Large volume concrete product casting equipment and method

By using fixed and swing mechanisms in large-scale concrete precast wall column pouring equipment, the problem of cement slurry and aggregate separation and pouring pipe swinging during vertical concrete pouring is solved, achieving uniform distribution of concrete and protection of formwork, improving improve the quality and structural strength of concrete.

CN118617589BActive Publication Date: 2024-10-11ANHUI WATER CONSERVANCY DEV CO LTD
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202411110190.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-14
Publication Date
2024-10-11
Estimated Expiration
2044-08-14

AI Technical Summary

Technical Problem

During the vertical pouring process of large-scale prefabricated concrete wall columns, the cement slurry and aggregates are prone to separate when the concrete falls freely from a high place, affecting the quality and compressive strength of the concrete; unfixed pouring pipes cause swings, affecting the uniform distribution of concrete. performance and service life of the formwork.

Method used

A large-volume concrete product pouring equipment is designed, including a support base with a pipe hole and a fixing mechanism. The internal support mechanism and swing mechanism realize step-by-step pouring from bottom to top to ensure the fixation of the pouring pipe and the uniform distribution of concrete. Avoid concrete segregation and formwork damage during pouring.

Benefits of technology

Through the cooperation of the fixed mechanism and the swing mechanism, the uniform distribution of concrete is ensured, the overall homogeneity and compactness of the concrete are improved, the deformation and service life problems of the formwork are avoided, and the accuracy and safety of the pouring process are ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118617589B_ABST
    Figure CN118617589B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of concrete pouring, and specifically to a large-volume concrete product pouring device and method, including a support seat with a cavity inside, a through-tube hole and a pouring pipe located in the through-tube hole and used for pouring concrete, and a fixing mechanism for positioning and fixing the support seat on a template. The operation mode of pouring from bottom to top is adopted in the template to ensure uniform distribution of coarse and fine aggregates and improve the overall homogeneity of concrete, and the pouring pipe mouth and the vibrating rod are swung back and forth at a uniform speed to ensure that the concrete is evenly distributed in the template, and vibrate layer by layer to ensure that each layer of concrete can be fully vibrated, making the concrete more compact, and by ensuring the fixation of the pouring position, the pouring pipe is prevented from directly hitting the template, and the concrete is prevented from being poured too high at one time, resulting in excessive pressure of the concrete's own weight, thereby ensuring the integrity and service life of the template.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of concrete pouring, and in particular to a large-volume concrete product pouring device and method. Background Art

[0002] Large precast concrete wall columns are a type of large-volume precast concrete product with the advantages of high strength, good durability, controllable quality, and rapid on-site installation. They are widely used in infrastructure, public facilities, civil buildings, and industrial buildings. In order to ensure that large precast concrete wall columns have a better stress state during actual use, they need to be prepared by vertical casting. During the vertical casting process, casting equipment is required to cast from bottom to top in the formwork.

[0003] At present, there are the following disadvantages in the vertical pouring of large prefabricated concrete wall columns: 1. When the large prefabricated concrete wall columns are vertically poured, the pouring pipe is usually placed directly above the prepared formwork, and then the concrete is directly poured into the formwork by gravity. When the concrete falls freely from a height, the cement slurry and the aggregate will separate, which will affect the quality and compressive strength of the concrete; 2. In the process of pouring large prefabricated concrete wall columns, the pipe mouth of the pouring pipe is not fixed, which makes the pipe easily shift or swing during the pouring process, resulting in the inability to pour the concrete to the specified position, resulting in uneven distribution of the concrete in the formwork, affecting the structural strength and stability of the large prefabricated concrete wall columns, and the pipe mouth will directly hit the formwork, which is easy to cause the formwork to deform, shift or even break, thereby affecting the service life and construction quality of the formwork. Summary of the invention

[0004] In order to solve the above technical problems, the present invention provides a large-volume concrete product casting equipment and method, which are achieved by the following specific technical means: a large-volume concrete product casting equipment, including a support seat with a cavity inside, the support seat is provided with a through pipe hole penetrating the upper and lower end surfaces thereof and a casting pipe located in the through pipe hole and used for casting concrete, the support seat is provided with a fixing mechanism for positioning and fixing the support seat on the template; the fixing mechanism includes a fixing part arranged on the support seat and used for internal support, pressing and fixing adjacent threaded columns in the template, and the fixing part is provided with a transmission part for providing power to the fixing part.

