Ecological slope protection system based on ecological blanket and waste tires and its construction method
By using a zoning management method of using a combination of used tire sets and fixtures in the ecological blanket slope protection system, the problems of low construction efficiency, unfixed fixation and uneven watering are solved, and more efficient construction and maintenance are achieved.
Patent Information
- Application Number
- CN202411087473.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2044-08-09
AI Technical Summary
The existing ecological blanket slope protection construction has problems such as slow construction speed, low efficiency, high labor intensity, inconvenient local maintenance and replacement, unstable steel nails, easy to overhead, and uneven watering.
Using an ecological slope protection system based on ecological blankets and waste tires, a laying area is formed by setting up several second tire groups and the first tire groups, and the second fixing member and pressing mechanism are used to realize the partitioning and fixing of the ecological blankets, and watering is used to The components are evenly watered and maintained.
It improves construction speed and efficiency, reduces labor intensity, facilitates local maintenance and replacement, enhances the fixing and firmness of the ecological blanket, and ensures the uniformity of watering and construction quality.
Smart Images

Figure CN118600923B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of slope protection, in particular to an ecological slope protection system formed based on ecological blankets and waste tires and a construction method thereof. Background Art
[0002] In order to improve the ecological environment of the river bank and prevent soil erosion on the embankment slope, the river bank governance ecological project is divided into three parts: greening of embankments and flood control roads, ecological slope protection and ecological landscape. The main feature of this governance is to highlight ecological improvement, and the ecological blanket slope protection construction has attracted much attention due to its environmental protection, economy and good effect. Therefore, the process of laying flexible soil and water conservation ecological blankets is adopted. After governance, the goal of "clear water, smooth river, green bank, beautiful scenery and solid embankment" can be achieved, which will better benefit the people along the river.
[0003] The current construction process of ecological blanket is slope leveling → grooving → laying → overlapping and anchoring → maintenance; although the ecological blanket has a good effect, the existing ecological blanket slope protection still has the following problems:
[0004] First, for the overlapping and anchoring construction links: the ecological blanket needs to be overlapped along the direction of the water flow. At the shoulder position, a steel nail needs to be hammered in every 1m; at the overlapping position, a T-shaped steel nail needs to be hammered in every 1m; for other positions, a steel nail should be hammered in every 2-3m. Since the slope is inclined, workers have no fulcrum when standing on the slope for construction, so the construction is time-consuming and labor-intensive, and the construction speed is slow; and the relatively dense steel nail points further increase the labor intensity of the workers; the overlapping and fixed construction process determines that it needs to be overlapped and laid from one side to the other, which further reduces the overall construction efficiency; secondly, there are more steel nail points, which means that the probability of the ecological blanket being damaged by workers during the construction process is high. Once damaged, it needs to be repaired in time. If the damage is serious, it needs to be replaced with a new ecological blanket; however, after the overlap and fixation, the ecological blankets are chained together, which is very troublesome for replacing new ecological blankets and inconvenient for quick replacement; similarly, after the ecological blankets are installed and used for a certain period of time, for the ecological blankets that need to be partially replaced, it is not convenient to replace them because they are overlapped and fixed. Obviously, the workload of replacement will increase a lot.
[0005] Secondly, since the ecological blanket is fixed with steel nails, the effect of steel nails in the initial stage of construction is acceptable. However, if the local soil is loose, or long-term rain causes soil loss and landslides, if the plant seeds are not deeply rooted, the ecological blanket will slip and fail to protect the slope. In addition, the ecological blanket construction requirements mention that the ecological blanket needs to be close to the cushion or foundation and cannot be suspended; however, the steel nail fixation method is limited by the workers' level and is prone to overhead problems, which cannot guarantee the construction quality.
[0006] Third, during maintenance, watering is required to improve the germination and growth effects of the plants. Currently, watering is done manually with a water pipe. The biggest problem with this method is uneven watering, which is not conducive to maintenance management and is laborious, which may ultimately affect the germination and growth effects of the plants.
