Charging pile orderly charging method, system and fusion terminal based on fusion terminal

Through the orderly charging method of charging piles based on the integrated terminal, the charging demand, status and power consumption data are used to intelligently schedule charging time and power, and the problem of insufficient capacity saturation and charging control strategies of community power grids is solved, which improves charging efficiency and reduces the cost. The impact of the power grid.

CN118578927BActive Publication Date: 2024-11-15CHENGDU HANDU TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411063506.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-05
Publication Date
2024-11-15
Estimated Expiration
2044-08-05

AI Technical Summary

Technical Problem

The rapid growth of private piles for community electric vehicles has led to saturation of community power grid capacity, and the existing community charging control strategies lack adjustable load control, resulting in the impact of private pile electricity on community power grids, and the hardware upgrade cost is high and the promotionality is poor.

Method used

The orderly charging method of charging piles based on the fusion terminal is adopted. By obtaining the charging demand data of each vehicle, the charging status data of the charging module, the power consumption data of the distribution station area and the open capacity of the transformer, a charging strategy is generated and charging is intelligently dispatched. Time and charging power achieve on-time and on-demand charging, reducing the impact on the community power grid.

Benefits of technology

It improves charging efficiency, reduces the impact of private pile electricity on the community power grid, avoids the high cost of hardware upgrades, makes full use of the peak and valley volatility of the power grid, and realizes intelligent and orderly charging.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118578927B_ABST
    Figure CN118578927B_ABST
Patent Text Reader

Abstract

The present application discloses a method, system and fusion terminal for orderly charging of charging piles based on fusion terminals, and relates to the field of new energy technology. The method includes: obtaining charging demand data of each vehicle, current charging status data of the charging module, current power consumption data of the distribution station area and the open capacity of the transformer; the charging module includes multiple charging piles; according to the charging demand data, charging status data, power consumption data and the open capacity of the transformer, a charging strategy is generated, and the charging strategy is sent to the charging module, and the charging strategy includes the charging time and charging power corresponding to each vehicle. In this way, an orderly charging strategy can be formulated for users on time and on demand, charging efficiency can be improved, and the impact of private pile electricity consumption on the community power grid can be reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of new energy technology, and in particular to a method and system for orderly charging of charging piles based on a fusion terminal, and a fusion terminal. Background Art

[0002] As the number of private charging stations for electric vehicles in communities increases, the distribution capacity of the substations gradually reaches saturation or even exceeds the capacity, which will have an impact on the community power grid capacity.

[0003] If the grid capacity is increased to reduce the impact of private charging piles on the community grid, the community distribution network needs to be upgraded, which is costly and has poor scalability and feasibility. In addition, the current community charging control strategy lacks adjustable load control for charging piles. Summary of the invention

[0004] The main purpose of this application is to provide a charging pile orderly charging method, system and fusion terminal based on a fusion terminal, so as to formulate an orderly charging strategy for users on time and on demand, improve charging efficiency, and reduce the impact of private pile electricity consumption on the community power grid.

[0005] To achieve the above objectives, the present application provides a charging pile orderly charging method based on a fusion terminal, comprising:

[0006] Obtaining charging demand data of each vehicle, current charging status data of the charging module, current power consumption data of the distribution station area, and available capacity of the transformer; the charging module includes multiple charging piles;

[0007] A charging strategy is generated according to the charging demand data, the charging status data, the power consumption data and the open capacity of the transformer, and the charging strategy is sent to the charging module. The charging strategy includes the charging time and charging power corresponding to each of the vehicles.

[0008] Optionally, the charging demand data includes the required charging amount and required charging completion time of the vehicle, the charging status data includes the number of idle charging piles, the output power of idle charging piles, the number of operating charging piles, the output power of operating charging piles and the service time of operating charging piles, and the power consumption data includes the current load data of the distribution station area, heavy load time and light load time; generating a charging strategy based on the charging demand data, the charging status data, the power consumption data and the openable capacity of the transformer includes: determining the charging sequence of each of the vehicles based on the openable capacity of the transformer, the number of idle charging piles, the output power of the idle charging piles, the number of operating charging piles, the output power of the operating charging piles and the service time of the operating charging piles; for any vehicle, determining the charging time and charging power of the vehicle based on the required charging amount, the required charging completion time, the current load data, the heavy load time, the light load time, the charging sequence and preset electricity price data.

[0009] Optionally, determining the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the current load data, the heavy load time, the light load time, the charging sequence and the preset electricity price data includes: when the distribution station area is determined to be in a light load state according to the current load data, determining the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the charging sequence and the preset electricity price data; when the distribution station area is determined to be in a heavy load state according to the current load data, determining the charging time and charging power of the vehicle according to the required charging amount, the current load data, the required charging completion time, the heavy load time, the light load time, the charging sequence and the preset electricity price data.

[0010] Optionally, the charging pile is a V2G charging pile, and the method further includes: when it is determined according to the current load data that the distribution station area is in an overloaded state, sending discharge order information to the user terminal corresponding to each of the vehicles, and receiving feedback information sent by each of the user terminals based on the discharge order information; when it is determined according to the feedback information that the vehicle corresponding to the user terminal has accepted the order, determining the discharge time and discharge power of the vehicle.

