Integrated installation structure, storage container and manufacturing method for marine equipment

By adopting an integrated installation structure in the marine cargo tank and connecting the main insulation layer, secondary insulation layer and secondary shielding film with prefabricated connection devices, the problems of disadvantages in the prior art and the complexity of construction are solved, and more efficient and Safe construction process.

CN118665660BActive Publication Date: 2024-11-29SINOTECH ENERGY CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202411156481.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2024-11-29
Estimated Expiration
2044-08-22

AI Technical Summary

Technical Problem

The container walls of existing marine cargo tanks have unfavorable sealing problems with screw connections, resulting in leakage, and the cancellation of the connection in the form of door-type wedges will reduce the load bearing of the fixed point, increasing structural complexity and construction cycle.

Method used

The integrated installation structure is adopted, including the main insulation layer, the secondary insulation layer and the secondary shielding film, and the layers are connected together through prefabricated connecting devices to reduce on-site construction steps and high-altitude working time.

Benefits of technology

The construction process of storage containers is simplified, the on-site construction time and aerial work time are reduced, and the construction safety and efficiency are improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118665660B_ABST
    Figure CN118665660B_ABST
Patent Text Reader

Abstract

The present application provides an integrated installation structure, storage container and manufacturing method for marine equipment, and relates to the technical field of marine equipment. The integrated installation structure includes a main insulation layer composed of at least one first main insulation plate and at least one second main insulation plate, a secondary insulation layer arranged on the outside of the main insulation layer, and a secondary shielding membrane located between the two. Among them, the first main insulation plate is prefabricated and connected to the secondary shielding membrane as an integral component through a first connecting device, and the second main insulation plate is a structure separated from the secondary shielding membrane and is connected to the secondary insulation layer through a second connecting device. According to the scheme of the present application, the laying process of the main insulation layer can be simplified, and a part of the installation operation at the construction site can be converted into prefabrication operation of the processing plant, thereby greatly reducing the length of high-altitude operations during the construction of the storage container, which can not only speed up the construction period, but also help to improve construction safety.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of marine equipment, and in particular to an integrated mounting structure for marine equipment, a storage container having the integrated mounting structure, and a corresponding manufacturing method. Background Art

[0002] LNG usually needs to rely on transportation equipment, such as ships and other marine equipment to achieve transportation. In the relevant technology, marine cargo tanks are usually used to store related media. The container wall of the marine cargo tank is usually a multi-layer structure, including an insulation layer, a film shielding layer, etc. At present, the existing technology often uses a door-type wedge to connect the layers together through screws. However, the screw connection is not conducive to the sealing of the container wall and is prone to cold leakage. Some solutions avoid the problem of sealing leakage by eliminating the connection in the form of a door-type wedge. Since the door-type wedge is eliminated, the load-bearing at the fixed point will be greatly reduced. Therefore, the insulation layer and other structures are divided into small blocks to reduce weight and ensure a certain degree of rigidity. However, this block installation method has a complex structure, cumbersome procedures, a long construction period, and low installation efficiency.

[0003] Therefore, it is necessary to provide an integrated mounting structure for marine equipment, a storage container having the same, and a corresponding manufacturing method to at least partially solve the above problems. Summary of the invention

[0004] The purpose of the present application is to provide an integrated installation structure for marine equipment, a storage container having the integrated installation structure and a corresponding manufacturing method, which can significantly reduce the on-site construction time in the storage container, especially the high-altitude operation time of on-site construction, which is conducive to speeding up the construction period and improving construction safety.

[0005] In one aspect, the present application provides an integrated mounting structure for marine equipment, the integrated mounting structure being used to form at least a portion of a wall of a storage container, the integrated mounting structure comprising:

[0006] A main insulating layer, wherein the main insulating layer is composed of at least one first main insulating plate and at least one second main insulating plate;

[0007] A secondary insulating layer, the secondary insulating layer being disposed on an outer side of the primary insulating layer defined according to the storage container, the secondary insulating layer being composed of an arrangement of secondary insulating plates; and

[0008] A secondary shielding membrane is arranged between the main insulating layer and the secondary insulating layer, wherein the first main insulating plate is prefabricated and connected to the secondary shielding membrane as an integral component through a first connecting device, and the second main insulating plate is a structure separate from the secondary shielding membrane and is connected to the secondary insulating plate through a second connecting device.

[0009] In some embodiments, each of the second main insulating plates is arranged adjacent to at least one of the first main insulating plates, and / or any two of the second main insulating plates are not adjacent to each other.

[0010] In some embodiments, the first connecting device includes:

[0011] a first anchoring element connected to an inner side of the secondary shielding membrane; and

[0012] A first fastening element is provided, wherein the first fastening element passes through the first main insulating plate and the first anchoring element to fasten the first main insulating plate and the first anchoring element together.

[0013] In some embodiments, a first recess is provided on the outer side of the first main insulating plate facing the secondary shielding membrane, and when the first main insulating plate and the secondary shielding membrane are prefabricated and connected as an integral component, at least a portion of the first anchoring element is accommodated in the first recess.

[0014] In some embodiments, the first anchoring element includes a flat plate portion and a ridge portion protruding relative to the flat plate portion, the flat plate portion is connected to the secondary shielding membrane, and the first fastening element passes through the first main insulating plate and is fastened to the ridge portion.

[0015] In some embodiments, the first fastening element includes a connecting column and a cap located at an end of the connecting column, the inner side of the first main insulating plate facing away from the secondary shielding film is provided with a second recess, and the cap is accommodated in the second recess and is lower than the inner side of the first main insulating plate. The cap can be, for example, the end of a rivet that is radially enlarged after riveting.

[0016] In some embodiments, the first connecting device includes:

[0017] a first connecting post connected to an inner side surface of the secondary shielding film;

[0018] a first anchoring element, the first anchoring element being disposed on the first main insulating plate, the first connecting column passing through the first anchoring element; and

[0019] A first fastening element is connected to the first connecting column at an inner side of the first anchoring element to fasten the first anchoring element and the secondary shielding film together.