[0005] The support seat is provided with an internal support mechanism for driving the pouring pipe to pour step by step from bottom to top in the template; the internal support mechanism includes a lifting part arranged on the support seat, and the lifting part is provided with an internal support part for fixing the lifting part in the template and a driving part for providing power to the internal support part.

[0006] The lifting part is provided with a swing mechanism for fixing the vibrating rod and the pouring pipe; the swing mechanism includes a swing part provided on the lifting part and used for evenly swinging the vibrating rod and the pouring pipe, and a synchronization part providing synchronization power for the swing part; the swing part is provided with a vibration part for transmitting vibration during the vibration of the vibrating rod to pour the pouring pipe.

[0007] As a preferred technical solution of the present invention, the fixed part includes a first slideway, a first slider, an arc-shaped support plate and a bidirectional screw. The lower end surface of the support seat is penetrated by a left-right symmetrical first slideway, and the first slideways are slidably installed with front-and-back symmetrical first sliders. The ends of the front-and-back symmetrical first sliders on the same first slideway that are away from each other are fixedly installed with an arc-shaped support plate. A bidirectional screw is installed in the support seat through a bearing and is located above the first slider and is threadedly connected to the corresponding front-and-back symmetrical first slider.

[0008] As a preferred technical solution of the present invention, the transmission part includes a first belt and a first motor, the bidirectional screws are fixedly sleeved with a first pulley, the first pulleys are connected by a first belt transmission, and a first motor with an output end fixedly connected to one of the bidirectional screws is fixedly installed on the support seat.

[0009] As a preferred technical solution of the present invention, the lifting part includes a sling, an equipment support block, a first cavity, a second cavity and a through hole. The four corners of the upper end surface of the support seat are all slidably penetrated by slings, and the lower ends of the slings are fixedly installed with an equipment support block located directly below the support seat. The equipment support block is provided with a first cavity and a second cavity located directly below the first cavity, and the equipment support block is penetrated by a through hole corresponding to the through pipe hole.

[0010] As a preferred technical solution of the present invention, the internal support part includes a bearing seat, a screw sleeve, a screw rod, an internal support plate, a support slide cylinder and a sliding rod. The upper end surface of the first cavity is fixedly installed with a bearing seat located at its four corners. The bearing seat is penetrated by a screw sleeve that passes through the corresponding corner of the support seat. The screw sleeve is threadedly connected with a screw rod, and the ends of the screw rods that are away from each other are fixedly installed with an internal support plate. A support slide cylinder located below the screw sleeve is fixedly installed in the first cavity, and a sliding rod fixedly connected to the corresponding inner support plate is slidably installed in the support slide cylinder.

[0011] As a preferred technical solution of the present invention, the driving part includes a gear ring and a second motor, the ends of the screw sleeves close to each other are fixedly sleeved with a first bevel gear, the upper end surface inside the first cavity is rotatably mounted with a gear ring through a bearing, the second motor is fixedly mounted in the first cavity, the output end of the second motor is fixedly sleeved with a first gear meshing with the gear ring, and the lower end surface of the gear ring is fixedly mounted with a bevel gear ring meshing with multiple first bevel gears at the same time.

[0012] As a preferred technical solution of the present invention, the swinging part includes a supporting ball, a rocker rod, an axle rod, a turntable and a swinging plate. The lower end surface of the second cavity is penetrated by a supporting ball located below the corresponding bearing seat and movably installed. The supporting ball is fixedly penetrated by a rocker rod located at the center thereof. The upper end surface of the second cavity is installed with an axle rod located directly above the corresponding supporting ball through a bearing. The axle rod is fixedly sleeved with a turntable. The side of the lower end surface of the turntable deviating from the center of the circle is ball-connected with the corresponding rocker rod, and the lower end of the rocker rod is jointly ball-connected with the swinging plate.

[0013] As a preferred technical solution of the present invention, the synchronous part includes a second pulley, a second gear and a third motor, the shafts are all fixedly sleeved with a second pulley, the second pulleys are connected by a second belt transmission, one of the shafts is fixedly sleeved with a second gear, the third motor is fixedly installed in the second cavity, and the output end of the third motor is fixedly sleeved with a third gear meshing with the second gear.

[0014] As a preferred technical solution of the present invention, the vibration part includes a second slide, a second slider, bolts and a fixed pipe mouth. The fixed pipe mouth is fixedly installed at the center of the lower end surface of the swinging plate. The lower end of the casting pipe passes through the through hole and is fixedly connected to the fixed pipe mouth. The lower end surface of the swinging plate is provided with a second slide that is symmetrical about the fixed pipe mouth. The swinging plate is provided with a placement hole located at the center of the second slide and used to pass the vibrating rod. The second sliders that are symmetrical front and back and used to clamp the vibrating rod are slidably installed in the second slide. The two second sliders on the front side are threadedly connected with bolts that are symmetrical left and right. The two second sliders on the rear side are provided with screw holes corresponding to the corresponding bolts.

