A core sampling device for engineering inspection

By introducing a vertical orientation component and a drilling detection platform into the pile foundation coring equipment, it ensures that the core pipe is drilled vertically, solves the problem of drilling inclination, improves sampling accuracy and detection reliability, and avoids damage to the steel cage and Increased repair costs.

CN118670792BActive Publication Date: 2024-10-29SICHUAN WENMAO CONSTR ENG INSPECTION CO LTD

Patent Information

Application Number
CN202411163992.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2024-10-29
Estimated Expiration
2044-08-23

AI Technical Summary

Technical Problem

Pile foundation coring equipment can easily cause the borehole to tilt during the drilling process, affecting the accuracy of sampling. In severe cases, it may damage the steel cage, increasing the difficulty and cost of repair.

Method used

A drilling core sampling device for engineering inspection is designed, including a vertical orientation component and a drilling inspection platform. The hoop body and extrusion channel are used to ensure that the core tube is drilled vertically, and the extrusion ball and elastic member are used to maintain the core tube. The axis is parallel to the axis of the through hole, and the detection component is used to determine whether the drilling direction is vertical.

Benefits of technology

It effectively prevents drilling deviation, ensures sampling accuracy, avoids damage to the steel cage, reduces repair costs, and improves the accuracy and reliability of pile foundation detection.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118670792B_ABST
    Figure CN118670792B_ABST
Patent Text Reader

Abstract

The present invention provides a core sampling device for engineering inspection, which belongs to the technical field of pile foundation coring inspection tools, and includes a vertical directional assembly, wherein the vertical directional assembly includes a hoop body for limiting the drilling direction of a core tube, wherein the hoop body is provided with a through hole with a diameter greater than or equal to the diameter of the core tube, wherein the core tube first passes through the through hole and then drills into the ground, and the through hole can limit the core tube from drilling in a direction perpendicular to the ground; using such a core sampling device for engineering inspection, a hoop body for limiting the drilling direction of the core tube is provided at a position close to the ground, wherein the core tube first passes through the through hole and then drills into the ground, and the through hole can limit the core tube from drilling in a direction perpendicular to the ground. A squeezing ball is provided in the hoop body, an squeezing elastic member is provided between the channel plug and the squeezing ball, and a limiting structure for preventing the squeezing ball from detaching is provided at the proximal end of the squeezing channel; the squeezing ball is used to squeeze the core tube so that the axis of the core tube remains parallel to the axis of the through hole.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of pile foundation coring detection tools, and more specifically relates to a core drilling sampling device for engineering detection. Background Art

[0002] Pile foundation coring equipment is a kind of equipment specially used to drill holes underground and take out rock or soil samples. It mainly consists of drill bit, coring tube, drill rod, drilling rig, lifting equipment, control system and mud pump.

[0003] Pile foundation coring test is a method to test the quality of pile foundation concrete. It is done by drilling a concrete core sample of a certain diameter and length from the hardened concrete pile foundation, and then performing various physical and chemical tests on the concrete core sample to evaluate the quality of the pile foundation.

[0004] This detection method can intuitively understand the concrete quality of the pile foundation, such as the density and strength of the concrete, so as to determine whether the quality of the pile foundation meets the standards. At the same time, the actual length of the pile foundation can also be determined through core sampling, and whether the construction process of the pile foundation is standardized, and provide a basis for pile foundation repair.

[0005] However, when the pile foundation coring equipment is working, the coring tube needs to be drilled downward perpendicular to the ground. If the drill bit is not pushed downward along the center, the borehole will be tilted. If the coring tube is not pushed downward along the center line, the borehole will deviate from the predetermined trajectory, which may affect the accuracy of the sampling. When it is severely tilted, it will damage the steel cage and cause losses. Summary of the invention

[0006] Based on this, an object of the present invention is to provide a core sampling device for engineering inspection, comprising a drill bit for cutting rocks to obtain underground rock samples, a core tube for storing rock samples, a drill rod connecting the drill bit and the core tube, a drilling rig for providing rotational force, a propulsion device for propulsing the drill rod, and a lifting device for lifting the drill rod; the drilling rig drives the drill bit to drive the drill rod to rotate, and grooves are arranged at intervals along the axial direction of the drill rod. The propulsion device propels the drill rod underground through the grooves, and the lifting device is connected to the drill rod and lifts the drill rod to the ground; the core sampling device also includes a vertical orientation component, and the vertical orientation component includes a hoop body for limiting the drilling direction of the core tube, and the hoop body is provided with a through hole with a diameter greater than or equal to the diameter of the core tube. The core tube first passes through the through hole and then drills into the ground, and the through hole can limit the core tube to drill in a direction perpendicular to the ground;

[0007] An extrusion channel is arranged inside the hoop body along the radial direction of the through hole, and an extrusion assembly is arranged inside the extrusion channel; the extrusion assembly includes an extrusion ball and an extrusion elastic member for pushing the extrusion ball to move toward the axis direction of the through hole; the extrusion channel includes a proximal end and a distal end, the proximal end of the extrusion channel penetrates the through hole, and the distal end of the extrusion channel penetrates to the outside of the hoop body;

[0008] A channel plug is provided at the distal end of the extrusion channel, which is used to close the distal end of the extrusion channel. The extrusion elastic member is provided between the channel plug and the extrusion ball. A limiting structure for preventing the extrusion ball from detaching is provided at the proximal end of the extrusion channel. The extrusion ball is used to squeeze the core tube so that the axis of the core tube remains parallel to the axis of the through hole.

[0009] Preferably, a plurality of extrusion channels are arranged inside the hoop body, and an extrusion assembly is arranged inside each extrusion channel;

[0010] The multiple extrusion channels include at least three extrusion channels evenly distributed along the circumferential direction of the through hole, and also include at least two layers of extrusion channels arranged along the axial direction of the through hole.

