A method for monitoring and analyzing transformer faults in power supply system

By constructing the abnormal fluctuation curve of the current transformer and identifying the fluctuation characteristics, the problems that have not been considered in the existing technology of time synchronization and external environmental factors are solved, and more accurate fault diagnosis and residual magnetic recognition are achieved, improving the accuracy of fault analysis. and system stability.

CN118604713BActive Publication Date: 2024-11-12JIANGSU SUAIER POWER EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411074118.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-07
Publication Date
2024-11-12
Estimated Expiration
2044-08-07

AI Technical Summary

Technical Problem

The prior art fails to fully consider time synchronization and external environmental factors in transformer fault monitoring, resulting in misjudgment and mishandling of fault diagnosis, and lacks the identification and processing of residual magnetic phenomena.

Method used

By constructing an abnormal fluctuation curve of the current transformer, identify the fluctuation characteristics, troubleshoot the origin of the fault, determine the residual magnetic phenomenon, and perform demagnetization operations to determine the origin of the fault and maintenance requirements.

Benefits of technology

It improves the accuracy and time synchronization of fault diagnosis, avoids misjudgment, timely identify and deal with residual magnetic phenomena, reduces the risk of misjudgment of fault analysis, and improves the comprehensiveness and accuracy of fault analysis.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118604713B_ABST
    Figure CN118604713B_ABST
Patent Text Reader

Abstract

The present invention belongs to the technical field of transformer fault monitoring and analysis, and specifically discloses a transformer fault monitoring and analysis method in a power supply system, the method comprising: by analyzing the synchronization status of the specific deviation time point of the monitoring data corresponding to the environmental meteorology and the application load and the deviation time point of the operation data, the misjudgment caused by time dislocation is avoided, and then the fault origin of the abnormal operation of the current transformer corresponding to the environmental level and the application level is identified; based on the complex structural state of the abnormal area of ​​the current transformer, the accuracy parameters of the secondary contour scanning equipment are optimized to locate the key fault area on the transformer; by demagnetizing the current transformer, it is judged whether the fault origin of the abnormal operation of the current transformer is the residual magnetism phenomenon, and then the strength of the residual magnetism phenomenon is identified to judge whether the current transformer is to be maintained, thereby avoiding the misjudgment of the data detection caused by the residual magnetism phenomenon.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of transformer fault monitoring and analysis, and relates to a transformer fault monitoring and analysis method in a power supply system. Background Art

[0002] Instrument transformers play an important role in power supply systems. Their failures may lead to inaccurate voltage and current measurements in the power system, which in turn affects the normal operation of the power system's control and protection functions. Therefore, it is very important to monitor and analyze the faults of the instrument transformers. By monitoring the operating status of the instrument transformers in real time, timely discovering potential faults and taking appropriate measures, the occurrence or expansion of faults can be effectively avoided, and the reliability and stability of the power supply system can be improved.

[0003] In the prior art, there are also some related solutions related to current transformer fault identification, for example, the invention patent application for a current transformer fault diagnosis method with application number 202111467564.2, which collects and analyzes the output waveform signal of the fault state detector to extract the fault waveform parameters; and performs wavelet transform on the metering channel data and protection channel data in the power grid operation data, and then performs singular value detection on the wavelet transformed data, starts the power grid diagnosis program, and diagnoses two types of transformer faults: power grid fault and self-fault.

[0004] Although the above scheme proposes some identification methods for current transformer fault factors, it still has the following limitations: 1. When collecting fault abnormal data, only the deviation between the operating data and the threshold is considered, and whether the specific deviation time point of the fault factor is synchronized with the deviation time point of the operating data is not considered. In the real-time monitoring and early warning system, time synchronization is particularly critical for accurately diagnosing problems, preventing further damage, and quickly restoring the system to normal operating status. If this is not considered, it may lead to misjudgment of the time when the fault occurred, thereby affecting the timeliness of fault warning and processing.

