A construction technology based on the center-dividing belt using a rotary drill to quickly drop piers

By using a rotary drill to quickly drop the piers during the construction of the bridge piers on the highway, combined with the adjustment of traffic flow and risk coefficient, efficient bridge pier construction was achieved, solving the problems of low construction efficiency and large traffic impact, and improving construction efficiency. and traffic safety.

CN118563671BActive Publication Date: 2024-10-25POLY CHANGDA ENGINEERING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411052836.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-10-25
Estimated Expiration
2044-08-02

AI Technical Summary

Technical Problem

When the existing technology is constructing bridge piers on highways, the construction efficiency is low and has a great impact on traffic, resulting in long blockage time and affecting traffic order.

Method used

The rapid pier-falling construction technology of rotary drilling based on the middle zone is adopted, and the pre-drilling measurement, setting out and construction of multiple bridge piers are carried out at the same time, the traffic flow and risk coefficient are adjusted to optimize the construction sequence and scope, and reduce the length and construction time of the blocked road section. time.

Benefits of technology

Improved construction efficiency, reduced the impact on traffic, ensured reduced blocking time when traffic flow was high, improved construction efficiency when traffic flow was low, and improved construction accuracy by adjusting the pile foundation center judgment range and strengthening the anti-collision structure and security.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118563671B_ABST
    Figure CN118563671B_ABST
Patent Text Reader

Abstract

The invention relates to a construction process for quickly dropping piers by using a rotary drilling drill based on a center dividing zone, belongs to the technical field, and comprises the following steps: step one: measuring and laying out before drilling a hole for the first pier, and drilling a hole at the layout point by using a rotary drilling drill; step two: constructing the upper structure of the first pier, starting measuring and laying out before drilling a hole for a subsequent pier, and drilling a hole at the layout point by using a rotary drilling drill; step three: constructing the upper structure of the pier after drilling, and simultaneously starting measuring and laying out before drilling a hole for a subsequent pier, and drilling a hole at the layout point by using a rotary drilling drill; step four: repeating step three until the construction of the piers based on the center dividing zone is completed; the construction efficiency is high and the impact on traffic is small.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of high-speed construction, and in particular relates to a construction process for rapidly dropping piers by using a rotary drill based on a center-dividing belt. Background Art

[0002] The median strip, or central dividing strip, is an important component of the highway. A general highway bridge has a gap between the two-way lanes. This gap and the median guardrails on both sides of the gap together constitute the median strip. When the highway is expanded, it is necessary to build a new highway bridge on the basis of the original highway bridge. At this time, the new highway bridge chooses to set the piers in the gap of the central dividing strip of the existing highway.

[0003] Although this type of structure saves area and improves the flexibility of high-speed bridge layout, it is inevitable that this type of structure will have an impact on the road section near the pier during construction. For example, the general construction method is: first, close the highway section near the pier construction site, use a rotary drilling rig to dig holes for the pier construction, and carry out column foundation construction. Then, cancel the closed section and change it to a partial closure, and carry out pier construction to complete the pier. However, in the above method, it is necessary to carry out a new pier construction after the construction of one pier is completed, which is inefficient. The low construction efficiency will also lead to a longer time for blocking the highway, affecting traffic. For this reason, a construction process for rapid pier dropping based on a median strip using a rotary drilling rig is needed, which has high construction efficiency and less impact on traffic. Summary of the invention

[0004] In order to solve the above problems existing in the prior art, the present invention provides a construction process for quickly dropping piers using a rotary drill based on a center-dividing belt, which has the characteristics of high construction efficiency and less impact on traffic.

[0005] The purpose of the present invention can be achieved through the following technical solutions:

[0006] A construction process for quickly dropping piers using a rotary drill based on a center-dividing belt includes the following steps:

[0007] Step 1: Conduct survey and layout before drilling the first pier, and use a rotary drill to drill at the layout point;

[0008] Step 2: Carry out superstructure construction of the first pier, measure and stake out before drilling the next pier, and use a rotary drill to drill at the staked point;

[0009] Step 3: Carry out superstructure construction on the piers that have been drilled, and start surveying and staking out the next pier before drilling, and use a rotary drill to drill holes at the staking out points;

[0010] Step 4: Repeat step 3 until the construction of the bridge piers based on the median strip is completed.