[0011] Preferably, a liquid channel is further provided inside the hoop body, and a liquid injection hole is provided on the surface of the hoop body, and the liquid injection hole is used to inject liquid into the liquid channel;

[0012] The liquid channel is connected to at least one extrusion channel. The liquid injected from the liquid injection hole flows into the extrusion channel through the liquid channel. The liquid plays a role in lubricating and cooling the extrusion ball.

[0013] Preferably, the vertical orientation assembly further comprises a guide track on which a sliding seat is arranged; the hoop body is connected to the sliding seat, the hoop body is arranged on the guide track through the sliding seat, and can translate along the length direction of the guide track.

[0014] Preferably, the hoop body is composed of two tightening hoop units, namely a first tightening hoop unit and a second tightening hoop unit; the first tightening hoop unit and the second tightening hoop unit are respectively connected to the guide track through different sliding seats;

[0015] The through hole is arranged at the connection part of the first tightening hoop unit and the second tightening hoop unit, and the first tightening hoop unit and the second tightening hoop unit are respectively provided with a semicircular hole, and the first tightening hoop unit and the second tightening hoop unit are spliced ​​into a complete through hole when connected;

[0016] When the first tightening unit and the second tightening unit are spliced, the axis of the core tube is forced to remain collinear or parallel with the axis of the through hole; when the first tightening unit and the second tightening unit are separated, the core tube or drill rod can be quickly removed from the gap between the first tightening unit and the second tightening unit.

[0017] Preferably, a first driving device is arranged between the first tightening hoop unit and the second tightening hoop unit, and the first driving device comprises two connecting parts, namely a first driving part and a second driving part; the first driving part is connected to the first tightening hoop unit, and the second driving part is connected to the second tightening hoop unit;

[0018] The first driving device is used to control the opening and closing of the first tightening unit and the second tightening unit; the first driving device controls the first driving part and the second driving part to move away from each other, and can drive the first tightening unit and the second tightening unit to separate; the first driving device controls the first driving part and the second driving part to move towards each other, and can drive the first tightening unit and the second tightening unit to merge.

[0019] Preferably, a centering elastic member is sleeved on the guide track; when the first tightening unit and the second tightening unit are separated, the first tightening unit and the second tightening unit are in contact with different centering elastic members respectively;

[0020] The centering elastic member is used to move the first and second tightening units away from the core tube or drill pipe when the first and second tightening units are separated; so that the separated first and second tightening units are still located close to the axis of the core tube.

[0021] Preferably, a locking piece is provided at the connection portion between the hoop body and the guide rail; when the locking piece is in an unlocked state, the hoop body can translate on the guide rail; when the locking assembly is in a locked state, the relative positions of the hoop body and the guide rail are locked, and the hoop body cannot translate on the guide rail.

[0022] Preferably, the core sampling device further comprises a drilling detection platform and a detection component arranged on the drilling detection platform;

[0023] The detection assembly includes a detection rod disposed on the drilling detection platform and capable of contacting the core tube or drill rod, a rotating shaft connecting the detection rod and the drilling detection platform, an encoder connected to the rotating shaft and capable of obtaining the rotation angle of the detection rod, and a pushing elastic member that pushes the detection rod to contact the core tube or drill rod;

[0024] When the core tube is in a rotating state, pushing the elastic member can push the detection rod to contact the core tube or the drill rod; the swing, vibration or deviation generated when the core tube or the drill rod rotates can drive the detection rod to rotate, and the encoder obtains the rotation angle of the detection rod. The rotation angle of the detection rod can be used to determine whether the drilling direction of the core tube is perpendicular to the ground.

[0025] Preferably, a plurality of detection components are arranged on the drilling detection platform, and the detection rods of the plurality of detection components can contact the core tube or drill rod from different positions and angles; the encoders of the plurality of detection components can collaboratively determine the swing, vibration or deviation generated when the core tube or drill rod rotates and the direction of the deviation;

[0026] The drilling detection platform is also provided with a second driver and a retractable connecting piece connecting the second driver and the detection rod; the second driver can control the retractable connecting piece to be tightened, and when the retractable connecting piece is tightened, it can compress and push the elastic piece to make the detection rod move away from the core tube or drill rod; when the rotation of the core tube or drill rod stops, the second driver can control the detection rod to move away from the core tube or drill rod to protect the detection rod.

[0027] According to an embodiment of the present invention, a core sampling device for engineering inspection is provided with a hoop body for limiting the drilling direction of a core tube at a position close to the ground. The core tube first passes through a through hole and then drills into the ground. The through hole can limit the core tube from drilling in a direction perpendicular to the ground. A squeezing ball is provided in the hoop body, an squeezing elastic member is provided between the channel plug and the squeezing ball, and a limiting structure for preventing the squeezing ball from detaching is provided at the proximal end of the squeezing channel; the squeezing ball is used to squeeze the core tube so that the axis of the core tube remains parallel to the axis of the through hole. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] The present disclosure includes drawings, which should be considered to be included in and constitute a part of the specification, and together with the specification, illustrate various exemplary embodiments, features and aspects of the present disclosure, and are used to explain the principles of the present disclosure. The present invention will be more fully understood through the following detailed description in conjunction with the drawings. Among them:

[0029] Figure 1 is a usage state diagram of a core sampling device for engineering inspection according to an embodiment of the present invention;

[0030] Figure 2 is a schematic diagram of the tail of a core sampling device for engineering inspection according to an embodiment of the present invention;

[0031] Figure 3 is a schematic diagram of a drilling inspection platform of a core sampling device for engineering inspection according to an embodiment of the present invention;