[0015] As a preferred technical solution of the present invention, the present invention also provides a method for casting large-volume concrete products, which is completed in cooperation with the above-mentioned large-volume concrete product casting equipment, and specifically includes the following steps: S1: Preparation work: Install the formwork according to the design requirements, and tie the steel bars according to the design drawings, and determine the concrete mix ratio according to the design requirements and construction environment conditions.

[0016] S2: Fixing device: Move the support base to the upper end of the template, and fix the support base to the upper end of the template through the inner support pressure of the fixing mechanism.

[0017] S3: Adjust the height: adjust the height of the casting pipe in the formwork through the internal support mechanism, and fix the internal support mechanism in the formwork after reaching the appropriate height.

[0018] S4: pouring: the vibrating rod and the pouring pipe are evenly swung by the swing mechanism, and the concrete is passed into the pouring pipe for pouring, while the vibrating rod vibrates the poured concrete.

[0019] S5: Step-by-step pouring: The inner support mechanism and the swing mechanism are used to perform step-by-step pouring from bottom to top in the formwork.

[0020] S6: Subsequent operations: After pouring, cover with plastic film and sprinkle water regularly for maintenance, and demould according to the development of concrete strength, and then check the quality of the surface of large concrete precast wall columns.

[0021] Compared with the prior art, the present invention has the following beneficial effects: 1. The large-volume concrete product casting equipment and method, through the coordinated use of the fixed mechanism, the internal support mechanism and the swing mechanism, adopts an operation mode of step-by-step pouring from bottom to top in the template, so as to avoid the segregation of concrete during the free fall process, ensure the uniform distribution of coarse and fine aggregates, improve the overall homogeneity of concrete, and ensure that the concrete is evenly distributed in the template by the uniform reciprocating swing of the casting pipe mouth and the vibrating rod, and at the same time, vibrate layer by layer to ensure that each layer of concrete can be fully vibrated, making the concrete more compact, and by ensuring the fixation of the casting position, it is avoided that the casting pipe directly hits the template, and it is prevented that the concrete is poured too high at one time, resulting in excessive self-weight pressure of the concrete and then causing deformation or rupture of the template, thereby ensuring the integrity and service life of the template.

[0022] 2. The large-volume concrete product casting equipment and method can swing the casting nozzle and the vibrating rod back and forth at a uniform speed at the same time by setting a swing mechanism, so that the concrete can be evenly distributed to every corner in the template, avoiding the problem of local over-pouring or insufficient pouring of concrete, thereby improving the uniformity of the large-scale concrete prefabricated wall column structure, and the swing of the vibrating rod can uniformly vibrate the poured concrete, reduce the generation of bubbles and pores, so as to improve the density and strength of the concrete, and during the vibration of the vibrating rod, its vibration will be transmitted to the casting nozzle, thereby preventing the segregation of concrete in the pipeline, ensuring the homogeneity of the concrete during the casting process.

[0023] 3. The large-volume concrete product casting equipment and method ensure the fixation of the casting position during the casting process through the coordinated use of the internal support mechanism and the swing mechanism, thereby more accurately controlling the concrete casting process, further ensuring that the concrete is evenly distributed in the formwork, improving the uniformity and accuracy of casting, and preventing the casting pipe from directly hitting the formwork during swing casting, while preventing the concrete from concentratedly impacting a specific position of the formwork, thereby ensuring the integrity and service life of the formwork. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram of the three-dimensional structure of the present invention when it is working.

[0025] Figure 2 It is a partial three-dimensional structural schematic diagram of the present invention.

[0026] Figure 3 It is a schematic diagram of the internal three-dimensional structure of the fixing mechanism of the present invention.

[0027] Figure 4 It is a partial cross-sectional three-dimensional structural schematic diagram of the inner support mechanism of the present invention.

[0028] Figure 5 It is a schematic diagram of the cross-sectional three-dimensional structure of the inner support part of the present invention.

[0029] Figure 6 It is a schematic diagram of a partially cutaway three-dimensional structure of the swing part of the present invention.

[0030] Figure 7 It is a top view of the three-dimensional structure of the synchronization part of the present invention.