[0005] 2. The analysis is more focused on the operating factors of the power itself, and there is a lack of identification of the influencing factors of the external environment. When analyzing the cause of the fault through the power operation data, only the operating fluctuation of the data is analyzed, and the operating data detection error caused by the residual magnetism of the transformer itself is not considered, which may lead to misjudgment of the cause of the fault. For example, when the data of the transformer is abnormal due to residual magnetism, if only the data fluctuation is analyzed, it may be wrongly attributed to other power operation factors. Summary of the invention

[0006] In view of this, in order to solve the problems raised in the above background technology, a method for monitoring and analyzing transformer faults in a power supply system is now proposed.

[0007] The purpose of the present invention can be achieved through the following technical solutions: The present invention provides a method for monitoring and analyzing transformer faults in a power supply system, step one, constructing an abnormal fluctuation curve: real-time collection of power parameters of the current transformer in the power supply system during operation, and constructing a corresponding circuit operation fluctuation curve of the current transformer.

[0008] Step 2: Identification and analysis of fluctuation characteristics: Extract and analyze the fluctuation characteristics of the current transformer corresponding circuit operation fluctuation curve to determine the abnormal operation of the current transformer.

[0009] Step 3. Troubleshooting of abnormal causes: Extract historical operation data of the power supply system to determine the source of abnormal operation of the current transformer, including environmental penetration, application overload, and equipment failure.

[0010] Step 4: Determine the cause of residual magnetism: Based on the above fault origins are all unreasonable, demagnetize the current transformer to determine whether the fault origin of the abnormal operation of the current transformer is residual magnetism.

[0011] Step 5: Equipment maintenance identification: Based on the fact that the fault source of abnormal operation of the current transformer is residual magnetism, determine whether to perform equipment maintenance on the current transformer.

[0012] Compared with the prior art, the beneficial effects of the present invention are as follows: (1) By analyzing the synchronization status of the specific deviation time points of the monitoring data corresponding to the environmental meteorological factors and the application load factors and the deviation time points of the operating data, the present invention can more accurately determine the exact time when the fault occurs, thereby avoiding the misjudgment caused by time dislocation in the traditional method.

[0013] (2) The present invention identifies the fault origins of abnormal operation of current transformers at the environmental level and application level by comparing the co-frequency between the meteorological fluctuation curve and the circuit operation fluctuation curve, and the co-frequency between the load fluctuation curve and the circuit operation fluctuation curve, thereby avoiding the limitation of starting only from the circuit operation data and improving the comprehensiveness of fault origin identification.

[0014] (3) The present invention optimizes the accuracy parameters of the secondary contour scanning of the current transformer by identifying the structural complexity of the abnormal area on the current transformer, thereby determining whether there is a critical fault area in the transformer, thereby greatly reducing the risk of defect omission caused by insufficient scanning accuracy.

[0015] (4) The present invention performs a demagnetization operation on the current transformer to determine whether the fault source of the abnormal operation of the current transformer is the residual magnetism phenomenon, and then identifies the strength of the residual magnetism phenomenon to determine whether the current transformer should be maintained. The residual magnetism phenomenon can be identified and processed in time, which can prevent potential faults caused by residual magnetism and avoid misjudgment of data detection caused by the residual magnetism phenomenon. It can more accurately analyze the fault cause of the abnormal operation of the current transformer, thereby improving the accuracy of fault analysis. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for describing the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0017] Figure 1 It is a schematic diagram of the process of the present invention. DETAILED DESCRIPTION

[0018] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0019] See also Figure 1 As shown, the present invention provides a method for monitoring and analyzing transformer faults in a power supply system, the method comprising: step one, constructing an abnormal fluctuation curve: real-time collecting power parameters of the current transformer in the power supply system during operation, including primary side current, secondary side current, and harmonic content, and constructing a corresponding circuit operation fluctuation curve of the current transformer.

[0020] In a preferred embodiment, the content of constructing the circuit operation fluctuation curve corresponding to the current transformer includes: obtaining the primary side current and the secondary side current of the current transformer at each time point within a set unit time limit through a current detector, and comparing to obtain the transformation ratio of the current transformer at each time point within the set unit time limit.