[0032] Figure 4 is a top view of a drilling inspection platform of a core sampling device for engineering inspection according to an embodiment of the present invention;

[0033] Figure 5 is a schematic diagram of a vertical orientation component of a core sampling device for engineering inspection according to an embodiment of the present invention;

[0034] Figure 6 is a cross-sectional view of a vertical orientation component of a core sampling device for engineering inspection according to an embodiment of the present invention;

[0035] Figure 7 yes Figure 6 A partial enlarged view of the middle A;

[0036] Figure 8 is a schematic diagram of a first tightening unit and a second tightening unit of a core sampling device for engineering inspection according to an embodiment of the present invention in an open state;

[0037] Fig. 9 It is a schematic diagram of a detection rod of a core sampling device for engineering detection drilling into a detection platform in contact with a core sampling tube according to an embodiment of the present invention;

[0038] Fig.10 It is a schematic diagram of a core sampling device for engineering inspection and a drill rod part docking according to an embodiment of the present invention;

[0039] Fig.11 It is a schematic diagram of a detection rod of a core sampling device for engineering inspection drilling into an inspection platform in contact with a drill rod according to an embodiment of the present invention;

[0040] Among them: core tube 11, drill rod 12, drilling rig 13, propulsion equipment 14, hoop body 21, first tightening hoop unit 211, second tightening hoop unit 212, extrusion channel 22, extrusion ball 23, extrusion elastic member 24, channel plug 25, limiting structure 26, liquid channel 31, injection hole 32, guide rail 41, sliding seat 42, first driving device 43, centering elastic member 44, locking member 45, drilling detection platform 51, detection rod 52, rotating shaft 53, encoder 54, pushing elastic member 55, second driver 56, retracting connecting member 57, steering column 58. DETAILED DESCRIPTION

[0041] The technical solution of the present invention is further described in detail below through embodiments and in conjunction with the accompanying drawings, but the present invention is not limited to the following embodiments.

[0042] Pile foundation coring equipment is a device specially used for drilling underground and taking out rock or soil samples. It is mainly composed of a drill bit, a coring tube 11, a drill rod 12, a drilling rig 13, a lifting device, a control system and a mud pump. Pile foundation coring equipment is mainly used in civil engineering, geological exploration, environmental monitoring, mineral development and other scenarios. In civil engineering, it can be used to detect the stability and bearing capacity of the foundation; in geological exploration, it can be used to obtain underground rock or soil samples for geological structure analysis and mineral resource evaluation; in environmental monitoring, it can be used to collect groundwater samples for water quality analysis and pollution source tracking; in mineral development, it can be used to obtain ore samples for ore quality evaluation and mining plan formulation. The main function of pile foundation coring equipment is to obtain underground rock or soil samples, which can be used for various analyses and evaluations, thereby providing important data support for engineering design, resource development, environmental protection, etc.

[0043] However, when the pile foundation coring equipment is working, the coring tube 11 needs to be drilled downward perpendicular to the ground. If the drill bit is not pushed downward along the center, the borehole will be tilted. If the coring tube 11 is not pushed downward along the center line, the borehole will deviate from the predetermined trajectory, which may affect the accuracy of the sampling. When it is severely tilted, it will damage the steel cage and cause losses.

[0044] In order to solve the above problems, the object of the present invention is to provide a core sampling device for engineering inspection, comprising a drill bit for cutting rocks to obtain underground rock samples, a core tube 11 for storing rock samples, a drill rod 12 connecting the drill bit and the core tube 11, a drill rig 13 for providing rotational force, a propulsion device 14 for propulsing the drill rod 12, and a lifting device for lifting the drill rod 12; the drill rig 13 drives the drill bit to drive the drill rod 12 to rotate, grooves are arranged at intervals along the axial direction on the drill rod 12, the propulsion device 14 propels the drill rod 12 underground through the grooves, and the lifting device is connected to the drill rod 12 and lifts the drill rod 12 to the ground; the core sampling device also includes a vertical orientation component, the vertical orientation component includes a hoop body 21 for limiting the drilling direction of the core tube 11, the hoop body 21 is provided with a through hole with a diameter greater than or equal to the diameter of the core tube 11, the core tube 11 first passes through the through hole and then drills into the ground, and the through hole can limit the core tube 11 to drill in a direction perpendicular to the ground;

[0045] An extrusion channel 22 is provided inside the hoop body 21 along the radial direction of the through hole, and an extrusion assembly is provided inside the extrusion channel 22; the extrusion assembly includes an extrusion ball 23 and an extrusion elastic member 24 for pushing the extrusion ball 23 to move toward the axis direction of the through hole; the extrusion channel 22 includes a proximal end and a distal end, the proximal end of the extrusion channel 22 penetrates the through hole, and the distal end of the extrusion channel 22 penetrates to the outside of the hoop body 21;

[0046] A channel plug 25 is provided at the distal end of the extrusion channel 22, and the channel plug 25 is used to close the distal end of the extrusion channel 22. The extrusion elastic member 24 is provided between the channel plug 25 and the extrusion ball 23. A limiting structure 26 is provided at the proximal end of the extrusion channel 22 for preventing the extrusion ball 23 from detaching; the extrusion ball 23 is used to extrude the core tube 11 so that the axis of the core tube 11 remains parallel to the axis of the through hole.

[0047] The core sampling device for engineering detection of the present invention can be used for pile foundation coring detection.

[0048] Pile foundation coring test is a method to test the quality of pile foundation concrete. It is done by drilling a concrete core sample of a certain diameter and length from the hardened concrete pile foundation, and then performing various physical and chemical tests on the concrete core sample to evaluate the quality of the pile foundation.

