A method for intelligent construction of BIM model for construction projects
By building a BIM model database, analyzing historical construction data, and predicting subsequent construction time, the problem of poor accuracy of BIM models in project progress supervision is solved, and accurate estimation of subsequent progress and enhancement of construction management are achieved.
Patent Information
- Application Number
- CN202411052253.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-08-02
AI Technical Summary
The BIM model has poor accuracy in project progress supervision and cannot effectively help customers understand the estimated construction time of each subsequent progress.
By building a BIM model database, we can obtain data such as material usage, construction progress, workers' rest and working hours during the historical construction process, analyze workers' work completion, material supply stability, and construction stability, and predict subsequent construction progress based on construction difficulty. Time, construct the BIM model of each subsequent time node.
It improves the accuracy of BIM models in project progress supervision, helps customers understand the estimated construction time of each subsequent progress, and enhances the controllability of construction management.
Smart Images

Figure CN118586676B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of data processing, and in particular to a method for intelligently constructing a BIM model for a construction project. Background Art
[0002] BIM (Building Information Modeling, or BIM for short) is a three-dimensional digital model technology that integrates information related to construction projects. It is widely used in building planning, design, construction and operation management processes, significantly improving the efficiency of project management. BIM model construction is based on data such as geometric information, professional attributes and status information of building construction.
[0003] In the construction of engineering projects, BIM technology can well display the design intent and construction progress. However, in the specific implementation process, BIM technology is usually not good in the supervision of construction project progress. Generally, designers will build BIM models for each time node based on the ideal construction situation. However, due to the different actual construction conditions of each project, such as the working status of workers, material supply status, construction difficulty and other factors, the BIM model has poor accuracy in project progress supervision and cannot effectively help customers understand the estimated construction time of each subsequent progress of the project. Summary of the invention
[0004] In order to solve the technical problem that the BIM model in the prior art has poor accuracy in project progress supervision and cannot effectively help customers understand the estimated construction time of each subsequent progress of the project, the purpose of the present invention is to provide a method for intelligently constructing a BIM model for a construction project. The technical solution adopted is as follows:
[0005] A method for intelligently constructing a BIM model for a construction project, the method comprising:
[0006] Step S1: construct a BIM model database based on the material usage, construction progress, worker rest time, and worker working time at each moment of the historical construction process;
[0007] Step S2: according to the overall average rest time, the overall average working time under all construction schedules of the historical construction process and the average rest time and the average working time under a construction schedule, obtain the working time performance of the workers under the schedule;
[0008] Step S3: Obtain the work completion degree of the worker in the progress according to the planned and actual material usage quantity of the worker in an area under the progress, the planned and actual construction building area of the area under the progress, and the working time performance of the worker in the progress;
[0009] Step S4: According to the quantity of materials that the supplier should deliver under a schedule and the quantity of materials that are not delivered on time, the actual delivery time and the stipulated delivery time of the materials, and the remaining principal of the project, the stability of the material supply under the schedule is obtained;
[0010] Step S5: Obtaining the construction stability under a progress according to the completion degree of the workers' work under a progress and the stability of the material supply under the progress;
[0011] Step S6: Obtaining an estimated construction time for each subsequent progress according to the construction time, construction difficulty, and construction stability of each progress in the historical construction process, as well as the construction stability and construction difficulty of each subsequent progress;
[0012] Step S7: Construct the BIM model of each subsequent time node according to the estimated construction time of each subsequent progress.
[0013] Furthermore, the time specifically corresponding to each moment in step S1 is every day.
[0014] Further, in step S2:
[0015] The average rest time is specifically: the average of the rest time of the workers at each moment in a progress; the rest time is 24 hours minus the total working time of the workers at that moment;
[0016] The average working time is specifically: the average working time of the worker at each moment under a progress; the working time is the total working time of the worker punching in at that moment;
[0017] The overall average rest time is specifically: the mean of the average rest time of workers at each progress in the historical construction process;
[0018] The overall average working time is specifically: the mean of the average working time of workers at each progress in the historical construction process.
