A construction method for supporting small pipe shed advance grouting combined with branch excavation tunnels in mining area crossing projects
Through the advanced grouting of the small pipe shed combined with the branch excavation tunnel support method, the problem of tunnel collapse and floor subsidence in the over-mining area was solved, the stability and safety of the tunnel was achieved, and the efficient recovery of mine residual ore resources was promoted.
Patent Information
- Application Number
- CN202411090184.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-10-18
- Estimated Expiration
- 2044-08-09
AI Technical Summary
Existing roadway support methods cannot meet the support requirements for roadways that pass through the ruins in over-mining areas. They are prone to collapse and floor subsidence, which affects the safe and efficient recovery of mine residual ore resources.
The tunnel support method of small pipe shed advanced grouting combined with branch excavation is adopted, including advanced 'small pipe shed + grouting' combined support, low disturbance branch excavation, secondary support, tunnel back sealing and supplementary reinforcement. Through a variety of advanced rapid The corresponding joint support method forms a stable tunnel as a whole to avoid collapse and subsidence.
It effectively maintains the stability of the tunnel and the safety of workers, achieves safe and efficient recovery of mine residual ore resources, reduces accident risks and losses, and has high promotion and application value.
Smart Images

Figure CN118622283B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel support, and in particular to a construction method for small pipe shed advance grouting combined with branch excavation tunnel support suitable for a mining area through-the-wall project. Background Art
[0002] Due to the backward mining technology in the early days, the shallow mineral resources of the mines were not fully recovered, leaving many low-grade residual ore resources and surrounding rocks near the mines in the mining area. With the reduction of the reserves of most mine resources, the residual ore resources left in the shallow part have a certain recycling value. However, due to the restrictions of early mining expansion and random mining, the recycling of these residual ore resources will involve the layout of the over-mining area and ruins engineering. When the roadway passes through the mining area full of residual ore, it will face the risks of landslides, spalling, and floor sinking, making it difficult to achieve safe and efficient recovery of residual ore resources.
[0003] At present, the support methods for tunnels through ruins are rarely used in metal mines. The biggest problem is that the existing mainstream support methods are difficult to meet the support requirements of tunnels through ruins, such as the small diffusion radius of grouting slurry in bulk, the low anchoring force generated by anchor rods, and the difficulty in ensuring the safety of workers during support operations.
[0004] Therefore, designing a tunnel support technology that can effectively maintain the stability of the tunnel and the safety of workers during excavation operations in over-mined areas and has on-site practicality is of great significance for the recovery of residual ore resources in over-mined areas in my country. Summary of the invention
[0005] In order to solve the problems of landslides and bottom plate sinking in over-mining area tunneling projects, the present invention provides a construction method of small pipe shed advance grouting combined with branch excavation tunnel support suitable for over-mining area tunneling projects. The construction method includes the processes of advance "small pipe shed + grouting" joint support, low-disturbance branch excavation, secondary support, tunnel bottom sealing, supplementary reinforcement, etc. The present invention forms the over-mining area tunneling into an integral project by providing a variety of advanced and fast-response joint support methods, avoids accidents such as landslides and sinking in the tunneling process, and can maintain the long-term normal use of the tunnel, thereby realizing safe and efficient recovery of mine residual ore resources.
[0006] The present invention provides a construction method for small pipe shed advance grouting combined with branch excavation tunnel support applicable to a mining area crossing project, comprising the following steps:
[0007] S1, determine the type and proportion of grouting materials and the type of early strength agent according to the distribution of cracks in the granular body;
[0008] S2, determine the parameters of the pipe support hole and grouting hole according to the tunnel section specifications;
[0009] The tunnel is divided into an upper arch and a lower core area; the arch is divided into an arch left area and an arch right area; the core area is divided into a core area left area and a core area right area;
[0010] The initial position of the pipe support hole is arranged in the arch contour area of the tunnel. After the tunnel is excavated, the opening is arranged on the last steel arch frame of the previous cycle. The hole spacing is 300-500 mm, the elevation angle is 8-12°, the diameter is 40-42 mm, and the hole depth is 3-5 m.