[0031] Figure 8 It is a bottom-up stereoscopic structural schematic diagram of the vibration part of the present invention.

[0032] In the figure: 1, support seat; 2, through-hole; 3, casting pipe; 4, fixing mechanism; 41, fixing part; 411, first slideway; 412, first slider; 413, arc support plate; 414, bidirectional screw; 42, transmission part; 421, first belt; 422, first motor; 5, inner support mechanism; 51, lifting part; 511, sling; 512, equipment support block; 513, first cavity; 514, second cavity; 515, through hole; 52, inner support part; 521, bearing seat; 522, screw sleeve; 523, Screw rod; 524, inner support plate; 525, supporting slide; 526, slide rod; 53, driving part; 531, gear ring; 532, second motor; 6, swing mechanism; 61, swing part; 611, supporting ball; 612, rocker rod; 613, shaft rod; 614, turntable; 615, swing plate; 62, synchronous part; 621, second pulley; 622, second gear; 623, third motor; 63, vibration part; 631, second slideway; 632, second slider; 633, bolt; 634, fixed nozzle. DETAILED DESCRIPTION

[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0034] See also Figure 1 and Figure 2A large-volume concrete product casting equipment includes a support base 1 with a cavity inside, the support base 1 is provided with a through-tube hole 2 penetrating the upper and lower end surfaces thereof and a casting pipe 3 located in the through-tube hole 2 and used for casting concrete, the support base 1 is provided with a fixing mechanism 4 for positioning and fixing the support base 1 on a template; the fixing mechanism 4 includes a fixing part 41 arranged on the support base 1 and used for internally supporting, pressing and fixing adjacent threaded columns in the template, and the fixing part 41 is provided with a transmission part 42 for providing power to the fixing part 41.

[0035] See also Figure 1 and Figure 2 The support seat 1 is provided with an internal support mechanism 5 for driving the pouring pipe 3 to perform step-by-step pouring from bottom to top in the template; the internal support mechanism 5 includes a lifting part 51 arranged on the support seat 1, and the lifting part 51 is provided with an internal support part 52 for fixing the lifting part 51 in the template and a driving part 53 for providing power to the internal support part 52.

[0036] See also Figure 1 and Figure 2 The lifting part 51 is provided with a swing mechanism 6 for fixing the vibrating rod and the pouring pipe 3; the swing mechanism 6 includes a swing part 61 provided on the lifting part 51 and used for evenly swinging the vibrating rod and the pouring pipe 3, and a synchronization part 62 for providing synchronization power to the swing part 61; the swing part 61 is provided with a vibration part 63 for transmitting vibration during the vibration of the vibrating rod to pour the pouring pipe 3.

[0037] See also Figure 1 , Figure 2 and Figure 3 The fixing portion 41 includes a first slideway 411, a first slider 412, an arc-shaped support plate 413 and a bidirectional screw 414. A left-right symmetrical first slideway 411 is provided through the lower end surface of the support seat 1. The first slideways 411 are slidably installed with front-to-back symmetrical first sliders 412. The ends of the front-to-back symmetrical first sliders 412 on the same first slideway 411 that are away from each other are fixedly installed with an arc-shaped support plate 413. A bidirectional screw 414 is installed in the support seat 1 through a bearing and is located above the first slider 412 and is threadedly connected to the corresponding front-to-back symmetrical first slider 412.

[0038] See also Figure 2 and Figure 3 The transmission part 42 includes a first belt 421 and a first motor 422. The bidirectional screws 414 are fixedly sleeved with a first pulley, and the first pulleys are connected through the first belt 421. The support seat 1 is fixedly mounted with a first motor 422 whose output end is fixedly connected to one of the bidirectional screws 414.

[0039] During specific work, when it is necessary to cast large prefabricated concrete wall columns, the support seat 1 is first hoisted to the uppermost end of the template by an external crane, and the internal support mechanism 5 and the swing mechanism 6 are placed in the template. At this time, the lower end face of the support seat 1 contacts the upper end of the threaded column of the template, and then the first motor 422 is started to rotate with the bidirectional screw 414 fixed to it, and the bidirectional screw 414 on the other side is synchronously rotated through the cooperation of the first pulley and the first belt 421, thereby driving the front and rear symmetrical first sliders 412 in the first slideways 411 on both sides to move away from each other synchronously, until the first slider 412 on the same side carries the corresponding arc-shaped support plate 413 to press against the adjacent threaded column. After the two sets of arc-shaped support plates 413 on the left and right sides are pressed against the threaded columns, the support seat 1 is fixed to the upper end of the template by the internal support pressure.