[0007] In view of the above pain points, it is necessary to optimize the existing ecological slope protection system and construction methods. Summary of the invention
[0008] The present invention aims to solve at least one of the technical problems in the related art to a certain extent. To this end, the present invention proposes an ecological slope protection system based on ecological blankets and waste tires and a construction method thereof. One of the purposes of the present invention is to solve the problems of slow construction speed, low efficiency, high labor intensity, low construction efficiency caused by the ecological blanket interlocking process, and inconvenient local maintenance and replacement; the second purpose of the present invention is to solve the problem of weak fixation due to steel nails and the ecological blanket being easily suspended; the third purpose of the present invention is to solve the problems of uneven watering and time-consuming and labor-intensive maintenance of the ecological blanket.
[0009] The technical solution of the present invention to solve the technical problem is:
[0010] In the first aspect, the technical solution proposes an ecological slope protection system based on ecological blankets and waste tires, including a slope body, wherein the slope body has a slope top and a slope foot, and a slope surface is formed between the slope top and the slope foot; a slope protection system is provided on the slope body, and the slope protection system includes:
[0011] Several second tire groups are arranged along the slope, each second tire group has several second tires arranged vertically; the second tire groups are arranged at intervals to divide the slope, and a paving area is formed between two adjacent second tire groups, and an ecological blanket is laid in the paving area; the second tire is a semi-buried structure; a cavity is formed between the second tire and the slope as a fulcrum;
[0012] The top end of the ecological blanket is fixed to the top of the slope, and the bottom end of the ecological blanket is laid to the foot of the slope;
[0013] The two side edges of the ecological blanket are fixed to the slope surface by a plurality of second fixing members arranged at intervals; the second fixing members are connected to the second tire;
[0014] It also includes several pressing mechanisms for fixing the ecological blanket in zones, the pressing mechanisms include a support frame detachably connected to a second fixing member, a gap being provided between the support frame and the ecological blanket; a rectangular pressing frame is placed on the ecological blanket, a plurality of second bolts are threadedly connected to the support frame, the bottom ends of the second bolts are positioned to act on the surface of the pressing frame, a plurality of pressing areas are formed on the surface of the ecological blanket, and the ecological blanket is tightly pressed on the slope.
[0015] Preferably, it also includes a first tire group arranged horizontally along the top of the slope, the first tire group is composed of several first tires arranged vertically, and the first tires are semi-buried structures; the top of the ecological blanket is fixed to the top of the slope by several first fixing members arranged at intervals; the first fixing member is connected to the first tire.
[0016] Preferably, the first fixing member includes two anchor rods, the rod walls of the anchor rods have threaded sections; the bottom ends of the anchor rods penetrate the first tire and are buried in the top of the slope; it also includes a base, the base is fixedly connected to one end of a cross brace, and the other end of the cross brace is threadedly connected to a first bolt for pressing down and fixing the ecological blanket; the top ends of the anchor rods are bolted and fixed to the base.
[0017] Preferably, the second fixing member includes a support device and a pressure plate, the two ends of the pressure plate are pressed on the edge of the ecological blanket, and the bottom end of the support frame is bolted and fixed to the pressure plate; the bottom end of the support device is pressed on the surface of the pressure plate, and the top end is supported on the second tire to form a counter-support structure.
[0018] Preferably, it also includes a pouring assembly, which includes a guide rail, the guide rail has two groups of slide grooves arranged along the length direction, the top of each group of second tire groups is connected to a guide rail, and a spray plate is slidably connected between adjacent guide rails. The spray plate is provided with a plurality of spray heads, and the spray plate is provided with a water inlet nozzle; the spray plate is also provided with a pull rope for driving the spray plate to move up and down.
[0019] Preferably, a pad is provided between the first bolt and the ecological blanket.
[0020] Preferably, a hardened layer is provided at the slope foot.
[0021] Secondly, this technical solution also proposes a construction method for an ecological slope protection system formed by ecological blankets and waste tires, the steps are as follows:
[0022] S1: Slope repair and construction stakeout;
[0023] S2: Install the first tire at the top of the slope to form a first tire group;
[0024] S3: installing second tires on the slope surface to form a plurality of second tire groups arranged at intervals; a paving area is formed between adjacent second tire groups;
[0025] S4: cutting the eco-mat according to the size of the laying area, and laying the cut eco-mat on the laying area;
[0026] S5: installing a first fixing member, and using the first fixing member to press and fix the top of the ecological blanket;
[0027] S6: installing a second fixing member, and using the second fixing member to press and fix the side edge of the ecological blanket;
[0028] S7: Install a pressing mechanism, and use the pressing mechanism to press and fix the surface of the ecological blanket in different areas. The first tire group, the second tire group and the ecological blanket together constitute the main body of the ecological slope protection system;
[0029] S8: Eco-mat maintenance: Use watering components to maintain the eco-mat.
