A method and system for adaptive sag of cable-suspended spanning frame
By combining historical operation activities and environmental prediction data to optimize the sag adjustment sequence, the problems of low control accuracy and slow response speed in traditional methods are solved, and adaptive adjustment of the sag of the sag of the snail is realized, which improves construction safety and efficiency.
Patent Information
- Application Number
- CN202410977491.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2044-07-22
AI Technical Summary
The traditional suspension strut sag control method relies on manual experience and regular inspection, resulting in low control accuracy, slow response speed and poor stability, making it difficult to meet the requirements of construction safety and efficiency, especially in complex environments, it is difficult to deal with severe weather conditions.
By combining historical operation activities, construction planning information and environmental prediction data, the sag adjustment sequence is optimized to realize sag adaptive adjustment, and sag optimization adjustment is performed using computer instructions and electronic equipment to improve construction safety and efficiency.
The adaptive adjustment accuracy and response speed of the suspension span frame sag are improved, construction safety and efficiency are enhanced, and construction needs are adapted to the construction needs in complex environments.
Smart Images

Figure CN118523200B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of frequency converters, and in particular to a sag self-adaptive method and system for a suspension-cable type spanning frame. Background Art
[0002] With the continuous advancement of modern infrastructure construction, cable-stayed spans, as an important construction equipment, play a vital role in the construction of bridges, power lines, communication lines, etc. Cable-stayed spans are usually used to cross obstacles such as rivers, canyons, roads, etc., providing a stable and safe passage for construction. However, with the expansion of construction scale and the improvement of process requirements, the control and management of cable-stayed span sag, that is, the degree of droop of the cable under the action of deadweight and load, is also facing increasing challenges.
[0003] Traditional cable-stayed span sag control methods often rely on manual experience and regular testing, which has problems such as low control accuracy, slow response speed, and poor stability. Especially in complex construction environments, such as strong winds, high temperatures, high humidity and other severe weather conditions, traditional control methods often fail to meet the requirements of construction safety and efficiency. Summary of the invention
[0004] The present application provides a method and system for self-adapting sag of a cable-stayed span, which are used to solve the technical problem that the prior art relies on manual experience and regular inspections and is difficult to meet the requirements of construction safety and efficiency.
[0005] In view of the above problems, the present application provides a method and system for sag self-adaptation of a cable-suspended spanning frame.
[0006] In a first aspect of the present application, a method for sag self-adaptation of a suspension cable-type spanning frame is provided, the method comprising:
[0007] Obtain historical work activities of the spanning object; obtain the erection height parameters of the cable-type spanning frame, and obtain the sag distance constraint based on the erection height parameters and the historical work activities, wherein the cable-type spanning frame is a construction platform constructed above the spanning object; obtain construction planning information, and obtain a sag construction adjustment sequence based on the construction planning information and the sag distance constraint; obtain environmental prediction data with the construction planning information as a constraint; optimize the sag construction adjustment sequence based on the environmental prediction data to obtain a sag optimization adjustment sequence; in the execution stage of the construction planning information, use the sag optimization adjustment sequence to perform sag adaptive adjustment.
[0008] A second aspect of the present application provides a cable-suspended spanning frame sag adaptive system, the system comprising:
[0009] A historical work activity acquisition module, the historical work activity acquisition module acquires historical work activities of a crossing object; a sag distance constraint acquisition module, the sag distance constraint acquisition module acquires an erection height parameter of a cable-stayed span frame, and acquires a sag distance constraint based on the erection height parameter and the historical work activities, wherein the cable-stayed span frame is a construction platform constructed above the crossing object; a sag adjustment analysis module, the sag adjustment analysis module acquires construction planning information, and acquires a sag construction adjustment sequence based on the construction planning information and the sag distance constraint; an environmental data calling module, the environmental data calling module acquires environmental prediction data with the construction planning information as a constraint; a sag optimization adjustment sequence acquisition module, the sag optimization adjustment sequence acquisition module optimizes the sag construction adjustment sequence according to the environmental prediction data to acquire a sag optimization adjustment sequence; a sag adaptive adjustment execution module, the sag adaptive adjustment execution module uses the sag optimization adjustment sequence to execute sag adaptive adjustment during the construction planning information execution stage.
[0010] The third aspect of the present application provides a sag adaptive electronic device for a suspended cable-type span, the electronic device comprising at least one processor; and a memory communicatively connected to the at least one processor; the memory stores instructions executable by the at least one processor, the instructions being executed by the at least one processor so that the at least one processor can execute the method of the first aspect of the present invention.
[0011] According to a fourth aspect of the present invention, there is provided a non-transitory computer-readable storage medium storing computer instructions, wherein the computer instructions are used to cause the computer to execute the method according to the first aspect of the present invention.
[0012] One or more technical solutions provided in this application have at least the following technical effects or advantages:
[0013] The present application obtains historical operation activities of a spanning object; obtains the erection height parameters of a cable-type spanning frame, and obtains a sag distance constraint based on the erection height parameters and the historical operation activities, wherein the cable-type spanning frame is a construction platform constructed above the spanning object; obtains construction planning information, and obtains a sag construction adjustment sequence based on the construction planning information and the sag distance constraint; obtains environmental prediction data with the construction planning information as a constraint; optimizes the sag construction adjustment sequence based on the environmental prediction data to obtain a sag optimization adjustment sequence; and uses the sag optimization adjustment sequence to perform sag adaptive adjustment during the execution phase of the construction planning information. The present invention solves the technical problem that the prior art relies on manual experience and regular testing and is difficult to meet the requirements of construction safety and efficiency. By combining historical operation activities, construction planning information, environmental prediction data and other factors, the present invention realizes adaptive adjustment of the sag of the cable-type spanning frame, thereby achieving the technical effect of improving the safety and efficiency of construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the following briefly introduces the drawings required for use in the description of the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.