[0020] In some embodiments, the inner side surface of the first main insulating plate facing away from the secondary shielding film is provided with a second recess, and the first anchoring element is provided in the second recess and supported by the bottom surface of the second recess. Preferably, the first fastening element is accommodated in the second recess and is lower than the inner side surface of the first main insulating plate.

[0021] In some embodiments, the second connecting device includes:

[0022] a second outer anchoring element, the second outer anchoring element being arranged on an inner side of the secondary insulating plate facing the secondary shielding film,

[0023] a second inner anchoring element, said second inner anchoring element being arranged on said second main insulating plate, and

[0024] The second fastening element, the secondary shielding membrane has a through hole, the second fastening element passes through the second inner anchoring element from the inner side of the second inner anchoring element, the secondary shielding membrane and is connected with the second outer anchoring element to fasten the second main insulating plate, the secondary shielding membrane and the secondary insulating plate together.

[0025] In some embodiments, the second outer anchoring element is configured as a plate-like structure, the plate-like structure is provided with a first fixing hole, the first fixing hole through which the second fastening element passes is fastened with a nut, or the first fixing hole is provided with a threaded portion, and the second fastening element is connected to the first fixing hole through the threaded portion.

[0026] In some embodiments, the plate-like structure is provided with a boss portion protruding from the inner side surface facing the secondary shielding film, the through hole of the secondary shielding film has a shape substantially the same as the boss portion for the boss portion to pass through, and the secondary shielding film is welded to the boss portion. Preferably, the inner side surface of the secondary insulating plate is provided with a mounting groove, and the plate-like structure is embedded in the mounting groove. Preferably, the plate-like structure is fastened in the mounting groove by an additional fastener. Preferably, the outer side surface of the second main insulating plate facing the secondary shielding film is provided with a fourth recess, and in the installed state, at least a portion of the boss portion is accommodated in the fourth recess.

[0027] In some embodiments, the second connecting device includes:

[0028] a second inner anchoring element, said second inner anchoring element being arranged on said second main insulating plate,

[0029] a second outer anchoring element, the second outer anchoring element being disposed on an inner side of the secondary insulating plate facing the secondary shielding film, the second outer anchoring element having a second connecting column extending toward the secondary shielding film, the second connecting column passing through the secondary shielding film and the second inner anchoring element; and

[0030] A second fastening element is connected to the second connection column at an inner side of the second inner anchoring element to fasten the second main insulating plate, the secondary shielding film, and the secondary insulating plate together.

[0031] In some embodiments, the second outer anchoring element is configured as a plate-like structure, the second connecting column is welded to the plate-like structure, or the second connecting column is integrally formed with the plate-like structure. Preferably, the inner side surface of the secondary insulating board is provided with a mounting groove, the plate-like structure is embedded in the mounting groove, and is fastened in the mounting groove by an additional fastener.

[0032] In some embodiments, a third recess is provided on the inner side surface of the second main insulating plate facing away from the secondary shielding membrane, an anchor hole penetrating the second main insulating plate is provided on the bottom surface of the third recess, and the second inner anchoring element is disposed in the third recess and supported by the bottom surface of the third recess.

[0033] In some embodiments, the second fastening element includes or forms a cap located inside the second inner anchoring element, and the second inner anchoring element and the cap of the second fastening element are both accommodated in the third recess and are lower than the inner side surface of the second main insulating plate.

[0034] In some embodiments, the integrated mounting structure also includes a main shielding membrane, which is arranged on the inner side of the main insulating layer facing away from the secondary shielding membrane, and a third anchoring element is provided on the inner side of the first main insulating plate and / or the second main insulating plate facing the main shielding membrane, and the main shielding membrane is connected to the third anchoring element.

[0035] In some embodiments, the position of the third anchoring element arranged on the first main insulating plate coincides with the first connecting device along the thickness direction of the first main insulating plate, and / or the position of the third anchoring element arranged on the second main insulating plate coincides with the second connecting device along the thickness direction of the first main insulating plate.

[0036] In some embodiments, the third anchoring element is configured as a plate-like structure, the plate-like structure is provided with a boss portion protruding from the inner side surface facing the main shielding membrane, and the main shielding membrane is provided with a through hole for the boss portion to pass through and having a shape substantially the same as that of the boss portion. Preferably, the inner side surface of the first main insulating plate and / or the second main insulating plate provided with the third anchoring element is provided with a mounting groove, and the plate-like structure is embedded in the mounting groove. Preferably, the plate-like structure is fastened in the mounting groove by an additional fastener.

[0037] In some embodiments, the secondary shielding membrane is constructed as a corrugated plate made of a metal material, on which a plurality of transverse corrugations and a plurality of longitudinal corrugations are formed, and two adjacent transverse corrugations and two adjacent longitudinal corrugations cross to form an installation area, and each of the installation areas is provided with a first main insulating plate or a second main insulating plate.

[0038] Another aspect of the present application provides a storage container, which comprises the integrated mounting structure as described above, wherein the integrated mounting structure forms a part of a container wall of the storage container. Preferably, the storage container is a large land-based storage tank.

[0039] In another aspect, the present application also provides a method for manufacturing a storage container, which comprises the following steps:

[0040] manufacturing the secondary insulating layer;

[0041] making an integrated prefabricated component including the secondary shielding membrane and the first main insulating plate;

[0042] Install the secondary insulation layer to form a secondary insulation box;

[0043] fixing the integrated prefabricated component on the inner side of the secondary insulating layer;

[0044] Laying the second main insulating plate on the inner side of the secondary shielding film and connecting it to the secondary insulating layer;

[0045] The main shielding film is installed on the inner side of the main insulating layer. The construction site of the manufacturing method includes at least a field construction side and a factory prefabrication side. Preferably, at least the step of manufacturing the integrated prefabricated component is completed at the factory prefabrication side.

