A horizontal reactor for dry desulfurization

By installing a powder spraying section, a Venturi section and a mass transfer section in the dry desulfurization horizontal reactor, the three-stage forced adsorption reaction of flue gas is realized, which solves the problem of limited equipment layout space, improves desulfurization efficiency and reduces Desulfurizer ratio, suitable for low sulfur content flue gas treatment.

CN118477472BActive Publication Date: 2024-10-18BEIJING LIDEHENG ENVIRONMENTAL PROTECTION ENG CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202410926454.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-11
Publication Date
2024-10-18
Estimated Expiration
2044-07-11

AI Technical Summary

Technical Problem

The existing dry desulfurization process in low-sulfur flue gas treatment is limited in equipment layout and cannot meet the flue layout of sufficient length, resulting in insufficient reaction time of the desulfurization agent and affecting the desulfurization efficiency.

Method used

A dry desulfurization horizontal reactor is designed. By arranging a powder spraying section, a Venturi section and a mass transfer section in sequence in the reactor shell, a three-stage forced adsorption reaction of flue gas is realized, which overcomes the limitation of equipment layout space. question. The powder spraying part sprays powdered desulfurizer along the reactor. The Venturi section realizes the second stage adsorption through the tapering throat and gradually expanding tube. The mass transfer part realizes the third stage adsorption by generating vortex motion through the mass transfer blades.

Benefits of technology

This design increases the probability of the reaction between the desulfurizer and the flue gas, makes up for the problem of insufficient design length of the site flue, improves the reaction efficiency, reduces the desulfurizer ratio, achieves the goal of saving resources, and is suitable for technical transformation projects, reaction efficiency It can reach more than 85%.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118477472B_ABST
    Figure CN118477472B_ABST
Patent Text Reader

Abstract

The present application relates to a dry desulfurization horizontal reactor, comprising: a reactor shell is arranged horizontally, the front end is arranged as the reactor inlet, and the rear end is arranged as the reactor outlet; a powder spraying part, a venturi section and a mass transfer part are arranged in sequence inside; the powder spraying part is arranged at a position close to the reactor inlet, and is used to spray powdered desulfurizer along the conveying direction of the flue gas in the reactor shell to realize the adsorption reaction of the first stage of the flue gas; the venturi section is arranged in the middle of the reactor shell to realize the adsorption reaction of the second stage of the flue gas; the mass transfer part is arranged at a position close to the reactor outlet, and is used to change the motion trajectory of the mixed flue gas and generate eddy motion to realize the adsorption reaction of the third stage of the flue gas. The dry desulfurization horizontal reactor of the present application is compactly designed and more suitable for technical transformation projects. The reaction efficiency can be increased to more than 85%, which can make up for the disadvantage that the design length of the flue on the site cannot meet the reaction time, improve the reaction probability, reduce the desulfurizer ratio, and achieve the expected goal of saving resources.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of flue gas treatment, and in particular to a horizontal dry desulfurization reactor. Background Art

[0002] With the increasingly stringent emission indicators for flue gas from hot blast furnaces in steel plants, coke ovens in coking plants, and gas-fired power plants, many desulfurization processes have emerged for low-sulfur flue gas, mainly wet desulfurization processes, dry desulfurization processes, semi-dry desulfurization processes, etc. These processes are endless and have many problems, such as the excessive energy loss of wet desulfurization processes and semi-dry desulfurization processes for low-sulfur flue gas and the inability to achieve energy conservation, so dry desulfurization processes have become the best choice.

[0003] Currently, the two most widely used dry desulfurization processes are sodium-based dry desulfurization and calcium-based dry desulfurization. These two desulfurization processes have strict time limits on the reaction time of the desulfurizer and require the arrangement of flue ducts of sufficient length for the reaction. However, most technical transformation projects of flue gas desulfurization projects such as hot blast furnaces, coke ovens in coking plants, and gas-fired power plants are limited in the equipment layout site and environment, and cannot meet the requirements of flue duct layout of sufficient length.

[0004] Therefore, there is an urgent need to provide a dry desulfurization horizontal reactor to solve the above-mentioned technical problems. Summary of the invention

[0005] Based on this, a dry desulfurization horizontal reactor is provided, which is compactly designed under the premise of improving the reaction probability of the desulfurizer and the flue gas, thereby overcoming the problem of limited equipment layout space.

