A train control method, system, device and medium for reducing CTCS-3 level constant speed to CTCS-2 level

By adding low-frequency code sequences and modifying the tracking code sequence relationship, longer driving permission information is provided, which solves the problem of train deceleration and braking after the CTCS-3 level train control system is downgraded, and improves railway transportation efficiency.

CN118651280BActive Publication Date: 2024-10-29CRSC RESEARCH & DESIGN INSTITUTE GROUP CO LTD
View PDF 10 Cites 0 Cited by

Patent Information

Application Number
CN202411123994.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-10-29
Estimated Expiration
2044-08-16

AI Technical Summary

Technical Problem

When the CTCS-3 level train control system was downgraded to CTCS-2 level, due to the insufficient code sequence of the track circuit's maximum number of idle information for the seven blocked areas in front, the train slowed down and affected the driving efficiency and the transportation organization of the road network.

Method used

Add low-frequency code sequences through data configurable methods, modify the relationship definition of tracking code sequences to increase the number of free blocked partitions, provide longer driving permission information for trains, and add the second positive direction line provided in front of the transponder. The data is used as the starting point for braking, and the braking distance is calculated based on the modified tracking code sequence and the highest low-frequency code sequence to achieve constant speed degradation.

Benefits of technology

The braking distance is extended, the CTCS-3 train degradation and braking problems are solved, and the efficiency of railway transportation is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118651280B_ABST
    Figure CN118651280B_ABST
Patent Text Reader

Abstract

The present disclosure relates to a train control method, system, device and medium for downgrading a CTCS-3 level constant speed to a CTCS-2 level, the method comprising the following steps: obtaining the number of low-frequency code sequences to be added and the highest low-frequency code sequence of the track circuit; adding all the low-frequency code sequences to be added to the lower frequency side and / or higher frequency side of the existing low-frequency information, and modifying the relationship definition of the tracking code sequence to increase the number of idle block sections, providing longer driving permission information for the train; and obtaining the braking distance based on the modified tracking code sequence and the highest low-frequency code sequence. The present disclosure provides longer driving permission information to the train through the track circuit and the transponder, extends the braking distance, realizes the downgrading of CTCS-3 level constant speed to CTCS-2 level, solves the problems of downgrading and speed reduction of CTCS-3 level trains and braking caused by downgrading of CTCS-3 level trains, and improves the efficiency of railway transportation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the field of train control technology, and in particular, relates to a train control method, system, device and medium for downgrading a CTCS-3 level constant speed to a CTCS-2 level. Background Art

[0002] The CTCS-2 train control system is based on the track circuit and balise to transmit train driving permission information, and uses the target distance continuous speed control mode to monitor the safe operation of trains. It is suitable for 200km / h-250km / h speed-up trunk lines and passenger dedicated lines. As the ground core equipment of the CTCS-2 train control system, the train control center sends coded information to the track circuit, sends route parameter information to the active balise, and provides the train with the required operating permission based on the position of each train within its jurisdiction (track occupancy status), interlocking route, and line speed limit status.

[0003] The CTCS-3 train control system is a domestic train control system that is based on the CTCS-2 train control system and realizes two-way transmission of train-ground information based on GSM-R wireless communication and generates driving permits by the radio block center (RBC). The system uses advanced technical means to monitor the train running speed, running interval, etc. under high-speed conditions in real time and protect against overspeeding. It determines the train braking curve according to the target distance, target speed and the performance of the train itself in the target distance continuous speed control mode. The high-speed train operation control system standard system and technical platform are constructed, which are suitable for high-speed railways above 300km / h. The working principle of the system is: based on GSM-R wireless communication, two-way transmission of train-ground information is realized, the radio block center (RBC) generates driving permits, the track circuit realizes train occupancy inspection, the transponder realizes train positioning, and the on-board adopts the target-distance continuous speed control mode curve and equipment braking priority to monitor the safe operation of the train.

[0004] When a CTCS-3 train needs to be downgraded to a CTCS-2 train control system due to GSM-R failure, onboard equipment and RBC communication failure, etc., the CTCS-3 train control onboard equipment combines the remaining length of the CTCS-2 driving permit or the track circuit information, and determines the driving permit end point or outputs braking according to the current position of the train. Since the track circuit gives the information that the 7 block sections ahead are idle at most, the information code sequence is insufficient, resulting in the train running at a reduced speed. In extreme cases, the train braking is triggered, affecting the driving efficiency and the transportation organization of the network.

[0005] Therefore, it is necessary to provide a new CTCS-3 level constant speed downgrade to CTCS-2 level train control method, system, equipment and medium to solve the above technical problems. Summary of the invention

[0006] The purpose of the present disclosure is to provide a train control method, system, device and medium for downgrading CTCS-3 level to CTCS-2 level at a constant speed in order to solve the above-mentioned problems.

