Anti-scouring groin structure and construction method

By setting up the side baffles and end baffles of the cofferdam in the groyne structure to form a closed space, vehicles and equipment can run on the base and filling bodies of the groyne, solving the problem of low efficiency in groyne construction and achieving efficient construction and maintenance.

CN118563710BActive Publication Date: 2024-10-18浙江江南春建设集团有限公司
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411049182.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-10-18
Estimated Expiration
2044-08-01

AI Technical Summary

Technical Problem

The construction efficiency of spur dams is low, mainly because the process of setting up cofferdams and spreading rocks on the water by ships takes a long time, resulting in low construction efficiency.

Method used

The anti-scush groyne structure is adopted, including the river bed, river bank and groyne. The groyne base is surrounded by the river bank to form a cofferdam structure. The side baffles and end baffles of the cofferdam form a closed space. Vehicles and equipment can run on the groyne base and filling body, reducing The use of water working tools, and convenient construction and maintenance through prefabricated covers and support structures.

Benefits of technology

It improves the construction efficiency of groyne dam, reduces the construction difficulty, shortens the construction period, simplifies the maintenance and bottom protection process, and reduces the dependence on ships.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118563710B_ABST
    Figure CN118563710B_ABST
Patent Text Reader

Abstract

The invention discloses an anti-scouring spur dike structure and a construction method, and belongs to the technical field of water conservancy dam bodies. The structure comprises a riverbed, a river bank and a spur dike, wherein the river bank is located on both sides of the extending direction of the riverbed, a plurality of spur dikes are arranged at intervals along the extending direction of the river bank, the spur dike also comprises a spur dike base, a spur dike filling body, a cofferdam side baffle, a cofferdam end baffle, a spur dike body, a prefabricated cover body and a supporting structure, the spur dike base is cast and arranged at the junction of the riverbed and the river bank, the spur dike base is in a semicircular shape, and the spur dike base and the river bank are surrounded to form a cofferdam structure. The vehicles and equipment for construction work of the invention can be directly operated on the spur dike base and the spur dike filling body, and when the spur dike body is cast, the vehicles and equipment can be directly operated on the spur dike body to cast the next closed space, so that there is no need to use water operation tools such as ships during the construction process, which can effectively reduce the construction difficulty, thereby improving the construction efficiency of the spur dike.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an anti-scouring groin structure and a construction method, belonging to the technical field of water conservancy dam bodies. Background Art

[0002] A spur dam, also known as a "stream diversion dam", is a river regulation structure that extends into the river at right angles or obliquely to the river bank. The end of the spur dam is connected to the embankment in a "T" shape.

[0003] During the construction of the spur dam, ships are needed to set up cofferdams on the water surface, and then the dam body is constructed. At the same time, a large amount of stone needs to be piled on the bottom of the riverbed as the dam bottom. Since ships sail slowly on the water surface and need to travel back and forth between the river banks to replenish construction materials, this will take a lot of time, thereby reducing the construction efficiency of the spur dam. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide an anti-scouring groin structure and a construction method, which solves the problem of low construction efficiency of the groin in the prior art.

[0005] The technical problem to be solved by the present invention is achieved by adopting the following technical scheme: an anti-scouring spur dam structure, including a riverbed, a river bank and a spur dam, the river bank is located on both sides of the extending direction of the riverbed, a number of spur dams are arranged at intervals along the extending direction of the river bank, the spur dam also includes a spur dam base, a spur dam filling body, a cofferdam side baffle, a cofferdam end baffle, a spur dam body, a prefabricated cover body and a supporting structure, the spur dam base is cast and arranged at the junction of the riverbed and the river bank, the spur dam base is semicircular, the spur dam base and the river bank are surrounded to form a cofferdam structure, the spur dam filling body is cast and arranged in the cofferdam structure, a horizontal end of the cofferdam side baffle is embedded in the spur dam base, the horizontal extension direction of the cofferdam side baffle is perpendicular to the extension direction of the river bank, two cofferdam side baffles are arranged in parallel along the extension direction of the river bank, the vertical ends of the cofferdam side baffles are inserted into the riverbed, the cofferdam end baffles are arranged at both ends of the horizontal extension direction of the cofferdam side baffles and a cofferdam end baffle close to the river bank is embedded in the spur dam base, the cofferdam end baffle The vertical end is inserted into the riverbed, the cofferdam end baffle is sealed and connected to the end of the cofferdam side baffle, the two cofferdam end baffles and the two cofferdam side baffles surround and form a closed space, and a number of closed spaces are arranged side by side from the river bank to the riverbed. The spur dam body is cast and arranged in the closed space, and the supporting structure is fixedly installed on the spur dam body. The prefabricated cover body is arranged in an arch shape, and the convex side of the prefabricated cover body arch faces the direction away from the spur dam body. A first countersunk hole is opened on the side of the prefabricated cover body away from the spur dam body, and a first threaded column is inserted into the first countersunk hole. The first threaded column vertically penetrates the prefabricated cover body and the first threaded column is detachably fixedly connected to the supporting structure. The supporting structure abuts against the recessed side of the prefabricated cover body to support the prefabricated cover body, and the side of the prefabricated cover body facing the spur dam body is tightly abutted against the spur dam body, and the two ends of the prefabricated cover body facing the extension direction of the cofferdam side baffles are embedded and connected with prefabricated side covers, and the prefabricated side covers are tightly abutted against the end faces of the cofferdam end baffles.

[0006] By adopting the above technical scheme, a cofferdam structure is formed by pouring a spur dam base, and then concrete mortar is poured on the inner side of the cofferdam structure to make the spur dam filling body and the spur dam base form the foundation of the spur dam structure, and then based on the spur dam base and the spur dam filling body, the cofferdam side baffles are inserted side by side into the river channel and two cofferdam end baffles are inserted between the cofferdam side baffles to form a closed space, and vehicles and equipment for the construction of the cofferdam side baffles, the cofferdam end baffles and the closed space can be directly operated on the spur dam base and the spur dam filling body. When the spur dam body is poured, the vehicles and equipment can be directly operated on the spur dam body to pour the next closed space, so that there is no need to use water operation tools such as ships during the construction process, which can effectively reduce the construction difficulty and thus improve the construction efficiency of the spur dam.

