Transmission line spacer fault handling tool and its use method

By designing fault treatment tools for insulating rods, clamping mechanisms, opening and closing mechanisms, stepping lift mechanisms and hook components, the problem of fault treatment difficulties caused by the fall of the transmission line spacing rods is solved, the operation efficiency is improved and the operation strength is reduced, and the operation strength is reduced. The synchronous docking of the interphase spacer and the split spacer is carried out.

CN118712946BActive Publication Date: 2024-11-19WEIHAI POWER SUPPLY COMPANY OF STATE GRID SHANDONG ELECTRIC POWER COMPANY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411181552.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-27
Publication Date
2024-11-19
Estimated Expiration
2044-08-27

AI Technical Summary

Technical Problem

Under the action of wind vibration, the hinges of the power transmission line spacing rods are prone to fall off, resulting in difficulty in handling faults, high labor intensity and low operating efficiency.

Method used

A fault treatment tool including an insulating rod, a clamping mechanism, an opening and closing mechanism, a stepping lifting mechanism and a hook assembly are designed. The metal rod of the interphase spacer is clamped by a clamping mechanism, and the hook assembly and a stepping lifting mechanism are realized. The synchronous docking of interphase spacer and split spacer reduces the operation difficulty and labor intensity of the operators.

Benefits of technology

It improves the efficiency and safety of fault handling, reduces the working strength under single operation, and ensures the one-time connection between the lower end slot of the interphase spacer and the split spacer insert plate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118712946B_ABST
    Figure CN118712946B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of power transmission line maintenance, and discloses a power transmission line spacer fault handling tool and a method of using the tool, comprising an insulating rod, a clamping mechanism, an opening and closing mechanism, a stepping lifting mechanism and a hook assembly, wherein the clamping mechanism is installed at the upper end of the insulating rod via a bent pipe connecting rod, and is used to clamp the metal rod at the upper end of the interphase spacer, the opening and closing mechanism is installed at the lower end of the insulating rod, and is used to drive the clamping mechanism to engage, the hook assembly comprises a hook plate and a U-shaped clamping plate, the hook plate is used to hook the split spacer of the falling conductor, the U-shaped clamping plate is used to cooperate with the plug plate of the split spacer, the closed end of the U-shaped clamping plate extends outward and is connected to the outer side of the stepping lifting mechanism, and the stepping lifting mechanism is movably connected to the insulating rod, and is used to drive the hook assembly to move in the direction close to / away from the clamping mechanism. The present invention improves the operating efficiency of operators and reduces the operating intensity of operators on the premise of ensuring that the spacer is intact during the processing.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power transmission line maintenance, in particular to a power transmission line spacer fault processing tool and a use method thereof. Background Art

[0002] In order to maintain the phase spacing between transmission lines and prevent the lines from whipping each other due to the dancing of wind, spacers need to be installed between the transmission lines for protection. That is, the split conductors in the same group are connected by split spacers, and the split spacers between the upper and lower groups of split conductors are connected by phase spacers.

[0003] In order to ensure that the transmission lines where the spacers are installed still have a certain degree of mobility, the phase spacers and the split spacers are hinged by setting slots and plug-in plates; however, under the vibration of wind, the hinge at the lower end of the phase spacers may fall off, thereby affecting the safe operation of the transmission lines in the area.

[0004] At present, the method for handling the detached conductor at the lower end of the phase spacer is to use a soft ladder and equipotential operation, that is, the operator climbs to the vicinity of the detachment operation position of the split conductor below through the soft ladder, pulls down the phase spacer at the corresponding position until the lower end slot of the phase spacer is docked with the split spacer plug-in plate on the split conductor below, and uses the pin shaft to complete the fixation again; since the split conductor at the working point position is added with the load of the operator and the soft ladder, the distance between the upper and lower split conductors is bound to increase. In order to effectively grab the phase spacer, the operator generally uses an insulated hook as an auxiliary tool to hook the equalizing ring at the lower end of the phase spacer and pull it down. However, when pulling the phase spacer, the equalizing ring is easily deformed due to the offset of the pulling force, thereby making it impossible to carry out the fault handling work smoothly. Moreover, the docking of the slot and the plug-in plate under the condition of large spacing is not only labor-intensive, but also difficult for the operator to achieve successful docking in one go, resulting in low work efficiency. Summary of the Invention

[0005] In order to solve the above-mentioned deficiencies of the prior art, the present invention provides a transmission line spacer fault handling tool and a method of using the same, which improves the operating efficiency of operators and reduces their working intensity while ensuring that the spacer is intact during the handling process.

[0006] The technical solution of the present invention is: a transmission line spacer fault handling tool, including an insulating rod, a clamping mechanism, an opening and closing mechanism, a step-by-step lifting mechanism and a hook assembly, the clamping mechanism is installed on the upper end of the insulating rod through a bent pipe connecting rod, and is used to clamp the metal rod at the upper end of the phase spacer, the opening and closing mechanism is installed at the lower end of the insulating rod, and is used to drive the clamping mechanism to engage, the hook assembly includes a hook plate and a U-shaped splint, the hook plate is fixed under the U-shaped splint, and is used to hook the split spacer of the detached conductor, the open end of the U-shaped splint faces the bending direction of the hook plate, and is used to cooperate with the plug plate of the split spacer, the closed end of the U-shaped splint extends outward and is connected to the outside of the step-by-step lifting mechanism, the step-by-step lifting mechanism is movably connected to the insulating rod, and is used to drive the hook assembly to move in the direction of approaching / away from the clamping mechanism. This tool controls the opening and closing of the clamping mechanism at the upper end of the insulating rod through the opening and closing mechanism at the lower end of the insulating rod, thereby realizing the clamping operation of the metal rod at the equalizing ring at the upper end of the interphase spacer, which can ensure the integrity of the interphase spacer when the interphase spacer is pulled down. At the same time, the hook assembly at the lower end of the insulating rod completes the positioning of the split spacer on the detached conductor under the action of the hook plate and the U-shaped clamp. Under the action of the stepping lifting mechanism, the interphase spacer located above and the split spacer located below are synchronously approached along the axis, thereby completing the one-time docking of the slot at the lower end of the interphase spacer with the plug-in plate of the split spacer, thereby improving the work efficiency of the operator and effectively reducing the work intensity under single-person operation.