[0007] The present invention achieves the above-mentioned purpose through the following technical solutions:

[0008] A train control method for constant speed downgrading from CTCS-3 to CTCS-2 includes the following steps:

[0009] The number of low-frequency code sequences to be added and the highest low-frequency code sequence of the track circuit are obtained by using a data matching method;

[0010] Add all the low-frequency code sequences that need to be newly added to the lower frequency side and / or higher frequency side of the existing low-frequency information, and modify the relationship definition of the tracking code sequence to increase the number of idle block sections to provide longer driving permission information for the train;

[0011] The position of the second transponder group providing positive direction line data in front of the transponder is used as the braking starting point, and the braking distance is obtained based on the modified tracking code sequence and the highest low-frequency code sequence;

[0012] A constant speed downgrade is implemented based on the driving permission information and the braking distance.

[0013] As a further optimization solution of the present disclosure, the number of low-frequency code sequences to be added and the highest low-frequency code sequence of the track circuit are obtained in a data-matchable manner, including:

[0014] According to the engineering line design data, combined with the length of the track section within the line, the line slope and the train braking performance factors, through traction calculation simulation operation, it is calculated that when the allowable speed reaches 350km / h under CTCS-2 level, in the most unfavorable case, in order to meet the train's common braking distance requirements, the number of idle block sections ahead needs to be provided to the train, and then the number of low-frequency code sequences that need to be added is obtained in combination with the existing low-frequency information, thereby determining the highest low-frequency code sequence of the line; the most unfavorable case is the alternation of continuous long and large slopes, uphill sections, and downhill sections.

[0015] As a further optimization scheme of the present disclosure, the number of idle block sections ahead that need to be provided to the train is calculated, and then the number of low-frequency code sequences that need to be added is obtained by combining the existing low-frequency information, so as to determine the highest low-frequency code sequence of the line, including:

[0016] It is calculated that the number of idle block sections ahead that need to be provided to the train is N, N>7, and the highest low-frequency code sequence in the existing low-frequency information is L5, indicating that 7 block sections ahead of the train are idle. The number of low-frequency code sequences that need to be added is (N-7), and the highest low-frequency code sequence of the line is L(5+N-7), which is L(N-2).

[0017] As a further optimization scheme of the present disclosure, the position of the second transponder group providing positive direction line data in front of the transponder is taken as the braking starting point, and the braking distance is obtained based on the modified tracking code sequence and the highest low-frequency code sequence, including:

[0018] The position of the second balise group in front of the balise that provides positive line data is taken as the braking starting point. The braking length is consistent with the highest tracking code sequence design of the line. The highest low-frequency code sequence of the line is L (N-2). Combined with the tracking code sequence relationship, it takes (N+2) block sections to track from the HU code to the L (N-2) code. The braking distance is the length of the (N+2) block sections in front of the operation.

[0019] A train control system for constant speed downgrading from CTCS-3 to CTCS-2, comprising:

[0020] An acquisition module is used to obtain the number of low-frequency code sequences to be added and the highest low-frequency code sequence of the track circuit in a data-configurable manner;

[0021] A low-frequency code sequence adding module is used to add all the low-frequency code sequences that need to be newly added to the lower frequency side and / or higher frequency side of the existing low-frequency information, and modify the relationship definition of the tracking code sequence to increase the block section vacancy and provide longer driving permission information for the train;

[0022] A braking distance calculation module, used for taking the position of the second transponder group providing positive direction line data in front of the transponder as the braking starting point, and obtaining the braking distance based on the modified tracking code sequence and the highest low-frequency code sequence;

[0023] A constant speed degradation module is used to implement constant speed degradation based on the driving permission information and the braking distance.

[0024] As a further optimization solution of the present disclosure, the acquisition module uses a data configurable method to obtain the number of low-frequency code sequences to be added and the highest low-frequency code sequence of the track circuit, including:

[0025] The acquisition module calculates the number of idle block sections ahead that need to be provided to the train in the most unfavorable case to meet the train's common braking distance requirements when the permissible speed reaches 350 km / h under CTCS-2 level based on the engineering line design data, combined with the length of the track section in the line, the line slope and the train braking performance factors through traction calculation simulation operation, and then combines the existing low-frequency information to obtain the number of low-frequency code sequences that need to be added, thereby determining the highest low-frequency code sequence of the line; the most unfavorable case is that continuous long and large slopes, uphill sections and downhill sections appear alternately.

[0026] As a further optimization scheme of the present disclosure, the acquisition module calculates the number of idle block sections ahead that need to be provided to the train, and then combines the existing low-frequency information to obtain the number of low-frequency code sequences that need to be added, thereby determining that the highest low-frequency code sequence of the line includes:

[0027] The acquisition module calculates that the number of idle block sections ahead that need to be provided to the train is N, N>7, and the highest low-frequency code sequence in the existing low-frequency information is L5, indicating that 7 block sections ahead of the train are idle, and the number of low-frequency code sequences that need to be added is (N-7). The highest low-frequency code sequence of the line is L(5+N-7), that is, L(N-2).

[0028] As a further optimization scheme of the present disclosure, the braking distance calculation module takes the position of the second transponder group providing positive direction line data in front of the transponder as the braking starting point, and obtains the braking distance based on the modified tracking code sequence and the highest low-frequency code sequence, including:

[0029] The braking distance calculation module takes the position of the second balise group providing positive direction line data in front of the balise as the braking starting point, and the braking length is consistent with the highest tracking code sequence design of the line, wherein the highest low-frequency code sequence of the line is L (N-2). Combined with the tracking code sequence relationship, it takes (N+2) block sections to track from the HU code to the L (N-2) code, and the braking distance is the length of the (N+2) block sections in front of the operation.