[0049] This detection method can intuitively understand the concrete quality of the pile foundation, such as the density and strength of the concrete, so as to determine whether the quality of the pile foundation meets the standards. At the same time, the actual length of the pile foundation can also be determined through core sampling, and whether the construction process of the pile foundation is standardized, and provide a basis for pile foundation repair.

[0050] The process of pile foundation coring detection mainly includes the following steps:

[0051] Drilling: Use a special drill bit and drilling machine 13 to drill holes in the concrete pile foundation. The depth and position are determined according to the detection requirements.

[0052] Coring: Use special coring equipment to take out the concrete core sample from the drilled hole.

[0053] Testing: The core samples of concrete taken out are sent to the laboratory for various physical and chemical tests, such as strength test, density test, etc.

[0054] Analysis: Analyze based on the test results to determine whether the quality of the pile foundation meets the standards and whether repair is needed.

[0055] The equipment needed mainly includes: drilling rig 13, special drill bit, coring equipment, concrete strength testing machine, density testing equipment, etc. Among them, the drilling rig 13 and the drill bit are used for drilling and coring, and the concrete strength testing machine and the density testing equipment are used to detect the concrete core sample.

[0056] If the centerline is offset during the coring process of the pile foundation, it may cause 1) inaccurate test results: If the drilling position deviates from the centerline, the core sample may not represent the average quality of the entire pile foundation, resulting in inaccurate test results. 2) Reduced strength of the pile foundation: If the drilling position deviates from the centerline, it may affect the bearing capacity of the pile foundation, especially if the deviation is large, it may cause the strength of the pile foundation to decrease. Severe tilting will damage the steel cage and cause losses. If the drilling position deviates from the centerline, a larger range and deeper depth may be required for repair, increasing the difficulty and cost of repair.

[0057] Therefore, during the core drilling process of the pile foundation, the drilling position should be as accurate as possible to avoid deviation from the center line.

[0058] The main part of a core sampling device for engineering inspection of the present invention is similar to the existing core sampling device, including a drill bit for cutting rocks to obtain underground rock samples, a core sampling tube 11 for storing rock samples, a drill rod 12 connecting the drill bit and the core sampling tube 11, a drilling rig 13 for providing rotational force, a propulsion device 14 for propelling the drill rod 12, and a lifting device for lifting the drill rod 12.

[0059] like Figure 1 , Figure 2 As shown, the rotary power generated by the diesel engine or electric motor of the drilling rig 13 is transmitted through a belt drive, and then the rotary power is transmitted to the drill bit through a bevel gear or other mechanism that can change the direction of rotation. The drill bit drives the drill rod 12 to rotate. The end of the drill rod 12 close to the ground is connected to the core tube 11. The core tube 11 is a hollow tube. The drill rod 12 drives the core tube 11 to rotate. The core tube 11 drills into the ground to extract the sample inside the ground. The lifting device can be connected to the end of the drill rod 12 away from the ground. The drill rod 12 can be lifted upward to lift the core tube 11 to the surface, so as to remove the sample stored in the core tube 11.

[0060] Compared with the existing equipment, the core sampling device for engineering inspection of the present invention also includes a vertical directional component, which includes a hoop body 21 for limiting the drilling direction of the core tube 11, and the hoop body 21 is provided with a through hole with a diameter greater than or equal to the diameter of the core tube 11. The core tube 11 first passes through the through hole and then drills into the underground. The through hole can limit the core tube 11 to drill in a direction perpendicular to the ground.

[0061] The vertical orientation component is arranged on the ground near the surface. The core tube 11 first passes through the through hole of the hoop body 21 and then contacts the ground to be drilled into the underground. The diameter of the through hole matches the core tube 11. The axis of the through hole is perpendicular to the horizontal plane. The vertical orientation component is used to assist in stabilizing the core tube 11, ensuring the angle of the core tube 11 drilling into the ground and preventing the drilling angle from tilting.

[0062] like Figure 5 , Figure 6 as well as Figure 7 As shown, the squeezing ball 23 is a sphere. When the core tube 11 rotates, a part of the squeezing ball 23 is on the side of the through hole. The squeezing ball 23 rotates synchronously with the core tube 11, so as to reduce the resistance of the core tube 11 to rotation and prevent the through hole from affecting the rotation of the core tube 11.

[0063] The extrusion channel 22 is a cylindrical channel, and the extrusion ball 23 can move in the channel. The axis of the extrusion channel 22 is parallel to the radial direction of the through hole; the extrusion elastic member 24 can be a spring or a spring sheet, and the channel plug 25 is connected to the extrusion channel 22 by threads. The channel plug 25 can be provided with a hexagonal hole or a plum wrench hole, and the channel plug 25 can be rotated by a matching tool.

[0064] The spring and the squeezing ball 23 can be taken out by taking out the channel plug 25 , and the pressure of the spring and the squeezing ball 23 can be adjusted by screwing in the channel plug 25 and adjusting the position of the channel plug 25 .

[0065] like Figure 7 As shown, a limiting structure 26 for preventing the extrusion ball 23 from escaping is provided at the proximal end of the extrusion channel 22 ; the limiting structure 26 of this embodiment is an annular blocking portion provided at the end of the extrusion channel 22 to prevent the extrusion ball 23 from being extruded by the extrusion elastic member 24 .

[0066] Preferably, two squeezing balls 23 are arranged in the squeezing channel 22, a push plate is arranged between the squeezing spring and the squeezing ball 23, the spring is connected to the push plate, and the push plate is connected to the two squeezing balls 23 in sequence, so as to reduce the resistance of the squeezing ball 23 to rotation.

[0067] Furthermore, a plurality of extrusion channels 22 are provided inside the hoop body 21, and an extrusion component is provided inside each extrusion channel 22;

[0068] The plurality of extrusion channels 22 include at least three extrusion channels 22 evenly distributed along the circumferential direction of the through hole, and also include at least two layers of extrusion channels 22 arranged along the axial direction of the through hole.

