Maximum power tracking control method and device for photovoltaic optimizer

The photovoltaic optimizer maximum power tracking control method through real-time sampling and mode switching solves the problem of power loss in the photovoltaic power generation system, achieves stable and efficient maximum power point tracking, and improves photovoltaic power generation efficiency.

CN118502537BActive Publication Date: 2024-10-29浙江华昱欣科技有限公司
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202410956248.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-17
Publication Date
2024-10-29
Estimated Expiration
2044-07-17

AI Technical Summary

Technical Problem

The existing maximum power point tracking (MPPT) control method based on the perturbation observation method causes the operating point of the photovoltaic cell to oscillate in the photovoltaic power generation system, resulting in power loss and failure to maintain the maximum power point stably.

Method used

A maximum power tracking control method of a photovoltaic optimizer is used to determine the current working mode by sampling electrical parameters in real time, and perform disturbance tracking in re-tracking mode. When the target power point is reached, it switches to the voltage stabilization mode until the preset is met. Exit the condition and switch back to re-tracking mode to reduce power loss.

Benefits of technology

It achieves rapid response to changes in the P-V curve, quickly re-tracks to the new maximum power point, reduces power loss, and improves the efficiency of photovoltaic power generation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118502537B_ABST
    Figure CN118502537B_ABST
Patent Text Reader

Abstract

The present application relates to a maximum power tracking control method and device for a photovoltaic optimizer. The method obtains the input power of the photovoltaic optimizer input terminal by real-time sampling and calculation; determines the current working mode of the photovoltaic optimizer and executes the control task corresponding to the current working mode; when the working mode is the re-tracking mode, performs disturbance tracking on the input power, and after obtaining the maximum power tracking point, switches the working mode to the voltage stabilization mode until the preset exit condition is met, and switches the working mode from the voltage stabilization mode back to the re-tracking mode, thereby solving the problem of power loss caused by the output power of the photovoltaic panel oscillating near the maximum power point, achieving rapid response to the change of the P-V curve, quickly re-tracking to the new maximum power point, and switching to the "voltage stabilization mode" after reaching the maximum power point, thereby reducing power loss and improving the efficiency of photovoltaic power generation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of photovoltaic power generation technology, and in particular to a maximum power tracking control method and device for a photovoltaic optimizer. Background Art

[0002] In photovoltaic power generation systems, the utilization rate of photovoltaic cells is not only related to the internal characteristics of the photovoltaic array, but also affected by external conditions (such as light intensity, load and temperature). Under different external conditions, the photovoltaic array can operate at different and unique maximum power points. In order to ensure that the photovoltaic power generation system can always maintain maximum power tracking at any light intensity and temperature, it is usually necessary to perform maximum power point tracking (MPPT) on the photovoltaic cells.

[0003] At present, the commonly used MPPT methods include constant voltage tracking method, short-circuit current proportional coefficient method, disturbance observation method, conductance increment method, fuzzy control method and artificial neural network control method, etc. Among them, the disturbance observation method is the most commonly used MPPT control method. This method starts to disturb the PV voltage value from an initial value close to the maximum power point voltage, measures its power change, and compares it with the power value before the disturbance. If the power value increases, it means that the disturbance direction is correct and continues to disturb in the same direction. If the power value decreases, it disturbs in the opposite direction.

[0004] However, the above method requires continuous perturbation and observation, and it cannot stabilize the working point of the photovoltaic cell at the maximum power point. The existing MPPT control method based on the perturbation observation method often oscillates near the maximum power point, resulting in large power loss. Summary of the invention

[0005] In this embodiment, a maximum power point tracking control method and device for a photovoltaic optimizer are provided to solve the problem of large power loss in the related art.

[0006] In a first aspect, a maximum power point tracking control method for a photovoltaic optimizer is provided in this embodiment. The method is applied to a photovoltaic maximum power point tracking system. The system includes a photovoltaic panel, a photovoltaic optimizer, and a load. The input end of the photovoltaic optimizer is connected to the photovoltaic panel, and the output end of the photovoltaic optimizer is connected to the load. The method includes:

[0007] Sampling electrical parameters of a photovoltaic optimizer in real time, and calculating input power at an input end of the photovoltaic optimizer in real time based on the electrical parameters;

[0008] Determine the current working mode of the photovoltaic optimizer, and execute the control task corresponding to the current working mode; wherein the working mode includes a re-tracking mode and a voltage stabilization mode; when the working mode is the re-tracking mode, perform disturbance tracking on the input power, and after obtaining the target power point, switch the working mode to the voltage stabilization mode, until a preset exit condition is met, and then switch the working mode from the voltage stabilization mode back to the re-tracking mode;

[0009] After the current control task is completed, a pulse signal is generated based on the updated duty cycle to control the photovoltaic optimizer.

[0010] In some embodiments, when the working mode is the re-tracking mode, disturbance tracking is performed on the input power, and after obtaining the target power point, the working mode is switched to the voltage stabilization mode, including:

[0011] When the working mode is a re-tracking mode, performing disturbance processing to adjust the duty cycle;

[0012] After the disturbance processing, recalculating the input power;

[0013] If the input power after the disturbance processing meets the preset tracking condition, the duty cycle and the maximum power tracking point are updated based on the result of the disturbance processing, and the current control task is terminated;

[0014] If the input power after the disturbance processing does not meet the tracking condition, the flag bit of the working mode is modified to the voltage stabilization mode, and the current control task is terminated.

[0015] In some embodiments, if the input power after the disturbance processing meets the preset tracking condition, the duty cycle and the maximum power tracking point are updated based on the result of the disturbance processing, and after the current control task is terminated, the method further includes:

[0016] Comparing the electrical parameters after the disturbance processing with the electrical parameters before the disturbance processing to obtain a comparison result;

[0017] If the comparison result does not meet the preset parameter change requirement, a static tracking state is entered. In the static tracking state, the voltage and duty cycle of the input terminal are kept unchanged until a preset exit condition is reached, and then the static tracking state is exited.

[0018] In some embodiments, when the working mode is the re-tracking mode, performing disturbance processing to adjust the duty cycle includes:

[0019] When the working mode is the re-tracking mode, performing a first disturbance based on the first disturbance direction to obtain an adjusted first duty cycle;

[0020] Based on the first duty cycle, determining whether the first disturbance direction is a correct disturbance direction;

[0021] If the first disturbance direction is a correct disturbance direction, performing a secondary disturbance based on the first disturbance direction to obtain an adjusted second duty cycle;

[0022] If the first disturbance direction is not the correct disturbance direction, a secondary disturbance is performed based on a second disturbance direction to obtain an adjusted second duty cycle, wherein the second disturbance direction is opposite to the first disturbance direction;

[0023] According to the obtained correct disturbance direction, the disturbance is continued and the duty cycle is updated until the input power no longer increases.

