A suspension bridge cable system dismantling bracket and use method thereof
By designing the suspension bridge cable system to remove the bracket and using the combined structure of the bracket main body and the hanging basket wire rope, the cumbersome and safety hazards of high-altitude operations during the removal of the suspension bridge cable system is solved, and efficient, safe and green construction results are achieved.
Patent Information
- Application Number
- CN202411154388.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-22
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2044-08-22
AI Technical Summary
During the dismantling of the suspension bridge cable system, high-altitude operations are cumbersome and dangerous. The existing hanging basket installation is cumbersome and consuming materials, which affects the construction progress and safety, and poses a hidden danger of falling from high altitudes.
Design a suspension bridge cable system to remove the bracket, including the bracket main body, connecting parts and multiple hanging basket wire ropes, which are fixed to the main cable and beam body through the connecting parts and hanging basket wire ropes, achieving stable support and movement. The bracket main body includes an upper diagonal support rod The components, longitudinal beams, columns and clasps support reuse and height adjustment to ensure smooth removal.
It improves the removal efficiency and safety, saves materials, reduces operating risks, realizes efficient, green and safe demolition of the suspension bridge cable system, and simplifies the construction operation process.
Smart Images

Figure CN118668607B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of suspension bridge dismantling construction, and more specifically, to a suspension bridge cable system dismantling bracket and a method for using the bracket. Background Art
[0002] A self-anchored suspension bridge is a suspension bridge system that does not have a gravity anchor, but anchors the main cable at the end of the stiffening beam to bear the horizontal and vertical forces at the end of the main cable. The removal of its cable system mainly includes: cable removal, cable clamp removal, wire wrapping and coating removal, etc. The most important thing in the removal construction of the cable system of a suspension bridge is the high-altitude working channel and temporary working site. The high-altitude work of removing the cable superstructure, cable clamp, and wire wrapping coating system is very cumbersome and dangerous. At present, most suspension bridges remove cables, cable clamps, wire wrapping coatings, etc. by installing multiple simple hanging baskets at the part to be removed. The installation process of multiple hanging baskets is cumbersome and consumes materials, which affects the construction progress and the removal efficiency is low. There is also a safety hazard of personnel and construction machinery falling from high altitude due to the instability of the hanging basket.
[0003] Therefore, the present application proposes a suspension bridge cable system dismantling bracket and a method of using the bracket to solve the above technical problems. Summary of the invention
[0004] One object of the present invention is to provide a suspension bridge cable system dismantling bracket and a method of using the same, which can be accurately located at a location to be dismantled during the dismantling of the suspension bridge cable system and can be reused, saving materials and being environmentally friendly, improving construction efficiency, having a reasonable structure, clear functions, and reducing operational risks.
[0005] In order to solve the above technical problems, the present invention provides a suspension bridge cable system dismantling bracket, comprising a bracket body, connecting parts arranged on both sides of the bracket body along the extension direction of the main cable, and a plurality of hanging basket steel ropes connected to the bracket body, the lower end of the connecting part is disassembled and fixed to the main cable, the lower ends of the plurality of hanging basket steel ropes are disassembled and fixedly connected to the beam body, the hanging basket steel ropes are first hoisted on the hanging basket construction platform to the part to be dismantled, and then fixed to the beam body and tightened, and the dismantling bracket is fixed by two connecting parts and a plurality of tightened hanging basket steel ropes to achieve stable support.
[0006] Preferably, the bracket body includes a pair of upper oblique support rods arranged opposite to each other and a longitudinal beam arranged perpendicular to the upper oblique support rods, the longitudinal beam is arranged along the extension direction of the main cable, two connecting members are respectively arranged at both ends of the longitudinal beam, a pair of upper oblique support rods extend in a direction perpendicular to the longitudinal beam and four hanging basket steel ropes are respectively fixed at four end points, and the upper oblique support rods are a trapezoidal frame structure.