[0011] In addition, to achieve the above-mentioned purpose, the present application also provides a fusion terminal, including an uplink module and a local module; the uplink module communicates with the distribution cloud master station, and is used to receive the current power consumption data of the distribution station area sent by the distribution cloud master station, and send the power consumption data to the local module; the local module is used to receive the charging demand data of each vehicle, the charging status data of the charging module and the open capacity of the transformer, and generate a charging strategy based on the charging demand data, the charging status data, the power consumption data and the open capacity of the transformer, and send the charging strategy to the charging module.

[0012] Optionally, the charging module includes multiple charging piles, the charging demand data includes the required charging amount and required charging completion time of the vehicle, the charging status data includes the number of idle charging piles, the output power of idle charging piles, the number of operating charging piles, the output power of operating charging piles and the service time of operating charging piles, and the power consumption data includes the current load data of the distribution station area, heavy load time and light load time; the local module is specifically used to: determine the charging sequence of each of the vehicles according to the open capacity of the transformer, the number of idle charging piles, the output power of the idle charging piles, the number of operating charging piles, the output power of the operating charging piles and the service time of the operating charging piles; for any vehicle, determine the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the current load data, the heavy load time, the light load time, the charging sequence and preset electricity price data.

[0013] Optionally, the local module is also specifically used to: when the distribution station area is determined to be in a light-load state according to the current load data, determine the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the charging sequence and the preset electricity price data; when the distribution station area is determined to be in a heavy-load state according to the current load data, determine the charging time and charging power of the vehicle according to the required charging amount, the current load data, the required charging completion time, the heavy-load time, the light-load time, the charging sequence and the preset electricity price data.

[0014] Optionally, the charging pile is a V2G charging pile, and the local module is further specifically used to: when it is determined that the distribution station area is in an overloaded state according to the current load data, send discharge order information to the user terminal corresponding to each of the vehicles, and receive feedback information sent by each of the user terminals based on the discharge order information; when it is determined that the vehicle corresponding to the user terminal has accepted the order according to the feedback information, determine the discharge time and discharge power of the vehicle.

[0015] In addition, to achieve the above-mentioned purpose, the present application also provides an orderly charging system for charging piles based on a fusion terminal, including a fusion terminal as described in any of the above, and a distribution cloud master station, a vehicle networking platform and a charging module that are communicatively connected to the fusion terminal; the distribution cloud master station is used to obtain the current power consumption data of the distribution station area and send the power consumption data to the fusion terminal; the vehicle networking platform is used to obtain the charging demand data of each vehicle, and send each charging demand data to the distribution cloud master station, and the distribution cloud master station sends it to the fusion terminal; the charging module includes multiple charging piles, and the charging module is used to The fusion terminal is used to obtain the current charging status data and send the charging status data to the fusion terminal; the fusion terminal is used to obtain the open capacity of the transformer, and receive the charging demand data, the charging status data and the power consumption data, and generate a charging strategy according to the charging demand data, the charging status data, the power consumption data and the open capacity of the transformer, and send the charging strategy to the charging module, wherein the charging strategy includes the charging time and charging power corresponding to each of the vehicles; the charging module is also used to control the operation of each of the charging piles according to the charging strategy sent by the fusion terminal.

[0016] Optionally, the system further includes a communication unit; the charging module and the fusion terminal establish a communication connection based on the communication unit.

[0017] The orderly charging method of charging piles based on the integrated terminal provided in the present application obtains the charging demand data of each vehicle, the current charging status data of the charging module, the current power consumption data of the distribution station area and the open capacity of the transformer; the charging module includes multiple charging piles; and then generates a charging strategy based on the charging demand data, charging status data, power consumption data and the open capacity of the transformer, and sends the charging strategy to the charging module. The charging strategy includes the charging time and charging power corresponding to each vehicle, fully utilizing the peak and valley fluctuations of electricity consumption in the community power grid, and intelligently setting the charging time and charging power for each vehicle in combination with user needs, thereby realizing the formulation of orderly charging strategies for users on time and on demand, improving charging efficiency, and reducing the impact of private pile electricity consumption on the community power grid. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 is a schematic diagram of an orderly charging system for charging piles based on a fusion terminal according to an embodiment of the present application;

[0019] Figure 2 This is one of the flow charts of the method for orderly charging of charging piles based on a fusion terminal in an embodiment of the present application;

[0020] Figure 3 This is the second flow chart of the orderly charging method of the charging pile based on the fusion terminal in the embodiment of the present application;

[0021] Figure 4 This is the third flow chart of the orderly charging method of the charging pile based on the fusion terminal in the embodiment of the present application;

[0022] Figure 5 This is the fourth flowchart of the method for orderly charging of charging piles based on a fusion terminal in an embodiment of the present application.

[0023] The realization of the purpose, functional features and advantages of this application will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION

[0024] In order to make the purpose, technical solutions and advantages of this application clearer, the technical solutions in this application will be clearly and completely described below in conjunction with the drawings in this application. Obviously, the described embodiments are part of the embodiments of this application, not all of them. Based on the embodiments in this application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0025] At present, due to the rapid development of new energy vehicles, the number of private charging piles for electric vehicles in communities has gradually increased, and community private charging piles are usually connected to the community power grid. As a result, the community power distribution capacity has gradually reached saturation or even overloaded, which has caused a certain impact on the capacity of the community power grid. If this problem is solved by increasing the capacity of the power grid, it is necessary to upgrade the hardware of the community distribution network, which is costly and has poor scalability and executability. In addition, the conventional power grid load in the community has peak and valley fluctuations, and the current management model of the community power grid does not fully utilize this fluctuation, and lacks adjustable load control for charging piles.