[0024] In some embodiments, executing the control task corresponding to the current working mode further includes:

[0025] When the working mode is the voltage stabilization mode, determining whether the number of voltage stabilization times reaches a preset number;

[0026] If the voltage stabilization times do not reach the preset times, voltage stabilization is performed on the currently sampled input voltage, the voltage stabilization times are recorded once, and the current control task is terminated;

[0027] If the voltage stabilization times have reached the preset times, the working mode is modified to the re-tracking mode, and the current control task is terminated.

[0028] In some embodiments, executing the control task corresponding to the current working mode further includes:

[0029] When the working mode is the power-on direct mode, determining whether the current duty cycle reaches a preset maximum value;

[0030] If the current duty cycle has reached the preset maximum value, it is determined whether the load side has entered the working state;

[0031] If the load side has entered the working state, when the input power no longer increases, the flag bit of the working mode is modified to the voltage stabilization mode, and the current control task is terminated.

[0032] In some embodiments, executing the control task corresponding to the current working mode further includes:

[0033] When the working mode is the power-on tracking mode, determining whether the current input power is greater than a reference power; the reference power is the power of the input end sampled when the previous round of the control task is completed;

[0034] If the input power is greater than the reference power, the maximum power tracking point is updated based on the current input power, and after increasing the current duty cycle, the current control task is terminated;

[0035] If the input power is not greater than the preset reference power, the flag bit of the working mode is modified to the voltage stabilization mode, and the current control task is terminated.

[0036] In some embodiments, after the current control task is finished, a pulse signal is generated based on the updated duty cycle to control the photovoltaic optimizer, including:

[0037] After the current control task is finished, two pulse signals with complementary waveforms are generated based on the updated duty cycle to respectively control the two field effect transistors in the photovoltaic optimizer.

[0038] In a second aspect, a maximum power tracking control device for a photovoltaic optimizer is provided in this embodiment, and the device is applied to a photovoltaic maximum power tracking system, the system comprising a photovoltaic panel, a photovoltaic optimizer and a load, the input end of the photovoltaic optimizer is connected to the photovoltaic panel, and the output end of the photovoltaic optimizer is connected to the load;

[0039] The device comprises:

[0040] A sampling module, used for sampling electrical parameters of the photovoltaic optimizer in real time, and calculating the input power of the input end of the photovoltaic optimizer in real time based on the electrical parameters;

[0041] A power control module, used to determine the current working mode of the photovoltaic optimizer and execute the control task corresponding to the current working mode; wherein the working mode includes a re-tracking mode and a voltage stabilization mode; when the working mode is the re-tracking mode, disturbance tracking is performed for the input power, and after obtaining the target power point, the working mode is switched to the voltage stabilization mode, until a preset exit condition is met, and the working mode is switched from the voltage stabilization mode back to the re-tracking mode;

[0042] The driving module is used to generate a pulse signal based on the updated duty cycle after completing the current control task to control the photovoltaic optimizer.

[0043] In a third aspect, the present application also provides a photovoltaic maximum power tracking system, the system comprising: a photovoltaic panel, a photovoltaic optimizer and a load;

[0044] One end of the photovoltaic optimizer is connected to the photovoltaic panel, and the other end of the photovoltaic optimizer is connected to the load;

[0045] The photovoltaic optimizer is used to execute the steps of the maximum power point tracking control method for the photovoltaic optimizer described in any one of the first aspects.

[0046] In a fourth aspect, the present application further provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the maximum power point tracking control method for the photovoltaic optimizer described in the first aspect is implemented.

[0047] Compared with the related art, the maximum power tracking control method and device of the photovoltaic optimizer provided in this embodiment samples the electrical parameters of the photovoltaic optimizer in real time, and calculates the input power of the input end of the photovoltaic optimizer in real time based on the electrical parameters; determines the current working mode of the photovoltaic optimizer, and executes the control task corresponding to the current working mode; wherein, executing the control task corresponding to the current working mode includes: when the working mode is the re-tracking mode, performing disturbance tracking on the input power, and after obtaining the maximum power tracking point, switching the working mode to the voltage stabilization mode until the preset exit condition is met, and switching the working mode from the voltage stabilization mode back to the re-tracking mode, which solves the problem of power loss caused by the output power of the photovoltaic panel oscillating near the maximum power point, realizes rapid response to changes in the PV curve, quickly re-tracks to the new maximum power point, and switches to the "voltage stabilization mode" after reaching the maximum power point, reducing power loss, thereby improving the efficiency of photovoltaic power generation.

[0048] Details of one or more embodiments of the present application are set forth in the following drawings and description to make other features, objects, and advantages of the present application more readily apparent. BRIEF DESCRIPTION OF THE DRAWINGS

[0049] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:

[0050] Figure 1 A hardware structure block diagram of a terminal of a maximum power tracking control method for a photovoltaic optimizer in one embodiment;

[0051] Figure 2 A schematic diagram of the structure of a photovoltaic maximum power point tracking system in one embodiment;

[0052] Figure 3is a schematic flow chart of a maximum power point tracking control method for a photovoltaic optimizer in one embodiment;

[0053] Figure 4 is a schematic diagram of switching working modes of a photovoltaic optimizer in one embodiment;

[0054] Figure 5 A schematic flow chart of a maximum power point tracking control method for a photovoltaic optimizer in a preferred embodiment;

[0055] Figure 6 1 is a structural block diagram of a maximum power tracking control device for a photovoltaic optimizer in one embodiment.

[0056] Reference numerals: 102, processor; 104, memory; 106, transmission device; 108, input / output device; 21, photovoltaic panel; 22, photovoltaic optimizer; 23, load; 71, sampling module; 72, power control module. DETAILED DESCRIPTION

[0057] In order to more clearly understand the purpose, technical solutions and advantages of the present application, the present application is described and illustrated below in conjunction with the accompanying drawings and embodiments.

