Step length refinement method for arch dam construction simulation
The multi-sensing and CEEMDAN-Transformer-BiLSTM combination model is used to predict the single cycle time of the cable hoist, which solves the problem of uncertainty factors in the arch dam construction simulation in the existing technology, and realizes the prediction of the cable crane in units of strips/blasts/pouring blocks. The arch dam construction simulation step length is refined, which improves simulation accuracy and real-time control capabilities.
Patent Information
- Application Number
- CN202411090790.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-08-09
AI Technical Summary
Existing arch dam construction simulation technology is difficult to capture the nonlinear and random fluctuation characteristics of uncertain factors such as topographic and geological conditions, construction technology, worker proficiency, and weather, resulting in deviations between simulation analysis results and actual construction progress, and is based on warehouses. The calculation method leads to the accumulation of simulation deviations, affecting real-time precise control.
Use multi-sensing technology to monitor the operating status of the cable machine, integrate multiple monitoring data characteristics, establish a cable machine pattern recognition method, and predict the single cycle time of the cable machine using the CEEMDAN-Transformer-BiLSTM combination model to achieve strip/blast/pouring block unit Arch dam construction simulation step size refinement.
Through multi-sensing and combined prediction models, we can accurately extract the single cycle duration of the cable hoist, reduce the complexity of data features, achieve multi-step prediction, provide multiple optional event step lengths, improve the accuracy of arch dam construction simulation, and support real-time precise control.
Smart Images

Figure CN118627397B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of arch dam construction simulation, and relates to a method for refining the step length of an arch dam construction simulation, and in particular to a method for refining the step length of an arch dam construction simulation based on multi-sensing and real-time prediction. Background Art
[0002] As an effective means of organizing and arranging construction projects and controlling progress in real time, construction simulation technology has been widely used in arch dam construction management. Practice has found that arch dam construction is affected by many uncertain factors such as topographic and geological conditions, construction technology, worker proficiency, and weather. It is difficult to capture the nonlinear and random fluctuation characteristics of simulation parameters using construction simulation parameter calculation and update methods such as engineering experience, probability statistics, and Bayesian updating, resulting in deviations between simulation analysis results and actual construction progress. Even if it is proposed to use machine learning algorithms to predict simulation construction parameters based on engineering data, the prediction accuracy needs to be further improved because the information characteristics of influencing factors are ignored during data preparation, and the arithmetic average is calculated in days. In addition, in the current arch dam construction simulation, the pouring duration is calculated in bins as the simulation step length, and then the construction simulation parameters are dynamically updated at an average monthly or weekly frequency, which makes the simulation deviation gradually accumulate from the bin level to the weekly or monthly level before being corrected, which is obviously not conducive to the real-time and accurate control of the arch dam construction progress. Summary of the invention
[0003] In order to solve the above technical problems existing in the background technology, the present invention provides a method that can realize the integration of multiple perception means and data, accurately and efficiently extract the single cycle duration of the cable crane, and establish a CEEMDAN-Transformer-BiLSTM combined model to predict the single cycle duration of the cable crane. It can be constructed according to the actual cable crane "strip method" to realize the arch dam construction simulation step refinement method with strips / germ layers / casting blocks as unit steps and refine the arch dam construction simulation advancement process.
[0004] In order to achieve the above object, the present invention adopts the following technical solution:
[0005] A method for refining the step length of an arch dam construction simulation, characterized in that the method comprises the following steps:
[0006] 1) Multivariate sensing technology is used to monitor the operation status of the cable crane during arch dam construction, and the multivariate monitoring data features are integrated to establish a cable crane pattern recognition method, and the cable crane single cycle duration is extracted using the cable crane pattern recognition method;
[0007] 2) Performing modal decomposition on the cable car single cycle duration obtained in step 1), together with the multivariate monitoring data obtained in step 1), to form a multi-feature time series data set, and dividing the multi-feature time series data set into a training set of the prediction model and a test set of the prediction model in a ratio of 9:1;
[0008] 3) Based on Transformer-Encoder, the BiLSTM network is integrated to form a combined prediction model; the training set of the prediction model in step 2) is substituted into the combined prediction model using the sliding window method, hyperparameters are selected to train the combined prediction model, and the accuracy is tested using the test set of the prediction model until the prediction accuracy that meets the engineering requirements is achieved, and the combined prediction model with determined hyperparameters is obtained;
[0009] 4) Obtain the actual cable crane single cycle duration during the pouring construction process in the manner of step 1), and obtain the multi-feature time series data set of the actual cable crane during the pouring construction process in the manner of step 2); Use the combined prediction model determined by the hyperparameters obtained in step 3) to perform multi-step prediction on the actual cable crane single cycle duration during the pouring construction process to obtain the prediction result;
[0010] 5) Based on the prediction results obtained in step 4), a simulation clock advancement mechanism with strip / embryo / casting block as unit step length is designed to complete the refinement of the simulation step length of arch dam construction.