[0007] Preferably, the connecting member comprises a vertical member with adjustable height and a clamp provided at the bottom end of the vertical member, the clamp is fastened to the main cable, and the vertical members included in a pair of connecting members have different heights to adapt to the line shape of the main cable.
[0008] Preferably, the vertical member includes a pair of columns and a plurality of cross-links connecting the columns into one, forming a telescopic ladder structure; a pair of columns are assembled in sequence from a plurality of column units, and the two corresponding column units of a pair of columns are connected by cross-links to form an I-shaped structure, and the cross-links and the column units are connected by bolts or grooves and snap-fit ends.
[0009] Preferably, both ends of the clamp are hingedly connected to the bottom ends of a pair of columns through movable hinge supports fixed to the bottom ends of a pair of columns, so as to adapt to the shape of the main cable.
[0010] Preferably, the beam body is provided with a beam body anchoring ear plate, and the lower end of the hanging basket wire rope is disassembled and fixed to the beam body anchoring ear plate; the end of the upper oblique support rod is provided with a wire rope anchor buckle, which is used to connect the upper end of the hanging basket wire rope.
[0011] Preferably, a pair of longitudinal beams are provided with a hand-chain hoist load-bearing buckle in the middle, which is used to connect the hand-chain hoist, and the disassembly and lifting of the parts to be dismantled are achieved through the hand-chain hoist.
[0012] The present invention also provides a method for using a suspension bridge cable system to remove a bracket, comprising the following steps:
[0013] S1. Position the entire disassembly bracket to the part to be disassembled, adjust the height of a pair of connectors on both sides according to the shape of the main cable, adjust the angle of the clamp, and then lock the clamp on the main cable to fix it;
[0014] S2. A person operates the hanging basket construction platform to rise to the part to be demolished through the electric hanging basket wire rope, and connects the lower end of the electric hanging basket wire rope to the beam anchoring ear plate fixed to the beam body;
[0015] S3. After the anchor ear plates of the beam are fixed, tighten the steel wire rope of the electric hanging basket to ensure the stability of the overall dismantling support structure and start the dismantling operation.
[0016] Preferably, after the removal operation in step S3 is completed, step S4 is further included. After the removal operation of one removal site is completed, the removal support is moved to another removal site to be removed, and the removal operation is performed again, which specifically includes the following steps:
[0017] S41, symmetrically loosen the connection between the two electric hanging basket wire ropes at the front end of the removal bracket along the moving direction and the beam body anchoring ear plate, and connect them with the beam body anchoring ear plate at the lower end of the next part to be removed;
[0018] S42, gradually loosen the anchoring of the main cable by the clamp, and at the same time set the winch to synchronously pull the two loosened electric hanging basket wire ropes to drive the removal bracket to move along the main cable. During the movement, the two electric hanging basket wire ropes at the rear end of the removal bracket are synchronously loosened and connected to the beam anchoring ear plate at the lower end of the next part to be removed;
[0019] S43, repeat the above steps S1 to S3 to perform the dismantling operation;
[0020] S44: After completion, continue to repeat the above steps until all the parts to be dismantled are dismantled.
[0021] Preferably, in step S42, during the entire traction process, the hanging basket wire ropes at the front and rear ends form a triangular stable traction until the removal bracket moves to the next removal position.
[0022] The present invention has at least the following beneficial effects:
[0023] 1. The suspension bridge cable system dismantling bracket and use method disclosed in the present invention can be accurately positioned at the part to be dismantled during the dismantling process of the suspension bridge cable system and can be reused, and has the advantages of simple operation, high work efficiency, small safety hazards, saving materials, and being green and environmentally friendly.