[0011] As a preferred technical solution of the present invention, step three also includes: during the construction of the superstructure of the drilled pier, detecting the traffic flow and judging whether the traffic flow is within a threshold range; when the traffic flow exceeds the threshold range, starting the measurement and layout before drilling the next pier after the construction of the superstructure of the drilled pier is completed; when the traffic flow is less than the threshold range, starting the measurement and layout before drilling the next two piers, and drilling at the layout point using a rotary drill; when the traffic flow is within the threshold range, starting the measurement and layout before drilling the next pier at the same time, and drilling at the layout point using a rotary drill.

[0012] As a preferred technical solution of the present invention, the step three further comprises: during measurement and setting out, judging whether the determined pile foundation center is within a judgment range around the theoretical coordinates;

[0013] As a preferred technical solution of the present invention, the step three further includes: when the traffic flow exceeds the threshold range, expanding the determination range, and when the traffic flow is less than the threshold range, narrowing the determination range toward the theoretical coordinates;

[0014] As a preferred technical solution of the present invention, step four also includes: before each repetition of step three, a risk factor assessment is performed on the superstructure of the drilled pier; when the risk factor exceeds a threshold, step three is executed and an additional anti-collision layer is constructed during the construction of the superstructure of the drilled pier; when the risk factor is less than the threshold, step three is executed without performing additional actions.

[0015] As a preferred technical solution of the present invention, before each repetition of step three, the superstructure of the drilled pier is evaluated for a risk factor F, F=(θ / θ0)×(L / L0)×(180 / D), wherein θ is the angle between the median guardrail and the road surface, L is the traffic volume during normal traffic on the current section, D is the turning angle of the current section, θ0 is a pre-calculated reference angle constant, and L0 is a pre-calculated reference traffic volume constant.

[0016] As a preferred technical solution of the present invention, the step one further includes: setting a dust detection device; the step three further includes: the dust monitoring device issues an alarm when the dust is greater than a threshold value.

[0017] The beneficial effects of the present invention are:

[0018] (1) By carrying out the survey and layout of the next pier while the superstructure of the first pier is being constructed, the construction of one pier and the survey and layout of another pier can be completed at the same time, thus shortening the construction time, improving the construction efficiency and reducing the impact on traffic;

[0019] (2) By judging the traffic flow each time step 3 is executed, the number of bridge piers under construction at the same time is reduced when the traffic flow is large, thereby reducing the length of the blocked road section. This ensures that the impact on traffic is reduced when the traffic flow is large, and increases the number of bridge piers under construction at the same time when the traffic flow is small. This ensures that the construction efficiency is improved without affecting traffic when the traffic flow is small.

[0020] (3) By adjusting the judgment range of the pile foundation center according to the traffic flow judgment results, when multiple bridge piers are being constructed at the same time, the influence of random factors on the measurement accuracy reduction caused by the inability to correct the measurement results of the previous bridge pier is reduced. When only one bridge pier is being constructed at the same time, the judgment range is expanded to reduce the time spent in the pile foundation center alignment process. While ensuring the measurement accuracy through the previously completed bridge pier, the construction efficiency is also taken into account.

[0021] (4) Before executing step 3 each time, the risk factor F = (θ / θ0) × (L / L0) × (180 / D) is calculated for the bridge pier under construction. When the risk factor exceeds the threshold, step 3 is executed and an additional anti-collision layer is constructed during the construction of the upper structure of the pier after drilling. When the risk factor is less than the threshold, step 3 is executed without performing additional actions. When the probability of an accident occurring on a certain section of road is high, the anti-collision structure needs to be additionally strengthened to ensure the strength of the bridge pier structure. When the probability of an accident occurring on a certain section of road is low, there is no need to additionally strengthen the anti-collision structure to ensure construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to facilitate understanding by those skilled in the art, the present invention is further described below with reference to the accompanying drawings.

