Integrated metal sound barrier assembling device
By designing an automated sound barrier assembly device, we solve the problems of low manual handling and flipping assembly efficiency and high safety hazards, achieve precise installation of components and lighting adjustment, and improve production efficiency and equipment reliability.
Patent Information
- Application Number
- CN202410992941.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-23
- Publication Date
- 2024-10-01
AI Technical Summary
The assembly process of existing sound barriers requires manual handling and flipping for assembly, resulting in low efficiency, high safety hazards, unstable product quality, and cumbersome lighting adjustments that affect operational accuracy.
An integrated metal sound barrier assembly device is designed, including components, storage platform, driving frame, lifting fixture, assembly operating table and flip fixture. Through the cooperation of racks, rotating columns, electric push rods, dampers and other components, Realize the automatic transportation and flip installation of parts, and adjust the height of the driving frame and the brightness of the lighting according to the work needs.
Improves installation efficiency and safety, ensures accurate installation of components, reduces manual operating errors and safety hazards, provides optimal lighting conditions, reduces impact, extends equipment service life, and improves overall work quality and production efficiency.
Smart Images

Figure HDA0004959362710000011 
Figure HDA0004959362710000021 
Figure HDA0004959362710000031
Abstract
Description
Technical Field
[0001] The invention relates to the field of sound barrier production and assembly, and in particular to an integrated metal sound barrier assembly device. Background Art
[0002] At present, the sound barrier assembly production line mainly relies on manual operation, and workers perform assembly work on ordinary operating tables. The whole process usually includes material preparation, assembly, fixation and inspection of components. Workers need to manually operate in each step, such as cutting, punching, connecting and assembling sound barrier components. Although the whole process is relatively simple and does not require complex equipment, workers still need to have certain skills and experience to ensure the quality and precision of each sound barrier component; it is highly flexible and can be quickly adjusted according to different project requirements. In addition, the manual operation method makes the production line investment cost lower, does not require a large number of mechanical equipment and automation systems, and is suitable for small and medium-sized production enterprises. At the same time, since workers can monitor and adjust in real time at each step, the assembled sound barrier has certain advantages in quality control.
[0003] Since there are many parts in the sound barrier, if all the parts are placed around the operating table, the site will become very chaotic. This chaos not only affects the workers' operating efficiency, but also increases the time cost of workers in finding and moving parts. If the placement and order of each part are not clear, it is easy to cause confusion and wrong operation in the workers' work, which further affects the assembly efficiency and product quality. In addition, during the assembly process, the sound-absorbing board is usually heavy, and the metal sound barrier needs to be frequently turned over. If these tasks are completed by manpower alone, the efficiency is very low. Moreover, workers are prone to fatigue and injury due to long-term heavy lifting and turning operations.
[0004] In addition, when the equipment is adapted to the operator's operating space, lighting is also an important factor. As the operating height changes, the lighting angle and intensity will also change, which requires frequent manual adjustments to the lighting position and height. This adjustment process is not only time-consuming and labor-intensive, but also prone to insufficient or over-bright lighting, affecting the worker's line of sight and operating accuracy, further reducing production efficiency.
[0005] When moving the various components of the sound barrier, due to the limited space on the operating table, collisions between components are likely to occur. The impact force generated at this time may cause damage to the components, especially some delicate components and surface-treated components. During operation, if the components are damaged, it will not only affect the appearance and quality of the finished product, but also increase production costs and rework time. Summary of the invention
[0006] In view of the deficiencies in the prior art, the present invention provides an integrated metal sound barrier assembly device, which solves the problem that the assembly process requires manual handling and flipping for assembly.
[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions: an integrated metal sound barrier assembly device, including a component assembly, a storage platform is arranged on the top of the component assembly, a traveling frame is arranged on the top of the storage platform, a lifting fixture is arranged inside the traveling frame, an assembly workbench is arranged on one side of the component assembly, a flip fixture is fixedly connected to the top of the assembly workbench, and a finished product sample is arranged on one side of the assembly workbench.
[0008] Preferably, the traveling frame includes a plurality of supporting legs, each of which is slidably connected to an inner support rod, each of which is fixedly connected to a rack inside one side of the supporting legs, each of which is rotatably connected to a rotating column one inside the inner support rod on one side, each of which has a cylindrical gear fixedly connected to the outer wall of the rotating column one, the cylindrical gear being meshed with the rack, and each of which is provided with an electric push rod inside the other side of the supporting legs, and each of which has an output end fixedly connected to the bottom of the inner support rod.