[0019] Furthermore, in the step S2, based on the overall average rest time, the overall average working time of all construction schedules in the historical construction process and the average rest time and average working time under one construction schedule, the working time performance of the workers under the schedule is obtained. Specifically, the working time performance of the workers under one construction schedule is obtained based on the difference between the average working time under one construction schedule and the overall average working time under all construction schedules in the historical construction process, and the difference between the average rest time under one construction schedule and the overall average rest time under all construction schedules in the historical construction process.
[0020] Furthermore, in step S3, according to the planned material usage quantity and actual usage quantity of a worker in an area under a progress, the planned construction area and actual construction area of the area under the progress, and the working time performance of the worker under the progress, the work completion degree of the worker under the progress is obtained specifically as follows:
[0021] Calculate the ratio of the actual material usage of workers in an area under a schedule to the actual construction area of the area under the schedule, and obtain the actual material consumption per unit area under the schedule;
[0022] Calculate the ratio of the planned material usage quantity of a worker in an area under a schedule to the planned construction area under the schedule in the area, and obtain the material consumption of the planned unit area under the schedule in the area;
[0023] The worker's work completion degree under a schedule is obtained based on the absolute value of the difference between the worker's actual material consumption per unit area under a schedule and the planned material consumption per unit area and the worker's working time performance under the schedule.
[0024] Furthermore, in step S3, the smaller the absolute value of the difference between the actual material consumption per unit area of the worker at a certain progress and the planned material consumption per unit area, and the greater the working time performance of the worker at the certain progress, the higher the work completion degree of the worker at the certain progress.
[0025] Furthermore, in step S4, the stability of material supply under a schedule is obtained according to the quantity of materials that should be delivered by the supplier under a schedule and the quantity of materials not delivered on time, the actual delivery time of the materials and the prescribed delivery time, and the remaining principal of the project. Specifically, the stability of material supply under a schedule is obtained according to the ratio of the quantity of materials not delivered on time to the quantity of materials that should be delivered under a schedule, the difference between the actual delivery time of the materials and the prescribed delivery time, and the remaining principal of the project.
[0026] Furthermore, in step S4, the smaller the ratio of the number of materials not delivered on time by the supplier under a certain schedule to the number of materials that should be delivered, the smaller the difference between the actual delivery time of the materials and the prescribed delivery time, and the more the remaining principal of the project, the higher the stability of the material supply under this schedule.
[0027] Furthermore, in step S5, the higher the degree of completion of the workers' work at a certain progress and the higher the stability of the material supply, the higher the construction stability at that progress.
[0028] Furthermore, in step S6, according to the construction time of each progress in the historical construction process, the construction difficulty of each progress, the construction stability of each progress and the construction stability of each subsequent progress, and the construction difficulty of each subsequent progress, the estimated construction time of each subsequent progress is obtained. Specifically, according to the construction time of each progress in the historical construction process, the ratio of construction stability to construction difficulty under each progress, the ratio of construction stability to construction difficulty of each subsequent progress, and the number of construction progresses in the historical construction process, the estimated construction time of each subsequent progress is obtained.
[0029] The present invention has the following beneficial effects: it can solve the technical problems in the prior art that the BIM model has poor accuracy in project progress supervision and cannot effectively help customers understand the estimated construction time of each progress. The present invention predicts the relevant data information of the subsequent stage based on the data information of the existing historical construction process of the construction project; analyzes the working status of the workers in the construction process, combines the stability of the materials provided by the material suppliers in each progress of the construction project, and the construction difficulty of each project progress, calculates the stability of the construction process, and further combines the overall difficulty of different project progress to predict the duration of the subsequent project progress, and helps to build a subsequent BIM model, so that the construction party can provide customers with subsequent predictions based on the current construction progress, so that customers have a certain understanding of the project progress, which can have a certain supervision effect on the project. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] In order to more clearly illustrate the technical solutions and advantages in the embodiments of the present invention or the prior art, the drawings required for use in the embodiments or the prior art descriptions are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0031] Figure 1 A flow chart of a method for intelligently constructing a BIM model for a construction project provided by an embodiment of the present invention. DETAILED DESCRIPTION
[0032] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the following is a detailed description of the specific implementation method, structure, characteristics and effects of a construction engineering BIM model intelligent construction method proposed by the present invention in combination with the accompanying drawings and preferred embodiments. In the following description, different "one embodiment" or "another embodiment" does not necessarily refer to the same embodiment. Unless otherwise defined, all technical and scientific terms used in this article have the same meaning as those generally understood by technicians in the technical field of the present invention.