[0030] An electronic device comprises a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory communicate with each other via the communication bus;

[0031] Memory, for storing computer programs;

[0032] The processor is used to implement the train control method of CTCS-3 level constant speed downgrading to CTCS-2 level when executing the program stored in the memory.

[0033] A computer-readable storage medium stores a computer program, which, when executed by a processor, implements the train control method of CTCS-3 level constant speed downgrade to CTCS-2 level.

[0034] The beneficial effects of the present disclosure are:

[0035] The present invention provides longer driving permission information to the train through the track circuit and the transponder, prolongs the braking distance, realizes the constant speed downgrade of CTCS-3 to CTCS-2, solves the problem of downgrading and speed reduction of CTCS-3 trains and braking caused by downgrading of CTCS-3 trains, and improves the efficiency of railway transportation. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 is a flow chart of the method disclosed herein;

[0037] Figure 2 It is a schematic diagram of the maximum range of the balise data in the CTCS-2 level of the prior art disclosed in the present invention, which is designed according to the second balise group in front of the train that provides the positive direction line data and then extends the 300km / h common braking.

[0038] Figure 3 It is a schematic diagram of the maximum range of the balise data, which is designed by downgrading the CTCS-3 level to CTCS-2 at a constant speed in the embodiment of the present disclosure, and extending the second balise group in front of the train that provides the line data in the positive direction by 350 km / h for common braking;

[0039] Figure 4 is a system structure block diagram in an embodiment of the present disclosure;

[0040] Figure 5 It is a block diagram of the device structure in an embodiment of the present disclosure. DETAILED DESCRIPTION

[0041] The present application is further described in detail below in conjunction with the accompanying drawings. It is necessary to point out here that the following specific implementation methods are only used to further illustrate the present application and cannot be understood as limiting the scope of protection of the present application. Technical personnel in this field can make some non-essential improvements and adjustments to the present application based on the above application content.

[0042] The CTCS-2 level train control system is a train control system that transmits train driving permission information based on track circuits and balises, and uses a target distance continuous speed control mode to monitor the safe operation of trains.

[0043] Track circuit: realize the section occupancy check of the train; provide the number of free block sections ahead of the train; provide continuous driving permission (Movement Authority, referred to as MA). According to the Definition and Allocation of Locomotive Signal Information (TB / T3060-2016), the allocation of low-frequency information of the existing ZPW-2000 standard track circuit is shown in Table 1.

[0044] Table 1 ZPW-2000 low frequency information distribution

[0045]

[0046] The definition of track circuit low-frequency coding information is as follows:

[0047] H: Disaster / earthquake occurs;

[0048] HU: indicates that the block section ahead of the train is occupied;

[0049] U: Indicates that a block section ahead of the train is free, or the train lights up the U light to start at a semi-automatic exit.

[0050] LU: Indicates that the two block sections ahead of the train are free

[0051] L: Indicates that the three block sections ahead of the train are free

[0052] L2: Indicates that the 4 block sections ahead of the train are free

[0053] L3: Indicates that the 5 block sections ahead of the train are free

[0054] L4: Indicates that the 6 block sections ahead of the train are free

[0055] L5: Indicates that at least 7 block sections are free ahead of the train.

[0056] UU: Indicates that the train is running at the UU light at the station ahead or the train is departing from the siding below No. 18 (check the speed limit and other conditions in the following instructions).

[0057] UUS: Indicates that the train is running with the USU light at the station ahead or the train is departing on the siding of turnout No. 18 and above (see the subsequent instructions for speed limit and other conditions).

[0058] U2: Indicates that the block section ahead of the train is idle and the UU code is sent

[0059] U2S: Indicates that the block section ahead of the train is idle and the UUS code is sent

[0060] HB: indicates that the train is running ahead of the open route guidance signal

[0061] JC: If a block section in the section is occupied, JC is sent at the rear, and the switch area in the station sends JC code by default

[0062] SP: Frequency switching

[0063] As the ground core equipment of the CTCS-2 and CTCS-3 train control systems, the train control center sends coded information to the track circuit, sends route parameter information to the active transponder, and provides the train with the required operating permission based on the position of each train within its jurisdiction (track occupancy status), interlocking route, and line speed limit status. The train control center controls the low-frequency coding of the track circuit equipment according to the route conditions and the status of the section ahead, and the highest low-frequency code sequence is L5. The train control center exchanges boundary low-frequency information and tracks the code sequence according to the highest low-frequency code sequence L5 between stations; the highest low-frequency code sequence sent by the train control center to the track circuit equipment is L5. According to the definition requirements of the section tracking code sequence, the train can be given information that up to 8 block sections ahead are idle. The tracking code sequence is defined as follows:

[0064] H<—HU<—U<—LU<—L<—L2<—L3<—L4<—L5<—L5;

[0065] JC<—HU<—U<—LU<—L<—L2<—L3<—L4<—L5<—L5;

[0066] HB<—U<—LU<—L<—L2<—L3<—L4<—L5<—L6<—L5;

[0067] UU<—U2<—LU<—L<—L2<—L3<—L4<—L5<—L6<—L5;

[0068] UUS<—U2S<—LU<—L<—L2<—L3<—L4<—L5<—L5.

