temporary cable 10 is constructed;

[0073] The upper chord beam 2 and the lower chord arch 3 are constructed by using a hanging basket with a lifting function, which is cantilevered from the top of the pier 1 to both sides. The hanging basket with a lifting function includes an upper chord hanging basket 41 and a lower chord hanging basket 42. The upper chord hanging basket 41 and the lower chord hanging basket 42 both include a walking system 50, a main girder system, a suspension system and a bottom basket system. The walking system 50 is installed on the upper surface of the upper chord beam 2 or the lower chord arch 3. The main girder system is installed on the walking system 50 and extends in the direction of the cantilever end. The upper end of the suspension system is detachably connected to the main girder system, and the lower end of the suspension system is connected to the bottom basket system. The bottom basket system serves as a supporting platform to bear the construction load. In this solution, the walking system 50 and the main girder system of the hanging basket with a lifting function are the same as those in the prior art. The focus of this embodiment is that the lifting function is given to the upper chord hanging basket 41 through the lifting system, so that the bottom basket system can move downward, so that the upper chord hanging basket 41 and the lower chord hanging basket 42 can alternately use the suspension system and the bottom basket system.

[0074] like Figure 2 As shown, the main truss system of the upper chord hanging basket 41 and the lower chord hanging basket 42 both include a prismatic main truss 51, a front crossbeam 52 is welded to the front end of the main truss 51, and a rear crossbeam 53 is welded to the middle of the main truss 51. The front crossbeam 52 and the rear crossbeam 53 are both formed by combining two parallel I-beams, and a gap is left between the two parallel I-beams; Figure 4 As shown, the main truss systems of the upper chord cradle 41 and the lower chord cradle 42 differ in that the slopes of the bottoms of the main trusses 51 are different to accommodate walking on the upper chord beam 2 and the lower chord arch 3, respectively.

[0075] The bottom basket system of the upper chord hanging basket 41 includes a front cantilever beam 61 and a rear cantilever beam 62. The front cantilever beam 61 is located directly below the front cross beam 52, and the rear cantilever beam 62 is located directly below the rear cross beam 53. Two longitudinal beams 63 are arranged between the front cantilever beam 61 and the rear cantilever beam 62. The longitudinal beam 63 can provide support for the formwork of the lower chord arch 3. The front cantilever beam 61 and the rear cantilever beam 62 are both formed by a combination of two parallel I-beams, and a gap is left between the two parallel I-beams. Two hinged units are arranged on the front cantilever beam 61, and each hinged unit includes two connecting blocks 64. The two connecting blocks 64 are welded to the front cross beam 52. The left end of the longitudinal beam 63 is slidably supported on the rear cantilever beam 62. A rotating shaft 65 is arranged at the right end of the longitudinal beam 63. The rotating shaft 65 passes through the right end of the longitudinal beam 63 and the two connecting blocks 64 at the same time and is rotatably connected to the three. The right end of the longitudinal beam 63 is arranged between the two connecting blocks 64.

[0076] The lifting system includes four lifting devices (not shown in the figure), the lifting devices are winches or electric hoists 7. In this embodiment, the lifting devices are electric hoists 7; the upper ends of the electric hoists 7 are bolted to the main truss system of the upper chord hanging basket 41, specifically located at the two ends of the front crossbeam 52 and the rear crossbeam 53, and the lower ends of the steel cables of the electric hoists 7 are hung at the two ends of the front cantilever beam 61 and the rear cantilever beam 62 respectively;

[0077] The suspension system of the upper chord hanging basket 41 includes four suspension units, and the positions of the suspension units and the electric hoists 7 correspond one to one. The suspension units all include a suspension rod 84 and an extension rod 85. The upper and lower ends of the suspension rod 84 are respectively provided with an upper connecting piece 81 and a lower connecting piece. The upper end of the suspension rod 84 passes through the front cross beam 52 or the rear cross beam 53 of the main truss system of the upper chord hanging basket 41. The upper connecting piece 81 includes an upper nut 811 and an upper pad 812. The upper pad 812 is supported on the front cross beam 52 or the rear cross beam 53 and is passed through by the suspension rod 84. The upper nut 811 is threadedly connected to the upper nut 811. Connect to the upper end of the suspension rod 84, tighten the upper nut 811, the upper nut 811 cooperates with the front cross beam 52 or the rear cross beam 53 to clamp the upper pad 812; similarly, the composition of the lower connecting member is the same as that of the upper nut 811, the lower connecting member includes a lower nut and a lower pad, the lower pad is arranged at the lower side of the front cantilever beam 61 or the rear cantilever beam 62 and is passed through by the lower end of the suspension rod 84, the lower nut is threadedly connected to the lower end of the suspension rod 84, tighten the lower nut, the lower nut cooperates with the front cantilever beam 61 or the rear cantilever beam 62 to clamp the lower pad, thereby providing support for the front cantilever beam 61 or the rear cantilever beam 62;