[0030] The above technical solution has the following advantages or beneficial effects:
[0031] 1. The present invention adopts the idea of "zoning management" to divide the slope into several small paving areas, which can reduce the construction difficulty. Each paving area can be constructed separately, and multiple paving areas can be constructed at the same time, which greatly improves the construction efficiency. In the present invention, multiple groups of second tire groups are used to realize the segmentation of the slope, and the second tire is a semi-buried structure with a cavity as a fulcrum. This has the advantage of not only realizing waste utilization, but also using the cavity of the waste tire as a landing point for the sole of the foot or a gripping point for the palm of the hand, so that the workers have a fulcrum on the inclined slope, which is convenient for moving up and down, and improves safety and construction speed. Moreover, the elasticity of the waste tire can also be used to adaptively resist the swelling and shrinkage or frost heave and thaw deformation of the slope. The above idea can effectively solve the problems of slow construction speed, low efficiency and high labor intensity.
[0032] 2. The present invention abandons the traditional steel nail fixing method and adopts a second fixing part that can be easily disassembled to achieve the pressure and fixation of the side edge of the ecological blanket, which has the advantage of convenient disassembly. In addition, by setting a pressing mechanism, the zoned pressure and fixation of the surface of the ecological blanket is achieved. The pressing mechanism adopts a pressing frame pressing method, and the pressing area is large. Multiple pressing areas can be formed on the surface of the ecological blanket. The fixation is firm, the ecological blanket and the cushion layer or foundation fit well, it is not easy to be overhead, and the construction quality is guaranteed; in addition, the second fixing part and the pressing mechanism are both detachable, with a simple structure, low cost, easy transportation and assembly, and convenient disassembly and installation, which is beneficial to the local maintenance and replacement of the ecological blanket during the construction process or subsequent use, provides conditions for the idea of zoning management, and can solve the problems of low construction efficiency and inconvenient local maintenance and replacement caused by the chain process of the ecological blanket.
[0033] 3. The top surface of the second tire group is used as the installation base of the guide rail. A spray plate is installed on the guide rail. The spray plate can slide along the guide rail by its own gravity. Workers only need to pull the pull rope to control the up and down movement of the spray plate at the top of the slope, so as to facilitate the all-round watering and maintenance of the ecological blanket in the laying area, which can effectively solve the problems of uneven watering, time-consuming and labor-intensive maintenance of the ecological blanket. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] The accompanying drawings are used to provide further understanding of the present invention and constitute a part of the specification. They are used to explain the present invention together with the embodiments of the present invention and do not constitute a limitation of the present invention.
[0035] Figure 1 It is a structural stereogram of the ecological slope protection system proposed by the present invention (before the plants in the ecological blanket grow).
[0036] Figure 2 yes Figure 1 Schematic diagram of the enlarged structure of area A in the middle.
[0037] Figure 3 It is a structural schematic diagram of the connection relationship between the first fixing member and the first tire.
[0038] Figure 4 It is a schematic structural diagram of the matching relationship among the second fixing member, the second tire and the pressing mechanism in the present invention.
[0039] Figure 5 It is a structural stereogram of the ecological slope protection system proposed by the present invention (after the plants in the ecological blanket grow).
[0040] Figure 6 yes Figure 5 Schematic diagram of the enlarged structure of the middle C region.
[0041] Figure 7 It is a schematic diagram of the structure of the cooperation relationship between the second tire group, the holding mechanism and the guide rail.
[0042] Figure 8 yes Figure 7 Schematic diagram of the enlarged structure of the D region in the middle.
[0043] Description of reference numerals:
[0044] 1. Slope; 2. Slope foot; 3. Slope top; 4. First tire set; 401. Anchor rod; 5. Second tire set; 6. Guide rail; 7. Spray plate; 8. Pull rope; 9. Support frame; 10. Press frame; 11. Eco-mat; 12. Base; 13. Cross brace; 14. First bolt; 15. Pad; 16. Press plate; 17. Top support; 18. Upper positioning plate; 19. Second bolt; 20. Ear plate; 21. Fastening bolt; 22. Wheel; 23. Water inlet. DETAILED DESCRIPTION
[0045] In order to make the purpose, features and advantages of the present invention more obvious and easy to understand, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the embodiments described below are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0046] It should be noted that, in the description of the present invention, terms such as "up", "down", "left", "right", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the drawings. This is merely for the convenience of description and does not indicate or imply that the device or element must have a specific orientation, be constructed and operated in a specific orientation. Therefore, it should not be understood as a limitation on the present invention.