[0058] Unless otherwise defined, the technical terms or scientific terms involved in this application shall have the general meaning understood by people with general skills in the technical field to which this application belongs. The words "one", "a", "the", "these" and the like in this application do not indicate a quantitative limitation, and they may be singular or plural. The terms "include", "comprise", "have" and any variants thereof involved in this application are intended to cover non-exclusive inclusions; for example, a process, method and system, product or device comprising a series of steps or modules (units) is not limited to the listed steps or modules (units), but may include unlisted steps or modules (units), or may include other steps or modules (units) inherent to these processes, methods, products or devices. The words "connect", "connected", "coupled" and the like involved in this application are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. The "multiple" involved in this application refers to two or more. "And / or" describes the association relationship of associated objects, indicating that there may be three relationships, for example, "A and / or B" may mean: A exists alone, A and B exist at the same time, and B exists alone. Generally, the character " / " indicates that the objects associated with each other are in an "or" relationship. The terms "first", "second", "third", etc. in this application are only used to distinguish similar objects and do not represent a specific ordering of the objects.

[0059] The method embodiment provided in this embodiment can be executed in a terminal, a computer or a similar computing device. For example, running on a terminal, Figure 1 is a hardware structure block diagram of a terminal of the maximum power tracking control method of the photovoltaic optimizer of this embodiment. Figure 1 As shown, the terminal may include one or more ( Figure 1 Only one is shown in the figure) a processor 102 and a memory 104 for storing data, wherein the processor 102 may include but is not limited to a processing device such as a microprocessor MCU or a programmable logic device FPGA. The above terminal may also include a transmission device 106 and an input and output device 108 for communication functions. It can be understood by those skilled in the art that Figure 1 The structure shown is only for illustration and does not limit the structure of the above terminal. Figure 1 More or fewer components as shown, or with Figure 1 Different configurations shown.

[0060] The memory 104 can be used to store computer programs, for example, software programs and modules of application software, such as the computer program corresponding to the maximum power tracking control method of the photovoltaic optimizer in this embodiment. The processor 102 executes various functional applications and data processing by running the computer program stored in the memory 104, that is, to implement the above method. The memory 104 may include a high-speed random access memory, and may also include a non-volatile memory, such as one or more magnetic storage devices, flash memory, or other non-volatile solid-state memory. In some examples, the memory 104 may further include a memory remotely arranged relative to the processor 102, and these remote memories may be connected to the terminal via a network. Examples of the above-mentioned network include, but are not limited to, the Internet, an intranet, a local area network, a mobile communication network, and combinations thereof.

[0061] The transmission device 106 is used to receive or send data via a network. The above network includes a wireless network provided by the communication provider of the terminal. In one example, the transmission device 106 includes a network adapter (Network Interface Controller, referred to as NIC), which can be connected to other network devices through a base station so as to communicate with the Internet. In one example, the transmission device 106 can be a radio frequency (Radio Frequency, referred to as RF) module, which is used to communicate with the Internet wirelessly.

[0062] In this embodiment, a photovoltaic maximum power point tracking system is provided. Figure 2 This is a schematic diagram of the structure of the photovoltaic maximum power tracking system, see Figure 2The system includes a photovoltaic panel 21, a photovoltaic optimizer 22 and a load 23. One end of the photovoltaic optimizer 22 is connected to the photovoltaic panel 21, and the other end of the photovoltaic optimizer 22 is connected to the load 23. The load 23 is an inverter or a resistor R1 or the like.

[0063] The photovoltaic optimizer 22 is used to execute the steps of the maximum power point tracking control method of the photovoltaic optimizer in any of the following embodiments.

[0064] Specifically, the main power circuit of the photovoltaic optimizer 22 adopts a BUCK circuit, and the BUCK circuit includes a first field effect tube M1, a second field effect tube M2, an inductor L1, a first capacitor C1 and a second capacitor C2. The drain of the first field effect tube M1 is connected to the positive electrode of the photovoltaic panel 21, the source of the first field effect tube M1 is connected to one end of the inductor L1, and the other end of the inductor L1 is connected to one end of the load 23. The second field effect tube M2 is connected between the source of the first field effect tube M1 and the ground wire. The first capacitor C1 is connected between the drain of the first field effect tube M1 and the ground wire. The second capacitor C2 is connected between the other end of the inductor L1 and the ground wire.

[0065] The BUCK circuit further includes a first diode D1 and a second diode D2. The first diode D1 is connected between the drain and the source of the first field effect transistor M1, and the second diode D2 is connected between the drain and the source of the second field effect transistor M2.

[0066] The photovoltaic optimizer 22 also includes a resistor R1 and a third diode D2. The photovoltaic optimizer is grounded through the resistor R1. The cathode of the third diode D2 is connected to one end of the load 23. The anode of the third diode D2 is connected to the other end of the load 23. The other end of the load 23 is connected to the ground wire.

[0067] The working principle of the photovoltaic optimizer 22 is as follows: the first field effect tube M1 and the second field effect tube M2 receive complementary PWM waves and are turned on alternately. 1. When the first field effect tube M1 is turned on and the second field effect tube M2 is turned off, the inductor L1 is charged and the current of the inductor L1 increases. 2. When the first field effect tube M1 is turned off and the second field effect tube M2 is turned on, since the current of the inductor L1 cannot change suddenly, the current supplies power to the load 23, and the current of the inductor L1 decreases. The chip controls the changes in the voltage, current, and power of the photovoltaic panel 21 by controlling the PWM duty cycle.

[0068] In this embodiment, the photovoltaic optimizer 22 accurately controls the on and off of the first field effect transistor M1 and the second field effect transistor M2, and quickly responds to changes in the PV curve, quickly re-tracks to the new maximum power point, and switches to the voltage regulation mode after reaching the maximum power point, thereby reducing power loss and improving the efficiency of photovoltaic power generation.

[0069] Figure 3is a flow chart of the maximum power tracking control method of the photovoltaic optimizer of this embodiment. Figure 3 As shown, the process includes the following steps:

[0070] Step S210 , sampling electrical parameters of the photovoltaic optimizer 22 in real time, and calculating input power at the input end of the photovoltaic optimizer 22 in real time based on the electrical parameters.

[0071] Specifically, the electrical parameters include the current at the input end, the voltage at the input end, the current at the output end, and the voltage at the output end. During the sampling process, the voltage is converted and A / D conversion is performed through the integrated operational amplifier to obtain a 1ms AD sampling value.

[0072] Step S220, determine the current working mode of the photovoltaic optimizer 22, and execute the control task corresponding to the current working mode; wherein, the working mode includes a re-tracking mode and a voltage stabilization mode; when the working mode is the re-tracking mode, disturbance tracking is performed on the input power, and after obtaining the target power point, the working mode is switched to the voltage stabilization mode, until the preset exit condition is met, and the working mode is switched from the voltage stabilization mode back to the re-tracking mode.