[0006] On the one hand, a dry desulfurization horizontal reactor is provided, comprising: a reactor shell, wherein the reactor shell is arranged horizontally, the front end of the reactor shell is arranged as a reactor inlet, and the rear end of the reactor shell is arranged as a reactor outlet; a powder spraying part, a venturi section and a mass transfer part are sequentially arranged inside the reactor shell; the powder spraying part is arranged at a position close to the reactor inlet, and is used for uniformly spraying powdered desulfurizer along the conveying direction of the flue gas in the reactor shell, so as to realize the first stage adsorption reaction of the flue gas; the venturi section is arranged in the middle part of the reactor shell, so as to realize the second stage adsorption reaction of the flue gas; the mass transfer part is arranged at a position close to the reactor outlet, and is used for changing the motion trajectory of the mixed flue gas and generating vortex motion, so as to realize the third stage adsorption reaction of the flue gas.

[0007] A preferred solution is that the powder spraying part includes a rotating nozzle, which is provided with a powder inlet and a powder outlet; the powder inlet is rotatably connected to the desulfurizer delivery pipeline; the rotating nozzle is arranged to rotate around the horizontal axis of the reactor shell; the powder outlet is provided with at least two, and at least two of the powder outlets are respectively located on both sides of the powder inlet around the horizontal axis of the reactor shell.

[0008] A preferred solution is that the rotary nozzle includes a rotating joint, a reducing pipe and an elbow; one end of the rotating joint is set as the powder inlet and the other end is set as the installation port; two reducing pipes are set, and the two reducing pipes are symmetrically arranged on the installation port with the horizontal axis of the rotating joint as the center, and each of the reducing pipes is respectively interconnected with the rotating joint; the elbow is connected to one end of the reducing pipe away from the rotating joint, and the end of the elbow away from the reducing pipe is the powder outlet.

[0009] A preferred solution is that the end with a larger diameter in the variable diameter pipe is connected to the rotary joint, and the end with a smaller diameter is connected to the elbow.

[0010] A preferred solution is that the powder spraying part includes a powder spraying pipe, which extends vertically into the reactor shell and is provided with a plurality of nozzles; the nozzles spray powdered desulfurizer in the flow direction of the flue gas; the front end of the powder spraying pipe is provided with diffusion heads corresponding to the positions of the nozzles at intervals; the diffusion heads are arranged in a conical shape, and the cone of the diffusion head corresponds to the nozzle.

[0011] A preferred solution is that an air balancing plate is further provided in the reactor shell, and a plurality of air balancing holes are evenly opened on the air balancing plate; the air balancing plate is arranged between the powder spraying part and the Venturi section; and the diameter of the air balancing holes is 150-250 mm.

[0012] A preferred solution is that the Venturi section includes a convergent pipe, a throat pipe and a divergent pipe connected in sequence;

[0013] The convergent tube is configured as a reducer, one end of the convergent tube close to the powder spraying part is configured as a flaring port, and the other end is configured as a contracting port; a first sealing plate is provided at the connection between the throat and the convergent tube, and a second sealing plate is provided at the connection between the divergent tube; a plurality of air equalizing tubes connecting the first sealing plate and the second sealing plate are provided inside the throat, and the air equalizing tubes connect the convergent tube and the divergent tube; the divergent tube is configured as a reducer, one end of the divergent tube connected to the throat is configured as a contracting port, and the other end is configured as a flaring port.

[0014] A preferred solution is that the mass transfer section includes a mass transfer pipe section, a mass transfer component and an end plate; the mass transfer pipe section is extended along the conveying direction of the flue gas, and the end plates are respectively arranged at both ends of the mass transfer pipe section, and the end plates are respectively provided with channels; the mass transfer component is arranged in the mass transfer pipe section, and the front and rear ends are respectively connected to the channels of the end plates.

[0015] A preferred solution is that the channels are distributed in a circular array on the end plate; the mass transfer component is arranged to correspond to the channels; the mass transfer component includes a cylinder, a circular ring, a mounting shaft and mass transfer blades; the front end of the cylinder is connected to the end plate located at the front end of the mass transfer pipe section, and the rear end of the cylinder is connected to the end plate located at the rear end of the mass transfer pipe section; the circular ring fits the inner circumferential wall of the cylinder and is arranged to rotate; the mounting shaft is arranged at the center of the circular ring; the mass transfer blades are arranged in a plurality of pieces, and the plurality of mass transfer blades are distributed in a circular array around the outer circumference of the mounting shaft, and the inclination angle of the mass transfer blades is set to 25°.

[0016] A preferred solution is that an ash hopper is also provided on the reactor shell; the ash hopper is connected to the reactor shell after the position of the mass transfer part.