[0015] Figure 1 A schematic diagram of a flow chart of a sag self-adaptation method for a suspension-type spanning frame provided in an embodiment of the present application;
[0016] Figure 2 A schematic diagram of the structure of a sag adaptive system for a cable-suspended span provided in an embodiment of the present application;
[0017] Figure 3 A block diagram of an exemplary electronic device capable of implementing embodiments of the present invention is shown.
[0018] Explanation of the accompanying drawings: 11 is a historical work activity acquisition module; 12 is a sag distance constraint acquisition module; 13 is a sag adjustment analysis module; 14 is an environmental data calling module; 15 is a sag optimization adjustment sequence acquisition module; 16 is a sag adaptive adjustment execution module; 300 is an electronic device, 301 is a computing unit, 302 is a ROM, 303 is a RAM, 304 is a bus, 305 is an I / O interface, 306 is an input unit, 307 is an output unit, 308 is a storage unit, and 309 is a communication unit. DETAILED DESCRIPTION
[0019] The present application provides a method and system for adaptively adjusting the sag of a cable-suspended span, aiming to solve the technical problem that the prior art relies on manual experience and regular inspections and is difficult to meet the requirements of construction safety and efficiency. By combining historical work activities, construction planning information, environmental prediction data and other factors, adaptive adjustment of the sag of a cable-suspended span is achieved, thereby achieving the technical effect of improving the safety and efficiency of construction.
[0020] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0021] It should be noted that any variations of the terms "include" and "have" are intended to cover non-exclusive inclusions. For example, a process, method, system, product or server that includes a series of steps or units is not necessarily limited to those steps or units explicitly listed, but may include other steps or modules that are not explicitly listed or inherent to these processes, methods, products or devices.
[0022] Embodiment 1
[0023] like Figure 1 As shown, the present application provides a method for sag self-adaptation of a suspension cable-type spanning frame, the method comprising:
[0024] Step S100: Obtain historical operation activities across objects.
[0025] In an embodiment of the present application, historical work activities across objects are obtained by interacting with relevant construction logs, maintenance records, accident reports and other documents.
[0026] At the same time, the document management system or archive can be used to quickly locate and obtain the required historical operation activity data. The historical operation activity data includes operation time, operation type, operation height, etc.
[0027] Step S200: obtaining an erection height parameter of a cable-stayed span frame, and obtaining a sag distance constraint according to the erection height parameter and the historical operation activities, wherein the cable-stayed span frame is a construction platform constructed above the spanning object.
[0028] In an embodiment of the present application, the erection height parameters of the cable-stayed crossing frame are collected from a relevant database or data source through a preset data interface or API, and these parameters include the main span, side span, crossing height, etc.
[0029] Based on the erection height parameters and historical operation activity data, mechanical calculations are performed. This process involves the deformation and sagging of the cable-stayed span under different loads and meteorological conditions. Specialized engineering mechanics software is used to complete these calculations. Specifically, the catenary equation is first determined as ,in is the horizontal tension, w is the weight per unit length of the cable, and x is the horizontal position. The horizontal tension is calculated using the equilibrium equation and boundary conditions. Specifically, Calculated, where is the main span, H is the span height. The maximum sag is at the midpoint of the cable. To determine the maximum load and sag under adverse weather conditions, the influence of additional loads and weather conditions on the cables is considered by adding load and temperature effect correction factors. ,in is the weight per unit length of the additional load, Identify the actual effective unit length weight and convert the calculated As the weight per unit length of the cable. Considering the safety factor k, the sag safety distance is ,in It is a reserved safety gap, pre-set by technical experts.
[0030] According to the calculation results, the sag safety distance of the cable-stayed span under the maximum load and adverse weather conditions is determined. This distance needs to ensure that the cable-stayed span will not contact or collide with the spanning object or obstacle below under any circumstances.
[0031] The calculated sag safety distance is used as the sag distance constraint condition for the design and construction of cable-stayed spans.
[0032] Step S300: Obtain construction planning information, and obtain a sag construction adjustment sequence according to the construction planning information and the sag distance constraint.
[0033] In the embodiment of the present application, the construction planning information is automatically obtained from the project management system, CAD design software or other related systems through the integrated data interface. The construction planning information includes the construction schedule, construction steps, material list, equipment configuration, etc. Next, the built-in data parsing function is used to parse and organize the construction planning information to extract the key data related to the construction of the cable-stayed span.
[0034] According to the construction planning information and sag distance constraints, the influence of different construction stages on the sag of the cable-stayed span is simulated, including the potential influence of factors such as loading and unloading processes and equipment movement on sag. By using engineering mechanics software to analyze the potential influence of each construction stage on the sag of the cable, the sag change curve of each stage is generated, and the sag adjustment strategy is generated based on the simulation results. These strategies include the timing of adjustment, the method of adjustment, and the target value of adjustment. Specifically, the adjustment timing is determined as the key node of the construction stage, and the adjustment method includes adjusting the cable tension, redistributing the load, optimizing the equipment position, etc. The adjustment target value is set according to the sag safety distance and construction efficiency requirements. At the same time, the optimization algorithm is applied to optimize the sag adjustment strategy to find the optimal adjustment scheme while meeting the construction efficiency and safety requirements. The optimization process includes constructing an objective function (such as minimizing sag deviation and maximizing construction efficiency), setting constraints (such as safety distance and load limit), and using advanced optimization techniques such as genetic algorithms, particle swarm optimization or simulated annealing to gradually approach the optimal solution through multiple iterative calculations. The objective function is: ; ; ;in Indicates the sag deviation, Represents the total construction time, It is a comprehensive objective function that combines sag deviation and construction time by weighted sum. is the actual sag value of the i-th construction stage, is the target sag value, n is the total number of construction stages, t is the sum of the time taken for all construction stages, and It is the weight coefficient of the two objectives, which is pre-set by technical experts.