[0073] Specifically, Figure 4 As shown, the working modes of the photovoltaic optimizer 22 include a voltage stabilization mode and a re-tracking mode. When the system is started and the input power no longer changes, the photovoltaic optimizer 22 will enter the voltage stabilization mode; when the PV curve changes, it quickly switches to the re-tracking mode, and performs disturbance tracking with a large step size, and switches to the voltage stabilization mode after the maximum power point is reached. The re-tracking mode is applied after the voltage stabilization mode ends and the input voltage changes significantly. Its purpose is to continuously find the latest MPPT point to prevent the maximum power point from changing due to the PV curve. In addition, the power-on mode can also be set to continuously increase the input power after the system is started. The power-on mode can include a power-on direct mode and a power-on tracking mode. The power-on direct mode is used in the scenario where the inverter on the load 23 side has not yet started working. After power-on, the power-on direct mode needs to be maintained before the voltage of the photovoltaic panel 21 can be output to the inverter. The power-on tracking mode is used in the scenario where the optimizer is added to the string system that is already operating normally. In this scenario, the current will continue to increase. In this case, the machine can be directly started to track the MPPT.

[0074] Step S230 , after the current control task is finished, a pulse signal is generated based on the updated duty cycle to control the photovoltaic optimizer 22 .

[0075] In this embodiment, the electrical parameters of the photovoltaic optimizer 22 are sampled in real time, and the input power of the input end of the photovoltaic optimizer 22 is calculated in real time based on the electrical parameters; the current working mode of the photovoltaic optimizer 22 is determined, and the control task corresponding to the current working mode is executed; wherein, the control task corresponding to the current working mode is executed, including: when the working mode is the re-tracking mode, disturbance tracking is performed on the input power, and after the maximum power tracking point is obtained, the working mode is switched to the voltage stabilization mode, until the preset exit condition is met, and the working mode is switched from the voltage stabilization mode to the re-tracking mode, which solves the problem of power loss caused by the output power of the photovoltaic panel 21 oscillating near the maximum power point, and realizes a rapid response to the change of the PV curve, quickly re-tracks to the new maximum power point, and switches to the "voltage stabilization mode" after the maximum power point is reached, thereby reducing power loss and improving the efficiency of photovoltaic power generation.

[0076] In some embodiments, when the working mode is the re-tracking mode, disturbance tracking is performed on the input power, and after the maximum power tracking point is obtained, the working mode is switched to the voltage stabilization mode, including the following steps:

[0077] Step S310: When the working mode is the re-tracking mode, disturbance processing is performed to adjust the duty cycle.

[0078] Step S320, recalculating the input power after the disturbance processing.

[0079] Step S330: if the input power after the disturbance processing meets the preset tracking condition, the duty cycle and the maximum power tracking point are updated based on the result of the disturbance processing, and the current control task is terminated.

[0080] Specifically, the preset tracking condition is set to determine whether the input power increases. If the input power increases, the tracking condition is met, and if the input power does not increase, the tracking condition is not met. To determine whether the input power increases, the input power corresponding to the adjusted duty cycle is compared with the input power corresponding to the duty cycle before the adjustment.

[0081] Step S340: If the input power after the disturbance processing does not meet the tracking condition, the flag of the working mode is modified to the voltage regulation mode, and the current control task is terminated.

[0082] Specifically, after the flag of the working mode is modified to the voltage stabilization mode, in the next round of working mode judgment step, based on the flag set to the voltage stabilization mode, it will be judged to enter the voltage stabilization mode, and the control task corresponding to the voltage stabilization mode will be executed subsequently.

[0083] In this embodiment, when the input power meets the tracking conditions, it means that the disturbance direction is correct. In the next round of working mode judgment, the current working mode will be maintained, and the disturbance processing will continue to search for the latest MPPT point. When the input power does not meet the tracking conditions, it means that the required MPPT point has been tracked, and it can be switched to the voltage stabilization mode to slow down the oscillation, thereby avoiding power loss.

[0084] In some embodiments, if the input power after the disturbance processing meets the preset tracking condition, the duty cycle and the maximum power tracking point are updated based on the result of the disturbance processing, and after the current control task is terminated, the following steps are specifically included:

[0085] Step S360, comparing the electrical parameters after the disturbance processing with the electrical parameters before the disturbance processing to obtain a comparison result.

[0086] Step S370, if the comparison result does not meet the preset parameter change requirement, then enter the static tracking state, in which the voltage and duty cycle of the input terminal are kept unchanged until the preset exit condition is reached, then exit the static tracking state.

[0087] Specifically, after each re-tracking, the input voltage and input power of the current state are compared with those before the disturbance. If the difference in input power is less than 5W, and the difference in input voltage is less than 1V, it is considered that the PV curve has not changed. If this situation occurs after three consecutive re-trackings, the static tracking state is entered, and the target voltage and duty cycle are kept unchanged for 1 minute. If a change in the PV curve is detected, resulting in a significant change in voltage, the subsequent steps are continued to track the maximum power again.

[0088] In this embodiment, two re-tracking modes, dynamic and static, are provided. The static re-tracking mode reduces the number and amplitude of disturbances when the PV curve does not change, thereby improving the static efficiency.

[0089] In some of these embodiments, see Figure 5 Based on the above step S310, when the working mode is the re-tracking mode, disturbance processing is performed to adjust the duty cycle, specifically including the following steps:

[0090] Step S311, when the working mode is the re-tracking mode, performing a first disturbance based on a first disturbance direction to obtain an adjusted first duty cycle.

[0091] Step S312: based on the first duty cycle, determining whether the first disturbance direction is a correct disturbance direction.

[0092] Step S313: If the first disturbance direction is the correct disturbance direction, a secondary disturbance is performed based on the first disturbance direction to obtain an adjusted second duty cycle.

[0093] Step S314: if the first disturbance direction is not the correct disturbance direction, a secondary disturbance is performed based on the second disturbance direction to obtain an adjusted second duty cycle, where the second disturbance direction is opposite to the first disturbance direction.

[0094] Step S315: Continue the disturbance according to the correct disturbance direction obtained, and update the duty cycle until the input power stops increasing.

[0095] Specifically, the first direction can be set to reduce the duty cycle, and the second reverse direction can be set to increase the duty cycle. First, perform the first disturbance (reduce the duty cycle) and determine whether the power increases. If the power increases, it means that the disturbance direction is correct, and continue to reduce the duty cycle and perform a second disturbance; otherwise, it means that the disturbance direction is wrong, and increase the duty cycle instead and perform a second disturbance. Continue to determine whether the power increases. If the power increases, continue to disturb in the direction of the secondary disturbance, and record the current state as the new MPPT point; otherwise, switch to "voltage regulation mode".