[0046] According to the solution of the present application, by simplifying the laying process of the main insulation layer, a part of the installation operations at the construction site are converted into prefabrication operations in the processing factory, thereby greatly reducing the length of high-altitude operations during the construction of storage containers, which can not only speed up the construction period but also help improve construction safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0047] In order to better understand the above and other purposes, features, advantages and functions of the present application, reference may be made to the preferred embodiments shown in the accompanying drawings. It should be understood by those skilled in the art that the accompanying drawings are intended to schematically illustrate the preferred embodiments of the present application and have no limiting effect on the scope of the present application.

[0048] Figure 1 A portion of a container wall of a storage container according to a preferred embodiment of the present application, the container wall comprising an integrated mounting structure;

[0049] Figure 2 For along Figure 1 The cross-sectional view taken along line AA in FIG.

[0050] Figure 3 for Figure 2 A partial enlarged view of part I;

[0051] Figure 4 is a three-dimensional schematic diagram of a first main insulating plate;

[0052] Figure 5 is another three-dimensional schematic diagram of the first main insulating plate;

[0053] Figure 6 is along Figure 4 The cross-sectional view taken along line BB in FIG.

[0054] Figure 7 is a schematic diagram of a preferred embodiment of the first anchoring element;

[0055] Figure 8 yes Figure 2 A partial enlarged view of part II;

[0056] Fig. 9 is a perspective schematic diagram of a second main insulating plate;

[0057] Fig.10 is another perspective schematic diagram of a second main insulating plate;

[0058] Fig.11 is along Fig. 9 The cross-sectional view taken along the CC line in FIG.

[0059] Fig.12 is a schematic diagram of a preferred embodiment of the second outer anchoring element;

[0060] Fig.13 is a schematic diagram of a preferred embodiment of the second inner anchoring element;

[0061] Fig.14 is a schematic diagram of a preferred embodiment of the third anchoring element;

[0062] Fig.15 is a schematic diagram of a preferred embodiment of a secondary insulation board;

[0063] Fig.16 is a schematic diagram of an assembly formed by mounting a second outer anchoring element to a secondary insulating panel;

[0064] Fig.17 This is a schematic diagram of the shielding film;

[0065] Fig.18 is a schematic diagram of an integrated component formed by prefabricating and connecting a secondary shielding membrane and a first main insulating plate;

[0066] Fig.19 This is a schematic diagram of the layout of the insulation box;

[0067] Fig. 20 yes Fig.18 A schematic diagram showing the installation of the integrated component to the secondary insulation box;

[0068] Fig.21 is Fig. 20 Schematic diagram of installing a second main insulating board on the foundation;

[0069] Fig. 22 is Fig.21 A schematic diagram of installing a third anchoring element on the foundation;

[0070] Fig.23 is a schematic diagram of another preferred embodiment of the first connecting device;

[0071] Fig.24 yes Fig.23 An exploded schematic diagram of the first connecting device shown;

[0072] Fig.25 is a schematic diagram of another preferred embodiment of the second connecting device;

[0073] Fig.26 yes Fig.25 An exploded schematic diagram of the second connecting device is shown. DETAILED DESCRIPTION

[0074] Now, with reference to the accompanying drawings, the specific embodiments of the present application are described in detail. What is described here is only the preferred embodiment of the present application. Those skilled in the art can think of other ways to implement the present application based on the preferred embodiment, and the other ways also fall within the scope of the present application.

[0075] The present application provides an integrated mounting structure for marine equipment, a storage container having the integrated mounting structure, and a corresponding manufacturing method. The storage container can be used for marine engineering equipment or land engineering equipment, for example, for storing liquefied gas such as liquefied natural gas (LNG), liquid nitrogen, liquid oxygen, liquid hydrogen, liquid ammonia, and liquid helium.

[0076] First of all, it should be noted that the directional terms and positional terms mentioned in this application are only exemplary descriptions and not restrictive descriptions. The description of the position of a component should be understood as a relative position rather than an absolute position, and the description of the extension direction of a component should be understood as a relative direction rather than an absolute direction.

[0077] Figure 1An integrated mounting structure 1 according to a preferred embodiment of the present application is shown. The integrated mounting structure 1 is used to form a part of a container wall of a storage container. The integrated mounting structure 1 can realize the integrated mounting of various components of the container wall (especially various layers of the container wall). The following will be described in detail with reference to the accompanying drawings.

[0078] like Figure 1 and Figure 2 As shown, the integrated mounting structure 1 includes, from the outside to the inside of the container, a secondary insulating layer 10, a secondary shielding film 20, a primary insulating layer 30, and a primary shielding film 40. That is, the primary shielding film 40 is located at the innermost side of the container wall, in contact with the contents (e.g., LNG) in the storage container, and the secondary insulating layer 10 is located at the outermost side, which can be connected to the secondary insulating polyurethane layer 50 on the outside. The secondary insulating layer 10 can be integrally connected to the secondary insulating polyurethane layer 50 by gluing, and the two are combined together to form a secondary insulating box. In practical applications, the secondary insulating box can be connected to other parts of the container wall.

[0079] refer to Figures 4 to 6 , Figures 9 to 11 , Fig.18 and Fig.21 , the main insulating layer 30 is formed by arranging at least one first main insulating plate 31 and at least one second main insulating plate 32. The first main insulating plate 31 and the second main insulating plate 32 can both be constructed in the form of wooden plywood. According to the present application, the first main insulating plate 31 can be connected to the secondary shielding membrane 20 by a first connecting device to form an integrated component. The second main insulating plate 32 can be installed to the secondary shielding membrane 20 during the assembly process of the storage container by a second connecting device. That is to say, at least a portion of the main insulating layer 30 can be prefabricated with the secondary shielding membrane 20 in the factory as an integrated component, so that the steps and man-hours required for the on-site construction of the main insulating layer 30 during the construction of the storage container can be reduced, thereby achieving the purpose of simplifying the process and speeding up the construction period. Especially for large storage containers that can accommodate hundreds of thousands of cubic meters of content, due to the large volume, a part of the container wall of the storage container is located at a high place, and the entire installation and construction period has a considerable amount of man-hours related to high-altitude operations. According to the solution of the present application, by simplifying the laying process of the main insulation layer 30, a part of the on-site installation operation is converted into a factory prefabrication operation, thereby significantly reducing the duration of high-altitude operations during the construction of the storage container, which can not only speed up the construction period, but also help improve construction safety.