[0007] The clamping mechanism includes a fixed arm, a transmission arm, a spring and a spring stopper. The insulating rod and the bent pipe connecting rod have an inner cavity pipe that is connected to each other. The spring stopper is fixed on the inner side of the middle part of the bent pipe connecting rod, and the fixed arm is fixed on the outer side of the end of the bent pipe connecting rod. The transmission arm is arranged opposite to the fixed arm, and jaws are provided on the opposite surfaces of the transmission arm and the fixed arm. A pull rod is fixed at one end of the transmission arm, which is inserted into the bent pipe connecting rod and slides through the spring stopper. The end of the pull rod is connected to the opening and closing mechanism along the inner cavity pipe via a pull rope. The spring is sleeved on the pull rod, and the two ends of the spring are respectively in contact with the transmission arm and the spring stopper.

[0008] The opening and closing mechanism includes an adjusting screw sleeve, an adjusting rod, and a fixed block. The upper end of the adjusting screw sleeve is rotatably connected to the lower end of the insulating rod. The fixed block is fixedly mounted on the inner side of the insulating rod near the adjusting screw sleeve. One end of the adjusting screw sleeve is threadedly mounted on the inner side of the adjusting screw sleeve. The other end of the adjusting screw sleeve is connected to the end of a traction rope on the inner side of the insulating rod via a non-cylindrical sliding rod. The opening and closing mechanism and the clamping mechanism are connected by a traction rope within the inner cavity of the insulating rod and the elbow connecting rod, effectively reducing the space required for the entire tool and facilitating single-person operation.

[0009] The step-by-step lifting mechanism includes a slide, a rack, a first internally-toothed ratchet, a first non-return pawl and a first tension spring, the rack being fixed to the outside of the insulating rod along the axis, the slide being sleeved on the insulating rod on the outside of the rack, and a gear box being fixed to the side of the slide close to the rack, the first internally-toothed ratchet being rotatably connected to the gear box via a center axis, and the center axis of the first internally-toothed ratchet passing through the gear box to form a first wrench part, the outer tooth part of the first internally-toothed ratchet being meshed with the rack, one end of the first non-return pawl being rotatably connected to the gear box via a hinge shaft, the hinge shaft of the first non-return pawl passing through the gear box and connected to the first toggle rod, the other end of the first non-return pawl having a pawl that prevents the first internally-toothed ratchet from reversing, and the two ends of the first tension spring being fixedly connected to the middle part of the first non-return pawl and the fixed shaft in the gear box respectively. By the forward rotation of the first internally-toothed ratchet and the meshing transmission with the rack, the stepping lifting mechanism drives the hook assembly to move in the direction close to the clamping mechanism, and under the action of the first non-return pawl, the unidirectional movement of the stepping lifting mechanism can be guaranteed; at the same time, the first internally-toothed ratchet serves as a small gear driving structure, which can save the operator's effort during operation.

[0010] The stepping lifting mechanism includes a lifting handle, a connecting rod, a step card, a step spring, a sliding sleeve, a locking sleeve, a locking spring and a steel ball. The sliding sleeve and the locking sleeve are slidably sleeved on the insulating rod from the inside to the outside in sequence. The lower end of the sliding sleeve extends out of the locking sleeve and is connected to the toggle ring. A spring pressure plate is formed on the upper end of the sliding sleeve, and a spring groove that matches the spring pressure plate is formed on the upper end of the locking sleeve. The upper end opening of the spring groove is sealed by a sealing ring. The locking spring is sleeved on the sliding sleeve between the spring pressure plate and the bottom of the spring groove. A plurality of fixing holes are opened in the middle of the sliding sleeve along the circumferential direction. The steel ball is movably arranged in the fixed hole, and the inner side of the locking sleeve has a wedge-shaped surface that forms a radial locking force on the steel ball. The step card is sleeved on the insulating rod above the locking sleeve, and the step spring is sleeved on the insulating rod between the step card and the locking sleeve. The two ends of the connecting rod are respectively hinged to the outer side of the step card and the middle part of the lifting handle. One end of the lifting handle is hinged to the outer side of the locking sleeve, and a control arm is formed at the hinged end of the lifting handle. The control arm moves along the rotation direction of the lifting handle and is squeezed with the spring pressure plate through the top pressure port opened on the sealing ring.

[0011] The cam is secured to the outside of the gear train with a second latch, and the cam is secured to the outside of the gear train with a second latch, and the cam is secured to the inside of the gear train with a second latch, and the cam is secured to the outside of the gear train with a second latch, and the cam is secured to the inside of the gear train with a second latch, and the cam is secured to the outside of the gear train with a second latch, and the cam is secured to the inside of the gear train with a second latch, Because the operators are performing equipotential operations, the detachment position of the split conductor below will be vertically offset due to uneven force during the movement of the operators or the action of its own gravity, that is, the two branches of the split conductor cannot be on the same horizontal plane. At this time, the split spacer on the split conductor is in an offset state, and a correction mechanism is installed at the connection position of the hook assembly and the stepping lifting mechanism. In the free state, the hook assembly is connected with the offset split spacer, and the split spacer is corrected to a horizontal position in the correction state. At this time, the opening of the U-shaped splint of the hook assembly is coaxial with the jaws of the clamping mechanism, which effectively improves the positioning effect of the slot at the lower end of the interphase spacer and the plug-in plate of the split spacer.