[0017] Beneficial effects:

[0018] First: The dry desulfurization horizontal reactor in this embodiment is mainly used in flue gas desulfurization systems with low sulfur dioxide content such as hot blast furnaces in steel plants, coke ovens in coking plants, and gas-fired power plants. It is installed between the flue gas inlet and the bag filter. The horizontal reactor is compact in design and can be arranged on the ground or in the air according to the site conditions. It is not restricted by the site and environment. A powder spraying section, a venturi section, and a mass transfer section are sequentially arranged inside the reactor shell. Through the arrangement of these three components, the flue gas undergoes three stages of forced adsorption reactions and can achieve the designed desulfurization emission indicators. Therefore, the present invention is compactly designed on the premise of increasing the reaction probability of the desulfurizer and the flue gas, which can make up for the disadvantage that the design length of the flue in the site cannot meet the reaction time, while increasing the reaction probability, reducing the desulfurizer ratio, and achieving the expected goal of saving resources;

[0019] Second: In this embodiment, the minimum flow rate of the horizontal dry desulfurization reactor at the reactor inlet is 10m / s, and the circular tube design does not have dead corners, which prevents the desulfurizer from accumulating in the reactor, and does not involve power and other energy losses. The maintenance rate is almost zero, and it can be manufactured as a whole in the prefabrication site and then transported and installed to achieve modular installation;

[0020] Third: The overall resistance of the horizontal dry desulfurization reactor in this embodiment is 800Pa, which has little effect on the energy consumption of the entire desulfurization system, and the compact design is more suitable for technical transformation projects, and the reaction efficiency can be increased to more than 85%. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 This is a schematic diagram of the structure of the horizontal dry desulfurization reactor in Example 1;

[0022] Figure 2 For along Figure 1 The aa line section view in;

[0023] Figure 3 It is a partial schematic diagram showing the rotating nozzle in the first embodiment;

[0024] Figure 4 is a schematic diagram showing the rotation direction of the rotating nozzle in the first embodiment;

[0025] Figure 5 For along Figure 1 The bb line section view;

[0026] Figure 6 It is a schematic diagram showing the structure of the Venturi section in the first embodiment;

[0027] Figure 7 For along Figure 1 The cc line section view;

[0028] Figure 8 For along Figure 1 dd line section view;

[0029] Fig. 9 is a cross-sectional schematic diagram showing the mass transfer component in the first embodiment;

[0030] Fig.10 It is a structural schematic diagram showing the connection relationship between the mass transfer blades, the mounting shaft and the circular ring in the mass transfer component in the first embodiment;

[0031] Fig.11 This is a schematic diagram of the structure of the horizontal dry desulfurization reactor in the second embodiment.

[0032] Figure numerals: 1. reactor shell; 11. reactor inlet; 12. reactor outlet; 2. powder spraying part; 21. rotating nozzle; 211. powder inlet; 212. powder outlet; 213. rotating joint; 214. reducing pipe; 215. elbow; 22. powder spraying pipe; 221. nozzle; 3. venturi section; 31. convergent pipe; 32. throat; 321. first sealing plate; 322. second sealing plate; 323. gas equalizing pipe; 33. divergent pipe; 4. mass transfer part; 41. mass transfer pipe section; 42. mass transfer component; 421. cylinder; 422. ring; 423. mounting shaft; 424. mass transfer blade; 43. end plate; 5. desulfurizer delivery pipeline; 6. gas equalizing orifice plate; 61. gas equalizing orifice; 7. ash hopper; 8. L-shaped bracket; 9. connecting rod; 101. diffuser head; 102. support frame. DETAILED DESCRIPTION

[0033] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0034] It should be noted that the illustrations provided in this embodiment only illustrate the basic concept of the present application in a schematic manner, and therefore the drawings only show components related to the present application rather than being drawn according to the number, shape and size of components in actual implementation. In actual implementation, the type, quantity and proportion of each component may be changed arbitrarily, and the component layout may also be more complicated.

[0035] The structures, proportions, sizes, etc. illustrated in the drawings of this specification are only used to match the contents disclosed in the specification so as to facilitate understanding and reading by persons familiar with this technology. They are not used to limit the conditions under which this application can be implemented, and therefore have no substantive technical significance. Any structural modification, change in proportion or adjustment of size, without affecting the effects and purposes that can be achieved by this application, should still fall within the scope of the technical contents disclosed in this application.

[0036] The directions or positional relationships indicated by the terms "upper", "lower", "left", "right", "middle", "longitudinal", "lateral", "horizontal", "inner", "outer", "radial", "circumferential" and the like in this specification are based on the directions or positional relationships shown in the drawings and are only for the convenience of simplifying the description. They do not indicate or imply that the devices or elements referred to must have a specific direction, be constructed and operate in a specific direction, and therefore cannot be understood as limiting the present application. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0037] The embodiment of the present application provides a horizontal dry desulfurization reactor, which is mainly used in sodium-based dry desulfurization and calcium-based dry desulfurization processes in the fields of hot air flue gas treatment in steel plants, coke oven flue gas treatment in coking plants, and flue gas treatment in gas power plants. It is installed between the flue gas inlet and the bag filter. By compactly designing the horizontal dry desulfurization reactor, and the compact design is more suitable for technical transformation projects, the reaction efficiency can be increased to more than 85%, which can make up for the disadvantage that the design length of the site flue cannot meet the reaction time, while increasing the reaction probability, reducing the desulfurizer ratio, and achieving the expected goal of saving resources.