[0007] The present invention is further configured as follows: the supporting structure includes a second reserved hole, a fixing column, a supporting block and a threaded hole, the second reserved hole is arranged on the spur dam body, the supporting block is fixedly connected to the end of the fixing column, the end of the fixing column away from the supporting block is inserted into the second reserved hole and embeddedly connected to the spur dam body, the threaded hole is arranged on a side surface of the supporting block away from the fixing column, the threaded hole extends to the inside of the fixing column, the end of the first threaded column is inserted into the threaded hole and threadedly connected to the inner wall of the threaded hole, and the edge of the supporting block is arranged to be an arc-shaped curved surface and abuts against the recessed side surface of the prefabricated cover body.

[0008] By adopting the above technical scheme, a prefabricated cover body is prefabricated and connected to the dam body of the groyne, and the fixing column is integrally cast in the dam body of the groyne. A support block is used to abut against the recessed side of the prefabricated cover body to support the prefabricated cover body in the vertical direction. At the same time, the first threaded column is screwed into the threaded hole to restrict the vertical movement of the prefabricated cover body, thereby fixing the prefabricated cover body to the groyne body. The assembled structure can remove the restriction on the vertical direction of the prefabricated cover body by screwing out the first threaded column after a single prefabricated cover body is damaged, and then the prefabricated cover body is lifted for removal, and then a new prefabricated cover body is replaced and placed on the groyne body, and then the first threaded column is screwed in to restrict the prefabricated cover body. The operation is simple and can improve the convenience of maintenance of the groyne.

[0009] The present invention is further configured as follows: an assembled dam body structure is arranged on the side of the cofferdam side baffle plate located outside the closed space, the assembled dam body structure comprises a prefabricated dam bottom block, a sliding groove and a limit plate, the sliding groove is arranged on the side of the cofferdam side baffle plate located outside the closed space, the sliding groove extends vertically, one end of the prefabricated dam bottom block extends into the sliding groove and is connected with the mortise and tenon joints of the sliding groove, a side of the prefabricated dam bottom block away from the riverbed is fixed with a plurality of limit columns, the limit plate is inserted into the sliding groove and is located on the side of the prefabricated dam bottom block away from the riverbed, the limit plate is welded at the connection between the limit plate and the inner wall of the sliding groove, and one end of the limit plate facing the prefabricated dam bottom block is tightly abutted against the prefabricated dam bottom block.

[0010] The present invention is further configured as follows: a dam bottom connecting block inserted into the riverbed is provided on one side of the cofferdam side baffle plate located outside the closed space, the dam bottom connecting block is located on the side of the prefabricated dam bottom block facing the riverbed, a first connecting groove is provided on the dam bottom connecting block, a second connecting groove is provided on the side of the prefabricated dam bottom block facing the riverbed, a portion of the dam bottom connecting block extends into the second connecting groove and a portion of the prefabricated dam bottom block extends into the first connecting groove so that the dam bottom connecting block is plugged into the prefabricated dam bottom block.

[0011] By adopting the above technical scheme, a dam bottom connecting block is arranged at the part of the cofferdam side baffle located outside the closed space, and the dam bottom connecting block is inserted into the riverbed, so that a gap is generated between one end of the dam bottom connecting block with the first connecting groove and the cofferdam side baffle, namely, the first connecting groove. When the prefabricated dam bottom block slides vertically to the riverbed along the sliding groove, the part of the prefabricated dam bottom block with the second connecting groove cooperates with the end of the dam bottom connecting block with the first connecting groove, so that the prefabricated dam bottom block and the dam bottom connecting block form a stable connection structure. At this time, the dam bottom connecting block and the sliding groove can jointly limit the horizontal displacement of the prefabricated dam bottom block on the riverbed, which is beneficial to improve the stability of the prefabricated dam bottom block after installation. Then, a limit plate is inserted into the sliding groove and the limit plate abuts against the prefabricated dam bottom block. , can limit the vertical displacement of the prefabricated dam bottom block, thereby further ensuring the stability of the prefabricated dam bottom block after installation, the prefabricated dam bottom block can increase the width of the bottom of the spur dam, and because the prefabricated dam bottom block is hard-connected with the spur dam body through the cofferdam side baffles, this can improve the overall stability of the spur dam. After the construction of the spur dam is completed, the cofferdam side baffles and the cofferdam end baffles do not need to be removed. The cofferdam side baffles can be used as connecting parts between the prefabricated dam bottom block and the spur dam body, reducing the process of pulling out and disassembling the cofferdam side baffles and the cofferdam end baffles in traditional construction, which can effectively shorten the construction period of the spur dam and improve construction efficiency. When a soft row of bottom protection is set on the prefabricated dam bottom block, the limit column can limit the displacement of the soft row, effectively ensuring the stability of the soft row.

[0012] The present invention is further configured as follows: the raised side surface of the prefabricated cover body is detachably provided with an auxiliary structure, the auxiliary structure includes a fixed track, a sliding base plate, a fixed block and a hinged plate, the fixed track is fixedly installed on the end surface of the cofferdam side baffle away from the riverbed, the fixed track and the cofferdam side baffle have the same horizontal extension direction, the sliding base plate is arched and the recessed side of the sliding base plate is opposite to the raised side of the prefabricated cover body, the two ends of the sliding base plate are respectively connected with the fixed track, the sliding base plate can only slide along the extension direction of the fixed track, the fixed block is fixedly arranged on the side of the sliding base plate away from the prefabricated cover body, the hinged plate is hingedly arranged at both ends of the fixed block in the extension direction along the river bank, and an elastic member is arranged at the hinge between the hinge plate and the fixed block, the elastic member is used to keep the hinge plate in a horizontal state and restore the hinge plate to a horizontal state after being flipped along the hinge.

[0013] The present invention is further configured as follows: an intermediate block is fixedly installed on the sliding bottom plate, the interior of the intermediate block is hollow and an opening is provided on the side facing the prefabricated cover body, a rotating wheel is rotatably provided inside the intermediate block, the outer side surface of the rotating wheel extends to the outside of the intermediate block and abuts against the raised surface of the prefabricated cover body, the rotating axis of the rotating wheel is tangential to the raised surface of the prefabricated cover body, and the rotating wheel rotates when the sliding bottom plate slides along the extension direction of the fixed track.