[0026] To this end, the embodiments of the present application provide a method, system and fusion terminal for orderly charging of charging piles based on fusion terminals. Under the premise of not affecting the basic load power supply of the substation area, the charging efficiency is improved through an intelligent and orderly charging strategy, and users are guided to charge their vehicles in batches, on time and on demand, thereby reducing the impact of private pile electricity consumption on the community power grid.

[0027] For ease of understanding, the orderly charging system for charging piles based on a fusion terminal provided in an embodiment of the present application is first introduced in detail below.

[0028] Figure 1 Schematic diagram of the orderly charging system of charging piles based on the fusion terminal in the embodiment of the present application. Figure 1 As shown, the charging pile orderly charging system based on the fusion terminal may include: a fusion terminal 110, a power distribution cloud master station 120, a vehicle networking platform 130 and a charging module 140. The power distribution cloud master station 120, the vehicle networking platform 130 and the charging module 140 establish communication connections with the fusion terminal 110 respectively.

[0029] Among them, the distribution cloud master station 120 is used to obtain the current power consumption data of the distribution station area, and send the power consumption data to the fusion terminal 110; the Internet of Vehicles platform 130 is used to obtain the charging demand data of each vehicle, and send each charging demand data to the fusion terminal 110 through the distribution cloud master station 120; the charging module 140 includes multiple charging piles, and the charging module 140 is used to obtain the current charging status data, and send the charging status data to the fusion terminal 110; the fusion terminal 110 is used to obtain the openable capacity of the transformer, and receive the charging demand data, charging status data and power consumption data, and generate a charging strategy based on the charging demand data, charging status data, power consumption data and the openable capacity of the transformer, and send the charging strategy to the charging module 140, the charging strategy includes the charging time and charging power corresponding to each vehicle; the charging module 140 is also used to control the operation of each charging pile according to the charging strategy issued by the fusion terminal 110.

[0030] In this embodiment, the power distribution cloud master station 120 can be a cloud platform, and the power distribution cloud master station 120 can monitor the power consumption data of the power distribution station area in real time and store the power consumption data of the power distribution station area. The power consumption data of the power distribution station area can generally include the current load data of the power distribution station area, daily heavy load time, and daily light load time, etc.; the current load data of the power distribution station area can be used to determine whether the power distribution station area is currently in a peak power consumption period or a low power consumption period, and the daily heavy load time and light load time can be used as a reference. In this embodiment, the power distribution cloud master station 120 can establish a communication connection with the fusion terminal 110 through the Internet, and the power distribution cloud master station 120 can send the acquired power consumption data of the power distribution station area to the fusion terminal 110 in real time, so that the fusion terminal 110 determines the charging strategy based on the power consumption data.

[0031] In some implementations, the load data in the power consumption data may not need to be sent from the power distribution cloud master station 120 to the fusion terminal 110. In actual application, the load data can be directly transmitted from the area master meter to the fusion terminal 110 via RS485.

[0032] Furthermore, the Internet of Vehicles platform 130 is a platform that combines automobiles with the Internet through cloud computing technology and includes multiple functions, such as querying vehicle information, owner information, real-time traffic conditions, navigation, remote control, etc. Users can query information on the Internet of Vehicles platform 130 through user terminals, or upload vehicle charging and discharging requests. The Internet of Vehicles platform 130 then sends the vehicle charging and discharging requests uploaded by the user terminals to the fusion terminal 110, and the fusion terminal 110 then determines the charging strategy based on the vehicle charging and discharging requests.

[0033] Specifically, after the user establishes a connection with the Internet of Vehicles platform 130 through the user terminal, the user can report the charging demand or discharge request to the Internet of Vehicles platform 130 through the user terminal, and can also report the current status data of the vehicle, such as the remaining power, etc. to the Internet of Vehicles platform 130 through the user terminal. In addition, the Internet of Vehicles platform 130 can also send the charging status data of the vehicle (for example, whether charging has been completed, the current charging amount, etc.) to the user terminal so that the user can obtain the charging status of his vehicle.

[0034] In this embodiment, the charging module 140 may include multiple charging piles, and the Internet of Vehicles platform 130 may establish a communication connection with the charging module 140 so that the Internet of Vehicles platform 130 can obtain the charging status data of the vehicle from the charging module 140 in real time. It should be noted that some sensors are usually set inside the charging pile to detect its working voltage, working power, etc., and the charging status of the charging pile can be known through these data. These data that can characterize the charging status of the charging pile can all be used as the charging status data of the charging pile, and the charging module 140 can be sent to the fusion terminal 110 through various communication methods such as LoRa, RS485, HPLC, etc.

[0035] It is worth mentioning that when deploying charging facilities for the community, it can be configured according to about 20% of the total surplus load of the community's distribution capacity, that is, when the regular power load of the community is met, 20% of the surplus distribution capacity will be used for electric vehicle charging, and the average distribution capacity of each charging pile is about 8kW. Taking the most common AC charging pile as an example, the rated power of a charging pile is 7kW. According to the load characteristics and load analysis of the distribution station area, a daily dynamic open capacity curve is formed, which can fully calculate the surplus capacity resources of the distribution, maximize the use of the dynamic power supply capacity of the station area, and greatly increase the number of charging piles that the distribution station area can carry.