[0096] When performing disturbance, illustratively, the disturbance step size is set to 1 / 100 of the duty cycle. A small step size is obtained when the duty cycle is small, and a large step size is obtained when the duty cycle is large. The small duty cycle and large duty cycle here can be understood as: compared with the duty cycle before the change, if the duty cycle after the change is larger than the duty cycle before the change, the duty cycle after the change is considered to be a large duty cycle, otherwise, it is a small duty cycle. Because when the duty cycle is very small, the large step size has too much impact on the photovoltaic optimizer 22 circuit, which may cause the tracking point to "fly around" and get out of control; when the duty cycle is very large, the small step size has too little impact on the photovoltaic optimizer 22 circuit, which may cause the tracking speed to be too slow.

[0097] In this embodiment, rapid tracking can be achieved through disturbances in the first direction and the second direction.

[0098] In some of these embodiments, see Figure 6 Based on the above step S220, executing the control task corresponding to the current working mode also includes the following steps:

[0099] Step S310, when the working mode is the voltage stabilization mode, determine whether the number of voltage stabilization times reaches a preset number.

[0100] Exemplarily, the preset number Stable_Time is set to 50, and when the voltage stabilization number re_MPPT_count≥Stable_Time, it is determined that the preset number is reached.

[0101] Step S320: If the voltage stabilization times do not reach the preset times, voltage stabilization is performed on the currently sampled input voltage, the voltage stabilization times are recorded once, and the current control task is terminated.

[0102] Step S330, if the voltage stabilization times have reached the preset times, the working mode is changed to the re-tracking mode, and the current control task is terminated.

[0103] Specifically, first determine whether the voltage stabilization times have been reached. If the voltage stabilization times have not been reached, the voltage is stabilized using the PID (Proportional-Integral-Derivative) method, and the voltage stabilization times are recorded once; otherwise, switch to the re-tracking mode.

[0104] In this embodiment, the voltage stabilization mode is applied after other modes track the MPPT, and its purpose is to stabilize the voltage for a period of time after each disturbance to avoid excessive oscillation caused by continuous disturbances.

[0105] In some of these embodiments, see Figure 6 Based on the above step S220, executing the control task corresponding to the current working mode also includes the following steps:

[0106] Step S410, when the working mode is the power-on direct mode, determine whether the current duty cycle reaches a preset maximum value.

[0107] Step S420: If the current duty cycle has reached the preset maximum value, it is determined whether the load 23 side enters the working state.

[0108] Step S430, if the load 23 has entered the working state, when the input power no longer increases, the flag of the working mode is modified to the voltage stabilization mode, and the current control task is terminated.

[0109] Specifically, when the load 23 is an inverter, first determine whether the duty cycle has reached the maximum value. If the duty cycle has not reached the maximum value, it means that the optimizer has not reached the direct pass state, and the duty cycle must continue to increase; otherwise, it means that the optimizer has reached the direct pass state, and then determine whether the output current at the output end is greater than 1A. If the output current is greater than 1A, it means that the inverter has started working, and the input power should gradually increase. When the power no longer increases, switch to the "voltage regulation mode"; otherwise, it means that the inverter has not started working and continues to maintain the direct pass state. The working mode of the optimizer initially defaults to the power-on direct pass mode. Because the input end of the optimizer in the string system is connected to the photovoltaic panel 21, and the output end is connected to the inverter, it is necessary to directly pass after power-on to output the voltage of the photovoltaic panel 21 to the inverter so that the inverter can start.

[0110] In this embodiment, the power-on pass-through mode is applied to the scenario where the inverter is connected to the load 23 side and the inverter has not yet started. By judging the current duty cycle and the working status of the load 23 side, power control can be completed quickly and accurately.

[0111] In some embodiments, based on the above step S220, executing the control task corresponding to the current working mode further includes the following steps:

[0112] Step S510, when the working mode is the power-on tracking mode, it is determined whether the current input power is greater than the reference power; the reference power is the power of the input end sampled when the previous round of control tasks is completed.

[0113] Step S520: If the input power is greater than the reference power, the maximum power tracking point is updated based on the current input power, and after increasing the current duty cycle, the current control task is terminated.

[0114] Step S530: If the input power is not greater than the preset reference power, the flag of the working mode is modified to the voltage stabilization mode, and the current control task is terminated.

[0115] Specifically, first determine whether the power has increased. If the power has increased, it means that the maximum power point has not been reached, and the duty cycle needs to be further increased, and the current state is recorded as the new MPPT point; otherwise, it means that the maximum power point has been reached, and it is time to switch to voltage regulation mode. The power-on tracking mode is used in scenarios where an optimizer is added to a string system that is already operating normally. As the optimizer PWM duty cycle increases from 0, the current will gradually increase. In this case, there is no need to achieve direct pass first, and the machine can be started directly to track the MPPT.

[0116] Specifically, the power-on tracking mode can better match the scenario of adding an optimizer to a string system that is already operating normally, thereby completing power control quickly and accurately.

[0117] In some embodiments, after the current control task is finished, a pulse signal is generated based on the updated duty cycle to control the photovoltaic optimizer 22, including:

[0118] After the current control task is finished, two pulse signals with complementary waveforms are generated based on the updated duty cycle to control the two field effect transistors in the photovoltaic optimizer 22 respectively.

[0119] Specifically, the main power circuit of the photovoltaic optimizer 22 adopts a BUCK circuit, and the BUCK circuit includes a first field effect tube M1 and a second field effect tube M2. The first field effect tube M1 is connected in series between the photovoltaic panel 21 and the load 23, and the second field effect tube M2 is connected in parallel between the photovoltaic panel 21 and the load 23. After the perturbation function is completed, the calculated new duty cycle is sent to the PWM drive module, and a PWM wave is sent to the first field effect tube M1 with a new pulse width, and a complementary PWM wave is generated and sent to the second field effect tube M2. The on-off time of the first field effect tube M1 and the second field effect tube M2 in the next cycle are controlled respectively by two complementary waveform pulse signals, so as to control the voltage, current and power of the photovoltaic panel 21 to change according to the current IV and PV curves. The longer the conduction time of the first field effect tube M1 is, the smaller the voltage and the larger the current of the photovoltaic panel 21; conversely, the larger the voltage and the smaller the current of the photovoltaic panel 21.