[0021] Connect the current signal on the secondary side of the current transformer to the harmonic measuring instrument, select appropriate measurement parameters on the instrument, such as current range, sampling rate, etc., measure and record the harmonic content at each time point within the set unit time limit.

[0022] The transformation ratio and harmonic content of the current transformer at each time point within the set unit time limit are normalized and integrated into the corresponding circuit operation fluctuation curve of the current transformer.

[0023] Specifically, the normalization processing includes: comparing the transformation ratio of the current transformer at each time point within the set unit time limit with the preset standard transformation ratio value of the current transformer to obtain the transformation ratio excess rate at each time point, and comparing the harmonic content of the current transformer at each time point within the set unit time limit with the preset harmonic content conventional value of the current transformer to obtain the harmonic content excess rate at each time point, and comparing and screening out the maximum excess rate of the current transformer at each time point within the set unit time limit, which is recorded as the fluctuation value at each time point, and then constructing the current transformer corresponding circuit operation fluctuation curve with the time point as the horizontal coordinate and the fluctuation value as the vertical coordinate.

[0024] Exemplarily, if the transformation ratio excess rate at a certain time point is greater than the harmonic content excess rate, the transformation ratio excess rate at the time point is recorded as the fluctuation value at the corresponding time point.

[0025] Step 2: Identification and analysis of fluctuation characteristics: Extract and analyze the fluctuation characteristics of the abnormal power supply fluctuation curve corresponding to the current transformer to determine the abnormal operation of the current transformer.

[0026] In a preferred embodiment, the content of determining the abnormal operation of the current transformer includes: extracting various fluctuation characteristics in the fluctuation curve of the circuit operation corresponding to the current transformer , including the highest fluctuation value among all peak points, non-periodic change amplitude, waveform curve area, and determine the abnormal operation evaluation coefficient of the current transformer ,in For the Each fluctuation feature corresponds to a preset control indicator. is the number of the fluctuation feature, , e is a natural constant.

[0027] Specifically, the non-periodic variation amplitude is obtained by: obtaining the duration of the fluctuation curve segment corresponding to each peak point and its adjacent peak point in the circuit operation fluctuation curve corresponding to the current transformer and slope Based on this, the non-periodic variation amplitude of the current transformer corresponding circuit operation fluctuation curve is calculated ,in , Respectively The duration and slope of the fluctuation curve segment corresponding to each peak point and its adjacent peak point, They are respectively the set basic deviation duration and the set basic deviation slope between the fluctuation curve segments corresponding to two adjacent peak points. is the number of fluctuation characteristics.

[0028] The abnormal operation evaluation coefficient of the current transformer is compared with the preset rated value of the abnormal operation evaluation coefficient to identify whether the abnormal operation evaluation coefficient of the current transformer exceeds the preset rated value. When it exceeds the preset rated value, it is determined that the current transformer has an abnormal operation.

[0029] The present invention collects and analyzes abnormal fluctuations of power parameters during operation of current transformers in the power supply system in real time, discovers abnormalities of current transformers in time, and can take measures before the fault expands to avoid power outages caused by transformer faults, thereby improving the stability and reliability of the power supply system.

[0030] Step 3. Troubleshooting of abnormal causes: Extract historical operation data of the power supply system to determine the source of abnormal operation of the current transformer, including environmental penetration, application overload, and equipment failure.

[0031] In a preferred embodiment, the historical operation data of the power supply system includes environmental record data and circuit current data.

[0032] The environmental record data includes various meteorological parameters, such as air humidity, temperature, air pressure, and wind speed.

[0033] The circuit flow data includes various load parameters, such as load flow, input current and voltage of the circuit.

