A shaft support method for solving the problem of loess vibration liquefaction in saturated soft loess sections
By combining the construction method of cast pile curtains and advance pipe sheds in the ground and wellbore, the liquefaction problem of saturated soft loess layer is solved, the stable construction and safety of the wellbore tunnel is ensured, and the control of the construction environment and the design requirements are met. .
Patent Information
- Application Number
- CN202411055605.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
During the construction of coal mine shafts, the vibration liquefaction of the saturated soft loess layer causes the steel arch frame to sink, displacement and mud flow, resulting in unstable construction and the inability to excavate normally, which poses a great safety risk.
The method of constructing concrete cast-in-place pile curtains and construction of advance pipe sheds in the wellbore is adopted to modify and protect the saturated soft loess in situ to block the disturbed mudified silt and ensure the stable construction environment.
It effectively blocks the liquefied flow of saturated soft loess, ensures the construction quality and safety of the wellbore tunnel, avoids the sinking and displacement of the steel arch frame, and ensures the stability of the construction environment and the meeting of design requirements.
Smart Images

Figure CN118564255B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of coal mine shaft construction, and in particular to a shaft support method for solving the problem of loess vibration liquefaction in a saturated soft loess section. Background Art
[0002] The Huangsongjie Coal Mine Project is located in Yulin City, Shaanxi Province. It adopts the inclined shaft development method. The shaft sections of the main inclined shaft and the auxiliary inclined shaft are both straight wall semi-circular arches. Among them: the shaft design engineering volume of the main inclined shaft is 1392m, the connecting tunnel is 77m, the inclination is 16 degrees, the shaft net width is 5400mm, the net height is 4100mm, the wall height is 1400mm, and the arch height is 2700mm; the shaft design engineering volume of the auxiliary inclined shaft is 1114m, the inclination is 20 degrees, the shaft net width is 5400mm, the net height is 4300mm, the wall height is 1600mm, and the arch height is 2700mm. When the shaft is excavated to the loess section of the Lishi Group, considering the poor stability of the loess layer, the design adopts 20b I-beam + reinforced concrete composite support, the steel arch frame spacing is 650mm, the concrete support thickness is 400mm, the concrete strength grade is C35, and the impermeability grade is not less than P8.
[0003] On April 12, 2022, the main inclined shaft and on April 15, 2022, the auxiliary inclined shaft entered the designed composite support section construction respectively. On the morning of June 9, when the main inclined shaft was excavated to 178m of loess layer, and on June 13, when the auxiliary inclined shaft was excavated to 142m of loess layer, the water content of the soil layer of the steel arch legs of both suddenly increased, and water seepage occurred under the steel arch frame of the wall. The excavation work was immediately stopped, and measures such as drilling dewatering wells on the ground, constructing seepage wells in the shaft, using curing agents to solidify the soil layer, filling cell bags with legs and bottom plates, spraying + paving with stone slabs, advance small guide tubes, seepage pipes + self-priming pumps, advance small guide tubes + grouting curtains were taken in turn. However The steel arch frame still sank as a whole, with the maximum sinking amount reaching 350mm, and the left arch and leg steel arch frames of the main inclined shaft bulged and shifted to the right, with the maximum right shift and swelling amount being 170mm. On August 19, when the main inclined shaft was constructed to 227 meters, the head steel arch frame part experienced overall settlement, with the settlement amount reaching 180mm. The soil layer in the head excavated wasteland part showed muddy sliding as a whole, with the maximum amount reaching 700mm. During the construction of the auxiliary inclined shaft, the core soil showed serious muddy flow. After the core soil was sealed, muddy flow and water seepage still occurred locally, and the closed face sprayed concrete was severely cracked, and the bottom plate softened into "plasticine", which was extremely unstable. At this time, the vertical depths of the construction faces of the main and auxiliary shafts were 49.1m and 48.6m respectively. Affected by the static water storage environment formed by the microstructure near the shaft, the excavation face entered below the water table, and the loess was in a saturated state. The entire excavation section of the main and auxiliary shafts was in the water-saturated loess layer. Affected by the superposition of engineering deviatoric stress and vibration load caused by shaft excavation, the saturated loess in the composite support section showed liquefaction flow phenomenon, and its engineering strength was completely lost. As of August 19, the excavation of the main inclined shaft and the auxiliary inclined shaft was completely stopped. The main inclined shaft excavated 49m from June 9 to August 19, and the auxiliary inclined shaft excavated 33m from June 13 to August 19.