[0012] There are two hook plates, which are symmetrically distributed on both sides of the U-shaped clamping plate and are fixedly connected to the U-shaped clamping plate via a connecting frame.

[0013] An inner arc groove is formed on the inner side of the curved section of the curved tube connecting rod, and the radial distance between the lowest point of the inner arc groove and the outer wall of the curved tube connecting rod is equal to the radial distance between the rope connection hole in the middle of the pull rod and the outer wall of the curved tube connecting rod.

[0014] The present invention also provides a method for using a transmission line spacer fault handling tool, the specific operating steps are as follows:

[0015] S1. Initialization: Move the stepping lifting mechanism away from the clamping mechanism until the hook assembly reaches the initial position, and drive the opening and closing mechanism to control the clamping mechanism to be in the open state;

[0016] S2. Hooking preparation: Hold the insulating rod and extend the clamping mechanism at the upper end of the insulating rod to the metal rod at the upper end of the interphase spacer, drive the opening and closing mechanism to control the clamping mechanism to clamp the metal rod; pull down the insulating rod and toggle the second toggle lever to free the hook assembly, rotate the hook assembly until the hook portion and the U-shaped clamping plate of the hook assembly respectively engage with the split spacer of the detached conductor and the plug of the split spacer;

[0017] S3. Correct the wire: Use a wrench to buckle onto the second wrench part to drive the second internally geared ratchet to rotate forward. The second internally geared ratchet drives the closed end extension of the U-shaped splint to rotate reversely until the split spacer matched with the hook assembly reaches a horizontal position.

[0018] S4. Docking wires: Drive the stepping lifting mechanism to drive the hook assembly to move in the direction close to the clamping mechanism. The interphase spacer and the split spacer are synchronously moved close to each other until the slot at the lower end of the interphase spacer is mated with the plug plate of the split spacer, and then fixed with a pin;

[0019] S5. Completion: Move the stepping lifting mechanism in the direction away from the clamping mechanism until the hook assembly is separated from the split spacer, drive the opening and closing mechanism to control the clamping mechanism to be in the open state, and hold the insulating rod away from the transmission line.

[0020] In summary, the present invention mainly has the following beneficial effects:

[0021] The present invention controls the opening and closing of the clamping mechanism at the upper end of the insulating rod through the opening and closing mechanism located at the lower end of the insulating rod, thereby realizing the clamping operation of the metal rod located at the equalizing ring at the upper end of the phase spacer bar, which can ensure the integrity of the phase spacer bar when the phase spacer bar is pulled down. At the same time, the hook assembly located at the lower end of the insulating rod completes the positioning of the split spacer bar on the detached conductor under the action of the hook plate and the U-shaped clamp. Under the action of the stepping lifting mechanism, the phase spacer bar located above and the split spacer bar located below are synchronously approached along the axis, completing the one-time docking of the slot at the lower end of the phase spacer bar and the plug-in plate of the split spacer bar, thereby improving the work efficiency of the operator and effectively reducing the work intensity under single-person operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 is a structural diagram of embodiment 1 of the present invention;

[0023] Figure 2 It is a structural schematic diagram of the clamping mechanism of the present invention;

[0024] Figure 3 It is a structural schematic diagram of the opening and closing mechanism of the present invention;

[0025] Figure 4 1 is a schematic structural diagram of the stepping lifting mechanism in Example 1 of the present invention;

[0026] Figure 5 is a schematic structural diagram of embodiment 2 of the present invention;

[0027] Figure 6 2 is a schematic structural diagram of a step-by-step lifting mechanism in Example 2 of the present invention;

[0028] Figure 7 This is a diagram of the use state of the correction mechanism of the present invention, wherein Figure 7 (a) is a schematic diagram of the connection between the control hook assembly and the tilted split spacer in the free state of the correction mechanism. Figure 7 Middle (b) is a schematic diagram of the control hook assembly adjusting the split spacer to a horizontal position when the correction mechanism is in the correction state;

[0029] Figure 8 yes Figure 7 A partial enlarged view of middle A;

[0030] Figure 9 It is a diagram of the internal structure of the correction mechanism of the present invention;

[0031] Figure 10 yes Figure 5 A partial enlarged view of B.

[0032] 1. Insulating rod; 2. Elbow connecting rod; 201. Inner arc groove; 3. Clamping mechanism; 301. Fixed arm; 302. Transmission arm; 303. Spring stopper; 304. Spring; 305. Pull rod; 306. Pull rope; 4. Opening and closing mechanism; 401. Adjusting screw sleeve; 402. Adjusting screw; 403. Fixed block; 404. Fixed seat; 405. Positioning screw; 5. Hook assembly; 501. U-shaped splint; 502. Hook plate; 503. Missing teeth; 6. Stepping lifting mechanism; 601. Rack; 602. Slide; 603. Gear box; 604. First internally meshing ratchet; 605. First toggle lever; 606. First check pawl; 607. First wrench part; 6 08. First tension spring; 609. Sliding sleeve; 610. Locking sleeve; 611. Steel ball; 612. Locking spring; 613. Step card; 614. Pull handle; 615. Connecting rod; 616. Control arm; 617. Step spring; 618. Toggle ring; 619. Sealing ring; 620. Top pressure port; 7. Correction mechanism; 701. Connecting seat; 702. Second internal gear ratchet; 703. Second check pawl; 704. Hinge groove; 705. Second tension spring; 706. Second wrench part; 707. Second toggle rod; 708. Gear chamber; 8. Split spacer; 801. Insert plate; 9. Interphase spacer; 901. Equalizing ring; 902. Metal rod; 903. Slot. DETAILED DESCRIPTION

[0033] In order to enable those skilled in the art to better understand the technical solutions in the present invention, the technical solutions in the present invention are clearly and completely described below in conjunction with the accompanying drawings. Other embodiments obtained by those skilled in the art without making any creative work should fall within the scope of protection of the present invention.