[0034] In a further preferred embodiment, the method of determining the fault origin of abnormal operation of the current transformer includes: extracting various meteorological parameters of the area where the current transformer is located at each time point within a set unit time limit from environmental record data, using the preset suitable values ​​of the corresponding meteorological parameters as reference indicators, calculating the meteorological fluctuation values ​​at each time point within the set unit time limit, and then drawing a meteorological fluctuation curve with the time point as the horizontal coordinate and the meteorological fluctuation value as the vertical coordinate, comparing it with the circuit operation fluctuation curve corresponding to the current transformer, obtaining the intersection area of ​​the meteorological fluctuation curve and the circuit operation fluctuation curve, obtaining the ratio between the meteorological fluctuation curve and the preset basic reference value of the intersection area, and then recording the inverse value as the same frequency of the meteorological fluctuation curve and the circuit operation fluctuation curve.

[0035] Identify whether the frequency of the meteorological fluctuation curve and the circuit operation fluctuation curve exceeds the preset limit value. If it exceeds the preset limit value, the fault source of the abnormal operation of the current transformer is identified as environmental penetration.

[0036] The load parameters of the current transformer at each time point within the set unit time limit are extracted from the circuit current data, and the preset rated value of the corresponding load parameter is used as a reference indicator. The load fluctuation value at each time point within the set unit time limit is calculated, and then the load fluctuation curve is drawn with the time point as the horizontal coordinate and the load fluctuation value as the vertical coordinate. The load fluctuation curve is compared with the corresponding circuit operation fluctuation curve of the current transformer, and then the co-frequency of the load fluctuation curve and the circuit operation fluctuation curve is analyzed in the same way as above, and it is identified whether the co-frequency of the load fluctuation curve and the circuit operation fluctuation curve exceeds the preset limit value. If it exceeds the preset limit value, it is identified that the fault source of the abnormal operation of the current transformer is the application overload.

[0037] The present invention identifies the fault origins of abnormal operation of current transformers at the environmental level and application level by comparing the co-frequency of meteorological fluctuation curves and circuit operation fluctuation curves, as well as the co-frequency of load fluctuation curves and circuit operation fluctuation curves, thereby avoiding the limitation of starting from circuit operation data only and improving the comprehensiveness of fault origin identification.

[0038] Step 4: Determine the cause of residual magnetism: Based on the unreasonable fault origins mentioned above, demagnetize the current transformer, compare the abnormal operation of the current transformer before and after the demagnetization operation, and determine whether the fault origin of the abnormal operation of the current transformer is residual magnetism.

[0039] In a preferred embodiment, the method for determining the fault origin of abnormal operation of the current transformer further includes: scanning and detecting the current transformer to obtain the precision scanning structure profile of the current transformer, obtaining the preset healthy structure profile of the current transformer, overlapping and comparing it with the precision scanning structure profile, extracting each non-overlapping area, namely each damaged area on the current transformer equipment structure, and identifying each damage feature of each damaged area on the current transformer equipment structure based on the contour recognition technology. , various damage characteristics include corrosion degree, fracture amplitude, etc., and the comprehensive failure impact index of the damaged area is analyzed ,in The first structure of the current transformer equipment The damaged area Each damage feature corresponds to a preset reference value. is the number of the damaged area, , is the number of the damage feature, , the comprehensive fault impact index of the damaged area is compared with the preset comprehensive fault impact index threshold. If it exceeds the comprehensive fault impact index threshold, it is determined that there is comprehensive cumulative damage.

[0040] Each damage feature of each damage area is compared with the preset safety critical value of the corresponding damage feature of the corresponding damage area. If a damage feature of a damage area is greater than the preset safety critical value of the corresponding damage feature of the corresponding damage area, the damage feature of the damage area is recorded as a key damage feature, and then the damage area is recorded as a key damage area.

[0041] When there is a critical damage area or a comprehensive cumulative damage, the fault origin of the abnormal operation of the current transformer is recorded as an equipment fault, and the fault point is extracted and fed back, which includes the critical damage area and the comprehensive cumulative damage.