[0047] In addition, it should be noted that in the description of the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected" and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For those skilled in the art, the specific meanings of the above terms in the present invention can be understood according to the specific circumstances.
[0048] Embodiment 1:
[0049] like Figure 1 - Figure 8 As shown, this embodiment proposes an ecological slope protection system based on ecological blankets and waste tires, including a slope body 1, the slope body 1 has a slope top 3 and a slope foot 2, and a slope surface is formed between the slope top 3 and the slope foot 2; a slope protection system is provided on the slope body 1, and the slope protection system includes:
[0050] Several second tire groups 5 are arranged along the slope direction, and the second tire groups 5 are arranged along the water flow direction; each second tire group 5 has several vertically arranged second tires, and the second tires can be arranged at intervals or closely arranged. In this embodiment, a closely arranged manner is preferred; the second tire groups 5 are arranged at intervals to divide the slope, and a paving area is formed between two adjacent second tire groups 5, and an ecological blanket 11 is laid in the paving area; the structural form of the ecological blanket 11 can be as follows: the ecological blanket 11 includes a coconut fiber layer, a non-woven fabric layer, a water storage substrate layer, a coconut fiber layer, a non-woven fabric layer, a seed layer containing seeds, a non-woven fabric layer and a coconut fiber layer, which are arranged in sequence from bottom to top.
[0051] In this embodiment, it should be noted that the second tire is a semi-buried structure, and a cavity serving as a fulcrum is formed between the second tire and the slope surface; the central cavity of the second tire is used as a fulcrum, which makes it convenient for workers to grasp or step on the cavity during construction, facilitates up and down movement of construction, and improves safety.
[0052] The top of the ecological blanket 11 is fixed to the top of the slope 3, and the bottom of the ecological blanket 11 is laid to the foot of the slope 2;
[0053] The two side edges of the ecological blanket 11 are fixed to the slope surface through a plurality of second fixing members arranged at intervals; the second fixing members are connected to the second tire to form an integral body.
[0054] In this embodiment, a hardened layer is provided at the foot of the slope 2, and the hardened layer can be a gabion stone cage. As for the fixing method of the top and bottom of the ecological blanket 11, the existing grooving process can be used for fixing, that is, a groove is opened at the top of the slope 3 and the foot of the slope 2, and the top of the slope 3 is fixed with steel nails and then C20 concrete is used to press the top to fix the slope, and the foot of the slope 2 is fixed with steel nails and then gabion stone cages are used to fix the slope. For the groove, its depth and cross-sectional form should meet the requirements of the construction drawings. If there is a large amount of accumulated water in it, it is necessary to do a good job of drainage to avoid softening of its facade.
[0055] In addition, it should be noted that, in this embodiment, the ecological blanket 11 at the three locations on the top of the slope can also be fixed by a first fixing member, specifically in the following manner:
[0056] The ecological slope protection system also includes a first tire group 4 arranged horizontally along the slope top 3, the first tire group 4 is composed of several vertically arranged first tires, and the first tires are semi-buried structures; the top of the ecological blanket 11 is fixed to the slope top 3 by several first fixing members arranged at intervals; the first fixing member is connected to the first tire, and the first fixing member and the first tire are connected as a whole.
[0057] Regarding the first fixing member mentioned above, a detachable structure is preferably adopted, for example:
[0058] The first fixing member includes two anchor rods 401, and the rod wall of the anchor rod 401 has a threaded section; the bottom end of the anchor rod 401 passes through the first tire and is buried in the slope top 3; it also includes a base 12, the base 12 is fixedly connected to one end of a cross brace 13, and the other end of the cross brace 13 is threadedly connected to a first bolt 14 for pressing down and fixing the ecological blanket 11; the top end of the anchor rod 401 is bolted and fixed to the base 12; the base 12 is provided with a mounting hole, and the top end of the anchor rod 401 can freely pass through the mounting hole, and the top of the anchor rod 401 is threadedly connected to a fastening nut, so that the base 12 and the anchor rod 401 can be fixedly connected.