[0120] In this embodiment, two pulse signals with complementary waveforms are used to control the on and off time of the first field effect transistor M1 and the second field effect transistor M2 in the next cycle, thereby controlling the voltage, current and power of the photovoltaic panel 21 to change according to the target effect, so that the MPPT tracking effect is better.

[0121] The present embodiment is described and illustrated below through a preferred embodiment. Figure 6 The preferred embodiment of the maximum power tracking control method for the photovoltaic optimizer in this embodiment includes the following steps:

[0122] S1, the voltage and current at the input and output ends are converted into voltage and A / D through the integrated operational amplifier to obtain the 1ms AD sampling value and calculate the input power.

[0123] S2, determine the current working mode and perform processing in the corresponding mode, the initial default is "power-on direct mode".

[0124] S3, if S2 is judged as "power-on direct pass mode", first determine whether the duty cycle has reached the maximum value. If the duty cycle has not reached the maximum value, it means that the optimizer has not reached the direct pass state, and the duty cycle must continue to increase; otherwise, it means that the optimizer has reached the direct pass state, and then determine whether the output current is greater than 1A. If the output current is greater than 1A, it means that the inverter has started working, and the input power should gradually increase. When the power no longer increases, switch to "voltage regulation mode"; otherwise, it means that the inverter has not started working and continues to maintain the direct pass state. The working mode of the optimizer is initially defaulted to "power-on direct pass mode". Because the input end of the optimizer in the string system is connected to the photovoltaic panel 21, and the output end is connected to the inverter, it is necessary to directly pass after power-on to output the voltage of the photovoltaic panel 21 to the inverter so that the inverter can start.

[0125] S4, if it is judged as "power-on tracking mode" in S2, first determine whether the power increases. If the power increases, it means that the maximum power point has not been reached, and the duty cycle needs to be further increased, and the current state is recorded as the new MPPT point; otherwise, it means that the maximum power point has been reached, and it is switched to "voltage regulation mode". "Power-on tracking mode" is used in the scenario of adding an optimizer to a string system that is already operating normally. As the optimizer PWM duty cycle increases from 0, the current will gradually increase. In this case, there is no need to achieve direct pass first, and the machine can be directly started to track MPPT.

[0126] S5, if it is judged as "voltage stabilization mode" in S2, first determine whether the voltage stabilization times have been reached. If the voltage stabilization times have not been reached, the voltage is stabilized by the PID method and the voltage stabilization times are recorded once; otherwise, it switches to "re-tracking mode". "Voltage stabilization mode" is applied after tracking MPPT in other modes. Its purpose is to stabilize the voltage for a period of time after each disturbance to avoid excessive oscillation caused by continuous disturbances.

[0127] S6, if it is judged as "re-tracking mode" in S2, the first disturbance is performed (duty cycle is reduced) and it is judged whether the power increases. If the power increases, it means that the disturbance direction is correct, and the duty cycle is continued to be reduced to perform a second disturbance; otherwise, it means that the disturbance direction is wrong, and the duty cycle is increased to perform a second disturbance. Continue to judge whether the power increases. If the power increases, continue to disturb in the direction of the secondary disturbance, and record the current state as the new MPPT point; otherwise, switch to "voltage stabilization mode". The "re-tracking mode" is applied after the "voltage stabilization mode" ends and the voltage of the photovoltaic panel 21 changes significantly. Its purpose is to continuously find the latest MPPT point to prevent the PV curve from changing and not being at the maximum power point.

[0128] S7, when making disturbances in S6, select a small step size when the duty cycle is small, and select a large step size when the duty cycle is large. Because when the duty cycle is very small, the large step size has too much impact on the BUCK circuit, which may cause the tracking point to "fly around" and get out of control; when the duty cycle is very large, the small step size has too little impact on the BUCK circuit, which may cause the tracking speed to be too slow. After each re-tracking, compare the voltage and power in the current state and before the disturbance. If the power difference is less than 5W and the voltage difference is less than 1V, it is considered that the PV curve has not changed. If this situation occurs after three consecutive re-trackings, enter the static MPPT mode, keep the target voltage and duty cycle unchanged, and continue for 1 minute until the PV curve changes and causes a significant change in voltage, and then re-track.

[0129] S8, after completing the processing in S3 / S4 / S5 / S6, the previous power is updated, that is, the current input power is used as the previous power for the next calculation, for comparison and judgment of whether the current input power has changed.

[0130] S9, end the disturbance function, and send the calculated new duty cycle to the PWM drive module, send a PWM wave to the upper MOS tube with a new pulse width, and generate a complementary PWM wave to send to the lower MOS tube.

[0131] S10, the new PWM wave controls the on-off time of the upper and lower MOS tubes of the BUCK circuit in the next cycle, so as to control the voltage, current and power of the photovoltaic panel 21 to change according to the current IV and PV curves. The longer the upper tube is on, the smaller the voltage and the larger the current of the photovoltaic panel 21; conversely, the larger the voltage and the smaller the current of the photovoltaic panel 21.

[0132] It should be noted that the steps shown in the above process or the flowchart in the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although a logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0133] In this embodiment, a maximum power tracking control device for a photovoltaic optimizer is also provided, which is used to implement the above-mentioned embodiments and preferred implementation modes, and will not be repeated hereafter. The terms "module", "unit", "subunit", etc. used below can implement a combination of software and / or hardware of a predetermined function. Although the devices described in the following embodiments are preferably implemented in software, the implementation of hardware, or a combination of software and hardware, is also possible and conceivable.

[0134] Figure 6 is a structural block diagram of the maximum power tracking control device of the photovoltaic optimizer of this embodiment, such as Figure 6 As shown, the device includes: a sampling module 71 and a power control module 72.

[0135] The sampling module 71 is used to sample the electrical parameters of the photovoltaic optimizer 22 in real time, and calculate the input power of the input end of the photovoltaic optimizer 22 in real time based on the electrical parameters.

[0136] The power control module 72 is used to determine the current working mode of the photovoltaic optimizer 22 and execute the control task corresponding to the current working mode; wherein the working mode includes a re-tracking mode and a voltage stabilization mode; when the working mode is the re-tracking mode, disturbance tracking is performed on the input power, and after obtaining the target power point, the working mode is switched to the voltage stabilization mode, until the preset exit condition is met, and the working mode is switched from the voltage stabilization mode back to the re-tracking mode.

[0137] After the current control task is completed, a pulse signal is generated based on the updated duty cycle to control the photovoltaic optimizer.