[0036] In some embodiments, the orderly charging system of charging piles based on the fusion terminal may further include a communication unit (not shown in the figure); the charging module 140 and the fusion terminal 110 establish a communication connection based on the communication unit. In this embodiment, the communication mode of the communication unit may include wireless communication and wired communication, and the wireless communication may be implemented by LoRa (radio frequency communication), and the wired communication may be implemented by RS485 equipment and HPLC (High Power Line Carrier, low voltage power line high speed carrier communication) equipment.

[0037] Specifically, based on the principles of safety, reliability, and economic applicability, a regional network for various communications such as long-distance wireless can be constructed between the charging module 140 and the fusion terminal 110. For example, multiple communications can be constructed using RS485 equipment, HPLC equipment, and LoRa equipment. As a result, each charging pile can communicate with the fusion terminal 110 based on the communication protocol to achieve long-distance wireless communication or wired communication, so that the fusion terminal 110 can collect the charging and discharging status data, power size and other data of each charging pile in real time, and support the unified access and collection of the data of each charging pile device in the group quantity perception layer.

[0038] In addition, intelligent micro-breaker devices (not shown in the figure) can also be deployed in the orderly charging system of charging piles based on the fusion terminal. Intelligent micro-breaker devices are devices that integrate miniature circuit breakers, contactors, electric meters and RS485 communication functions. Intelligent micro-breaker devices can communicate with the fusion terminal through RS485. It has the ability to integrate sub-item metering and sub-item control. Intelligent micro-breaker devices use magnetic latching relays and MCU technology to achieve automatic disconnection protection for overcurrent and short circuit of charging piles, and closing / disconnection of remote automatic and on-site manual control circuits, thereby achieving observable, adjustable and controllable charging pile data.

[0039] In this embodiment, the fusion terminal 110 may also establish a connection relationship with the transformer 150 of the substation, and the fusion terminal 110 may obtain the openable capacity of the transformer, so as to determine the charging strategy based on the openable capacity of the transformer.

[0040] Specifically, after the user sends a charging request to the Internet of Vehicles platform 130 through the user terminal, the Internet of Vehicles platform 130 sends the corresponding charging demand data to the fusion terminal 110 through the power distribution cloud master station 120. At the same time, the power distribution cloud master station 120 can send the current power consumption data of the distribution station area to the fusion terminal 110, and the charging module 140 reports the current charging status data of the charging pile to the fusion terminal 110 through the communication unit. Further, the fusion terminal 110 can obtain the open capacity of the transformer. After the fusion terminal 110 receives the above data, it will generate a charging strategy based on the above data, for example, in which period the charging pile charges the user's vehicle, and what is the corresponding output power; the fusion terminal 110 can send the charging strategy to the charging module 140, so that the charging module 140 operates according to the charging strategy. In this way, while meeting the user's vehicle demand, the charging pile can charge the user's vehicle during the low power consumption period or low electricity price period of the distribution station area.

[0041] The structure and function of the converged terminal 110 are further described in detail below.

[0042] On the basis of the above-mentioned embodiments, the embodiment of the present application further provides a fusion terminal 110, which may include an uplink module and a local module. Among them, the uplink module can communicate with the power distribution cloud master station 120, and the uplink module is used to receive the current power consumption data of the distribution station area sent by the power distribution cloud master station 120, and send the power consumption data to the local module; the local module is used to receive the charging demand data of each vehicle, the charging status data of the charging module 140, and the open capacity of the transformer, and generate a charging strategy based on the charging demand data, charging status data, power consumption data, and the open capacity of the transformer, and send the charging strategy to the charging module 140.

[0043] Specifically, the uplink module can communicate with the power distribution cloud master station 120 through a wireless network, and the uplink module can receive the current power consumption data of the power distribution station area sent by the power distribution cloud master station 120, and the uplink module sends the power consumption data to the local module. The local module can receive the charging demand data of each vehicle sent by the Internet of Vehicles platform 130, the current charging status data of the charging pile reported by the charging module 140 through the communication unit, and obtain the open capacity of the transformer.

[0044] Furthermore, the local module can be based on the current power consumption data of the distribution station area, with the charging time and charging power of the vehicle as the control variables, and taking into account the user's charging needs and battery performance (for example, charge and discharge rate, state of charge, cycle life), etc., with the goal of minimizing the impact on the power grid or optimizing the economy, comprehensively determine a charging strategy, and send the charging strategy to the charging module 140, so as to achieve orderly charging of electric vehicles. In addition, the charging strategy of this embodiment will also be determined based on the order in which users request charging, that is, users need to make an appointment for charging through the user terminal, and those who make an appointment first can charge first, thus realizing "first come, first charge, appointment charging". By automatically optimizing and adjusting the real-time charging power or splitting and combining the power output, the charging time period is allocated in an orderly and reasonable manner, the resource utilization efficiency of the substation area is improved, and the travel needs of users are maximized.