[0040] See also Figure 2 , Figure 4 and Figure 5 The lifting part 51 includes a sling 511, an equipment support block 512, a first cavity 513, a second cavity 514 and a through hole 515. The slings 511 are slidably installed at the four corners of the upper end surface of the support seat 1, and the lower ends of the slings 511 are fixedly installed with an equipment support block 512 located directly below the support seat 1. The equipment support block 512 is provided with a first cavity 513 and a second cavity 514 located directly below the first cavity 513. A through hole 515 corresponding to the through pipe hole 2 is penetrated through the equipment support block 512.

[0041] See also Figure 2 , Figure 4 and Figure 5 The inner support part 52 includes a bearing seat 521, a screw sleeve 522, a screw rod 523, an inner support plate 524, a support slide 525 and a slide rod 526. The upper end surface of the first cavity 513 is fixedly installed with a bearing seat 521 located at its four corners. A screw sleeve 522 that passes through the corresponding corner of the support seat 1 is installed on the bearing seat 521 through the bearing. The screw sleeve 522 is threadedly connected with a screw rod 523. The inner support plate 524 is fixedly installed at one end of the screw rod 523 that is away from each other. A support slide 525 located below the screw sleeve 522 is fixedly installed in the first cavity 513. Slide rods 526 fixedly connected to the corresponding inner support plate 524 are slidably installed in the support slide 525.

[0042] See also Figure 2 , Figure 4 and Figure 5The driving part 53 includes a gear ring 531 and a second motor 532. The ends of the screw sleeves 522 that are close to each other are fixedly sleeved with a first bevel gear. The gear ring 531 is rotatably installed on the upper end surface of the first cavity 513 through a bearing. The second motor 532 is fixedly installed in the first cavity 513. The output end of the second motor 532 is fixedly sleeved with a first gear meshing with the gear ring 531. The lower end surface of the gear ring 531 is fixedly installed with a bevel gear ring that is meshing with multiple first bevel gears at the same time.

[0043] During specific operation, after the fixing mechanism 4 fixes the support base 1, the winder fixedly installed on the support base 1 is started so that the slings 511 at the four corners can be synchronously retracted or released, and the slings 511 distributed at the four corners can ensure the stability of the equipment support block 512 when it descends or rises, and the height of the equipment support block 512 in the template is adjusted by the slings 511.

[0044] After the equipment support block 512 is moved down to the appropriate position in the template by the winder, the winder can be stopped, and after the equipment support block 512 is stable, the second motor 532 can be started to rotate the gear ring 531 through the first gear, and the gear ring 531 will drive the bevel gear ring to rotate the first bevel gear on the screw sleeve 522 at the same time, so that the screw sleeves 522 at the four corners can rotate synchronously, and in the process of rotation, the movement of the inner support plate 524 is limited by the sliding rod 526, so that under the cooperation of the screw sleeve 522 and the screw rod 523, the inner support plate 524 at the four corners moves to the side away from the equipment support block 512 until the expanded inner support plate 524 at the four corners presses on the corresponding threaded column, and the second motor 532 is stopped at this time, so that the swing mechanism 6 can be fixed in the template through the equipment support block 512, so as to ensure the fixation of the pouring position during the pouring process and prevent the pouring pipe 3 from directly hitting the template during swing pouring.

[0045] See also Figure 2 , Figure 6 , Figure 7 and Figure 8 The swinging part 61 includes a supporting ball 611, a swing rod 612, a shaft rod 613, a turntable 614 and a swinging plate 615. The lower end surface of the second cavity 514 is penetrated by a supporting ball 611 located below the corresponding bearing seat 521, and a swing rod 612 located at the center is fixedly penetrated by the supporting ball 611. The upper end surface of the second cavity 514 is installed with a shaft rod 613 located directly above the corresponding supporting ball 611 through a bearing. A turntable 614 is fixedly sleeved on the shaft rod 613. The side of the lower end surface of the turntable 614 deviating from the center of the circle is ball-connected with the corresponding swing rod 612, and the lower end of the swing rod 612 is jointly ball-connected with the swinging plate 615.

[0046] See also Figure 2 , Figure 6 and Figure 7The synchronous part 62 includes a second pulley 621, a second gear 622 and a third motor 623. The second pulley 621 is fixedly sleeved on the shaft 613, and the second pulleys 621 are connected by a second belt transmission. A second gear 622 is fixedly sleeved on one of the shafts 613, and a third motor 623 is fixedly installed in the second cavity 514. The output end of the third motor 623 is fixedly sleeved with a third gear meshing with the second gear 622.