[0034] like Figure 1 and Figure 5 As shown, the present invention provides a transmission line spacer fault handling tool, including an insulating rod 1, a clamping mechanism 3, an opening and closing mechanism 4, a stepping lifting mechanism 6 and a hook assembly 5, wherein the clamping mechanism 3 is installed on the upper end of the insulating rod 1 via a bend connecting rod 2. Specifically, the bend connecting rod 2 is a right-angle bend, the clamping mechanism 3 is vertically arranged to the bend connecting rod 2, and the axis of the clamping part of the clamping mechanism 3 is parallel to the axis of the insulating rod 1, and is used to clamp the metal rod 902 at the upper end of the interphase spacer 9. The opening and closing mechanism 4 is installed at the lower end of the insulating rod 1, and is used to drive the clamping mechanism 3 to engage, so that the operator can operate the clamping mechanism 3 to open and close by holding the lower end of the insulating rod 1, and complete the operation of the interphase spacer 9. The metal rod 902 at the upper end equalizing ring 901 is clamped to ensure the integrity of the phase spacer 9 when the phase spacer 9 is pulled down; the hook assembly 5 includes a hook plate 502 and a U-shaped splint 501, and the hook plate 502 is fixed below the U-shaped splint 501, and is used to hook the split spacer 8 of the detached wire. The open end of the U-shaped splint 501 faces the bending direction of the hook plate 502, and is used to cooperate with the plug 801 of the split spacer 8. The closed end of the U-shaped splint 501 extends outward and is connected to the outside of the step-by-step lifting mechanism 6. The step-by-step lifting mechanism 6 is movably connected to the insulating rod 1, and is used to drive the hook assembly 5 to move in the direction of approaching / moving away from the clamping mechanism 3. The hook assembly 5 of the above structure completes the positioning of the split spacer 8 on the detached conductor. Under the action of the stepping lifting mechanism 6, the phase spacer 9 located above and the split spacer 8 located below are synchronously approached along the axis of the phase spacer 9 until the slot 903 at the lower end of the phase spacer 9 is docked with the plug-in plate 801 of the split spacer 8. Since the axis of the insulating rod 1 is parallel to the axis of the phase spacer 9 during the docking process, the above docking operation is a one-time docking, which greatly improves the work efficiency of the operator and at the same time reduces the work intensity under single-person operation.

[0035] Specifically, such as Figure 2As shown, the clamping mechanism 3 includes a fixed arm 301, a transmission arm 302, a spring 304 and a spring stopper 303, the insulating rod 1 and the elbow connecting rod 2 have an inner cavity pipeline that is interconnected, the spring stopper 303 is fixed on the inner side of the middle part of the elbow connecting rod 2, the fixed arm 301 is fixed on the outer side of the end of the elbow connecting rod 2, the transmission arm 302 is arranged on one side of the fixed arm 301, and the opposite surfaces of the transmission arm 302 and the fixed arm 301 are provided with jaws, which form the clamping part of the clamping mechanism 3; one end of the transmission arm 302 is fixed with a pull rod 305 that is inserted into the elbow connecting rod 2 and slides through the spring stopper 303, the end of the pull rod 305 is connected to the opening and closing mechanism 4 along the inner cavity pipeline via a pull rope 306, the spring 304 is sleeved on the pull rod 305, and the two ends of the spring 304 are respectively in contact with the transmission arm 302 and the spring stopper 303.

[0036] like Figure 3 As shown, the opening and closing mechanism 4 includes an adjusting screw sleeve 401, an adjusting screw 402 and a fixed block 403. The upper end of the adjusting screw sleeve 401 is rotatably connected to the lower end of the insulating rod 1, and the fixed block 403 is fixedly installed on the inner side of the insulating rod 1 near the adjusting screw sleeve 401. One end of the adjusting screw 402 is threadedly mounted on the inner side of the adjusting screw sleeve 401, and the other end of the adjusting screw 402 passes through the fixed block 403 through a non-cylindrical sliding rod and is connected to the end of the pull rope 306 on the inner side of the insulating rod 1. The opening and closing mechanism 4 and the clamping mechanism 3 are connected in the inner cavity pipe of the insulating rod 1 and the bent pipe connecting rod 2 through the pull rope 306, which can effectively reduce the usage space of the entire tool and facilitate single-person operation. When the operator operates, by rotating the adjusting screw sleeve 401 in the forward direction, the adjusting screw 402 is driven to move downward and the pull rope 306 is driven to pull the transmission arm 302 inward, and the jaws of the transmission arm 302 and the jaws of the fixed arm 301 are close to each other, thereby generating a clamping force; when the adjusting screw sleeve 401 is reversed, the adjusting screw 402 moves upward, and the compressed spring 304 unloads the force to push the transmission arm 302 to reset, thereby putting the clamping mechanism 3 in an open state.

[0037] Further preferably, in order to improve the smoothness of the movement of the pull rope 306 driving the pull rod 305, an inner arc groove 201 is formed on the inner side of the curved section of the curved tube connecting rod 2, and the radial distance between the lowest point of the inner arc groove 201 and the outer wall of the curved tube connecting rod 2 is equal to the radial distance between the pull rope 306 connection hole in the middle of the pull rod 305 and the outer wall of the curved tube connecting rod 2.

[0038] In order to facilitate the installation of the opening and closing mechanism 4 at the lower end of the insulating rod 1, the fixing block 403 is located on the inner side of the lower end of the insulating rod 1, and the outer side of the lower end of the insulating rod 1 is sleeved with a fixing seat 404. A plurality of screws are provided on the circumference of the fixing seat 404, which pass through the fixing seat 404 and the insulating rod 1 in sequence and are threadedly connected to the fixing block 403. A through opening is provided in the middle of the fixing seat 404 for the adjusting screw sleeve 401 to pass through. There is an annular gap between the fixing block 403 and the connecting seat 701, and a boss is formed on the upper end of the adjusting screw sleeve 401 that cooperates with the annular gap. The rotation cooperation between the adjusting screw sleeve 401 and the insulating rod 1 is achieved by rotating the boss in the annular gap; further preferably, the non-cylindrical sliding rod at the upper end of the adjusting screw 402 is rectangular, and a plurality of positioning screws 405 are fixed on the position of the insulating rod 1 close to the sliding rod. The end face of the positioning screw cooperates with the side face of the sliding rod to slide, further ensuring the directional movement of the sliding rod.