[0035] According to the sag adjustment strategy and optimization results, a sag construction adjustment sequence is generated. This sequence details the construction stages in which sag adjustment is performed, the specific parameter values of the adjustment, and the order and steps of the adjustment.
[0036] Step S400: Obtaining environmental prediction data with the construction planning information as a constraint.
[0037] In the embodiment of the present application, the types of environmental parameters that need to be predicted are determined based on the construction planning information, such as temperature, humidity, wind speed, wind direction, precipitation probability, etc. At the same time, the time range and spatial range of the predicted data are determined to ensure that they match the time and location of the construction plan.
[0038] Determine the data interface connected to the meteorological, geological, and environmental monitoring service providers. Set the time range for environmental data calls based on the key time points or time periods in the construction plan. Through the interface call, filter and obtain environmental data within the specified time range. Through the above process, obtain environmental prediction data.
[0039] Step S500: Optimizing the sag construction adjustment sequence according to the environmental prediction data to obtain a sag optimization adjustment sequence.
[0040] In the embodiment of the present application, historical data and professional knowledge are used to identify the main environmental factors affecting sag, such as temperature, wind speed, etc. The specific impact mechanism of these environmental factors on sag is analyzed, such as thermal expansion and contraction of wires caused by temperature changes.
[0041] Quantify the impact of different environmental factors on sag through ANSYS simulation or other analysis tools. For example, calculate the sag change of transmission lines under different temperature and wind speed conditions.
[0042] According to the environmental forecast data, select the period when the environmental parameters are relatively stable or have less impact on the construction for sag adjustment. For example, avoid construction under adverse weather conditions such as high temperature and strong wind to reduce safety risks and improve construction quality.
[0043] Based on the environmental prediction data, the possible environmental changes during the construction process are predicted, and the adjustment parameters such as the tension of the wire and the number of insulator strings are optimized accordingly. For example, during periods of high temperature, the tension of the wire can be appropriately reduced to reduce sag; during periods of high wind speed, the number of insulator strings can be increased to enhance the support of the line.
[0044] According to the construction planning information and environmental prediction data, the order of sag adjustment is optimized. The spans that have a greater impact on the overall sag of the line or the spans near the spanning objects are adjusted first; in the case of strong winds, the spans that are less affected by the wind can be adjusted first.
[0045] Based on the above analysis and optimization results, a sag optimization adjustment sequence is generated.
[0046] Step S600: In the construction planning information execution stage, the sag optimization adjustment sequence is used to perform sag adaptive adjustment.
[0047] In the embodiment of the present application, sensors and monitoring equipment are used to monitor the changes of environmental parameters and sag status in real time. The real-time monitoring data is compared with the environmental prediction data to analyze the change trend of environmental parameters and their impact on sag. According to the real-time monitoring data and the guidance in the sag optimization adjustment sequence, the parameters such as the tension of the wire and the number of insulator strings are automatically adjusted to achieve adaptive adjustment of the sag.
[0048] Furthermore, step S200 in the method provided in the application embodiment also includes:
[0049] A work association threshold is preset, and the layout position of the cable-type crossing frame and the work association threshold are used as constraints to call local spatial data of the historical work activities to obtain local work activities; the work height of the local work activities is collected to obtain work height constraints; the sag distance constraint is obtained by solving the erection height parameter and the work height constraint.
[0050] In the embodiment of the present application, an operation association threshold is preset before the construction of the cable-stayed span frame, and the operation association threshold is used to determine which historical operation activity data has direct relevance and reference value to the current construction activity.
[0051] Determine the precise location of the cable-stayed span, including longitude and latitude, topography and other detailed data. Filter out the operation activity data that is close or similar to the current cable-stayed span location from the historical operation activity database. The basis for the screening is the operation association threshold, that is, select the historical data that is close or similar to the current operation activity in spatial location. The filtered historical operation activity data is used as the local operation activity data.
[0052] Collect detailed information on the operating height of the selected local operating activity data, including the actual operating height, operating time, weather conditions, etc. of each historical operating activity. Perform statistical analysis on the collected operating height data to calculate key indicators such as the average operating height, the highest operating height, and the lowest operating height. According to the statistical analysis results, combined with the current design requirements and safety standards of the cable-stayed crossing frame, set a reasonable operating height constraint range. For example, the operating height shall not be less than 10 meters and not more than 30 meters.
[0053] According to the design scheme of the cable-stayed span and the actual construction requirements, the erection height parameters of the cable-stayed span are determined. Taking into account the erection height parameters, the operating height constraint range and the structural characteristics of the cable-stayed span, the sag distance constraint is calculated through a mathematical model or an existing empirical formula. At this time, the catenary equation is used to describe the curve formed by the cable under the action of gravity, that is, where a is a constant related to the cable tension and weight per unit length, i.e. the catenary constant; x is the horizontal position and y is the vertical position. The catenary constant a is given by Calculated, where is the horizontal tension of the cable, and w is the weight per unit length of the cable. According to the catenary equation, the sag D is the maximum vertical distance of the catenary at the midpoint, which is calculated by the above formula. Finally, according to the operating height constraint range, a reasonable sag safety distance is set. Considering that the maximum sag during construction should not be lower than the minimum operating height, it should be adjusted within the safety range. Assuming the minimum operating height is , combined with the erection height parameters and the operating height constraints, the final sag distance constraints This constraint ensures that during the operation of the cable-stayed span, the sag distance can meet safety requirements without affecting construction efficiency.
[0054] Furthermore, step S300 in the method provided in the application embodiment also includes:
[0055] Construction load prediction is performed according to the construction planning information, and construction load fitting is performed based on the prediction results to obtain multiple construction load variables; multiple sag adjustment information is obtained based on the multiple construction load variables and sag distance constraints; the multiple sag adjustment information is serialized based on the construction planning information to generate the sag construction adjustment sequence.
