Anti-settlement foundation structure

By using a combined structure of a landing seat and a compression spring in the filling pipe, the problem of filling speed control is solved, concrete hollowing is reduced, the efficiency and strength of foundation reinforcement are improved, and a more efficient anti-settlement effect is achieved.

CN118516969BActive Publication Date: 2024-10-18THE FOURTH OF CHINA EIGHTH ENG BUREAU
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202410985130.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-10-18
Estimated Expiration
2044-07-23

AI Technical Summary

Technical Problem

In the existing foundation reinforcement technology, the speed needs to be strictly controlled when filling concrete. Filling too fast will make it difficult for air to be discharged, resulting in hollowing in the concrete, reducing the reinforcement strength and low construction efficiency.

Method used

It adopts a combined structure of a filling pipe, a landing seat and a compression spring. The gravity of the concrete is used to press down the landing seat. The compression spring is gradually compressed. The concrete landing point is located at the mouth of the pipe, which reduces air leftover, reduces the amount of bubbles, enhances the strength of the concrete, and compresses the concrete. The insertion mechanism further enhances the anti-settlement effect of the foundation.

Benefits of technology

It realizes rapid filling of concrete, reduces hollowing rate, enhances the strength of concrete columns, improves construction efficiency and foundation anti-settlement effect.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118516969B_ABST
    Figure CN118516969B_ABST
Patent Text Reader

Abstract

The present invention relates to an anti-settlement foundation structure applied to the field of building construction, comprising a foundation pit dug on the ground, a filling pipe, a landing seat, a compression spring and a pressing and inserting mechanism, wherein the landing seat is located on the inner side of the filling pipe and is slidably fitted on the inner wall of the filling pipe, the compression spring is fixed between the landing seat and the inner bottom end of the filling pipe, and the compression spring and the landing seat are matched to each other, and the landing seat is located near the open end of the filling pipe under the elastic support of the compression spring when not subject to external force, and the landing point of concrete is always located near the upper pipe mouth of the filling pipe, and there will be no problem of air residue inside the filling pipe, and the height difference of concrete falling from top to bottom is small, which greatly reduces the amount of bubbles inside the concrete and enhances the strength of the concrete column. Compared with the prior art, the present scheme can reduce the hollowing rate of the concrete structure while speeding up the filling speed, which not only improves the construction efficiency but also enhances the anti-settlement effect of the foundation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a foundation structure, in particular to an anti-settlement foundation structure applied in the field of building construction. Background Art

[0002] The foundation refers to the soil or rock supporting the base of a building. The soil layers serving as the foundation of a building are divided into rock, gravel, sand, silt, clay and artificial fill. There are two types of foundations: natural foundations and artificial foundations. Natural foundations are natural soil layers that do not require human reinforcement, while artificial foundations require human reinforcement.

[0003] Among them, the artificial foundation is to compact the soil in the foundation pit artificially, and then place the foundation in the foundation pit and fix it. For example, the specification of the patent publication number CN111809599B discloses a foundation anti-settlement structure and construction method, which includes a foundation pit excavated on the ground, the bottom wall of the foundation pit is fixedly paved with an anti-settlement concrete layer, the upper surface of the anti-settlement concrete layer is paved with a sand and gravel layer, the upper surface of the sand and gravel layer is paved with a concrete tuff layer, and a fixed column is inserted above the concrete tuff layer. The bottom end of the fixed column penetrates the concrete tuff layer, the sand and gravel layer and the anti-settlement concrete layer in turn and inserts them into the ground. A steel cage is placed on the upper surface of the concrete tuff layer, and the steel cage is used for pouring concrete. The foundation is fixed on the upper surface of the steel cage, and a number of anti-settlement devices are provided under the foundation. The anti-settlement devices are used to support the foundation, thereby achieving the effect of effectively preventing the foundation from settling.