[0004] On the whole, the core soil at the head of the main inclined shaft and the auxiliary inclined shaft contains water and has serious disturbed mud flow phenomenon. The bottom plate excavation disturbance becomes "plasticine" and is extremely unstable. During excavation, the core soil at the head flows as a whole, resulting in frequent overall sinking and overall displacement of the original support structure. The safety risk is very high, and the tunnel cannot be excavated normally, and the construction quality cannot be guaranteed. Summary of the invention
[0005] In view of the defects existing in the above-mentioned prior art, the present invention aims to propose a shaft support construction method capable of blocking the muddy silt of the disturbed saturated soft loess section, wherein the saturated soft loess on both sides of the shaft is first modified in situ by constructing a concrete cast-in-place pile curtain on the ground, and then the excavated section of the shaft is protected by a curtain by constructing an advanced long pipe shed in the shaft, so that the construction conditions for excavating the shaft tunnel inward are met on site, thereby solving the problems existing in the above-mentioned background technology.
[0006] The above technical objectives of the present invention are achieved through the following technical solutions:
[0007] A shaft support method for solving the problem of loess vibration liquefaction in a saturated soft loess section comprises the following steps:
[0008] S1: Laying out concrete pile curtain;
[0009] Locate the excavation path of the roadway on the ground, and lay a concrete pile curtain on the relatively outer side of the excavation path;
[0010] S2: Lay out the advanced pipe shed to form the vault top curtain;
[0011] Carry out advanced pipe shed construction in sections from the tunnel section inside the shaft, form an arch support curtain at the top of the excavated wasteland, and excavate into the tunnel after the support is completed;
[0012] S3: Strengthen the tunnel floor;
[0013] The bottom plate of the tunnel excavated in step S2 is reinforced, and steps S2 and S3 are repeated in a cross-type manner until the shaft construction is completed.
[0014] A further optimization scheme of the above scheme is as follows: in step S1, the specific steps of laying the concrete cast-in-place pile curtain include:
[0015] S11: Locate the pile driving distance and the center point of the cast-in-place pile along both sides of the excavated wasteland path to determine the drilling position;
[0016] S12: drilling in sequence according to the drilling positions determined in step S11 to form a plurality of injection holes;
[0017] S13: Pour concrete into each grouting hole in turn, and form a concrete cast-in-place pile curtain after solidification.
[0018] By adopting the above solution, further, in step S12, after the drilling depth enters the tunnel floor, it continues downward into the hard bedrock within 1500~2000mm.
[0019] By adopting the above solution, further, in step S13, the diameter of each cast-in-place concrete pile is 1000 mm, and the distance between two adjacent cast-in-place concrete piles is 200 mm.
[0020] A further optimization scheme of the above scheme is as follows: in step S2, the advanced pipe shed construction adopts progressive segmented construction, from supporting the advanced pipe shed, to excavating the section, and then to reinforcing the bottom plate to complete a cycle. The specific steps are as follows:
[0021] S21: Positioning the construction angle of the advanced pipe shed;
[0022] S22: Determine the length of the pipe shed for the first cycle of construction according to the clear height in the tunnel and the angle positioned in step S21;
[0023] S23: start the construction of the first cycle of advanced pipe shed. After the construction is completed, excavate the tunnel section along the excavation direction. After the excavation reaches the set distance, carry out the next cycle of advanced pipe shed construction.