[0011] The grouting holes include contour holes arranged in the arch and two sides of the tunnel, reinforcement holes arranged inside the contour line of the tunnel arch, and core holes staggered in the left area and the right area of the core area of the tunnel branch excavation;
[0012] S3, build a mortar wall at the cross section of the tunnel, and use cement to make sure there are no cracks;
[0013] S4, marking the drilling positions according to the pipe-roof hole and grouting hole parameters;
[0014] First, the pipe support hole is drilled, and after each pipe support hole is drilled, a seamless steel pipe is immediately inserted into the pipe support hole. After the pipe support is completed, the grouting hole is drilled, and then grouting is performed in the grouting hole; the grouting sequence is from bottom to top, first the contour hole, then the reinforcement hole, and finally the core hole;
[0015] S5, after the grouting solution solidifies, a single-arm tunnel boring machine or a controlled blasting low-disturbance tunneling method is used to first excavate the left side of the arch, and after checking the arch advance support effect, the right side of the arch is excavated. After the arch area is completely pulled open, secondary support work is carried out;
[0016] S6, after the excavation and support of the arch area is completed, the left area of the core area is excavated in a low-disturbance tunneling mode, and the excavation depth is 200-400mm lower than the tunnel floor, and then the pumice treatment, shotcrete, mesh hanging, column erection, threaded steel welding, and foot locking processes are completed in sequence; after the excavation and support of the left area of the core area is completed, the right area of the core area is excavated and supported in the same way; or
[0017] First, excavate the right side of the core area. After the excavation and support of the right side of the core area is completed, excavate and support the left side of the core area in the same way.
[0018] S7, after the tunnel branch excavation is completed, the tunnel floor is immediately leveled and compacted, and then the scrap rails and metal mesh are laid. The laying length of the scrap rails and metal mesh is at least 20 cm longer than the length of the concrete pouring this time to avoid disconnection with the concrete cushion layer poured next time. Finally, concrete is poured with a pouring thickness of 200-400 mm, which is the same as the height of the tunnel floor;
[0019] S8, after the concrete cushion layer solidifies, enter the tunnel for secondary spraying with a thickness of 100~150mm. Wrap the steel arch frame and metal mesh in the spraying layer to complete the supplementary reinforcement work; then prepare for the next cycle of tunnel excavation support work.
[0020] As a further improvement of the present invention, the end of the seamless steel pipe inserted into the pipe rack hole is needle-shaped, with a diameter of 32-40 mm and a length of 3.2-5.2 m. The exposed length of the seamless steel pipe on the steel arch frame is 0.1-0.2 m.
[0021] As a further improvement of the present invention, the excavation depth of the core area is the same as the excavation depth of the arch area, both of which are 1-2m; after the excavation of the core area is completed, secondary support is immediately carried out.
[0022] As a further improvement of the present invention, the contour holes include first contour holes arranged in the tunnel arch and second contour holes arranged on both sides; the first contour holes and the pipe roof holes are arranged alternately, the elevation angle of the first contour holes is 15~20°, the elevation angle of the second contour holes is 8~12°, the hole spacing of the contour holes is 300~500mm, and the hole depth of the contour holes is 3~5m.
[0023] As a further improvement of the present invention, the reinforcement holes are arranged alternately with the first contour holes, the reinforcement holes are arranged 300~500mm away from the tunnel contour line, the hole spacing is 300~500mm, the elevation angle is 8~12°, and the hole depth is 3~5m.
[0024] As a further improvement of the present invention, the core holes are arranged in rows, the hole spacing of the core holes is 600-1000 mm, the row spacing is 300 mm, the elevation angle is 8-12°, and the hole depth is 3-5 m.
[0025] Due to the different fissures in the bulk body that the tunneling project passes through, the number and spacing of the pipe-roof holes and grouting holes will also be different, and the diffusion range of the grouting solution will also be different. Therefore, the hole layout parameters should be flexibly changed according to the on-site conditions and cannot be completely generalized. Secondly, due to the large number of fissures in the bulk body of the tunneling project, the permeability of the grouting solution is poor. In order to ensure the diffusion effect of the solution as much as possible, the solution concentration should be appropriately lowered to maintain good fluidity to facilitate penetration and diffusion in the bulk body. It is also best to find a bulk ore pile for buried pipe grouting before large-scale application to test the diffusion effect.
[0026] Specifically, step S1 includes the following process: selecting a mine bulk body, pre-burying a grouting pipe, testing the diffusion range and coagulation time of grouting solutions with different proportions, and sending the ore after grouting and solidification to the concentrator to detect whether the grouting will affect the grinding of the concentrator, and determining the type, proportion and early strength agent of the grouting material based on the results.
[0027] As a further improvement of the present invention, in the grouting solution, the weight ratio of water to ultrafine binder is (0.5~0.8):1, the amount of the early strength agent added is 5~8% of the weight of the binder, the particle size of the binder particles is less than 800 mesh, the chloride ion content of the grouting solution is lower than 0.06%, and the effective setting time is controlled within 7 days.