[0056] In the embodiment of the present application, a construction load prediction model is established based on historical construction data, engineering characteristics and expert experience. The model is a statistical model, a machine learning model or other applicable prediction tools. The construction planning information is input into the prediction model to predict various load conditions during the construction process, such as static load, dynamic load, temporary load, etc.
[0057] The predicted construction load data are sorted out, including the size, action time, distribution location, etc. of different types of loads. According to the characteristics of the data and fitting requirements, the construction load data is fitted through polynomial fitting to obtain multiple construction load variables.
[0058] According to the design requirements, safety standards and construction load prediction results of the cable-suspended span, the sag distance constraint is determined. Based on the structural characteristics, mechanical principles and engineering experience of the cable-suspended span, a sag adjustment model is established. Multiple construction load variables are input into the sag adjustment model to analyze how to adjust the sag distance of the cable-suspended span to meet the constraints under different construction loads. During the analysis, different adjustment strategies and methods can be considered, such as changing the tension of the tension wire, adjusting the cable length, etc. According to the results of the sag adjustment analysis, multiple sag adjustment information is obtained. Each adjustment information includes adjustment timing, adjustment parameters and adjustment effect.
[0059] According to the construction planning information, a serialization strategy of the sag construction adjustment sequence is determined. According to the serialization strategy, multiple sag adjustment information are sorted and numbered in chronological order to generate a sag construction adjustment sequence.
[0060] Further, construction load prediction is performed according to the construction planning information, and construction load fitting is performed based on the prediction result to obtain multiple construction load variables. The method also includes:
[0061] The construction planning information is split to obtain multiple construction task information; multiple sample construction resources of the multiple sample construction tasks are obtained, and the multiple sample construction tasks and the multiple sample construction resources are stored in association with each other based on the knowledge graph to construct a construction resource analysis library; the multiple construction task information is used to traverse the construction resource analysis library to analyze and output multiple construction resource prediction information; and the multiple construction load variables are obtained based on the multiple construction resource prediction information.
[0062] In the embodiment of the present application, key information directly related to the construction task is extracted from the construction planning information, such as task type, task location, task time, expected workload, etc. The construction planning information is split into multiple independent construction task information according to factors such as task type, location, time, etc. Each construction task information should contain all the key information required to complete the task.
[0063] Collect multiple sample construction tasks and their corresponding sample construction resources through interactive means. Sample construction resources include personnel, equipment, materials, time, etc. Use knowledge graph technology to associate and store multiple sample construction tasks and multiple sample construction resources. Construct a complete construction resource knowledge system through elements such as entities, relationships, and attributes. Store the data and relationships in the knowledge graph to form a construction resource analysis library.
[0064] Use multiple construction task information as query conditions to traverse the construction resource analysis library. According to the type and characteristics of the construction task information, match the corresponding construction resources from the construction resource analysis library. At the same time, based on the historical data and the relationship in the knowledge graph, predict the quantity, quality, time, etc. of construction resources. Output the prediction results in the form of construction resource prediction information. Each construction resource prediction information includes detailed information such as resource type, quantity, quality, time, etc.
[0065] Extract key parameters from construction resource forecast information, such as the number of personnel, equipment power, material weight, etc., as input data for construction load. Select a suitable fitting method based on the characteristics and fitting requirements of the construction load. For example, use linear fitting. Substitute the input data of the construction load into the selected fitting method for fitting calculation. Based on the fitting results, obtain multiple construction load variables.
[0066] Further, performing construction load fitting according to the plurality of construction resource prediction information to obtain the plurality of construction load variables, the method further includes:
[0067] Obtain structural design information of the cable-suspended span; use the structural design information as a modeling basis and adopt BIM technology to construct a span model; perform a temporary load simulation of first construction resource prediction information on the span model to obtain a first construction load variable, wherein the first construction resource prediction information is any one of the multiple construction resource prediction information; and similarly, perform a temporary load simulation of the multiple construction resource prediction information on the span model to obtain the multiple construction load variables; preset a load deviation, and smooth the multiple construction load variables based on the construction planning information and the load deviation to obtain multiple optimized load variables; and use the multiple optimized load variables to update the multiple construction load variables to perform sag adjustment analysis.
[0068] In an embodiment of the present application, the existing CAD parsing technology or a customized parsing algorithm is used to extract the structural design information of the cable-stayed span, such as the model, length, diameter, material properties, location and size of the supporting structure, etc. of the cable, from the pre-uploaded CAD file or input parameters.
[0069] Next, select appropriate BIM software, such as Revit, ArchiCAD, etc., and build 3D models of components such as cables, supporting structures, and connectors one by one based on the extracted structural design information. At the same time, add corresponding attribute information to these components, such as material, size, weight, etc., to complete the construction of the span model.
[0070] Multiple construction resource forecast information, such as the number of personnel, equipment type, material weight, etc., are input into the span model in sequence. The simulation analysis function of the BIM software is used to simulate the temporary loads corresponding to the construction resource forecast information on the span model. This process is achieved by adding virtual loads to the model, adjusting the tension of the suspension cable or the position of the supporting structure, etc. Repeat the above temporary load simulation steps for the remaining multiple construction resource forecast information to obtain the construction load variables corresponding to all the construction resource forecast information.
[0071] According to engineering experience and actual needs, technical experts preset a reasonable load deviation range. Combined with construction planning information, such as construction sequence, time schedule, etc., multiple construction load variables are smoothed. This is achieved through mathematical methods such as moving average method and filtering algorithm. Smoothing reduces the fluctuation and mutation of construction loads. After smoothing, multiple optimized construction load variables are obtained.
[0072] According to the structural characteristics and mechanical principles of the cable-type spanning frame, a sag adjustment analysis model is established. The model should be able to reflect the relationship between the construction load and the sag distance, and take into account factors such as the material nonlinearity of the cable and the constraints of the supporting structure. The optimized multiple construction load variables are used as input and substituted into the sag adjustment analysis model for analysis through numerical calculation, simulation and other methods. According to the analysis results, multiple sag adjustment information is output. This information includes adjustment timing, adjustment parameters and adjustment effect. The adjustment parameters include the increase in the tension of the tightening wire, the adjustment amount of the cable length, etc.; the adjustment effect is the sag distance after adjustment.