[0024] S24: Repeat step S23, and ensure that after each cycle of advanced pipe-roof construction is completed, the top steel arch support empty top distance does not exceed 400mm.
[0025] By adopting the above scheme, further, in step S23, the advanced pipe rack uses multiple seamless steel pipes with a diameter of Φ108mm and a thickness of 8mm for threaded connection. Except for the first cycle, the length of the advanced pipe rack in each of the remaining cycles is 15000mm.
[0026] By adopting the above scheme, further, when the advanced pipe-roof construction cannot be adopted on both sides of the arch, a horizontal small conduit pipe-roof construction with a diameter of Φ50mm and a length of 3000mm is adopted.
[0027] A further optimization scheme of the above scheme is: in step S3, the steps of reinforcing the tunnel floor are specifically as follows:
[0028] S31: After the base plate is excavated to the designed elevation, pipe piles are laid and driven into the bedrock;
[0029] S32: erecting I-beams above the pipe piles, and welding some of the pipe piles to the bottom beam of the I-beams;
[0030] S33: Lay a layer of cell bags under the I-beam and pour concrete according to the design requirements to form a stable tunnel floor.
[0031] By adopting the above solution, further, in step S31, the pipe piles are steel pipes with a diameter of Φ108 mm, and are arranged in a plum blossom shape.
[0032] By adopting the above solution, further, in step S33, the cell bag is made of crushed stone and cement mixed in a mass ratio of 1:0.5, and the depth of the cell bag at the bottom of the I-beam is 500 mm.
[0033] Another aspect disclosed by the present invention is: an application of a shaft support method for solving the problem of loess vibration liquefaction in saturated soft loess sections, wherein any of the methods described in any of the above items is applied to saturated soft loess sections caused by loess vibration liquefaction to achieve shaft excavation construction.
[0034] In combination with the above scheme, the main beneficial effects of the present invention are as follows:
[0035] 1. In order to solve the problem that the existing construction method cannot be used to excavate the main inclined shaft and the auxiliary inclined shaft of Huangsongjie when they are excavated to the saturated soft loess section, the method of the present invention proposes for the first time a construction idea of "cast-in-place piles combined with advanced pipe sheds", and cast-in-place pile curtains are used on the ground corresponding to the shaft of the section to be excavated along both sides of the excavated waste path, and the saturated soft loess on both sides of the shaft to be excavated is modified in situ, so as to achieve the purpose of blocking the disturbed silt outside the cast-in-place pile curtains when excavating along the tunnel, and then an arched advanced pipe shed is supported on the top of the tunnel along the excavation direction from the shaft, so as to achieve a construction environment with excavation conditions, and the pipe shed support, excavation and bottom plate reinforcement are carried out in a step-by-step alternating mode during excavation, thereby ensuring the construction quality of the shaft and tunnel to the greatest extent.
[0036] 2. The method of "cast-in-place piles combined with advanced pipe sheds" for shaft support adopted in the present invention can effectively block the saturated soft loess silt on both sides and the top of the shaft, prevent the displacement of the steel arch frame and the silt sliding down from the top due to excessive lateral pressure during construction, and block the disturbed mud outside the curtain, thereby achieving the stability of the legs and top of the steel arch frame and ensuring that the cross-sectional dimensions of the permanent support of the tunnel meet the design requirements. BRIEF DESCRIPTION OF THE DRAWINGS
[0037] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for use in the embodiments.
[0038] Figure 1 A schematic cross-sectional view of a pile foundation curtain of a shaft support method for a saturated soft loess section that solves loess vibration liquefaction according to the present invention;
[0039] Figure 2 It is a cross-sectional schematic diagram of the cast-in-place pile curtain arranged along the laneway of the present invention;
[0040] Figure 3 It is a plan view of the arrangement of the cast-in-place pile curtain and the advanced pipe shed of the present invention;
[0041] Figure 4 It is a schematic cross-sectional view of the arrangement of the advanced pipe rack of the present invention;
[0042] Figure 5 This is a schematic diagram of the advanced pipe shed layout of the present invention;
[0043] Figure 6 It is a plan view of the arrangement of I-beams and pipe piles of the tunnel floor of the present invention.