[0004] Based on the above search and in combination with the prior art, it is found that in order to achieve anti-settlement, most of the existing foundation structures adopt a foundation reinforcement method, and most of the foundation reinforcement adopts the method of pouring concrete under the foundation in the above-mentioned public scheme, specifically, a cylindrical deep groove is set under the foundation, and then concrete is poured into the cylindrical deep groove. After the concrete solidifies, it plays a reinforcement role. However, in actual applications, when pouring concrete into the cylindrical deep groove, the filling speed needs to be strictly controlled. Filling too fast will easily cause the air at the bottom of the deep groove to not have time to be discharged to the outside, resulting in a large amount of air mixed in the concrete, causing hollowing inside the concrete, reducing the reinforcement strength, and the standard filling speed is relatively slow, and the construction efficiency is low. Therefore, an anti-settlement foundation structure is proposed to improve the above problems. Summary of the invention

[0005] In view of the above-mentioned prior art, the technical problem to be solved by the present invention is that when pouring concrete into a cylindrical deep groove, the filling speed needs to be strictly controlled. Filling too quickly will easily cause the air at the bottom of the deep groove to not have time to be discharged to the outside, resulting in a large amount of air mixing into the concrete, causing hollowing inside the concrete, reducing the reinforcement strength. The standard filling speed is relatively slow and the construction efficiency is low.

[0006] In order to solve the above problems, the present invention provides an anti-settlement foundation structure, including a foundation pit dug on the ground, and also including:

[0007] Filling pipes, there are multiple filling pipes, and multiple filling pipes are evenly and vertically inserted at the bottom of the foundation pit, the upper end of the filling pipe is open, and a conical plug is fixed at the lower end of the filling pipe;

[0008] The landing seat is located on the inner side of the filling tube and is slidably fitted to the inner wall of the filling tube. A guide structure is provided between the landing seat and the filling tube to enable the landing seat to slide stably along the axial direction of the filling tube.

[0009] A compression spring is located inside the filling tube and fixed between the landing seat and the inner bottom end of the filling tube. The landing seat is located near the open end of the filling tube under the elastic support of the compression spring without being subjected to external force.

[0010] The pressing and inserting mechanism is arranged on the inner side of the filling tube. When the landing seat moves downward, the pressing and inserting mechanism partly extends to the outer side of the filling tube.

[0011] In the above-mentioned anti-settlement foundation structure, through the cooperation of the compression spring and the landing seat, the landing seat is located near the open end of the filling tube under the elastic support of the compression spring when not subject to external force, so that the premixed concrete can be quickly poured into the filling tube, and the gravity of the concrete is used to press down the landing seat, which gradually moves downward to compress the compression spring gradually. The landing point of the concrete is always located near the upper pipe mouth of the filling tube, and there will be no problem of air retention inside the filling tube. The height difference of the concrete falling from top to bottom is small, which greatly reduces the amount of bubbles inside the concrete, thereby reducing the hollowing rate of the concrete after solidification, enhancing the strength of the concrete column, and further enhancing the anti-settlement effect of the foundation. Compared with the prior art, this scheme can reduce the hollowing rate of the concrete structure while speeding up the filling speed, which not only improves the construction efficiency but also enhances the anti-settlement effect of the foundation.

[0012] As a further supplement to the present application, the guide structure includes a guide slider fixed on the inner wall of the filling tube along the length direction of the filling tube, and a guide adapter port arranged on the side end of the landing seat. The guide adapter port slides in cooperation with the guide slider to ensure that the landing seat slides stably along the axial direction of the filling tube.

[0013] As a further supplement to the present application, the bottom end of the guide slider extends to the bottom of the filling tube, the guide slider is hollow, the bottom end of the guide slider is provided with an exhaust hole connecting the filling tube and the guide slider, and the top side end of the filling tube is provided with an exhaust hole connected to the guide slider;

[0014] The inner bottom end of the filling tube is provided with a spring groove adapted to the compression spring, so that the compression spring is compressed on the inner side of the spring groove; as the landing seat gradually moves downward, the air at the bottom of the landing seat is discharged outward from the exhaust hole until the compression spring is completely compressed to the inner side of the spring groove.