[0059] In this embodiment, a backing plate 15 is provided between the first bolt 14 and the ecological blanket 11 , and the backing plate 15 may be a whole bolt or a plurality of bolts.
[0060] It should be noted that in order to improve the pull-out resistance, the rod wall of the anchor rod 401 can be provided with a boss, which is positioned on the bottom surface of the tire. The anchor rod 401 passes through the tire, while the boss cannot pass through. In this way, the effective connection between the anchor rod 401 and the tire can be improved, and the anchoring force can be increased.
[0061] In order to overcome the disadvantages of steel nail fixation, a new fixation method is proposed:
[0062] The whole system also includes several pressing mechanisms for fixing the ecological blanket 11 in different areas. The pressing mechanisms include a support frame 9 detachably connected to the second fixing member, and there is a gap between the support frame 9 and the ecological blanket 11. A rectangular pressing frame 10 is placed on the ecological blanket 11, and several second bolts 19 are threadedly connected to the support frame 9. The bottom ends of the second bolts 19 are positioned to act on the surface of the pressing frame 10, and several pressing areas are formed on the surface of the ecological blanket 11, so that the ecological blanket 11 is tightly pressed on the slope. In this embodiment, a new pressing method is adopted to fix the ecological blanket 11, which has a simple structure, does not require steel nails, and will not damage the structure of the ecological blanket 11. A pressing frame 10 is pressed by two groups of pressing mechanisms adjacent to each other, which can well ensure the contact between the pressing frame 10 and the ecological blanket 11, and at the same time ensure the pressing area. The pressing area is large, the fixing force is good, and multiple pressing areas can be formed on the surface of the ecological blanket 11. The fixing is firm, the ecological blanket 11 has a good fit with the cushion or foundation, and it is not easy to be overhead, and the construction quality is guaranteed.
[0063] The above is a method for fixing the surface of the ecological blanket 11, and the two side edges of the ecological blanket 11 can be fixed in the following manner:
[0064] As mentioned above, the two side edges of the ecological blanket 11 can be fixed to the slope surface by a plurality of second fixing members arranged at intervals; the second fixing members not only play the role of a carrier for carrying the pressing mechanism, but also play the role of fixing the edge of the ecological blanket 11; its specific structural design is as follows:
[0065] The second fixing member includes a support 17 and a pressure plate 16. The two ends of the pressure plate 16 are pressed on the edge of the ecological blanket 11. In order to save materials, the two ends of the pressure plate 16 can press on the edges of two adjacent ecological blankets 11 at the same time; the bottom end of the support frame 9 is bolted and fixed to the pressure plate 16 to form a detachable structure, which is convenient for installation and disassembly; the bottom end of the support 17 is pressed on the surface of the pressure plate 16, and the top end is supported on the second tire to form a counter-support structure. Since the second tire is half-buried in the slope 1, the second tire has a good fixing force. In this embodiment, the support 17 can be a jack, such as a scissor jack, a screw jack and other common structures. When in use, the support device 17 is placed in the cavity of the second tire, and the top of the support device 17 is supported on the inner top of the second tire. Since the second tire cannot move, the bottom of the support device 17 can press the pressure plate 16 by relying on the reverse supporting force from the top, thereby tightly pressing the pressure plate 16 to the edge of the ecological blanket 11, thereby fixing the edge of the ecological blanket 11.
[0066] Invention concept:
[0067] The idea of "zoning management" is adopted to divide the slope into several small paving areas, which can reduce the construction difficulty. Each paving area can be constructed separately, and multiple paving areas can be constructed at the same time, which greatly improves the construction efficiency. In the present invention, multiple groups of second tire groups 5 are used to realize the segmentation of the slope, and the second tire is a semi-buried structure with a cavity as a fulcrum. This has the advantage of not only realizing waste recycling, but also using the cavity of the waste tire as a landing point for the sole of the foot or a gripping point for the palm of the hand, so that the workers have a fulcrum on the inclined slope, which is convenient for moving up and down, and improves safety and construction speed. Moreover, the elasticity of the waste tire can also be used to adaptively resist the swelling and shrinkage or frost heave and thaw deformation of the slope. The above idea can effectively solve the problems of slow construction speed, low efficiency and high labor intensity.