[0024] 2. The present invention realizes the multifunctional and convenient operability of the cable system to dismantle the bracket by means of the hand-pulled hoist load-bearing buckle, and realizes the integrated multifunctionality of personnel operating the machinery and the dismantling platform. The hand-pulled hoist can be adaptively positioned at the part to be dismantled while the bracket is moving, thereby reducing the disassembly and other operation processes, achieving the purpose of convenient operation and improving the work efficiency of the mechanical device transportation.
[0025] 3. The present invention can ensure the balance of the device and the stability during movement, reduce safety hazards, and ensure the safety and reliability of personnel operations by providing a clamp, an electric hanging basket wire rope anchor buckle, an electric hanging basket wire rope, and a beam anchoring ear plate.
[0026] 4. The electric hanging basket wire rope anchor buckle, electric hanging basket wire rope and beam anchoring ear plate are provided in the present invention, which can realize the rise and fall of the hanging basket during the demolition process, and can realize the personnel passage and the transportation passage of the convenient mechanical device while ensuring the construction safety. The construction operation is simple and material saving, and the demolition efficiency is improved.
[0027] Other advantages, objectives and features of the present invention will be embodied in part through the following description, and in part will be understood by those skilled in the art through study and practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] Figure 1 It is a structural schematic diagram of a dismantling bracket for a suspension bridge cable system provided by the present invention.
[0029] Figure 2 It is a vertical view of the dismantling bracket of the suspension bridge cable system provided by the present invention.
[0030] Figure 3 It is a cross-sectional view of the dismantling bracket of the suspension bridge cable system provided by the present invention.
[0031] Figure 4 It is a plan view of the dismantling bracket of the suspension bridge cable system provided by the present invention.
[0032] Description of reference numerals:
[0033] 1 upper diagonal bracing rod, 2 longitudinal beam, 3 column, 4 horizontal joint, 5 clamp, 6 hanging basket wire rope anchor buckle, 7 hand chain hoist load-bearing buckle, 8 hanging basket wire rope, 9 beam body anchor ear plate. DETAILED DESCRIPTION
[0034] In order to better understand the purpose, structure and function of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings so that those skilled in the art can implement it according to the description.
[0035] It should be noted that the experimental methods described in the following embodiments are conventional methods unless otherwise specified, and the reagents and materials are commercially available unless otherwise specified; in the description of the present invention, the terms "lateral", "longitudinal", "upper", "lower", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.
[0036] like Figures 1 to 4 As shown, the present invention provides a suspension bridge cable system dismantling bracket, comprising a bracket body, connecting parts arranged on both sides of the bracket body along the extension direction of the main cable, and a plurality of hanging basket steel wire ropes 8 connected to the bracket body, the lower end of the connecting part is disassembled and fixed to the main cable, the lower ends of the plurality of hanging basket steel wire ropes 8 are disassembled and fixedly connected to the beam body, the hanging basket steel wire ropes 8 are first hoisted on the hanging basket construction platform to the part to be dismantled, and then fixed to the beam body and tightened, and the dismantling bracket is fixed by two connecting parts and a plurality of tightened hanging basket steel wire ropes 8 to achieve stable support.
[0037] The support body includes a pair of upper oblique support rods 1 arranged opposite to each other and a longitudinal beam 2 arranged perpendicular to the upper oblique support rod 1. The longitudinal beam 2 is arranged along the extension direction of the main cable, and two connecting members are respectively arranged at the two ends of the longitudinal beam 2. The pair of upper oblique support rods 1 extend in a direction perpendicular to the longitudinal beam 2 and four hanging basket steel wire ropes 8 are respectively fixed at the four end points. The upper oblique support rod 1 is a trapezoidal frame structure. The beam body is provided with a beam body anchoring ear plate 9, and the lower end of the hanging basket steel wire rope 8 is disassembled and fixed to the beam body anchoring ear plate 9; the end of the upper oblique support rod 1 is provided with a wire rope anchor buckle, which is used to connect the upper end of the hanging basket steel wire rope 8. A hand winch load-bearing buckle 7 is provided in the middle of the pair of longitudinal beams 2, which is used to connect the hand winch, and the hand winch is used to realize the disassembly and lifting of the parts to be disassembled.