[0009] Preferably, the outer wall of the rotating column 1 is fixedly connected with a driving wheel 1, the inner part of the inner support rod is rotatably connected with a rotating column 2, the outer wall of the rotating column 2 is fixedly connected with a driven wheel 1, a belt 1 is provided between the driving wheel 1 and the driven wheel 1, the outer wall of the rotating column 2 is fixedly connected with a bevel gear 1, the inner part of the inner support rod is rotatably connected with a bevel gear 2, and the bevel gear 1 is meshed with the bevel gear 2.
[0010] Preferably, one side of the bevel gear two is fixedly connected with a driving wheel two, the inside of the inner support rod is rotatably connected with a driven wheel two, a belt two is arranged between the driving wheel two and the driven wheel two, the bottom of the driven wheel two is fixedly connected with a rotating column three, the inside of the inner support rod is provided with a lighting lamp, the top of the rotating column three is provided with a knob, and the bottom of the rotating column three is fixedly connected to the top of the knob.
[0011] Preferably, the assembly workbench includes a support column, a sliding rod is slidably connected inside the support column, a fixed column is slidably connected inside the sliding rod, a spring is sleeved on the outer wall of the fixed column, one end of the fixed column is fixedly connected inside the support column, and the other end of the fixed column is fixedly connected to the bottom of the sliding rod.
[0012] Preferably, a fixing plate is fixedly connected to the outer wall of the support column, and an operating table is fixedly connected to the top of the sliding rod.
[0013] Preferably, the sliding rod and one side of the operating table are fixedly connected with a connecting plate, a connecting rod is rotatably connected inside the connecting plate, a plurality of connecting rods are symmetrically distributed up and down, one end of the upper connecting rod is rotatably connected to one end of the lower connecting rod, and one end of each connecting rod is rotatably connected to a sliding block.
[0014] Preferably, the outer wall of the slider is slidably connected to a fixed frame, a limit frame is fixedly connected between the fixed frames, a damper 1 is arranged inside the fixed frame, and an output end of the damper 1 is fixedly connected to one side of the slider.
[0015] Preferably, one side of the connecting plate is fixedly connected with a fixing block, and the fixing block is slidably connected inside the limiting frame.
[0016] Preferably, a damper 2 is arranged between the fixing blocks, the damper 2 is arranged on the top of the fixing block at the bottom, and the output end of the damper 2 is fixedly connected to the bottom of the connecting plate at the top.
[0017] Working principle: When the whole equipment is running, the corresponding storage platform will generally be placed on the parts and components first, and then the two cranes running on the crane track of the crane will control the lifting fixture to move, and then the built-in hydraulic components will control the lifting fixture to lift and lower. Finally, the controlled lifting fixture will pick up the parts and components placed on the storage platform and transport them to the assembly operating table for the operators to assemble. Then the storage platform of the team leader will be turned over by the flipping fixture to assemble on the other side. Finally, the assembled finished samples will be obtained, and the finished samples will be transported to the corresponding positions for placement through the crane and the lifting fixture. During the process, the corresponding traveling frame can adjust the height according to the operation requirements of the operators. At this time, the electric push rod can be driven first, so that the electric push rod pushes the inner support rod to rise, and then the protruding bottom of the inner support rod slides into the position of the support foot, which can drive the traveling track of the traveling frame itself to rise together. While the inner support rod is pushed up by the electric push rod, the inner support rod on the other side will also rise synchronously, and then the cylindrical gear will start to rotate through the meshing of the tooth marks between the rack and the cylindrical gear. At this time, the cylindrical gear will synchronously drive the driving wheel one to rotate through the rotating column one, so that the driven wheel one can drive the rotating column two and the bevel gear one through the transmission of the belt one. The bevel gear 1 rotates synchronously, and the bevel gear 2 rotates through the meshing of the tooth marks between the bevel gear 1 and the bevel gear 2, so that the bevel gear 2 rotates and drives the driving wheel 2 to rotate synchronously, and then the driven wheel 2 drives the rotating column 3 to rotate together through the transmission of the belt 2. At the same time, the rotating column 3 can drive the knob to rotate to control the brightness of the lighting. In this way, the overall working height of the traveling frame is increased to prevent obstruction to the work of the team leader, and the intensity of the lighting can be adjusted synchronously while rising. When the lifting fixture clamps the components to be assembled and places them on the assembly operating table for assembly, the corresponding components will first be placed by applying force to the operating table surface. This then drives the sliding rod to squeeze the spring under the restriction of the fixed column, causing a slight change in the height of the operating table. At the same time, the connecting plate fixed at the corresponding operating table position will drive the corresponding fixed block to transmit force to the position of damper two, thereby achieving the first shock absorption. At the same time, the position between the two connecting plates will also change, thereby changing the inclination angle of the connecting rod, so that the connecting rod can push the corresponding sliding block to transmit the force to the position of damper one under the restriction of the fixed frame, thereby achieving the second shock absorption. It takes effect simultaneously when the flipping fixture is flipping, thereby preventing damage to the components caused by the impact force generated during the clamping and placement of the components during the assembly operation.