[0045] In some embodiments, the charging module 140 includes a plurality of charging piles, the charging demand data includes the required charging amount and the required charging completion time of the vehicle, the charging status data includes the number of idle charging piles, the output power of the idle charging piles, the number of running charging piles, the output power of the running charging piles and the service time of the running charging piles, and the power consumption data includes the current load data of the distribution station area, the heavy load time and the light load time. The local module is specifically used to: determine the charging sequence of each vehicle according to the open capacity of the transformer, the number of idle charging piles, the output power of the idle charging piles, the number of running charging piles, the output power of the running charging piles and the service time of the running charging piles; for any vehicle, determine the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the current load data, the heavy load time, the light load time, the charging sequence and the preset electricity price data.

[0046] Specifically, the local module can first determine the charging sequence of each vehicle based on the open capacity of the transformer, the number of idle charging piles, the output power of the idle charging piles, the number of running charging piles, the output power of the running charging piles, and the service time of the running charging piles. For example, when the open capacity of the transformer is small, or the number of idle charging piles is small, the vehicles that have been booked first can be charged first, or the vehicles whose required charging completion time is closer to the current time can be charged first, or the vehicles that have been charged for a period of time can be stopped from charging to avoid some vehicles occupying the charging piles for a long time.

[0047] In some embodiments, the local module is also specifically used to: when the distribution station area is determined to be in a light-load state according to the current load data, determine the charging time and charging power of the vehicle according to the required charging amount, required charging completion time, charging sequence and preset electricity price data; when the distribution station area is determined to be in a heavy-load state according to the current load data, determine the charging time and charging power of the vehicle according to the required charging amount, the current load data, the required charging completion time, the heavy-load time, the light-load time, the charging sequence and the preset electricity price data.

[0048] It should be noted that the preset electricity price data refers to the electricity prices for different time periods of the day determined according to policies, historical electricity prices, etc.; the demand charging completion time refers to the time before which the user needs to complete charging; the heavy load time refers to the time period when the load in the distribution station area is heavier, and the light load time refers to the time period when the load in the distribution station area is lighter. In this embodiment, both the heavy load time and the light load time can be determined by historical load data. For example, it is determined through historical load data that the load is heavier from 18:00 to 20:00 and lighter from 9:00 to 11:00 every day. In this way, the heavy load time can be set to include 18:00-20:00, and the light load time can be set to include 9:00-11:00. Other time periods of the day can be distinguished in the same way. Thus, different time periods of the day can be divided into two categories: heavy load time and light load time.

[0049] Specifically, the current load data of the distribution station area can reflect the load situation of the distribution station area, that is, whether the distribution station area is in a peak period or a low period. When it is determined that the distribution station area is currently in a low period or a peak period according to the current load data, the charging time and charging power can be determined for the vehicles that have made reservations first according to the order of reservations, specifically based on the required charging amount, required charging completion time, charging sequence, and preset electricity price data, so as to meet the user's vehicle needs while ensuring the lowest charging cost for the user.

[0050] In some embodiments, the charging pile is a V2G charging pile, and the local module is also specifically used to: when it is determined that the distribution station area is in an overloaded state according to the current load data, send discharge order information to the user end corresponding to each vehicle, and receive feedback information sent by each user end based on the discharge order information; when it is determined that the user end corresponds to the vehicle to receive the order according to the feedback information, determine the discharge time and discharge power of the vehicle.

[0051] It should be noted that the specific process of the integrated terminal-based charging pile orderly charging method executed by the integrated terminal 110 can refer to the process in the subsequent method embodiments, which will not be described in detail here.

[0052] On the basis of the above-mentioned embodiments, the embodiments of the present application further provide a method for orderly charging of charging piles based on a fusion terminal, which can be executed by the above-mentioned fusion terminal. Figure 2 This is one of the flow charts of the orderly charging method of the charging pile based on the fusion terminal in the embodiment of the present application. Figure 2 As shown, the orderly charging method of the charging pile based on the fusion terminal may include the following steps:

[0053] Step 210: Acquire the charging demand data of each vehicle, the current charging status data of the charging module, the current power consumption data of the distribution station area, and the available capacity of the transformer; the charging module includes multiple charging piles.

[0054] Step 220: Generate a charging strategy based on the charging demand data, charging status data, power consumption data and the available capacity of the transformer, and send the charging strategy to the charging module. The charging strategy includes the charging time and charging power corresponding to each vehicle.

[0055] It should be noted that the vehicle's charging demand data can be uploaded by the user through the user terminal, and may include the time the user needs to use the vehicle after charging, the remaining power of the vehicle, etc.; the current charging status data of the charging module may include information on whether the charging pile is in a charging state, the length of time it has been charged, etc.; the current power consumption data of the distribution station area may include the current load data of the station area, etc.; the open capacity of the transformer refers to how much additional load the transformer can withstand while ensuring normal operation.

[0056] Specifically, the fusion terminal can obtain the current power consumption data of the distribution area from the distribution cloud master station, the charging demand data of each vehicle from the Internet of Vehicles platform, and the current charging status data from the charging module. The fusion terminal can also directly collect the open capacity from the transformer. After the fusion terminal obtains the above data, it can generate a charging strategy based on the above data and send the charging strategy to the charging module, which operates based on the charging strategy.

[0057] In some embodiments, the charging demand data includes the required charging amount and the required charging completion time of the vehicle, the charging status data includes the number of idle charging piles, the output power of the idle charging piles, the number of operating charging piles, the output power of the operating charging piles and the service time of the operating charging piles, and the power consumption data includes the current load data of the distribution station area, the heavy load time and the light load time.