[0028] As a further improvement of the present invention, in step S5, the secondary support work refers to the immediate processing of pumice and spraying after the arch area is completely opened, the spraying thickness is 30~50mm, and then the metal mesh is hung, the arch ring is erected, and threaded steel bars are welded between the arch rings, and finally the arch rings are locked.
[0029] The supplementary reinforcement refers to secondary shotcrete support after the tunnel bottom is completed, with concrete grade C20 and a shotcrete layer thickness of 100~150mm.
[0030] The beneficial effects of the present invention are:
[0031] 1. The present invention provides a construction method for small pipe shed advance grouting combined with branch excavation tunnel support suitable for over-mining area tunneling projects, including advance "small pipe shed + grouting" combined support, branch low-disturbance tunneling, secondary support, tunnel bottom sealing, supplementary reinforcement and other processes. By providing a variety of advanced and fast-response combined support methods, the over-mining area tunneling is formed into a stable whole.
[0032] The working method is: according to the distribution of cracks in the scattered body of Chuanxu, the grouting solution and the early strength agent are selected, and the hole layout parameters are determined in combination with the diffusion range of the grouting solution to carry out the hole layout. Then the slurry blocking wall is constructed, and the processes of pre-buried seamless steel pipes and grouting are completed in sequence. After the grouting solidifies, a low-disturbance branch excavation method is adopted to excavate the arch area, the left area of the core area (the right area of the core area) and the right area of the core area (the left area of the core area) in sequence, and secondary support is carried out. Finally, the tunnel is sealed and supplemented with reinforcement to complete the tunnel excavation cycle of Chuanxu. The construction method of the present invention fully takes into account the problems of difficult grouting of scattered bodies, easy collapse of Chuanxu projects, and easy sinking of tunnels after long-term use, and further controls the range of accident risks that may occur in the Chuanxu process to the minimum, the loss to the minimum, and the remediation to the fastest. It has a high value of promotion and application, which is helpful for the recovery of residual mineral resources in mines and achieves longer-term development.
[0033] 2. The present invention sequentially carries out the processes of advanced "small pipe shed + grouting" combined grouting, branch low-disturbance excavation, secondary support, etc., to meet the safety requirements of the mining area tunneling project in different excavation periods. When tunneling through the mining area, the scattered structure that fails to form an entirety cannot effectively provide the initial support force, causing the tunnel to be difficult to shape, prone to collapse and sinking when it first begins to be excavated. Therefore, before tunnel excavation, the first step of the present invention is to first form a hard shell with preliminary support force in the scattered structure, and then excavate the tunnel in the hard shell. By implementing the advanced "small pipe shed + grouting" combined support, a solid hard shell is artificially created in the scattered body, and tunnel excavation in the hard shell solves the problem of the tunneling project being difficult to shape.
[0034] 3. One end of the seamless steel pipe (small pipe shed) of the tunnel arch of the present invention is inserted into the bulk body with an upward tilt, and the other end is exposed in the arch frame for a short section, becoming a "lever". With this arrangement, while one end of the steel pipe is under pressure in the bulk body, the other end will provide an upward supporting force to the arch frame, effectively preventing the steel arch frame from sinking.
[0035] 4. When the tunnel is excavated in full section, only 30~50cm of the tunnel shell is left to support the bulk pressure, which makes it difficult to ensure safety. In addition, simultaneous excavation makes the tunnel prone to collapse and the difficulty of handling greatly increased. After completing the advance "small pipe shed + grouting" joint support, the present invention adopts a branch excavation method to divide the tunnel into three areas for excavation in sequence. The length of each excavation is 1~2m, which is less than the advance grouting length. With this design, after excavation, a 2~3m long support dam will be retained in the tunnel to prevent the bulk from pouring into the excavated area, and the support dam can serve as a grouting wall during the next cycle of excavation, without the need to re-do grouting to prevent blocking. After the arch area is excavated, secondary support is immediately carried out. In this way, when excavating the core areas II and III, the operators work under the supported arch, which greatly improves safety. After the branch tunnel is excavated and the secondary support is completed, the tunnel bottom sealing work needs to be carried out. By pouring the concrete cushion layer, the cushion layer is connected with the steel arch frame to prevent the tunnel from sinking further. After the tunnel bottom sealing is completed, the tunnel is finally reinforced and the integrity and stability of the tunnel are further improved through secondary grouting. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 This is a schematic diagram of the hole layout before excavation for the mining area crossing project.