[0069] In this embodiment, Figure 4 , Figure 5 As shown, the two layers of extrusion channels 22 refer to different heights above the ground. Multiple extrusion channels 22 are arranged at the same height above the ground. In this embodiment, three extrusion channels 22 are arranged at the same height above the ground, and are evenly spaced in the circumferential direction of the through hole.

[0070] In the specific implementation process, four or even more extrusion channels 22 can be set at the same height above the ground. The purpose of setting multiple extrusion channels 22 at the same height above the ground is to push the core tube 11 from at least three positions in the circumferential direction so that the axis of the core tube 11 is collinear with the axis of the through hole.

[0071] The purpose of at least two layers of extrusion channels 22 arranged along the axial direction of the through hole is to prevent the core tube 11 from tilting.

[0072] Furthermore, a liquid channel 31 is provided inside the hoop body 21, and a liquid injection hole 32 is provided on the surface of the hoop body 21, and the liquid injection hole 32 is used to inject liquid into the liquid channel 31;

[0073] The liquid channel 31 is connected to at least one extrusion channel 22 . The liquid injected from the liquid injection hole 32 flows into the extrusion channel 22 through the liquid channel 31 . The liquid has the function of lubricating and cooling the extrusion ball 23 .

[0074] In this embodiment, Figure 6 , Figure 7 As shown, the injection hole 32 of the liquid channel 31 is set on the upper surface of the hoop body 21. The injection hole 32 is used to add liquid into the extrusion channel 22. The liquid can be used for lubrication and cooling. The liquid is used to reduce the friction between the extrusion ball 23 and the core tube 11. Heat may be generated at the friction position, and the heat will cause metal deformation. Lowering the temperature can extend the life of the equipment.

[0075] In addition, there may be rock and soil debris on the surface of the core tube 11, and the debris may be brought into the extrusion channel 22 after contacting the extrusion ball 23, affecting the rotation of the extrusion ball 23. The liquid can also bring these debris out of the extrusion channel 22, and the liquid can be discharged through the proximal end of the extrusion channel 22, or through other channels for discharging liquid. The liquid can be a lubricant, a coolant, etc.

[0076] Furthermore, the vertical orientation assembly also includes a guide rail 41 , on which a sliding seat 42 is disposed; the hoop body 21 is connected to the sliding seat 42 , and the hoop body 21 is disposed on the guide rail 41 through the sliding seat 42 and can translate along the length direction of the guide rail 41 .

[0077] In this embodiment, the guide track 41 is used to fine-tune the position of the hoop body 21 , and the position of the hoop body 21 is fine-tuned to match the position of the core tube 11 .

[0078] Furthermore, the hoop body 21 is composed of two tightening hoop units, namely a first tightening hoop unit 211 and a second tightening hoop unit 212; the first tightening hoop unit 211 and the second tightening hoop unit 212 are respectively connected to the guide rail 41 through different sliding seats 42;

[0079] The through hole is arranged at the connection part of the first tightening hoop unit 211 and the second tightening hoop unit 212. The first tightening hoop unit 211 and the second tightening hoop unit 212 are respectively provided with a semicircular hole. When the first tightening hoop unit 211 and the second tightening hoop unit 212 are connected, they are spliced ​​into a complete through hole.

[0080] When the first tightening unit 211 and the second tightening unit 212 are spliced, the axis of the core tube 11 is forced to remain collinear or parallel with the axis through the hole; when the first tightening unit 211 and the second tightening unit 212 are separated, the core tube 11 or the drill rod 12 can be quickly removed from the gap between the first tightening unit 211 and the second tightening unit 212.

[0081] In this embodiment, Figure 5 , Figure 8 As shown, the first tightening hoop unit 211 and the second tightening hoop unit 212 can move on the guide rail 41 respectively, and the first tightening hoop unit 211 and the second tightening hoop unit 212 are respectively provided with a semicircular hole. When the first tightening hoop unit 211 and the second tightening hoop unit 212 are spliced, the semicircular holes on the first tightening hoop unit 211 and the second tightening hoop unit 212 are merged into a through hole.

[0082] When installing the core tube 11 into the through hole, the first tightening unit 211 and the second tightening unit 212 are separated, and after the core tube 11 is placed in place, the first tightening unit 211 and the second tightening unit 212 are combined, so that the core tube 11 can be quickly installed in place. Conversely, after the lifting device takes out the core tube 11, the first tightening unit 211 and the second tightening unit 212 are separated, so that the core tube 11 can be quickly taken out of the through hole without having to lift the core tube 11 to a height higher than the through hole. Figure 6 A diagram showing a state in which the first tight hoop unit 211 and the second tight hoop unit 212 are combined; Figure 8 The diagram shows a state in which the first tightening unit 211 and the second tightening unit 212 are separated.

[0083] Furthermore, a first driving device 43 is arranged between the first tightening hoop unit 211 and the second tightening hoop unit 212. The first driving device 43 includes two connecting parts, namely a first driving part and a second driving part; the first driving part is connected to the first tightening hoop unit 211, and the second driving part is connected to the second tightening hoop unit 212.

[0084] The first driving device 43 is used to control the opening and closing of the first tightening unit 211 and the second tightening unit 212; the first driving device 43 controls the first driving part and the second driving part to move away from each other, and can drive the first tightening unit 211 and the second tightening unit 212 to separate; the first driving device 43 controls the first driving part and the second driving part to move towards each other, and can drive the first tightening unit 211 and the second tightening unit 212 to merge.