[0014] By adopting the above technical scheme, when it is necessary to pile geobags and other soft bottom protection on the prefabricated dam bottom block, since the end of the prefabricated cover body away from the riverbed is arranged in an arc shape, it is not easy to stand firm and maintain balance when manually throwing geobags on the prefabricated dam bottom block. The sliding bottom plate is connected to the fixed track and slides along the extension direction of the fixed track. At this time, the geobags can be stacked on the fixed block, and the sliding bottom plate is pushed to slide by manpower. At this time, the manual hand grasps the fixed block to maintain the manual balance, and when the sliding bottom plate slides, the rotating wheel contacts the raised side of the prefabricated cover body, and the original sliding friction between the sliding bottom plate and the prefabricated cover body is converted into rolling friction. This can reduce the resistance of the sliding bottom plate during the sliding process, reduce the physical exertion of manually pushing the sliding bottom plate to move, and during the movement of the fixed block, the geobags Pull in the direction of the hinged plate. When the geobag moves to the hinged plate, due to the increase of load on the hinged plate, the hinged plate flips and tilts along the hinge. Under the action of gravity, the geobag on the hinged plate can slide away from the fixed block, eventually falling into the water and settling on the prefabricated dam bottom block. The traditional bottom protection soft structure layout requires the use of ships to transport the geobags to the top of the prefabricated dam bottom block and then throw the geobags into the water. This requires the ship to repeatedly travel back and forth to the shore to replenish the geobags. The use of fixed blocks for transportation can reduce the use of ships, and only requires a straight line back and forth between the soft structure layout position and the geobag replenishment position. Compared with ship transportation, it is more efficient. If the fixed block is driven by a driving device, the operating speed of the fixed block can be further improved, thereby further improving the layout efficiency of the protective soft structure.

[0015] The present invention is further configured as follows: an expansion track is detachably fixedly provided on the spur filler body, an end of the expansion track is butted with an end of the fixed track, a first reserved hole is provided on the spur filler body, an expansion cover body is placed on the portion of the spur filler body where the first reserved hole is provided, the expansion cover body is butted with a prefabricated side cover close to the river bank, the expansion cover body has the same structure and shape as the prefabricated cover body, and a second countersunk hole is provided on the raised side of the expansion cover body, a second threaded column is provided in the second countersunk hole, an end of the second threaded column penetrates the expansion cover body and extends into the first reserved hole, the second threaded column is threadedly connected with the inner wall of the first reserved hole, a sand pump is detachably fixedly provided on the fixed block, the sand pump is provided with a feed end and a discharge end, a sand guide pipe is fixedly installed on the feed end and the discharge end of the sand pump, and the sand guide pipe extends to the connection between the river bank and the riverbed at one end away from the sand pump and there is a gap between the sand guide pipe and the riverbed.

[0016] By adopting the above technical solution, the expansion cover is placed at the spur dam base and the spur dam filling body, and the second threaded column is inserted into the second countersunk hole and the end of the second threaded column extends into the first reserved hole and is threadedly connected to the first reserved hole. At this time, the stability of the expansion cover can be maintained, and then the expansion track is docked with the fixed track and the expansion track is fixed to the spur dam filling body, and the sliding bottom plate is pulled to slide to the expansion cover. At this time, the sliding bottom plate is located at the junction of the river bank and the riverbed. After the spur dam has been used for a long time, the silt entrained in the water will accumulate on the water-facing side of the root of the spur dam, that is, the water-facing side of the spur dam base, causing silt sedimentation. At the same time, the spur dam at the root On the backwater side, that is, the backwater side of the spur dam base, some silt will be carried away by the backflow of water, causing cavities. Therefore, it is necessary to frequently remove the silt on the silt settling side and backfill the silt cavities with silt to ensure the stability of the spur dam root. At this time, the sand guide pipes on both sides of the sand pump are respectively inserted into the water-facing side and the backwater side of the spur dam base, and then the sand pump is started. The sand guide pipe at the feed end of the sand pump sucks the silt from the silt accumulation, and then discharges it to the silt cavity through the sand guide pipe on the other side, thereby completing the artificial repair and backfilling construction of the river bank silt. There is no need to use large equipment to excavate and transfer the silt, which improves the convenience of silt backfilling.

[0017] The construction method of the anti-scouring groin structure includes:

[0018] S1: Cast the spur dike base at the junction of the riverbed and the riverbank. The height of the spur dike base is higher than the height difference between the riverbank and the riverbed, and the accumulated water in the cofferdam structure formed by the spur dike base and the riverbank is pumped out;

[0019] S2: Casting work is carried out in the cofferdam structure to form the spur fill body;

[0020] S3: Based on the spur dam base, cofferdam side baffles are inserted into the riverbed side by side, and then cofferdam end baffles are inserted into the two ends between the two cofferdam side baffles, so that the cofferdam side baffles and the cofferdam end baffles form a closed space;

[0021] S4: Casting work is carried out in a closed space to form the spur dam body;

[0022] S5: Based on the spur dam body, the cofferdam side baffles are continuously inserted side by side in the direction away from the river bank, and then the cofferdam end baffles are inserted into the two ends between the two cofferdam side baffles, so that the cofferdam side baffles and the cofferdam end baffles form a closed space;

[0023] S6: repeat the steps of S4 and S5;

[0024] S7: Installing a support structure and a prefabricated cover body on the spur dam body on the side away from the river bank so that the support structure supports the prefabricated cover body;

[0025] S8: Then, the steps of installing the supporting structure and the prefabricated cover in S7 are repeated on the spur dam in a direction close to the river bank.

[0026] The beneficial effects of the present invention are:

[0027] The cofferdam structure is formed by pouring the spur dam base, and then concrete mortar is poured on the inner side of the cofferdam structure to make the spur dam filling body and the spur dam base form the foundation of the spur dam structure. Then, based on the spur dam base and the spur dam filling body, the cofferdam side baffles are inserted side by side into the river channel and two cofferdam end baffles are inserted between the cofferdam side baffles to form a closed space. Vehicles and equipment for the construction of the cofferdam side baffles, the cofferdam end baffles and the closed space can be directly operated on the spur dam base and the spur dam filling body. When the spur dam body is poured, the vehicles and equipment can be directly operated on the spur dam body to pour the next closed space. In this way, there is no need to use water operation tools such as ships during the construction process, which can effectively reduce the construction difficulty and thus improve the construction efficiency of the spur dam. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 It is a structural schematic diagram of the present invention;

[0029] Figure 2 This is a schematic diagram of the structure of the present invention when the prefabricated cover is removed;

[0030] Figure 3 It is a structural explosion diagram of the present invention;

[0031] Figure 4 This is a schematic diagram of the structure when the auxiliary structure is installed in the present invention;

[0032] Figure 5 This is a schematic diagram of the structure of the present invention after the expansion cover is installed;

[0033] Figure 6 It is a structural cross-sectional view of the auxiliary structure in the present invention.