[0078] like Figure 5 As shown, when the suspension rod 84 is extended, the suspension rod 84 and the extension rod 85 can be connected by an extension connector 82. The extension connector 82 is a sleeve with an internal thread. The lower end of the extension connector 82 is threadedly connected to the upper end of the suspension rod 84. The threads on the suspension rod 84 and the extension rod 85 have the same direction. A conversion pad 83 is welded at the lower end of the extension connector 82, and the upper end of the suspension rod 84 can pass through the conversion pad 83.

[0079] Example 2

[0080] The cast-in-place construction method of arch-beam composite bridge segments based on a hanging basket with lifting function, such as Figure 6-Figure 11 As shown, the construction is carried out based on the hanging basket with lifting function in Example 1, including the following steps:

[0081] Step 1: Figure 6 As shown in the figure, the construction of the bridge pier 1 is completed. During the construction of the bridge pier 1, a horizontally arranged lower chord arch 0# segment 30 is reserved on both sides of the bridge pier 1, an upper chord beam 0# segment 20 is cast on the top of the bridge pier 1, an upper chord hanging basket 41 is installed on the upper chord beam 0# segment 20, and the upper chord hanging basket 41 is used to cast the upper chord beam 1# segment 21, and a longitudinal temporary prestress is applied to the upper side of the upper chord beam 1# segment 21. The method of applying the temporary prestress is as follows: a longitudinal steel strand is buried in the upper part of the upper chord beam 2, and a jack is used to lift the upper chord beam 2 along the longitudinal direction. Figure 6 The longitudinal steel strands are tensioned in the direction of the middle arrow, and the ends of the longitudinal steel strands are anchored with anchors, thereby generating pre-compression stress on the upper part of the upper chord beam 2 to prevent the end of the upper chord beam 2 from sinking; a lifting system is installed on the main truss system of the upper chord hanging basket 41, and the lifting system can drive the bottom basket system to move downward, and remove the connection between the upper end of the suspension system and the main truss system;

[0082] Step 2, remove the upper connector 81 at the upper end of the suspension rod 84, temporarily tie and fix the suspension rod 84 and the steel cable of the electric hoist by wire, and the four electric hoists 7 jointly drive the bottom basket system to move downward, the lower end of the electric hoist on the rear crossbeam 53 is lower than the lower end of the electric hoist 7 on the front crossbeam 52, and the right end of the longitudinal beam 63 rotates around the rotating shaft 65 on the front crossbeam 52, so that the slope of the longitudinal beam 63 of the bottom basket system is the same as the slope of the bottom of the lower chord arch 1# section 31, and the main truss system, the suspension system and the bottom basket system are driven backward by the walking mechanism of the upper chord hanging basket 41, and the bottom basket system is driven to move to the arch foot position of the lower chord arch 3, and the template of the lower chord arch 1# section 31 is set on the bottom basket system, and the bottom basket system and the template of the lower chord arch 1# section 31 are detachably connected by fasteners or other connecting parts, and the template of the lower chord arch 1# section 31 is connected to the lower chord arch 0# section 30;

[0083] like Figure 7 As shown, the upper end of the suspension system is extended to connect the upper end of the suspension system with the main truss system of the upper chord hanging basket: the upper end of the extension rod 85 passes through the main truss system of the upper chord hanging basket 41 and is threadedly connected to the upper connecting piece 81, the upper connecting piece 81 is supported on the main truss system, the extension connecting piece 82 is threadedly connected to the lower end of the extension rod 85, the iron wire on the suspension rod 84 and the steel cable of the electric hoist is removed, and the lower chord arch 1# section 31 is cast with the bottom basket system as support;