[0068] Construction technology:
[0069] This embodiment also proposes a construction method of an ecological slope protection system formed by an ecological blanket and waste tires, and the steps are as follows:
[0070] S1: Slope 1 repair and construction layout; 1) Slope leveling: Before construction, the slope surface needs to be repaired to make it sufficiently flat. If necessary, secondary leveling can be carried out manually. When leveling the slope, it is important to ensure that the slope or foundation that has been prepared meets the slope ratio in the drawing. There should be no gravel with a particle size of more than 50mm on the slope surface, nor should there be tree stumps, tree roots, or other garbage; there should be no concave or convex parts, and it needs to be compacted and all accumulated water within the paving construction range should be removed. If there is no natural topsoil on the slope surface, or the topsoil is thinner than the thickness required in the construction drawings, it is necessary to add topsoil to meet the design standards; 2) Locating: According to the design drawings, draw lines on the slope 1 to locate the installation position.
[0071] S2: According to the designed position, the first tire is installed at the slope top 3 to form the first tire group 4; a groove is first made at the slope top 3, and then the first tire is buried to form the first tire group 4. It should be noted that before installing the first tire, the anchor rod 401 needs to be installed on the first tire in advance, and then the anchor rod 401 is installed together with the first tire.
[0072] S3: According to the designed position, the second tires are installed on the slope to form a plurality of second tire groups 5 arranged at intervals; a paving area is formed between adjacent second tire groups 5; and the construction method of grooving and burying the second tires is also adopted.
[0073] S4: cutting the ecological blanket 11 according to the size of the laying area, and laying the cut ecological blanket 11 on the laying area;
[0074] S5: Install the first fixing part, and use the first fixing part to press and fix the top of the ecological blanket 11; the specific method is: connect the first bolt 14 to the cross brace 13 in advance; then use the base 12, the cross brace 13, and the first bolt 14 as a whole, and bolt the whole to the anchor rod 401; then screw the first bolt 14, press the first bolt 14 downward, and press and fix the upper edge of the ecological blanket 11.
[0075] S6: Install the second fixing member, and use the second fixing member to press and fix the side edge of the ecological blanket 11; when installing the second fixing member, it can be installed from top to bottom, using the second tire as a gripping point or a foothold, and installing the second fixing members in sequence to achieve the pressing and fixing of the side edge of the ecological blanket 11. Since the second tire is used as a foothold, the ecological blanket 11 will not be stepped on, so the damage to the ecological blanket 11 caused by the construction is very small, and there is almost no damage to the ecological blanket 11, which can effectively ensure the construction quality.
[0076] S7: Install the pressing mechanism, and use the pressing mechanism to realize the zoned pressing and fixing of the surface of the ecological blanket 11. The first tire group 4, the second tire group 5 and the ecological blanket 11 together constitute the main body of the ecological slope protection system. The specific method is: bolt the support frame 9 and the pressing plate 16, then place the pressing frame 10, screw the second bolt 19, and the lower end of the second bolt 19 will be pressed on the surface of the pressing frame 10, so as to realize the zone pressing and fixing of the surface of the ecological blanket 11.
[0077] The above construction methods show that:
[0078] The present invention abandons the traditional steel nail fixing method and adopts a second fixing part that can be easily disassembled to achieve the pressure and fixation of the side edge of the ecological blanket 11, which has the advantage of convenient disassembly. In addition, by setting a pressing mechanism, the zoned pressing and fixing of the surface of the ecological blanket 11 is achieved. The pressing mechanism adopts the pressing frame 10 to press down, and the pressing area is large. Multiple pressing areas can be formed on the surface of the ecological blanket 11. The fixation is firm, and the ecological blanket 11 has a good fit with the cushion layer or foundation. It is not easy to be overhead, and the construction quality is guaranteed. In addition, the second fixing part and the pressing mechanism are both detachable, with a simple structure, low cost, easy transportation and assembly, and convenient disassembly and installation. It is beneficial to the local maintenance and replacement of the ecological blanket 11 during the construction process or subsequent use, and provides conditions for the idea of zoning management, which can solve the problems of low construction efficiency and inconvenient local maintenance and replacement caused by the chain process of the ecological blanket 11.