[0047] See also Figure 2 and Figure 8 The vibration part 63 includes a second slide 631, a second slider 632, a bolt 633 and a fixed nozzle 634. The fixed nozzle 634 is fixedly installed at the center of the lower end surface of the swing plate 615. The lower end of the casting pipe 3 passes through the through hole 515 and is fixedly connected to the fixed nozzle 634. The lower end surface of the swing plate 615 is provided with a second slide 631 that is symmetrical about the fixed nozzle 634. The swing plate 615 is provided with a placement hole located at the center of the second slide 631 and used to pass the vibrating rod. The second sliders 632 that are symmetrical front and back and used to clamp the vibrating rod are slidably installed in the second slide 631. The two second sliders 632 located on the front side are threadedly connected with the bolts 633 that are symmetrical left and right. The two second sliders 632 located on the rear side are provided with screw holes corresponding to the corresponding bolts 633.

[0048] During the specific work, before pouring, the vibrator head of the vibrator (mainly composed of a vibrator head, a hose and a driver) fixedly installed on the equipment support block 512 is passed through the placement hole. At this time, the hose part of the vibrator passes through the equipment support block 512, and then the front and rear symmetrical second sliders 632 are brought close to each other so that the second sliders 632 clamp the hose part of the vibrator, and after the clamping is completed, the front and rear symmetrical second sliders 632 are fixed by bolts 633, thereby completing the fixation of the hose part of the vibrator.

[0049] After the inner support mechanism 5 completes the fixing of the device, the third motor 623 is started to rotate the second gear 622 through the third gear, thereby driving the corresponding shaft rod 613 to rotate, and then the shaft rod 613 is synchronously rotated by the cooperation of the second pulley 621 and the second belt, and the turntable 614 is driven to rotate during the rotation of the shaft rod 613, and the turntable 614 drives the upper end of the swing rod 612 to rotate around the central axis of the turntable 614, and the lower end of the swing rod 612 takes the supporting ball 611 as the center point, driving the swing plate 615 to swing back and forth at a uniform speed, thereby The swinging plate 615 drives the fixed pipe mouth 634 and the vibrating rod to swing back and forth at a uniform speed at the same time. At this time, the concrete is injected into the pouring pipe 3 and flows through its interior to reach the fixed pipe mouth 634 for discharge. At this time, with the cooperation of the swinging mechanism 6, the concrete can be evenly distributed to every corner of the template, and the swinging of the vibrating rod can evenly vibrate the poured concrete, and during the vibration of the vibrating rod, its vibration will be transmitted to the fixed pipe mouth 634, thereby preventing the concrete from segregating in the pipe and ensuring the homogeneity of the concrete during the pouring process.

[0050] After completing the vibration and pouring at this height, start the second motor 532 in reverse to release the fixation of the inner support mechanism 5, then start the winder to drive the fixed pipe mouth 634 to move from bottom to top through the inner support mechanism 5, and repeat the above process, so as to complete the step-by-step pouring of concrete from bottom to top in the template, thereby avoiding the segregation of concrete during the free fall process and improving the overall homogeneity of the concrete.

[0051] The present invention also provides a casting method using the above-mentioned large-volume concrete product casting equipment. The specific processing method includes the following steps: S1: Preparation work: Install the formwork according to the design requirements, and tie the steel bars according to the design drawings, and determine the concrete mix ratio according to the design requirements and construction environment conditions.

[0052] S2: Fixing equipment: Use an external crane to hoist the support base 1 to the uppermost end of the template, and place the inner support mechanism 5 and the swing mechanism 6 inside the template. At this time, start the first motor 422 to press the two sets of arc-shaped support plates 413 on the left and right sides against the threaded columns through the fixing mechanism 4, thereby fixing the support base 1 to the upper end of the template through the inner support pressure.

[0053] S3: Adjust the height: After the fixing mechanism 4 fixes the support seat 1, start the winder fixedly installed on the support seat 1 to adjust the height of the equipment support block 512 in the template. After the equipment support block 512 moves down to a suitable position in the template, the winder can be stopped. After the equipment support block 512 is stable, start the second motor 532 to press the inner support plates 524 expanded at the four corners against the corresponding threaded columns through the inner support part 52 and the driving part 53. At this time, stop the second motor 532, so that the swing mechanism 6 can be fixed in the template through the equipment support block 512.