[0042] In a further preferred embodiment, the specific steps of scanning and detecting the current transformer are: performing a preliminary rotation scan on the current transformer at each designated rotation position point by an X-ray scanning device, combining and constructing its image structure contour, matching it with a preset healthy structure contour of the current transformer, and identifying the positions of various abnormal areas of the image structure contour.

[0043] Based on the contour recognition technology, the structural complexity of the positions of various abnormal areas in the preset healthy structural contour of the current transformer is identified, the maximum structural complexity is screened out, and it is matched with the preset structural complexity range corresponding to each scanning accuracy parameter to determine the secondary scanning accuracy parameters. The scanning accuracy parameters include image resolution, radiation dose, etc., and then the current transformer is subjected to secondary scanning detection to obtain the precision scanning structural contour of the current transformer.

[0044] In a further preferred implementation, the process of performing the demagnetization operation on the current transformer is as follows: extracting a planned maintenance window time period of a circuit corresponding to the power supply system.

[0045] Disconnect all primary and secondary circuits connected to the current transformers.

[0046] Obtain the demagnetization requirements of the current transformer, including the specifications of the current transformer and the site conditions, and analyze the demagnetization requirements of the transformer, including complex requirements and simple requirements. If the demagnetization requirements of the transformer are complex requirements, select the closed demagnetization mode.

[0047] If the demagnetization requirement of the transformer is simple, select the open circuit demagnetization mode.

[0048] Specifically, the planned maintenance window period refers to a specific period of time pre-set by the power supply system during which necessary maintenance, inspection, repair or upgrade of the system is carried out. It is usually selected during the period when the grid load is low and the impact on users is minimal, such as late at night to early morning, to reduce interference with residents' lives and commercial operations.

[0049] The specifications of the transformer include rated current, rated voltage, number of winding turns, etc. Transformers of different specifications will affect parameters such as current, voltage and duration required for demagnetization; the site conditions include power supply requirements and the complexity of wiring layout.

[0050] The analysis of the demagnetization requirements of the transformer specifically includes the following two types: 1. Compare the rated data in the current transformer specifications with the corresponding preset conventional rated data. If a certain rated data in the current transformer specifications exceeds the corresponding preset conventional rated data, then the demagnetization requirement of the transformer is determined to be a complex requirement. If the rated data in the current transformer specifications do not exceed the corresponding preset conventional rated data, then the demagnetization requirement of the transformer is determined to be a simple requirement.

[0051] 2. Compare the power supply demand and wiring complexity of the current transformer's on-site conditions with the preset corresponding reference indicators. If one or both of the power supply demand and wiring complexity exceed the preset corresponding reference indicators, the demagnetization requirement of the transformer is determined to be a complex requirement, otherwise the demagnetization requirement of the transformer is determined to be a simple requirement.

[0052] Since the open circuit demagnetization method is relatively simple to operate, it is suitable for transformers with not particularly strong residual magnetism, while the closed circuit demagnetization method is suitable for transformers with strong residual magnetism or that require more thorough demagnetization. Therefore, if the residual magnetism of the transformer is not determined and the transformer application scenario is relatively simple, the open circuit demagnetization method should be used for demagnetization operation and analysis first.

[0053] According to the selected demagnetization mode, perform the demagnetization operation.

[0054] Exemplarily, the specific contents of the demagnetization operation corresponding to the open circuit demagnetization mode are as follows: use a suitable power supply device to provide industrial frequency AC current, increase the current according to the prescribed procedure, initially starting from zero and gradually increasing to 10% of the rated current; uniformly and slowly reduce the current to zero, repeat 2 to 3 times, and the current applied each time decreases gradually; if at 10% of the rated current, the voltage peak induced across the open circuit winding exceeds 75% of the specified value of the turn-to-turn insulation test, reduce the applied current value and then perform demagnetization until the voltage peak no longer exceeds 75% of the specified value.