[0011] Preferably, the multi-sensing in step 1) adopted in the present invention includes: a lifting weight monitor installed on the cable crane hook, a high-precision GPS installed on the main moving parts of the cable crane, a high-resolution camera set up near the cable crane feeding platform and an all-weather integrated meteorological monitoring station configured at the arch dam construction site, wherein the main moving parts are a trolley, a small car and a hanging tank.
[0012] Preferably, the method for extracting the single cycle duration of the cable car in step 1) adopted in the present invention is: first, detect whether there is a hanging tank on the hook based on the video data of multivariate monitoring, and if so, distinguish the working stages based on the characteristic differences of the combination of multivariate monitoring data, and aggregate the duration of each working stage to form a single cycle duration; the multivariate monitoring data includes the lifting weight, X coordinate and Z coordinate.
[0013] Preferably, step 2) of the present invention is to use CEEMDAN algorithm to decompose the cable car single cycle duration, and form a multi-feature time series data set with the multivariate monitoring data that affects the cable car single cycle duration in step 1).
[0014] Preferably, the prediction in step 3) of the present invention is to determine the combined prediction model of hyperparameters to simultaneously extract multi-factor correlation features and contextual time series features from the multi-feature time series data set of the actual cable crane during the pouring construction process, and use a sliding window to achieve multi-step prediction.
[0015] Preferably, the specific implementation method of the sliding window used in the present invention to realize multi-step prediction is: using the previous x feature data at each time point, after prediction y target data at each time point, where x is the size of the sliding window, y is the step size of the sliding window; x According to the size of the casting block, a cable casting cycle that can fully cover the entire casting block is selected; y A casting cycle that can cover one embryonic layer; preferably, the x =96, y =20.
[0016] Preferably, the specific implementation method of step 5) adopted by the present invention is: extract the first N cable machine single cycle durations from the prediction results, then calculate the pouring duration of the next strip, the next embryonic layer or the next pouring block, and provide a variety of optional event steps to advance the simulation clock of the arch dam construction simulation; the N is related to the size of the above sliding window x The values are consistent.
[0017] Preferably, the method for calculating the pouring duration of the next strip adopted in the present invention is: in the arch dam construction simulation modeling, after each strip pouring is completed and before the next strip pouring is started, the single cycle duration of the first N rounds of cable crane pouring concrete is extracted from the multivariate perception module, and the combined prediction model with determined hyperparameters is used to predict the step length of the next sliding window. y ; Assume that the current completion is i Strip, then i The pouring duration of +1 strip is:
[0018] ,
[0019] in:
[0020] Cyc t It represents the predicted duration of each cable machine single cycle of the next belt, where t ∈[1 ,M ];
[0021] M For the i +1 total number of pouring cycles for strip, M The value does not exceed the step size of the above sliding window y, M The calculation method is:
[0022] ,
[0023] in:
[0024] b is the strip width, obtained according to the cable crane station planning;
[0025] l is the length of the strip, obtained from the geometric information of the cast block;
[0026] h is the thickness of the germ layer, and its value is 50cm;
[0027] q is the capacity of the concrete hanging tank;
[0028] by Advance the simulation clock of the arch dam construction simulation as the step length for the next strip concreting event.
[0029] Preferably, the method for calculating the pouring duration of the next embryonic layer used in the present invention is: in the arch dam construction simulation modeling, after each embryonic layer is completed and before the next embryonic layer is poured, the pouring duration calculation method of the next strip is used to predict the pouring time of the first strip of the next embryonic layer. , and then calculate the entire pouring time of the next germ layer: , the entire pouring time of the next embryonic layer is used as the step length of the next embryonic layer concrete pouring event to advance the simulation clock of the arch dam construction simulation; among them, T 大车 It is the time it takes for the cable car to move horizontally once. I is the total number of bands in the next germ layer.