[0073] Furthermore, the method further comprises:
[0074] Obtain a historical adjustment log of the cable-suspended span, wherein the historical adjustment log includes multiple groups of sample safety distances-sample load variables-sample sag adjustment parameters; call N random operators to construct N sag adjustment analysis branches; use the multiple groups of sample safety distances-sample load variables-sample sag adjustment parameters to train the N sag adjustment analysis branches until the sag adjustment accuracy of the N sag adjustment analysis branches is higher than a preset accuracy constraint; and connect the N sag adjustment analysis branches in parallel to generate a sag adjustment network.
[0075] In an embodiment of the present application, interaction is performed with the management or maintenance team of the cable-stayed span to obtain its historical adjustment logs. These logs generally record the adjustment of the cable-stayed span under different construction conditions. The historical adjustment logs include multiple sets of sample data, each set of data containing a sample safety distance, a sample load variable, and a sample sag adjustment parameter. The sample safety distance is the safety distance that the cable-stayed span needs to maintain in actual operation; the sample load variable is the construction load variable under different construction resource forecast information; the sample sag adjustment parameter is the specific parameter for sag adjustment performed to maintain a safety distance.
[0076] Select machine learning or deep learning algorithms suitable for handling such problems, such as neural networks, decision trees, random forests, etc. These algorithms can learn the relationship between load variables and sag adjustment parameters based on historical data. BP neural network is used in this application. Call N random operators, such as different initialization weights, network structures, hyperparameters, etc. to construct N different sag adjustment analysis branches.
[0077] The sample data in the historical adjustment log is divided into a training set and a validation set. The training set is used to train the sag adjustment analysis branch, and the validation set is used to evaluate the performance of the branch. Use the training set to train N sag adjustment analysis branches. During the training process, the branch will learn how to predict the appropriate sag adjustment parameters from the sample load variables to maintain the sample safety distance. Use the validation set to evaluate the performance of the trained sag adjustment analysis branch. The evaluation indicators are the error and accuracy between the predicted sag adjustment parameters and the actual adjustment parameters. If the performance of a branch does not meet the preset accuracy constraint, that is, the error between the predicted sag adjustment parameters and the actual adjustment parameters exceeds the allowable range, continue to train the branch or adjust its parameters until its performance meets the requirements.
[0078] The trained N sag adjustment analysis branches are connected in parallel to form a sag adjustment network. In the prediction stage, the new construction load variables are input into the sag adjustment network, and each branch will give a predicted value of the sag adjustment parameter. These predicted values are then combined through averaging, voting or other strategies to obtain the final sag adjustment parameter.
[0079] Furthermore, based on the multiple construction load variables and the sag distance constraints, a plurality of sag adjustment information is obtained, and the method further comprises:
[0080] The first construction load variable and sag distance constraint are synchronized to the N sag regulation analysis branches in the sag regulation network to obtain N alternative sag regulation information; mode aggregation is performed on the N alternative sag regulation information to obtain first sag regulation information; and so on, the multiple construction load variables and sag distance constraints are input into the sag regulation network to perform sag regulation analysis to obtain the multiple sag regulation information.
[0081] In an embodiment of the present application, the first construction load variable and the sag distance constraint are synchronized to each sag regulation analysis branch in the sag regulation network. In each sag regulation analysis branch, sag regulation analysis is performed based on the input construction load variable and the sag distance constraint. Each analysis branch outputs one or more alternative sag regulation information. This information includes the adjustment amount, adjustment direction, adjustment timing, etc.
[0082] Collect the candidate sag adjustment information output by all analysis branches. Perform mode aggregation on the collected information. The mode refers to the value that appears most frequently in a set of data. In the context of sag adjustment information, mode aggregation is to find the most commonly recommended sag adjustment parameters or strategies. Use the mode as the first sag adjustment information.
[0083] For the remaining multiple construction load variables, repeat the above steps of synchronizing data, performing sag adjustment analysis and mode aggregation. After performing the above process for each construction load variable, multiple sag adjustment information corresponding to the number of construction load variables is obtained.
[0084] In the embodiments of the present application, in summary, the embodiments of the present application have at least the following technical effects:
[0085] The present application obtains historical operation activities of a spanning object; obtains the erection height parameters of a cable-type spanning frame, and obtains a sag distance constraint based on the erection height parameters and the historical operation activities, wherein the cable-type spanning frame is a construction platform constructed above the spanning object; obtains construction planning information, and obtains a sag construction adjustment sequence based on the construction planning information and the sag distance constraint; obtains environmental prediction data with the construction planning information as a constraint; optimizes the sag construction adjustment sequence based on the environmental prediction data to obtain a sag optimization adjustment sequence; and uses the sag optimization adjustment sequence to perform sag adaptive adjustment during the execution phase of the construction planning information. The present invention solves the technical problem that the prior art relies on manual experience and regular testing and is difficult to meet the requirements of construction safety and efficiency. By combining historical operation activities, construction planning information, environmental prediction data and other factors, the present invention realizes adaptive adjustment of the sag of the cable-type spanning frame, thereby achieving the technical effect of improving the safety and efficiency of construction.