[0055] On the one hand, the present invention can more accurately determine the exact time when the fault occurs by analyzing the synchronization status of the specific deviation time points of the monitoring data corresponding to the environmental meteorological factors and the application load factors and the deviation time points of the operating data, thereby avoiding the misjudgment caused by time dislocation in the traditional method. This precise time synchronization helps operation and maintenance personnel to more accurately identify the type of fault and locate the source of the fault, providing strong support for subsequent fault handling. On the other hand, the present invention optimizes the accuracy parameters of the secondary contour scanning of the current transformer by identifying the complex structural state of the abnormal area on the current transformer, and determines whether there is a critical fault area in the transformer, thereby greatly reducing the risk of defect omission caused by insufficient scanning accuracy.

[0056] Step 5: Equipment maintenance identification: Based on the fact that the fault source of abnormal operation of the current transformer is residual magnetism, determine whether to perform equipment maintenance on the current transformer.

[0057] In a preferred embodiment, the method for determining whether the fault origin of abnormal operation of the current transformer is residual magnetism is as follows: according to the construction method of the circuit operation fluctuation curve corresponding to the current transformer, the circuit operation fluctuation curve corresponding to the demagnetization operation of the current transformer is constructed in the same way;

[0058] According to the method for obtaining each fluctuation feature in the circuit operation fluctuation curve corresponding to the current transformer, similarly obtain each fluctuation feature in the circuit operation fluctuation curve corresponding to the current transformer after the demagnetization operation, and then according to the method for determining the abnormal operation evaluation coefficient of the current transformer, similarly determine the abnormal operation evaluation coefficient of the current transformer after the demagnetization operation, record it as the current transformer verification operation coefficient, compare it with the abnormal operation evaluation coefficient of the current transformer identified before the demagnetization operation, obtain the difference, and record it as the verification effect evaluation index of the current transformer.

[0059] If the verification effect evaluation index exceeds the set threshold standard, the fault origin of the abnormal operation of the current transformer is recorded as residual magnetism.

[0060] In a further preferred embodiment, the method for determining whether to perform equipment maintenance on the current transformer is: comparing the abnormal operation evaluation coefficient of the current transformer after the demagnetization operation with the preset rated value safety threshold of the abnormal operation evaluation coefficient; if the abnormal operation evaluation coefficient of the current transformer after the demagnetization operation exceeds the preset rated value safety threshold of the abnormal operation evaluation coefficient, it is determined that the current transformer has an abnormal operation after the demagnetization operation, and then the demagnetization mode selected by the current transformer is extracted, and based on the abnormal operation evaluation coefficient of the current transformer after the demagnetization operation, the abnormal degree of the current transformer residual magnetism phenomenon is identified, including the severity and the mildness.

[0061] Specifically, the content of identifying the abnormal degree of the residual magnetism phenomenon of the current transformer is: matching the abnormal operation evaluation coefficient after the demagnetization operation of the current transformer with the set abnormal operation evaluation coefficient range of each abnormal degree to obtain the abnormal degree of the residual magnetism phenomenon of the current transformer.

[0062] If the demagnetization mode selected for the current transformer is the open circuit demagnetization mode and the abnormal degree of the residual magnetism phenomenon of the current transformer is mild, a secondary demagnetization operation is performed on the current transformer in the closed circuit demagnetization mode.

[0063] If the demagnetization mode selected for the current transformer is the open circuit demagnetization mode and the abnormality level of the residual magnetism phenomenon of the current transformer is severe, equipment maintenance is performed on the current transformer.

[0064] If the demagnetization mode selected for the current transformer is the closed demagnetization mode, perform equipment maintenance on the current transformer.

[0065] The present invention performs a demagnetization operation on the current transformer to determine whether the fault source of the abnormal operation of the current transformer is the residual magnetism phenomenon, and then identifies the strength of the residual magnetism phenomenon to determine whether to perform equipment maintenance on the current transformer. The residual magnetism phenomenon is identified and processed in time, potential faults caused by the residual magnetism can be prevented, and misjudgment of data detection caused by the residual magnetism phenomenon can be avoided. The fault cause of the abnormal operation of the current transformer can be analyzed more accurately, thereby improving the accuracy of fault analysis.