[0084] Step 3: Figure 8 As shown, the walking system 50 of the upper chord hanging basket 41 drives the main truss system, the lifting system, the suspension system and the bottom basket system to move forward together, and the lower chord arch 2# section 32 is cast with the bottom basket system as support; the two ends of a temporary cable 10 are respectively anchored in the lower chord arch 2# section 32 on both sides of the pier 1;

[0085] Step 4: Fig. 9 As shown, the walking system 50 and the main truss system of the lower chord hanging basket 42 are installed on the lower chord arch 1# segment 31 and 2# segment, the main truss system of the lower chord hanging basket 42 is connected to the upper end of the suspension system of the upper chord hanging basket 41, and the suspension system and the bottom basket system of the upper chord hanging basket 41 are converted into the suspension system and the bottom basket system of the lower chord hanging basket 42;

[0086] The method for converting the suspension system and bottom basket system of the upper hanging basket 41 into the suspension system and bottom basket system of the lower hanging basket 42 is as follows:

[0087] Step 4.1, during the installation of the main truss system of the lower chord hanging basket 42, the suspension rod 84 of the upper chord hanging basket 41 is passed through the front cross beam 52 or the rear cross beam 53 of the lower chord hanging basket 42. Since the front cross beam 52 or the rear cross beam 53 is composed of two I-beams, when welding the front cross beam 52, the suspension rod 84 is located between the two I-beams, so that the suspension rod 84 can pass through the front cross beam 52 or the rear cross beam 53 without disconnecting the suspension rod 84 and the extension rod 85;

[0088] The upper end of the electric hoist 7 is bolted to the front crossbeam 52 or the rear crossbeam 53 of the lower string hanging basket 42, and the lower end of the electric hoist 7 is hung on the front cantilever beam 61 or the rear cantilever beam 62 of the upper line hanging basket;

[0089] Step 4.2: Figure 5 As shown, rotate the extension connector 82 to move it downward so that the conversion pad 83 at the lower end of the extension connector 82 is supported on the main truss system of the lower chord hanging basket 42, remove the upper connector 81 at the upper end of the extension rod 85, rotate the extension rod 85 to disengage the lower end of the extension rod 85 from the extension connector 82, and remove the extension rod 85 and the electric hoist 7.

[0090] Step 5: Fig.10 As shown, the lower chord arch section 3# 33 is cast, and the two ends of a temporary cable 10 are respectively anchored in the lower chord arch section 3# 33 on both sides of the pier 1; the upper chord hanging basket 41 is removed, and brackets 9 are set up on the lower chord arch section 1# 31 and the lower chord arch section 2# 32 as support for the upper chord beam 2, and the temporary prestress applied to the upper chord beam section 1# 21 is removed, that is, the anchors at the ends of the longitudinal steel strands are removed, and the upper chord beam section 2# 22 is cast;

[0091] Step 6: Fig.11 As shown, repeat step 5, the upper chord beam 2 lags behind the lower chord arch 32 segments and advances the construction synchronously until the pouring reaches Figure 1 The closed section 22 of the upper chord beam 2 and the lower chord arch 3 shown is the 13# section of the upper chord beam 2 and the lower chord arch 3 .

[0092] Example 3

[0093] Embodiment 3 is based on embodiment 2: four strip-shaped bolt holes 831 are opened on the conversion pad 83, and a limiting bolt 832 can be installed in each bolt hole;

[0094] In step 4.2, the conversion pad 83 is supported on the front crossbeam 52 or the rear crossbeam 53 of the main truss system of the lower chord hanging basket 42, and four limit bolts 832 are installed on the conversion pad 83. Taking the front crossbeam 52 as an example, Fig.12 As shown, four limit bolts 832 are evenly distributed and fit on both sides of the front cross beam 52, so as to limit the distance between the two I-beams constituting the front cross beam 52. The limit bolts 832 need to be fixed in the strip bolt holes 831 in cooperation with nuts. When limiting the distance between the two I-beams by the limit bolts 832, the size of the nuts needs to be considered.