[0037] Figure 2 This is a schematic diagram of the support front of the tunneling project through the mining area.
[0038] Figure 3 for Figure 2 A partial enlarged schematic diagram of .
[0039] Figure 4 For along Figure 2 A side view schematic diagram of the support structure of the tunneling project through the mining area cut by the middle line II. DETAILED DESCRIPTION
[0040] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention is described in detail below with reference to the accompanying drawings and specific embodiments.
[0041] It should also be noted that, in order to avoid obscuring the present invention due to unnecessary details, only structures and / or processing steps closely related to the scheme of the present invention are shown in the drawings, while other details that are not closely related to the present invention are omitted.
[0042] In addition, it should be noted that the terms "comprises", "includes" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or apparatus that includes a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or apparatus.
[0043] See also Figures 1 to 4 As shown, the present invention provides a construction method for small pipe shed advance grouting combined with branch excavation tunnel support suitable for mining area crossing engineering, comprising the following steps:
[0044] S1, determine the type and proportion of grouting materials and the type of early strength agent according to the distribution of cracks in the granular body;
[0045] Specifically, a representative mine bulk material is selected, a grouting pipe is pre-buried, the diffusion range and coagulation time of grouting solutions with different proportions are tested, and the ore after grouting and solidification is sent to the concentrator to detect whether the grouting will affect the grinding of the concentrator. Based on the results, the type of grouting material, proportion and early strength agent are determined.
[0046] In the present invention, by weight, in the grouting solution, the weight ratio of water to ultrafine binder is (0.5-0.8):1, the amount of early strength agent added is 5-8% of the weight of the binder, the particle size of the binder particles is less than 800 mesh, the chloride ion content of the grouting solution is less than 0.06%, and the effective setting time is controlled within 7 days.
[0047] S2, determine the parameters of the pipe support hole and grouting hole according to the tunnel section specifications;
[0048] The tunnel is divided into the upper arch (area I) and the lower core area; the arch is divided into the left area of the arch and the right area of the arch; the core area is divided into the left area of the core area (area II) and the right area of the core area (area III);
[0049] The initial position of the pipe-roof hole is arranged in the contour area of the tunnel arch. After the tunnel is excavated, the opening is arranged on the last steel arch frame of the previous cycle. The hole spacing is 300~500mm, the elevation angle is 8~12°, the diameter is 40~42mm, and the hole depth is 3~5m.
[0050] The grouting holes include contour holes 80 arranged in the arch and both sides of the tunnel, reinforcement holes 70 arranged inside the contour line of the tunnel arch, and core holes 40 staggered in the left area and the right area of the core area of the tunnel branch excavation.
[0051] Specifically, the contour holes include first contour holes arranged in the arch of the tunnel and second contour holes arranged in the two sides. The first contour holes are arranged alternately with the pipe shed holes, the elevation angle of the first contour holes is 15-20°, the elevation angle of the second contour holes is 8-12°, the hole spacing of the contour holes is 300-500mm, and the hole depth of the contour holes is 3-5m.
[0052] The reinforcement holes are arranged alternately with the first contour holes. The reinforcement holes are arranged 300~500mm away from the tunnel contour line, with a hole spacing of 300~500mm, an elevation angle of 8~12°, and a hole depth of 3~5m. The purpose of the arrangement is to make up for the blind area caused by grouting of the arch contour holes so that the grouting liquid can completely wrap the seamless steel pipe (pipe shed).
[0053] The core holes 40 are arranged in rows, the hole spacing of the core holes 40 is 600-1000 mm, the row spacing is 300 mm, the elevation angle is 8-12°, and the hole depth is 3-5 m.
[0054] S3, build a mortar blocking wall 30 at the cross section of the tunnel, and use cement to plaster the surface to ensure that there are no cracks;
[0055] Specifically, the slurry blocking wall 30 is used to block the entire section during the initial excavation of the tunnel. The wall thickness is 24 walls, and it is ensured to be tightly fitted to prevent the grouting liquid from leaking.
[0056] S4, marking the drilling positions according to the pipe-roof hole and grouting hole parameters;
[0057] First, the pipe support hole 10 is drilled. After each pipe support hole 10 is drilled, the seamless steel pipe 11 is immediately inserted into the pipe support hole 10. After the pipe support is completed, the grouting hole is drilled, and then grouting is performed in the grouting hole. The grouting sequence is from bottom to top, first the contour hole 80, then the reinforcement hole 70, and finally the core hole 40.