[0044] In the figure: 1-concrete cast-in-place pile curtain; 2-advanced pipe shed; 3-tunnel bottom plate; 4-tunnel top plate; 5-I-beam; 6-pipe pile; 7-cell bag; 8-steel arch frame. DETAILED DESCRIPTION
[0045] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments.
[0046] Reference Figure 1-6 The present invention proposes a shaft support method for solving the problem of loess vibration liquefaction in saturated soft loess sections, which adopts a method of combining the construction of a concrete cast-in-place pile curtain 1 on the ground with the construction of an advanced pipe shed 2 in the shaft to form a curtain on the excavation section of the shaft. The method includes the following steps:
[0047] S1: Laying concrete pile curtain 1;
[0048] Locate the excavation path of the roadway on the ground, and lay a concrete cast-in-place pile curtain 1 outside the excavation path;
[0049] S2: Laying out the advanced pipe shed 2 to form the vault top curtain;
[0050] The advanced pipe shed 2 is constructed in sections from the tunnel section inside the shaft, and an arch support curtain is formed at the top of the excavated wasteland. After the support is completed, excavation is carried out into the tunnel;
[0051] S3: reinforced tunnel floor 3;
[0052] The tunnel floor 3 excavated in step S2 is reinforced, and steps S2 and S3 are repeated in a cross-type manner until the shaft construction is completed.
[0053] Specifically, a wall curtain is formed on both sides of the excavated wasteland of the tunnel by drilling from the ground to block the saturated soft loess silt, prevent the displacement of the steel arch frame 8 caused by excessive pressure or deformation during construction, and block the muddy silt after disturbance outside the curtain to achieve the purpose of stabilizing the legs of the steel arch frame 8, ensuring that the cross-sectional size of the permanent support of the tunnel meets the design requirements. When laying the concrete cast-in-place pile curtain:
[0054] A: Locate the location of the roadway excavation path, the pile driving distance and the center point of the cast-in-place pile on both sides of the excavation path on the ground to determine the drilling position; Figure 3 As shown, within 2000mm on both sides of the excavation section, the cast-in-place piles are positioned in an arc shape with a radius of 2000mm. Therefore, this section is located at the face of saturated soft loess. If it is too close to the excavation path, leakage will occur during concrete pouring. Therefore, an arc-shaped arrangement is adopted here.
[0055] B: According to the drilling positions set out by the surveyors, reverse circulation drilling is used to drill in sequence along the excavation direction on both sides of the tunnel, arranging two rows of cast-in-place holes. The schematic diagram of multiple cast-in-place piles formed by the two rows is shown in the figure. Figure 3As shown; after the depth of the drill hole enters the tunnel ground, it continues to drill downward to within 1500~2000mm of the hard bedrock.
[0056] C: Pour concrete into each pouring hole in turn, and after the concrete solidifies, a concrete pile curtain 1 is formed; combined Figure 1-Figure 3 As shown, the diameter of each bored pile is 1000mm, and the height is determined according to the thickness of the soil layer, ensuring that the bottom of the bored pile is 1500~2000mm in the bedrock, and the spacing between two adjacent concrete bored piles is 200mm, and the bored pile is 200mm away from the excavation diameter. The strength grade of the concrete bored pile is cast with plain concrete of C35 and C15, specifically: Figure 2 Each pile is first poured with C35 plain concrete. When the pouring depth is 10m above the tunnel roof, the pouring is stopped and the C35 concrete is initially set before C15 plain concrete is poured to the pile mouth.
[0057] Furthermore, if during the excavation construction process, the mud between the piles is severely muddied and cannot be blocked, the second row of bored piles will be constructed. The second row of bored piles will be arranged on the relatively outer side of the first row of bored piles and arranged opposite to the gap between the two bored piles in the first row. The second row of bored piles will be poured with C35 plain concrete to the top of the rough path of the excavated section, and then the pouring can be stopped.