[0033] The specific scheme of the intelligent construction method of the BIM model of a construction project provided by the present invention is explained in detail below with reference to the accompanying drawings.
[0034] The specific scenario targeted by the embodiments of the present invention is: mainly for various construction projects, during the construction process, the construction party needs to provide customers with subsequent forecasts based on the current construction progress, especially the construction time forecasts under various subsequent progress. Therefore, it is necessary to predict the duration of each subsequent progress and build a BIM model for each time node to help customers understand the progress of the project, which can have a certain supervisory effect on the project.
[0035] See also Figure 1 , which shows a flow chart of a construction engineering BIM model intelligent construction method provided by an embodiment of the present invention, the method comprising the following steps:
[0036] Step S1: Construct a BIM model database based on the material usage, construction progress, worker rest time, and worker working time at each moment of the historical construction process.
[0037] The time corresponding to each moment may be daily or weekly.
[0038] In this embodiment, it is first necessary to use various data of the construction process of the project to build a model, so data collection is required. These data include the use of building materials, construction progress, workers' rest time, workers' working time, etc. at each moment in the construction process. The specific collection method is: monitor the data information in the construction project within a certain period of time, and obtain the data information of the construction process at each moment within a certain period of time. Among them, the certain time described in this embodiment is from the beginning of construction to the end of construction, and the time corresponding to each moment is one day. Then, according to each construction cycle in the construction project design drawing, a real-time BIM model is constructed.
[0039] Real-time BIM model construction can intuitively reflect the current construction progress of the project. Before the construction project design begins, designers generally divide the project into progress categories. For customers, more accurate information is needed to understand the progress of the project construction. Therefore, it is necessary to predict the time to reach the next construction plan based on the relevant information shown in the current construction progress, and then build a BIM model based on data such as material consumption, so that customers can have a corresponding degree of control over the construction progress. Therefore, this embodiment further sets the following steps.
[0040] Step S2: According to the overall average rest time, the overall average working time under all construction schedules of the historical construction process and the average rest time and average working time under a construction schedule, the working time performance of the workers under the schedule is obtained.
[0041] Specifically, in step S2: the average rest time is specifically: the average of the rest time of the workers at each moment in a progress; the rest time is 24 hours minus the total working time of the workers punching in at that moment; the average working time is specifically: the average of the working time of the workers at each moment in a progress; the working time is the total working time of the workers punching in at that moment; the overall average rest time is specifically: the average of the average rest time of the workers at each progress in the historical construction process; the overall average working time is specifically: the average of the average working time of the workers at each progress in the historical construction process.
[0042] In order to obtain the working time performance of workers under this progress, first, in each progress of the construction project, define the average rest time of workers at each moment under a progress ,in Indicates The rest time is defined as 24 hours a day minus the total working time of workers punching in on that day; the average working time is further defined as: the average working time of workers at each moment under a progress , define working time as the total working time of workers punching in on that day; define overall average rest time as the average of the average rest time of workers at each progress in the historical construction process ; Define the overall average working time as the mean of the average working time of workers at each progress in the historical construction process ; The average rest time of workers under all completed progress builds a data series (in, is the mean of the rest time at each moment under the first progress, is the mean of the rest time at each moment under the second progress, is the mean of the rest time at each moment under the third progress, For the The minimum value of the data series is ; The average working time of workers under all completed progress builds a data series (in, is the average working time at each moment under the first progress, is the average working time at each moment under the second progress, is the average working time at each moment under the third progress, For the The maximum value of this data series is .
[0043] In engineering construction, if the average rest time and average working time of workers are in the data series , When the average rest time of workers is between the minimum and maximum values, when the average rest time of workers is smaller than the overall average rest time, it means that the workers have good working time performance; when the average working time of workers is larger than the overall average working time, it means that the workers have good working time performance.