[0058] Specifically, the end of the seamless steel pipe 11 inserted into the pipe rack hole 10 is needle-shaped, with a diameter of 38 mm and a length of 3.2 to 5.2 m. The exposed length of the seamless steel pipe 11 on the steel arch is 0.2 m.
[0059] In addition, one end of the seamless steel pipe (small pipe shed) is inserted into the bulk body at an upward angle, and the other end is exposed in the arch frame for a short period of time, forming a "lever". The advantage of this design is that while the steel pipe is under pressure at one end of the bulk body, the other end will provide an upward supporting force to the arch frame, effectively preventing the steel arch frame from sinking.
[0060] The grouting pipe 12 is used for advance grouting support. The grouting liquid penetrates into the cracks of the bulk through the grouting pipe, thereby solidifying the bulk into a whole and producing a supporting effect. The end of the grouting pipe 12 is needle-shaped, and the grouting pipe 12 has grouting holes throughout its entire length. The grouting holes have a diameter of 5-10 mm and are spaced 300-500 mm apart.
[0061] During grouting, the grouting pressure should be flexibly adjusted according to the scattered material conditions in the tunneling project. To ensure the grouting effect, the final grouting pressure must reach about 1~2MPa. The grouting order is from bottom to top and from both sides to the middle.
[0062] S5: After the grouting solution solidifies, use a low-disturbance excavation method such as a single-arm tunnel boring machine or controlled blasting to first excavate the left side of the arch. After checking the arch advance support effect, excavate the right side of the arch. After the arch area is completely pulled open, carry out secondary support work.
[0063] Use low-disturbance excavation methods such as single-arm tunnel boring machines or controlled blasting to excavate the tunnel to avoid damaging the stability of the tunnel perimeter.
[0064] In step S5, the secondary support work refers to the arch area being completely opened, and after the roadway is excavated and the slag is cleared, the floating stone is first cleaned, and then the shotcrete support is carried out. The concrete grade is C20, and the thickness of the shotcrete layer shall not be less than 30mm. Finally, the metal mesh is hung, and the steel arch frame 50 is erected and locked. Among them, the columns 52 of the steel arch frame are made of I-beams, and the arch ring 51 is made of channel steel. The spacing of the steel arch frame 50 is 0.3~0.7m. The steel arch frame support should be 300mm deep into the roadway floor and connected to the concrete cushion layer 72 as a whole.
[0065] The steel arches 50 are welded with threaded steel bars 62 , the threaded steel bars 62 have a diameter of 12 to 16 mm, a length of 0.3 to 0.7 m, and a spacing of 0.4 to 0.6 m.
[0066] S6, after the excavation and support of the arch area is completed, the left area of the core area is excavated by low-disturbance tunneling, and the excavation depth is 300mm lower than the tunnel floor. Then, the floating stone treatment, shotcrete, mesh hanging, 90 column erection, threaded steel welding, and foot locking processes are completed in sequence. After the excavation and support of the left area of the core area (area II) is completed, the right area of the core area (area III) is excavated and supported in the same way; or
[0067] First, excavate the right side of the core area. After the excavation and support of the right side of the core area is completed, excavate and support the left side of the core area in the same way.
[0068] The excavation depth of the core area is the same as that of the arch area, both of which are 1~2m; after the excavation of the core area is completed, secondary support is carried out immediately.
[0069] That is, the excavation length each time is 1~2m, which is less than the advance grouting length. The purpose of this design is to retain a 2~3m long support dam in the tunnel after excavation to prevent the bulk from pouring into the excavated area, and the support dam can serve as a grouting wall during the next cycle of excavation, without the need for grouting again.
[0070] The branch low-disturbance excavation method is adopted to weaken the destructive intensity of the tunnel excavation method on the advance support, and at the same time effectively control the exposed area and duration of the tunnel during the excavation process, which greatly reduces the risk of accidents in the tunnel during the excavation process. In addition, the branch excavation method will further reduce the scope and severity of accidents, allowing operators to quickly deal with dangerous situations and avoid reducing the excavation speed.
[0071] After the arch area is excavated, secondary support is immediately carried out. In this way, when excavating the core areas II and III, the workers can work under the supported arch, which greatly improves safety. After the branch tunnel is excavated and the secondary support is completed, the tunnel bottom needs to be sealed. By pouring a concrete cushion layer, the cushion layer is connected to the steel arch frame to prevent the tunnel from sinking further. After the tunnel bottom is sealed, the tunnel is finally reinforced and the integrity and stability of the tunnel are further improved through secondary grouting.