[0086] Embodiment 2
[0087] Based on the same inventive concept as the sag adaptive method of a suspension cable type spanning frame in the aforementioned embodiment, Figure 2 As shown, the present application provides a suspension cable type spanning frame sag adaptive system, and the system and method embodiments in the present application are based on the same inventive concept. The system includes:
[0088] A historical operation activity acquisition module 11, wherein the historical operation activity acquisition module 11 obtains historical operation activities across objects;
[0089] A sag distance constraint acquisition module 12, wherein the sag distance constraint acquisition module 12 obtains an erection height parameter of a cable-stayed span frame, and obtains a sag distance constraint according to the erection height parameter and the historical operation activity, wherein the cable-stayed span frame is a construction platform constructed above the spanning object;
[0090] A sag adjustment analysis module 13, wherein the sag adjustment analysis module 13 obtains construction planning information, and obtains a sag construction adjustment sequence according to the construction planning information and the sag distance constraint;
[0091] An environmental data calling module 14, wherein the environmental data calling module 14 obtains environmental prediction data based on the construction planning information as a constraint;
[0092] A sag optimization adjustment sequence acquisition module 15, wherein the sag optimization adjustment sequence acquisition module 15 optimizes the sag construction adjustment sequence according to the environmental prediction data to obtain a sag optimization adjustment sequence;
[0093] The sag adaptive adjustment execution module 16 executes sag adaptive adjustment by using the sag optimization adjustment sequence during the construction planning information execution stage.
[0094] Furthermore, the system is also used to implement the following functions:
[0095] Preset an operation association threshold, and use the layout position of the cable-type spanning frame and the operation association threshold as constraints to call local spatial data of the historical operation activities to obtain local operation activities;
[0096] Collecting the working height of the local working activities to obtain working height constraints;
[0097] The sag distance constraint is obtained by solving the erection height parameter and the operation height constraint.
[0098] Furthermore, the system is also used to implement the following functions:
[0099] Performing construction load prediction according to the construction planning information, and performing construction load fitting based on the prediction results to obtain multiple construction load variables;
[0100] Based on the multiple construction load variables and the sag distance constraints, obtaining multiple sag adjustment information;
[0101] The plurality of sag adjustment information are serialized based on the construction planning information to generate the sag construction adjustment sequence.
[0102] Furthermore, the system is also used to implement the following functions:
[0103] Splitting the construction planning information to obtain multiple construction task information;
[0104] Obtain multiple sample construction resources for multiple sample construction tasks, and store the multiple sample construction tasks and the multiple sample construction resources in association with each other based on the knowledge graph to construct a construction resource analysis library;
[0105] Using the multiple construction task information to traverse the construction resource analysis library, analyzing and outputting multiple construction resource prediction information;
[0106] The plurality of construction load variables are obtained according to the plurality of construction resource prediction information.
[0107] Furthermore, the system is also used to implement the following functions:
[0108] Obtaining structural design information of the cable-suspended spanning frame;
[0109] Based on the structural design information, a spanning frame model is constructed and generated by using BIM technology;
[0110] Performing a temporary load simulation of first construction resource prediction information on the spanning frame model to obtain a first construction load variable, wherein the first construction resource prediction information is any one of the plurality of construction resource prediction information;
[0111] Similarly, a temporary load simulation of the plurality of construction resource prediction information is performed on the spanning frame model to obtain the plurality of construction load variables;
[0112] Preset a load deviation, and smooth the multiple construction load variables based on the construction planning information and the load deviation to obtain multiple optimized load variables;
[0113] The plurality of optimized load variables are used to update the plurality of construction load variables to perform a sag adjustment analysis.
[0114] Furthermore, the system is also used to implement the following functions:
[0115] Obtaining a historical adjustment log of the cable-stayed span, wherein the historical adjustment log includes multiple sets of sample safety distances, sample load variables, and sample sag adjustment parameters;
[0116] Call N random operators to construct N sag regulation analysis branches;
[0117] Using the multiple groups of sample safety distances-sample load variables-sample sag adjustment parameters to train the N sag adjustment analysis branches until the sag adjustment accuracy of the N sag adjustment analysis branches is higher than a preset accuracy constraint;
[0118] The N sag regulation analysis branches are connected in parallel to generate a sag regulation network.
[0119] Furthermore, the system is also used to implement the following functions:
[0120] Synchronizing the first construction load variable and the sag distance constraint to the N sag regulation analysis branches in the sag regulation network to obtain N candidate sag regulation information;
[0121] Performing mode aggregation on the N candidate sag adjustment information to obtain first sag adjustment information;
[0122] By analogy, the multiple construction load variables and sag distance constraints are input into the sag regulation network to perform sag regulation analysis and obtain the multiple sag regulation information.
[0123] It should be noted that the above-mentioned sequence of the embodiments of the present application is only for description and does not represent the advantages and disadvantages of the embodiments. And the above-mentioned specific embodiments of this specification are described. The processes depicted in the accompanying drawings do not necessarily require the specific order and continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.
[0124] The above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present application shall be included in the protection scope of the present application.
[0125] Figure 3 A schematic block diagram of an electronic device 300 that can be used to implement an embodiment of the present invention is shown. The electronic device is intended to represent various forms of digital computers, such as laptop computers, desktop computers, workstations, personal digital assistants, servers, blade servers, mainframe computers, and other suitable computers. The electronic device can also represent various forms of mobile devices, such as personal digital processing, cellular phones, smart phones, wearable devices, and other similar computing devices. The components shown herein, their connections and relationships, and their functions are merely examples and are not intended to limit the implementation of the present invention described and / or required herein.
[0126] The electronic device 300 includes a computing unit 301, which can perform various appropriate actions and processes according to a computer program stored in a read-only memory (ROM) 302 or a computer program loaded from a storage unit 308 into a random access memory (RAM) 303. In the RAM 303, various programs and data required for the operation of the electronic device 300 can also be stored. The computing unit 301, the ROM 302, and the RAM 303 are connected to each other via a bus 304. An input / output (I / O) interface 305 is also connected to the bus 304.
[0127] A number of components in the electronic device 300 are connected to the I / O interface 305, including: an input unit 306, such as a keyboard, a mouse, etc.; an output unit 307, such as various types of displays, speakers, etc.; a storage unit 308, such as a disk, an optical disk, etc.; and a communication unit 309, such as a network card, a modem, a wireless communication transceiver, etc. The communication unit 309 allows the electronic device 300 to exchange information / data with other devices through a computer network such as the Internet and / or various telecommunication networks.