[0039] In Example 1, Figure 1 and Figure 4 As shown, the step-by-step lifting mechanism 6 includes a slide 602, a rack 601, a first internally-geared ratchet 604, a first anti-return pawl 606 and a first tension spring 608. The rack 601 is fixed to the outside of the insulating rod 1 along the axis, and the slide 602 is sleeved on the insulating rod 1 outside the rack 601, and a gear box 603 is fixed to the side of the slide 602 close to the rack 601. The first internally-geared ratchet 604 is rotatably connected to the gear box 603 via the central axis, and the central axis of the first internally-geared ratchet 604 passes through the gear box 603. A first wrench portion 607 is formed by passing through the gear box 603, and the outer tooth portion of the first internally meshing ratchet is engaged with the rack 601. One end of the first non-return pawl 606 is rotatably connected to the gear box 603 via a hinge shaft. The hinge shaft of the first non-return pawl 606 passes through the gear box 603 and is connected to the first toggle rod 605. The other end of the first non-return pawl 606 has a pawl for preventing the first internally meshing ratchet 604 from reversing. The two ends of the first tension spring 608 are respectively fixedly connected to the middle part of the first non-return pawl 606 and the fixed shaft in the gear box 603. By the forward rotation of the first internally geared ratchet 604 and the meshing transmission with the rack 601, the stepping lifting mechanism 6 drives the hook assembly 5 to move in the direction close to the clamping mechanism 3, and under the action of the first non-return claw 606, the unidirectional movement of the stepping lifting mechanism 6 can be guaranteed; the first non-return claw 606 is driven away from the first internally geared ratchet 604 by the first toggle rod 605, that is, the reverse locking state of the first internally geared ratchet 604 is cancelled, and the gear box 603 can be slid in the reverse direction to drive the hook assembly 5 to move in the direction away from the clamping mechanism 3.

[0040] like Figure 7As shown in the figure, when the operator is performing equipotential operation, the detachment position of the lower split conductor will be vertically offset due to the uneven force generated by the operator's movement and the gravity of the split conductor itself, that is, the two branches of the split conductor cannot be on the same horizontal plane, such as Figure 7 As shown in (a), the split spacer 8 on the split conductor is in an offset state. In order to make the hook assembly 5 fit with the split spacer 8 in this state and adjust it to a horizontal state, a correction mechanism 7 is provided between the hook assembly 5 and the step-by-step lifting mechanism 6. Figure 8 and Figure 9 As shown, the correction mechanism 7 includes a connecting seat 701, a second internally meshed ratchet 702, a second anti-return pawl 703 and a second tension spring 705. One end of the connecting seat 701 is fixed to the outside of the step-by-step lifting mechanism 6. Specifically, in Example 1, the connecting seat 701 is fixed below the gear box 603, and the other end of the connecting seat 701 has a hinge groove 704 hinged to the closed end extension of the U-shaped splint 501. The connecting seat 701 has a gear chamber 708 connected to the hinge groove 704. The first internally meshed ratchet is rotatably connected to the gear chamber 708 via the central axis, and the second internally meshed ratchet The central axis of 702 passes through the connecting seat 701 to form a second wrench part 706, and the outer tooth part of the second internally meshing ratchet engages with the missing tooth 503 formed on the extended part of the closed end of the U-shaped splint 501. One end of the second non-return pawl 703 is connected to the gear chamber 708 via a hinge shaft. The hinge shaft of the second non-return pawl 703 passes through the connecting seat 701 and is connected to the second toggle rod 707. The other end of the second non-return pawl 703 has a pawl for preventing the second internally meshing ratchet 702 from reversing. The two ends of the second tension spring 705 are fixedly connected to the middle part of the second non-return pawl 703 and the fixed shaft in the gear chamber 708 respectively. When the hook assembly 5 is adapted to the split spacer 8 in the offset state, the second toggle rod 707 is toggled to make the second anti-return claw 703 away from the second internally geared ratchet 702, canceling the reverse lock of the second internally geared ratchet 702, so that the hook assembly 5 is in a free state, and the hook assembly 5 is rotated to a certain angle to connect with the offset split spacer 8, and the second toggle rod 707 is released. At this time, the correction mechanism 7 enters the correction state, and the second internally geared ratchet 702 is rotated forward. The second internally geared ratchet 702 drives the missing tooth 503 to rotate, thereby driving the U-shaped splint 501 to rotate in the opposite direction. Figure 7 As shown in (b), the split spacer 8 is corrected to a horizontal position. At this time, the opening of the U-shaped clamping plate 501 of the hook assembly 5 is coaxial with the jaws of the clamping mechanism 3, which effectively improves the positioning effect of the slot 903 at the lower end of the interphase spacer 9 and the plug plate 801 of the split spacer 8.

[0041] In order to ensure that the force exerted by the hook assembly 5 on the split spacer 8 is balanced and to improve the stability of the split spacer 8 on the hook assembly 5 during the upward movement of the hook assembly 5, there are two hook plates 502, which are symmetrically distributed on both sides of the U-shaped splint 501 and fixedly connected to the U-shaped splint 501 via a connecting frame.

[0042] When an operator discovers that a gap spacer on a transmission line has fallen off during an inspection, the operator should carry this tool and a corresponding wrench, climb to the location where the split conductor has fallen off using a soft ladder, and troubleshoot the problem according to the following steps.