[0072] S7, after the tunnel branch excavation is completed, the tunnel floor is immediately leveled and compacted, and then the scrap rails and metal mesh are laid. The laying length of the scrap rails and metal mesh is at least 20cm longer than the length of the concrete pouring this time to avoid disconnection with the concrete cushion layer poured next time. Finally, the concrete is poured with a pouring thickness of 200~400mm, which is the same as the height of the tunnel floor;
[0073] S8, after the concrete cushion layer 72 solidifies, enter the tunnel for secondary spraying with a thickness of 100-150 mm. The steel arch frame and the metal mesh are wrapped in the spraying layer to complete the supplementary reinforcement work; then prepare for the next cycle of tunnel excavation support work.
[0074] The tunnel bottom sealing refers to cleaning the tunnel floor and making a concrete cushion layer to seal the bottom after the tunnel excavation is completed. First, the scrap rails are laid on the ore pile on the tunnel floor, with a mesh size of 0.5~1m×0.5~1m, and then two layers of metal mesh are laid on the rails, and then concrete is poured to form an integral concrete cushion layer. The thickness of the concrete cushion layer is 300mm, and the length of the two sides embedded in the two sides of the tunnel is 200~300mm. The rails are exposed to the inside of the tunnel for more than 200mm, which is convenient for connecting with the concrete cushion layer of the next cycle to form a whole.
[0075] Supplementary reinforcement refers to secondary shotcrete support after the tunnel bottom is completed. The concrete grade is C20 and the thickness of the shotcrete layer is 100~150mm.
[0076] Example 1
[0077] See also Figures 1 to 4As shown in the figure, a construction method for small pipe shed advance grouting combined with branch excavation tunnel support suitable for over-mining area tunneling engineering is presented. According to the loose body grouting test in the over-mining area of a domestic mine, the grouting solution ratio is determined. The weight ratio of water: ultrafine cementitious material is 0.8:1, the early strength agent is an alkali metal salt early strength agent, and the addition amount is 8%. The minimum diffusion range of the grouting solution in the loose body is 0.3m, and the ore after grouting solidification does not affect the ore dressing of the concentrator.
[0078] Before the excavation of the Chuanxu project, a full-section mortar blocking wall 30 is first built with a wall thickness of 24 walls, and then cement is used to plaster the surface to ensure the mortar blocking effect.
[0079] According to the specifications of the mine tunnel (2.6×2.6m) and the diffusion range of the grouting solution, holes were arranged, including 11 pipe-roof holes ( Figure 1 D1 to D11 in the figure), arranged on the arch contour line 20 of the tunnel, with a diameter of 40 mm, an elevation angle of 10°, a hole spacing of 300 mm, and a hole depth of 4 m.
[0080] 22 contour holes ( Figure 1 The hole spacing is 300mm, the diameter is 40mm, and the hole depth is 4m. The elevation angle of the arch hole (first contour hole) is 18°, and the elevation angle of the two-side contour hole (second contour hole) is 10°.
[0081] 9 reinforcement holes ( Figure 1 The diameter of the holes (G1 to G9) is 40 mm, the elevation angle is 10°, and the distance from the pipe support hole 10 is 300 mm. The spacing between adjacent reinforcement holes 70 is 300 mm, and the hole depth is 4 m.
[0082] 18 core holes ( Figure 1 H1 to H18 in the figure) are staggered in the area below the tunnel arch, with a hole spacing of 600mm, a row spacing of 300mm, an elevation angle of 10°, and a hole depth of 4m.
[0083] After marking the hole positions, first drill the pipe-roof hole 10. After drilling each pipe-roof hole 10, immediately insert a seamless steel pipe 11 with a diameter of 38 mm, and then drill the grouting holes. The drilling order is contour hole 80, reinforcement hole 70 and core hole 40. The holes are drilled from bottom to top. After drilling each grouting hole, immediately protect the hole and perform grouting to avoid hole collapse and blockage due to too long time. After the grouting pressure reaches 2 MPa, stop grouting and seal the hole.
[0084] After the grouting solution solidifies, a single-arm tunnel boring machine is used to excavate the left area of the arch (the left side of zone I). The excavation length is 1.5m. First, the left area of the arch is excavated to observe the effect of the advance support of the arch. After confirming the effect, the right area of the arch (the right side of zone I) is excavated. After the arch is completely excavated, the pumice is immediately processed and sprayed with a thickness of 300mm. Then, a metal mesh 61 is hung and an arch ring 51 is erected. A total of 3 arch rings 51 are erected with a spacing of 0.5m. Finally, threaded steel bars 62 with a diameter of 14mm are welded between the arch rings 51, and the arch rings 51 are locked with threaded anchor rods 60 with a diameter of 22mm and a length of 2.2m.