[0030] Preferably, the method for calculating the pouring duration of the next pouring block used in the present invention is: in the arch dam construction simulation modeling, each time the cable crane completes pouring of a pouring block, before pouring the next pouring block; the method for calculating the pouring duration of the next strip is used to predict the pouring time of the first strip of the first germ layer of the next pouring block. , further calculate the pouring time of the first germ layer: , and the time it takes for each cable crane to complete the pouring of all embryonic layers: , select the longest pouring time as the pouring duration of the next pouring block: , the pouring duration of the next pouring block is used as the step length of the next pouring block concrete pouring event, and the simulation clock of the arch dam construction simulation is advanced; where: J Indicates the total number of germ layers for the next casting block. CC nRepresents the nth cable machine.
[0031] The advantages of the present invention are:
[0032] The present invention provides a method for refining the step length of arch dam construction simulation, including: 1) using multi-sensing means to overcome the limitations of a single sensor and avoid the phenomenon of "feeling but knowing little", integrating the cable crane pattern recognition method established by multi-sensing data features, and accurately and efficiently extracting the single-cycle duration data of the cable crane from the massive multi-sensing data, providing a data basis for subsequent real-time prediction. 2) The designed combined prediction model, on the one hand, uses the CEEMDAN algorithm to reduce the feature complexity of the single-cycle duration data of the cable crane; on the other hand, uses the Transformer-Encoder and BiLSTM combined model to simultaneously extract the multi-factor correlation and contextual time series features of the multi-feature time series; at the same time, a linear layer is used to realize the multi-step prediction of the single-cycle duration of the cable crane. 3) Combined with the actual cable crane "strip method" construction design, the arch dam construction simulation clock advancement mechanism with strip / embryo / casting block as the unit step length provides multiple selectable event step lengths for arch dam construction simulation modeling, and the appropriate step length unit can be selected according to the accuracy requirements of the simulation calculation and the usage scenario. The present invention can extract and predict the single-cycle duration of the cable crane by combining the multivariate monitoring data of the project itself, and refine the simulation step length according to the actual cable crane casting process, so as to realize the refined modeling of arch dam construction simulation. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is a multivariate monitoring data diagram of the cable crane in different working states in the concrete lifting mode of the present invention;
[0034] Figure 2 It is a flow chart of the implementation of modal decomposition using the CEEMDAN algorithm of the present invention;
[0035] Figure 3 It is the overall structure diagram of the multi-step combined prediction model of the present invention;
[0036] Figure 4 It is a schematic diagram of the actual cable machine "strip method" construction process of the present invention;
[0037] Figure 5 It is a corresponding relationship diagram of calculating the strip casting duration using the prediction results of the present invention. DETAILED DESCRIPTION
[0038] The principle of the present invention is: first, integrate multiple monitoring means and data, establish a cable crane pattern recognition method, and extract the single cycle duration of the cable crane; then, use the combined CEEMDAN-Transformer-BiLSTM prediction model to train and predict the single cycle duration data of the cable crane that integrates multiple factors; finally, according to the "strip method" of the cable crane, extract the multi-step prediction results, calculate the pouring duration of the next strip / germ layer / casting block, and use it as the event step to advance the simulation clock of the arch dam construction simulation. Specifically, the present invention provides a method for refining the step length of arch dam construction simulation, including the following steps:
[0039] Step 1: Use multivariate sensing technology to monitor the operation status of the cable crane during dam construction, integrate the multivariate monitoring data features, establish a cable crane pattern recognition method, and accurately and efficiently extract the single cycle duration of the cable crane from massive monitoring data;
[0040] The multiple sensing methods include: 1) a lifting capacity monitor installed on the cable crane hook; 2) a high-precision GPS installed on the main moving parts of the cable crane (trolley, trolley and hanging tank); 3) a high-resolution camera set up near the cable crane feeding platform; 4) an all-weather integrated meteorological monitoring station configured at the arch dam construction site, etc.