[0095] The effect of Example 3 is as follows Fig.13As shown in the figure, the weight of the formwork of the lower chord arch 3, the loads generated by the concrete and various parts will be transmitted to the longitudinal beam 63. Since the longitudinal beam 63 and the front cantilever beam 61 are hinged, most of the load of the longitudinal beam 63 is transmitted to the front cantilever beam 61 through the rotating shaft 65. If only the rotating shaft 65 is considered to bear most of the load, the strength of the rotating shaft 65 is often difficult to bear. In turn, this embodiment also needs to consider the direct contact point P between the longitudinal beam 63 and the front cantilever beam 61. When the longitudinal beam 63 rotates to a certain angle, the load of the longitudinal beam 63 is transmitted to the longitudinal beam 63 through the point P. However, at this time, the longitudinal beam 63 generates a pressure perpendicular to the length direction of the longitudinal beam 63 on the front cantilever beam 61 (the direction of the arrow in the figure), thereby driving the lower end of the suspension rod 84 to move to the right through the front cantilever beam 61, thereby driving the suspension rod 84 to tilt. The greater the pressure change, the greater the back and forth swing. In this solution, by setting a limit bolt 832, the upper end of the suspension rod 84 is clamped through the front cross beam 52 of the lower chord hanging basket 42 to limit the tilt of the suspension rod 84, thereby reducing this swing and ensuring construction safety.

[0096] The above is only an embodiment of the present invention, and the common knowledge such as the known specific technical solutions and / or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, without departing from the technical solution of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.

Claims

1. A cast-in-place construction method for arch-beam composite bridge segments based on a hanging basket with a lifting function, characterized in that: The arch-beam composite bridge includes an upper chord beam and a lower chord arch. One end of the upper chord beam and the arch foot of the lower chord arch are connected to the bridge pier, and the other end of the upper chord beam is closed with the arch top of the lower chord arch. The upper chord beam and the lower chord arch are cast in several sections. The arch-beam composite bridge adopts hanging basket construction, which is cantilevered from the top of the pier to both sides. The hanging basket is divided into upper chord hanging basket and lower chord hanging basket. Both upper chord hanging basket and lower chord hanging basket include walking system, main truss system, suspension system and bottom basket system. The walking system is installed on the upper surface of the upper chord beam or the lower chord arch. The main truss system is installed on the walking system and extends to the cantilever end. The upper end of the suspension system is detachably connected to the main truss system, and the lower end of the suspension system is connected to the bottom basket system. The bottom basket system serves as a supporting platform to bear the construction load. The following steps are involved: Step 1: Complete the construction of the bridge piers, cast the 0# section of the upper chord beam on the top of the piers, install the upper chord hanging basket on the 0# section of the upper chord beam, use the upper chord hanging basket to cast the 1# section of the upper chord beam, install the lifting system on the main truss system of the upper chord hanging basket, the lifting system can drive the bottom basket system to move downward, and remove the connection between the upper end of the suspension system and the main truss system; Step 2: The lifting system drives the bottom basket system to move downward to the arch foot of the lower chord arch, and the upper end of the suspension system is extended to connect the upper end of the suspension system with the main truss system of the upper chord hanging basket, and the lower chord arch 1# section is cast with the bottom basket system as support; Step 3: The walking system of the upper chord hanging basket drives the main truss system, the lifting system, the suspension system and the bottom basket system to move forward together, and the lower chord arch section 2# is cast with the bottom basket system as support; Step 4: Install the walking system and main truss system of the lower chord hanging basket on the lower chord arch sections 1# and 2#, connect the main truss system of the lower chord hanging basket with the upper end of the suspension system of the upper chord hanging basket, and convert the suspension system and bottom basket system of the upper chord hanging basket into the suspension system and bottom basket system of the lower chord hanging basket; Step 5: Cast the lower chord arch section 3#, remove the upper chord hanging basket, set up brackets on the lower chord arch sections 1# and 2# as support for the upper chord beam, and cast the upper chord beam section 2#; Step 6: Repeat step 5 until the upper chord beam and the lower chord arch are cast to the closed position; The lifting system includes several electric hoists; In step 1, during the construction of the bridge pier, a horizontally set lower chord arch 0# section is reserved, the upper ends of the electric hoists are connected to the main truss system of the upper chord hanging basket, and the lower ends of the electric hoists are hung on the bottom basket system; In step 2, during the process of the electric hoist driving the bottom basket system to move downward, the upper end of the suspension system is temporarily fixed on the steel cable of the electric hoist; after the electric hoist drives the bottom basket system to move downward, a template of the lower chord arch section 1# is set up on the bottom basket system, the bottom basket system and the template of the lower chord arch section 1# are detachably connected, and the template of the lower chord arch section 1# is connected to the lower chord arch section 0#; The suspension system of the upper chord hanging basket includes a plurality of suspension units, each of which includes a suspension rod and an extension rod. The upper and lower ends of the suspension rod are respectively provided with an upper connecting piece and a lower connecting piece. The upper end of the suspension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connecting piece. The upper connecting piece is supported on the main truss system. In step 2, the upper connector is removed, and the steel cables of the boom and the electric hoist are temporarily fixed by iron wire. The electric hoist drives the bottom basket system to move downward, and the upper end of the extension rod passes through the main truss system of the upper chord hanging basket and is threadedly connected to the upper connector. The upper connector is supported on the main truss system, and the extension connector is threadedly connected at the lower end of the extension rod. The lower end of the extension connector is threadedly connected to the upper end of the boom, and the iron wire on the steel cables of the boom and the electric hoist is removed; The thread directions of the suspension rod and the extension rod are the same, and a conversion pad is welded at the lower end of the extension connector, and the upper end of the suspension rod can pass through the conversion pad; the main truss system of the upper chord hanging basket and the lower chord hanging basket both include a main truss, and the main truss is provided with a front crossbeam and a rear crossbeam, and the front crossbeam or the rear crossbeam is composed of two parallel I-beams, and the distance between the two I-beams is less than the width of the conversion pad; the bottom basket system of the upper chord hanging basket includes a front cantilever beam and a rear cantilever beam, and a plurality of longitudinal beams are provided between the front cantilever beam and the rear cantilever beam; In step 4, the method of converting the suspension system and bottom basket system of the upper string hanging basket into the suspension system and bottom basket system of the lower string hanging basket is as follows: Step 4.1, during the installation of the main truss system of the lower chord hanging basket, make the suspension rod of the upper chord hanging basket pass through the front beam or rear beam of the lower chord hanging basket, hang the upper end of the electric hoist on the front beam or rear beam, and hang the lower end of the electric hoist on the front cantilever beam or rear cantilever beam; Step 4.2, rotate the extension connector so that the conversion pad at the lower end of the extension connector is supported on the main truss system of the lower chord hanging basket, remove the upper connector at the upper end of the extension rod, rotate the extension rod to separate the lower end of the extension rod from the extension connector, and remove the extension rod and the electric hoist.