[0085] In this embodiment, the first driving device 43 is used to control the opening and closing of the first tightening unit 211 and the second tightening unit 212, and the two connecting parts of the first driving device 43 are respectively installed on the first tightening unit 211 and the second tightening unit 212. In this embodiment, the first driving device 43 can be one of a hydraulic cylinder, an electric cylinder, and a linear motor. In this embodiment, it is a hydraulic cylinder. When the first tightening unit 211 and the second tightening unit 212 are in a combined state, the first driving device 43 can also provide a locking force to keep the first tightening unit 211 and the second tightening unit 212 in a combined state, so as to prevent the rotating core tube 11 from separating the first tightening unit 211 and the second tightening unit 212.

[0086] Furthermore, a centering elastic member 44 is sleeved on the guide track 41; when the first tightening unit 211 and the second tightening unit 212 are separated, the first tightening unit 211 and the second tightening unit 212 are in contact with different centering elastic members 44 respectively;

[0087] The centering elastic member 44 is used to move the first tightening unit 211 and the second tightening unit 212 away from the core tube 11 or the drill pipe 12 when the first tightening unit 211 and the second tightening unit 212 are separated; so that the first tightening unit 211 and the second tightening unit 212 after separation are still in a position close to the axis of the core tube 11.

[0088] In this embodiment, the guide rail 41 includes two guide rods, and the sliding seat 42 is connected to the two guide rods. The two guide rods can limit the sliding seat 42 to only move but not rotate.

[0089] The centering elastic member 44 of this embodiment is a spring. This embodiment includes 4 centering springs, which are respectively arranged at the left and right ends of the two guide rods. The centering elastic member 44 is used to move the first tightening unit 211 and the second tightening unit 212 away from the core tube 11 or the drill rod 12 when the first tightening unit 211 and the second tightening unit 212 are separated. After the first tightening unit 211 and the second tightening unit 212 are separated, they are still in a position close to the axis of the core tube 11.

[0090] Furthermore, a locking piece 45 is provided at the connection portion between the hoop body 21 and the guide rail 41; when the locking piece 45 is in an unlocked state, the hoop body 21 can translate on the guide rail 41; when the locking assembly is in a locked state, the relative positions of the hoop body 21 and the guide rail 41 are locked, and the hoop body 21 cannot translate on the guide rail 41.

[0091] In this embodiment, the locking member 45 can be a screw rod, and a matching screw rod is provided at the corresponding position of the hoop body 21. Rotating the locking member 45 can make the screw rod contact the guide track 41, and the friction between the hoop body 21 and the guide track 41 increases to lock the position of the hoop body 21. The locking member 45 is released when the position of the hoop body 21 is adjusted, and the position is locked after the adjustment is completed. The function of the locking member 45 is to prevent the swing of the core tube 11 from causing the hoop body 21 to move on the guide track 41 when the core tube 11 rotates.

[0092] Furthermore, the core sampling device further comprises a drilling detection platform 51 and a detection component arranged on the drilling detection platform 51;

[0093] The detection assembly includes a detection rod 52 disposed on a drilling detection platform 51 and capable of contacting the core tube 11 or the drill rod 12, a rotating shaft 53 connecting the detection rod 52 and the drilling detection platform 51, an encoder 54 connected to the rotating shaft 53 and capable of obtaining the rotation angle of the detection rod 52, and a pushing elastic member 55 pushing the detection rod 52 to contact the core tube 11 or the drill rod 12;

[0094] When the core tube 11 is in a rotating state, pushing the elastic member 55 can push the detection rod 52 to contact the core tube 11 or the drill rod 12; the swing, vibration or deviation generated when the core tube 11 or the drill rod 12 rotates can drive the detection rod 52 to rotate, and the encoder 54 obtains the rotation angle of the detection rod 52. The rotation angle of the detection rod 52 can be used to determine whether the drilling direction of the core tube 11 is perpendicular to the ground.

[0095] In this embodiment, the drilling detection platform 51 is as follows Figure 3 , Figure 4 As shown, the detection rod 52 can rotate around the rotation axis 53 , the encoder 54 is used to obtain the rotation angle of the detection rod 52 , and the pushing elastic member 55 is used to push the detection rod 52 to contact the core tube 11 or the drill rod 12 .

[0096] When the coring tube 11 or the drill rod 12 rotates, the detection rod 52 contacts the coring tube 11 or the drill rod 12, and the coring tube 11 or the drill rod 12 swings, which can cause the detection rod 52 to rotate. The encoder 54 converts the rotation amount of the detection rod 52 into an electrical signal, and the swing amount of the coring tube 11 or the drill rod 12 can be determined according to the electrical signal. In the specific implementation process, before the coring tube 11 is drilled into the ground from the surface, the encoder 54 information is collected as the reference information, and the encoder 54 information is continuously collected during the drilling process and compared with the reference information, and the difference between the real-time information and the reference information is used to determine whether the drilling direction of the coring tube 11 is perpendicular to the ground. Figure 1 and Fig. 9 A schematic diagram showing the contact between the detection rod 52 of the drilling detection platform 51 and the core tube 11; Fig.10 and Fig.11 A schematic diagram showing the contact between the detection rod 52 of the drilling detection platform 51 and the drilling rod 12 is shown.

[0097] The position of the drilling detection platform 51 remains unchanged, and the dynamic information of the core tube 11 can be determined when the core tube 11 passes through the detection rod 52. The dynamic information of the drill rod 12 can be determined when the drill rod 12 passes through the detection rod 52.

[0098] In this embodiment, the pushing elastic member 55 is a torsion spring arranged on the rotating shaft 53 , one end of the torsion spring is connected to the drilling detection platform 51 , and the other end is connected to the detection rod 52 , which is used to push the detection rod 52 to contact the core tube 11 or the drill rod 12 .