[0038] In a specific embodiment, electric hanging basket wire rope anchor buckles 6 are welded at both ends of the upper oblique support rod 1; the electric hanging basket wire rope anchor buckle 6 is buckled to the electric hanging basket wire rope 8; the lower end of the electric hanging basket wire rope 8 is buckled to the beam body anchoring ear plate 9; the upper oblique support rod 1 is fixed in parallel to the front and rear ends of the longitudinal beam 2; the longitudinal beam 2 is parallel and symmetrically distributed, and a hand winch load-bearing buckle 7 is welded at one end; parallel and symmetrically distributed columns 3 are welded at the front and rear ends of the longitudinal beam 2; the column 3 is reinforced by welding the cross link 4; the lower end of the column 3 is welded with a clamp 5, which can be fixed to the main cable through the clamp 5.
[0039] Two symmetrically parallel upper oblique bracing members 1 are welded to two symmetrically parallel longitudinal beams 2, the upper oblique bracing members 1 are welded at 90 degrees to the longitudinal beams 2, and the upper oblique bracing members 1 are symmetrically parallel to the front and rear ends of the two symmetrically parallel longitudinal beams 2, and the electric hanging basket wire rope anchor buckles 6 are welded to the left and right ends of the two parallel upper oblique bracing members 1. The upper end of the electric hanging basket wire rope 8 is buckled to the electric hanging basket wire rope anchor buckle 6, and the lower end is buckled to the beam body anchoring ear plate 9, and the beam body anchoring ear plate 9 is anchored to the concrete beam during the demolition construction operation to ensure the stability of the overall structure of the bracket.
[0040] The electric hanging basket wire rope 8 plays different roles in different processes: during the erection of the structure, the hanging basket is installed by two electric hanging basket wire ropes 8 on the same side to achieve the lifting and lowering of the hanging basket. When the hanging basket rises to the support position, the hanging basket wire rope is locked at the anchor point at the same time. In implementation, the hanging basket wire rope is also used to ensure the stability of the hanging basket construction platform structure on both sides. After the hanging basket construction platform is installed, the electric hanging basket wire rope 8 is connected to the beam anchoring ear plate 9 and tightened to fix the entire support.
[0041] In another embodiment, the connecting member includes a height-adjustable vertical member and a clamp 5 provided at the bottom end of the vertical member, the clamp 5 is fastened to the main cable, and the vertical members included in a pair of connecting members have different heights to adapt to the shape of the main cable. The vertical member includes a pair of columns 3 and a plurality of cross-links 4 that connect the columns 3 as a whole, forming a telescopic ladder structure; a pair of columns 3 are assembled in sequence from a plurality of column units, and the two column units corresponding to a pair of columns 3 are connected by cross-links 4 to form an I-shaped structure, and the cross-links 4 and the column units are connected by bolts or grooves and clamping ends. The two ends of the clamp 5 are respectively hingedly connected to the bottom ends of a pair of columns 3 through movable hinge supports fixed to the bottom ends of a pair of columns 3 to adapt to the shape of the main cable.
[0042] The columns 3 are arranged symmetrically in parallel in front and back, and the columns 3 of different heights in front and back are adjustable columns, similar to a telescopic ladder structure. The height adjustment of the structure is achieved by telescoping to adapt to the shape of the main cable line. The columns 3 are welded through the cross-link 4, welded at 90° to the cross-link 4, and arranged in parallel with the longitudinal beam 2 at 90° and welded to the front and rear ends of the longitudinal beam 2. A hand-pulled hoist load-bearing buckle 7 is welded in the middle of the two symmetrically parallel longitudinal beams 2. The lower ends of the columns 3 arranged in parallel in front and back are welded with clamps 5, and the clamps 5 cooperate with high-strength bolts to ensure that the bracket is fastened to the main cable, ensure that the bracket is fixed at the location to be removed, and ensure the stability of the structure during construction. The connection between the clamp 5 and the lower end of the pillar is similar to a movable hinge support, which can realize angle rotation. Combined with the adjustment of the height of the above-mentioned column 3, the shape of the main cable line can be adapted.