[0034] In the figure: 10, riverbed; 11, river bank; 12, spur dike base; 13, spur dike filling body; 14, first reserved hole; 15, cofferdam side baffle; 16, cofferdam end baffle; 17, spur dike body; 20, dam bottom connection block; 21, first connection groove; 22, prefabricated dam bottom block; 23, limit column; 24, sliding groove; 25, limit plate; 26, second connection groove; 30, prefabricated cover; 31, first countersunk hole ; 32. Prefabricated side cover; 33. Second reserved hole; 34. Fixed column; 35. Support block; 36. Threaded hole; 37. First threaded column; 40. Fixed track; 41. Extension track; 42. Extension cover; 43. Second countersunk hole; 44. Second threaded column; 50. Sliding bottom plate; 51. Middle block; 52. Fixed block; 53. Rotating wheel; 54. Articulated plate; 55. Sand pump; 56. Sand guide pipe. DETAILED DESCRIPTION

[0035] In order to make the technical means, creative features, objectives and effects of the present invention easier to understand, the following is a brief introduction Figure 1-6 The present invention is further described.

[0036] like Figure 1-3As shown, the anti-scouring spur dam structure includes a riverbed 10, a river bank 11 and a spur dam. The river bank 11 is located on both sides of the extending direction of the riverbed 10. A plurality of spur dams are arranged at intervals along the extending direction of the river bank 11. The spur dam also includes a spur dam base 12, a spur dam filling body 13, a cofferdam side baffle 15, a cofferdam end baffle 16, a spur dam body 17, a prefabricated cover body 30 and a supporting structure. The spur dam base 12 is cast and arranged at the junction of the riverbed 10 and the river bank 11. The spur dam base 12 is semicircular in shape. The spur dam base 12 and the river bank 11 surround a cofferdam structure. The dam filling body 13 is cast and arranged in the cofferdam structure, a horizontal end of the cofferdam side baffle 15 is embedded in the spur dam base 12, the horizontal extension direction of the cofferdam side baffle 15 is perpendicular to the extension direction of the river bank 11, two cofferdam side baffles 15 are arranged in parallel along the extension direction of the river bank 11, and the vertical ends of the cofferdam side baffles 15 are inserted into the riverbed 10, and the cofferdam end baffles 16 are arranged at both ends of the cofferdam side baffle 15 in the horizontal extension direction and one cofferdam end baffle 16 close to the river bank 11 is embedded in the spur dam base 12, and the vertical ends of the cofferdam end baffles 16 are inserted into the riverbed 10, the cofferdam end baffle 16 is sealed and connected to the end of the cofferdam side baffle 15, the two cofferdam end baffles 16 and the two cofferdam side baffles 15 surround and form a closed space, a plurality of closed spaces are arranged side by side from the river bank 11 to the riverbed 10, the spur dam body 17 is cast and arranged in the closed space, the supporting structure is fixedly installed on the spur dam body 17, the prefabricated cover body 30 is arranged in an arch shape, the convex side of the arch of the prefabricated cover body 30 faces the direction away from the spur dam body 17, and the side of the prefabricated cover body 30 away from the spur dam body 17 is provided with a first sinking Hole 31, a first threaded column 37 is inserted into the first countersunk hole 31, the first threaded column 37 vertically penetrates the prefabricated cover body 30 and the first threaded column 37 is detachably fixedly connected to the supporting structure, the supporting structure abuts against the recessed side of the prefabricated cover body 30 to support the prefabricated cover body 30, the side of the prefabricated cover body 30 facing the spur dam body 17 is tightly abutted against the spur dam body 17, and the two ends of the prefabricated cover body 30 facing the extension direction of the cofferdam side baffle 15 are embedded and connected with prefabricated side covers 32, and the prefabricated side covers 32 are tightly abutted against the end surface of the cofferdam end baffle 16. The supporting structure includes a second reserved hole 33, a fixing column 34, a supporting block 35 and a threaded hole 36. The second reserved hole 33 is provided on the spur dam body 17. The supporting block 35 is fixedly connected to the end of the fixing column 34. The end of the fixing column 34 away from the supporting block 35 is inserted into the second reserved hole 33 and embedded and connected to the spur dam body 17. The threaded hole 36 is provided on a side of the supporting block 35 away from the fixing column 34. The threaded hole 36 extends into the interior of the fixing column 34. The end of the first threaded column 37 is inserted into the threaded hole 36 and is threadedly connected to the inner wall of the threaded hole 36. The edge of the supporting block 35 is set to an arc-shaped curved surface and abuts against the recessed side of the prefabricated cover body 30.

[0037] like Figure 3As shown, a prefabricated dam body structure is provided on the side of the cofferdam side baffle 15 located outside the closed space, and the prefabricated dam body structure includes a prefabricated dam bottom block 22, a sliding groove 24 and a limit plate 25. The sliding groove 24 is provided on the side of the cofferdam side baffle 15 located outside the closed space, and the sliding groove 24 extends vertically. One end of the prefabricated dam bottom block 22 extends into the sliding groove 24 and is connected with the sliding groove 24 by mortise and tenon joints. A plurality of limit columns 23 are fixed on the side of the prefabricated dam bottom block 22 away from the riverbed 10. The limit plate 25 is inserted into the sliding groove 24 and is located on the side of the prefabricated dam bottom block 22 away from the riverbed 10. The limit plate 25 is welded to the connection between the inner wall of the sliding groove 24, and the limit plate 25 is tightly abutted against the prefabricated dam bottom block 22 at one end thereof facing the prefabricated dam bottom block 22. A dam bottom connection block 20 inserted into the riverbed 10 is provided on one side of the cofferdam side baffle 15 located outside the enclosed space. The dam bottom connection block 20 is located on the side of the prefabricated dam bottom block 22 facing the riverbed 10. A first connection groove 21 is opened on the dam bottom connection block 20, and a second connection groove 26 is opened on the side of the prefabricated dam bottom block 22 facing the riverbed 10. The dam bottom connection block 20 partially extends into the second connection groove 26 and the prefabricated dam bottom block 22 partially extends into the first connection groove 21 so that the dam bottom connection block 20 is plugged into the prefabricated dam bottom block 22.