[0069] Balise: Active balises provide temporary speed limits and route status information; passive balises provide information such as line allowable speed and block section length. The principles and contents of balise messages are within the scope of the prior art. Therefore, in order to prevent confusion with the product of the present invention, the above principles and contents will not be described in detail. (Q / CR 769-2020, Technical Requirements for the Application of Balises in Train Control Systems)

[0070] The existing CTCS-2 train control system is designed according to the maximum operating speed of 300km / h. When running in the forward direction, the ground balise group provides the train with the running line data range ahead. The track section information package [CTCS-1], speed information package [ETCS-27] and slope information package [ETCS-21] in the balise data range are described as the second balise group in front of the train that provides the forward direction line data and then extends the 300km / h common braking, such as Figure 2 shown.

[0071] like Figure 1 As shown, a method for constant speed downgrading of CTCS-3 level to CTCS-2 level train control includes the following steps:

[0072] The number of low-frequency code sequences to be added and the highest low-frequency code sequence of the track circuit are obtained by using a data matching method;

[0073] Add all the low-frequency code sequences that need to be newly added to the lower frequency side and / or higher frequency side of the existing low-frequency information, and modify the relationship definition of the tracking code sequence to increase the number of idle block sections to provide longer driving permission information for the train;

[0074] The position of the second transponder group providing positive direction line data in front of the transponder is used as the braking starting point, and the braking distance is obtained based on the modified tracking code sequence and the highest low-frequency code sequence;

[0075] A constant speed downgrade is implemented based on the driving permission information and the braking distance.

[0076] The number of low-frequency code sequences to be added and the highest low-frequency code sequence of the track circuit are obtained by using data matching method, including:

[0077] According to the engineering line design data, combined with the length of the track section within the line, the line slope and the train braking performance factors, through traction calculation simulation operation, it is calculated that when the allowable speed reaches 350km / h under CTCS-2 level, in the most unfavorable case, in order to meet the train's common braking distance requirements, the number of idle block sections ahead needs to be provided to the train, and then the number of low-frequency code sequences that need to be added is obtained in combination with the existing low-frequency information, thereby determining the highest low-frequency code sequence of the line; the most unfavorable case is the alternation of continuous long and large slopes, uphill sections, and downhill sections.

[0078] The number of idle block sections ahead that need to be provided to the train is calculated, and then the number of low-frequency code sequences that need to be added is obtained by combining the existing low-frequency information, so as to determine the highest low-frequency code sequence of the line, including:

[0079] It is calculated that the number of idle block sections ahead that need to be provided to the train is N, N>7, and the highest low-frequency code sequence in the existing low-frequency information is L5, indicating that 7 block sections ahead of the train are idle. The number of low-frequency code sequences that need to be added is (N-7), and the highest low-frequency code sequence of the line is L(5+N-7), which is L(N-2).

[0080] Adding all the low-frequency code sequences that need to be newly added to the lower frequency side and / or higher frequency side of the existing low-frequency information, and modifying the relationship definition of the tracking code sequence includes:

[0081] Adding all the low-frequency code sequences that need to be newly added to the lower frequency side and / or the higher frequency side of the existing low-frequency information;

[0082] Modify the relationship definition of the tracking code sequence, including:

[0083] H<—HU<—U<—LU<—L<—L2<—L3<—L4<—L5……<—L(N-2)<—

[0084] L(N-2);

[0085] JC<—HU<—U<—LU<—L<—L2<—L3<—L4<—L5……<—L(N-2)<—

[0086] L(N-2);

[0087] HB<—U<—LU<—L<—L2<—L3<—L4<—L5……<—L(N-2)<—L(N-2);

[0088] UU<—U2<—LU<—L<—L2<—L3<—L4<—L5……<—L(N-2)<—L(N-2);

[0089] UUS<—U2S<—LU<—L<—L2<—L3<—L4<—L5……<—L(N-2)<—L(N-2);

[0090] H: Disaster / earthquake occurs;

[0091] HU: indicates that the block section ahead of the train is occupied;

[0092] U: Indicates that a block section ahead of the train is free, or the train lights up the U light to start at a semi-automatic exit;

[0093] LU: Indicates that two block sections ahead of the train are free;

[0094] L: Indicates that the three block sections ahead of the train are free;

[0095] L2: Indicates that the 4 block sections ahead of the train are free;

[0096] L3: Indicates that 5 block sections ahead of the train are free;

[0097] L4: Indicates that 6 block sections ahead of the train are free;

[0098] L5 code: indicates that 7 block sections ahead of the train are free;

[0099] L (N-2) code: indicates that N block sections ahead of the train are idle.

[0100] The position of the second transponder group providing positive direction line data in front of the transponder is used as the braking starting point, and the braking distance is obtained based on the modified tracking code sequence and the highest low-frequency code sequence, including:

[0101] The position of the second balise group in front of the balise that provides positive line data is taken as the braking starting point. The braking length is consistent with the highest tracking code sequence design of the line. The highest low-frequency code sequence of the line is L (N-2). Combined with the tracking code sequence relationship, it takes (N+2) block sections to track from the HU code to the L (N-2) code. The braking distance is the length of the (N+2) block sections in front of the operation.

