A distributed scheduling system for mathematical modeling

The distributed dispatch system performs feature classification and time series analysis on historical and real-time data, calculates early warning indexes and prioritizes models, which solves the shortcomings of traditional systems in data utilization and early warning mechanisms, and improves the flexibility and predictability of power plant operations. , achieving more efficient resource allocation and risk management.

CN118656802BActive Publication Date: 2024-10-29深能智慧能源科技有限公司
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202411132056.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-19
Publication Date
2024-10-29
Estimated Expiration
2044-08-19

AI Technical Summary

Technical Problem

Traditional systems cannot make full use of historical and real-time data when dealing with the complex operating environment of power plants. They lack dynamic data classification and analysis capabilities, make it difficult to adjust model strategies, and lack effective early warning mechanisms and prioritization functions, resulting in unreasonable resource allocation and affecting operational efficiency and Security.

Method used

A distributed scheduling system is designed, including data collection, data processing, multi-model construction and comprehensive analysis modules. By performing label extraction and feature classification on historical data, a regression or classification model is constructed, and feature classification and time series are performed on real-time data. Analyze, calculate the early warning index, and prioritize models based on the early warning index to achieve dynamic adjustment and priority processing.

Benefits of technology

It improves data utilization and prediction capabilities, ensures the accuracy and efficiency of real-time data processing, enhances the adaptability and early warning capabilities of the system, can promptly identify potential risks and prioritize emergency issues, and improves the operational efficiency and safety of the power plant. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118656802B_ABST
    Figure CN118656802B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of distributed scheduling, and in particular to a distributed scheduling system for mathematical modeling, which comprises a data collection module, a data processing module, a multi-model construction module and a comprehensive analysis module, wherein: the data collection module collects real-time power plant data and historical power plant data; the data processing module is used to extract labels from historical power plant data to generate label data; and generate historical classification data based on the label data; the multi-model construction module constructs different models according to the historical classification data; the comprehensive analysis module performs the same feature classification on the real-time power plant data according to the feature classification results of the historical classification data in the data processing module to generate real-time feature classification data; and performs time series analysis on the real-time feature classification data to form an early warning index; the comprehensive analysis module generates a model priority list according to the size of the early warning index; and the model is output according to the order of the model priority list.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of distributed scheduling, and in particular to a distributed scheduling system for mathematical modeling. Background Art

[0002] Traditional systems have many shortcomings when dealing with the complex operating environment of power plants. First, they often fail to fully utilize the value of historical and real-time data, resulting in low data utilization and insufficient accuracy and adaptability of prediction models.

[0003] Secondly, these systems usually adopt fixed data processing processes, lack the ability to dynamically classify and analyze real-time data, and cannot timely capture data trends and potential risks. In addition, traditional systems are relatively rigid in model construction and application, and it is difficult to flexibly adjust model strategies according to the characteristics of different operating indicators.

[0004] More importantly, they lack effective early warning mechanisms and priority sorting functions, and are unable to quickly identify and handle the most urgent problems, resulting in irrational resource allocation and delayed problem handling. These limitations have seriously affected the operational efficiency and safety of power plants, making it difficult for managers to fully and deeply understand the operating status of equipment, and unable to make timely and accurate decisions to prevent potential equipment failures and operational risks.

[0005] In general, the shortcomings of traditional systems have resulted in power plants lacking the necessary flexibility, foresight and adaptability when facing complex and changing operating environments. Summary of the invention

[0006] The purpose of the present invention is to provide a distributed scheduling system for mathematical modeling to solve the problems raised in the above background technology.