[0018] The present invention provides an integrated metal sound barrier assembly device, which has the following beneficial effects:
[0019] 1. The present invention enables the entire equipment to realize automatic transportation and flip installation of sound barrier components through the coordination between components such as spare parts, storage platform, and traveling frame. This design eliminates the reliance on manual operation and greatly improves the installation efficiency and safety. It not only reduces the operational errors and safety hazards that may occur during manual transportation, but also ensures the precise installation of each component through an automated process, thereby improving the overall work quality and speed.
[0020] 2. The present invention enables the traveling frame to automatically adjust its height as needed during operation to adapt to different working spaces through the coordination between the rack, the rotating column and the driving wheel. The corresponding lighting lamps will also automatically adjust their brightness according to the change in the height of the traveling frame to provide optimal lighting conditions. This not only improves the convenience of operation, but also ensures that the lighting of the working environment is always in the best state, reducing operational errors caused by insufficient light.
[0021] 3. The present invention achieves a double-layer shock absorption effect through the cooperation between damper 1, damper 2, and fixed frame and other components. This design effectively reduces the impact force that the sound barrier components may generate on the operating table surface during installation, thereby protecting the safety of the equipment and operators. At the same time, the optimization of the shock absorption effect also extends the service life of the equipment, reduces maintenance costs, and improves the overall reliability of the equipment. BRIEF DESCRIPTION OF THE DRAWINGS
[0022] Figure 1 A perspective view of the present invention;
[0023] Figure 2 It is a schematic diagram of the internal structure of the traveling frame of the crane of the present invention;
[0024] Figure 3 for Figure 2 Enlarged view of point A in the middle;
[0025] Figure 4 for Figure 2 Enlarged view of point B in the middle;
[0026] Figure 5 for Figure 2 Enlarged view of point C in the middle;
[0027] Figure 6 It is a schematic diagram of an assembly operation table of the present invention;
[0028] Figure 7 for Figure 6 Enlarged view of point D in the middle;
[0029] Figure 8 It is a schematic diagram of the shock absorbing mechanism of the present invention.
[0030] Among them, 1. Components; 2. Storage platform; 3. Traveling frame; 4. Lifting fixture; 5. Assembly table; 6. Flip fixture; 7. Finished sample; 301. Support foot; 302. Inner support rod; 303. Rack; 304. Rotating column 1; 305. Driving wheel 1; 306. Cylindrical gear; 307. Belt 1; 308. Rotating column 2; 309. Driven wheel 1; 310. Bevel gear 1; 311. Bevel gear 2; 312. Driving wheel 2; 313 , belt two; 314, driven wheel two; 315, rotating column three; 316, knob; 317, lighting lamp; 318, electric push rod; 501, supporting column; 502, fixing column; 503, spring; 504, sliding rod; 505, operating table; 506, fixing plate; 507, connecting plate; 508, fixing block; 509, connecting rod; 510, sliding block; 511, damper one; 512, limiting frame; 513, damper two; 514, fixing frame. DETAILED DESCRIPTION
[0031] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0032] Example:
[0033] Please see attached Figure 1 An embodiment of the present invention provides an integrated metal sound barrier assembly device, including a component assembly 1, a storage platform 2 is arranged on the top of the component assembly 1, a traveling frame 3 is arranged on the top of the storage platform 2, a lifting fixture 4 is arranged inside the traveling frame 3, an assembly workbench 5 is arranged on one side of the component assembly 1, a flip fixture 6 is fixedly connected to the top of the assembly workbench 5, and a finished product sample 7 is arranged on one side of the assembly workbench 5.