[0041] The fusion of multi-dimensional monitoring data features includes: mechanical and physical information obtained by the lifting weight monitor, three-dimensional spatial information obtained by real-time positioning monitoring, and semantic information of the construction process recorded by high-definition cameras. The fusion of multi-dimensional monitoring data features, specific implementation steps:
[0042] 1) Taking the time frequency and time point of positioning monitoring as the basic time scale, other monitoring data are unified to the corresponding time scale through interval interpolation;
[0043] 2) Preprocessing of cable crane multivariate monitoring data: Map the three-dimensional spatial data to the engineering coordinate system through projection transformation to enhance the readability of positioning monitoring data; remove outliers in the multivariate monitoring data, including the situation where the elevation data in the positioning data is lower than the elevation of the arch dam foundation surface and the abnormal hoisting value in the hoisting data; delete time duplicate data; use spline interpolation to fill missing values; mark the hoisting objects of the cable crane in the image data;
[0044] 3) Wavelet adaptive threshold denoising is selected according to the interval correlation of the hoisting weight, and soft threshold denoising is performed only on the hoisting weight data of the two trips in the cable crane hoisting concrete pouring working mode;
[0045] 4) Perform first-order difference on the lifting weight (W) data and the X and Z data of the positioning coordinates in the multivariate monitoring data to calculate the change values of the lifting weight and the hanging tank position over time;
[0046] 5) Select the multivariate monitoring data of the cable crane in the concrete lifting mode to draw a scatter plot, analyze the multivariate data characteristics under different working states, and construct the sample characteristics of the cable crane in the concrete lifting mode.
[0047] In this way, the single cycle duration of the cable crane is extracted. The multivariate monitoring data of different working states in the cable crane concrete lifting mode have different data characteristics. First, it is detected whether there is a hanging tank on the hook based on the video data, so as to exclude the working conditions other than lifting concrete. Then, the working stages are distinguished according to the characteristic differences of the combination of multivariate monitoring data such as lifting weight, X coordinate, and Z coordinate. The duration of each working stage is aggregated to form the single cycle duration.
[0048] The working states of the cable crane in the concrete lifting mode mainly include: waiting state, forward state, alignment state, unloading state, and return state. The waiting state can be subdivided into waiting for the car state and loading state, the forward state can be divided into lifting state and full tank transportation state, and the return state can also be subdivided into empty tank transportation state and return state. The return state includes platform alignment and descending. Therefore, each time the cable crane completes a round of concrete lifting, it will go through 9 working state changes. The multivariate monitoring data under different working states are as follows: Figure 1 In the cable crane concrete lifting mode, the multivariate monitoring data of different working states have different data characteristics. The following table describes a typical cable crane concrete lifting cycle and the multivariate monitoring data characteristics of each working state:
[0049]
[0050] Step 2: Use the CEEMDAN algorithm to decompose the single cycle duration data of the cable machine, consider multiple main influencing factors to construct multi-feature time series data, and divide the training set and test set of the prediction model into 9:1;
[0051] Data preprocessing is performed using the CEEMDAN algorithm. CEEMDAN (Completely Adaptive Noise Ensemble Empirical Mode Decomposition) is an improved method based on EMD (Empirical Mode Decomposition) that adds specific Gaussian noise and cancels out the noise through multiple superpositions and averages to reduce the modal aliasing problem of the EMD algorithm. Using the CEEMDAN algorithm to perform modal decomposition on the extracted cable car single cycle duration data can reduce the complexity of data feature information, facilitate the subsequent prediction model to extract feature information through machine learning, and improve the accuracy of prediction.
[0052] The CEEMDAN algorithm is used to decompose the single cycle duration data of the cable car. The specific steps are as follows: Figure 2 As shown. Represents the cable car single cycle duration data set, is the EMD decompositionj modal components, For the first i Satisfaction Distributed white noise.
[0053] 1) Add positive and negative pairs of Gaussian white noise to the original data In, get . Perform the first round of EMD decomposition, take the first modal component of each EMD decomposition and add and average to get the first eigenmodal component:
[0054] ;
[0055] 2) Calculate the residual term of the first round of decomposition:
[0056] ;
[0057] 3) Add the positive and negative paired Gaussian white noise to the residual term of the previous round, and perform the second round of EMD decomposition. Similarly, take the first modal component of each EMD decomposition and add and average to obtain the second eigenmodal component:
[0058] ;
[0059] 4) Calculate the residual term of the second round of decomposition:
[0060] ;
[0061] 5) Repeat the above steps until the residual term is monotonic or fixed in time, and then stop decomposing. Decompose into K The eigenmode components and the residual term .