[0007] To achieve the above object, the present invention provides the following technical solution: a distributed scheduling system for mathematical modeling, comprising a data collection module, a data processing module, a multi-model construction module and a comprehensive analysis module, wherein:

[0008] The data collection module collects real-time power plant data and historical power plant data;

[0009] The data processing module is used to extract labels from the historical power plant data to generate label data; and to perform feature classification on the historical power plant data based on the label data to generate historical classification data;

[0010] The multi-model construction module constructs corresponding regression or classification models according to different label types in the historical classification data;

[0011] The comprehensive analysis module receives the feature classification results of the historical classification data in the data processing module, performs corresponding feature classification on the real-time power plant data, and generates real-time feature classification data; and performs time series analysis on the real-time feature classification data, establishes an autoregressive integrated moving average model through the data corresponding to different feature groups in the real-time feature classification data, uses the model to perform short-term prediction, obtains the predicted value, calculates the distance between the predicted value and the safety threshold, and forms an early warning index;

[0012] The comprehensive analysis module prioritizes the models constructed in the multi-model construction module corresponding to different feature groups in the real-time feature classification data according to the size of the early warning index, and generates a model priority list; according to the order of the model priority list, the corresponding models are selected in turn, and the data of the feature group in the real-time feature classification data corresponding to the model is used as input, and the model output is performed.

[0013] As a further improvement of the present technical solution, the real-time power plant data in the data collection module is collected in real time through sensors and monitoring equipment distributed throughout the power plant. The collected real-time power plant data includes but is not limited to the instantaneous output power of the generator set, boiler temperature and pressure, turbine speed, cooling system parameters, grid frequency, voltage and environmental data; the historical power plant data is past operation records extracted from the database, including the historical records of the above-mentioned real-time power plant data, as well as other long-term data, including but not limited to equipment maintenance records and energy consumption statistics.

[0014] As a further improvement of the present technical solution, the data processing module is used to extract labels from the historical power plant data and generate label data. Specifically, based on the long-term data in the historical power plant data, the continuous data and categorized data at each time point are selected as labels.

[0015] As a further improvement of the technical solution, the data processing module performs feature classification on the historical power plant data based on the label data to generate historical classification data, specifically including:

[0016] Feature importance ranking: For each label, use different learning models to evaluate feature importance. For regression problems, that is, for continuous data, use random forest regressor; for classification problems, that is, for categorical data, use random forest classifier; obtain the importance score of each feature for predicting the label, and sort the features according to the importance score;

[0017] Feature selection: Set an importance threshold, select features whose importance scores are greater than the importance threshold, form feature groups, and allow features to appear in multiple groups. That is, if a feature is greater than the importance threshold for multiple labels, it will be assigned multiple times to form a feature classification result; finally, the feature groups and corresponding labels in the feature classification results are used as historical classification data.

[0018] As a further improvement of the present technical solution, the multi-model construction module constructs corresponding regression or classification models according to different label types in the historical classification data. Specifically, the labels corresponding to each feature group in the historical classification data are used as training data for different models. For continuous label results, a regression model is selected for training; for categorized label results, a classification model is selected for training.

[0019] As a further improvement of the technical solution, the comprehensive analysis module includes a real-time data classification unit, which performs the same feature classification on the real-time power plant data according to the feature classification results of the historical classification data in the data processing module to generate real-time feature classification data, specifically including:

[0020] Obtaining feature classification results of historical classification data from the data processing module, including each feature group and its corresponding label, and receiving real-time power plant data from the data collection module;

[0021] According to each feature group in the historical classification data, corresponding features are extracted from the real-time power plant data; the extracted features are made consistent with the feature groups in the historical classification data; and real-time feature classification data is generated, including multiple data subsets, each subset corresponding to a specific feature group.

[0022] As a further improvement of the technical solution, the comprehensive analysis module includes a time series analysis unit, and the time series analysis unit performs time series analysis on the real-time feature classification data, specifically including:

[0023] For the real-time feature classification data of each feature group, a fixed time window size is selected for autoregressive integrated moving average model training;

[0024] For each feature group of data, a stationarity test is performed. If the data is not stationary, differential processing is performed to determine the differential order d; the autocorrelation function and partial autocorrelation function graphs are analyzed to determine the range of p and q; the optimal p and q parameters are automatically selected using grid search; an autoregressive integrated moving average model is constructed and fitted using fixed time window data, where p, d, and q represent the autoregressive order, differential order, and moving average order, respectively;

[0025] Use the constructed autoregressive integrated moving average model to make short-term predictions for each feature group and obtain the predicted value sequence for each feature group.