[0080] Figure 2 and Figure 3A first connecting device 100 according to a preferred embodiment is shown. Specifically, the first connecting device 100 includes a first anchor 101 and a first fastener 105. The first anchor 101 is connected to the inner side of the secondary shielding film 20. The first fastener 105 passes through the first main insulating plate 31 and is connected to the first anchor 101, so that the first main insulating plate 31 is connected to the secondary shielding film 20 through the first anchor 101 to form an integrated component.

[0081] like Figures 4 to 6 As shown, the first main insulating plate 31 is provided with a first recess 311 on the outer side facing the secondary shielding film 20. When the first main insulating plate 31 and the secondary shielding film 20 are prefabricated and connected as an integral component, at least a portion of the first anchor 101 is accommodated in the first recess 311. Preferably, the first anchor 101 is completely accommodated in the first recess 311 as a whole. In this way, the first anchor 101 can avoid interference between the first main insulating plate 31 and the secondary shielding film 20, allowing the two to fit closely.

[0082] Figure 7 A preferred embodiment of the first anchor 101 is shown, which includes a flat plate portion 103 and a ridge portion 102 protruding relative to the flat plate portion 103. The flat plate portion 103 is used to connect with the secondary shielding membrane 20. In some embodiments, the first anchor 101 and the secondary shielding membrane 20 can be made of metal materials, and the flat plate portion 103 can be connected to the secondary shielding membrane 20 by welding or the like. At least one connecting hole 104 is provided at the top of the ridge portion 102 for connecting with the first fastener 105. Preferably, the first anchor 101 can be constructed as a flat plate structure, and the ridge portion 102 and the connecting hole 104 are formed by stamping or the like.

[0083] In some embodiments, the first fastener 105 may be a rivet fastener that passes through the first anchor hole 313 of the first main insulating plate 31 and the connection hole 104 of the ridge 102 to achieve a fastened connection. It is understood that in other embodiments, the first fastener 105 may also be a screw, a bolt, a nut, a pin, or any other part suitable for fastening two or more separate components into one. Figure 3 It can be seen that the first fastener 105 includes a connecting column for passing through these elements and a radially enlarged cap located at both ends of the connecting column for fastening. Among them, the cap located at the lower end is accommodated in the internal space of the ridge 102. The first main insulating plate 31 is provided with a second recess 312 on the inner side facing away from the secondary shielding membrane 20. The cap located at the upper end is accommodated in the second recess 312. Preferably, the above-mentioned cap is completely accommodated in the second recess 312, that is, it is lower than the inner side of the first main insulating plate 31. This arrangement can prevent the first fastener 105 from interfering with the subsequent fitting between the main shielding membrane 40 and the main insulating layer 30.

[0084] Fig.23 and Fig.24 A first connection device 100 according to another preferred embodiment is shown, wherein each layer of the integrated mounting structure follows the same Figure 3 The same reference numerals are used for the embodiments shown. Fig.23 and Fig.24 In the embodiment of the present invention, the first connecting device 100 includes a first connecting column 401 fixed on the secondary shielding film 20 and an anchoring gasket 402 arranged on the first main insulating plate 31. The first connecting column 401 is arranged on the inner side of the secondary shielding film 20 facing the main insulating layer, one end of which can be connected and fixed to the secondary shielding film 20 by welding or the like, and the other end can be provided with a connection feature for cooperating with the second fastener 403. In the illustrated embodiment, the second fastener 403 is a nut, and accordingly, the connection feature of the first connecting column 401 can be a threaded portion. It can be understood that when the second fastener 403 is constructed in a form other than a nut, the connection feature can change accordingly with the specific form of the second fastener 403.

[0085] The anchoring gasket 402 is generally configured as a plate-like structure and has a hole for the first connecting column 401 to pass through. For example, the anchoring gasket 402 can be specifically configured as a gasket or a washer. Figure 3 Similar to the embodiment shown, the inner side surface of the first main insulating plate 31 is provided with a second recess 312, and the bottom surface thereof is provided with an anchor hole 313 penetrating the first main insulating plate 31. During prefabrication, the first main insulating plate 31 is arranged on the inner side surface of the secondary shielding film 20, so that the first connecting column 401 passes through the anchor hole 313 and its end is located in the second recess 312. Then the anchoring gasket 402 can be placed in the second recess 312 and sleeved on the first connecting column 401. Then the second fastener 403 can be installed at the end of the first connecting column 401 and pressed against the anchoring gasket 402 to achieve a fastened connection. Among them, the anchoring gasket 402 is supported by the bottom surface of the second recess 312.

[0086] It can be understood that in order to facilitate distinction from the similar structure of the second connecting device, the first anchor 101 and the anchor gasket 402 can be collectively referred to as a first anchor element, and the first fastener 105 and the second fastener 403 can be collectively referred to as a first fastening element.

[0087] Figure 2 and Figure 8A second connecting device 200 according to a preferred embodiment is shown. In addition to connecting the secondary shielding film 20 and the second main insulating plate 32 of the main insulating layer 30, the second connecting device 200 also connects the secondary insulating layer 10 to the former two. According to the present application, the setting of the first connecting device 100 can be prefabricated in advance in the factory before the on-site construction of the storage container. Unlike the first connecting device 100, the setting of the second connecting device 200 needs to be operated at the construction site.