[0062] .
[0063] The steps for constructing a multi-feature time series and dividing it into training and test sets in proportion are as follows:
[0064] 1) According to the time point, space and other information of the cable crane single cycle duration data in step 1, query the arch dam pouring construction records and historical weather data, and match the position information, labor information (workers and working hours), weather information (temperature, rainfall intensity, U Direction breakdown of wind speed, V Direction decomposition of wind speed, etc.), a total of 7 different dimensions of information features;
[0065] 2) Using the above CEEMDAN algorithm to decompose the single cycle time of the cable machine, we can get KThe single cycle duration component of the cable machine, where the calculation parameters are set as: number of iterations = 100, convergence speed (signal-to-noise ratio) = 0.005;
[0066] 3) Combine the cable machine single cycle time with the above steps 1) and 2) to form 1+7+ K Time series data with dimensional features;
[0067] 4) According to the data length, the training set and test set are divided into 9:1.
[0068] Step 3: Based on the Transformer-Encoder, the BiLSTM network is integrated to form a combined prediction model, which simultaneously extracts multi-factor correlation features and contextual time series features from multi-feature time series, and uses a sliding window to achieve multi-step prediction.
[0069] Based on Transformer-Encoder, BiLSTM network is integrated to form a combined prediction model. Affected by various uncertain factors such as casting block location, manual operation, weather, etc., the single cycle time of the cable crane is nonlinear and randomly fluctuates. The multi-head self-attention mechanism in the Transformer-Encoder model can extract the correlation characteristics between multiple factors and the single cycle time of the cable crane; in addition, the cable crane adopts the "strip method" casting construction. After completing the casting of one strip, it enters the next strip until the casting of a germ layer is completed, and then continues to cast strips one by one until all germ layers of a casting block are completed, and then transfers to the next casting block, and so on. Therefore, the single cycle time of the cable crane has certain periodic change characteristics between the strip, germ layer and casting block. The purpose of integrating BiLSTM network is to further extract the time series characteristics of the periodic change of the single cycle time of the cable crane between the strip, germ layer and casting block, and improve the prediction model's ability to capture the stage change time point during the casting process of the cable crane; finally, the fully connected layer is used to calculate the single cycle time of multiple cable cranes in the future to achieve multi-step prediction.
[0070] The combined prediction model uses the position encoder in the Transformer-Encoder to record the time series information of the multi-feature time series of the cable machine single cycle duration constructed in step 2; and uses a multi-head self-attention mechanism to extract the multi-factor and time correlation of the multi-feature time series constructed in step 2. Furthermore, the output of the Transformer-Encoder is sent to the BiLSTM network to improve the model's capture of the contextual temporal feature information. Finally, through a fully connected layer, a linear connection is established between the BiLSTM network output result and the predicted value to achieve multi-step prediction of the multi-feature cable machine single cycle duration. The structure of the combined prediction model is as follows: Figure 3 As shown, IMFs Indicates mode 1 to mode m, ht It is a bidirectional long short-term memory model. t The hidden layer state at time instant, where the superscript “→” indicates forward direction and “←” indicates reverse direction.
[0071] Position encoder, the calculation formula is as follows:
[0072] ,
[0073] ,
[0074] In the formula, POS is the position of the time series, i is the result of dividing the feature vector dimension index by 2. d is the feature dimension.
[0075] Furthermore, the calculation formula of the multi-head self-attention mechanism is as follows:
[0076] ,
[0077] In the formula, Q is the query vector; V is a value vector; In d k is the key vector K The dimension is used to reduce the risk of gradient explosion and gradient vanishing of the similarity score.
[0078] Use sliding windows to achieve multi-step predictions and use the previous x feature data at each time point, after prediction y The target data at each time point, the specific data correspondence is as follows Figure 5 As shown. Among them, x is the size of the sliding window, y is the step length of the sliding window. Further, the sliding window is used to extract the input data and label data required for prediction model training and testing from the training set and test set in step 2). For example, the length of the entire multi-feature cable machine single cycle duration data is L , the feature dimension is 1+7+ K , distributed proportionally, the data length of the test set is 0.9 L , then the format of the training input data extracted by the sliding window is (“|” indicates integer division), the format of the training target data is .