[0026] As a further improvement of the technical solution, the comprehensive analysis module includes a model priority analysis unit that performs model priority analysis according to the prediction results of the time series analysis unit, specifically including:

[0027] Warning index calculation: For the data in the predicted value sequence of each feature group, determine the corresponding safety threshold, calculate the distance between each data and the safety threshold, and add them up to get the sum of the distances between the data in each feature group and the safety threshold, and use it as the warning index; if the prediction sequence contains multiple time points, take the average value as the final warning index of the feature group;

[0028] Model priority sorting: Collect the warning indexes of all feature groups, sort them from large to small according to the warning index, and obtain the feature group priority list. Different feature groups correspond to different models, and the feature group priority list is used as the model priority list;

[0029] According to the order of the model priority list, the corresponding models are selected in turn, and the data of the feature group in the real-time feature classification data corresponding to the model is used as input, and the output of the model is performed.

[0030] Compared with the prior art, the present invention has the following beneficial effects:

[0031] 1. This distributed scheduling system for mathematical modeling maximizes the use of data value through multiple applications of historical classified data; first, different prediction models are built based on historical classified data to ensure that the models can accurately capture the characteristics and changing patterns of various operating indicators; second, the feature classification results of historical data are applied to real-time data to ensure the consistency and comparability of real-time data processing, and effectively improve the accuracy and efficiency of data analysis; finally, by performing time series analysis on real-time feature classification data, the system can timely capture the dynamic change trend of data and provide a more reliable basis for prediction and decision-making; this multi-level and multi-angle historical data application method not only improves data utilization, but also significantly enhances the system's predictive ability and adaptability, allowing power plant managers to have a more comprehensive and in-depth understanding of equipment operating conditions and potential risks.

[0032] 2. The multiple applications of real-time feature classification data in this distributed scheduling system for mathematical modeling demonstrate its powerful real-time analysis and early warning capabilities; by using the autoregressive integrated moving average model to make short-term predictions on real-time data, the system can promptly detect potential anomalies or risks; the calculation of the early warning index combines the prediction results with the safety threshold, providing an intuitive and quantitative risk assessment indicator; more importantly, the system prioritizes different models according to the early warning index and executes the models in this order. This dynamic adjustment method ensures that the most urgent problems are given priority. In addition, by using real-time feature classification data as the input of the highest priority model, the system can quickly respond to the most critical current operating conditions; this intelligent scheduling and analysis method significantly improves the operating efficiency and safety of power plants, enabling managers to make decisions faster and more accurately, and effectively prevent potential equipment failures and operational risks. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] Figure 1 It is a schematic diagram of the overall module of the present invention;

[0034] Figure 2 It is a schematic diagram of the comprehensive analysis module unit of the present invention.

[0035] In the figure: 100, data collection module; 200, data processing module; 300, multi-model construction module; 400, comprehensive analysis module; 401, real-time data classification unit; 402, time series analysis unit; 403, model priority analysis unit. DETAILED DESCRIPTION

[0036] The following will be combined with the accompanying drawings in the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] See also Figure 1-Figure 2 The present invention provides a technical solution: a distributed scheduling system for mathematical modeling, including a data collection module 100, a data processing module 200, a multi-model construction module 300 and a comprehensive analysis module 400.

[0038] The data collection module 100 collects real-time power plant data and historical power plant data, wherein the real-time power plant data is collected in real time through sensors and monitoring equipment distributed throughout the power plant, and the collected real-time power plant data includes but is not limited to the instantaneous output power of the generator set, boiler temperature and pressure, turbine speed, cooling system parameters, grid frequency and voltage and environmental data (such as air temperature, humidity, wind speed, etc.); the historical power plant data is the past operation records extracted from the database, including the historical records of the above-mentioned real-time power plant data, and other long-term data, such as equipment maintenance records, energy consumption statistics, etc.

[0039] The data processing module 200 is used to extract labels from the historical power plant data and generate label data; specifically, based on the long-term data in the historical power plant data, the continuous data and categorized data at each time point are selected as labels, for example, the equipment failure events (categorized data) at each time point are extracted from the maintenance records as equipment failure labels; the actual power generation (continuous data) at each time point is extracted from the historical power plant data.