[0102] In this embodiment, the specific contents include:

[0103] The design of the CTCS-3 train control system downgraded to the CTCS-2 system at constant speed mainly provides longer driving permission information to the train through track circuits and balises.

[0104] Track circuit: realizes the section occupancy check of the train; provides the number of free block sections ahead of the train; provides continuous driving permission (Movement Authority, MA for short).

[0105] Balise: Active balises provide temporary speed limits and route status information; passive balises provide information such as line allowable speed and block section length.

[0106] As the ground core equipment of the CTCS-2 and CTCS-3 train control systems, the train control center sends coded information to the track circuit and route parameter information to the active balise, and provides the train with the required operating permissions based on information such as the position of each train within its jurisdiction (track occupancy status), interlocking route, and line speed limit status.

[0107] When a CTCS-3 train needs to be downgraded to a CTCS-2 train control system, the on-board equipment installed on the train obtains the number of idle block sections ahead by receiving low-frequency information from the track circuit, and obtains new driving permission information such as interlocking route, line speed limit status, line allowable speed and block section length by receiving transponder messages, and uses the target distance continuous speed control mode to monitor the safe operation of the train.

[0108] Without affecting the existing transportation capacity, combined with the existing CTCS-3 line conditions (line slope and block section length), the low-frequency information of the track circuit is expanded, the highest low-frequency code sequence of the track circuit is increased, and a redundant switching technology is formed to downgrade the CTCS-3 train control system from 350km / h to CTCS-2 at a constant speed.

[0109] The highest low-frequency code sequence of the track circuit is implemented in a data-matchable manner. According to the actual engineering line design, combined with factors such as the length of the track section in the line, the line slope, and the braking performance of the train, through traction calculation simulation operations, it is calculated that when the allowable speed reaches 350km / h under CTCS-2 level, under the most unfavorable conditions (continuous long slopes, uphill sections and downhill sections alternately appear), in order to meet the train's common braking distance requirements, it is necessary to provide the train with the number of idle block sections ahead, thereby determining the highest low-frequency code sequence of the line. It should be noted that the calculation of the highest low-frequency code sequence of the line belongs to the scope of the prior art. Therefore, in order to avoid confusion with the product of the present invention, it will not be described in detail. Specifically, through traction calculation simulation operations, the highest low-frequency code sequence required to allow the speed to reach 350km / h under CTCS-2 level. For example, the Zhengzhou-Wanzhou High-speed Railway adopts the CTCS-3 train control system and the backup CTCS-2 train control system, with a designed line speed of 350km / h. In the Baokang County-Nanzhang section of the Zhengzhou-Wanzhou High-speed Railway upline, there are continuous long and steep slopes, with uphill sections and downhill sections alternating, which are 3550m (-7‰), 4800m (13‰), 4050m (-20‰), 4000m (-25‰), 3021m (-4‰), 4000m (-25‰), 4500m (-20‰), and 4650m (4‰). After traction calculation simulation, under the most unfavorable condition, the L5 code is required to allow the speed to reach 350km / h under the CTCS-2 level, and the code sequence required for normal operation is the L6 code.

[0110] On the basis of TB / T 3060-2016 "Definition and Allocation of Locomotive Signal Information", the existing low-frequency information (including reserved low-frequency information) maintains the status quo, and new low-frequency information is added on the lower frequency side, or on the higher frequency side, or on both lower and higher frequency sides. The track circuit adds corresponding low-frequency information, and the highest tracking code sequence of the track circuit is expanded to accurately indicate the number of idle block sections ahead of the train, providing the train with longer driving permission information to meet the requirement for the number of idle track sections ahead when the CTCS-3 level train control system is downgraded from 350km / h to CTCS-2 level. Specifically, the existing low-frequency information (including reserved low-frequency information) maintains the status quo, and new low-frequency information is added on the lower frequency side, or on the higher frequency side, or on both the lower and higher frequencies. The track circuit adds four low-frequency information, L6, L7, L8, and L9, and the highest tracking code sequence of the track circuit is extended to L9 code, which indicates that there are at least 11 idle block sections ahead of the operation, providing the train with longer driving permission information to meet the requirement for the number of idle track sections ahead when the CTCS-3 level train control system is downgraded from 350km / h to CTCS-2 level.

[0111] The highest low-frequency code sequence of the track circuit is implemented in a data-configurable manner. The corresponding relationship between the number of idle block sections ahead provided to the train and the highest code sequence of the line is:

[0112]

[0113] The low-frequency information added to the lower and higher frequencies of the existing track circuit low-frequency information is used as an example. On the basis of maintaining the existing track circuit low-frequency information unchanged, in order to meet the requirements of the CTCS-3 level train control system downgrading from 350km / h to CTCS-2 level, the track circuit adds four low-frequency information of L6, L7, L8, and L9, and expands the highest tracking code to L9 code. The allocation of the newly added low-frequency information of the ZPW-2000 standard track circuit is shown in Table 2.