[0079] Sliding window size xIn the present invention, the value is 96, which can be selected according to the size of the casting block in actual application, so as to fully cover the cable casting cycle of the entire casting block. y In the present invention, the value is 20, which is also suitable for a casting cycle that can cover one embryonic layer.
[0080] Step 4: Substitute the training set in step 2 into the combined prediction model in step 3), select appropriate hyperparameters for model training, and perform accuracy test on the test set until the prediction accuracy that meets the engineering requirements is achieved, and obtain the combined prediction model with determined hyperparameters;
[0081] Hyperparameters include the number of heads and feature mapping dimensions of the multi-head self-attention mechanism, the size of each batch of training data, the number of hidden layers of the BiLSTM network, the default training rounds, the choice of optimizer for back-propagation loss value calculation, and the learning rate.
[0082] The prediction model hyperparameters are selected as follows in the present invention: a two-head self-attention mechanism is used to train the input 7+ K The dimension feature is mapped to 64 dimensions; the batch size is 256, then the data input for each batch of training is ; The number of hidden layers of BiLSTM is 128, and the data output after one forward LSTM and one reverse LSTM is The default number of training rounds is 50, with Adam as the optimizer and the learning rate set to 0.0005.
[0083] Step 5: According to the actual cable crane "strip method" pouring construction process, in the arch dam construction simulation modeling, the combined prediction model for determining the hyperparameters obtained in step 4) is used for prediction to obtain the prediction results. According to the prediction results, a simulation clock advancement mechanism with strips / germ layers / casting blocks as unit steps is designed. The arch dam construction simulation model is developed based on the principle of discrete event system and adopts an event step simulation clock system, that is, the simulation clock is advanced according to the time to complete an event until all discrete events are completed and the simulation clock advancement ends.
[0084] According to the actual cable crane "strip method" construction, the predicted multi-step single cycle duration is converted into the simulation step length of the arch dam pouring activity construction simulation. The conversion method is: arch dams often use multiple cable cranes to cast dam blocks in strips and germ layers. The cable crane "strip method" construction process is as follows Figure 4 shown. CC 1 ~ CC 3 They represent the casting range of No. 1 to No. 3 cable cranes respectively. ly 1 ~ ly 6 Indicates the casting layer. str 1~ str 3 represents the casting strip. Then, t The time step corresponds to n Cableway pouring j green layer i Striped m The round cycle time can be expressed as: , abbreviated as , and the prediction results obtained by the prediction model There is a corresponding relationship: .
[0085] Assuming the total number of cable cranes is N, the number of layers of the casting block is J , the number of strips within the casting range of a cable crane is I The total casting cycle of the strip is M . t Time is complete m round of pouring, then the remaining pouring cycle for the strip is Mm Round. The prediction results output from the prediction model y Extract in order before Mm The remaining pouring time of the strip is The corresponding relationship between the prediction result and the strip casting time is as follows: Figure 5 As shown. m Casting cycle time ,in is the actual cable machine single cycle time. i The pouring duration is:
[0086] ,
[0087] According to the cable machine strip casting process, after a single cable machine completes the casting of a strip, it will transfer to the casting of the next strip through the trolley. After the casting of the billet layer is completed, the trolley will be moved horizontally to the starting strip of the next billet layer. Therefore, for a total number of strips I The layer j , its pouring duration:
[0088] ,
[0089] In the formula, represents the total time of the trolley shifting, and the trolley shifting time can be simulated by Monte Carlo. Then, for n The time it takes for the No. cable car to complete the pouring of this pouring block is:
[0090] ,
[0091] Due to the differences in the pouring range, operators and task list composition of each cable crane, the pouring time of each cable crane is different. The pouring time of the last cable crane to complete pouring is taken as the pouring time of this warehouse: ,So t The remaining pouring duration of this warehouse at this moment is:
[0092] ,
[0093] The designed simulation clock uses strips / embryo layers / casting blocks as unit steps to advance the arch dam construction simulation. The method is as follows: when the strip is used as the unit step, that is, in the arch dam construction simulation modeling, after each strip is poured by the cable crane, before the next strip is poured, the single cycle duration of the previous N rounds of cable crane pouring concrete is extracted from the multi-sensing module, and the next single cycle duration is predicted by the real-time prediction model. y The length of a single cycle of the cable car. Assume that the i Strip, then i The pouring duration of +1 strip is:
[0094] ,
[0095] In the formula, M For the i +1 total number of pouring cycles for strip, M The value does not exceed the step size of the above sliding window y , can be calculated according to the following formula:
[0096] ,
[0097] In the formula, b is the strip width, which can be obtained according to the cable crane station planning; l is the length of the strip, which can be obtained from the geometric information of the cast block; h is the thickness of the germ layer, and its value is 50cm; q is the capacity of the concrete hanging tank.