[0040] The data processing module 200 performs feature classification on the historical power plant data based on the label data to generate historical classification data, specifically including:

[0041] Feature importance ranking: For each label, use different learning models to evaluate feature importance. For regression problems (such as predicting power generation), that is, for continuous data, use random forest regressors; for classification problems (such as predicting equipment failures), that is, for categorical data, use random forest classifiers; obtain the importance score of each feature for predicting the label, and rank the features according to the importance score;

[0042] Feature selection: set an importance threshold, select features with importance scores greater than the importance threshold, form feature groups, and allow features to appear in multiple groups, that is, if a feature is greater than the importance threshold for multiple labels, it will be assigned multiple times to form feature classification results; finally, the feature groups and corresponding labels in the feature classification results are used as historical classification data. For example:

[0043] Power generation forecast model input:

[0044] Feature group: including but not limited to historical power generation, temperature, wind speed, sunshine time, etc.;

[0045] Tags: Actual power generation;

[0046] Equipment failure prediction model input:

[0047] Feature group: including but not limited to equipment operation time, vibration data, temperature data, etc.;

[0048] Tags: Equipment failure event.

[0049] The multi-model construction module 300 constructs different models based on the historical classification data, specifically using the labels corresponding to each feature group in the historical classification data as training data for different models, for example, the label is the actual power generation and the corresponding feature group is used as training data for the power generation prediction model. Different training models are selected based on the data type results of the labels, specifically including:

[0050] For continuous label results (such as actual power generation), a regression model is selected for training, such as a linear regression model.

[0051] For categorical label results (such as equipment failure events), select a classification model for training, such as a logistic regression model.

[0052] The real-time data classification unit 401 in the comprehensive analysis module 400 performs the same feature classification on the real-time power plant data according to the feature classification results of the historical classification data in the data processing module 200, and generates real-time feature classification data, which specifically includes:

[0053] Obtaining feature classification results of historical classification data from the data processing module 200, including each feature group and its corresponding label; receiving real-time power plant data from the data collection module 100;

[0054] According to each feature group in the historical classification data (such as power generation prediction, equipment failure prediction, etc.), the corresponding features are extracted from the real-time power plant data; the extracted features are made consistent with the feature groups in the historical classification data; real-time feature classification data is generated, which includes multiple data subsets, each subset corresponding to a specific feature group.

[0055] The time series analysis unit 402 in the comprehensive analysis module 400 performs time series analysis on the real-time feature classification data, specifically including:

[0056] Classify the real-time features of each feature group to ensure that the data is an ordered time series and handle possible missing values ​​or outliers; select a fixed time window size, such as the data of the last 24 hours or 7 days, for training the autoregressive integrated moving average model;

[0057] Autoregressive integrated moving average model construction: Perform a stationarity test (such as ADF test) on the data of each feature group. If the data is not stationary, perform differential processing to determine the differential order d; analyze the ACF (autocorrelation function) and PACF (partial autocorrelation function) graphs to preliminarily determine the range of p and q; use grid search or information criteria (such as AIC, BIC) to automatically select the optimal p and q parameters; construct an autoregressive integrated moving average (p, d, q) model and use fixed time window data for fitting, where p, d, and q represent the autoregressive order, differential order, and moving average order, respectively;

[0058] Short-term prediction: Use the constructed autoregressive integrated moving average model to make short-term predictions for each feature group and obtain the predicted value sequence for each feature group.

[0059] The model priority analysis unit 403 in the comprehensive analysis module 400 performs model priority analysis according to the prediction result of the time series analysis unit 402, which specifically includes:

[0060] Warning index calculation: For the data in the predicted value sequence of each feature group, determine the corresponding safety threshold, calculate the distance between each data and the safety threshold, and add them up to obtain the sum of the distances between the data in each feature group and the safety threshold, and use it as the warning index;

[0061] If the prediction sequence contains multiple time points, the average value is taken as the final warning index of the feature group;

[0062] Model priority sorting: Collect the warning indexes of all feature groups, sort them from large to small according to the warning index, and obtain the feature group priority list. Since different feature groups correspond to different models, the feature group priority list is used as the model priority list;

[0063] According to the order of the model priority list, the corresponding models are selected in turn, and the data of the feature group in the real-time feature classification data corresponding to the model is used as input, and the output of the model is performed.