[0138] In some of the embodiments, the power control module 72 is also used to perform disturbance processing to adjust the duty cycle when the working mode is the re-tracking mode; after the disturbance processing, the input power is recalculated; if the input power after the disturbance processing meets the preset tracking conditions, the duty cycle and the maximum power tracking point are updated based on the result of the disturbance processing, and the current control task is terminated; if the input power after the disturbance processing does not meet the tracking conditions, the flag of the working mode is modified to the voltage stabilization mode, and the current control task is terminated.

[0139] In some of the embodiments, the power control module 72 is also used to compare the electrical parameters after the disturbance processing with the electrical parameters before the disturbance processing to obtain a comparison result; if the comparison result does not meet the preset parameter change requirement, a static tracking state is entered, in which the voltage and duty cycle of the input terminal are kept unchanged until a preset exit condition is reached, and then the static tracking state is exited.

[0140] In some of the embodiments, the power control module 72 is further used to generate two pulse signals with complementary waveforms based on the updated duty cycle after the current control task is completed, so as to respectively control the two field effect transistors in the photovoltaic optimizer 22.

[0141] In some of the embodiments, the power control module 72 is also used to, when the working mode is the re-tracking mode, perform a first disturbance based on a first disturbance direction to obtain an adjusted first duty cycle; based on the first duty cycle, determine whether the first disturbance direction is a correct disturbance direction; if the first disturbance direction is the correct disturbance direction, perform a secondary disturbance based on the first disturbance direction to obtain an adjusted second duty cycle; if the first disturbance direction is not the correct disturbance direction, perform a secondary disturbance based on the second disturbance direction to obtain an adjusted second duty cycle, and the second disturbance direction is opposite to the first disturbance direction; continue to disturb according to the obtained correct disturbance direction, and update the duty cycle until the input power no longer increases.

[0142] In some of the embodiments, the power control module 72 is also used to determine whether the number of voltage stabilization times reaches a preset number when the working mode is the voltage stabilization mode; if the number of voltage stabilization times does not reach the preset number, voltage stabilization processing is performed on the currently sampled input voltage, the number of voltage stabilization times is recorded once, and the current control task is terminated; if the number of voltage stabilization times has reached the preset number, the working mode is modified to the re-tracking mode, and the current control task is terminated.

[0143] In some of the embodiments, the power control module 72 is also used to determine whether the current duty cycle has reached a preset maximum value when the working mode is a power-on pass-through mode; if the current duty cycle has reached the preset maximum value, determine whether the load 23 side has entered the working state; if the load 23 side has entered the working state, then when the input power no longer increases, modify the flag of the working mode to the voltage stabilization mode, and terminate the current control task.

[0144] In some of the embodiments, the power control module 72 is also used to determine whether the current input power is greater than a reference power when the working mode is a power-on tracking mode; the reference power is the power of the input end sampled when the previous round of the control task is completed; if the input power is greater than the reference power, the maximum power tracking point is updated based on the current input power, and after increasing the current duty cycle, the current control task is terminated; if the input power is not greater than the preset reference power, the flag of the working mode is modified to the voltage regulation mode, and the current control task is terminated.

[0145] It should be noted that the above modules can be functional modules or program modules, and can be implemented by software or hardware. For modules implemented by hardware, the above modules can be located in the same processor; or the above modules can be located in different processors in any combination.

[0146] In addition, in combination with the maximum power tracking control method for the photovoltaic optimizer provided in the above embodiments, a storage medium can also be provided in this embodiment to implement the maximum power tracking control method for the photovoltaic optimizer. The storage medium stores a computer program; when the computer program is executed by the processor, any of the maximum power tracking control methods for the photovoltaic optimizer in the above embodiments is implemented.

[0147] It should be understood that the specific embodiments described herein are only used to explain the application, rather than to limit it. Based on the embodiments provided in this application, all other embodiments obtained by ordinary technicians in this field without creative work are within the protection scope of this application.

[0148] Obviously, the drawings are only some examples or embodiments of the present application. For ordinary technicians in the field, the present application can also be applied to other similar situations based on these drawings without creative work. In addition, it is understandable that although the work done in this development process may be complicated and lengthy, for ordinary technicians in the field, certain changes in design, manufacturing or production based on the technical content disclosed in this application are only conventional technical means and should not be regarded as insufficient content disclosed in this application.

[0149] The term "embodiment" in this application refers to a specific feature, structure or characteristic described in conjunction with the embodiment that can be included in at least one embodiment of the present application. The appearance of this phrase in various locations in the specification does not necessarily mean the same embodiment, nor does it mean that it is mutually exclusive with other embodiments and is independent or optional. It is clearly or implicitly understood by those of ordinary skill in the art that the embodiments described in this application can be combined with other embodiments without conflict.

[0150] The above-mentioned embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of patent protection. It should be pointed out that, for a person of ordinary skill in the art, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the scope of protection of the present application. Therefore, the scope of protection of the present application shall be subject to the attached claims.

Claims

1. A maximum power point tracking control method for a photovoltaic optimizer, characterized in that: The method is applied to a photovoltaic maximum power tracking system, the system comprising a photovoltaic panel, a photovoltaic optimizer and a load, the input end of the photovoltaic optimizer is connected to the photovoltaic panel, and the output end of the photovoltaic optimizer is connected to the load; the method comprises: Sampling electrical parameters of a photovoltaic optimizer in real time, and calculating input power at an input end of the photovoltaic optimizer in real time based on the electrical parameters; Determine the current working mode of the photovoltaic optimizer, and execute the control task corresponding to the current working mode; wherein the working mode includes power-on direct mode, power-on tracking mode, re-tracking mode and voltage stabilization mode; when the working mode is the re-tracking mode, perform disturbance tracking on the input power, and after obtaining the target power point, switch the working mode to the voltage stabilization mode, until the preset exit condition is met, and then switch the working mode from the voltage stabilization mode back to the re-tracking mode; Wherein, the execution of the control task corresponding to the current working mode further includes: when the working mode is the voltage stabilization mode, determining whether the number of voltage stabilization times reaches a preset number; if the number of voltage stabilization times does not reach the preset number, performing voltage stabilization processing on the currently sampled input voltage, recording the number of voltage stabilization times once, and ending the current control task; if the number of voltage stabilization times has reached the preset number, modifying the working mode to the re-tracking mode, and ending the current control task; The executing the control task corresponding to the current working mode also includes: when the working mode is the power-on direct mode, judging whether the current duty cycle reaches a preset maximum value; if the current duty cycle has reached the preset maximum value, judging whether the load side has entered the working state; if the load side has entered the working state, when the input power no longer increases, modifying the flag bit of the working mode to the voltage stabilization mode, and ending the current control task; The execution of the control task corresponding to the current working mode also includes: when the working mode is the power-on tracking mode, judging whether the current input power is greater than the reference power; the reference power is the power of the input end sampled when the previous round of the control task is completed; if the input power is greater than the reference power, updating the maximum power tracking point based on the current input power, and ending the current control task after increasing the current duty cycle; if the input power is not greater than the preset reference power, modifying the flag bit of the working mode to the voltage stabilization mode, and ending the current control task; After the current control task is finished, a pulse signal is generated based on the updated duty cycle to control the photovoltaic optimizer; Wherein, after the current control task is finished, a pulse signal is generated based on the updated duty cycle to control the photovoltaic optimizer, including: After the current control task is finished, two pulse signals with complementary waveforms are generated based on the updated duty cycle to respectively control the two field effect transistors in the photovoltaic optimizer.