[0058] When the concrete pile curtain 1 is laid out, the construction personnel enter the excavated section in the tunnel and construct the arch of the section with an advanced pipe shed 2 from inside the tunnel, so as to form a continuous steel curtain on the top of the excavated path, blocking the disturbed muddy sludge outside the steel curtain to ensure that there is no roof collapse and sludge sliding off the top during excavation, thereby achieving stability of the top of the steel arch frame 8 and ensuring that the cross-sectional size of the permanent support of the tunnel meets the design requirements.
[0059] Specifically, when the advanced pipe shed 2 is set up in the internal section of the shaft, a progressive segmented construction is adopted, from setting up the advanced pipe shed 2, to excavating the section, and then to reinforcing the bottom plate to complete a cycle. Overall, the construction process of the advanced pipe shed 2 is the same as that of the prior art. On the basis of the above construction process, the shaft construction steps in the tunnel of the present invention are specifically as follows:
[0060] A: The construction angle of the advance pipe shed 2 is positioned according to the design requirements of the tunnel. The advance pipe shed 2 is constructed basically along the arch base line upwards and on the inside of the concrete piles. The construction adopts a fan-shaped arrangement with an outward angle (according to the "Construction Plan for Advanced Long Pipe Shelves in the Main and Auxiliary Inclined Shafts of Huanghaojie Coal Mine of Shaanxi Yuansheng Coal Industry Co., Ltd.", it is recommended that the outward angle be 3°~6°). The length of the advance pipe shed 2 in the first cycle is determined according to the clear height in the tunnel and the positioned construction angle. The starting part of the first cycle occupies the permanent support size and is the key reinforcement processing link.
[0061] B: Start the construction of the first cycle of advanced pipe shed 2. Advanced pipe shed 2 is connected by threading with multiple seamless steel pipes with a diameter of Φ108mm and a thickness of 8mm. Each steel pipe is densely arranged. When the advanced pipe shed cannot be used on both sides of the arch, or when the roof falls, a small horizontal conduit with a diameter of Φ50mm and a length of 3000mm is used for construction. The small conduit is laid at a larger angle than the advanced pipe shed until it is erected and contacts the concrete piles. The small horizontal conduit is laid at Figure 1 On both sides of the arch in the middle, in order to prevent the unstable rock formation at the top of the arch from falling in a large area, except for the first cycle, the length of the advanced pipe shed 2 in each cycle is 15000mm. After the current advanced pipe shed 2 is completed, the tunnel section is excavated along the excavation direction. The tunnel excavation adopts manual cooperation with the excavator to excavate the arch first and then the wall in steps and set up the steel arch frame 8 for support. At the same time, it must be ensured that the empty top distance of the top steel arch frame 8 does not exceed 400mm. During the excavation construction, the empty top space of the arch is filled with sprayed concrete. Each time the excavation is carried out to a distance of 4000~5000mm from the advanced pipe shed 2, the next cycle of advanced pipe shed 2 construction is carried out;
[0062] The erection of steel arch frame 8 support is the same as the conventional shaft excavation process, including two processes: scaffolding support and pouring concrete construction. The scaffolding support adopts a combined support method of metal mesh + 18# I-beam steel scaffolding + shotcrete + masonry. The metal mesh is made of φ6mm round steel, the grid is 120mm×120mm, the overlap spacing is 120mm, and it is tied with iron wire. The spacing of the binding holes is connected. The mesh is close to the rock surface and there must be no empty side or empty top. Then the I-beam steel scaffold is erected. The spacing of the scaffolds in the loess section is 500mm, and the spacing of the scaffolds in the Luohe section is 800mm. The base is welded with 380*380*16mm steel plates. The base of the wall leg must fall on the solid bottom. In case of soft soil, steel plates need to be added to the base of the wall leg to prevent the wall leg from sinking and causing the steel scaffold to tilt. Φ20 steel bars are used for welding and fixing between the scaffolds, with a spacing of 600mm. The mesh is completely covered with shotcrete.