[0038] Embodiment 1

[0039] The following is a detailed description of a dry desulfurization horizontal reactor provided in this embodiment. Please refer to Figure 1As shown, it includes: a reactor shell 1, a powder spraying part 2, a venturi section 3 and a mass transfer part 4, the powder spraying part 2, the venturi section 3 and the mass transfer part 4 are sequentially arranged inside the reactor shell 1, the reactor shell 1 is arranged horizontally, and the front end of the reactor shell 1 is arranged as a reactor inlet 11, the flue gas flow rate at the reactor inlet 11 is designed to be 10-12m / s, and the rear end of the reactor shell 1 is arranged as a reactor outlet 12, so that the flue gas enters from the reactor inlet 11, and flows out from the reactor outlet 12 after three adsorption reactions of the powder spraying part 2, the venturi section 3 and the mass transfer part 4 in sequence; the powder spraying part 2 is arranged at a position close to the reactor inlet 11, and is used for uniformly spraying the powdered desulfurizer along the conveying direction of the flue gas in the reactor shell 1, so as to realize the first stage adsorption reaction of the flue gas; the venturi section 3 is arranged at the middle position of the reactor shell 1, so as to realize the second stage adsorption reaction of the flue gas; the mass transfer part 4 is arranged at a position close to the reactor outlet 12, and is used for changing the motion trajectory of the mixed flue gas and generating vortex motion, so as to realize the third stage adsorption reaction of the flue gas.

[0040] The dry desulfurization horizontal reactor in this embodiment is compactly designed under the premise of increasing the reaction probability between the desulfurizer and the flue gas, thereby overcoming the situation where the equipment layout is limited. The dry desulfurization horizontal reactor is mainly composed of a reactor shell 1, a powder spraying part 2, a venturi section 3 and a mass transfer part 4. The powdered desulfurizer is transported to the powder spraying part 2 through the desulfurizer delivery pipeline 5, and then the powdered desulfurizer is sprayed to the reactor inlet 11 near the front end of the reactor shell 1 by the powder spraying part 2, so that the flue gas and the powdered desulfurizer are mixed to form a first-stage adsorption reaction; the powdered desulfurizer follows the driving force of the flue gas through the venturi section 3 to perform the second-stage adsorption reaction of the flue gas, and accelerates the flow rate of the flue gas. When the accelerated flue gas passes through the mass transfer part 4, the movement trajectory of the mixed flue gas is changed through the mass transfer part 4 and a first-stage adsorption reaction is formed. The vortex motion is generated to realize the adsorption reaction of the third stage of the flue gas, so that the horizontal reactor in this embodiment can produce three adsorption reactions, improve the desulfurization efficiency, reduce the ratio of desulfurizer to pollutants, and adopt a horizontal arrangement in which the powder spraying section 2, the venturi section 3 and the mass transfer section 4 are arranged in sequence, so that a compact arrangement can be achieved. In the case of a compact arrangement, it can be arranged on the ground according to the site conditions, or it can be arranged in the air, without being restricted by the arrangement site and environment. The compact dry desulfurization horizontal reactor is more suitable for technical transformation projects, and the reaction efficiency can be increased to more than 85%. It can also make up for the disadvantage that the design length of the flue on the site cannot meet the reaction time, while increasing the reaction probability, reducing the desulfurization agent ratio, and achieving the expected goal of saving resources.

[0041] Please refer to Figure 1-Figure 4As shown, in the present embodiment, it should be noted that one end of the desulfurizer delivery pipeline 5 is connected to the bin for storing the desulfurizer, and the other end of the desulfurizer delivery pipeline 5 extends vertically from the side of the reactor shell 1 into the reactor shell 1, and the desulfurizer delivery pipeline 5 is located at one end of the reactor shell 1 and is bent in the direction of the reactor outlet 12, and the bent desulfurizer delivery pipeline 5 is coaxially arranged with the horizontal axis of the reactor shell 1.

[0042] The powder spraying part 2 includes a rotating nozzle 21, which is provided with a powder inlet 211 and a powder outlet 212. The powder inlet 211 is rotatably connected to the outlet end of the desulfurizing agent delivery pipeline 5 and the two are arranged coaxially. The rotating nozzle 21 is arranged to rotate around the horizontal axis of the reactor shell 1; at least two powder outlets 212 are arranged, and at least two powder outlets 212 are respectively located on both sides of the powder inlet 211 around the horizontal axis of the reactor shell 1, and the two powder outlets 212 are arranged on the same vertical section. On the circumferential surface of the surface, in this way, the desulfurizer delivery pipeline 5 sprays the powdered desulfurizer into the rotating nozzle 21 through the powder inlet 211, and the rotating nozzle 21 dynamically sprays the powdered desulfurizer from the two powder outlets 212 when rotating, and the two powder outlets 212 spray the powdered desulfurizer while rotating with the rotating nozzle 21. In this way, the sprayed powdered desulfurizer can be evenly sprayed within the circumference of the same vertical cross-section, thereby improving the degree of mixing with the flue gas.