[0015] As a further supplement to the present application, the pressing and inserting mechanism includes a plurality of pressing and inserting units, which are evenly distributed around the filling tube, and when the landing seat is not subjected to external force, the plurality of pressing and inserting units are all located on the lower side of the landing seat.

[0016] As a further supplement to the present application, the pressing and inserting unit includes a pressing and inserting block, which is arranged at an angle, and the downwardly inclined end of the pressing and inserting block is arranged toward the outside of the filling tube and is provided with a cutting edge. The side end of the filling tube is provided with a sliding hole for damping the sliding of the pressing and inserting block.

[0017] As a further supplement to the present application, a pre-break positioning block is fixed on the inner wall of one side of the sliding hole, and a positioning groove compatible with the pre-break positioning block is provided at the side end of the press-insertion block; the press-insertion block is squeezed during the downward movement of the landing seat, the pre-break positioning block is forced to break, and the press-insertion block continues to be forced outward to the soil outside the insertion filling tube, which can further enhance the anti-settling effect of the foundation.

[0018] As a further supplement to the present application, an anti-retreat limit block is fixed on the inner wall on the other side of the sliding hole, and a side end of the press-insertion block is provided with a long limit groove that slides with the anti-retreat limit block; the anti-retreat limit block can prevent external soil from squeezing the press-insertion block into the inside of the landing seat and detaching it from the landing seat during the process of inserting the landing seat into the bottom of the foundation pit.

[0019] As a further supplement to the present application, a wedge-shaped pressure block is fixed at the bottom end of the landing seat, the wedge-shaped pressure block is located directly above the pressure block, the inclined surface of the wedge-shaped pressure block is in vertical contact with the pressure block, and the inner bottom end of the filling tube is provided with a storage groove adapted to the wedge-shaped pressure block; the inclined surface of the wedge-shaped pressure block is in vertical contact with the pressure block, so that the pressure block can be smoothly inserted into the soil outside the filling tube.

[0020] As a further supplement to this application, the bottom of the foundation pit is provided with anti-settlement concrete layer, sand and gravel layer, concrete ash soil layer, steel cage and foundation from bottom to top, and the filling pipe penetrates the concrete ash soil layer, sand and gravel layer and anti-settlement concrete layer from top to bottom.

[0021] An anti-settlement foundation structure is constructed using the following construction steps:

[0022] S1. Use a pile driver to vertically drive the filling pipe into the bottom of the foundation pit so that the air outlet is located outside the foundation pit;

[0023] S2. Use a concrete filling device to quickly pour the premixed concrete into the filling pipe, and use the gravity of the concrete to press down the landing seat, so that the landing seat gradually moves downward to gradually compress the compression spring, and the air at the bottom of the landing seat is discharged outward from the exhaust hole until the compression spring is completely compressed to the inner side of the spring groove;

[0024] S3. During the downward movement of the landing seat, the pressing block is squeezed and pushed outward to the soil outside the filling tube. In order to ensure that the pressing block can be smoothly inserted into the soil, a steel bar column can be used to simultaneously press the landing seat downward, and the steel bar column is kept on the inner side of the filling tube after the concrete filling is completed;

[0025] S4. Then, the anti-settlement concrete layer, the sand and gravel layer, the concrete soil layer, the steel cage mesh and the foundation are successively buried at the bottom of the foundation pit.