[0079] Embodiment 2:
[0080] Continue to refer to the attached Figure 1 - Figure 8 On the basis of the first embodiment, in order to solve the problem of inconvenient maintenance, the whole system further includes a pouring assembly, which includes a guide rail 6, the guide rail 6 has two groups of slide grooves arranged along the length direction, and each group of second tire groups 5 is connected to a guide rail 6 at the top, and spray plates 7 are slidably connected between adjacent guide rails 6, and wheels 22 are connected on both sides of the spray plates 7, and the wheels 22 can slide along the slide grooves; a plurality of spray heads are provided on the spray plate 7, and the spray plate 7 is provided with a water inlet nozzle 23; the spray plate 7 is also provided with a pull rope 8 for driving the spray plate 7 to move up and down.
[0081] In this embodiment, in order to facilitate the installation of the guide rail 6, an upper positioning plate 18 is further provided, and the upper positioning plate 18 is supported on the top of the top support 17, and the upper positioning plate 18 is fixed by the top support 17. At the same time, the upper positioning plate 18 is also provided with a lower through hole, and a lug plate 20 is fixedly welded to the side wall of the guide rail 6, and the lug plate 20 is also provided with an upper through hole corresponding to the lower through hole, and fastening bolts 21 are inserted in the upper through hole and the lower through hole, so that the guide rail 6 can be fixedly installed.
[0082] This embodiment also proposes a construction method of an ecological slope protection system formed by an ecological blanket and waste tires, which, based on the method of the first embodiment, further includes the following steps:
[0083] S8: Ecological blanket 11 maintenance: The ecological blanket 11 is maintained using a watering assembly.
[0084] The specific construction method is: after the pressing mechanism and the second fixing member are installed, the guide rail 6 is installed, and then the spray plate 7 is installed. After the laying is completed, watering and curing treatment is required. According to the actual weather conditions, curing for 1 to 2 weeks is required to improve the germination and growth effect of the plants. During maintenance, water can be taken on site, such as pumping water from the river. The water pipe is connected to the water inlet 23, and then the pull rope 8 is pulled. The spray plate 7 slides downward under its own weight, and the pull rope 8 is slowly loosened to slowly lower the spray plate 7, thereby achieving uniform irrigation of the paving area. The watering amount can be determined according to actual conditions. The spray plate 7 moves up and down reciprocatingly to achieve multiple irrigations until the required watering amount is reached. After the paving area is watered, the spray plate 7 is pulled to the top of the slope 3, and the pull rope 8 is tied to the first tire to achieve positioning and fixation of the spray plate 7; then the water pipe is removed and connected to the spray plate 7 corresponding to another ecological blanket 11, and the above process is repeated to achieve maintenance of the ecological blanket 11; the above scheme is used to complete the maintenance of all ecological blankets 11.
[0085] Application results:
[0086] The top surface of the second tire group 5 is used as the installation base surface of the guide rail 6. A spray plate 7 is installed on the guide rail 6. The spray plate 7 can slide along the guide rail 6 by its own gravity. Workers only need to pull the pull rope 8 to control the spray plate 7 to move up and down at the top of the slope 3, so as to facilitate the all-round watering and maintenance of the ecological blanket 11 in the laying area, which can effectively solve the problems of uneven watering, time-consuming and labor-intensive maintenance of the ecological blanket 11.
[0087] Although the above describes the specific implementation mode of the invention in conjunction with the drawings, it is not intended to limit the scope of protection of the invention. Based on the technical solution of the present invention, various modifications or variations that can be made by those skilled in the art without creative work are still within the scope of protection of the present invention.