[0023] Figure 1 It is a flowchart of the overall steps of the present invention;

[0024] Figure 2 This is a flowchart of step 2 of the present invention;

[0025] Figure 3 This is a flowchart of step three of the present invention. DETAILED DESCRIPTION

[0026] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation methods, structures, features and effects of the present invention are described in detail below in conjunction with the accompanying drawings and preferred embodiments.

[0027] See also Figure 1-3 A construction process for quickly dropping piers using a rotary drill based on a center-split belt includes the following steps:

[0028] Step 1: Conduct survey and layout before drilling the first pier, and use a rotary drill to drill at the layout point;

[0029] Specifically, for surveying and setting out: the coordinates specified in the construction drawings are used as the theoretical coordinates of each pile, the center of the pile position is set out by aligning the encrypted guide points with the theoretical coordinates, the pile foundation center is determined by connecting the four points around the pile in a cross, and drilling is performed at the set out point. In this embodiment, a steel casing needs to be buried before the drilling operation, and the axial line of the steel casing coincides with the pile foundation center determined by the cross connection. After the steel casing is buried, the rotary drilling drill is used to drill holes to complete the foundation column construction of the current bridge pier construction;

[0030] After the first pier is staked out and drilled in step 1, proceed to step 2;

[0031] Step 2: Carry out superstructure construction of the first pier, measure and stake out before drilling the next pier, and use a rotary drill to drill at the staked point;

[0032] Since the traditional method of construction of the second pier is to start after the first pier is completely placed, the efficiency is low, which leads to the extension of the overall construction of several piers, and the time period of traffic impact is extended, which has a greater impact on traffic. At this time, it is necessary to shorten the overall construction time of the pier as much as possible, improve the construction efficiency, and reduce the impact on traffic. Therefore, step 2: the upper structure of the first pier is constructed, and at the same time, the measurement and layout before drilling the next pier is started, and the rotary drilling drill is used to drill at the layout point;

[0033] Specifically, during the process of hoisting and pouring the steel cage of the first pier, the piers adjacent to the first pier along the extension direction of the bridge begin to be measured and laid out. The measurement and laying out method is the same as that of the first pier. At this time, the construction of one pier and the measurement and laying out of another pier can be carried out at the same time.

[0034] By carrying out the survey and layout of the next pier while the superstructure of the first pier is being constructed, the construction of one pier and the survey and layout of another pier can be completed at the same time, thus shortening the construction time, improving the construction efficiency and reducing the impact on traffic;

[0035] When the measurement and setting out of the next bridge pier in step 2 is completed, execute step 3;

[0036] Step 3: Carry out superstructure construction on the piers that have been drilled, and start surveying and staking out the next pier before drilling, and use a rotary drill to drill holes at the staking out points;

[0037] Specifically, step three is that after the upper layer construction of each pier that has been drilled begins, the piers adjacent to the drilled piers along the extension direction of the bridge begin to be measured and laid out; at this time, step four is executed: step three is repeated until the construction of the piers based on the median strip is completed, that is, one pier is carrying out the upper structure construction, and the other pier is carrying out the measurement, layout and drilling, then the upper structure construction is implemented on the drilled pier, and the next pier is carrying out the measurement, layout and drilling mode, so as to realize the synchronous construction of the two piers uninterruptedly, reduce the construction time, and reduce the impact on traffic.

[0038] In the above steps, for each bridge pier construction, it is necessary to block part of the lanes of some sections of the current expressway to divide the construction area and facilitate the construction of workers. In this embodiment, the blocked part is the overtaking lane closest to the median strip in the two-way lane. When one bridge pier is under construction, the overtaking lane blocking part only covers the section around one bridge pier. When two bridge piers are under construction at the same time, the overtaking lane blocking will cover the sections of the two bridge piers. However, the blocking of the overtaking lane will still affect the traffic, and the longer the blocking part, the greater the impact on the traffic.