[0043] Since the powdered desulfurizer is sprayed from the outside, it has a certain kinetic energy. In this embodiment, the kinetic energy of the powdered desulfurizer is utilized and the rotating nozzle 21 is uniquely designed to realize the automatic rotation of the rotating nozzle 21. The rotating nozzle 21 is made of 316L stainless steel or 2205 alloy, specifically:

[0044] The rotating nozzle 21 includes a rotating joint 213, a reducing pipe 214 and an elbow 215; one end of the rotating joint 213 is rotatably connected to the outlet end of the desulfurizing agent delivery pipe 5, so this end of the rotating joint 213 is set as the powder inlet 211, the rotating joint 213 and the horizontal axis of the reactor shell 1 are coaxially arranged, and the other end of the rotating joint 213 is set as the installation port. There are two reducing pipes 214, and the two reducing pipes 214 are symmetrically arranged on the installation port with the horizontal axis of the rotating joint 213 as the center, and each reducing pipe 214 is connected to the rotating joint 213 respectively. With this arrangement, the powdered desulfurizing agent coming from the rotating joint 213 can be evenly divided into two when passing through the two reducing pipes 214, and enter the interior of the reducing pipe 214 respectively. The elbow 215 is connected to one end of the variable diameter pipe 214 away from the rotating joint 213, and the end of the elbow 215 away from the variable diameter pipe 214 is set as the powder outlet 212, wherein the end with a larger diameter in the variable diameter pipe 214 is connected to the rotating joint 213, and the end with a smaller diameter is connected to the elbow 215. Thus, by setting the elbow 215 with a certain angle, when the gas passes through the variable diameter pipe 214, due to the large diameter at the front end and the small diameter at the rear end, it is easy to form static pressure, and then it is ejected from the powder outlet 212 of the elbow 215 to generate kinetic energy, so that the rotating nozzle 21 automatically rotates, and the powdered desulfurizer ejected from the powder outlet 212 is better distributed on the cross section of the reactor inlet 11. In order to better realize the automatic rotation of the rotating nozzle 21, the bending directions of the two elbows 215 are set exactly oppositely, so that the rotating nozzle 21 can rotate in the same direction clockwise or counterclockwise when the powder outlets 212 of the two elbows 215 eject kinetic energy. Preferably, the end surface of the powder outlet 212 of the curved pipe 215 is arranged as an inclined surface, and the inclined surface is arranged to facilitate the powdered desulfurization agent sprayed out of the powder outlet 212 to drive the rotating nozzle 21 to rotate.

[0045] Please refer to Figure 1 , Figure 3 As shown, in one installation method, an L-shaped bracket 8 is installed on the desulfurizer delivery pipeline 5, and the horizontal section of the L-shaped bracket 8 is connected to the desulfurizer delivery pipeline 5, and the vertical section of the L-shaped bracket 8 is arranged at intervals in front of the rotating joint 213. A connecting rod 9 is installed on the vertical section of the L-shaped bracket 8, and the connecting rod 9 and the rotating joint 213 are arranged coaxially, and one end of the connecting rod 9 is rotatably connected to the vertical section of the L-shaped bracket 8 through a bearing, and the other end of the connecting rod 9 is connected to the intersection of two reducing pipes 214, so that the rotation stability of the rotating nozzle 21 can be improved by the arrangement of the connecting rod 9, and the powder inlet 211 of the rotating joint 213 and the outlet end of the desulfurizer delivery pipeline 5 are also rotatably connected by bearings, and the bearings all adopt high-sealing and high-wear-resistant bearings to ensure their service life, and the L-shaped bracket 8 and the desulfurizer delivery pipeline 5 are welded into one, so there is no need to arrange other brackets inside the reactor shell 1.

[0046] Please refer to Figure 1 , Figure 5 As shown, in this embodiment, it is also necessary to explain that an air-distributing plate 6 is also provided in the reactor shell 1, and the air-distributing plate 6 and the reactor shell 1 are coaxially arranged, and the outer peripheral surface of the air-distributing plate 6 and the inner peripheral surface of the reactor shell 1 are fitted, and the air-distributing plate 6 is arranged between the powder spraying part 2 and the venturi section 3, and a plurality of air-distributing holes 61 are evenly provided on the air-distributing plate 6, and the diameter of the air-distributing hole 61 is selected between 150-250 mm, and the specific size is determined according to the cross-sectional size of the reactor inlet 11 and the smooth simulation result. In this embodiment, the function of the air-distributing plate 6 is to form a certain resistance drop, slow down the gas flow rate, avoid flue gas deviation, and make the flue gas evenly distributed on the cross-sectional area of ​​the reactor inlet 11, so as to promote the adsorption of sulfur dioxide in the flue gas by the desulfurizer, thereby forming the first stage of forced adsorption reaction.