[0054] S4: pouring: after the internal support mechanism 5 completes the fixation of the equipment, start the third motor 623 to drive the swinging plate 615 to swing back and forth at a constant speed through the swinging mechanism 6, thereby driving the fixed pipe mouth 634 and the vibrating rod to swing back and forth at a constant speed at the same time. At this time, the concrete is injected into the pouring pipe 3 and flows through its interior to reach the fixed pipe mouth 634 for discharge. At this time, with the cooperation of the swinging mechanism 6, the concrete can be evenly distributed to every corner of the template, and the vibrating rod vibrates the poured concrete.

[0055] S5: Step-by-step pouring: After completing the vibration and pouring at this height, start the second motor 532 in reverse to release the fixation of the inner support mechanism 5, then start the winder to drive the fixed pipe mouth 634 to move from bottom to top through the inner support mechanism 5, and repeat the above process to complete the step-by-step pouring of concrete from bottom to top in the template.

[0056] S6: Subsequent operations: After pouring, cover with plastic film and sprinkle water regularly for maintenance, and demould according to the development of concrete strength, and then check the quality of the surface of large concrete precast wall columns.

[0057] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A large-volume concrete product casting device, comprising a support base (1) with a cavity inside, Features: The support seat (1) is provided with a through-hole (2) penetrating the upper and lower end surfaces thereof and a pouring pipe (3) located in the through-hole (2) and used for pouring concrete, and the support seat (1) is provided with a fixing mechanism (4) for positioning and fixing the support seat (1) on a template; The fixing mechanism (4) comprises a fixing part (41) arranged on the support seat (1) and used to drive the pouring pipe (3) to implement internal support, pressing and fixing of adjacent threaded columns in the template, and a transmission part (42) is arranged on the fixing part (41) to provide power for the fixing part (41); An internal support mechanism (5) is provided on the support seat (1) for performing step-by-step pouring from bottom to top in the template; The inner support mechanism (5) comprises a lifting part (51) arranged on the support seat (1), and the lifting part (51) is provided with an inner support part (52) for fixing the lifting part (51) in the template and a driving part (53) for providing power to the inner support part (52); The lifting part (51) is provided with a swing mechanism (6) for fixing and installing a vibrating rod and a pouring pipe (3); The swing mechanism (6) comprises a swing part (61) arranged on the lifting part (51) and used for evenly swinging the vibrating rod and the casting pipe (3), and a synchronization part (62) for providing synchronization power to the swing part (61); the swing part (61) is provided with a vibration part (63) for transmitting vibration during the vibration of the vibrating rod to cast the casting pipe (3); The swinging part (61) comprises a supporting ball (611), a swing rod (612), a shaft (613), a rotating disk (614) and a swinging plate (615); the lower end of the lifting part (51) is movably installed with a supporting ball (611); the supporting ball (611) is fixedly installed with a swing rod (612) located at the center thereof; the upper end of the lifting part (51) is installed with a shaft (613) located directly above the corresponding supporting ball (611) through a bearing; the shaft (613) is fixedly sleeved with a rotating disk (614); the side of the lower end surface of the rotating disk (614) deviating from the center of the circle is ball-connected with the corresponding swing rod (612); the lower end of the swing rod (612) is ball-connected with the swinging plate (615); The vibration part (63) comprises a second slideway (631), a second slider (632), a bolt (633) and a fixed nozzle (634); the fixed nozzle (634) is fixedly installed at the center of the lower end surface of the swing plate (615); the lower end of the casting pipe (3) is fixedly connected to the fixed nozzle (634); the lower end surface of the swing plate (615) is provided with a second slideway (631) which is symmetrical with respect to the fixed nozzle (634); a placement hole is provided through the swing plate (615) which is located at the center of the second slideway (631) and is used to pass a vibrating rod; second sliders (632) which are symmetrical in front and back and are used to clamp the vibrating rod are slidably installed in the second slideway (631); the two second sliders (632) located at the front side are threadedly connected with bolts (633) which are symmetrical in front and back; the two second sliders (632) located at the rear side are provided with screw holes which correspond to the corresponding bolts (633) one by one.

2. A large-volume concrete product casting device according to claim 1, Features: The fixing portion (41) comprises a first slideway (411), a first slider (412), an arc-shaped support plate (413) and a bidirectional screw (414); a left-right symmetrical first slideway (411) is provided through the lower end surface of the support seat (1); first sliders (412) that are symmetrical in front and back are slidably installed in the first slideway (411); the ends of the first sliders (412) that are symmetrical in front and back on the same first slideway (411) that are away from each other are fixedly installed with an arc-shaped support plate (413); a bidirectional screw (414) that is located above the first slider (412) and is threadedly connected to the corresponding first slider (412) that is symmetrical in front and back is installed in the support seat (1) through a bearing.