[0039] At the same time, for traffic, when the traffic volume is small, the traffic does not need more lanes to travel, and the impact of partially blocked roads on traffic is small. At this time, more bridge piers can be constructed at the same time. When the traffic volume is large, the traffic needs more lanes to travel, and the impact of partially blocked roads on traffic is greater. When the traffic volume exceeds the threshold, it is necessary to reduce the number of bridge piers constructed at the same time as much as possible, thereby reducing the length of the blocked section of the overtaking lane, so as to ensure traffic flow;

[0040] To this end, step three also includes: each time step three is executed, during the construction of the upper structure of the pier after drilling, firstly detecting the traffic flow and determining whether the traffic flow is within a threshold range;

[0041] When the traffic volume exceeds the threshold range, after the construction of the upper structure of the pier that has been drilled is completed, the measurement and layout before drilling the next pier will be started. At this time, the traffic volume is large, and the number of piers under construction at the same time needs to be reduced as much as possible, thereby reducing the length of the blocked section of the overtaking lane to ensure traffic flow. At this time, the measurement and layout of the next construction will no longer be carried out at the same time as the drilling of the upper structure of the pier has been completed, and the blocking of the overtaking lane will be maintained around the pier that has been drilled, so that the construction time is appropriately extended to ensure that the impact on traffic is reduced;

[0042] When the traffic flow is less than the threshold range, it means that the blocking of the overtaking lane has less impact on traffic. At this time, more bridge piers can be constructed at the same time to ensure construction efficiency. At this time, while the upper structure of the bridge pier is drilled, the measurement and layout before drilling of the next two bridge piers are started, and the rotary drilling drill is used to drill at the layout point. At this time, it is equivalent to constructing three bridge piers at the same time, which further ensures construction efficiency and takes into account the impact of reducing traffic under the condition of less traffic flow;

[0043] When the traffic flow is within the threshold range, it means that the traffic flow is within the normal range. At this time, it is necessary to ensure the construction efficiency while reducing the impact on traffic. At the same time, the measurement and layout before drilling the next pier is started, and the rotary drilling drill is used to drill at the layout point;

[0044] After the drilling of the bridge pier in the last step 3 is completed, when the step 3 is executed again, the traffic flow is re-judged, and then the action to be performed in the current step 3 is determined;

[0045] By judging the traffic flow each time step three is executed and reducing the number of bridge piers under construction at the same time when the traffic flow is large, thereby reducing the length of the blocked road section, it is ensured that the impact on traffic is reduced when the traffic flow is large, and the number of bridge piers under construction at the same time is increased when the traffic flow is small, thereby ensuring that the construction efficiency is improved without affecting the traffic when the traffic flow is small.

[0046] Specifically, in steps one, two and three, when measuring and laying out, the pile foundation center is determined by connecting four points around the pile in a cross position, and further measurement is performed to determine whether the pile foundation center is within the determination range around the theoretical coordinates, and then determine whether the pile foundation center of the current pier meets the standards.

[0047] During the construction process, there are random factors that affect the positioning accuracy of the bridge piers. Therefore, it is necessary to measure the piers after the construction of each pier is completed, and correct the measurement results of the next pier according to the measurement results. When two or three piers are constructed at the same time based on the traffic flow, it is impossible to correct the random factors of the previous pier before constructing the next pier, which inevitably affects the measurement accuracy. In order to take into account both construction efficiency and accuracy, step three also includes: when the traffic flow exceeds the threshold range, the judgment range is expanded; when the traffic flow is less than or within the threshold range, the judgment range is narrowed toward the theoretical coordinates;

[0048] When the traffic flow exceeds the threshold range, it means that the construction of the next pier will be carried out after the construction of the previous pier is completed. At this time, the measurement and setting out of the next pier can be assisted by taking the previous pier as the benchmark. At this time, in order to reduce the impact of non-simultaneous construction on construction efficiency, the judgment range is too large. At this time, the pile foundation center has a greater probability of being within the judgment range, reducing the probability of pile foundation center recalibration affecting construction efficiency. While ensuring measurement accuracy through the previous pier, construction efficiency is taken into account;

[0049] When the traffic flow is less than or within the threshold range, it means that the construction of the next or next two piers is being carried out at the same time as the construction of the previous pier. Since it is impossible to correct the random factors based on the measurement results of the previous pier before carrying out the construction of the next pier, it will inevitably affect the measurement accuracy and it is necessary to improve the measurement accuracy. At this time, the judgment range is narrowed to ensure that the center of the pile foundation is closer to the theoretical coordinates. While carrying out the construction of multiple piers at the same time, the measurement accuracy is taken into account by narrowing the judgment range.