[0044] Furthermore, in step S2, based on the overall average rest time, the overall average working time under all construction schedules of the historical construction process and the average rest time and average working time under one construction schedule, the working time performance of the workers under the schedule is obtained. Specifically, the working time performance of the workers under one construction schedule is obtained based on the difference between the average working time under one construction schedule and the overall average working time under all construction schedules of the historical construction process, and the difference between the average rest time under one construction schedule and the overall average rest time under all construction schedules of the historical construction process.
[0045] However, if the average rest time of workers is less than and / or the worker’s working hours are greater than When the worker's working time performance is improved compared with all previous progress, this situation needs to be considered in the worker's working time performance.
[0046] In this embodiment, the worker who builds The working time performance calculation formula under each progress is as follows:
[0047] ,
[0048] In the formula, Indicates that workers Working time performance under each schedule; Indicates that workers The average rest time at each moment under the progress, that is, Average rest time under each progress; It represents the average rest time of workers in all progress so far, that is, the overall average rest time of all construction progress in the historical construction process; Indicates that workers The average working time under the progress, that is, Average working time under each progress; It represents the average working time of workers in all progress so far, that is, the overall average working time of all construction progress in the historical construction process; Indicates the correction factor, which can be preset or 1.1 or 1, is a natural constant; Indicates normalization of values.
[0049] In the above workers In the working time performance calculation formula under each progress, Indicates that workers The difference between the average working time under the progress and the overall average working time under all construction progress in the historical construction process is related to the worker’s The working time performance under each progress is positively correlated; Indicates that workers The difference between the average rest time under the progress and the overall average rest time under all construction progress in the historical construction process is related to the worker’s rest time in the first The working time performance under each schedule is negatively correlated; , As natural constants The exponent of can effectively prevent the result from being 0; Represents the correction factor, when and , it means that the worker's working time performance at this moment is better than all previous progress, so it can be preset ;when , or , , it means that the worker's working time performance at this moment is better than all previous progress, so it can be preset ;when and , it means that the worker's working time performance at this moment is more referenceable than all previous progress, so it can be preset When the worker's rest time under this schedule is smaller than the historical average rest time, and the working time is larger than the historical working time, it means that the worker's working time performance is good; when the worker's rest time is smaller than the historical minimum rest time, and / or the worker's working time is longer than the historical maximum working time, it means that the worker's working time performance is particularly good. Therefore, Can be used as a worker in Working time performance under a schedule.
[0050] In the above, only considering the performance of workers' working hours as the subsequent estimated completion of the construction project, that is, the degree of work completion, is unreliable, and it is also necessary to comprehensively consider the work efficiency of workers during working hours. Specifically, the work efficiency of workers during working hours can be analyzed based on the material consumption of the construction process, but at the same time, when analyzing the material consumption of the construction process, it cannot be separated from the actual project, and it is necessary to specifically analyze the degree of work completion of workers in combination with the progress of the project within a specific time. Therefore, this embodiment further sets the following steps.
[0051] Step S3: Obtain the worker's work completion degree under a schedule based on the planned and actual material usage quantity of a worker in an area under a schedule, the planned and actual construction area of the area under the schedule, and the worker's working time performance under the schedule.
[0052] Specifically, in step S3, based on the planned material usage quantity and actual usage quantity of the workers in an area under a schedule, the planned construction area and actual construction area under the schedule, and the workers' working time performance under the schedule, the degree of completion of the workers' work under the schedule is obtained. Specifically, the ratio of the actual material usage quantity of the workers in an area under a schedule to the actual construction area under the schedule, and the actual material consumption per unit area under the schedule is obtained; the ratio of the planned material usage quantity of the workers in an area under a schedule to the planned construction area under the schedule, and the planned material consumption per unit area under the schedule is calculated to obtain the planned material consumption per unit area under the schedule; the degree of completion of the workers' work under the schedule is obtained according to the absolute value of the difference between the actual material consumption per unit area of the workers and the planned material consumption per unit area and the workers' working time performance under the schedule.
[0053] Furthermore, in step S3, the smaller the absolute value of the difference between the actual material consumption per unit area of a worker at a certain progress and the planned material consumption per unit area, and the greater the working time performance of the worker at the certain progress, the higher the work completion degree of the worker at the certain progress.