Claims
1. An ecological slope protection system based on an ecological blanket and waste tires, comprising a slope body (1), wherein the slope body (1) has a slope top (3) and a slope foot (2), and a slope surface is formed between the slope top (3) and the slope foot (2); characterized in that: The slope body (1) is provided with a slope protection system, which comprises: A plurality of second tire groups (5) are arranged along the slope surface, each second tire group (5) comprising a plurality of second tires arranged vertically; the second tire groups (5) are arranged at intervals to divide the slope surface, a paving area is formed between two adjacent second tire groups (5), and an ecological blanket (11) is laid in the paving area; the second tire is a semi-buried structure; a cavity serving as a fulcrum is formed between the second tire and the slope surface; The top end of the ecological blanket (11) is fixed to the top of the slope (3), and the bottom end of the ecological blanket (11) is laid to the foot of the slope (2); The two side edges of the ecological blanket (11) are fixed to the slope surface by a plurality of second fixing members arranged at intervals; the second fixing members are connected to the second tires; It also includes a plurality of pressing mechanisms for fixing the ecological blanket (11) in sections, the pressing mechanisms including a support frame (9) detachably connected to a second fixing member, a gap being provided between the support frame (9) and the ecological blanket (11); a rectangular pressing frame (10) is placed on the ecological blanket (11), a plurality of second bolts (19) are threadedly connected to the support frame (9), the bottom ends of the second bolts (19) are positioned to act on the surface of the pressing frame (10), a plurality of pressing areas are formed on the surface of the ecological blanket (11), and the ecological blanket (11) is tightly pressed on the slope surface; It also includes a first tire group (4) arranged transversely along the top of the slope (3), the first tire group (4) consisting of a plurality of first tires arranged vertically, the first tires being of a semi-buried structure; the top of the ecological blanket (11) is fixed to the top of the slope (3) by a plurality of first fixing members arranged at intervals; the first fixing members are connected to the first tires; The first fixing member comprises two anchor rods (401), the rod walls of the anchor rods (401) having threaded sections; the bottom ends of the anchor rods (401) penetrate the first tire and are buried in the slope top (3); the first fixing member further comprises a base (12), the base (12) being fixedly connected to one end of a cross brace (13), the other end of the cross brace (13) being threadedly connected to a first bolt (14) for pressing down and fixing the ecological blanket (11); the top ends of the anchor rods (401) are bolted and fixed to the base (12); The second fixing member comprises a support (17) and a pressure plate (16); the two ends of the pressure plate (16) are pressed against the edge of the ecological blanket (11); the bottom end of the support frame (9) is bolted and fixed to the pressure plate (16); the bottom end of the support (17) is pressed against the surface of the pressure plate (16), and the top end is supported on the second tire to form a counter-support structure.
2. The ecological slope protection system based on ecological blanket and waste tires according to claim 1 is characterized in that: The invention also comprises a watering assembly, wherein the watering assembly comprises a guide rail (6), the guide rail (6) having two groups of slide grooves arranged along the length direction, the top of each group of second tire groups (5) is connected to a guide rail (6), and a spray plate (7) is slidably connected between adjacent guide rails (6), the spray plate (7) is provided with a plurality of spray heads, and the spray plate (7) is provided with a water inlet nozzle (23); the spray plate (7) is also provided with a pull rope (8) for driving the spray plate (7) to move up and down.
3. The ecological slope protection system based on ecological blanket and waste tires according to claim 2 is characterized in that: A pad (15) is provided between the first bolt (14) and the ecological blanket (11).
4. The ecological slope protection system based on ecological blanket and waste tires according to claim 1 is characterized in that: A hardened layer is provided at the slope foot (2).
5. The construction method of the ecological slope protection system formed by the ecological blanket and waste tires is characterized by: The ecological slope protection system based on the ecological blanket and waste tires described in claim 3 is applied, and the steps are as follows: S1: Slope (1) repair and construction layout; S2: installing a first tire at the top of the slope (3) to form a first tire set (4); S3: installing second tires on the slope surface to form a plurality of second tire groups (5) arranged at intervals; and forming a paving area between adjacent second tire groups (5); S4: cutting the ecological blanket (11) according to the size of the laying area, and laying the cut ecological blanket (11) on the laying area; S5: installing a first fixing member, and using the first fixing member to press and fix the top end of the ecological blanket (11); S6: installing a second fixing member, and using the second fixing member to press and fix the side edge of the ecological blanket (11); S7: installing a pressing mechanism, and using the pressing mechanism to press and fix the surface of the ecological blanket (11) in sections, wherein the first tire group (4), the second tire group (5) and the ecological blanket (11) together constitute the main body of the ecological slope protection system; S8: Ecological blanket (11) maintenance: using a watering assembly to maintain the ecological blanket (11).
Citation Information
Patent Citations
Method for conducting slope ecological repairing and slope protecting through waste tire
CN106812142A
Water conservancy ecological slope protection structure and operation method thereof
CN112195861A
Embankment structure reinforced by waste tires