[0038] like Figure 4-6 As shown, the raised side of the prefabricated cover body 30 is detachably provided with an auxiliary structure, the auxiliary structure comprising a fixed rail 40, a sliding base plate 50, a fixed block 52 and a hinged plate 54, the fixed rail 40 is fixedly installed on the end face of the cofferdam side baffle 15 away from the riverbed 10, the fixed rail 40 and the cofferdam side baffle 15 have the same horizontal extension direction, the sliding base plate 50 is arched and the recessed side of the sliding base plate 50 is opposite to the raised side of the prefabricated cover body 30, the two ends of the sliding base plate 50 are respectively connected with the fixed rail 40, the sliding base plate 50 can only slide along the extension direction of the fixed rail 40, the fixed block 52 is fixedly set on the side of the sliding base plate 50 away from the prefabricated cover body 30, the hinged plate 54 is hingedly set at both ends of the fixed block 52 along the extension direction of the river bank 11, and an elastic member is set at the hinge between the hinge plate 54 and the fixed block 52, the elastic member is used to keep the hinge plate 54 in a horizontal state and restore the hinge plate 54 to a horizontal state after flipping along the hinge. An intermediate block 51 is fixedly installed on the sliding base plate 50. The interior of the intermediate block 51 is hollow and has an opening on the side facing the prefabricated cover body 30. A rotating wheel 53 is rotatably arranged inside the intermediate block 51. The outer side surface of the rotating wheel 53 extends to the outside of the intermediate block 51 and abuts against the raised surface of the prefabricated cover body 30. The rotating axis of the rotating wheel 53 is tangential to the raised surface of the prefabricated cover body 30. When the sliding base plate 50 slides along the extension direction of the fixed track 40, the rotating wheel 53 rotates.

[0039] like Figure 5-6As shown, an expansion track 41 is detachably fixedly arranged on the spur filler 13, and the end of the expansion track 41 is butted with the end of the fixed track 40. A first reserved hole 14 is provided on the spur filler 13, and an expansion cover 42 is placed on the portion of the spur filler 13 where the first reserved hole 14 is provided. The expansion cover 42 is butted with a prefabricated side cover 32 close to the river bank 11, and the structure and shape of the expansion cover 42 are the same as those of the prefabricated cover 30, and a second countersunk hole 43 is provided on the convex side of the expansion cover 42, and the second countersunk hole 43 is provided inside the second countersunk hole 43. A second threaded column 44 is provided, and the end of the second threaded column 44 passes through the expansion cover body 42 and extends into the first reserved hole 14. The second threaded column 44 is threadedly connected to the inner wall of the first reserved hole 14. A sand pump 55 is detachably fixedly provided on the fixed block 52. The sand pump 55 is provided with a feeding end and a discharging end. A sand guide pipe 56 is fixedly installed at the feeding end and the discharging end of the sand pump 55. The end of the sand guide pipe 56 away from the sand pump 55 extends to the connection between the river bank 11 and the riverbed 10 and there is a gap between the sand guide pipe 56 and the riverbed 10.

[0040] A cofferdam structure is formed by pouring the spur dam base 12 and the river bank 11, and then concrete mortar is poured on the inner side of the cofferdam structure to make the spur dam filling body 13 and the spur dam base 12 form the foundation of the spur dam structure. Then, based on the spur dam base 12 and the spur dam filling body 13, the cofferdam side baffles 15 are inserted side by side into the river channel, and two cofferdam end baffles 16 are inserted between the cofferdam side baffles 15 to form a closed space. Vehicles and equipment for the construction of the cofferdam side baffles 15, the cofferdam end baffles 16 and the closed space can be directly operated on the spur dam base 12 and the spur dam filling body 13. When the spur dam body 17 is poured, the vehicles and equipment can be directly operated on the spur dam body 17 to pour the next closed space. In this way, there is no need to use water operation tools such as ships during the construction process, which can effectively reduce the construction difficulty and thus improve the construction efficiency of the spur dam. The prefabricated cover body 30 is prefabricated and connected to the groyne body 17, the fixing column 34 is integrally cast in the groyne body 17, and the support block 35 is used to abut against the recessed side of the prefabricated cover body 30 to support the prefabricated cover body 30 in the vertical direction. At the same time, the first threaded column 37 is screwed into the threaded hole 36 to restrict the vertical movement of the prefabricated cover body 30, thereby fixing the prefabricated cover body 30 to the groyne body 17. The assembled structure can remove the vertical restriction on the prefabricated cover body 30 by screwing out the first threaded column 37 after a single prefabricated cover body 30 is damaged, and then the prefabricated cover body 30 is lifted for removal, and then a new prefabricated cover body 30 is replaced, the prefabricated cover body 30 is placed on the groyne body 17, and then the first threaded column 37 is screwed in to restrict the prefabricated cover body 30. The operation is simple and can improve the convenience of maintenance of the groyne.

[0041] By arranging a dam bottom connection block 20 at the part of the cofferdam side baffle 15 located outside the closed space, and the dam bottom connection block 20 is inserted into the riverbed 10, a gap is generated between one end of the dam bottom connection block 20 with the first connection groove 21 and the cofferdam side baffle 15, namely the first connection groove 21. When the prefabricated prefabricated dam bottom block 22 slides vertically to the riverbed 10 along the sliding groove 24, the part of the prefabricated dam bottom block 22 with the second connection groove 26 cooperates with the end of the dam bottom connection block 20 with the first connection groove 21, so that the prefabricated dam bottom block 22 and the dam bottom connection block 20 form a stable connection structure. At this time, the dam bottom connection block 20 and the sliding groove 24 can jointly limit the horizontal displacement of the prefabricated dam bottom block 22 on the riverbed 10, which is beneficial to improve the stability of the prefabricated dam bottom block 22 after installation. Then, a limit plate 25 is inserted into the sliding groove 24 and the limit plate 25 is aligned with the prefabricated dam bottom The block 22 abuts against the prefabricated dam bottom block 22, which can limit the vertical displacement of the prefabricated dam bottom block 22, thereby further ensuring the stability of the prefabricated dam bottom block 22 after installation. The prefabricated dam bottom block 22 can increase the width of the bottom of the spur dam, and because the prefabricated dam bottom block 22 is hard-connected with the spur dam body 17 through the cofferdam side baffles 15, this can improve the overall stability of the spur dam. After the construction of the spur dam is completed, the cofferdam side baffles 15 and the cofferdam end baffles 16 do not need to be removed. The cofferdam side baffles 15 can be used as a connecting piece between the prefabricated dam bottom block 22 and the spur dam body 17, reducing the process of pulling out and disassembling the cofferdam side baffles 15 and the cofferdam end baffles 16 in traditional construction, which can effectively shorten the construction period of the spur dam and improve construction efficiency. When a soft row bottom protection is set on the prefabricated dam bottom block 22, the limit column 23 can limit the displacement of the soft row, effectively ensuring the stability of the soft row.