[0043] S1. Initialization: Toggle the first toggle lever 605 on the step-by-step lifting mechanism 6 to disengage the first anti-return pawl 606 from the first internally geared ratchet 604, slide the slide 602 of the step-by-step lifting mechanism 6 away from the clamping mechanism 3, and drive the hook assembly 5 to the initial position. Rotate the adjusting screw sleeve 401 in the reverse direction to drive the adjusting screw 402 upward. The front end of the traction rope 306 is unloaded, and the transmission arm 302 moves away from the fixed arm 301 under the reset action of the spring 304, so that the clamping mechanism 3 is in the open state.

[0044] S2, hook preparation: hold and lift the insulating rod 1 until the clamping mechanism 3 at the upper end of the insulating rod 1 reaches above the grading ring 901 at the upper end of the interphase spacer 9, move the insulating rod 1 close to the interphase spacer 9 until the jaws of the clamping mechanism 3 are aligned with the metal rod 902 at this position of the interphase spacer 9, rotate the adjusting screw sleeve 401 forward, drive the adjusting screw 402 to move downward and drive the pull rope 306 to pull the transmission arm 302 inward, the jaws of the transmission arm 302 and the jaws of the fixed arm 301 approach each other, and generate a clamping force on the metal rod 902; at this time, hold the hook assembly 5 (specifically, hold the closed end extension of the U-shaped splint 501) and pull down the insulating rod 1, and at the same time, toggle the second toggle rod 707 to make the hook assembly 5 in a free state, rotate the hook assembly 5 until the hook part of the hook assembly 5 and the U-shaped splint 501 are respectively matched with the split spacer 8 of the fallen wire and the plug 801 of the split spacer 8;

[0045] S3. Correct the wire: Release the second toggle lever 707, the second anti-return pawl engages the second internally-toothed ratchet 702, and the correction mechanism 7 is in the correction state. Use a wrench to engage the second wrench portion 706, driving the second internally-toothed ratchet 702 to rotate forward. The second internally-toothed ratchet 702 drives the closed end extension of the U-shaped clamping plate 501 to reverse until the split spacer 8 matched with the hook assembly 5 reaches the horizontal position. At this time, the opening of the U-shaped clamping plate 501 of the hook assembly 5 is coaxial with the jaws of the clamping mechanism 3.

[0046] S4. Docking wires: Use a wrench to buckle on the first wrench part 607 to drive the first internally geared ratchet 604 to rotate forward, meshing with the rack 601 for transmission, and driving the hook assembly 5 to move in the direction close to the clamping mechanism 3. Since the first internally geared ratchet 604 is a pinion drive structure compared to the rack 601, the operator can save effort to complete the step-by-step movement of the hook assembly 5. During the synchronous approach of the interphase spacer 9 and the split spacer 8, the split spacer 8 plug-in plate 801 at the opening of the U-shaped plate and the interphase spacer 9 clamped by the clamping mechanism 3 are always in a coaxial state, thereby completing the docking operation of the plug-in plate 801 of the split spacer 8 and the slot 903 at the lower end of the interphase spacer 9 at one time, and finally use the pin shaft to fix it;

[0047] S5. Completion: Toggle the first toggle rod 605 and slide the slide 602 away from the clamping mechanism 3 to drive the hook assembly 5 to disengage the split spacer 8, reverse the adjusting screw sleeve 401 to reset the transmission arm 302 to the open state, and hold the insulating rod 1 away from the power transmission line.

[0048] The difference between Example 2 and Example 1 is that Figure 5 and Figure 6 As shown, the stepping lifting mechanism 6 includes a lifting handle 614, a connecting rod 615, a stepping card 613, a stepping spring 617, a sliding sleeve 609, a locking sleeve 610, a locking spring 612 and a steel ball 611. The sliding sleeve 609 and the locking sleeve 610 are slidably sleeved on the insulating rod 1 from the inside to the outside in sequence. The lower end of the sliding sleeve 609 extends out of the locking sleeve 610 and is connected to the toggle ring 618. A spring pressure plate is formed on the upper end of the sliding sleeve 609, and a spring groove that matches the spring pressure plate is formed on the upper end of the locking sleeve 610. The upper end opening of the spring groove is sealed by a sealing ring 619. The locking spring 612 is sleeved on the sliding sleeve 609 between the spring pressure plate and the bottom of the spring groove. A plurality of fixed holes are opened in the middle of the sliding sleeve 609 along the circumferential direction. The steel ball 611 is movably disposed within the fixed hole. The inner side of the locking sleeve 610 has a wedge-shaped surface that exerts a radial locking force on the steel ball 611. The stepping clamp 613 is sleeved onto the insulating rod 1 above the locking sleeve 610. The stepping spring 617 is sleeved onto the insulating rod 1 between the stepping clamp 613 and the locking sleeve 610. The ends of the connecting rod 615 are respectively hinged to the outer side of the stepping clamp 613 and the middle of the lifting handle 614. One end of the lifting handle 614 is hinged to the outer side of the locking sleeve 610. A control arm 616 is formed at the hinged end of the lifting handle 614. The control arm 616 moves in the direction of rotation of the lifting handle 614 and is pressed against the spring pressure plate through the top pressure port 620 provided on the sealing ring 619. Correspondingly, in Example 2, the connecting seat 701 within the correction mechanism 7 is fixed to the outer side of the locking sleeve 610.