[0088] Specifically, the second connecting device 200 includes a secondary anchor 201, a second main anchor 205 and a third fastener 208. The secondary anchor 201 is connected to the secondary insulating layer 20. More specifically, the secondary insulating layer 10 is composed of a plurality of secondary insulating plates 11 arranged in an arranged manner. Fig.15 and 16 As shown, the secondary insulating board 11 can also be constructed in the form of a wooden plywood, and a first mounting groove 111 is provided on the inner side thereof facing the secondary shielding film 20. The secondary anchor 201 is embedded in the first mounting groove 111. Fig.12 The secondary anchor 201 is generally configured as a plate-like structure, which is provided with a first fixing hole 202 for the third fastener 208 to pass through. Preferably, when the secondary anchor 201 is embedded in the first mounting groove 111, the surface of the plate-like structure is substantially flush with the inner side surface of the secondary insulating board 11. Preferably, the secondary anchor 201 can also be more firmly embedded in the first mounting groove 111 by additional fasteners such as screws or rivets. To this end, the secondary anchor 201 is provided with a mounting hole 204 for the additional fastener to pass through. Preferably, the operation of installing the secondary anchor 201 to the secondary insulating board 11 can be prefabricated in a factory.

[0089] The second main anchor 205 is disposed on the second main insulating plate 32. Fig.13 As shown, in some embodiments, the second main anchor 205 can be constructed as a plate-like structure and have a second fixing hole 206 for the third fastener 208 to pass through. Figures 8 to 11 The inner side surface of the second main insulating plate 32 is provided with a third recess 321, and a second anchor hole 322 is provided on the bottom surface of the third recess 321 and penetrates the second main insulating plate 32. The second main anchor 205 is arranged in the third recess 321 and supported by the bottom surface thereof. In this way, the second main anchor 205 can be fixed in a simple manner, thereby omitting an additional fastener for fixing the main anchor, which is beneficial to reducing the weight of the wall of the storage container and is easy to install.

[0090] In addition, the secondary shielding membrane 20 is provided with a through hole 23 at a position corresponding to the second anchor 201. After the second main insulating plate 32 is installed in place, the third fastener 208 can be used to pass through (or reversely pass through) the second fixing hole 206 of the second main anchor 205, the second anchor hole 322 of the second main insulating plate 32, the through hole 23 of the secondary shielding membrane 20, and the first fixing hole 202 of the second anchor 201 in sequence to fasten the second main insulating plate 32, the secondary shielding membrane 20, and the secondary insulating plate 11 together. In some embodiments, the third fastener 208 can be a screw and a nut. Depending on the actual design, the nut can be located on one side of the secondary insulating plate 11 or on one side of the second main insulating plate 32. In some embodiments, the screw or the nut can also be set as a structure integrated with the second anchor 201. It can be understood that in other embodiments, the third fastener 208 can also be a screw, a rivet, a pin or any other part suitable for fastening two or more separate components into one. From Figure 8 It can be seen that the third fastener 208 is formed with a cap having a blocking and fastening function on the inner side of the second main anchor 205. Preferably, the cap is completely accommodated in the third recess 321, that is, it is lower than the inner side of the second main insulating plate 32. This arrangement can prevent the third fastener 208 from interfering with the subsequent bonding between the main shielding film 40 and the main insulating layer 30.

[0091] Fig.25 and Fig.26 FIG. 2 shows a second connection device 200 according to another preferred embodiment. Figure 8 The same reference numerals are used for the embodiments shown. Fig.25 and Fig.26 In the illustrated embodiment, the inner side surface of the third anchor 501 is provided with a second connecting column 502 protruding toward the secondary shielding film 20. The second connecting column 502 can be fixed to the main structure of the third anchor 501 by welding, or can be integrally formed with the third anchor 501. The end of the second connecting column 502 can be provided with a connecting feature for cooperating with the fourth fastener 504. In the illustrated embodiment, the fourth fastener 504 is a nut, and accordingly, the connecting feature of the second connecting column 502 can be a threaded portion. It can be understood that when the fourth fastener 504 is constructed in a form other than a nut, the connecting feature can change accordingly with the specific form of the fourth fastener 504.

[0092] The third anchor 501 can be fixed to the secondary insulating board in the same manner as Figure 8 The secondary anchor 201 in the illustrated embodiment is substantially the same. And the third primary anchor 503 may be similar to Figure 8The second main anchors 205 in the illustrated embodiment have substantially the same structure and arrangement.

[0093] During assembly, the secondary shielding membrane 20 is first laid on the secondary insulating layer 10 so that the second connecting column 502 of the third anchor 501 passes through the through hole 23 on the secondary shielding membrane 20. Then the second main insulating plate 32 is laid on the inner side of the secondary shielding membrane 20, and the second connecting column 502 passes through the second anchor hole 322. Next, the third main anchor 503 can be placed in the third recess 321 and sleeved on the second connecting column 502. Finally, the fourth fastener 504 can be connected to the end of the second connecting column 502 and pressed against the third main anchor 503 to achieve a fastened connection. Preferably, a gasket 505 can also be provided, which is clamped between the fourth fastener 504 and the third main anchor 503. The gasket 505 can be an elastic gasket that can provide a certain elasticity in the axial direction of the connection and can prevent the fourth fastener 504 from loosening.

[0094] It can be understood that the force borne by the second connection device 200 is significantly greater than the force borne by the first connection device 100. Therefore, the size of the third main anchor 503 in the second connection device 200 can be larger than the size of the anchoring pad 402 of the first connection device 100. For example, a standard-sized pad or washer can be used as the anchoring pad 402, but a larger-sized component is required for the third main anchor 503.

[0095] It can be understood that, for the sake of distinction, the secondary anchor 201 and the tertiary anchor 501 can be collectively referred to as the second outer anchor element, the second main anchor 205 and the third main anchor 503 can be collectively referred to as the second inner anchor element, and the third fastener 208 or the fourth fastener 504 connecting the two can be collectively referred to as the second fastening element. The second connecting column 502 and the first connecting column 401 described above can be collectively referred to as the connecting column.