[0026] In summary, through the coordinated arrangement of the compression spring and the landing seat, the landing seat is located near the open end of the filling tube under the elastic support of the compression spring without being subjected to external force, so that the premixed concrete can be quickly poured into the filling tube, and the gravity of the concrete is used to press down the landing seat, and the landing seat gradually moves downward to make the compression spring gradually compressed, and the landing point of the concrete is always located near the upper pipe mouth of the filling tube, and there will be no problem of air retention inside the filling tube, and the drop height of the concrete falling from top to bottom is small, which greatly reduces the amount of bubbles inside the concrete, thereby reducing the hollowing rate of the concrete after solidification, enhancing the strength of the concrete column, and further enhancing the anti-settling effect of the foundation. Compared with the prior art, this scheme can reduce the hollowing rate of the concrete structure while speeding up the filling speed, which not only improves the construction efficiency, but also enhances the anti-settling effect of the foundation; and in the process of the landing seat moving downward, the compression block is squeezed, the pre-break positioning block is disconnected by force, and the compression block continues to be pressed outward by force to the soil inserted outside the filling tube, which can further enhance the anti-settling effect of the foundation. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 This is a schematic diagram of the overall three-dimensional structure of the filling tube in the first embodiment of the present application before installation;

[0028] Figure 2 This is a schematic cross-sectional view of the filling tube before installation according to the first embodiment of the present application;

[0029] Figure 3 This is a schematic diagram of the overall three-dimensional structure of the first embodiment of the present application after installation;

[0030] Figure 4 This is a schematic diagram of the three-dimensional structure of the landing seat of the first embodiment of the present application;

[0031] Figure 5This is a schematic diagram of a partially cutaway structure of a filling tube according to a first embodiment of the present application;

[0032] Figure 6 for Figure 5 A schematic diagram of the enlarged structure at A in the middle;

[0033] Figure 7 The three-dimensional structure of the compression block of the first embodiment of the present application is shown in FIG. Figure 1 ;

[0034] Figure 8 The three-dimensional structure of the compression block of the first embodiment of the present application is shown in FIG. Figure 2 ;

[0035] Fig. 9 It is a schematic diagram of the planar structure of the anti-settlement foundation structure according to the first embodiment of the present application.

[0036] Description of the numbers in the figure:

[0037] 1. Filling tube; 101. Air outlet; 102. Spring groove; 103. Storage groove; 104. Slide hole; 2. Landing seat; 201. Guide adapter; 3. Compression spring; 4. Guide slider; 401. Air vent; 5. Press-insert block; 501. Positioning groove; 502. Limiting long groove; 6. Wedge-shaped press block; 7. Pre-break positioning block; 8. Anti-retreat limit block; 9. Cone plug; 10. Foundation pit; 11. Anti-settlement concrete layer; 12. Sand and gravel layer; 13. Concrete soil layer; 14. Steel cage mesh; 15. Foundation. DETAILED DESCRIPTION

[0038] An implementation method of the present application is described in detail below with reference to the accompanying drawings.

[0039] The first implementation method:

[0040] The present invention provides an anti-settlement foundation structure, please refer to Figure 1-Figure 9 , including a foundation pit 10 dug on the ground, and also including a filling pipe 1, a landing seat 2, a compression spring 3 and a pressing and inserting mechanism. The bottom of the foundation pit 10 is provided with an anti-settlement concrete layer 11, a sand and gravel layer 12, a concrete tuff layer 13, a steel cage mesh 14 and a foundation 15 from bottom to top, and the filling pipe 1 penetrates the concrete tuff layer 13, the sand and gravel layer 12 and the anti-settlement concrete layer 11 from top to bottom.

[0041] Among them, there are multiple filling tubes 1, and the multiple filling tubes 1 are evenly and vertically inserted at the bottom of the foundation pit 10, the upper end of the filling tube 1 is open, and a conical plug 9 is fixed at the lower end of the filling tube 1. The landing seat 2 is located on the inner side of the filling tube 1 and is slidably fitted on the inner wall of the filling tube 1. A guide structure is arranged between the landing seat 2 and the filling tube 1. Specifically, the guide structure includes a guide slider 4 fixed on the inner wall of the filling tube 1 along the length direction of the filling tube 1, and a guide adapter 201 arranged at the side end of the landing seat 2. The guide adapter 201 slides with the guide slider 4 to ensure that the landing seat 2 slides stably along the axial direction of the filling tube 1.