[0066] The above contents are merely examples and explanations of the concept of the present invention. The technicians in this technical field may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the concept of the invention or exceed the scope defined by the present invention, they should all fall within the protection scope of the present invention.

Claims

1. A method for monitoring and analyzing transformer faults in a power supply system, characterized in that: The method comprises the following steps: Step 1: Constructing the circuit operation fluctuation curve: Real-time collection of power parameters of the current transformer in the power supply system during operation, and constructing the circuit operation fluctuation curve corresponding to the current transformer; Step 2: Identification and analysis of fluctuation characteristics: extract and analyze the fluctuation characteristics of the current transformer corresponding circuit operation fluctuation curve to determine the abnormal operation of the current transformer; Step 3: Troubleshooting of abnormal causes: Extract historical operation data of the power supply system to determine the source of abnormal operation of the current transformer, including environmental penetration, application overload, and equipment failure; Step 4: Determine the cause of residual magnetism: Based on the above fault origins being unreasonable, demagnetize the current transformer to determine whether the fault origin of the abnormal operation of the current transformer is residual magnetism; Step 5: Equipment maintenance identification: Based on the fact that the fault of abnormal operation of the current transformer originates from the residual magnetism phenomenon, determine whether to perform equipment maintenance on the current transformer; The historical operation data of the power supply system includes environmental record data and circuit current data; The environmental record data includes various meteorological parameters, specifically air humidity, temperature, air pressure, and wind speed; The circuit flow data includes various load parameters, specifically load flow, circuit input current and voltage; The method of determining the fault origin of abnormal operation of the current transformer comprises: Extract the meteorological parameters of the area where the current transformer is located at each time point within the set unit time limit from the environmental record data, use the preset suitable value of the corresponding meteorological parameter as the reference index, calculate the meteorological fluctuation value at each time point within the set unit time limit, draw the meteorological fluctuation curve, compare it with the corresponding circuit operation fluctuation curve of the current transformer, and analyze the same frequency of the meteorological fluctuation curve and the circuit operation fluctuation curve; Identify whether the frequency of the meteorological fluctuation curve and the circuit operation fluctuation curve exceeds the preset limit value. If it exceeds the preset limit value, the fault source of the abnormal operation of the current transformer is identified as environmental penetration; Extract various load parameters of the current transformer at various time points within a set unit time limit from the circuit current data, draw a load fluctuation curve, analyze the frequency co-occurrence between the load fluctuation curve and the circuit operation fluctuation curve, and identify whether the frequency co-occurrence between the load fluctuation curve and the circuit operation fluctuation curve exceeds a preset limit value. If it exceeds the preset limit value, identify that the fault source of the abnormal operation of the current transformer is application overload; The determining of the fault origin of abnormal operation of the current transformer also includes: scanning and detecting the current transformer, extracting each damaged area on the current transformer equipment structure and each damage feature, analyzing the comprehensive fault impact index of the damaged area, and determining whether there is comprehensive cumulative damage based on the index; Extract the key damage features corresponding to each damage area, and determine whether there is a key damage area based on this; When there is a critical damage area or comprehensive cumulative damage, the fault origin of abnormal operation of the current transformer is recorded as an equipment fault.

2. A method for monitoring and analyzing transformer faults in a power supply system according to claim 1, characterized in that: The content of constructing the circuit operation fluctuation curve corresponding to the current transformer includes: obtaining the primary side current and the secondary side current of the current transformer at each time point within the set unit time limit through a current detector, and comparing to obtain the transformation ratio of the current transformer at each time point within the set unit time limit; Connect the current signal on the secondary side of the current transformer to the harmonic measuring instrument, select appropriate measurement parameters on the instrument, measure and record the harmonic content at each time point within the set unit time limit; The transformation ratio and harmonic content of the current transformer at each time point within the set unit time limit are normalized and integrated into the corresponding circuit operation fluctuation curve of the current transformer.