[0096] Preferably, in order to facilitate the fixation and connection of the secondary shielding membrane 20, the secondary anchor 201 is provided with a boss portion 203 on the inner side, which is preferably located at the center of the plate-like structure and is roughly square in shape. The through hole 23 of the secondary shielding membrane 20 can have a shape roughly the same as the boss portion 203 and a slightly larger size. In this way, the boss portion 203 of the secondary anchor 201 can extend from the through hole 23, facilitating the welding operation between the boss portion 203 and the secondary shielding membrane 20. Further preferably, the outer side of the second main insulating plate 32 facing the secondary shielding membrane 20 is provided with a fourth recess 323, which can have a shape and size roughly the same as the through hole 23. The portion of the boss portion 203 extending beyond the secondary shielding membrane 20 can be accommodated in the fourth recess 323, thereby avoiding the boss portion 203 from extending too much and interfering with the fitting between the layers.

[0097] Preferably, the secondary anchor 201 is provided with a first fixing hole 202 for the third fastener 208 to pass through, rather than providing a bolt or other structure used as the third fastener 208 at this position. In this way, during the on-site construction process, after the secondary shielding membrane 20 is hoisted in place, the temporary fastener 302 (see Fig. 20 ) is screwed into the first fixing hole 202 to temporarily fix the secondary shielding membrane 20, which is conducive to the smooth progress of the welding operation. After the welding is completed, the temporary fastener 302 is removed, and the next step of laying the second main insulation board 32 and installing the second connecting device 200 can be carried out.

[0098] After the second main insulating plate 32 is laid and installed, the main shielding film 40 can be laid and installed. The main shielding film 40 can be connected to the main insulating layer 30 through the main shielding film anchoring piece installed on the inner side of the main insulating layer 30. Fig.14 A preferred embodiment of a main shielding film anchor 301 for connecting the main shielding film 40 is shown. It can be seen that the main shielding film anchor 301 has a similar structure to the secondary anchor 201 of the second connecting device 200 installed on the secondary insulating plate 11, which is also constructed as a plate-like structure. After the main shielding film 40 is hoisted in place, the main shielding film 40 and the main shielding film anchor 301 can be welded and fixed through the through hole 23 of the main shielding film 40, so that the main shielding film 40 is connected to the main insulating layer 30.

[0099] Preferably, similar to the secondary insulating plate 11, the inner side surface of the main insulating plate for mounting the above-mentioned main shielding membrane anchor 301 is provided with a mounting groove, and the main shielding membrane anchor 301 is embedded in the mounting groove. Furthermore, similar to the secondary anchor 201 of the above-mentioned second connecting device 200, the main shielding membrane anchor 301 can also be more firmly embedded in the mounting groove of the main insulating plate by additional fasteners such as screws or rivets. To this end, the main shielding membrane anchor 301 is provided with a mounting hole 204 for the additional fastener to pass through, and the main insulating plate is provided with an additional mounting hole for the additional fastener to pass through. Preferably, when the main shielding membrane anchor 301 is embedded in the mounting groove, the surface of its plate-like structure is roughly flush with the inner side surface of the main insulating plate. Of course, for the main shielding membrane anchor 301, there is no need to set a structure similar to the first fixing hole 202 in its center.

[0100] In order to facilitate the connection of the main shielding film 40, a boss portion 203 similar to the secondary anchor 201 can also be provided on the main shielding film anchor 301, which is preferably located at the center of the plate-like structure and is roughly square in shape. The through hole 23 of the main shielding film 40 can have a shape roughly the same as the boss portion 203 and a slightly larger size. In this way, the boss portion 203 of the main shielding film anchor 301 can extend from the through hole 23 of the main shielding film 40, facilitating the welding operation between the boss portion 203 and the main shielding film 40.

[0101] Fig. 9 The second mounting groove 325 and the additional mounting hole 324 provided on the second main insulating plate 32 are shown. Preferably, the second mounting groove 325 is provided at a position corresponding to the third recess 321, so that the connection force between the layers is transmitted approximately at the same position of the storage container wall, which is conducive to uniform force and avoids stress concentration. It can be understood that the structure related to the installation of the main shielding membrane anchor 301 can also be provided on the first main insulating plate 31. And the installation position of the main shielding membrane anchor 301 can preferably correspond to the position of the first connecting device. It can be understood that, for the sake of distinction, the main shielding membrane anchor 301 used to install the main shielding membrane 40 can also be referred to as a third anchoring element. In addition, the second mounting groove 325 and the first mounting groove 111 described above can be collectively referred to as mounting grooves.

[0102] Combine the following Figures 18 to 22 The installation steps of the integrated installation structure according to the present application are introduced.

[0103] First, some parts are prefabricated in a processing factory, for example, the first main insulating plate 31 is prefabricated and connected with the secondary shielding film 20 by a first connecting device to form an integrated component 24 (see Fig.18 ), the second outer anchor 201 is installed to the secondary insulation board 11 to form a secondary insulation board assembly 12 (see Fig.16 ) etc. Preferably, a first main insulating plate 31 or a second main insulating plate 32 is arranged in each of the multiple regions enclosed by the longitudinal corrugations 21 and the transverse corrugations 22 of the corrugated plate.

[0104] Through prefabrication, as many installation steps as possible can be transferred from the construction site to the processing factory. On the one hand, the processing factory has a better working environment than the construction site, such as permanent production lines, safer protective measures, etc., which can have higher processing efficiency, processing quality (improve yield rate) and safety. On the other hand, it can also reduce the operations on the construction site, especially reducing high-altitude operations, which is conducive to shortening the construction period and thus improving the safety of the construction site.

[0105] Next, the secondary insulation board assembly 12 can be integrally connected to the secondary insulation polyurethane layer 50 by gluing, and the two are combined together to form a Fig.19 The secondary insulation box shown. Depending on the actual situation, this step can be completed on the construction site or prefabricated in a processing factory.

[0106] Then, if Fig. 20 As shown, the first main insulating plate 31 and the secondary shielding membrane 20 can be prefabricated and connected to form an integrated component 24 to be installed in the secondary insulating box. Preferably, after the integrated component 24 is hoisted in place, the temporary fastener 302 can be screwed into the first fixing hole 202 of the second outer anchor 201 on the secondary insulating plate 11 to temporarily fix the integrated component 24, so as to complete the welding fixation between the secondary shielding membrane 20 and the boss portion 203 of the second outer anchor 201.