[0063] The concrete pouring construction is carried out in parallel with the excavation. After the excavation, net hanging, I-beam shed erection and spraying are completed, the arch frame and formwork are erected to carry out the concrete pouring construction. The pouring section distance is 3m at a time. If the surrounding rock conditions are good, the pouring length can be appropriately extended. After 24 hours of pouring, the demoulding is carried out to enter the next cycle.
[0064] C: According to the standard construction process, the concrete floor is poured on the current circulation roadway surface (the floor concrete material cement can be P.042.5 ordinary silicate cement, 12mm gravel and fine sand are used as aggregates, and the poured concrete strength is C30 self-mixed concrete). After completion, the roadway bottom plate 3 is reinforced. When muddy mud flows at the bottom of the poured roadway, pipe piles 6 and wooden boards are used to block the muddy flow at the bottom to prevent large-area cavities in the bottom plate. After the bottom plate is excavated to the designed elevation, plum blossom-shaped layout is used. Pipe piles 6 are placed for construction. The diameter of the pipe piles 6 is Φ108mm. The pipe piles 6 are driven into the bedrock of the Luohe Formation. 18# I-beams 5 are arranged in sequence above the pipe piles 6. Individual pipe piles 6 are welded to the bottom beams of the I-beams 5. To prevent mud flow, a layer of cell bags 7 is laid under the I-beams 5. The cell bags 7 are made of crushed stone and cement mixed in a mass ratio of 1:0.5. The depth of the cell bags 7 at the bottom of the I-beams 5 is 500mm. Then, the roadway floor is constructed according to the floor design structure drawing. Concrete is poured according to the design requirements. After solidification, the floor is stabilized.
[0065] D: Carry out the next cycle of construction along the excavation direction, repeating steps C and D in a cross-type manner. The construction process is as follows: Figure 5 As shown, until the construction of the entire shaft is completed.
[0066] It should be noted that the verticality of each bored pile directly determines the expected effect of the curtain on the wall of the tunnel in the shaft. If the pile body exceeds the rough diameter too much, not only will the workload of sealing the water and mud bursts at the pile spacing increase, but it will also easily form voids outside the bored pile curtain, making excavation more difficult, and will cause the filling volume to be too large or fail to achieve the curtain effect. At the same time, the starting part of the first cycle pipe shed constructed in advance 2 occupies the size of the permanent support and is the key reinforcement link. When the tunnel is excavated inward, the tunnel floor 3 is the weak point in the pressure equalization process after the drainage well stops draining. Therefore, it is particularly important for the present invention to reinforce the floor with pipe piles, cell bags, etc.
[0067] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for illustrating the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which shall fall within the scope of the present invention to be protected. The scope of the present invention to be protected is defined by the attached claims and their equivalents.
Claims
1. A shaft support method for solving the problem of loess vibration liquefaction in saturated soft loess sections, characterized in that: The following steps are involved: S1: Laying out the concrete pile curtain (1); Locate the excavation path of the roadway on the ground, set out the pile driving distance and the center point of the cast-in-place pile along both sides of the excavation path, and determine the drilling position; Drill holes in sequence according to the determined drilling positions to form multiple injection holes. The holes are arranged in an arc shape with a radius of 2000 mm on both sides of the excavation section. After the drilling depth reaches the bottom plate of the tunnel (3), it continues downward to within 1500-2000 mm of the hard bedrock. Concrete is poured into each of the grouting holes in turn, and after solidification, a concrete pile curtain (1) is formed, wherein the diameter of each concrete pile is 1000 mm, and the distance between two adjacent concrete piles is 200 mm; If the mud flow between the piles is serious and cannot be blocked during the excavation construction, continue to construct the second row of piles. The second row of piles is arranged outside the first row of piles and arranged in the gap between the two piles in the first row. S2: Laying out the advanced pipe shed (2) to form an arch support curtain; The advanced pipe shed (2) is constructed in sections from the tunnel section inside the shaft, and an arch support curtain is formed at the top of the excavated wasteland. After the support is completed, the tunnel is excavated into the tunnel; S3: reinforce the tunnel floor (3); The tunnel floor (3) excavated in step S2 is reinforced, and steps S2 and S3 are repeated in a cross-type manner until the shaft construction is completed.