[0114] Table 2 New low-frequency information allocation

[0115]

[0116] After the highest low-frequency code sequence of the track circuit is extended to the L9 code, the low-frequency coding information of the track circuit is defined as follows:

[0117] H: Disaster / earthquake occurs;

[0118] HU: indicates that the block section ahead of the train is occupied;

[0119] U: Indicates that a block section ahead of the train is free, or the train lights up the U light to start at a semi-automatic exit.

[0120] LU: Indicates that the two block sections ahead of the train are free

[0121] L: Indicates that the three block sections ahead of the train are free

[0122] L2: Indicates that the 4 block sections ahead of the train are free

[0123] L3: Indicates that the 5 block sections ahead of the train are free

[0124] L4: Indicates that the 6 block sections ahead of the train are free

[0125] L5 code: Indicates that 7 block sections ahead of the train are idle.

[0126] L6 code: Indicates that the 8 block sections ahead of the train are idle.

[0127] L7 code: Indicates that 9 block sections ahead of the train are idle.

[0128] L8 code: Indicates that 10 block sections ahead of the train are idle.

[0129] L9 code: indicates that there are at least 11 free block sections ahead of the train.

[0130] The train control center controls the low-frequency coding of the track circuit equipment according to the route conditions and the status of the running section ahead. The highest low-frequency code sequence is extended to L9 code, and the modified code sequence tracking relationship is defined as:

[0131] H<—HU<—U<—LU<—L<—L2<—L3<—L4<—L5<—L6<—L7<—L8<—L9

[0132] <—L9;

[0133] JC<—HU<—U<—LU<—L<—L2<—L3<—L4<—L5<—L6<—L7<—L8

[0134] <—L9<—L9;

[0135] HB<—U<—LU<—L<—L2<—L3<—L4<—L5<—L6<—L7<—L8<—L9<—L9;

[0136] UU<—U2<—LU<—L<—L2<—L3<—L4<—L5<—L6<—L7<—L8<—L9

[0137] <—L9;

[0138] UUS<—U2S<—LU<—L<—L2<—L3<—L4<—L5<—L6<—L7<—L8<—L9

[0139] <—L9.

[0140] When the train control center sends low-frequency coded information to the track circuit equipment, the codes of the extended low-frequency information L6, L7, L8, and L9 are added accordingly.

[0141] The train control center exchanges boundary block partition low-frequency information between stations. When the relay station sends the block partition low-frequency information to the main station, the codes of the extended low-frequency information L6, L7, L8, and L9 are added accordingly.

[0142] Table 3 Track circuit low frequency coding

[0143]

[0144] The CTCS-3 level train control system sets up a ground balise group on the trackside, which provides the train with the data range of the running line ahead, which is used for train positioning and sending fixed line information such as the line allowable speed, line slope, track section and special section to the CTCS-2 level onboard equipment. The balise setting rules, the sending principles and content of the balise message belong to the scope of the prior art. Therefore, in order to prevent confusion with the product of the present invention, the sending principles and content are not described in detail. (Q / CR 769-2020, Technical Conditions for the Application of Balises in Train Control Systems).

[0145] In order to meet the requirements of the CTCS-3 train control system being downgraded to the CTCS-2 system at the same speed, when the maximum operating speed of the CTCS-2 train control system is increased to 350km / h, due to the increase in the common braking distance, the track section information package [CTCS-1], speed information package [ETCS-27] and slope information package [ETCS-21] in the passive balise data range in the ground balise group should be extended accordingly. During forward operation, the data range provided by the ground balise group to the train is designed according to the second balise group in front of the train that provides forward line data and is further extended by 350km / h for common braking. The maximum range of balise data is as follows: Figure 3 shown.

[0146] The braking distance starts from the location of the second balise group in front of the balise that provides the positive direction line data as the braking starting point. It is the common braking distance for the train to decelerate from the maximum allowable speed of the line to 0km / h. The length of the braking distance is determined according to the actual engineering line design conditions, and the description range is consistent with the highest tracking code sequence design of the line. For example, when the highest tracking code of the line is L5 code, combined with the code sequence tracking relationship, 8 block sections are required to track from the HU code to the L5 code, and the braking distance is the length of the 8 block sections ahead. For another example, when the highest tracking code of the line is L9 code, combined with the code sequence tracking relationship, 12 block sections are required to track from the HU code to the L9 code, and the braking distance is the length of the 12 block sections ahead.

[0147] like Figure 4 As shown, an embodiment of the present disclosure provides a train control system for constant speed downgrading of CTCS-3 level to CTCS-2 level, including:

[0148] An acquisition module 11 is used to obtain the number of low-frequency code sequences to be added and the highest low-frequency code sequence of the track circuit in a data-configurable manner;

[0149] The low-frequency code sequence adding module 12 is used to add all the low-frequency code sequences to be added to the lower frequency side and / or higher frequency side of the existing low-frequency information, and modify the relationship definition of the tracking code sequence to increase the number of idle block sections to provide longer driving permission information for the train;

[0150] A braking distance calculation module 13, configured to use the position of the second transponder group providing positive direction line data in front of the transponder as the braking starting point, and obtain the braking distance based on the modified tracking code sequence and the highest low-frequency code sequence;

[0151] The constant speed degradation module 14 is used to implement constant speed degradation based on the driving permission information and the braking distance.