[0058] Figure 3 This is the second flow chart of the method for orderly charging of charging piles based on the integrated terminal in the embodiment of the present application. Figure 3 As shown, step 220 generates a charging strategy according to the charging demand data, the charging state data, the power consumption data and the available capacity of the transformer, which may include the following steps:

[0059] Step 310: Determine the charging sequence of each vehicle according to the available capacity of the transformer, the number of idle charging piles, the output power of the idle charging piles, the number of operating charging piles, the output power of the operating charging piles, and the service time of the operating charging piles.

[0060] Step 320: For any vehicle, determine the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the current load data, the heavy load time, the light load time, the charging sequence and the preset electricity price data.

[0061] Specifically, the fusion terminal can first determine the charging sequence of each vehicle based on the available capacity of the transformer, the number of idle charging piles, the output power of the idle charging piles, the number of running charging piles, the output power of the running charging piles, and the service time of the running charging piles. For example, when the available capacity of the transformer is small, or the number of idle charging piles is small, the vehicles that have been booked first can be charged first, or the vehicles whose required charging completion time is closer to the current time can be charged first, or the vehicles that have been charged for a period of time can be stopped from charging to avoid some vehicles occupying the charging piles for a long time.

[0062] In this embodiment, the charging priority of each vehicle that needs to be charged, that is, the charging order of each vehicle, can be determined based on the open capacity of the transformer, the number of idle charging piles, the output power of the idle charging piles, the number of operating charging piles, the output power of the operating charging piles, and the service time of the operating charging piles. In addition, corresponding weights can be added to the above parameters according to their importance.

[0063] Among them, the transformer open capacity refers to the maximum value of the electric energy that the transformer can transmit under certain conditions. This value is usually less than the rated capacity of the transformer. It is related to the capacity of the transformer, but it is not completely equal to the rated capacity of the transformer. Considering the open capacity of the transformer is to ensure that the transformer will not be overloaded under normal operating conditions, thereby ensuring the normal operation and safety and stability of the power system. The number of idle charging piles and the output power of idle charging piles refer to the number of charging piles that are currently available for charging and not occupied by electric vehicles within the monitoring range and the corresponding output power of the charging piles. The number of operating charging piles and the output power of operating charging piles refer to the number of charging piles that are being charged within the monitoring range and the corresponding output power of the charging piles. The remaining charging time of the operating charging piles refers to the remaining time for the charging piles that are being charged to complete the current charging. The weight coefficient can be customized according to the attention of the judge, ranging from (0%-100%).

[0064] Furthermore, the charging time and charging power can be determined for each vehicle in sequence according to the charging sequence. The charging time can be determined specifically according to the required charging completion time, current load data, heavy load time, light load time, and preset electricity price data. For example, when the user's required charging completion time is met, the light load time of the station area or the time period with lower electricity price in the preset electricity price data is selected to charge the vehicle. The charging power can be determined specifically according to the charging time and the required charging amount.

[0065] Figure 4 This is the third flow chart of the orderly charging method of the charging pile based on the fusion terminal in the embodiment of the present application. Figure 4 As shown, in some embodiments, step 320 determines the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the current load data, the heavy load time, the light load time, the charging sequence, and the preset electricity price data, and may include the following steps:

[0066] Step 410: When the distribution station area is determined to be in a light-load state according to the current load data, the charging time and charging power of the vehicle are determined according to the required charging amount, the required charging completion time, the charging sequence and the preset fee data.

[0067] Step 420: When the distribution station area is determined to be in a heavy-load state according to the current load data, the charging time and charging power of the vehicle are determined according to the required charging amount, the current load data, the required charging completion time, the heavy-load time, the light-load time, the charging sequence and the preset fee data.

[0068] Specifically, the current load data of the distribution station area can reflect the load situation of the distribution station area, that is, whether the distribution station area is in a peak period or a low period. When it is determined according to the current load data that the distribution station area is currently in a low period (i.e., a light load state), the vehicles that have made reservations first can be charged first in the current time period according to the reservation order, and the charging power can be determined specifically according to the required charging amount and the required charging completion time.

[0069] As an example, if the current time is 10 a.m., and the current load data determines that the distribution station area is in a low electricity consumption period, and the preset electricity price data determines that this is a low electricity price, and the user uploads the required charging completion time as 6 p.m., then the vehicle can be charged starting in the current time period (i.e. 10 a.m.).

[0070] When it is determined based on the current load data that the distribution station area is currently in the peak period of electricity consumption (i.e., heavy load state), the charging time and charging power of the vehicle can be determined based on the required charging amount, current load data, required charging completion time, heavy load time, light load time, charging sequence, and preset fee data. For example, when it is currently in the peak period of electricity consumption, the vehicle will not be charged during this period. While meeting the user's required charging completion time, the light load time of the station area or the time period with lower electricity prices in the preset electricity price data can be selected to charge the vehicle, thereby meeting the user's vehicle use needs while ensuring the lowest charging cost for the user.

[0071] As an example, if the current time is 6 pm, and the current load data determines that the distribution station area is in the peak power consumption period, and the preset electricity price data determines that this is a high electricity price, and the user uploads the required charging completion time as 8 am the next day, then you can choose to charge the vehicle during the low power consumption period of 1 am to 6 am the next day.