[0128] The computing unit 301 may be a variety of general and / or special processing components with processing and computing capabilities. Some examples of the computing unit 301 include, but are not limited to, a central processing unit (CPU), a graphics processing unit (GPU), various dedicated artificial intelligence (AI) computing chips, various computing units running machine learning model algorithms, digital signal processors (DSPs), and any appropriate processors, controllers, microcontrollers, etc. The computing unit 301 performs the various methods and processes described above, such as methods S100~S600. For example, in some embodiments, methods S100~S600 may be implemented as a computer software program, which is tangibly contained in a machine-readable medium, such as a storage unit 308. In some embodiments, part or all of the computer program may be loaded and / or installed on the electronic device 300 via the ROM 302 and / or the communication unit 309. When the computer program is loaded into the RAM 303 and executed by the computing unit 301, one or more steps of the methods S100~S600 described above may be performed. Alternatively, in other embodiments, the computing unit 301 may be configured to execute methods S100 - S600 in any other appropriate manner (eg, by means of firmware).
[0129] Various implementations of the systems and techniques described above herein can be implemented in digital electronic circuit systems, integrated circuit systems, field programmable gate arrays (FPGAs), application specific integrated circuits (ASICs), application specific standard products (ASSPs), systems on chips (SOCs), load programmable logic devices (CPLDs), computer hardware, firmware, software, and / or combinations thereof. These various implementations can include: being implemented in one or more computer programs that can be executed and / or interpreted on a programmable system including at least one programmable processor, which can be a special purpose or general purpose programmable processor that can receive data and instructions from a storage system, at least one input device, and at least one output device, and transmit data and instructions to the storage system, the at least one input device, and the at least one output device.
[0130] The program code for implementing the method of the present invention can be written in any combination of one or more programming languages. These program codes can be provided to a processor or controller of a general-purpose computer, a special-purpose computer or other programmable data processing device, so that the program code, when executed by the processor or controller, enables the functions / operations specified in the flow chart and / or block diagram to be implemented. The program code can be executed entirely on the machine, partially on the machine, partially on the machine as a stand-alone software package and partially on a remote machine, or entirely on a remote machine or server.
[0131] In the context of the present invention, a machine-readable medium may be a tangible medium that may contain or store a program for use by or in conjunction with an instruction execution system, device, or equipment. A machine-readable medium may be a machine-readable signal medium or a machine-readable storage medium. A machine-readable medium may include, but is not limited to, an electronic, magnetic, optical, electromagnetic, infrared, or semiconductor system, device, or device, or any suitable combination of the foregoing. A more specific example of a machine-readable storage medium may include an electrical connection based on one or more lines, a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM), an optical fiber, a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
[0132] To provide interaction with a user, the systems and techniques described herein can be implemented on a computer having: a display device (e.g., a CRT (cathode ray tube) or LCD (liquid crystal display) monitor) for displaying information to the user; and a keyboard and pointing device (e.g., a mouse or trackball) through which the user can provide input to the computer. Other types of devices can also be used to provide interaction with the user; for example, the feedback provided to the user can be any form of sensory feedback (e.g., visual feedback, auditory feedback, or tactile feedback); and input from the user can be received in any form (including acoustic input, voice input, or tactile input).
[0133] The systems and techniques described herein may be implemented in a computing system that includes back-end components (e.g., as a data server), or a computing system that includes middleware components (e.g., an application server), or a computing system that includes front-end components (e.g., a user computer with a graphical user interface or a web browser through which a user can interact with implementations of the systems and techniques described herein), or a computing system that includes any combination of such back-end components, middleware components, or front-end components. The components of the system may be interconnected by any form or medium of digital data communication (e.g., a communication network). Examples of communication networks include: a local area network (LAN), a wide area network (WAN), and the Internet.
[0134] A computer system may include a client and a server. The client and the server are generally remote from each other and usually interact through a communication network. The relationship of client and server is generated by computer programs running on respective computers and having a client-server relationship with each other. The server may be a cloud server, a server of a distributed system, or a server combined with a blockchain.
[0135] It should be understood that the various forms of processes shown above can be used to reorder, add or delete steps. For example, the steps described in the present invention can be executed in parallel, sequentially or in different orders, as long as the desired results of the technical solution of the present invention can be achieved, and this document does not limit this.
[0136] This specification and drawings are merely exemplary illustrations of the present application and are deemed to cover any and all modifications, variations, combinations or equivalents within the scope of the present application. Obviously, a person skilled in the art may make various modifications and variations to the present application without departing from the scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the present application and its equivalents, the present application intends to include these modifications and variations.
Claims
1. A method for adaptive sag of a cable-stayed span, characterized in that: The method comprises: Obtaining historical operation activities across the object, wherein the historical operation activities include operation time, operation type, and operation height; Obtaining an erection height parameter of a cable-stayed span, and obtaining a sag distance constraint according to the erection height parameter and the historical operation activity, wherein the cable-stayed span is a construction platform constructed above the spanning object, the erection height parameter includes a main span, a side span, and a spanning height, and the sag distance constraint is a sag safety distance of the cable-stayed span under maximum load and adverse weather conditions; Obtaining construction planning information, and obtaining a sag construction adjustment sequence according to the construction planning information and the sag distance constraint; the construction planning information includes a construction schedule, construction steps, a material list, and equipment configuration, and the sag construction adjustment sequence includes an adjustment timing, an adjustment method, and an adjustment target value; Taking the construction planning information as a constraint, obtaining environmental prediction data; the environmental prediction data includes temperature, humidity, wind speed, wind direction, and precipitation probability; Optimizing the sag construction adjustment sequence according to the environmental prediction data to obtain a sag optimization adjustment sequence; During the execution phase of the construction planning information, the sag optimization adjustment sequence is used to perform sag adaptive adjustment; the sag adaptive adjustment is used to automatically adjust the tension of the wire and the number of insulator strings according to the real-time monitoring data and the guidance in the sag optimization adjustment sequence.