[0042] The compression spring 3 is located inside the filling tube 1 and fixed between the landing seat 2 and the inner bottom end of the filling tube 1. The landing seat 2 is located near the open end of the filling tube 1 under the elastic support of the compression spring 3 without being subjected to external force.

[0043] The anti-settlement foundation structure is arranged by the cooperation of the compression spring 3 and the landing seat 2. The landing seat 2 is located near the open end of the filling tube 1 under the elastic support of the compression spring 3 when not subject to external force. The premixed concrete can be quickly poured into the filling tube 1, and the gravity of the concrete is used to press down the landing seat 2. The landing seat 2 gradually moves downward to gradually compress the compression spring 3. The landing point of the concrete is always located near the upper pipe mouth of the filling tube 1. There will be no problem of air retention inside the filling tube 1, and the height difference of the concrete falling from top to bottom is small, which greatly reduces the amount of bubbles inside the concrete, thereby reducing the hollowing rate of the concrete after solidification, enhancing the strength of the concrete column, and further enhancing the anti-settlement effect of the foundation.

[0044] Compared with the existing technology, this solution can speed up the filling speed while reducing the hollowing rate of the concrete structure, which not only improves the construction efficiency but also enhances the anti-settlement effect of the foundation.

[0045] Among them, the bottom end of the guide slider 4 extends to the bottom of the filling tube 1, the guide slider 4 is hollow, and the bottom end of the guide slider 4 is provided with an exhaust hole 401 connecting the filling tube 1 and the guide slider 4, and the top side end of the filling tube 1 is provided with an exhaust hole 101 connected to the guide slider 4, and the inner bottom end of the filling tube 1 is provided with a spring groove 102 adapted to the compression spring 3, so that the compression spring 3 is compressed on the inner side of the spring groove 102.

[0046] The anti-settling foundation structure is provided with the exhaust hole 401 . When the landing seat 2 gradually moves downward, the air at the bottom of the landing seat 2 is discharged outward from the exhaust hole 401 until the compression spring 3 is completely compressed to the inner side of the spring groove 102 .

[0047] The pressing and inserting mechanism is arranged on the inner side of the filling tube 1. When the landing seat 2 moves downward, the pressing and inserting mechanism partially extends to the outer side of the filling tube 1. Specifically, the pressing and inserting mechanism includes a plurality of pressing and inserting units, which are evenly distributed on the peripheral side of the filling tube 1, and when the landing seat 2 is not subjected to external force, the plurality of pressing and inserting units are all located on the lower side of the landing seat 2. Specifically, the pressing and inserting unit includes a pressing and inserting block 5, which is inclined, and the downwardly inclined end of the pressing and inserting block 5 is arranged toward the outer side of the filling tube 1 and is provided with a cutting edge. The side end of the filling tube 1 is provided with a sliding hole 104 for damping the sliding of the pressing and inserting block 5.

[0048] like Figure 5-Figure 7 It is shown that in order to ensure that the press-insertion block 5 is stably located at the slide hole 104 before being inserted into the soil outside the filling tube 1, a pre-break positioning block 7 is fixed on the inner wall of one side of the slide hole 104, and a positioning groove 501 adapted to the pre-break positioning block 7 is provided at the side end of the press-insertion block 5.

[0049] The anti-settlement foundation structure is provided by cooperating the pre-break positioning block 7 with the positioning groove 501. When the landing seat 2 moves downward, the pressing block 5 is squeezed, the pre-break positioning block 7 is disconnected by force, and the pressing block 5 continues to be pressed outwards by force into the soil outside the filling tube 1, which can further enhance the anti-settlement effect of the foundation.

[0050] Among them, Figure 5 , Figure 6 and Figure 8 As shown, an anti-retraction limit block 8 is fixed on the inner wall of the other side of the sliding hole 104 , and a side end of the press-insertion block 5 is provided with a limit long groove 502 that slidably cooperates with the anti-retraction limit block 8 .