[0047] Please refer to Figure 1 , Figure 6 as well as Figure 7 As shown, in this embodiment, it is also necessary to explain that the venturi section 3 includes a gradually contracting pipe 31, a throat pipe 32 and a gradually expanding pipe 33 connected in sequence, the gradually contracting pipe 31 is set as a reducing section, one end of the gradually contracting pipe 31 close to the powder spraying part 2 is set as a flaring port, and the other end is set as a contracting port. The main function of such a setting is that the smoke can slowly transition to avoid the generation of rapids and dead corners; a first sealing plate 321 is provided at the connection between the throat pipe 32 and the gradually contracting pipe 31, and a second sealing plate 322 is provided at the connection between the throat pipe 32 and the gradually expanding pipe 33. Several gas-distributing pipes 323 are provided inside to connect the first sealing plate 321 and the second sealing plate 322. The gas-distributing pipes 323 are connected to the gradually contracting pipe 31 and the gradually expanding pipe 33. The function of the throat pipe 32 is to reduce the volume of the flue gas, generate Brownian motion, squeeze the distance between the desulfurizer particles and the pollutant molecules, accelerate the movement speed of the desulfurizer particles and the pollutant molecules, increase the probability of collision between the desulfurizer and the pollutant, accelerate the speed of sulfur dioxide adsorption on the surface of the desulfurizer, improve the reaction efficiency, and shorten the reaction time. This process is the second stage adsorption reaction. The gradually expanding pipe 33 is set as a reducing pipe, and one end of the gradually expanding pipe 33 connected to the throat pipe 32 is set as a contraction port, and the other end is set as an expansion port. After the flue gas passes through the throat pipe 32, it enters the gradually expanding pipe 33. The flue gas flow rate in the gradually expanding pipe 33 steadily recovers the original flow rate of 10-12m / s, creating favorable conditions for the forced reaction of the mass transfer part 4 in the next stage.

[0048] Please refer to Figure 1 , Figure 8As shown, in this embodiment, it is also necessary to explain that the mass transfer section 4 includes a mass transfer pipe section 41, a mass transfer component 42 and an end plate 43. The mass transfer pipe section 41 is extended along the conveying direction of the flue gas, and the end plates 43 are respectively arranged at both ends of the mass transfer pipe section 41. The end plates 43 are provided with a plurality of channels, and the plurality of channels are distributed in a circumferential array. The mass transfer component 42 is arranged in the mass transfer pipe section 41, and the front and rear ends are respectively connected to the channels of the end plates 43. The mass transfer component 42 is arranged to correspond to the channels one by one, that is, one mass transfer component 42 corresponds to one channel.

[0049] Please refer to Figure 8 , Fig. 9 as well as Fig.10 As shown, in one achievable manner, the mass transfer component 42 includes a cylinder 421, a ring 422, a mounting shaft 423 and a mass transfer blade 424; the front end of the cylinder 421 is connected to the end plate 43 located at the front end of the mass transfer pipe section 41, and the rear end of the cylinder 421 is connected to the end plate 43 located at the rear end of the mass transfer pipe section 41; the ring 422 fits the inner circumferential wall of the cylinder 421 and is arranged to rotate; the mounting shaft 423 is arranged at the center of the ring 422 and is arranged parallel to the axis of the reactor shell 1; the mass transfer blade 424 is arranged as a plurality of pieces, and the plurality of mass transfer blades 424 are arranged in a circular array around the outer circumference of the mounting shaft 423, one end of the mass transfer blade 424 is installed on the mounting shaft 423, and the other end is installed on the inner wall surface of the ring 422, and the inclination angle of the mass transfer blade 424 is set to 25°.

[0050] In this embodiment, the length of the mass transfer pipe section 41 is generally selected to be 700-850 mm, and the selection basis is determined by the sulfur dioxide content in the flue gas and the ratio of sulfur to the desulfurizer. The number of mass transfer blades 424 in the mass transfer component 42 and the angle value of the mass transfer blades 424 are used to calculate the efficiency and resistance of the mass transfer component 42. After calculation, it is found that when the resistance reduction is 550-600 Pa and the efficiency is 65%, the number of mass transfer blades 424 in the mass transfer component 42 is 12, the angle of the mass transfer blades 424 is 25°, and the flow rate is 22-25 m / s.