2. The method according to claim 1, characterized in that The obtaining of the erection height parameter of the cable-stayed span frame and obtaining the sag distance constraint according to the erection height parameter and the historical operation activities include: Preset an operation association threshold, and use the layout position of the cable-type spanning frame and the operation association threshold as constraints to call local spatial data of the historical operation activities to obtain local operation activities; Collecting the working height of the local working activities to obtain working height constraints; The sag distance constraint is obtained by solving the erection height parameter and the operation height constraint.
3. The method according to claim 1, characterized in that The obtaining of the construction planning information and obtaining the sag construction adjustment sequence according to the construction planning information and the sag distance constraint includes: Performing construction load prediction according to the construction planning information, and performing construction load fitting based on the prediction results to obtain multiple construction load variables; Based on the multiple construction load variables and the sag distance constraints, obtaining multiple sag adjustment information; The plurality of sag adjustment information are serialized based on the construction planning information to generate the sag construction adjustment sequence.
4. The method according to claim 3, characterized in that The construction load prediction is performed according to the construction planning information, and the construction load fitting is performed based on the prediction result to obtain multiple construction load variables, including: Splitting the construction planning information to obtain multiple construction task information; Obtain multiple sample construction resources for multiple sample construction tasks, and store the multiple sample construction tasks and the multiple sample construction resources in association with each other based on the knowledge graph to construct a construction resource analysis library; Using the multiple construction task information to traverse the construction resource analysis library, analyzing and outputting multiple construction resource prediction information; The plurality of construction load variables are obtained according to the plurality of construction resource prediction information.
5. The method according to claim 4, characterized in that The obtaining of the plurality of construction load variables according to the plurality of construction resource prediction information comprises: Obtaining structural design information of the cable-suspended spanning frame; Based on the structural design information, the spanning frame model is constructed and generated by using BIM technology; Performing a temporary load simulation of first construction resource prediction information on the spanning frame model to obtain a first construction load variable, wherein the first construction resource prediction information is any one of the plurality of construction resource prediction information; Similarly, a temporary load simulation of the plurality of construction resource prediction information is performed on the spanning frame model to obtain the plurality of construction load variables; Preset a load deviation, and smooth the multiple construction load variables based on the construction planning information and the load deviation to obtain multiple optimized load variables; The plurality of optimized load variables are used to update the plurality of construction load variables to perform a sag adjustment analysis.
6. The method according to claim 5, characterized in that Based on the multiple construction load variables and the sag distance constraints, multiple sag adjustment information is obtained, before, including: Obtaining a historical adjustment log of the cable-stayed span, wherein the historical adjustment log includes multiple sets of sample safety distances, sample load variables, and sample sag adjustment parameters; Call N random operators to construct N sag regulation analysis branches; Using the multiple groups of sample safety distances-sample load variables-sample sag adjustment parameters to train the N sag adjustment analysis branches until the sag adjustment accuracy of the N sag adjustment analysis branches is higher than a preset accuracy constraint; The N sag regulation analysis branches are connected in parallel to generate a sag regulation network.
7. The method according to claim 6, characterized in that The obtaining of a plurality of sag adjustment information based on the plurality of construction load variables and the sag distance constraints includes: Synchronizing the first construction load variable and the sag distance constraint to the N sag regulation analysis branches in the sag regulation network to obtain N candidate sag regulation information; Performing mode aggregation on the N candidate sag adjustment information to obtain first sag adjustment information; By analogy, the multiple construction load variables and sag distance constraints are input into the sag regulation network to perform sag regulation analysis and obtain the multiple sag regulation information.
8. A cable-type spanning frame sag adaptive system, characterized in that: The system comprises: A historical operation activity acquisition module, wherein the historical operation activity acquisition module obtains historical operation activities across objects, wherein the historical operation activities include operation time, operation type, and operation height; A sag distance constraint acquisition module, wherein the sag distance constraint acquisition module obtains an erection height parameter of a cable-stayed span, and obtains a sag distance constraint according to the erection height parameter and the historical operation activity, wherein the cable-stayed span is a construction platform constructed above the spanning object, the erection height parameter includes a main span, a side span, and a spanning height, and the sag distance constraint is a sag safety distance of the cable-stayed span under maximum load and adverse weather conditions; A sag adjustment analysis module, wherein the sag adjustment analysis module obtains construction planning information, and obtains a sag construction adjustment sequence according to the construction planning information and the sag distance constraint; the construction planning information includes a construction schedule, construction steps, a material list, and equipment configuration, and the sag construction adjustment sequence includes an adjustment timing, an adjustment method, and an adjustment target value; An environmental data calling module, wherein the environmental data calling module uses the construction planning information as a constraint to obtain environmental prediction data; the environmental prediction data includes temperature, humidity, wind speed, wind direction, and precipitation probability; A sag optimization adjustment sequence acquisition module, wherein the sag optimization adjustment sequence acquisition module optimizes the sag construction adjustment sequence according to the environmental prediction data to obtain a sag optimization adjustment sequence; A sag adaptive adjustment execution module, wherein the sag adaptive adjustment execution module uses the sag optimization adjustment sequence to perform sag adaptive adjustment during the construction planning information execution stage; the sag adaptive adjustment is used to automatically adjust the tension of the wire and the number of insulator strings according to the real-time monitoring data and the guidance in the sag optimization adjustment sequence.
9. An electronic device comprising at least one processor; and a memory connected in communication with the at least one processor; characterized in that: The memory stores instructions that can be executed by the at least one processor, and the instructions are executed by the at least one processor to enable the at least one processor to perform the method according to any one of claims 1 to 7.
10. A non-transitory computer-readable storage medium storing computer instructions, characterized in that: The computer instructions are used to cause the computer to execute the method according to any one of claims 1-7.