[0054] In this embodiment, the construction worker The calculation formula for the work completion degree under a progress is as follows:
[0055] ,
[0056] In the formula, Indicates that workers The degree of completion of work under each progress; Indicates the number of areas divided during the construction process; Indicates The progress of The actual amount of building materials used in each region; Indicates The progress of The actual building area of the area; Indicates The planned amount of building materials used in each area; Indicates The planned building area of the area; Indicates that workers Working time performance under each schedule; Indicates An exponential function with base 0 to prevent the denominator in the formula from being 0.
[0057] In the above workers In the work efficiency calculation formula under each progress, the formula logic is: , when the absolute value of the difference between the actual material consumption per unit area of workers under a certain schedule and the material consumption per unit area of the planned schedule is smaller, it means that the staff strictly abides by the construction standards and the workers have higher work efficiency under this schedule; in addition, when the workers Working time performance under each progress With workers in The degree of work completion under the progress Positive correlation, the better the worker's working time performance, the better the worker's work completion.
[0058] In this embodiment, the above process obtains the degree of completion of the workers' work at the progress. Since the requirements of each progress in the construction process are different, it is impossible to directly predict the time spent on the subsequent progress. However, during the construction process, the progress stability of the subsequent progress can be predicted based on the progress stability of the known progress, so as to further analyze the time spent on construction at each subsequent progress. Therefore, this embodiment sets the following steps.
[0059] Step S4: According to the quantity of materials that the supplier should deliver under a schedule and the quantity of materials not delivered on time, the actual delivery time of the materials and the stipulated delivery time, and the remaining principal of the project, the stability of the material supply under the schedule is obtained.
[0060] Specifically, in step S4, the stability of material supply under a schedule is obtained according to the quantity of materials that should be delivered by the supplier under a schedule and the quantity of materials not delivered on time, the actual delivery time of the materials and the prescribed delivery time, and the remaining principal of the project. Specifically, the stability of material supply under a schedule is obtained according to the ratio of the quantity of materials not delivered on time to the quantity of materials that should be delivered under a schedule, the difference between the actual delivery time of the materials and the prescribed delivery time, and the remaining principal of the project.
[0061] Furthermore, in step S4, the smaller the ratio of the number of materials not delivered on time by the supplier under a certain schedule to the number of materials that should be delivered, the smaller the difference between the actual delivery time of the materials and the prescribed delivery time, and the more the remaining principal of the project, the higher the stability of the material supply under this schedule.
[0062] When analyzing the stability of each progress, if the supplier's material supply efficiency is good, especially if the supplier's delivery of construction materials is good, it can be roughly considered that the stability of this progress during the construction process is high, where the delivery degree can be evaluated by the delivery quantity and delivery nodes; in addition, if the customer has more remaining capital, it means that it is more sufficient to purchase the materials needed for the progress, the material supplier will be more active, and the material supplier will deliver better construction materials.
[0063] In this embodiment, the constructed The calculation formula for the stability of material supply under a certain progress is as follows:
[0064] ,
[0065] In the formula, Indicates The stability of material supply under each schedule; Indicates the principal of the current project; Indicates The principal used for the project under the progress; Indicated in Progress has been completed before progress; Indicates that the supplier The number of deliveries not made on time under the schedule; Indicates The quantity of materials that the material supplier should deliver under the schedule; Indicates The difference between the actual delivery time of the material under the schedule and the stipulated delivery time; is a natural constant.
[0066] In the above-mentioned In the calculation formula of the stability of material supply under a certain progress, Indicates the remaining capital of the construction project. If the customer has more remaining capital, it means that it is more sufficient to purchase the materials required for the progress, so the stability of material supply is high. The supplier is in the first The ratio of the number of materials that should be delivered under the schedule to the number of materials that were not delivered on time The larger the The smaller the ratio of the number of materials not delivered on time to the number of materials that should be delivered under the progress, the higher the degree of material delivery by the supplier, so the stability of material supply is high; in addition, The smaller the difference between the actual delivery time and the stipulated delivery time under a schedule, the less the stability of the supply will be reduced. Therefore, the higher the stability of the material supply, the more stable the supply will be. Placed in natural constants The exponent is there to avoid the denominator being 0.