[0098] The current arch dam construction simulation model is generally based on the principle of discrete event system, and mostly adopts the event step simulation clock system. Then the simulation clock advancement mechanism with strip as the unit step is based on multi-sensing and real-time prediction to calculate the pouring duration of the next strip. , as the step length of the next strip concrete pouring event, advancing the simulation clock of the arch dam construction simulation.
[0099] Taking the embryonic layer as the unit step length, the simulation clock of arch dam construction is recommended. That is, in the simulation modeling of arch dam construction, after the cable crane completes the pouring of one embryonic layer and enters the next embryonic layer, the above strip pouring duration calculation method is first used to predict the pouring time of the first strip of the next embryonic layer. , and then calculate the entire pouring time of the next germ layer through the above conversion method: , taking it as the step length of the next embryonic layer concrete pouring event, advancing the simulation clock of the arch dam construction simulation.
[0100] Taking the casting block as the unit step length, the simulation clock of arch dam construction is recommended. That is, in the simulation modeling of arch dam construction, after the cable crane completes the casting of a casting block, it is planned to cast the next casting block. The same calculation method of strip casting duration is used to predict the casting time of the first strip of the first germ layer of the next casting block. , further calculate the pouring time of the first germ layer: , and the time it takes for each cable crane to complete the pouring of all embryonic layers: , select the longest pouring time as the pouring duration of the next pouring block: , taking it as the step size of the next pouring block concrete pouring event, advancing the simulation clock of the arch dam construction simulation.
Claims
1. A method for refining step length of arch dam construction simulation, characterized in that: The arch dam construction simulation step length refinement method comprises the following steps: 1) Multivariate sensing technology is used to monitor the operation status of the cable crane during arch dam construction, and the multivariate monitoring data features are integrated to establish a cable crane pattern recognition method, and the cable crane single cycle duration is extracted using the cable crane pattern recognition method; 2) Performing modal decomposition on the cable car single cycle duration obtained in step 1), together with the multivariate monitoring data obtained in step 1), to form a multi-feature time series data set, and dividing the multi-feature time series data set into a training set of the prediction model and a test set of the prediction model in a ratio of 9:1; 3) Based on Transformer-Encoder, the BiLSTM network is integrated to form a combined prediction model; the training set of the prediction model in step 2) is substituted into the combined prediction model using the sliding window method, hyperparameters are selected to train the combined prediction model, and the accuracy is tested using the test set of the prediction model until the prediction accuracy that meets the engineering requirements is achieved, and the combined prediction model with determined hyperparameters is obtained; 4) Obtain the actual cable crane single cycle duration during the pouring construction process in the manner of step 1), and obtain the multi-feature time series data set of the actual cable crane during the pouring construction process in the manner of step 2); Use the combined prediction model determined by the hyperparameters obtained in step 3) to perform multi-step prediction on the actual cable crane single cycle duration during the pouring construction process to obtain the prediction result; The specific implementation method of the multi-step prediction is: x feature data at each time point, after prediction y target data at each time point, where x is the size of the sliding window, y is the step size of the sliding window; x According to the size of the casting block, a cable casting cycle that can fully cover the entire casting block is selected; y A casting cycle capable of covering one germ layer; x =96, y =20; 5) According to the prediction results obtained in step 4), a simulation clock advancement mechanism with strip / embryo / casting block as the unit step length is designed to complete the refinement of the simulation step length of arch dam construction; The specific implementation method of step 5) is: extract the first N cable machine single cycle durations from the prediction results, then calculate the pouring duration of the next strip, the next embryonic layer or the next pouring block, and provide a variety of optional event steps to advance the simulation clock of the arch dam construction simulation; N is related to the size of the sliding window x Keep the value consistent.