[0042] When it is necessary to pile geobags or other soft bottom protection on the prefabricated dam bottom block 22, since the end of the prefabricated cover body 30 away from the riverbed 10 is arranged in an arc shape, it is not easy to stand firm and maintain balance when throwing geobags onto the prefabricated dam bottom block 22 manually. The sliding bottom plate 50 is connected to the fixed track 40 and slides along the extension direction of the fixed track 40. At this time, the geobags can be stacked on the fixed block 52, and the sliding bottom plate 50 is pushed to slide by manpower. At this time, the human hand holding the fixed block 52 can maintain the human balance. When the sliding bottom plate 50 slides, the rotating wheel 53 contacts the raised side of the prefabricated cover body 30, and the sliding friction between the original sliding bottom plate 50 and the prefabricated cover body 30 is converted into rolling friction. This can reduce the resistance of the sliding bottom plate 50 during the sliding process, reduce the physical exertion of manually pushing the sliding bottom plate 50 to move, and reduce the soil during the movement of the fixed block 52. The geobag is pulled toward the hinge plate 54. When the geobag moves onto the hinge plate 54, due to the increase in load on the hinge plate 54, the hinge plate 54 flips and tilts along the hinge. Under the action of gravity, the geobag on the hinge plate 54 can slide away from the fixed block 52, eventually falling into the water and settling on the prefabricated dam bottom block 22. The traditional bottom protection software layout requires the use of ships to transport the geobags to the top of the prefabricated dam bottom block 22, and then throwing the geobags into the water. This requires the ship to repeatedly travel back and forth to the shore to replenish the geobags. The use of fixed blocks 52 for transportation can reduce the use of ships, and only requires a straight line back and forth between the software layout position and the geobag replenishment position. Compared with ship transportation, it is more efficient. If a driving device is used to drive the fixed block 52 to move, the operating speed of the fixed block 52 can be further improved, thereby further improving the layout efficiency of the body protection software.

[0043] The expansion cover 42 is placed at the spur base 12 and the spur filling body 13, and the second threaded column 44 is inserted into the second countersunk hole 43, and the end of the second threaded column 44 extends into the first reserved hole 14 and is threadedly connected to the first reserved hole 14. At this time, the stability of the expansion cover 42 can be maintained, and then the expansion track 41 is docked with the fixed track 40 and the expansion track 41 is fixed to the spur filling body 13, and the sliding bottom plate 50 is pulled to slide to the expansion cover 42. At this time, the sliding bottom plate 50 is located at the junction of the river bank 11 and the riverbed 10. After the spur dam has been used for a long time, the silt entrained in the water will accumulate on the water-facing side of the root of the spur dam, that is, the water-facing side of the spur dam base 12, causing silt sedimentation. The backwater side of the root of the spur dike, that is, the backwater side of the spur dike base 12, will cause cavities due to the backflow of water carrying away part of the silt. Therefore, it is necessary to frequently remove the silt on the silt settling side and backfill the silt cavities with silt to ensure the stability of the root of the spur dike. At this time, the sand guide pipes 56 on both sides of the sand pump 55 are respectively inserted into the water-facing side and the backwater side of the spur dike base 12, and then the sand pump 55 is started. The sand guide pipe 56 at the feeding end of the sand pump 55 sucks the silt from the silt accumulation, and then discharges it to the silt cavities through the sand guide pipe 56 on the other side, thereby completing the artificial repair and backfilling construction of the river bank 11 silt, without the need to use large-scale equipment to dig and transfer the silt, thereby improving the convenience of silt backfilling.

[0044] The construction method of the anti-scouring groin structure includes:

[0045] S1: A closed cofferdam is formed at the junction of the riverbed 10 and the river bank 11 by stacking a large number of geobags. At this time, the closed cofferdam is the outline of the spur dam base 12, and the end of the closed cofferdam structure should be arranged on the river bank 11. Then, a concrete structure is set in the closed cofferdam and steel bars are implanted to form the spur dam base 12. The two ends of the spur dam base 12 are connected to the river bank 11 to prevent water from seeping in. A groove for embedding the cofferdam side baffle 15 is opened in advance on the spur dam base 12. The groove can also be separated by the baffle when pouring the spur dam base 12. Then, a pumping device is used to pump out the accumulated water in the cofferdam structure surrounded by the spur dam base 12 and the river bank 11;

[0046] S2: Use concrete pouring equipment to perform concrete pouring operations in the cofferdam structure. Before pouring, the steel structure needs to be prefabricated and installed in advance. After the concrete pouring solidifies, the spur dike filling body 13 is formed;

[0047] S3: Arrange the construction vehicles and equipment on the spur base 12 and the spur filling body 13, insert the cofferdam side baffles 15 into the riverbed 10 side by side based on the spur base 12, and then insert the cofferdam end baffles 16 into the two ends between the two cofferdam side baffles 15, so that the cofferdam side baffles 15 and the cofferdam end baffles 16 form a closed space, weld and seal the connection between the cofferdam side baffles 15 and the cofferdam end baffles 16, embed the cofferdam side baffles 15 into the preset groove of the spur base 12, pour concrete mortar at the embedded gap, and then perform waterproof treatment such as brushing a waterproof layer or laying a waterproof board;

[0048] S4: The water in the closed space is pumped out using a pumping device, and then a steel structure and a metal baffle are installed in the closed space. The metal baffle is a circular structure used to prevent concrete from entering the circular interior. Concrete is poured into the space outside the metal baffle in the closed space and solidified to form a spur dam body 17, and a second reserved hole 33 is formed inside the metal baffle;

[0049] S5: Then, the construction vehicles and equipment are arranged on the spur dam body 17, and the cofferdam side baffles 15 are inserted side by side in a direction away from the river bank 11 based on the spur dam body 17, and then the cofferdam end baffles 16 are inserted into the two ends between the two cofferdam side baffles 15, so that the cofferdam side baffles 15 and the cofferdam end baffles 16 form a new closed space;

[0050] S6: repeat the steps of S4 and S5;

[0051] S7: The dam bottom connection block 20 is attached to the side of the cofferdam side baffle 15 outside the closed space, and then the dam bottom connection block 20 is pressed into the riverbed 10 using equipment. At this time, only one end of the dam bottom connection block 20 provided with the first connection groove 21 is exposed from the riverbed 10, and the dam bottom connection block 20 is attached to the cofferdam side baffle 15;