[0034] Specifically, before the operation begins, the storage platform 2 is usually placed on the component assembly 1. The component assembly 1 includes various loose parts of the sound barrier and pre-processed parts. These component assemblies 1 are neatly arranged on the storage platform 2 for subsequent lifting and transportation; the traveling frame 3 is one of the key equipment of the entire operation production line. It runs through its own traveling track and controls two traveling cranes to realize the movement of the lifting fixture 4. The design of the traveling frame 3 ensures the smooth and precise operation, so that the movement and position adjustment of the component assembly 1 on the storage platform 2 can be carried out smoothly; the traveling frame 3 uses its control system to make the lifting fixture 4 move on the traveling track. After reaching the designated position, the lifting fixture 4 performs vertical lifting and lowering operation through its own hydraulic components. This process ensures that the component 1 on the storage platform 2 can be accurately lifted to a suitable height, ready for the next step of transportation; the lifting fixture 4 clamps the component 1 on the storage platform 2 and transports it to the position of the assembly operation table 5. During this process, the precise control of the lifting fixture 4 and the smooth operation of the traveling frame 3 ensure the safety and stability of the component 1. The component 1 is successfully placed on the assembly operation table 5 for the operator to perform the assembly operation; the operator assembles the component 1 on the assembly operation table 5 and flips the clamp. The tool 6 plays an important role in this process. It can flip the components 1 on the storage platform 2 so that the operator can easily perform the assembly work on the other side. The stability and accuracy of the flipping fixture 6 ensure the quality and efficiency of the assembly work. The finished sample 7 after assembly is transported by the traveling frame 3 and the lifting fixture 4. The lifting fixture 4 accurately clamps the finished sample 7 and moves it on the track of the traveling frame 3 to transport the finished sample 7 to the designated placement area. The finished sample 7 is neatly stacked here and is ready for further inspection or transportation. In the above scheme, the production line divides the metal sound barrier into three areas, namely, the parts storage area and the storage area. The storage area, assembly operation area and finished product placement area are connected together by a crane traveling frame 3. A set of sound barrier assembly production line is divided into two small crane devices, which are controlled separately and do not interfere with each other. The crane is connected under a lifting fixture 4, which can lift the loose parts or finished parts in different areas to the next area respectively, and the two ends of the lifting fixture 4 are made of rubber material to reduce the damage to the parts 1. The loose parts storage area and the finished product placement area are both provided with low-height storage platforms 2, which can temporarily place the parts 1. The assembly operation area is divided into two assembly workbenches 5. A space for one person is left between the two assembly workbenches 5 to assist the operations on both sides.
[0035] Please see attached Figure 2 -Attached Figure 5The traveling frame 3 includes a plurality of legs 301, each of which is slidably connected to an inner support rod 302, each of which is fixedly connected to a rack 303 inside one side of the legs 301, each of which is rotatably connected to a rotating column 1 304 inside the inner support rod 302 on one side, each of which is fixedly connected to a cylindrical gear 306 on the outer wall of the rotating column 1 304, which is meshed with the rack 303, and each of which is provided with an electric push rod 318 inside the legs 301 on the other side, and each of which has an output end fixedly connected to the bottom of the inner support rod 302, each of which is fixedly connected to a driving wheel 1 305 on the outer wall of the rotating column 1 304, each of which is rotatably connected to a rotating column 2 308 inside the inner support rod 302, each of which is fixedly connected to a driven wheel 1 309 on the outer wall of the rotating column 2 308, and each of which is fixedly connected to a driven wheel 1 305. A belt 1 307 is provided between the driven wheel 1 309, a bevel gear 1 310 is fixedly connected to the outer wall of the rotating column 2 308, a bevel gear 2 311 is rotatably connected to the inside of the inner support rod 302, the bevel gear 1 310 is meshed with the bevel gear 2 311, a driving wheel 2 312 is fixedly connected to one side of the bevel gear 2 311, the inside of the inner support rod 302 is rotatably connected to the driven wheel 2 314, a belt 2 313 is provided between the driving wheel 2 312 and the driven wheel 2 314, a rotating column 315 is fixedly connected to the bottom of the driven wheel 2 314, an illuminating lamp 317 is provided inside the inner support rod 302, a knob 316 is provided on the top of the rotating column 315, and the bottom of the rotating column 315 is fixedly connected to the top of the knob 316.