[0107] After welding is completed, the temporary fasteners 302 can be removed and the second main insulating plate 32 can be installed in place through the second connecting device 200. Fig.21 As shown, in the main insulating layer 30, the arrangement of the first main insulating plate 31 and the second main insulating plate 32 mainly considers two aspects. On the one hand, the number of the second main insulating plates 32 is reduced as much as possible to reduce the operation of the main insulating layer 30 at the construction site. On the other hand, it is also necessary to take into account that the number of connections between the main insulating layer 30 and the secondary insulating layer 10 (i.e., the number of second main insulating plates 32) can provide sufficient strength, and the connection force between the two is evenly distributed (i.e., a sufficient number of second main insulating plates 32 are dispersedly arranged). Specifically, the arrangement can be such that each second main insulating plate 32 is arranged adjacent to at least one first main insulating plate 31, and / or any two second main insulating plates 32 are not adjacent.

[0108] After the second main insulating plate 32 is installed, Fig. 22 As shown, the main shielding film anchor 301 is installed to the corresponding first main insulating plate 31 and / or second main insulating plate 32. After that, the main shielding film 40 can be hoisted in place and welded to the boss portion 203 of the main shielding film anchor 301 through the through hole 23 of the main shielding film 40, so that the main shielding film 40 is connected to the main insulating layer 30. The integrated installation structure 1 after the main shielding film 40 is installed is as shown in FIG. Figure 1 shown.

[0109] On the other hand, the present application also provides a storage container, which includes the integrated mounting structure 1 as described above, and the integrated mounting structure 1 forms a part of the container wall of the storage container. Specifically, the storage container can be used to store liquefied gas, such as liquefied natural gas, liquid nitrogen, liquid oxygen, liquid hydrogen, liquid ammonia and liquid helium.

[0110] In some embodiments, the storage container is a large land-based storage tank. The storage container is suitable for marine equipment and also suitable for large land-based storage tanks.

[0111] The above description of the various embodiments of the present application is provided to a person of ordinary skill in the relevant field for the purpose of description. It is not intended that the present application be exclusive or limited to a single disclosed embodiment. As above, a person of ordinary skill in the field of the above teaching will understand the various substitutions and modifications of the present application. Therefore, although some alternative embodiments are specifically described, a person of ordinary skill in the art will understand or relatively easily develop other embodiments. The present application is intended to include all substitutions, modifications and variations of the present application described herein, as well as other embodiments falling within the spirit and scope of the present application described above.

Claims

1. An integrated mounting structure for marine equipment, the integrated mounting structure being used to form at least a portion of a wall of a storage container, characterized in that: The integrated mounting structure comprises: A main insulating layer (30), wherein the main insulating layer (30) is composed of at least one first main insulating plate (31) and at least one second main insulating plate (32); A secondary insulating layer (10), the secondary insulating layer (10) being arranged on the outer side of the primary insulating layer (30) as defined by the storage container, the secondary insulating layer (10) being composed of an arrangement of secondary insulating plates (11); and A secondary shielding membrane (20), the secondary shielding membrane (20) being arranged between the primary insulating layer (30) and the secondary insulating layer (10), wherein the first primary insulating plate (31) is prefabricated and connected to the secondary shielding membrane (20) via a first connecting device (100) as an integral component, and the second primary insulating plate (32) is a structure separate from the secondary shielding membrane (20) and connected to the secondary insulating plate (11) via a second connecting device (200); The first connecting device comprises: a first connecting post connected to an inner side surface of the secondary shielding film; a first anchoring element, the first anchoring element being disposed on the first main insulating plate, the first connecting column passing through the first anchoring element; and a first fastening element connected to the first connecting column at an inner side of the first anchoring element to fasten the first anchoring element and the secondary shielding membrane together; Alternatively, the first connecting device (100) comprises: a first anchoring element connected to the inner side of the secondary shielding membrane (20); and A first fastening element, wherein the first fastening element passes through the first main insulating plate (31) and the first anchoring element to fasten the first main insulating plate (31) and the first anchoring element together.

2. The integrated installation structure according to claim 1, characterized in that: Each of the second main insulating plates (32) is arranged adjacent to at least one of the first main insulating plates (31), and / or any two of the second main insulating plates (32) are not adjacent to each other.

3. The integrated installation structure according to claim 1, characterized in that: A first recess (311) is provided on the outer side surface of the first main insulating plate (31) facing the secondary shielding membrane (20); when the first main insulating plate (31) and the secondary shielding membrane (20) are prefabricated and connected as an integral component, at least a portion of the first anchoring element is accommodated in the first recess (311).

4. The integrated installation structure according to claim 3, characterized in that: The first anchoring element comprises a flat plate portion (103) and a ridge portion (102) protruding relative to the flat plate portion (103), the flat plate portion (103) being connected to the secondary shielding membrane (20), and the first fastening element passes through the first main insulating plate (31) and is fastened to the ridge portion (102).

5. The integrated installation structure according to claim 1, characterized in that: The first fastening element comprises a connecting column and a cap located at the end of the connecting column, and the inner side surface of the first main insulating plate (31) facing away from the secondary shielding membrane (20) is provided with a second recess (312), and the cap is accommodated in the second recess (312) and is lower than the inner side surface of the first main insulating plate (31).

6. The integrated installation structure according to claim 1, characterized in that: A second recess is provided on an inner side surface of the first main insulating plate facing away from the secondary shielding film, and the first anchoring element is disposed in the second recess and supported by a bottom surface of the second recess.

7. The integrated mounting structure according to claim 6, characterized in that: The first fastening element is received in the second recess and is lower than the inner side surface of the first main insulating plate.