[0051] The anti-retraction limit block 8 provided in the anti-settlement foundation structure can prevent the external soil from squeezing the pressing block 5 into the inside of the landing seat 2 and separating from the landing seat 2 during the process of the landing seat 2 being inserted into the bottom of the foundation pit 10.

[0052] Among them, a wedge-shaped pressure block 6 is fixed to the bottom end of the landing seat 2, and the wedge-shaped pressure block 6 is located just above the pressure block 5. The inclined surface of the wedge-shaped pressure block 6 is in vertical contact with the pressure block 5. The inner bottom end of the filling tube 1 is provided with a storage groove 103 adapted to the wedge-shaped pressure block 6. The inclined surface of the wedge-shaped pressure block 6 is in vertical contact with the pressure block 5, so that the pressure block 5 can be smoothly inserted into the soil outside the filling tube 1.

[0053] Working principle: Use a pile driver to vertically drive the filling pipe 1 into the bottom of the foundation pit 10, so that the air outlet 101 is located outside the foundation pit 10; then use a concrete filling device to quickly pour the premixed concrete into the filling pipe 1, and use the gravity of the concrete to press down the landing seat 2, the landing seat 2 gradually moves down to gradually compress the compression spring 3, and the air at the bottom of the landing seat 2 is discharged outward from the exhaust hole 401 until the compression spring 3 is completely compressed to the inside of the spring groove 102; during the downward movement of the landing seat 2, the compression block 5 is squeezed and pressed outward to the soil outside the filling pipe 1, and the compression block 5 is inserted into the soil outside the filling pipe 1. The insert block 5 slides outward along the slide hole 104. When the end of the press-insertion block 5 located on the inner side of the filling tube 1 completely enters the slide hole 104, the landing seat 2 can continue to move downward to squeeze the press-insertion block 5 on the lower side until all the press-insertion blocks 5 are completely inserted into the soil outside the filling tube 1. In order to ensure that the press-insertion block 5 can be smoothly inserted into the soil, a steel bar column can be used to synchronously squeeze the landing seat 2 downward, and the steel bar column can be kept on the inner side of the filling tube 1 after the concrete filling is completed; then the anti-settlement concrete layer 11, the sand and gravel layer 12, the concrete soil layer 13, the steel cage mesh 14 and the foundation 15 are successively buried at the bottom of the foundation pit 10.

[0054] In view of current practical needs, the above-mentioned implementation mode adopted in this application is not limited to the scope of protection. Various changes made within the knowledge scope of technical personnel in this field without departing from the concept of this application still fall within the scope of protection of the present invention.