[0064] The following is a rough example using specific data:

[0065] Data collection module 100:

[0066] Real-time power plant data: generator set output power: 750MW, boiler temperature: 540°C, boiler pressure: 16.5MPa, turbine speed: 3000rpm, cooling water temperature: 25°C, grid frequency: 50.02Hz, ambient temperature: 28°C, wind speed: 5m / s;

[0067] Historical power plant data (one data point per hour for the past 24 hours): Power generation: [740, 745, 748, …, 750] MW, Boiler temperature: [538, 539, 540, …, 540] °C, Equipment failure events: [0, 0, 1, …, 0] (0 means no failure, 1 means failure);

[0068] Data processing module 200:

[0069] Label extraction: Continuous labels are actual power generation, and categorical labels are equipment failure events;

[0070] Feature importance ranking (using random forest, importance scores range 0-1):

[0071] Power generation forecast: historical power generation is 0.8, boiler temperature is 0.6, ambient temperature is 0.5, and wind speed is 0.3;

[0072] Equipment failure prediction: equipment operation time is 0.7, vibration data is 0.6, and temperature data is 0.5;

[0073] Feature selection (assuming importance threshold is 0.4):

[0074] Power generation prediction feature group: historical power generation, boiler temperature, ambient temperature;

[0075] Equipment failure prediction feature group: equipment operating time, vibration data, and temperature data.

[0076] Multi-model construction module 300: power generation prediction model (regression model, such as linear regression), equipment failure prediction model (classification model, such as logistic regression).

[0077] Comprehensive analysis module 400:

[0078] Real-time feature classification data: the power generation feature group is [750,540,28] (current power generation, boiler temperature, ambient temperature);

[0079] The equipment fault feature group is [5000, 0.5, 540] (accumulated operating time, vibration value, temperature);

[0080] Time series analysis (taking power generation forecast as an example): ARIMA model parameters are (2,1,1), short-term forecast (next 6 hours): [752,753,755,756,758,760]MW;

[0081] Calculation of early warning index: Assuming the power generation safety threshold is [700,800] MW, the early warning index = (752-700+753-700+…+760-700) / 6=55.5;

[0082] Similarly, the early warning index for equipment failure prediction is calculated, assuming it is 40.2;

[0083] Model priority ranking: power generation prediction model (warning index: 55.5), equipment failure prediction model (warning index: 40.2);

[0084] Execution order: First execute the power generation prediction model: Input: [750,540,28]; Output: predict the power generation in the next 24 hours;

[0085] Then execute the equipment failure prediction model: Input: [5000, 0.5, 540]; Output: The probability of equipment failure within the next 24 hours.