[0072] In some implementations, a charging pile avoidance charging time period can also be determined by setting the overload time, the low voltage time period in the area, and the preset electricity price data. On the premise of meeting the user's vehicle use needs, the vehicle can avoid charging in the charging pile avoidance charging time period. For example, the charging pile avoidance charging time period can be determined based on the three aspects of the area overload time period, the area low voltage time period, and the peak, flat and valley electricity price; in addition, the corresponding weights can be added to the above three parameters according to the importance.

[0073] Among them, the heavy overload time period of the substation refers to the fact that the substation will collect three-phase voltage and three-phase current every 15 minutes. According to the calculated heavy overload situation, the time can be divided into normal time period, light load time period, heavy load time period, and overload time period. The low voltage time period of the substation refers to the fact that the substation will collect three-phase voltage every 15 minutes. According to the calculated voltage situation, the time can be divided into normal time period, high voltage time period, and low voltage time period. In addition, the electricity fee is divided into peak, flat, and valley stages. The electricity fees corresponding to the peak period, flat period, and valley period are different. Generally, the peak period electricity fee is the most expensive, and the valley period is the cheapest.

[0074] Figure 5 This is the fourth flow chart of the method for orderly charging of charging piles based on the integrated terminal in the embodiment of the present application. Figure 5 As shown, in some embodiments, the charging pile is a V2G charging pile, and the charging pile orderly charging method based on the fusion terminal may also include the following steps:

[0075] Step 510: When it is determined that the distribution station area is in a heavy-load state according to the current load data, discharge order information is sent to the user terminal corresponding to each vehicle, and feedback information sent by each user terminal based on the discharge order information is received.

[0076] Step 520: When it is determined based on the feedback information that the vehicle corresponding to the user terminal has accepted the order, the discharge time and discharge power of the vehicle are determined.

[0077] Specifically, when the distribution station area is in the peak period of electricity consumption, discharge order information can be sent to the user terminal through the Internet of Vehicles platform. The discharge order information can include prompt information such as the current electricity price and whether to accept the order; after the user views the discharge order information through the user terminal, he can choose whether to accept the order and find a charging pile that can support vehicle discharge to discharge the vehicle to the station area; if the user chooses to accept the order, the user terminal sends feedback information to the fusion terminal through the Internet of Vehicles platform, and the feedback information is the information of the user's acceptance of the order (for example, the discharge time period, the dischargeable amount of electricity); if the user chooses not to accept the order, similarly, the user terminal sends feedback information to the fusion terminal through the Internet of Vehicles platform, and the feedback information is the information that the user does not accept the order.

[0078] When the user chooses to accept the order, he can also make an appointment for discharge through the user terminal first. The user terminal reports the discharge request to the Internet of Vehicles platform, which is then sent to the fusion terminal via the power distribution cloud master station. The fusion terminal adds the vehicle corresponding to the user to the discharge list. Furthermore, the fusion terminal can obtain the current remaining power of the vehicle and the user's subsequent use information (for example, when the user needs to use the vehicle, how much power is required after the vehicle is discharged, etc.) through the Internet of Vehicles platform, and then determine the discharge time and discharge power of the vehicle based on the remaining power, the user's subsequent use information, and the current power consumption data of the substation; or, the user can choose the discharge time and discharge power of the vehicle by himself. The user terminal can provide multiple discharge time and discharge power options for users to choose. The discharge time and discharge power available to users can be preset and adjusted based on the current power consumption of the substation, the external discharge power of different models, and other data.

[0079] When there is an unexpected power consumption event in the substation, such as high voltage in the substation or reverse overload in the substation, the fusion terminal controls the charging pile to terminate the discharge, and sends the termination discharge information to the user through the Internet of Vehicles platform, so as to avoid the adverse effects of the discharge on the substation. If the voltage in the substation is too high, continuing to discharge may aggravate the damage to the substation equipment and safety hazards. If the substation is reverse overloaded, continuing to discharge will not only increase the burden on the equipment, but may also cause equipment damage, power grid failure, and safety accidents.

[0080] Therefore, by controlling the bidirectional charging and discharging of electric vehicle batteries, the batteries of large-scale electric vehicles can be used as distributed energy storage systems, combined with energy router applications, to create local microgrid collaborative control. During the peak load period of the power grid in the substation area, users can choose to discharge on their own, and during the low load period of the power grid in the substation area, the user's vehicle is charged, and the charging and discharging process is reasonably optimized and coordinated, which plays a role of "peak shaving and valley filling", and can also participate in the frequency regulation of the power system. Compared with traditional system frequency modulation power supplies, electric vehicles participating in frequency modulation have the advantage of fast response speed. During the peak power consumption period, the discharge pressure of the substation area is effectively alleviated, and at the same time, it can bring certain benefits to users and achieve mutual assistance between vehicles and the grid.

[0081] It should be noted that for details not disclosed in the orderly charging method of charging piles based on the fusion terminal in this embodiment, please refer to the details disclosed in the orderly charging system of charging piles based on the fusion terminal or the embodiments of the fusion terminal in the embodiments of this specification, and they will not be repeated here.

[0082] The above are only preferred embodiments of the present application, and are not intended to limit the patent scope of the present application. Any equivalent structure or equivalent process transformation made using the contents of the present application specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present application.