2. The maximum power point tracking control method for a photovoltaic optimizer according to claim 1, characterized in that: When the working mode is the re-tracking mode, disturbance tracking is performed on the input power, and after obtaining the target power point, the working mode is switched to the voltage stabilization mode, including: When the working mode is a re-tracking mode, performing disturbance processing to adjust the duty cycle; After the disturbance processing, recalculating the input power; If the input power after the disturbance processing meets the preset tracking condition, the duty cycle and the maximum power tracking point are updated based on the result of the disturbance processing, and the current control task is terminated; If the input power after the disturbance processing does not meet the tracking condition, the flag bit of the working mode is modified to the voltage stabilization mode, and the current control task is terminated.

3. The maximum power point tracking control method of a photovoltaic optimizer according to claim 2, characterized in that: If the input power after the disturbance processing meets the preset tracking condition, the duty cycle and the maximum power tracking point are updated based on the result of the disturbance processing, and after the current control task is terminated, the method further includes: Comparing the electrical parameters after the disturbance processing with the electrical parameters before the disturbance processing to obtain a comparison result; If the comparison result does not meet the preset parameter change requirement, a static tracking state is entered. In the static tracking state, the voltage and duty cycle of the input terminal are kept unchanged until a preset exit condition is reached, and then the static tracking state is exited.

4. The maximum power point tracking control method for a photovoltaic optimizer according to claim 2, characterized in that: When the working mode is the re-tracking mode, performing disturbance processing to adjust the duty cycle includes: When the working mode is the re-tracking mode, performing a first disturbance based on the first disturbance direction to obtain an adjusted first duty cycle; Based on the first duty cycle, determining whether the first disturbance direction is a correct disturbance direction; If the first disturbance direction is a correct disturbance direction, performing a secondary disturbance based on the first disturbance direction to obtain an adjusted second duty cycle; If the first disturbance direction is not the correct disturbance direction, a secondary disturbance is performed based on a second disturbance direction to obtain an adjusted second duty cycle, wherein the second disturbance direction is opposite to the first disturbance direction; According to the obtained correct disturbance direction, the disturbance is continued and the duty cycle is updated until the input power no longer increases.

5. A maximum power tracking control device for a photovoltaic optimizer, characterized in that: The device is applied to a photovoltaic maximum power tracking system, which includes a photovoltaic panel, a photovoltaic optimizer and a load, wherein the input end of the photovoltaic optimizer is connected to the photovoltaic panel, and the output end of the photovoltaic optimizer is connected to the load; The device comprises: A sampling module, used for sampling electrical parameters of the photovoltaic optimizer in real time, and calculating the input power of the input end of the photovoltaic optimizer in real time based on the electrical parameters; A control module, used for determining the current working mode of the photovoltaic optimizer and executing the control task corresponding to the current working mode; wherein the working modes include power-on direct mode, power-on tracking mode, re-tracking mode and voltage stabilization mode; when the working mode is the re-tracking mode, disturbance tracking is performed for the input power, and after obtaining the target power point, the working mode is switched to the voltage stabilization mode, until a preset exit condition is met, and the working mode is switched from the voltage stabilization mode back to the re-tracking mode; Wherein, the execution of the control task corresponding to the current working mode further includes: when the working mode is the voltage stabilization mode, determining whether the number of voltage stabilization times reaches a preset number; if the number of voltage stabilization times does not reach the preset number, performing voltage stabilization processing on the currently sampled input voltage, recording the number of voltage stabilization times once, and ending the current control task; if the number of voltage stabilization times has reached the preset number, modifying the working mode to the re-tracking mode, and ending the current control task; The executing the control task corresponding to the current working mode also includes: when the working mode is the power-on direct mode, judging whether the current duty cycle reaches a preset maximum value; if the current duty cycle has reached the preset maximum value, judging whether the load side has entered the working state; if the load side has entered the working state, when the input power no longer increases, modifying the flag bit of the working mode to the voltage stabilization mode, and ending the current control task; The execution of the control task corresponding to the current working mode also includes: when the working mode is the power-on tracking mode, judging whether the current input power is greater than the reference power; the reference power is the power of the input end sampled when the previous round of the control task is completed; if the input power is greater than the reference power, updating the maximum power tracking point based on the current input power, and ending the current control task after increasing the current duty cycle; if the input power is not greater than the preset reference power, modifying the flag bit of the working mode to the voltage stabilization mode, and ending the current control task; A driving module is used to generate a pulse signal based on an updated duty cycle to control the photovoltaic optimizer after the current control task is completed; wherein, after the current control task is completed, a pulse signal is generated based on the updated duty cycle to control the photovoltaic optimizer, including: after the current control task is completed, two pulse signals with complementary waveforms are generated based on the updated duty cycle to respectively control two field effect transistors in the photovoltaic optimizer.

6. A photovoltaic maximum power tracking system, characterized in that: The system comprises: a photovoltaic panel, a photovoltaic optimizer and a load; One end of the photovoltaic optimizer is connected to the photovoltaic panel, and the other end of the photovoltaic optimizer is connected to the load; The photovoltaic optimizer is used to execute the steps of the maximum power point tracking control method for a photovoltaic optimizer according to any one of claims 1 to 4.

Citation Information

Patent Citations

  • Transformer control method with precise voltage and current limitation and maximum power point tracking functions

    CN102843035A

  • Maximum power point tracking (MPPT) method of self-adaption disturbance frequency and step

    CN103019294A

  • MPPT control method based on disturbance self-adaption

    CN104156029A

  • Fast photovoltaic power generation maximum power point tracking (MPPT) method

    CN106873709A

  • Photovoltaic system inter-harmonic suppression method and system based on adaptive MPPT

    CN113054663A