[0043] The present invention also provides a method for using a suspension bridge cable system to remove a bracket, comprising the following steps:
[0044] S1. Position the entire disassembly bracket to the position to be disassembled, adjust the height of a pair of connectors on both sides according to the shape of the main cable, adjust the angle of the clamp 5, and then lock the clamp 5 on the main cable to fix it;
[0045] S2, personnel operate the hanging basket construction platform to rise to the part to be demolished through the electric hanging basket wire rope 8, and connect the lower end of the electric hanging basket wire rope 8 to the beam anchoring ear plate 9 fixed to the beam body;
[0046] S3. After the beam anchoring lugs 9 are fixed, the electric hanging basket wire rope 8 is tightened to ensure the stability of the overall disassembly support structure, and the disassembly operation begins;
[0047] S4. After the demolition operation of one demolition part is completed, the demolition support is moved to another part to be demolished, and the demolition operation is performed again, which specifically includes the following steps:
[0048] S41, symmetrically loosen the connection between the two electric hanging basket wire ropes 8 at the front end of the removal bracket along the moving direction and the beam body anchoring ear plate 9, and connect with the beam body anchoring ear plate 9 at the lower end of the next part to be removed;
[0049] S42, gradually loosen the anchoring of the main cable by the clamp 5, and at the same time set the winch to synchronously pull the two loosened electric hanging basket wire ropes 8, drive the removal bracket to move along the main cable, and during the movement, synchronously loosen the two electric hanging basket wire ropes 8 at the rear end of the removal bracket, and connect them with the beam anchoring ear plate 9 at the lower end of the next part to be removed; during the entire traction process, the hanging basket wire ropes at the front and rear ends form a triangular stable traction until the removal bracket moves to the next removal part;
[0050] S43, repeat the above steps S1 to S3 to perform the dismantling operation;
[0051] S44: After completion, continue to repeat the above steps until all the parts to be dismantled are dismantled.
[0052] It is understood that the present invention is described by some embodiments, and those skilled in the art are aware that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. Although the embodiments of the present invention have been disclosed as above, they are not limited to the applications listed in the specification and the implementation mode, and they can be fully applied to various fields suitable for the present invention. For those familiar with the art, other modifications can be easily implemented, so without departing from the general concept defined by the claims and the equivalent scope, the present invention is not limited to the specific details and the illustrations shown and described here.
Claims
1. A suspension bridge cable system dismantling bracket, characterized in that: It includes a bracket body, connecting parts arranged on both sides of the bracket body along the extension direction of the main cable, and multiple hanging basket steel wire ropes connected to the bracket body. The lower end of the connecting part is disassembled and fixed to the main cable, and the lower ends of the multiple hanging basket steel wire ropes are disassembled and fixed to the beam body. The hanging basket steel wire ropes are first hoisted on the hanging basket construction platform to the part to be dismantled, and then fixed to the beam body and tightened. The dismantling bracket is fixed by two connecting parts and multiple tightened hanging basket steel wire ropes to achieve stable support.
2. The suspension bridge cable system dismantling bracket according to claim 1, characterized in that: The bracket body includes a pair of upper oblique support rods arranged opposite to each other and a longitudinal beam arranged perpendicular to the upper oblique support rods. The longitudinal beam is arranged along the extension direction of the main cable. Two connecting members are respectively arranged at both ends of the longitudinal beam. A pair of upper oblique support rods extend in a direction perpendicular to the longitudinal beam and four hanging basket steel ropes are fixedly arranged at four end points respectively. The upper oblique support rods are a trapezoidal frame structure.