[0067] Step S5: According to the degree of completion of the workers' work at a certain progress and the stability of the material supply at the certain progress, the construction stability at the certain progress is obtained.
[0068] Specifically, in step S5, the higher the degree of completion of the workers' work at a certain progress and the higher the stability of the material supply, the higher the construction stability at that progress.
[0069] In this embodiment, the constructed The calculation formula for construction stability under a certain progress is as follows:
[0070] ,
[0071] In the formula, Indicates Construction stability under the progress, Indicates The stability of material supply under each schedule; Indicates that workers The degree of completion of work under each progress; Indicates normalization of values.
[0072] In the above-mentioned In the calculation formula of construction stability under the progress, The stability of material supply under the progress It is positively correlated with the corresponding construction stability; workers in the The work completion degree under a certain progress is positively correlated with its corresponding construction stability. The higher the degree of work completion under a schedule and the more stable the material supply under that schedule, the higher the construction stability under that schedule.
[0073] Step S6: Obtain the estimated construction time of each subsequent progress according to the construction time of each progress in the historical construction process, the construction difficulty of each progress, the construction stability of each progress and the construction stability of each subsequent progress, and the construction difficulty of each subsequent progress.
[0074] Specifically, in step S6, the estimated construction time of each subsequent progress is obtained according to the construction time of each progress in the historical construction process, the construction difficulty of each progress, the construction stability of each progress and the construction stability of each subsequent progress, and the construction difficulty of each subsequent progress. Specifically, the estimated construction time of each subsequent progress is obtained according to the construction time of each progress in the historical construction process, the ratio of construction stability to construction difficulty under each progress, the ratio of construction stability to construction difficulty of each subsequent progress, and the number of construction progresses in the historical construction process.
[0075] First, the construction stability under the known progress is used to predict the construction stability under each subsequent progress. Specifically, these construction stabilities are used as input data of the prediction model and added to the ARIMA model (Auto-Regressive Moving Average Model). This model belongs to a type of time series analysis and is mainly used for time series prediction, especially for converting non-stationary time series into stationary time series and describing them through mathematical models (which are well-known technologies and will not be discussed in detail in this embodiment); then, according to the characteristics of the time series, the parameters (p, d, q) in the ARIMA model are determined; finally, the maximum likelihood estimation is performed to determine the specific values of the parameters in the model, and the ARIMA model finally determined is used to predict future data points to obtain the stability of the subsequent progress. Furthermore, in the process of construction engineering, the duration of the construction progress is also related to the construction stability and construction difficulty of the progress. For a progress project with low construction stability, if its construction difficulty is high, the corresponding construction duration should be long.
[0076] Therefore, the subsequent The calculation formula for the construction time of each progress is as follows:
[0077] ,
[0078] In the formula, Indicates Construction time for each progress; Indicates the number of construction progress that has been completed; Indicates The overall difficulty of each schedule is marked in the project plan at the beginning. The overall difficulty of each schedule should be different due to the different engineering projects arranged; Indicates The overall difficulty of the progress; Indicates Construction stability under different schedules; Indicates Construction stability under different schedules; Indicates The construction time of each progress.
[0079] The subsequent In the construction time calculation formula for each progress, the formula logic is mainly based on Use the ratio relationship to obtain The construction time of each progress can be combined with the construction time of the previous progress to predict the completion time of each subsequent progress.
[0080] Step S7: Construct the BIM model of each subsequent time node according to the estimated construction time of each subsequent progress.
[0081] According to the estimated construction time of each subsequent progress, the BIM model of each subsequent time node is constructed. Specifically, according to the estimated construction time of each subsequent progress and the estimated consumption of different materials under each subsequent progress, the BIM model of each subsequent time node is constructed. This BIM model can effectively help customers understand the estimated construction time of each subsequent project progress.