[0050] By adjusting the judgment range of the pile foundation center based on the traffic flow judgment results, when multiple piers are constructed at the same time, the inability to correct the impact of random factors on the reduced measurement accuracy caused by the measurement results of the previous pier is reduced. When only one pier is constructed at the same time, the judgment range is expanded to reduce the time spent in the pile foundation center alignment process. While ensuring the measurement accuracy through the previous completed pier, the construction efficiency is taken into account.

[0051] During construction, since the piers are set in the median strip of the high-speed bridge, there is a certain probability that a vehicle will collide with the guardrail when the high-speed bridge is open to traffic after the piers are built. When the vehicle's roll angle after the collision extends beyond the guardrail and invades the median strip, there is a probability that the vehicle will collide with the pier in the median strip. At this time, the pier needs to be designed with an additional anti-collision structure during construction. When the probability of an accident on a certain section of road is high, the anti-collision structure needs to be additionally strengthened to ensure the strength of the pier structure. When the probability of an accident on a certain section of road is low, there is no need to additionally strengthen the anti-collision structure to ensure construction efficiency. For this reason, step four also includes: before each repetition of step three, the upper structure of the drilled pier is evaluated for a risk factor. When the risk factor exceeds the threshold, step three is executed and an additional anti-collision layer is constructed during the construction of the upper structure of the drilled pier. When the risk factor is less than the threshold, step three is executed without performing additional actions.

[0052] Specifically, before each repetition of step three, the upper structure of the drilled pier is evaluated for the risk factor F, F = (θ / θ0) × (L / L0) × (180 / D), where θ is the angle between the median guardrail and the road surface, L is the traffic volume during normal traffic on the current section, D is the turning angle of the current section, θ0 is the pre-calculated reference angle constant, L0 is the pre-calculated reference traffic volume constant, and the operator sets the risk factor threshold F0 in advance through calculation;

[0053] θ is the angle between the side of the guardrail close to the road and the road surface. When the angle θ is large, it means that the side of the guardrail close to the road is inclined toward the bridge pier to a greater extent. When the vehicle collides with the guardrail and fits the side of the guardrail close to the road, it will be tilted closer to the bridge pier to a greater extent. The collision probability between the vehicle and the bridge pier is high. At this time, the value of F=(θ / θ0)×(L / L0)×(180 / D) increases, the risk coefficient increases, and the probability of F exceeding the threshold increases. Similarly, when the angle θ is small, the collision probability between the vehicle and the bridge pier is low. The probability of the vehicle contacting the bridge pier when colliding is introduced into the calculation of the risk coefficient, so that the risk coefficient is positively correlated with the probability of the vehicle contacting the bridge pier when colliding, taking into account both structural strength and construction efficiency.

[0054] L is the quantified traffic flow of the highway section around the bridge pier to be constructed after the drilling is completed in the current execution of step 3. When the traffic flow L is large, it means that there is a greater probability of accidents in the section around the bridge pier to be constructed in the current step 3, and then there is a greater probability of contact between the vehicle and the bridge pier. At this time, the value of F=(θ / θ0)×(L / L0)×(180 / D) increases, and the probability of F exceeding the threshold increases; similarly, when the traffic flow L is small, the probability of collision between the vehicle and the bridge pier is low, and the traffic flow L is introduced into the calculation of the risk coefficient, so that the risk coefficient is positively correlated with the probability of contact between the vehicle and the bridge pier when a collision occurs, taking into account both structural strength and construction efficiency;

[0055] D is the turning angle of the high-speed road section around the bridge pier to be constructed after the drilling of step 3 is completed. When D=180°, it means that the road section near the bridge pier to be constructed is a straight line, and the probability of an accident is low. At this time, the value of F=(θ / θ0)×(L / L0)×(180 / D) is small. When the value of D is small, it means that there is curvature in the road section near the bridge pier to be constructed, and the smaller the value of D, the greater the curvature of the road section, and the greater the probability of an accident. At this time, the value of F=(θ / θ0)×(L / L0)×(180 / D) is large, and the curvature D of the road section is introduced into the calculation of the risk coefficient, so that the risk coefficient is positively correlated with the probability of contact between the vehicle and the bridge pier when a collision occurs, taking into account both structural strength and construction efficiency.