3. The suspension bridge cable system dismantling bracket according to claim 1, characterized in that: The connecting member comprises a vertical member with adjustable height and a clamp arranged at the bottom end of the vertical member, the clamp is fastened to the main cable, and the vertical members comprised by a pair of connecting members have different heights to adapt to the line shape of the main cable.
4. The suspension bridge cable system dismantling bracket according to claim 3, characterized in that: The vertical member includes a pair of columns and a plurality of cross-links connecting the columns into one, forming a telescopic ladder structure; a pair of columns are assembled in sequence from a plurality of column units, and two corresponding column units of a pair of columns are connected by cross-links to form an I-shaped structure, and the cross-links and the column units are connected by bolts or grooves and snap-fit ends.
5. The suspension bridge cable system dismantling bracket according to claim 4, characterized in that: The two ends of the clamp are respectively hingedly connected to the bottom ends of a pair of columns through movable hinge supports fixed to the bottom ends of a pair of columns to adapt to the shape of the main cable.
6. The suspension bridge cable system dismantling bracket according to claim 2, characterized in that: The beam body is provided with a beam body anchoring ear plate, and the lower end of the hanging basket wire rope is disassembled and fixed on the beam body anchoring ear plate; the end of the upper oblique support rod is provided with a wire rope anchor buckle, which is used to connect the upper end of the hanging basket wire rope.
7. The suspension bridge cable system dismantling bracket according to claim 2, characterized in that: A hand-chain hoist load-bearing buckle is provided in the middle of a pair of longitudinal beams, which is used to connect the hand-chain hoist, and the dismantling and lifting of the parts to be dismantled are realized through the hand-chain hoist.
8. A method for using the suspension bridge cable system dismantling bracket according to claim 5, characterized in that: The steps include: S1. Position the entire disassembly bracket to the part to be disassembled, adjust the height of a pair of connectors on both sides according to the shape of the main cable, adjust the angle of the clamp, and then lock the clamp on the main cable to fix it; S2. A person operates the hanging basket construction platform to rise to the part to be demolished through the electric hanging basket wire rope, and connects the lower end of the electric hanging basket wire rope to the beam anchoring ear plate fixed to the beam body; S3. After the anchor ear plates of the beam are fixed, tighten the steel wire rope of the electric hanging basket to ensure the stability of the overall dismantling support structure and start the dismantling operation.
9. The method for using the suspension bridge cable system dismantling bracket according to claim 8, characterized in that: After the removal operation in step S3 is completed, step S4 is also included. After the removal operation of one removal part is completed, the removal bracket is moved to another removal part to be removed, and the removal operation is performed again, which specifically includes the following steps: S41, symmetrically loosen the connection between the two electric hanging basket wire ropes at the front end of the removal bracket along the moving direction and the beam body anchoring ear plate, and connect them with the beam body anchoring ear plate at the lower end of the next part to be removed; S42, gradually loosen the anchoring of the main cable by the clamp, and at the same time set the winch to synchronously pull the two loosened electric hanging basket wire ropes to drive the removal bracket to move along the main cable. During the movement, the two electric hanging basket wire ropes at the rear end of the removal bracket are synchronously loosened and connected to the beam anchoring ear plate at the lower end of the next part to be removed; S43, repeat the above steps S1 to S3 to perform the dismantling operation; S44: After completion, continue to repeat the above steps until all the parts to be dismantled are dismantled.
10. The method for using the suspension bridge cable system dismantling bracket according to claim 9, characterized in that: In step S42, during the entire traction process, the steel wire ropes of the hanging basket at the front and rear ends form a triangular stable traction until the removal bracket moves to the next removal position.
Citation Information
Patent Citations
Device for replacing main cable clip of suspension bridge and mounting method of device
CN107642049A
Sling dismantling device and sling dismantling method for suspension bridge
CN117888472A