3. A large-volume concrete product casting device according to claim 2, Features: The transmission part (42) comprises a first belt (421) and a first motor (422); the bidirectional screws (414) are all fixedly sleeved with a first pulley; the first pulleys are connected to each other through a first belt (421); and the support seat (1) is fixedly mounted with a first motor (422) whose output end is fixedly connected to one of the bidirectional screws (414).

4. A large-volume concrete product casting device according to claim 1, Features: The lifting part (51) comprises a sling (511), an equipment support block (512), a first cavity (513), a second cavity (514) and a through hole (515); the slings (511) are slidably installed at the four corners of the upper end surface of the support seat (1); the lower ends of the slings (511) are fixedly installed with an equipment support block (512) located directly below the support seat (1); the equipment support block (512) is provided with a first cavity (513) and a second cavity (514) located directly below the first cavity (513); and the equipment support block (512) is provided with a through hole (515) corresponding to the through pipe hole (2).

5. A large-volume concrete product casting device according to claim 4, Features: The inner support part (52) comprises a bearing seat (521), a screw sleeve (522), a screw rod (523), an inner support plate (524), a support slide cylinder (525) and a slide rod (526); the upper end surface of the first cavity (513) is fixedly installed with a bearing seat (521) located at its four corners; a screw sleeve (522) is installed on the bearing seat (521) through a bearing and passes through the corresponding corner of the support seat (1); the screw sleeve (522) is threadedly connected with the screw sleeve (523); the inner support plate (524) is fixedly installed at one end of the screw rod (523) away from each other; a support slide cylinder (525) located below the screw sleeve (522) is fixedly installed in the first cavity (513); and a slide rod (526) fixedly connected to the corresponding inner support plate (524) is slidably installed in the support slide cylinder (525).

6. A large-volume concrete product casting device according to claim 5, Features: The driving part (53) comprises a gear ring (531) and a second motor (532); the ends of the screw sleeves (522) close to each other are fixedly sleeved with a first bevel gear; the gear ring (531) is rotatably mounted on the upper end surface of the first cavity (513) via a bearing; the second motor (532) is fixedly mounted in the first cavity (513); the output end of the second motor (532) is fixedly sleeved with a first gear meshingly connected to the gear ring (531); and the lower end surface of the gear ring (531) is fixedly mounted with a bevel gear ring meshingly connected to a plurality of first bevel gears.

7. A large-volume concrete product casting device according to claim 5, Features: The support ball (611) is movably installed through the lower end surface of the second cavity (514) and is located below the corresponding bearing seat (521), and the lower end of the casting pipe (3) passes through the through hole (515).

8. A large-volume concrete product casting device according to claim 7, Features: The synchronous part (62) comprises a second pulley (621), a second gear (622) and a third motor (623); the second pulley (621) is fixedly sleeved on each of the shafts (613); the second pulleys (621) are connected via a second belt transmission; a second gear (622) is fixedly sleeved on one of the shafts (613); a third motor (623) is fixedly installed in the second cavity (514); and a third gear meshingly connected to the second gear (622) is fixedly sleeved on the output end of the third motor (623).

9. A method for casting a large-volume concrete product, using the large-volume concrete product casting equipment according to claim 1, It is characterized in that The specific steps include: S1: Preparation: Install the formwork according to the design requirements, tie the steel bars according to the design drawings, and determine the concrete mix ratio according to the design requirements and construction environment conditions; S2: Fixing device: moving the support base (1) to the upper end of the template, and fixing the support base (1) to the upper end of the template by means of the inner support pressure of the fixing mechanism (4); S3: adjusting the height: adjusting the height of the pouring pipe (3) in the formwork through the inner support mechanism (5), and fixing the inner support mechanism (5) in the formwork after reaching a suitable height; S4: pouring: the vibrating rod and the pouring pipe (3) are evenly swung by the swing mechanism (6), and concrete is passed into the pouring pipe (3) for pouring, while the vibrating rod vibrates the poured concrete; S5: pouring step by step: pouring step by step from bottom to top in the template through the cooperation of the inner support mechanism (5) and the swing mechanism (6); S6: Subsequent operations: After pouring, cover with plastic film and sprinkle water regularly for maintenance, and demould according to the development of concrete strength, and then check the quality of the surface of large concrete precast wall columns.