8. The integrated mounting structure according to claim 1, characterized in that: The second connecting device (200) comprises: a second outer anchoring element, the second outer anchoring element being arranged on the inner side of the secondary insulating plate (11) facing the secondary shielding film (20), a second inner anchoring element, the second inner anchoring element being arranged on the second main insulating plate (32), and A second fastening element, the secondary shielding membrane having a through hole (23), the second fastening element passing through the second inner anchoring element, the secondary shielding membrane (20) and the second outer anchoring element from the inner side of the second inner anchoring element, so as to fasten the second main insulating plate (32), the secondary shielding membrane (20) and the secondary insulating plate (11) together.

9. The integrated mounting structure according to claim 8, characterized in that: The second outer anchoring element is constructed as a plate-like structure, the plate-like structure is provided with a first fixing hole (202), wherein the second fastening element passes through the first fixing hole (202) and is fastened to a nut, or a threaded portion is provided in the first fixing hole (202), and the second fastening element is connected to the first fixing hole (202) via the threaded portion.

10. The integrated mounting structure according to claim 9, characterized in that: The plate-like structure is provided with a boss portion (203) protruding from the inner side surface facing the secondary shielding membrane (20), the through hole (23) of the secondary shielding membrane (20) has a shape substantially the same as that of the boss portion (203) for allowing the boss portion (203) to pass through, and the secondary shielding membrane (20) is welded to the boss portion (203).

11. The integrated mounting structure according to claim 10, characterized in that: The outer side surface of the second main insulating plate (32) facing the secondary shielding film (20) is provided with a fourth recess (323) for accommodating at least a part of the boss portion (203).

12. The integrated mounting structure according to claim 1, characterized in that: The second connecting device comprises: a second inner anchoring element, said second inner anchoring element being arranged on said second main insulating plate, a second outer anchoring element, the second outer anchoring element being disposed on an inner side of the secondary insulating plate facing the secondary shielding film, the second outer anchoring element having a second connecting column extending toward the secondary shielding film, the second connecting column passing through the secondary shielding film and the second inner anchoring element; and A second fastening element is connected to the second connection column at an inner side of the second inner anchoring element to fasten the second main insulating plate, the secondary shielding film, and the secondary insulating plate together.

13. The integrated mounting structure according to claim 12, characterized in that: The second outer anchoring element is configured as a plate-like structure, and the second connecting column is welded to the plate-like structure, or the second connecting column is integrally formed with the plate-like structure.

14. The integrated mounting structure according to claim 9 or 13, characterized in that: The inner side surface of the secondary insulating plate is provided with a mounting groove, and the plate-like structure is embedded in the mounting groove and fastened in the mounting groove by an additional fastener.

15. The integrated mounting structure according to claim 8 or 12, characterized in that: The inner side surface of the second main insulating plate facing away from the secondary shielding film is provided with a third recess, the bottom surface of the third recess is provided with an anchor hole penetrating the second main insulating plate, and the second inner anchoring element is arranged in the third recess and supported by the bottom surface of the third recess.

16. The integrated mounting structure according to claim 15, characterized in that: The second fastening element comprises or forms a cap located inside the second inner anchoring element, the second inner anchoring element and the cap of the second fastening element are both received in the third recess and below the inner side of the second main insulating plate.

17. The integrated mounting structure according to claim 1, characterized in that: The integrated mounting structure also includes a main shielding membrane (40), which is arranged on the inner side of the main insulating layer (30) facing away from the secondary shielding membrane (20), and a third anchoring element (301) is arranged on the inner side of the first main insulating plate (31) and / or the second main insulating plate (32) facing the main shielding membrane (40), and the main shielding membrane (40) is connected to the third anchoring element (301).

18. The integrated mounting structure according to claim 17, characterized in that: The position of the third anchoring element (301) arranged on the first main insulating plate (31) coincides with the first connecting device (100) along the thickness direction of the first main insulating plate (31), and / or the position of the third anchoring element (301) arranged on the second main insulating plate (32) coincides with the second connecting device (200) along the thickness direction of the first main insulating plate (31).

19. The integrated mounting structure according to claim 17, characterized in that: The third anchoring element (301) is constructed as a plate-like structure, the plate-like structure is provided with a boss portion (203) protruding from the inner side surface facing the main shielding membrane (40), and the main shielding membrane (40) is provided with a through hole (23) for the boss portion (203) to pass through and having a shape substantially the same as that of the boss portion (203).

20. The integrated mounting structure according to claim 19, characterized in that: The inner side surface of the first main insulating plate (31) and / or the second main insulating plate (32) provided with the third anchoring element (301) is provided with a mounting groove, and the plate-like structure is embedded in the mounting groove and fastened in the mounting groove by an additional fastener.

21. The integrated mounting structure according to claim 1, characterized in that: The secondary shielding membrane (20) is constructed as a corrugated plate made of a metal material, on which a plurality of transverse corrugations (22) and a plurality of longitudinal corrugations (21) are formed, and two adjacent transverse corrugations (22) and two adjacent longitudinal corrugations (21) cross to form an installation area, and each of the installation areas is provided with a first main insulating plate (31) or a second main insulating plate (32).

22. A storage container, characterized in that: Comprising an integrated mounting structure as described in any one of claims 1-21, wherein the integrated mounting structure forms a part of a container wall of the storage container.

23. The storage container according to claim 22, characterized in that: The storage container is a large land-based storage tank.

24. A method for manufacturing a storage container according to claim 22 or 23, characterized in that: The production method comprises the following steps: manufacturing the secondary insulating layer; making an integrated prefabricated component including the secondary shielding membrane and the first main insulating plate; Install the secondary insulation layer to form a secondary insulation box; fixing the integrated prefabricated component on the inner side of the secondary insulating layer; Laying the second main insulating plate on the inner side of the secondary shielding film and connecting it to the secondary insulating layer; A primary shielding film is mounted on the inner side of the primary insulating layer.

25. The manufacturing method according to claim 24, characterized in that: The construction site of the manufacturing method at least includes an on-site construction side and a factory prefabrication side, wherein at least the step of manufacturing the integrated prefabricated component is completed at the factory prefabrication side.

Citation Information

Patent Citations

  • Cargo oil hold heat insulating structure for liquefied gas tanker

    JP1993085463A