Claims

1. A charging pile orderly charging method based on a fusion terminal, characterized in that: include: Obtain the charging demand data of each vehicle, the current charging status data of the charging module, the current power consumption data of the distribution area, and the available capacity of the transformer; The charging module includes a plurality of charging piles; Generate a charging strategy according to the charging demand data, the charging status data, the power consumption data and the available capacity of the transformer, and send the charging strategy to the charging module, wherein the charging strategy includes the charging time and charging power corresponding to each of the vehicles; The charging demand data includes the required charging amount and required charging completion time of the vehicle, the charging status data includes the number of idle charging piles, the output power of idle charging piles, the number of running charging piles, the output power of running charging piles and the service time of running charging piles, and the power consumption data includes the current load data, heavy load time and light load time of the distribution station area; The generating a charging strategy according to the charging demand data, the charging state data, the power usage data and the available capacity of the transformer includes: Determine a charging sequence for each of the vehicles according to the available capacity of the transformer, the number of idle charging piles, the output power of the idle charging piles, the number of operating charging piles, the output power of the operating charging piles, and the service time of the operating charging piles; For any vehicle, determining the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the current load data, the heavy load time, the light load time, the charging sequence and the preset electricity price data; The charging pile is a V2G charging pile, and the method further includes: When it is determined that the distribution station area is in an overload state according to the current load data, sending discharge order information to the user terminals corresponding to each of the vehicles, and receiving feedback information sent by each of the user terminals based on the discharge order information; In the case where it is determined according to the feedback information that the vehicle corresponding to the user terminal has accepted an order, determining a discharge time and a discharge power of the vehicle; When a sudden power consumption event is detected in the distribution station area, the charging pile is controlled to terminate discharging.

2. The orderly charging method for charging piles based on a fusion terminal according to claim 1 is characterized in that: The determining the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the current load data, the heavy load time, the light load time, the charging sequence and the preset electricity price data includes: When it is determined according to the current load data that the distribution station area is in a light-load state, determining the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the charging sequence and the preset electricity price data; When the distribution station area is determined to be in a heavy-load state according to the current load data, the charging time and charging power of the vehicle are determined according to the required charging amount, the current load data, the required charging completion time, the heavy-load time, the light-load time, the charging sequence and the preset electricity price data.

3. A fusion terminal, characterized in that: Includes uplink module and local module; The uplink module communicates with the power distribution cloud master station, and is used to receive the current power consumption data of the power distribution station area sent by the power distribution cloud master station, and send the power consumption data to the local module; The local module is used to receive the charging demand data of each vehicle, the charging status data of the charging module and the open capacity of the transformer, and generate a charging strategy according to the charging demand data, the charging status data, the power consumption data and the open capacity of the transformer, and send the charging strategy to the charging module; The charging module includes a plurality of charging piles, the charging demand data includes the required charging amount and the required charging completion time of the vehicle, the charging status data includes the number of idle charging piles, the output power of idle charging piles, the number of running charging piles, the output power of running charging piles and the service time of running charging piles, and the power consumption data includes the current load data, heavy load time and light load time of the distribution station area; the local module is specifically used for: Determine a charging sequence for each of the vehicles according to the available capacity of the transformer, the number of idle charging piles, the output power of the idle charging piles, the number of operating charging piles, the output power of the operating charging piles, and the service time of the operating charging piles; For any vehicle, determining the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the current load data, the heavy load time, the light load time, the charging sequence and the preset electricity price data; The local module is also specifically used for: When it is determined that the distribution station area is in an overload state according to the current load data, sending discharge order information to the user terminals corresponding to each of the vehicles, and receiving feedback information sent by each of the user terminals based on the discharge order information; In the case where it is determined according to the feedback information that the vehicle corresponding to the user terminal has accepted an order, determining a discharge time and a discharge power of the vehicle; When a sudden power consumption event is detected in the distribution station area, the charging pile is controlled to terminate discharging.

4. The converged terminal according to claim 3, characterized in that: The local module is also specifically used for: When it is determined according to the current load data that the distribution station area is in a light-load state, determining the charging time and charging power of the vehicle according to the required charging amount, the required charging completion time, the charging sequence and the preset electricity price data; When the distribution station area is determined to be in a heavy-load state according to the current load data, the charging time and charging power of the vehicle are determined according to the required charging amount, the current load data, the required charging completion time, the heavy-load time, the light-load time, the charging sequence and the preset electricity price data.

5. An orderly charging system for charging piles based on a fusion terminal, characterized in that: include: The fusion terminal according to claim 3 or 4, and a power distribution cloud master station, a vehicle networking platform and a charging module communicatively connected to the fusion terminal; The power distribution cloud master station is used to obtain current power consumption data of the power distribution station area and send the power consumption data to the fusion terminal; The Internet of Vehicles platform is used to obtain charging demand data of each vehicle, and send each charging demand data to the power distribution cloud master station, and the power distribution cloud master station sends it to the fusion terminal; The charging module includes a plurality of charging piles, and the charging module is used to obtain current charging status data and send the charging status data to the fusion terminal; The fusion terminal is used to obtain the openable capacity of the transformer, and receive the charging demand data, the charging status data and the power consumption data, and generate a charging strategy according to the charging demand data, the charging status data, the power consumption data and the openable capacity of the transformer, and send the charging strategy to the charging module, wherein the charging strategy includes the charging time and charging power corresponding to each of the vehicles; The charging module is also used to control the operation of each charging pile according to the charging strategy sent by the fusion terminal.