[0052] S8: The prefabricated prefabricated dam bottom block 22 is transported to the spur dam body 17 by using a lifting vehicle or other equipment, and then the prefabricated dam bottom block 22 is lifted so that the prefabricated dam bottom block 22 is aligned with the opening of the sliding groove 24 and connected in a matching manner, and then the prefabricated dam bottom block 22 is slowly lowered and moves toward the riverbed 10 under the action of gravity. When the prefabricated dam bottom block 22 moves to the dam bottom connecting block 20, the second connecting groove 26 on the dam bottom connecting block 20 and the first connecting groove 21 on the prefabricated dam bottom block 22 are gradually plugged and matched. When the prefabricated dam bottom block 22 completely falls on the riverbed 10, the prefabricated dam bottom block 22 stops moving;

[0053] S9: insert the limit plate 25 into the opening of the sliding groove 24, so that the end of the limit plate 25 abuts against the prefabricated dam bottom block 22, and then weld the opening of the sliding groove 24 on the side of the cofferdam side baffle 15 away from the riverbed 10 to the limit plate 25;

[0054] S10: Install the support structure on the spur dam body 17 away from the river bank 11, insert the end of the fixing column 34 into the second reserved hole 33, weld the metal sealing plate and the outer side of the fixing column 34 at the abutment point, and fill the gap between the second reserved hole 33 and the fixing column 34 with concrete mortar to fully connect the fixing column 34 and the metal sealing plate, and then use the lifting equipment to lift the prefabricated cover 30 and place it above the fixing column 34 with better concealed rotation. At this time, the support block 35 is opposite to the concave side of the prefabricated cover body 30. When the prefabricated cover body 30 is placed on the spur dam body 17, the first threaded column 37 is inserted into the first countersunk hole 31 and passes through the prefabricated cover body 30 to cooperate with the threaded hole 36. The first threaded column 37 is screwed into the threaded hole 36 to complete the installation of the prefabricated cover body 30. At this time, the supporting structure supports the prefabricated cover body 30. Finally, the abutment between the prefabricated cover body 30 and the spur dam body 17 is waterproofed, such as filling concrete mortar, supplementing waterproof materials, etc.;

[0055] S11: Then, the steps of installing the support structure and the prefabricated cover 30 in the riverbed 10 are repeated on the spur dam body 17 in sequence toward the river bank 11 .

[0056] The above shows and describes the basic principles, main features and advantages of the present invention. It should be understood by those skilled in the art that the present invention is not limited to the above embodiments. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of the present invention is defined by the attached claims and their equivalents.

Claims

1. An anti-scouring spur dike structure, comprising a riverbed (10), a riverbank (11) and a spur dike, wherein the riverbank (11) is located on both sides of the extending direction of the riverbed (10), and a plurality of spur dikes are arranged at intervals along the extending direction of the riverbank (11), characterized in that: The spur dam further comprises a spur dam base (12), a spur dam filling body (13), a cofferdam side baffle (15), a cofferdam end baffle (16), a spur dam body (17), a prefabricated cover body (30) and a supporting structure. The spur dam base (12) is cast and arranged at the junction of the riverbed (10) and the river bank (11). The spur dam base (12) is in a semicircular shape. The spur dam base (12) and the river bank (11) are surrounded to form a cofferdam structure. The spur dam filling body (13) is cast and arranged in the cofferdam structure. The horizontal end of the cofferdam side baffle (15) is embedded in the spur dam base (12). The cofferdam side baffle (16) is embedded in the spur dam base (12). 5) The horizontal extension direction is perpendicular to the extension direction of the river bank (11), two cofferdam side baffles (15) are arranged in parallel along the extension direction of the river bank (11), the vertical ends of the cofferdam side baffles (15) are inserted into the riverbed (10), the cofferdam end baffles (16) are arranged at both ends of the cofferdam side baffles (15) in the horizontal extension direction, and one cofferdam end baffle (16) close to the river bank (11) is embedded in the spur dike base (12), the vertical ends of the cofferdam end baffles (16) are inserted into the riverbed (10), the cofferdam end baffles (16) are sealed and connected to the ends of the cofferdam side baffles (15), and the two The cofferdam end baffle (16) and the two cofferdam side baffles (15) surround and form a closed space. A plurality of closed spaces are arranged side by side in a direction from the river bank (11) to the river bed (10). The spur dam body (17) is cast and arranged in the closed space. The support structure is fixedly installed on the spur dam body (17). The prefabricated cover body (30) is arranged in an arch shape. The convex side of the arch of the prefabricated cover body (30) faces in a direction away from the spur dam body (17). A first countersunk hole (31) is opened on a side of the prefabricated cover body (30) away from the spur dam body (17). A support structure is inserted into the first countersunk hole (31). A first threaded column (37) is provided, the first threaded column (37) vertically passes through the prefabricated cover body (30) and the first threaded column (37) is detachably fixedly connected to the support structure, the support structure abuts against the concave side surface of the prefabricated cover body (30) to support the prefabricated cover body (30), the side surface of the prefabricated cover body (30) facing the spur dam body (17) is tightly abutted against the spur dam body (17), and the two ends of the prefabricated cover body (30) facing the extension direction of the cofferdam side baffle (15) are embedded and fixedly connected with the prefabricated side covers (32), and the prefabricated side covers (32) are tightly abutted against the end surface of the cofferdam end baffle (16).

2. The anti-scouring spur dike structure according to claim 1, characterized in that: The support structure comprises a second reserved hole (33), a fixing column (34), a support block (35) and a threaded hole (36); the second reserved hole (33) is provided on the spur dam body (17); the support block (35) is fixedly connected to the end of the fixing column (34); one end of the fixing column (34) away from the support block (35) is inserted into the second reserved hole (33) and is embedded and connected to the spur dam body (17); the threaded hole (36) is provided on a side surface of the support block (35) away from the fixing column (34); the threaded hole (36) extends into the interior of the fixing column (34); the end of the first threaded column (37) is inserted into the threaded hole (36) and is threadedly connected to the inner wall of the threaded hole (36); the edge of the support block (35) is arranged as an arc-shaped curved surface and abuts against the concave side surface of the prefabricated cover body (30).