[0051] The principle of the mass transfer section 4 is that when the mixed flue gas passes through the mass transfer component 42, the mass transfer blades 424 force it to change its motion trajectory to produce eddy motion, thereby accelerating the Brownian motion of the desulfurizer particles and pollutants. The pollutants continuously collide with the surface of the desulfurizer particles and are adsorbed to produce a mass transfer effect, which greatly increases the reaction probability of the desulfurizer, thereby improving the reaction efficiency. This process is the third stage adsorption reaction, and the flue gas undergoes three stages of forced adsorption reaction to achieve the designed desulfurization emission indicators.

[0052] Please refer to Figure 1As shown, in this embodiment, it should be noted that an ash hopper 7 is also provided on the reactor shell 1, and the ash hopper 7 is connected to the reactor shell 1 after the mass transfer part 4. The main purpose of providing the ash hopper 7 at the end of the reactor shell 1 is to prevent the accumulation of powdered desulfurizer when the flue gas volume is unstable and the flow rate fluctuates, and to be able to process it together with the desulfurization by-products collected by the bag filter.

[0053] The implementation principle of this embodiment: The present invention is compactly designed under the premise of improving the reaction probability of the desulfurizer and the flue gas, so as to overcome the situation where the equipment layout is limited. The dry desulfurization horizontal reactor in the present invention is mainly composed of a reactor shell 1, a powder spraying part 2, a venturi section 3 and a mass transfer part 4. The powdered desulfurizer is transported to the powder spraying part 2 through the desulfurizer delivery pipeline 5, and is rotated and sprayed by the rotating nozzle 21 in the powder spraying part 2. The powdered desulfurizer sprayed by the rotating nozzle 21 is better distributed on the cross section of the reactor inlet 11, which improves the mixing of the flue gas and the powdered desulfurizer, forming the first stage of suction. Attachment reaction; then through the throat 32 of the Venturi section 3, the volume of the flue gas is rapidly reduced to produce a second stage forced reaction, the accelerated flue gas passes through the mass transfer section 4 at the rear end, and is forced to change its motion trajectory by the mass transfer component 42 in the mass transfer section 4 to produce eddy motion, thereby accelerating the Brownian motion of the desulfurizer particles and pollutants. The pollutants continuously collide on the surface of the desulfurizer particles and are adsorbed to produce a mass transfer effect, thereby producing a third stage forced reaction. The dry desulfurization horizontal reactor can produce three adsorption reactions, thereby improving the desulfurization efficiency, reducing the ratio of desulfurizer to pollutants, and achieving the designed desulfurization emission indicators.

[0054] Embodiment 2

[0055] The difference between the second embodiment and the first embodiment is that: Fig.11 As shown, the powder spraying part 2 includes a powder spraying pipe 22, which extends vertically from the side of the reactor shell 1 into the reactor shell 1, and a plurality of nozzles 221 are provided on the powder spraying pipe 22, which spray powdered desulfurizer in the flow direction of the flue gas. The design of the powder spraying pipe 22 determines the number according to the size of the flue cross-section. Generally speaking, it is better to set one powder spraying pipe 22 for every 1 to 1.5 m2.

[0056] The front end of the powder spraying pipe 22 is spaced apart with diffusion heads 101 corresponding in position and number to the nozzles 221. The diffusion heads 101 are arranged in a conical shape, and the top angle of the cone is 90°. The nozzle 221 coincides with the center line of the cone of the diffusion head 101, and the cone of the diffusion head 101 corresponds to the nozzle 221. The function of the diffusion head 101 is to disperse the powdered desulfurizer sprayed out of the powder spraying pipe 22 and evenly diffuse it to the entire cross-section of the flue, so as to improve the mixing of the flue gas and the desulfurizer, fully integrate the desulfurizer and the flue gas, and increase the probability of sulfur dioxide being adsorbed by the desulfurizer.

[0057] A support frame 102 for supporting and installing the diffusion head 101 is arranged in the reactor shell 1 . The support frame 102 is vertically arranged in the reactor shell 1 and is arranged at the front end of the powder spraying tube 22 .

[0058] The powdered desulfurizer is sprayed to the reactor inlet 11 through the powder spraying pipe 22, and diffuses evenly to the flue cross section through the conical diffuser 101 along with the driving force of the flue gas, thereby improving the mixing of the flue gas and the powdered desulfurizer and forming the first stage adsorption reaction.

[0059] The technical features of the above embodiments may be combined arbitrarily. To make the description concise, not all possible combinations of the technical features in the above embodiments are described. However, as long as there is no contradiction in the combination of these technical features, they should be considered to be within the scope of this specification.

[0060] The above-described embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be construed as limiting the scope of the patent application. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application. Therefore, the protection scope of the patent application shall be subject to the attached claims.