2. The method for refining the step length of arch dam construction simulation according to claim 1, characterized in that: The multi-sensing in step 1) includes: a lifting weight monitor installed on the cable crane hook, a high-precision GPS installed on the main moving parts of the cable crane, a high-resolution camera set up near the cable crane feeding platform, and an all-weather integrated meteorological monitoring station configured at the arch dam construction site. The main moving parts are large carts, small cars and hanging tanks.
3. The method for refining the step length of arch dam construction simulation according to claim 2, characterized in that: The method for extracting the single cycle duration of the cable crane in step 1) is: based on the multivariate monitoring video data, detect whether there is a hanging tank on the hook. If so, distinguish the working stages based on the characteristic differences of the multivariate monitoring data combination, and aggregate the duration of each working stage to form a single cycle duration; the multivariate monitoring data includes the lifting weight, X coordinate and Z coordinate.
4. The method for refining the step length of arch dam construction simulation according to claim 3 is characterized in that: The step 2) is to use the CEEMDAN algorithm to decompose the single cycle duration of the cable car, and to form a multi-feature time series data set with the multivariate monitoring data that affects the single cycle duration of the cable car in step 1).
5. The method for refining the step length of arch dam construction simulation according to claim 4, characterized in that: The method of performing multi-step prediction in step 4) is to simultaneously extract multi-factor correlation features and contextual time series features from the actual cable car single cycle duration data, and implement multi-step prediction by using a sliding window method.
6. The method for refining the step length of arch dam construction simulation according to claim 5, characterized in that: The calculation method of the pouring duration of the next strip is as follows: in the arch dam construction simulation modeling, after each strip pouring is completed and before the next strip pouring begins, the single cycle duration of the first N rounds of cable crane pouring concrete is extracted from the multivariate perception module, and the combined prediction model with determined hyperparameters is used to predict the step length of the next sliding window. y ; Assume that the current completion is i Strip, then i The pouring duration of +1 strip is: ,in: Cyc t It represents the predicted duration of each cable machine single cycle of the next belt, where t ∈[1, M ]; M For the i +1 total number of pouring cycles for strip, M ≤20, M The calculation method is: ,in: b is the strip width, obtained according to the cable crane station planning; l is the length of the strip, obtained from the geometric information of the cast block; h is the thickness of the germ layer, and its value is 50cm; q is the capacity of the concrete hanging tank; by Advance the simulation clock of the arch dam construction simulation as the step length for the next strip concreting event.
7. The method for refining the step length of arch dam construction simulation according to claim 6, characterized in that: The calculation method of the pouring duration of the next embryonic layer is as follows: in the arch dam construction simulation modeling, after each embryonic layer is completed and before the next embryonic layer is poured, the pouring duration calculation method of the next strip is used to predict the pouring time of the first strip of the next embryonic layer. , and then calculate the entire pouring time of the next germ layer: , the entire pouring time of the next embryonic layer is used as the step length of the next embryonic layer concrete pouring event to advance the simulation clock of the arch dam construction simulation; among them, T 大车 It is the time it takes for the cable car to move horizontally once. I is the total number of bands in the next germ layer.
8. The method for refining the step length of arch dam construction simulation according to claim 7, characterized in that: The calculation method of the pouring duration of the next pouring block is as follows: in the arch dam construction simulation modeling, each time the cable crane completes the pouring of a pouring block, before the next pouring block is to be poured; the calculation method of the pouring duration of the next strip is used to predict the pouring time of the first strip of the first germ layer of the next pouring block. , further calculate the pouring time of the first germ layer: , and the time it takes for each cable crane to complete the pouring of all embryonic layers: , select the longest pouring time as the pouring duration of the next pouring block: , the pouring duration of the next pouring block is used as the step length of the next pouring block concrete pouring event, and the simulation clock of the arch dam construction simulation is advanced; where: J Indicates the total number of germ layers for the next casting block. CC n Represents the nth cable machine.
Citation Information
Patent Citations
Self-adaptive simulation analysis method for construction progress of high arch dam
CN106484977A
Simulation modeling method for high arch dam two-bin combined pouring system
CN117195375A