[0086] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited by the above embodiments. The above embodiments and descriptions are only preferred examples of the present invention and are not intended to limit the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, which fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A distributed scheduling system for mathematical modeling, characterized in that: The system comprises a data collection module (100), a data processing module (200), a multi-model construction module (300) and a comprehensive analysis module (400), wherein: The data collection module (100) collects real-time power plant data and historical power plant data; The data processing module (200) is used to extract labels from the historical power plant data to generate label data; and to perform feature classification on the historical power plant data based on the label data to generate historical classification data; The multi-model construction module (300) constructs corresponding regression or classification models according to different label types in the historical classification data; The comprehensive analysis module (400) receives the feature classification results of the historical classification data in the data processing module (200), performs corresponding feature classification on the real-time power plant data, and generates real-time feature classification data; and performs time series analysis on the real-time feature classification data, establishes an autoregressive integrated moving average model by analyzing the data corresponding to different feature groups in the real-time feature classification data, uses the model to perform short-term prediction, obtains a prediction value, calculates the distance between the prediction value and the safety threshold, and forms an early warning index; The comprehensive analysis module (400) prioritizes the models constructed in the multi-model construction module (300) corresponding to different feature groups in the real-time feature classification data according to the size of the early warning index, and generates a model priority list; selects the corresponding model in sequence according to the order of the model priority list, and uses the data of the feature group in the real-time feature classification data corresponding to the model as input, and outputs the model; The real-time power plant data in the data collection module (100) is collected in real time through sensors and monitoring equipment distributed throughout the power plant, and the collected real-time power plant data includes the instantaneous output power of the generator set, boiler temperature and pressure, turbine speed, cooling system parameters, grid frequency, voltage and environmental data; the historical power plant data is the past operation records extracted from the database, including the historical records of the above-mentioned real-time power plant data, equipment maintenance records, and energy consumption statistics; The data processing module (200) is used to extract labels from the historical power plant data to generate label data, specifically, based on the long-term data in the historical power plant data, selecting continuous data and categorical data at each time point therein as labels; The data processing module (200) performs feature classification on the historical power plant data based on the label data to generate historical classification data, specifically including: Feature importance ranking: For each label, use different learning models to evaluate feature importance. For regression problems, that is, for continuous data, use random forest regressor; for classification problems, that is, for categorical data, use random forest classifier; obtain the importance score of each feature for predicting the label, and sort the features according to the importance score; Feature selection: set an importance threshold, select features with importance scores greater than the importance threshold, form feature groups, and allow features to appear in multiple groups. That is, if a feature is greater than the importance threshold for multiple labels, it will be assigned multiple times to form feature classification results. Finally, the feature groups and corresponding labels in the feature classification results are used as historical classification data. The multi-model construction module (300) constructs corresponding regression or classification models according to different label types in the historical classification data, and specifically uses the labels corresponding to each feature group in the historical classification data as training data for different models. For continuous label results, a regression model is selected for training; for categorical label results, a classification model is selected for training; The comprehensive analysis module (400) comprises a real-time data classification unit (401), wherein the real-time data classification unit (401) performs the same feature classification on the real-time power plant data according to the feature classification result of the historical classification data in the data processing module (200), and generates real-time feature classification data, specifically comprising: Acquiring feature classification results of historical classification data from the data processing module (200), including each feature group and its corresponding label, and receiving real-time power plant data from the data collection module (100); According to each feature group in the historical classification data, corresponding features are extracted from the real-time power plant data; the extracted features are made consistent with the feature groups in the historical classification data; real-time feature classification data is generated, including multiple data subsets, each subset corresponding to a specific feature group; The comprehensive analysis module (400) comprises a time series analysis unit (402), wherein the time series analysis unit (402) performs time series analysis on the real-time feature classification data, specifically comprising: For the real-time feature classification data of each feature group, a fixed time window size is selected for autoregressive integrated moving average model training; For each feature group of data, a stationarity test is performed. If the data is not stationary, differential processing is performed to determine the differential order d; the autocorrelation function and partial autocorrelation function graphs are analyzed to determine the range of p and q; the optimal p and q parameters are automatically selected using grid search; an autoregressive integrated moving average model is constructed and fitted using fixed time window data, where p, d, and q represent the autoregressive order, differential order, and moving average order, respectively; Use the constructed autoregressive integrated moving average model to make short-term predictions for each feature group and obtain the predicted value sequence for each feature group; The comprehensive analysis module (400) includes a model priority analysis unit (403) which performs a model priority analysis according to the prediction result of the time series analysis unit (402), specifically including: Warning index calculation: For the data in the predicted value sequence of each feature group, determine the corresponding safety threshold, calculate the distance between each data and the safety threshold, and add them up to get the sum of the distances between the data in each feature group and the safety threshold, and use it as the warning index; if the prediction sequence contains multiple time points, take the average value as the final warning index of the feature group; Model priority sorting: Collect the warning indexes of all feature groups, sort them from large to small according to the warning index, and obtain the feature group priority list. Different feature groups correspond to different models, and the feature group priority list is used as the model priority list; According to the order of the model priority list, the corresponding models are selected in turn, and the data of the feature group in the real-time feature classification data corresponding to the model is used as input, and the output of the model is performed.

Citation Information

Patent Citations

  • Intelligent operation and maintenance system for power grid

    CN117474529A

  • Power customer demand prediction and analysis system based on big data

    CN117474584A

  • Alarm data processing method and system based on feature analysis

    CN117520955A

  • Emergency intelligent order priority management system for work orders of operation and maintenance department

    CN117592736A

  • Power station operation state monitoring system and method based on multivariate time series prediction

    CN117674420A