[0049] When the step-by-step lifting mechanism 6 in Example 2 is used to lift the hook assembly 5, since the hook assembly 5 outside the locking sleeve 610 is mated with the split spacer rod 8, the locking sleeve 610 is pulled downward under the action of gravity, and the wedge-shaped surface inside the locking sleeve 610 generates a radial locking force on the steel ball 611, so that the locking sleeve 610 and the inner sliding sleeve 609 are locked together on the insulating rod 1; the lifting handle 614 is pulled upward, and the inner wall of the step clamp 613 is tilted and clamped on the insulating rod 1, and the control arm 616 at the end of the lifting handle enters the locking sleeve 610 along the top pressure port as the lifting arm rotates and squeezes the spring pressure plate. The locking spring 612 below the spring pressure plate is compressed and the spring pressure plate drives the steel ball 611 on the sliding sleeve 609 to break away from the wedge-shaped surface inside the locking sleeve 610. The pressure applied by the steel ball 611 on the insulating rod 1, at this time, the sliding sleeve 609 and the locking sleeve 610 are in a sliding state together. Under the action of the lever, the hinge of the lifting handle 614 and the step card 613 is used to lock the stepping rod 1. When the lifting handle 614 is lowered, the control arm 616 is separated from the spring pressure plate, the locking spring 612 is reset, the steel ball contacts the inner wedge surface of the inner side of the locking sleeve 610, and under the action of gravity, the locking sleeve 610 is locked on the insulating rod 1 together with the inner sliding sleeve 609 again, and the inner wall of the stepping card 613 is restored to the insulating rod 1. The parallel gap between the outer walls drives the step card 613 to move up a certain distance under the reset action of the step spring 617, and the upward pulling operation of the lifting handle 614 is repeated to complete the step-by-step lifting operation of the step-by-step lifting mechanism 6; if it is necessary to restore the step-by-step lifting mechanism 6 to the initial position or move the step-by-step lifting mechanism 6 at the end position down to separate the hook assembly 5 from the split spacer rod 8, pull the toggle ring 618 downward to drive the steel ball in the sliding sleeve 609 to disengage from the wedge surface inside the locking sleeve 610.

[0050] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only preferred examples of the present invention and are not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the scope of protection of the present invention.

Claims

1. Transmission line spacer fault handling tool, characterized in that: The invention comprises an insulating rod (1), a clamping mechanism (3), an opening and closing mechanism (4), a step-by-step lifting mechanism (6) and a hook assembly (5); the clamping mechanism (3) is installed at the upper end of the insulating rod (1) via a bent tube connecting rod (2) and is used to clamp a metal rod (902) at the upper end of an interphase spacer (9); the opening and closing mechanism (4) is installed at the lower end of the insulating rod (1) and is used to drive the clamping mechanism (3) to engage; the hook assembly (5) comprises a hook plate (502) and a U-shaped clamp plate (501); the hook plate (502) is fixed below the U-shaped clamp plate (501) and is used to hook the split spacer of a fallen conductor. (8), the open end of the U-shaped clamping plate (501) faces the bending direction of the hook plate (502) and is used to cooperate with the plug plate (801) of the split spacer rod (8), the closed end of the U-shaped clamping plate (501) extends outward and is connected to the outside of the step-by-step lifting mechanism (6), the step-by-step lifting mechanism (6) is movably connected to the insulating rod (1), and is used to drive the hook assembly (5) to move in a direction approaching / away from the clamping mechanism (3); a correction mechanism (7) is provided between the hook assembly (5) and the step-by-step lifting mechanism (6), and the correction mechanism (7) includes a connecting seat (701), a second internally meshing ratchet ( 702), a second anti-return claw (703) and a second tension spring (705), one end of the connecting seat (701) is fixed to the outside of the stepping lifting mechanism (6), the other end of the connecting seat (701) has a hinge groove (704) hinged to the extended portion of the closed end of the U-shaped clamping plate (501), the connecting seat (701) has a gear chamber (708) connected to the hinge groove (704), the second internally-geared ratchet (702) is rotatably connected to the gear chamber (708) via the central axis, and the central axis of the second internally-geared ratchet (702) passes through the connecting seat (701) to form a second wrench portion (706) ), the outer tooth portion of the second internally meshing ratchet (702) meshes with the missing tooth (503) formed on the outer extension of the closed end of the U-shaped clamp (501), one end of the second anti-return pawl (703) is rotatably connected to the gear chamber (708) via a hinge shaft, the hinge shaft of the second anti-return pawl (703) passes through the connecting seat (701) and is connected to the second toggle rod (707), the other end of the second anti-return pawl (703) has a pawl for preventing the second internally meshing ratchet (702) from reversing, and the two ends of the second tension spring (705) are fixedly connected to the middle part of the second anti-return pawl (703) and the fixed shaft in the gear chamber (708), respectively.

2. The power transmission line spacer fault handling tool according to claim 1, characterized in that: The clamping mechanism (3) comprises a fixed arm (301), a transmission arm (302), a spring (304) and a spring stopper (303); the insulating rod (1) and the curved tube connecting rod (2) have an inner cavity pipeline that is interconnected; the spring stopper (303) is fixed to the inner side of the middle part of the curved tube connecting rod (2); the fixed arm (301) is fixed to the outer side of the end of the curved tube connecting rod (2); the transmission arm (302) is arranged opposite to one side of the fixed arm (301); and the transmission arm (304) is arranged opposite to the fixed arm (301); Jaws are provided on the opposite surfaces of the transmission arm (302) and the fixed arm (301), and a pull rod (305) is fixed at one end of the transmission arm (302) and is inserted into the curved tube connecting rod (2) and slides through the spring stopper (303). The end of the pull rod (305) is connected to the opening and closing mechanism (4) along the inner cavity pipeline via a pull rope (306), and the spring (304) is sleeved on the pull rod (305), and the two ends of the spring (304) are respectively in contact with the transmission arm (302) and the spring stopper (303).

3. The power transmission line spacer fault handling tool according to claim 2, characterized in that: The opening and closing mechanism (4) comprises an adjusting screw sleeve (401), an adjusting screw rod (402) and a fixing block (403); the upper end of the adjusting screw sleeve (401) is rotatably connected to the lower end of the insulating rod (1); the fixing block (403) is fixedly mounted on the inner side of the insulating rod (1) near the adjusting screw sleeve (401); one end of the adjusting screw rod (402) is threadedly mounted on the inner side of the adjusting screw sleeve (401); the other end of the adjusting screw rod (402) passes through the fixing block (403) via a non-cylindrical sliding rod and is connected to the end of a pull rope (306) on the inner side of the insulating rod (1).