3. The method for monitoring and analyzing transformer faults in a power supply system according to claim 1, characterized in that: The content of determining the abnormal operation of the current transformer includes: Extract the fluctuation characteristics in the fluctuation curve of the current transformer corresponding to the circuit operation, including the highest fluctuation value among all peak points, the amplitude of non-periodic changes, and the area of ​​the waveform curve, and determine the abnormal operation evaluation coefficient of the current transformer; Identify whether the abnormal operation evaluation coefficient of the current transformer exceeds the preset rated value. When it exceeds the preset rated value, it is determined that the current transformer has abnormal operation.

4. The method for monitoring and analyzing transformer faults in a power supply system according to claim 1, characterized in that: The specific steps of scanning and detecting the current transformer are: Perform a preliminary rotation scan of the current transformer at designated rotation position points through an X-ray scanning device, construct its image structure contour by combination, match it with the preset healthy structure contour of the current transformer, and identify the location of each abnormal area of ​​the image structure contour; Based on the contour recognition technology, the structural complexity of the positions of the abnormal areas in the preset healthy structural contour of the current transformer is identified, the maximum structural complexity is screened out, the secondary scanning accuracy parameters are optimized, and then the current transformer is subjected to secondary scanning detection.

5. The method for monitoring and analyzing transformer faults in a power supply system according to claim 1, characterized in that: The process of demagnetizing the current transformer is as follows: Extract the planned maintenance window time period of the corresponding circuit of the power supply system; Disconnect all primary and secondary circuits connected to the current transformer; Obtain the demagnetization requirements of the current transformer, including the specifications of the current transformer and the site conditions, and analyze the demagnetization requirements of the transformer. If the demagnetization requirements of the transformer are complex, select the closed demagnetization mode; If the demagnetization requirement of the transformer is simple, select the open circuit demagnetization mode; According to the selected demagnetization mode, perform the demagnetization operation.

6. A method for monitoring and analyzing transformer faults in a power supply system according to claim 3, characterized in that: The method for determining whether the fault source of abnormal operation of the current transformer is residual magnetism is as follows: According to the construction method of the circuit operation fluctuation curve corresponding to the current transformer, the circuit operation fluctuation curve corresponding to the current transformer after the demagnetization operation is constructed in the same way; According to the method for obtaining each fluctuation feature in the circuit operation fluctuation curve corresponding to the current transformer, similarly obtain each fluctuation feature in the circuit operation fluctuation curve corresponding to the current transformer after the demagnetization operation, and then according to the method for determining the abnormal operation evaluation coefficient of the current transformer, similarly determine the abnormal operation evaluation coefficient of the current transformer after the demagnetization operation, record it as the current transformer verification operation coefficient, compare it with the abnormal operation evaluation coefficient of the current transformer identified before the demagnetization operation, obtain the difference, and record it as the verification effect evaluation index of the current transformer; If the verification effect evaluation index exceeds the set threshold standard, the fault origin of the abnormal operation of the current transformer is recorded as residual magnetism.

7. A method for monitoring and analyzing transformer faults in a power supply system according to claim 6, characterized in that: The method for judging whether to perform equipment maintenance on the current transformer is as follows: determining whether the current transformer has abnormal operation after the demagnetization operation, and if so, extracting the demagnetization mode selected by the current transformer, and based on the abnormal operation evaluation coefficient after the demagnetization operation of the current transformer, identifying the abnormal degree of the residual magnetism phenomenon of the current transformer, including the severity and the mildness; If the demagnetization mode selected for the current transformer is the open circuit demagnetization mode and the abnormality of the residual magnetism of the current transformer is mild, the current transformer is subjected to secondary demagnetization operation according to the closed circuit demagnetization mode; If the demagnetization mode selected for the current transformer is the open circuit demagnetization mode and the abnormality level of the residual magnetism phenomenon of the current transformer is severe, the current transformer is to be maintained; If the demagnetization mode selected for the current transformer is the closed demagnetization mode, perform equipment maintenance on the current transformer.