[0056] By calculating the risk factor F = (θ / θ0) × (L / L0) × (180 / D) for the bridge pier under construction before executing step three each time, when the risk factor exceeds the threshold, executing step three and additionally constructing an anti-collision layer during the construction of the upper structure of the pier after drilling, and when the risk factor is less than the threshold, executing step three without performing additional actions, when the probability of an accident occurring on a certain section of road is high, the anti-collision structure needs to be additionally strengthened to ensure the strength of the pier structure, and when the probability of an accident occurring on a certain section of road is low, there is no need to additionally strengthen the anti-collision structure to ensure construction efficiency.

[0057] In order to reduce the impact of construction on the environment, in step one: the workers set up a dust detection device near the construction site; when executing step three: the dust monitoring device detects the dust and determines whether the dust density is greater than the threshold, and issues an alarm when the dust is greater than the threshold.

[0058] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.

Claims

1. A construction process based on the center-dividing belt and using a rotary drill to quickly drop piers, characterized in that: The following steps are involved: Step 1: Conduct survey and layout before drilling the first pier, and use a rotary drill to drill at the layout point; Step 2: Carry out superstructure construction of the first pier, measure and stake out before drilling the next pier, and use a rotary drill to drill at the staked point; Step 3: Carry out superstructure construction on the piers that have been drilled, and start surveying and staking out the next pier before drilling, and use a rotary drill to drill holes at the staking out points; Step 4: Repeat step 3 until the construction of the bridge pier based on the median strip is completed; The step three also includes: during the construction of the upper structure of the bored bridge pier, detecting the traffic flow and determining whether the traffic flow is within a threshold range, when the traffic flow exceeds the threshold range, starting to measure and stake out the next pier before drilling after the construction of the upper structure of the bored bridge pier is completed, when the traffic flow is less than the threshold range, starting to measure and stake out the next two piers before drilling, and drilling at the stakeout point using a rotary drilling drill, when the traffic flow is within the threshold range, starting to measure and stake out the next pier before drilling, and drilling at the stakeout point using a rotary drilling drill; The step 4 further comprises: before each repetition of step 3, performing a risk factor assessment on the upper structure of the pier after drilling; The step four also includes: before each repetition of step three, the risk factor F of the upper structure of the drilled pier is evaluated, F=(θ / θ0)×(L / L0)×(180 / D), wherein θ is the angle between the median guardrail and the road surface, L is the traffic volume during normal traffic on the current section, D is the turning angle of the current section, θ0 is a pre-calculated reference angle constant, and L is a pre-calculated reference traffic volume constant. When the risk factor exceeds a threshold, step three is executed and an anti-collision layer is additionally constructed during the construction of the upper structure of the drilled pier. When the risk factor is less than the threshold, step three is executed without performing additional actions.

2. According to claim 1, a construction process for rapid pier placement based on a center-dividing belt using a rotary drill, characterized in that: The step three also includes: during measurement and setting out, judging whether the determined pile foundation center is within a judgment range around the theoretical coordinates.

3. The construction process of using a rotary drill to quickly drop piers based on a center-dividing belt according to claim 2 is characterized by: The step three also includes: when the traffic flow exceeds the threshold range, expanding the determination range, and when the traffic flow is less than the threshold range, shrinking the determination range toward the theoretical coordinates.

4. The construction process of rapid pier placement based on the center-dividing belt using a rotary drill according to claim 1 is characterized by: The step one also includes: setting a dust detection device; the step three also includes: the dust monitoring device issues an alarm when the dust is greater than a threshold value.