[0152] The implementation process of the functions and effects of each module in the above system is specifically described in the implementation process of the corresponding steps in the above method, which will not be repeated here.

[0153] For the system embodiment, since it basically corresponds to the method embodiment, the relevant parts can refer to the partial description of the method embodiment. The system embodiment described above is only schematic, wherein the modules described as separate components may or may not be physically separated, and the components displayed as modules may or may not be physical modules, that is, they may be located in one place, or they may be distributed on multiple network modules. Some or all of the modules may be selected according to actual needs to achieve the purpose of the disclosed solution. A person of ordinary skill in the art can understand and implement it without paying any creative work.

[0154] In the above embodiments, any number of all modules can be combined into one module for implementation, or any one of the modules can be split into multiple modules. Alternatively, at least part of the functions of one or more of these modules can be combined with at least part of the functions of other modules and implemented in one module. At least one of all modules can be at least partially implemented as a hardware circuit, such as a field programmable gate array (FPGA), a programmable logic array (PLA), a system on a chip, a system on a substrate, a system on a package, an application specific integrated circuit (ASIC), or can be implemented by hardware or firmware such as any other reasonable way of integrating or packaging the circuit, or implemented in any one of the three implementation methods of software, hardware and firmware or in a suitable combination of any of them. Alternatively, at least one of all modules can be at least partially implemented as a computer program module, and when the computer program module is run, the corresponding function can be executed.

[0155] See also Figure 5 , an electronic device provided by an embodiment of the present disclosure includes a processor 1110, a communication interface 1120, a memory 1130 and a communication bus 1140, wherein the processor 1110, the communication interface 1120, and the memory 1130 communicate with each other through the communication bus 1140;

[0156] Memory 1130, for storing computer programs;

[0157] The processor 1110 is used to implement the train control method of CTCS-3 level constant speed downgrading to CTCS-2 level when executing the program stored in the memory 1130 as shown below.

[0158] The communication bus 1140 may be a Peripheral Component Interconnect (PCI) bus or an Extended Industry Standard Architecture (EISA) bus, etc. The communication bus 1140 may be divided into an address bus, a data bus, a control bus, etc. For ease of representation, only one thick line is used in the figure, but it does not mean that there is only one bus or one type of bus.

[0159] The communication interface 1120 is used for communication between the above electronic device and other devices.

[0160] The memory 1130 may include a random access memory (RAM) or a non-volatile memory, such as at least one disk memory. Optionally, the memory 1130 may also be at least one storage device located away from the processor 1110.

[0161] The above-mentioned processor 1110 can be a general-purpose processor, including a central processing unit (CPU), a network processor (NP), etc.; it can also be a digital signal processor (DSP), an application specific integrated circuit (ASIC), a field programmable gate array (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components.

[0162] The embodiment of the present disclosure further provides a computer-readable storage medium having a computer program stored thereon, and when the computer program is executed by a processor, the above-mentioned train control method of CTCS-3 level constant speed downgrade to CTCS-2 level is implemented.

[0163] The computer-readable storage medium may be included in the device / apparatus described in the above embodiment; or it may exist independently without being assembled into the device / apparatus. The above computer-readable storage medium carries one or more programs. When the above one or more programs are executed, the train control method of CTCS-3 level constant speed downgrade to CTCS-2 level according to the embodiment of the present disclosure is implemented.

[0164] According to an embodiment of the present disclosure, a computer-readable storage medium may be a non-volatile computer-readable storage medium, for example, may include but is not limited to: a portable computer disk, a hard disk, a random access memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), a portable compact disk read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination thereof. In the present disclosure, a computer-readable storage medium may be any tangible medium containing or storing a program, which may be used by or in combination with an instruction execution system, apparatus, or device.

[0165] The above-mentioned embodiments only express several implementation methods of the present disclosure, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present disclosure. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present disclosure, and these all belong to the protection scope of the present disclosure.

Claims

1. A train control method for constant speed downgrading of CTCS-3 to CTCS-2, characterized in that: The following steps are involved: The number of low-frequency code sequences to be added and the highest low-frequency code sequence of the track circuit are obtained in a data matching manner, including: according to the engineering line design data, combined with the length of the track section in the line, the line slope and the train braking performance factors, through traction calculation simulation operation, it is calculated that when the allowable speed reaches 350km / h under CTCS-2 level, in the most unfavorable case, in order to meet the train's common braking distance requirements, the number of idle block sections ahead needs to be provided to the train, and then combined with the existing low-frequency information to obtain the number of low-frequency code sequences to be added, so as to determine the highest low-frequency code sequence of the line; the most unfavorable case is that continuous long and long slopes, uphill sections, and downhill sections appear alternately; Add all the low-frequency code sequences that need to be newly added to the lower frequency side and / or higher frequency side of the existing low-frequency information, and modify the relationship definition of the tracking code sequence to increase the number of idle block sections to provide longer driving permission information for the train; The position of the second transponder group providing positive direction line data in front of the transponder is used as the braking starting point, and the braking distance is obtained based on the modified tracking code sequence and the highest low-frequency code sequence; A constant speed downgrade is implemented based on the driving permission information and the braking distance.