[0082] A method for intelligently constructing a BIM model for a construction project in this embodiment constructs a BIM model database according to the material usage, construction progress, worker rest time, and worker working time at each moment of the historical construction process; obtains the worker's working time performance at the progress according to the overall average rest time, the overall average working time, and the average rest time and the average working time at all construction progresses in the historical construction process; obtains the worker's work completion at the progress according to the planned material usage quantity and the actual usage quantity of a region of the worker at the progress, the planned construction area and the actual construction area of the region of the progress, and the worker's working time performance at the progress; obtains the stability of material supply at the progress according to the quantity of materials that should be delivered by the supplier at a progress and the quantity of materials that are not delivered on time, the actual delivery time of the materials and the specified delivery time, and the remaining principal of the project; obtains the construction stability at the progress according to the worker's work completion at a progress and the stability of material supply at the progress; obtains the estimated construction time of each subsequent progress according to the construction time at each progress in the historical construction process, the construction difficulty of each progress, the construction stability at each progress, and the construction stability and construction difficulty of each subsequent progress. It can solve the technical problems in existing technologies such as poor accuracy of BIM models in project progress supervision and inability to effectively help customers understand the estimated construction time of each subsequent progress of the project.
[0083] It should be noted that the sequence of the above embodiments of the present invention is only for description and does not represent the advantages and disadvantages of the embodiments. The processes depicted in the accompanying drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.
[0084] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.
Claims
1. A method for intelligently constructing a BIM model for a construction project, characterized in that: The method comprises: Step S1: construct a BIM model database based on the material usage, construction progress, worker rest time, and worker working time at each moment of the historical construction process; Step S2: according to the overall average rest time, the overall average working time under all construction schedules of the historical construction process and the average rest time and the average working time under a construction schedule, obtain the working time performance of the workers under the schedule; Step S3: Obtain the work completion degree of the worker in the progress according to the planned and actual material usage quantity of the worker in an area under the progress, the planned and actual construction building area of the area under the progress, and the working time performance of the worker in the progress; Step S4: According to the quantity of materials that the supplier should deliver under a schedule and the quantity of materials that are not delivered on time, the actual delivery time and the stipulated delivery time of the materials, and the remaining principal of the project, the stability of the material supply under the schedule is obtained; Step S5: Obtaining the construction stability under a progress according to the completion degree of the workers' work under a progress and the stability of the material supply under the progress; Step S6: Obtaining an estimated construction time for each subsequent progress according to the construction time, construction difficulty, and construction stability of each progress in the historical construction process, as well as the construction stability and construction difficulty of each subsequent progress; Step S7: constructing BIM models of subsequent time nodes according to the estimated construction time of each subsequent progress; Workers in the The working time performance calculation formula under each progress is as follows: , In the formula, Indicates that workers Working time performance under each schedule; Indicates that workers The average rest time at each moment under the progress, that is, Average rest time under each progress; It represents the average rest time of workers in all progress so far, that is, the overall average rest time of all construction progress in the historical construction process; Indicates that workers The average working time under the progress, that is, Average working time under each progress; It represents the average working time of workers in all progress so far, that is, the overall average working time of all construction progress in the historical construction process; represents the correction factor, is a natural constant; Indicates normalization of values; Workers in the The calculation formula for the work completion degree under a progress is as follows: , In the formula, Indicates that workers The degree of completion of work under each progress; Indicates the number of areas divided during the construction process; Indicates The progress of The actual amount of building materials used in each region; Indicates The progress of The actual building area of the area; Indicates The planned amount of building materials used in each area; Indicates The planned building area of the area; Indicates that workers Working time performance under each schedule; represents an exponential function with a natural constant as base; No. The calculation formula for the stability of material supply under a certain progress is as follows: , In the formula, Indicates The stability of material supply under each schedule; Indicates the principal of the current project; Indicates The principal used for the project under each progress; Indicated in Progress has been completed before progress; Indicates that the supplier The number of deliveries not made on time under the schedule; Indicates The quantity of materials that the material supplier should deliver under the schedule; Indicates The difference between the actual delivery time of the material under the schedule and the stipulated delivery time; No. The calculation formula for construction stability under a certain progress is as follows: , In the formula, Indicates Construction stability under the progress, Indicates The stability of material supply under each schedule; Indicates that workers The degree of completion of work under each progress; Subsequent The calculation formula for the construction time of each progress is as follows: , In the formula, Indicates Construction time for each progress; Indicates the number of construction progress that has been completed; Indicates The overall difficulty of the progress; Indicates The overall difficulty of the progress; Indicates Construction stability under different schedules; Indicates Construction stability under different schedules; Indicates The construction time of each progress.