3. The anti-scouring spur dam structure according to claim 1, characterized in that: An assembled dam structure is arranged on the side of the cofferdam side baffle (15) located outside the enclosed space. The assembled dam structure comprises a prefabricated dam bottom block (22), a sliding groove (24) and a limiting plate (25). The sliding groove (24) is arranged on the side of the cofferdam side baffle (15) located outside the enclosed space. The sliding groove (24) extends vertically. One end of the prefabricated dam bottom block (22) extends into the sliding groove (24) and is connected to the sliding groove (24) by mortise and tenon joints. A plurality of limiting columns (23) are fixed to a side of the prefabricated dam bottom block (22) away from the riverbed (10). The limiting plate (25) is inserted into the sliding groove (24) and is located on the side of the prefabricated dam bottom block (22) away from the riverbed (10). The connection between the limiting plate (25) and the inner wall of the sliding groove (24) is welded. The end of the limiting plate (25) facing the prefabricated dam bottom block (22) is tightly abutted against the prefabricated dam bottom block (22).

4. The anti-scouring spur dike structure according to claim 3, characterized in that: A dam bottom connection block (20) inserted into the riverbed (10) is provided on one side of the cofferdam side baffle (15) located outside the closed space. The dam bottom connection block (20) is located on a side of the prefabricated dam bottom block (22) facing the riverbed (10). A first connection groove (21) is provided on the dam bottom connection block (20). A second connection groove (26) is provided on a side of the prefabricated dam bottom block (22) facing the riverbed (10). A portion of the dam bottom connection block (20) extends into the second connection groove (26) and a portion of the prefabricated dam bottom block (22) extends into the first connection groove (21) so that the dam bottom connection block (20) is plugged into the prefabricated dam bottom block (22).

5. The anti-scouring spur dike structure according to claim 1, characterized in that: The raised side surface of the prefabricated cover body (30) is detachably provided with an auxiliary structure, the auxiliary structure comprising a fixed track (40), a sliding bottom plate (50), a fixed block (52) and a hinged plate (54), the fixed track (40) being fixedly mounted on the end surface of the cofferdam side baffle (15) away from the riverbed (10), the fixed track (40) and the cofferdam side baffle (15) extending in the same horizontal direction, the sliding bottom plate (50) being arranged in an arched shape, the concave side of the sliding bottom plate (50) being opposite to the raised side of the prefabricated cover body (30), and both ends of the sliding bottom plate (50) being The two fixing blocks (52) are respectively connected to the fixed rails (40), the sliding base plate (50) can only slide along the extension direction of the fixed rails (40), the fixing block (52) is fixedly arranged on a side of the sliding base plate (50) away from the prefabricated cover body (30), the hinged plate (54) is hingedly arranged at both ends of the fixing block (52) along the extension direction of the river bank (11), and an elastic member is arranged at the hinge between the hinged plate (54) and the fixing block (52), and the elastic member is used to keep the hinged plate (54) in a horizontal state and restore the hinged plate (54) to a horizontal state after turning over along the hinge.

6. The anti-scouring spur dike structure according to claim 5, characterized in that: An intermediate block (51) is fixedly mounted on the sliding bottom plate (50); the interior of the intermediate block (51) is hollow and has an opening on a side facing the prefabricated cover body (30); a rotating wheel (53) is rotatably arranged inside the intermediate block (51); the outer side surface of the rotating wheel (53) extends to the outside of the intermediate block (51) and abuts against a convex surface of the prefabricated cover body (30); the rotation axis of the rotating wheel (53) faces the tangent direction of the convex surface of the prefabricated cover body (30); and the rotating wheel (53) rotates when the sliding bottom plate (50) slides along the extension direction of the fixed track (40).

7. The anti-scouring spur dike structure according to claim 5, characterized in that: An expansion track (41) is detachably fixedly provided on the spur filler (13), the end of the expansion track (41) is butted against the end of the fixed track (40), a first reserved hole (14) is provided on the spur filler (13), an expansion cover (42) is placed on the portion of the spur filler (13) where the first reserved hole (14) is provided, the expansion cover (42) is butted against a prefabricated side cover (32) close to the river bank (11), the expansion cover (42) has the same structure and shape as the prefabricated cover (30), and a second countersunk hole (43) is provided on the convex side of the expansion cover (42), and the second countersunk hole (43) is provided inside the second countersunk hole (43). A second threaded column (44) is provided, the end of the second threaded column (44) passes through the expansion cover (42) and extends into the first reserved hole (14), the second threaded column (44) is threadedly connected to the inner wall of the first reserved hole (14), a sand pump (55) is detachably fixedly provided on the fixed block (52), the sand pump (55) is provided with a feed end and a discharge end, a sand guide pipe (56) is fixedly installed at the feed end and the discharge end of the sand pump (55), and an end of the sand guide pipe (56) away from the sand pump (55) extends to the connection between the river bank (11) and the riverbed (10) and there is a gap between the sand guide pipe and the riverbed (10).

8. The construction method of the anti-scouring groin structure according to any one of claims 1 to 7, characterized in that: The construction method comprises: S1: pouring a spur dike base (12) at the junction of the riverbed (10) and the riverbank (11), wherein the height of the spur dike base (12) is higher than the height difference between the riverbank (11) and the riverbed (10), and pumping out the accumulated water in the cofferdam structure formed by the spur dike base (12) and the riverbank (11); S2: Casting work is performed within the cofferdam structure to form a spur dike fill body (13); S3: inserting the cofferdam side baffles (15) side by side into the riverbed (10) based on the spur base (12), and then inserting the cofferdam end baffles (16) into the two ends between the two cofferdam side baffles (15), so that the cofferdam side baffles (15) and the cofferdam end baffles (16) form a closed space; S4: performing pouring operations in the closed space to form a spur dam body (17); S5: Based on the spur dam body (17), the cofferdam side baffles (15) are continuously inserted side by side in a direction away from the river bank (11), and then the cofferdam end baffles (16) are inserted into the two ends between the two cofferdam side baffles (15), so that the cofferdam side baffles (15) and the cofferdam end baffles (16) form a closed space; S6: repeat the steps of S4 and S5; S7: Installing a support structure and a prefabricated cover body (30) on the spur dam body (17) on the side away from the river bank (11) so that the support structure supports the prefabricated cover body (30); S8: Then, the steps of installing the support structure and the prefabricated cover (30) in S7 are repeated on the spur dam body (17) in sequence in the direction close to the river bank (11).

Citation Information

Patent Citations

  • Water-permeable waterway improvement spur dike

    CN102561260A

  • Ecological active water bank for rivers and manufacturing method thereof

    CN106927572A

  • Roadway spur dike structure and construction method thereof

    CN107881985A

  • Port channel breakwater for water transportation

    CN116145614A

  • Spur dike with geogrid enrockment capturing structure

    CN201695378U