[0085] After the arch support is completed, a single-arm tunnel boring machine is used to excavate the core area II. The excavation depth should be 300 mm deeper than the bottom plate to reserve space for pouring the concrete cushion layer. After excavation, grouting is immediately performed, a metal mesh 61 is hung, and then columns 52 are erected, the columns 52 are connected to the arch ring 51, and threaded steel bars 62 with a diameter of 14 mm are welded between the columns 52. Then, according to the same construction process, excavation is carried out to the core area III.
[0086] After the tunnel branch excavation is completed, the tunnel floor is immediately leveled and compacted, and then the scrap rails and metal mesh 61 are laid, and concrete is poured with a pouring thickness of 300mm. The laying grid of the scrap rails is 800×800mm, and the exposed length of the scrap rails and metal mesh is 300mm. They are poured together with the concrete cushion layer to be poured next time to form a whole.
[0087] After the tunnel bottom sealing was completed, the staff entered the tunnel to carry out secondary spraying with a thickness of 100mm. The steel arch frame and metal mesh were wrapped in the spraying layer to complete the supplementary reinforcement work and complete the excavation cycle of the Chuanxu tunnel project.
[0088] In summary, the present invention provides a construction method for small pipe shed advance grouting combined with branch excavation tunnel support suitable for over-mining area tunneling projects. This construction method adopts a variety of combined supports and branch low-disturbance tunneling methods, which greatly improves the safety of tunneling in over-mining areas and the stability of long-term use, helps to safely and efficiently recover the residual mineral resources of mines, and prolongs its service life, bringing certain economic benefits to the mine. Since advance grouting is carried out around the tunnel and in front of the excavation during the excavation process, the initial support can be provided quickly and timely, and the tunnel excavation method of branch excavation is adopted, the unexcavated area will limit the deformation of the tunnel wall, effectively avoiding tunnel collapse, and ensuring that the working surface of the tunneling project has good stability during excavation.
[0089] This construction method strictly controls the tunnel excavation cycle advance. Even if the workers encounter danger during the excavation process, they can quickly move away from the work surface, effectively ensuring the safety of the workers.
[0090] This construction method fully takes into account the problems of small grouting diffusion range in bulk, difficulty in slurry blocking, and impact on ore recovery. It has stronger on-site applicability and is helpful for mines to promote the use of this support technology.
[0091] The above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the present invention may be modified or replaced by equivalents without departing from the spirit and scope of the technical solution of the present invention.
Claims
1. A construction method for small pipe shed advance grouting combined with branch excavation tunnel support suitable for mining area crossing engineering, characterized in that: The steps include: S1, determine the type and proportion of grouting materials and the type of early strength agent according to the distribution of cracks in the granular body; S2, determine the parameters of the pipe support hole and grouting hole according to the tunnel section specifications; The tunnel is divided into an upper arch and a lower core area; the arch is divided into an arch left area and an arch right area; the core area is divided into a core area left area and a core area right area; The initial position of the pipe support hole is arranged in the arch contour area of the tunnel. After the tunnel is excavated, the opening is arranged on the last steel arch frame of the previous cycle. The hole spacing is 300-500 mm, the elevation angle is 8-12°, the diameter is 40-42 mm, and the hole depth is 3-5 m. The grouting holes include contour holes arranged in the arch and two sides of the tunnel, reinforcement holes arranged inside the contour line of the tunnel arch, and core holes staggered in the left area and the right area of the core area of the tunnel branch excavation; S3, build a mortar wall at the cross section of the tunnel, and use cement to plaster the surface to ensure that there are no cracks; S4, marking the drilling positions according to the pipe-roof hole and grouting hole parameters; First, the pipe support hole is drilled, and after each pipe support hole is drilled, a seamless steel pipe is immediately inserted into the pipe support hole. After the pipe support is completed, the grouting hole is drilled, and then grouting is performed in the grouting hole; the grouting sequence is from bottom to top, first the contour hole, then the reinforcement hole, and finally the core hole; S5, after the grouting solution solidifies, a single-arm tunnel boring machine or a controlled blasting low-disturbance tunneling method is used to first excavate the left side of the arch, and after checking the arch advance support effect, the right side of the arch is excavated. After the arch area is completely pulled open, secondary support work is carried out; S6, after the excavation and support of the arch area is completed, the left area of the core area is excavated in a low-disturbance tunneling mode, and the excavation depth is 200-400mm lower than the tunnel floor, and then the pumice treatment, shotcrete, mesh hanging, column erection, threaded steel welding, and foot locking processes are completed in sequence; after the excavation and support of the left area of the core area is completed, the right area of the core area is excavated and supported in the same way; or First, excavate the right side of the core area. After the excavation and support of the right side of the core area is completed, excavate and support the left side of the core area in the same way. S7, after the tunnel branch excavation is completed, the tunnel floor is immediately leveled and compacted, and then the scrap rails and metal mesh are laid. The laying length of the scrap rails and metal mesh is at least 20 cm longer than the length of the concrete pouring this time to avoid disconnection with the concrete cushion layer poured next time. Finally, concrete is poured with a pouring thickness of 200-400 mm, which is the same as the height of the tunnel floor; S8, after the concrete cushion layer solidifies, enter the tunnel for secondary spraying with a thickness of 100~150mm. Wrap the steel arch frame and metal mesh in the spraying layer to complete the supplementary reinforcement work; then prepare for the next cycle of tunnel excavation support work.