2. A construction engineering BIM model intelligent construction method according to claim 1, characterized in that: The time specifically corresponding to each moment in step S1 is every day.
3. A construction engineering BIM model intelligent construction method according to claim 1, characterized in that: In step S2: The average rest time is specifically: the average of the rest time of the workers at each moment in a progress; the rest time is 24 hours minus the total working time of the workers at that moment; The average working time is specifically: the average working time of the worker at each moment under a progress; the working time is the total working time of the worker punching in at that moment; The overall average rest time is specifically: the mean of the average rest time of workers at each progress in the historical construction process; The overall average working time is specifically: the mean of the average working time of workers at each progress in the historical construction process.
4. A construction engineering BIM model intelligent construction method according to claim 3, characterized in that: In the step S2, the working time performance of the workers in a construction progress is obtained based on the overall average rest time, the overall average working time of all construction progresses in the historical construction process, and the average rest time and average working time of the construction progress. Specifically, the working time performance of the workers in the construction progress is obtained based on the difference between the average working time of a construction progress and the overall average working time of all construction progresses in the historical construction process, and the difference between the average rest time of a construction progress and the overall average rest time of all construction progresses in the historical construction process.
5. The method for intelligently constructing a construction engineering BIM model according to claim 1, characterized in that: In step S3, the worker's work completion degree under a schedule is obtained according to the planned and actual material usage quantity of a worker in a region under a schedule, the planned and actual construction building area under the schedule and the region, and the worker's working time performance under the schedule: Calculate the ratio of the actual material usage of workers in an area under a schedule to the actual construction area of the area under the schedule, and obtain the actual material consumption per unit area under the schedule; Calculate the ratio of the planned material usage quantity of a worker in an area under a schedule to the planned construction area under the schedule in the area, and obtain the material consumption of the planned unit area under the schedule in the area; The worker's work completion degree under a schedule is obtained based on the absolute value of the difference between the worker's actual material consumption per unit area under a schedule and the planned material consumption per unit area and the worker's working time performance under the schedule.
6. A construction engineering BIM model intelligent construction method according to claim 5, characterized in that: In step S3, the smaller the absolute value of the difference between the actual material consumption per unit area of the worker at a certain progress and the planned material consumption per unit area, and the greater the working time performance of the worker at the certain progress, the higher the work completion degree of the worker at the certain progress.
7. A construction engineering BIM model intelligent construction method according to claim 1, characterized in that: In the step S4, the stability of the material supply under a schedule is obtained according to the quantity of materials that the supplier should deliver under a schedule and the quantity of materials not delivered on time, the actual delivery time of the materials and the prescribed delivery time, and the remaining principal of the project. Specifically, the stability of the material supply under a schedule is obtained according to the ratio of the quantity of materials not delivered on time to the quantity of materials that should be delivered under a schedule, the difference between the actual delivery time of the materials and the prescribed delivery time, and the remaining principal of the project.
8. A construction engineering BIM model intelligent construction method according to claim 7, characterized in that: In step S4, the smaller the ratio of the amount of materials not delivered on time by the supplier under a certain schedule to the amount of materials that should be delivered, the smaller the difference between the actual delivery time of the materials and the prescribed delivery time, and the larger the remaining principal of the project, the higher the stability of the material supply under the schedule.
9. The method for intelligently constructing a construction engineering BIM model according to claim 1, characterized in that: In step S5, the higher the degree of completion of the workers' work at a certain progress and the higher the stability of the material supply, the higher the construction stability at that progress.
10. The method for intelligently constructing a construction engineering BIM model according to claim 1, characterized in that: In the step S6, the estimated construction time of each subsequent progress is obtained according to the construction time of each progress in the historical construction process, the construction difficulty of each progress, the construction stability of each progress and the construction stability of each subsequent progress, and the construction difficulty of each subsequent progress. Specifically, the estimated construction time of each subsequent progress is obtained according to the construction time of each progress in the historical construction process, the ratio of construction stability to construction difficulty under each progress, the ratio of construction stability to construction difficulty of each subsequent progress, and the number of construction progresses in the historical construction process.