[0099] In the specific implementation process, the drilling detection platform 51 is installed on the ground through an independent mounting bracket. The mounting bracket can be used as follows: Figure 1 The two ground rods and the crossbeam arranged between the ground rods are shown, and the drilling detection platform 51 is movably installed on the crossbeam. When the drilling rig is tilted, the drill rods are still kept vertical due to gravity. The mounting bracket is adjusted to make the drilling detection platform 51 parallel to the horizontal plane.

[0100] Furthermore, multiple detection components are arranged on the drilling detection platform 51, and the detection rods 52 of the multiple detection components can contact the core tube 11 or the drill rod 12 from different positions and angles; the encoders 54 of the multiple detection components can collaboratively determine the swing, vibration or deviation generated when the core tube 11 or the drill rod 12 rotates and the direction of the deviation.

[0101] In this embodiment, the detection rods 52 of multiple detection components can contact the core tube 11 or the drill rod 12 from different positions and angles. Before the core tube 11 is drilled underground from the surface, multiple detection components collect reference information respectively, and continuously collect encoder 54 information during the drilling process and compare it with the reference information. The information of multiple detection components is judged in coordination. It is distinguished whether the angle change of the detection rod 52 is caused by the rotation of the core tube 11 or the drill rod 12 itself or by the angle offset of the core tube 11 or the drill rod 12.

[0102] The drilling detection platform 51 is also provided with a second driver 56 and a retractable connecting piece 57 connecting the second driver 56 and the detection rod 52; the second driver 56 can control the retractable connecting piece 57 to tighten, and when the retractable connecting piece 57 is tightened, it can compress and push the elastic piece 55 to make the detection rod 52 move away from the core tube 11 or the drill rod 12; when the core tube 11 or the drill rod 12 stops rotating, the second driver 56 can control the detection rod 52 to move away from the core tube 11 or the drill rod 12 to protect the detection rod 52.

[0103] In this embodiment, the retractable connecting member 57 can be an elastic connecting rope, and the second driver 56 can be a hydraulic cylinder, an electric cylinder, or a linear motor. In this embodiment, the hydraulic cylinder can be retracted to tighten the retractable connecting member 57, thereby controlling the detection rod 52 to move away from the core tube 11 or the drill rod 12.

[0104] In the specific implementation process, a steering column 58 for adjusting the routing route of the retractable connecting member 57 is also provided on the drilling detection platform 51. The steering column 58 can make the retractable connecting member 57 pull the detection rod 52 in a direction that is conducive to controlling the movement of the detection rod 52.

[0105] The various embodiments disclosed in the present invention have been described above. The above description is exemplary and not exhaustive, and the scope of the present invention is not limited to the above embodiments. Many modifications and changes are obvious to those of ordinary skill in the art without departing from the spirit and scope of the present invention. In other words, those of ordinary skill in the art can make various changes and improvements to the present invention in form and detail, and these are considered to fall within the scope of protection of the present invention. The choice of terms used herein is intended to best explain the principles of the various embodiments, practical applications, or improvements to the technology in the market, or to enable those of ordinary skill in the art to understand the various embodiments disclosed herein.

Claims

1. A core sampling device for engineering inspection, comprising a drill bit for cutting rock to obtain underground rock samples, a core sampling tube (11) for storing rock samples, a drill rod (12) connecting the drill bit and the core sampling tube (11), a drilling rig (13) for providing rotational force, a propulsion device (14) for propulsing the drill rod (12), and a lifting device for lifting the drill rod (12); the drilling rig (13) drives the drill bit to drive the drill rod (12) to rotate, grooves are arranged at intervals along the axial direction of the drill rod (12), the propulsion device (14) propels the drill rod (12) underground through the grooves, and the lifting device is connected to the drill rod (12) and lifts the drill rod (12) to the ground; Features: The core sampling device further comprises a vertical orientation component, the vertical orientation component comprising a hoop body (21) for limiting the drilling direction of the core tube (11), the hoop body (21) being provided with a through hole having a diameter greater than or equal to the diameter of the core tube (11), the core tube (11) first passing through the through hole and then being drilled into the ground, the through hole being able to limit the core tube (11) from drilling in a direction perpendicular to the ground; An extrusion channel (22) is provided inside the hoop body (21) along the radial direction of the through hole, and an extrusion assembly is provided inside the extrusion channel (22); the extrusion assembly comprises an extrusion ball (23) and an extrusion elastic member (24) for pushing the extrusion ball (23) to move in a direction close to the axis of the through hole; the extrusion channel (22) comprises a proximal end and a distal end, the proximal end of the extrusion channel (22) penetrates the through hole, and the distal end of the extrusion channel (22) penetrates to the outside of the hoop body (21); A channel plug (25) is provided at the distal end of the extrusion channel (22), the channel plug (25) is used to close the distal end of the extrusion channel (22), an extrusion elastic member (24) is provided between the channel plug (25) and the extrusion ball (23), and a limiting structure (26) is provided at the proximal end of the extrusion channel (22) for preventing the extrusion ball (23) from detaching; the extrusion ball (23) is used to extrude the core tube (11) so that the axis of the core tube (11) remains parallel to the axis of the through hole; The core sampling device further comprises a drilling detection platform (51) and a detection component arranged on the drilling detection platform (51); The detection assembly comprises a detection rod (52) arranged on a drilling detection platform (51) and capable of contacting a core tube (11) or a drill rod (12), a rotation shaft (53) connecting the detection rod (52) and the drilling detection platform (51), an encoder (54) connected to the rotation shaft (53) and capable of obtaining a rotation angle of the detection rod (52), and a pushing elastic member (55) pushing the detection rod (52) to contact the core tube (11) or the drill rod (12); When the coring tube (11) is in a rotating state, the pushing elastic member (55) can push the detection rod (52) to contact the coring tube (11) or the drill rod (12); the swing, vibration or deviation generated when the coring tube (11) or the drill rod (12) rotates can drive the detection rod (52) to rotate, and the encoder (54) obtains the rotation angle of the detection rod (52), and the rotation angle of the detection rod (52) can be used to determine whether the drilling direction of the coring tube (11) is perpendicular to the ground.