2. A train control method for constant speed downgrading of CTCS-3 to CTCS-2 according to claim 1, characterized in that: The number of idle block sections ahead that need to be provided to the train is calculated, and then the number of low-frequency code sequences that need to be added is obtained by combining the existing low-frequency information, so as to determine the highest low-frequency code sequence of the line, including: It is calculated that the number of idle block sections ahead that need to be provided to the train is N, N>7, and the highest low-frequency code sequence in the existing low-frequency information is L5, indicating that 7 block sections ahead of the train are idle. The number of low-frequency code sequences that need to be added is (N-7), and the highest low-frequency code sequence of the line is L(5+N-7), which is L(N-2).

3. A train control method for constant speed downgrading of CTCS-3 to CTCS-2 according to claim 2, characterized in that: The position of the second transponder group providing positive direction line data in front of the transponder is used as the braking starting point, and the braking distance is obtained based on the modified tracking code sequence and the highest low-frequency code sequence, including: The position of the second balise group in front of the balise that provides positive line data is taken as the braking starting point. The braking length is consistent with the highest tracking code sequence design of the line. The highest low-frequency code sequence of the line is L (N-2). Combined with the tracking code sequence relationship, it takes (N+2) block sections to track from the HU code to the L (N-2) code. The braking distance is the length of the (N+2) block sections in front of the operation.

4. A train control system for constant speed downgrade of CTCS-3 to CTCS-2, characterized in that: include: The acquisition module is used to obtain the number of low-frequency code sequences that need to be added and the highest low-frequency code sequence of the track circuit in a data-matchable manner, including: the acquisition module calculates the number of idle block sections ahead that need to be provided to the train in the most unfavorable case to meet the train's common braking distance requirements when the permissible speed reaches 350km / h under CTCS-2 level according to the engineering line design data, combined with the length of the track section in the line, the line slope and the train braking performance factors through traction calculation simulation operation, and then obtains the number of low-frequency code sequences that need to be added in combination with the existing low-frequency information, thereby determining the highest low-frequency code sequence of the line; the most unfavorable case is that continuous long and long slopes, uphill sections and downhill sections appear alternately; A low-frequency code sequence adding module is used to add all the low-frequency code sequences that need to be newly added to the lower frequency side and / or higher frequency side of the existing low-frequency information, and modify the relationship definition of the tracking code sequence to increase the block section vacancy and provide longer driving permission information for the train; A braking distance calculation module, used for taking the position of the second transponder group providing positive direction line data in front of the transponder as the braking starting point, and obtaining the braking distance based on the modified tracking code sequence and the highest low-frequency code sequence; A constant speed degradation module is used to implement constant speed degradation based on the driving permission information and the braking distance.

5. A train control system for constant speed downgrade of CTCS-3 to CTCS-2 according to claim 4, characterized in that: The acquisition module calculates the number of idle block sections ahead that need to be provided to the train, and then combines the existing low-frequency information to obtain the number of low-frequency code sequences that need to be added, thereby determining that the highest low-frequency code sequence of the line includes: The acquisition module calculates that the number of idle block sections ahead that need to be provided to the train is N, N>7, and the highest low-frequency code sequence in the existing low-frequency information is L5, indicating that 7 block sections ahead of the train are idle, and the number of low-frequency code sequences that need to be added is (N-7). The highest low-frequency code sequence of the line is L(5+N-7), that is, L(N-2).

6. A train control system for constant speed downgrade of CTCS-3 to CTCS-2 according to claim 5, characterized in that: The braking distance calculation module uses the position of the second transponder group providing positive direction line data in front of the transponder as the braking starting point, and obtains the braking distance based on the modified tracking code sequence and the highest low-frequency code sequence, including: The braking distance calculation module takes the position of the second balise group providing positive direction line data in front of the balise as the braking starting point, and the braking length is consistent with the highest tracking code sequence design of the line, wherein the highest low-frequency code sequence of the line is L (N-2). Combined with the tracking code sequence relationship, it takes (N+2) block sections to track from the HU code to the L (N-2) code, and the braking distance is the length of the (N+2) block sections in front of the operation.

7. An electronic device, characterized in that: It includes a processor, a communication interface, a memory and a communication bus, wherein the processor, the communication interface and the memory communicate with each other via the communication bus; Memory, for storing computer programs; The processor is used to implement the train control method of CTCS-3 level constant speed downgrading to CTCS-2 level as described in any one of claims 1 to 3 when executing the program stored in the memory.

8. A computer-readable storage medium storing a computer program, characterized in that: When the computer program is executed by a processor, the train control method of CTCS-3 level constant speed downgrading to CTCS-2 level according to any one of claims 1 to 3 is implemented.

Citation Information

Patent Citations

  • Implementation method of train operation control system with time speed of 200 to 350 kilometers

    CN101537847A

  • Method for improving safety of CTCS-3 (Chinese train control system-3) train control system

    CN102069825A

  • CTCS-3-level train control center system

    CN102320316A

  • Shifting method and device for train control system

    CN102387953A

  • Train control grade transition system and method thereof

    CN110194201A