2. The cast-in-place construction method for arch-beam composite bridge segments based on a hanging basket with a lifting function according to claim 1 is characterized in that: One ends of the plurality of longitudinal beams are hinged to the front cantilever beam, and the rear cantilever beam is provided with a plurality of horizontally arranged support tubes, and the other ends of the longitudinal beams are supported on the support tubes, and the other ends of the longitudinal beams can slide on the support tubes.

3. The cast-in-place construction method for arch-beam composite bridge segments based on a hanging basket with a lifting function according to claim 2 is characterized in that: There are four strip-shaped bolt holes on the conversion pad, and a limit bolt can be installed in each bolt hole; In step 4.2, the conversion pad is supported on the front beam or rear beam of the main truss system of the lower chord hanging basket, and four limit bolts are installed on the conversion pad. The four limit bolts are evenly distributed and fit on both sides of the front beam or rear beam, thereby limiting the distance between the two I-beams constituting the front beam or rear beam.

4. The cast-in-place construction method for arch-beam composite bridge segments based on a hanging basket with a lifting function according to claim 2 is characterized in that: Taking the center line of the pier as the axis of symmetry, the upper chord beam and the lower chord arch on both sides of the pier are constructed synchronously and symmetrically; a number of temporary cables are set on the pier, and the temporary cables all pass through the pier. The two ends of the temporary cables are anchored in the lower chord arch on both sides of the pier. Starting from the 2# section of the lower chord arch, each section is cast and a temporary cable is constructed; In step 3, two ends of a temporary cable are anchored in the 2# section of the lower chord arch on both sides of the bridge pier; In step five, the two ends of a temporary cable are anchored in the 3# section of the lower chord arch on both sides of the pier.

5. The cast-in-place construction method for arch-beam composite bridge segments based on a hanging basket with a lifting function according to claim 4 is characterized in that: In step 1, a temporary longitudinal prestress is applied to the upper side of the upper chord beam 1# segment; In step five, after the support is erected, the temporary prestress applied to the upper chord beam section 1# is removed.