2. A shaft support method for solving the problem of loess vibration liquefaction in saturated soft loess sections according to claim 1, characterized in that: In step S2, the construction of the advanced pipe shed (2) adopts progressive segmented construction, from supporting the advanced pipe shed (2), to excavating the section, and then to reinforcing the bottom plate to complete a cycle. The specific steps are as follows: S21: Positioning the construction angle of the advanced pipe shed (2); S22: Determine the length of the pipe shed for the first cycle of construction according to the clear height in the tunnel and the angle positioned in step S21; S23: starting the construction of the first cycle of advanced pipe shed (2), after which the tunnel section is excavated along the excavation direction, and after the excavation reaches a set distance, the next cycle of advanced pipe shed (2) is constructed; S24: Repeat step S23, and ensure that after the construction of each cycle of the advanced pipe shed (2) is completed, the top steel arch frame (8) supports the empty top distance no more than 400 mm.
3. A shaft support method for solving the problem of loess vibration liquefaction in saturated soft loess sections according to claim 2, characterized in that: In step S23, the advanced pipe rack (2) is constructed by threading a plurality of seamless steel pipes with a diameter of Φ108 mm and a thickness of 8 mm. Except for the first cycle, the length of the advanced pipe rack (2) in each of the remaining cycles is 15000 mm. When the advanced pipe rack (2) cannot be used for construction on both sides of the arch, a horizontal small conduit pipe rack with a diameter of Φ50 mm and a length of 3000 mm is used for construction.
4. A shaft support method for solving the problem of loess vibration liquefaction in saturated soft loess sections according to claim 3, characterized in that: In step S3, the steps of reinforcing the tunnel floor (3) are specifically as follows: S31: After the base plate is excavated to the designed elevation, pipe piles are arranged and the pipe piles (6) are driven into the bedrock; S32: erecting an I-beam above the pipe pile (6), and welding part of the pipe pile (6) to the bottom beam of the I-beam (5); S33: Lay a layer of cell bags (7) under the I-beam (5), and pour concrete according to design requirements to form a stable tunnel floor (3).
5. A shaft support method for solving the problem of loess vibration liquefaction in a saturated soft loess section according to claim 1, characterized in that: In step S31, the pipe piles (6) are steel pipes with a diameter of Φ108 mm, and the pipe piles (6) are arranged in a plum blossom shape.
6. A shaft support method for solving the problem of loess vibration liquefaction in saturated soft loess sections according to claim 5, characterized in that: In step S33, the cell bag (7) is made of crushed stone and cement mixed in a mass ratio of 1:0.5, and the depth of the cell bag (7) located at the bottom of the I-beam (5) is 500 mm.
7. An application of a wellbore support method for solving the problem of loess vibration liquefaction in saturated soft loess sections, characterized in that: The method described in any one of claims 1 to 6 is applied to a saturated soft loess section subjected to loess vibration liquefaction to achieve shaft excavation construction.
Citation Information
Patent Citations
Tunnel pavement longitudinal crack reinforcing treatment construction method
CN112301829A
Underpass tunnel structure for preventing lateral deformation of overpass pile foundation and construction method
CN114250780A
Shield tunneling machine interval earth surface reinforcing method
CN118375434A
Cast-in-place concrete pile curtain for reinforcing and supporting loess section shaft
CN221645836U
Tunnel excavation method for upper-soft and lower-hard stratum
WO2022083096A1