2. A core sampling device for engineering inspection according to claim 1, Features: A plurality of extrusion channels (22) are arranged inside the hoop body (21), and an extrusion component is arranged inside each extrusion channel (22); The multiple extrusion channels (22) include at least three extrusion channels (22) evenly distributed along the circumferential direction of the through hole, and also include at least two layers of extrusion channels (22) arranged along the axial direction of the through hole.

3. A core sampling device for engineering inspection according to claim 1 or 2, Features: The hoop body (21) is further provided with a liquid channel (31) inside, and a liquid injection hole (32) is provided on the surface of the hoop body (21), and the liquid injection hole (32) is used to inject liquid into the liquid channel (31); The liquid channel (31) is connected to at least one extrusion channel (22); liquid injected from the liquid injection hole (32) flows into the extrusion channel (22) through the liquid channel (31); the liquid has the function of lubricating and cooling the extrusion ball (23).

4. A core sampling device for engineering inspection according to claim 1 or 2, Features: The vertical orientation assembly further comprises a guide rail (41), on which a sliding seat (42) is arranged; the hoop body (21) is connected to the sliding seat (42), and the hoop body (21) is arranged on the guide rail (41) via the sliding seat (42) and is capable of translating along the length direction of the guide rail (41).

5. A core sampling device for engineering inspection according to claim 4, Features: The hoop body (21) is composed of two tightening hoop units, namely a first tightening hoop unit (211) and a second tightening hoop unit (212); the first tightening hoop unit (211) and the second tightening hoop unit (212) are respectively connected to the guide track (41) via different sliding seats (42); The through hole is arranged at the connection portion of the first tightening hoop unit (211) and the second tightening hoop unit (212); the first tightening hoop unit (211) and the second tightening hoop unit (212) are each provided with a semicircular hole; when the first tightening hoop unit (211) and the second tightening hoop unit (212) are connected, they are spliced ​​into a complete through hole; When the first tightening unit (211) and the second tightening unit (212) are spliced, the hole causes the axis of the core tube (11) to remain colinear or parallel with the axis of the hole; when the first tightening unit (211) and the second tightening unit (212) are separated, the core tube (11) or the drill rod (12) can be quickly removed from the gap between the first tightening unit (211) and the second tightening unit (212).

6. A core sampling device for engineering inspection according to claim 5, Features: A first driving device (43) is provided between the first tightening hoop unit (211) and the second tightening hoop unit (212); the first driving device (43) comprises two connecting parts, namely a first driving part and a second driving part; the first driving part is connected to the first tightening hoop unit (211), and the second driving part is connected to the second tightening hoop unit (212); The first driving device (43) is used to control the opening and closing of the first tightening hoop unit (211) and the second tightening hoop unit (212); the first driving device (43) controls the first driving part and the second driving part to move in directions away from each other, thereby driving the first tightening hoop unit (211) and the second tightening hoop unit (212) to separate; the first driving device (43) controls the first driving part and the second driving part to move in directions approaching each other, thereby driving the first tightening hoop unit (211) and the second tightening hoop unit (212) to merge.

7. A core sampling device for engineering inspection according to claim 5, Features: A centering elastic member (44) is sleeved on the guide track (41); when the first tightening hoop unit (211) and the second tightening hoop unit (212) are separated, the first tightening hoop unit (211) and the second tightening hoop unit (212) are in contact with different centering elastic members (44) respectively; The centering elastic member (44) is used to move the first tightening unit (211) and the second tightening unit (212) in a direction away from the core tube (11) or the drill rod (12) when the first tightening unit (211) and the second tightening unit (212) are separated, so that the first tightening unit (211) and the second tightening unit (212) after separation are still located close to the axis of the core tube (11).

8. A core sampling device for engineering inspection according to any one of claims 5 to 7, Features: The connection portion between the hoop body (21) and the guide track (41) is provided with a locking piece (45); when the locking piece (45) is in an unlocked state, the hoop body (21) can translate on the guide track (41); when the locking assembly is in a locked state, the relative positions of the hoop body (21) and the guide track (41) are locked, and the hoop body (21) cannot translate on the guide track (41).

9. A core sampling device for engineering inspection according to claim 1, Features: A plurality of detection components are arranged on the drilling detection platform (51); the detection rods (52) of the plurality of detection components can contact the core tube (11) or the drill rod (12) from different positions and angles; the encoders (54) of the plurality of detection components can collaboratively determine the swing, vibration or offset generated when the core tube (11) or the drill rod (12) rotates, as well as the direction of the offset; The drilling detection platform (51) is also provided with a second driver (56) and a retractable connecting piece (57) connecting the second driver (56) and the detection rod (52); the second driver (56) can control the retractable connecting piece (57) to be tightened, and when the retractable connecting piece (57) is tightened, it can compress and push the elastic piece (55) to make the detection rod (52) move away from the core tube (11) or the drill rod (12); when the core tube (11) or the drill rod (12) stops rotating, the second driver (56) controls the detection rod (52) to move away from the core tube (11) or the drill rod (12) to protect the detection rod (52).

Citation Information

Patent Citations

  • Rock core cabin clamp for deep in-situ fidelity coring calibration platform

    CN114458202A

  • High-frequency sound wave type low-disturbance drilling coring device and coring method

    CN118187730A

  • Pile foundation construction positioning device

    CN118390977A

  • Building concrete detection core drilling device

    CN218180353U

Cited By

  • Sampling device for detecting cast-in-place concrete pile

    CN119534018A