4. The power transmission line spacer fault handling tool according to any one of claims 1 to 3, characterized in that: The step-by-step lifting mechanism (6) comprises a slide (602), a rack (601), a first internally-meshed ratchet (604), a first anti-return pawl (606) and a first tension spring (608), wherein the rack (601) is fixed to the outside of the insulating rod (1) along an axis, the slide (602) is sleeved on the insulating rod (1) outside the rack (601), and a gear box (603) is fixed to the side of the slide (602) close to the rack (601), the first internally-meshed ratchet (604) is rotatably connected to the gear box (603) via a central axis, and the center of the first internally-meshed ratchet (604) is The shaft passes through the gear box (603) to form a first wrench portion (607), the outer tooth portion of the first internally meshing ratchet is meshed with the rack (601), one end of the first anti-return pawl (606) is rotatably connected to the gear box (603) via a hinge shaft, the hinge shaft of the first anti-return pawl (606) passes through the gear box (603) and is connected to the first toggle rod (605), the other end of the first anti-return pawl (606) has a pawl for preventing the first internally meshing ratchet (604) from reversing, and the two ends of the first tension spring (608) are respectively fixedly connected to the middle of the first anti-return pawl (606) and a fixed shaft in the gear box (603).

5. The power transmission line spacer fault handling tool according to any one of claims 1 to 3, characterized in that: The stepping lifting mechanism (6) comprises a lifting handle (614), a connecting rod (615), a stepping clamp (613), a stepping spring (617), a sliding sleeve (609), a locking sleeve (610), a locking spring (612) and a steel ball (611). The sliding sleeve (609) and the locking sleeve (610) are slidably sleeved on the insulating rod (1) from the inside to the outside in sequence. The lower end of the sliding sleeve (609) extends out of the locking sleeve (610) and is connected to the toggle ring (618). A spring pressure plate is formed on the upper end of the sliding sleeve (609). A spring groove matching the spring pressure plate is formed on the upper end of the locking sleeve (610), and the upper end opening of the spring groove is sealed by a sealing ring (619). The locking spring (612) is sleeved on the sliding sleeve (609) between the spring pressure plate and the bottom of the spring groove. A plurality of fixing holes are opened in the middle of the sliding sleeve (609) along the circumferential direction. The steel ball (611) is movably arranged in the fixing hole, the inner side of the locking sleeve (610) has a wedge-shaped surface for forming a radial locking force on the steel ball (611), the step card (613) is sleeved on the insulating rod (1) above the locking sleeve (610), the step spring (617) is sleeved on the insulating rod (1) between the step card (613) and the locking sleeve (610), the two ends of the linkage rod (615) are respectively hinged to the outer side of the step card (613) and the middle part of the lifting handle (614), one end of the lifting handle (614) is hinged to the outer side of the locking sleeve (610), and a control arm (616) is formed on the hinged end of the lifting handle (614), the control arm (616) moves along the rotation direction of the lifting handle (614) and is pressed against the spring pressure plate through a top pressure port (620) provided on the sealing ring (619).

6. The power transmission line spacer fault handling tool according to claim 1, characterized in that: There are two hook plates (502), which are symmetrically distributed on both sides of the U-shaped clamping plate (501) and are fixedly connected to the U-shaped clamping plate (501) via a connecting frame.

7. The power transmission line spacer fault handling tool according to claim 3, characterized in that: An inner arc groove (201) is formed on the inner side of the curved section of the curved tube connecting rod (2), and the radial distance between the lowest point of the inner arc groove (201) and the outer wall of the curved tube connecting rod (2) is equal to the radial distance between the connecting hole of the pull rope (306) in the middle of the pull rod (305) and the outer wall of the curved tube connecting rod (2).

8. A method for using a transmission line spacer fault handling tool, using the transmission line spacer fault handling tool according to claim 6, characterized in that: The specific steps are as follows: S1, initialization: moving the stepping lifting mechanism (6) in a direction away from the clamping mechanism (3) until the hook assembly (5) reaches an initial position, and driving the opening and closing mechanism (4) to control the clamping mechanism (3) to be in an open state; S2, hooking preparation: holding the insulating rod (1) and extending the clamping mechanism (3) at the upper end of the insulating rod (1) to the metal rod (902) at the upper end of the interphase spacer (9), driving the opening and closing mechanism (4) to control the clamping mechanism (3) to clamp the metal rod (902); pulling down the insulating rod (1), and moving the second moving rod (707) to make the hook assembly (5) in a free state, rotating the hook assembly (5) until the hook part of the hook assembly (5) and the U-shaped clamping plate (501) are respectively matched with the split spacer (8) of the fallen wire and the plug plate (801) of the split spacer (8); S3, correcting the wire: using a wrench to buckle onto the second wrench portion (706), driving the second internally-toothed ratchet (702) to rotate forward, and the second internally-toothed ratchet (702) drives the closed end extension of the U-shaped clamp (501) to rotate reversely until the split spacer (8) matched with the hook assembly (5) reaches a horizontal position; S4, docking the wires: driving the stepping lifting mechanism (6) to drive the hook assembly (5) to move in a direction close to the clamping mechanism (3), and the interphase spacer (9) and the split spacer (8) are synchronously approached until the slot (903) at the lower end of the interphase spacer (9) is docked with the plug plate (801) of the split spacer (8), and fixed with a pin shaft; S5, completion: move the stepping lifting mechanism (6) in a direction away from the clamping mechanism (3) until the hook assembly (5) is separated from the split spacer (8), drive the opening and closing mechanism (4) to control the clamping mechanism (3) to be in an open state, and hold the insulating rod (1) away from the power transmission line.