Claims

1. A horizontal dry desulfurization reactor, characterized in that: include: A reactor shell (1), wherein the reactor shell (1) is arranged in a horizontal position, the front end of the reactor shell (1) is arranged as a reactor inlet (11), and the rear end of the reactor shell (1) is arranged as a reactor outlet (12); A powder spraying section (2), a venturi section (3) and a mass transfer section (4) are sequentially arranged inside the reactor shell (1); The powder spraying part (2) is arranged at a position close to the reactor inlet (11) and is used to uniformly spray the powdered desulfurizing agent along the conveying direction of the flue gas in the reactor shell (1) to achieve the first stage adsorption reaction of the flue gas; A venturi section (3), wherein the venturi section (3) is arranged in the middle of the reactor shell (1) to realize a second-stage adsorption reaction of the flue gas; A mass transfer section (4), the mass transfer section (4) being arranged at a position close to the reactor outlet (12) and used for changing the motion trajectory of the mixed flue gas and generating eddy motion, so as to realize the third stage adsorption reaction of the flue gas; A uniform air hole plate (6) is also provided in the reactor shell (1), and a plurality of uniform air holes (61) are evenly provided on the uniform air hole plate (6); The air-distributing orifice plate (6) is arranged between the powder spraying section (2) and the Venturi section (3); The powder spraying part (2) comprises a rotating nozzle (21), and the rotating nozzle (21) is provided with a powder inlet (211) and a powder outlet (212); The powder inlet (211) is rotatably connected to the desulfurizing agent delivery pipeline (5); The rotating nozzle (21) is arranged to rotate around the horizontal axis of the reactor shell (1); The powder outlets (212) are at least two in number, and the at least two powder outlets (212) are located on both sides of the powder inlet (211) with the horizontal axis of the reactor shell (1) as the center. The rotating nozzle (21) comprises a rotating joint (213), a reducing pipe (214) and a curved pipe (215); One end of the rotary joint (213) is configured as the powder inlet (211), and the other end is configured as a mounting port; The variable diameter pipes (214) are provided in two numbers, and the two variable diameter pipes (214) are symmetrically arranged on the installation opening with the horizontal axis of the rotating joint (213) as the center, and each of the variable diameter pipes (214) is respectively communicated with the rotating joint (213); The curved pipe (215) is connected to an end of the reducing pipe (214) away from the rotating joint (213), and the end of the curved pipe (215) away from the reducing pipe (214) is the powder outlet (212); The end with a larger diameter in the variable diameter pipe (214) is connected to the rotating joint (213), and the end with a smaller diameter is connected to the curved pipe (215).

2. The dry desulfurization horizontal reactor according to claim 1, characterized in that: The diameter of the air balancing hole (61) is 150-250 mm.

3. The dry desulfurization horizontal reactor according to claim 1, characterized in that: The mass transfer section (4) comprises a mass transfer pipe section (41), a mass transfer component (42) and an end plate (43); The mass transfer pipe section (41) is extended along the conveying direction of the smoke, and the end plates (43) are respectively arranged at both ends of the mass transfer pipe section (41), and the end plates (43) are provided with channels; The mass transfer component (42) is arranged in the mass transfer pipe section (41), and the front and rear ends are respectively connected to the channels of the end plate (43).

4. The dry desulfurization horizontal reactor according to claim 3, characterized in that: The channels are distributed in a circumferential array on the end plate (43); The mass transfer component (42) is arranged to correspond to the channel; The mass transfer component (42) comprises a cylinder (421), a ring (422), a mounting shaft (423) and a mass transfer blade (424); The front end of the cylinder (421) is connected to the end plate (43) located at the front end of the mass transfer pipe section (41), and the rear end of the cylinder (421) is connected to the end plate (43) located at the rear end of the mass transfer pipe section (41); The circular ring (422) is fitted to the inner wall of the cylinder (421) and is arranged to rotate. The installation shaft (423) is arranged at the center of the circular ring (422); The mass transfer blades (424) are arranged in a plurality of pieces, and the plurality of mass transfer blades (424) are distributed in a circular array around the outer circumference of the installation shaft (423), and the inclination angle of the mass transfer blades (424) is set to 25°.

5. The dry desulfurization horizontal reactor according to claim 1, characterized in that: The reactor shell (1) is also provided with an ash hopper (7); The ash hopper (7) is connected to the reactor shell (1) after the mass transfer section (4).

Citation Information

Patent Citations

  • Semi-dry type fume cleaning method and device

    CN101288825A

  • Comprehensive treatment device for tail gas of heating furnace

    CN113019095A

  • A dry desulfurization, denitrification and dust removal integrated system

    CN114931850A

  • Dry desulfurization spray gun

    CN221207496U