Claims

1. An anti-settlement foundation structure, comprising a foundation pit (10) dug on the ground, characterized in that: Also includes: A filling pipe (1), wherein a plurality of the filling pipes (1) are provided, and the plurality of the filling pipes (1) are evenly and vertically inserted at the bottom of the foundation pit (10), the upper end of the filling pipe (1) is open, and a conical plug (9) is fixed at the lower end of the filling pipe (1); A landing seat (2), the landing seat (2) being located on the inner side of the filling tube (1) and being slidably fitted to the inner wall of the filling tube (1), and a guide structure being provided between the landing seat (2) and the filling tube (1) so as to enable the landing seat (2) to slide stably along the axial direction of the filling tube (1); a compression spring (3), the compression spring (3) being located inside the filling tube (1) and being fixed between the landing seat (2) and the inner bottom end of the filling tube (1); the landing seat (2) being located near the open end of the filling tube (1) under the elastic support of the compression spring (3) when not subjected to external force; A pressing and inserting mechanism, wherein the pressing and inserting mechanism is arranged on the inner side of the filling tube (1), and when the landing seat (2) moves downward, the pressing and inserting mechanism is partially extended to the outer side of the filling tube (1); The guide structure comprises a guide slider (4) fixed to the inner wall of the filling tube (1) along the length direction of the filling tube (1), and a guide adapter (201) arranged at the side end of the landing seat (2), the guide adapter (201) being in sliding cooperation with the guide slider (4); The bottom end of the guide slider (4) extends to the bottom of the filling tube (1); the guide slider (4) is hollow; the bottom end of the guide slider (4) is provided with an exhaust hole (401) communicating with the filling tube (1) and the guide slider (4); the top side end of the filling tube (1) is provided with an exhaust hole (101) communicating with the guide slider (4); The inner bottom end of the filling tube (1) is provided with a spring groove (102) adapted to the compression spring (3), so that the compression spring (3) is compressed on the inner side of the spring groove (102); The pressing and inserting mechanism comprises a plurality of pressing and inserting units, the plurality of pressing and inserting units being evenly distributed around the filling tube (1), and the plurality of pressing and inserting units being located on the lower side of the landing seat (2) when the landing seat (2) is not subjected to external force; The pressing and inserting unit comprises a pressing and inserting block (5), the pressing and inserting block (5) being arranged obliquely, and one end of the pressing and inserting block (5) which is inclined downward is arranged toward the outside of the filling tube (1) and is provided with a cutting edge, and a sliding hole (104) for damping sliding of the pressing and inserting block (5) is provided at a side end of the filling tube (1); The bottom of the foundation pit (10) is provided with an anti-settlement concrete layer (11), a gravel layer (12), a concrete ash soil layer (13), a steel cage (14) and a foundation (15) in order from bottom to top, and the filling pipe (1) passes through the concrete ash soil layer (13), the gravel layer (12) and the anti-settlement concrete layer (11) in order from top to bottom; The anti-settlement foundation structure is constructed using the following construction steps: S1. Using a pile driver, vertically drive the filling pipe (1) into the bottom of the foundation pit (10), so that the air outlet (101) is located outside the foundation pit (10); S2, using a concrete filling device to quickly pour premixed concrete into the filling tube (1), using the gravity of the concrete to press down the landing seat (2), the landing seat (2) gradually moves downward so that the compression spring (3) is gradually compressed, and the air at the bottom of the landing seat (2) is discharged outward from the exhaust hole (401) until the compression spring (3) is completely compressed to the inner side of the spring groove (102); S3, when the landing seat (2) moves downward, the pressing block (5) is squeezed, and the pressing block (5) is pressed outward to the soil outside the filling tube (1). In order to ensure that the pressing block (5) can be smoothly inserted into the soil, a steel bar column can be used to simultaneously press the landing seat (2) downward, and the steel bar column is kept on the inner side of the filling tube (1) after the concrete filling is completed; S4, then sequentially filling the bottom of the foundation pit (10) with an anti-settlement concrete layer (11), a sand and gravel layer (12), a concrete ash soil layer (13), a steel cage mesh (14) and a foundation (15).

2. The anti-settlement foundation structure according to claim 1, characterized in that: A pre-break positioning block (7) is fixed on one inner wall of the sliding hole (104), and a positioning groove (501) adapted to the pre-break positioning block (7) is provided at the side end of the pressing block (5).

3. The anti-settlement foundation structure according to claim 2, characterized in that: An anti-retraction limit block (8) is fixed on the inner wall of the other side of the sliding hole (104), and a side end of the pressing block (5) is provided with a limit long groove (502) that slidably cooperates with the anti-retraction limit block (8).

4. The anti-settlement foundation structure according to claim 3, characterized in that: A wedge-shaped pressing block (6) is fixed to the bottom end of the landing seat (2), the wedge-shaped pressing block (6) is located directly above the pressing block (5), the inclined surface of the wedge-shaped pressing block (6) is in vertical contact with the pressing block (5), and the inner bottom end of the filling tube (1) is provided with a receiving groove (103) adapted to the wedge-shaped pressing block (6).

Citation Information

Patent Citations

  • A foundation settlement prevention structure and construction method

    CN111809599B

  • Cast-in-place concrete anti-segregation structure for depth pile

    CN210216399U

  • High-strength deep hole pile foundation

    CN218060287U