2. The construction method of small pipe shed advance grouting combined with branch tunneling support suitable for over-mining area and ruins engineering according to claim 1 is characterized by: The end of the seamless steel pipe inserted into the pipe rack hole is needle-shaped, with a diameter of 32-40 mm and a length of 3.2-5.2 m. The exposed length of the seamless steel pipe on the steel arch is 0.1-0.2 m.
3. The construction method of small pipe shed advance grouting combined with branch tunneling support suitable for over-mining area and under-mine engineering according to claim 1 is characterized by: The excavation depth of the core area is the same as that of the arch area, both of which are 1-2 m. After the excavation of the core area is completed, secondary support is immediately carried out.
4. The construction method of small pipe shed advance grouting combined with branch tunneling support suitable for over-mining area and ruins engineering according to claim 1 is characterized in that: The contour holes include first contour holes arranged in the arch of the tunnel and second contour holes arranged on both sides; the first contour holes and the pipe roof holes are arranged alternately, the elevation angle of the first contour holes is 15~20°, the elevation angle of the second contour holes is 8~12°, the hole spacing of the contour holes is 300~500mm, and the hole depth of the contour holes is 3~5m.
5. The construction method of small pipe shed advance grouting combined with branch tunneling support suitable for over-mining area and under-mine engineering according to claim 4 is characterized by: The reinforcement holes are arranged alternately with the first contour holes. The reinforcement holes are arranged 300-500 mm away from the tunnel contour line, with a hole spacing of 300-500 mm, an elevation angle of 8-12°, and a hole depth of 3-5 m.
6. The construction method of small pipe shed advance grouting combined with branch tunneling support suitable for over-mining area and ruins engineering according to claim 1 is characterized by: The core holes are arranged in rows, the hole spacing of the core holes is 600-1000 mm, the row spacing is 300 mm, the elevation angle is 8-12°, and the hole depth is 3-5 m.
7. The construction method of small pipe shed advance grouting combined with branch excavation tunnel support suitable for over-mining area and ruins engineering according to claim 1 is characterized in that: Step S1 includes the following process: selecting a mine bulk body, pre-burying a grouting pipe, testing the diffusion range and coagulation time of grouting solutions with different proportions, and sending the ore after grouting and solidification to the concentrator to detect whether the grouting will affect the grinding of the concentrator, and determining the type, proportion and early strength agent of the grouting material based on the results.
8. The construction method of small pipe shed advance grouting combined with branch tunnel support for over-mining area and under-mine engineering according to claim 1 is characterized by: By weight ratio, in the grouting solution, the weight ratio of water to ultrafine binder is (0.5~0.8):1, the amount of the early strength agent added is 5~8% of the weight of the binder, the particle size of the binder is less than 800 mesh, the chloride ion content of the grouting solution is less than 0.06%, and the effective setting time is controlled within 7 days.
9. The construction method of small pipe shed advance grouting combined with branch tunnel support suitable for over-mining area and under-mine engineering according to claim 1 is characterized by: In step S5, the secondary support work refers to the immediate processing of pumice and spraying after the arch area is completely opened, with a thickness of 30 to 50 mm, followed by hanging of metal mesh, erection of arch rings, welding of threaded steel bars between the arch rings, and finally locking of the arch rings.
10. The construction method of small pipe shed advance grouting combined with branch tunneling support applicable to the mining area crossing project according to claim 1 is characterized in that: The supplementary reinforcement refers to secondary shotcrete support after the tunnel bottom is completed, with concrete grade C20 and a shotcrete layer thickness of 100~150mm.