[0036] Specifically, when it is necessary to adjust the height of the traveling frame 3, the electric push rod 318 is first driven, and the electric push rod 318 begins to extend, pushing the inner support rod 302 to move upward. With the force of the electric push rod 318, the inner support rod 302 gradually rises, and the protruding bottom of the inner support rod 302 slides into the position of the support leg 301, driving the traveling frame 3 and its own traveling track to rise together. In this process, the inner support rod 302 on the other side will also rise synchronously, ensuring the overall stability and coordination of the traveling frame 3; when the inner support rod 302 rises, the tooth marks between the rack 303 and the cylindrical gear 306 are engaged, The cylindrical gear 306 rotates, and the cylindrical gear 306 drives the belt 1 307 synchronously through the connected rotating column 1 304 for transmission. The belt 1 307 drives the driven wheel 1 309 and the rotating column 2 308 to rotate synchronously. The rotating column 2 308 and the bevel gear 1 310 rotate synchronously. The bevel gear 1 310 drives the bevel gear 2 311 to rotate through the tooth mark meshing. When the bevel gear 2 311 rotates, the driving wheel 2 312 also rotates synchronously, and further drives the driven wheel 2 314 and the rotating column 3 315 to rotate together through the transmission of the belt 2 313; the rotating column 315 drives the knob 316 to rotate, and the knob 316 controls the light The brightness of the bright lamp 317 is adjusted synchronously as needed during the ascending process of the traveling frame 3, so as to ensure that the working area always maintains good lighting conditions and improve work efficiency and operation safety; through the above detailed operation process, the height adjustment and synchronous operation of each component and system are fully demonstrated, and the specific effects include: precise height adjustment, precise control of the electric push rod 318 and the inner support rod 302 ensures that the height of the traveling frame 3 can be accurately adjusted according to the operation requirements to meet the operation requirements of different processes; smooth synchronous operation, the rack 303 and the cylindrical gear 306 are The precise meshing and efficient operation of the belt drive system ensure that the traveling frame 3 is stable and synchronous during the height adjustment process without tilting or shaking, thereby ensuring the safety of equipment and personnel; the lighting system is intelligently adjusted, and the linkage between the rotating column 315 and the knob 316 allows the brightness of the lighting lamp 317 to be synchronously adjusted according to the height change, always maintaining the best lighting state, and improving the visibility and safety of the working environment; improving work efficiency, through automatic and semi-automatic height adjustment and synchronous operation, reducing manual intervention and adjustment time, greatly improving the overall work efficiency and the continuity of the production line.
[0037] Please see attached Figure 6 -Attached Figure 8The assembly operation table 5 includes a support column 501, a sliding rod 504 is slidably connected inside the support column 501, a fixed column 502 is slidably connected inside the sliding rod 504, a spring 503 is sleeved on the outer wall of the fixed column 502, one end of the fixed column 502 is fixedly connected to the inside of the support column 501, and the other end of the fixed column 502 is fixedly connected to the bottom of the sliding rod 504, a fixed plate 506 is fixedly connected to the outer wall of the support column 501, and an operation table 505 is fixedly connected to the top of the sliding rod 504, and a connecting plate 507 is fixedly connected to one side of the sliding rod 504 and the operation table 505, and a connecting rod 509 is rotatably connected inside the connecting plate 507, and a plurality of connecting rods 509 are symmetrically distributed up and down, and the upper connecting rod 509 One end is rotatably connected to one end of the lower connecting rod 509, and one end of the connecting rod 509 is rotatably connected to a slider 510. The outer wall of the slider 510 is slidably connected to a fixed frame 514. The fixed frames 514 are fixedly connected to a limit frame 512. A damper 1 511 is arranged inside the fixed frame 514. The output end of the damper 1 511 is fixedly connected to one side of the slider 510. A fixed block 508 is fixedly connected to one side of the connecting plate 507. The fixed blocks 508 are slidably connected inside the limit frame 512. A damper 2 513 is arranged between the fixed blocks 508. The damper 2 513 is arranged on the top of the bottom fixed block 508. The output end of the damper 2 513 is fixedly connected to the bottom of the top connecting plate 507.
[0038] Specifically, when the component 1 is placed on the operating table 505, force is first applied to the operating table 505 to drive the slide bar 504 to compress the spring 503 under the restriction of the fixed column 502. This operation causes a slight change in the height of the operating table 505, thereby starting the first stage of the shock absorption system. In this process, the connecting plate 507 fixed at the position of the operating table 505 is also driven to transmit force to the fixed block 508, and then transmit the force to the second damper 513. The second damper 513 plays a role at this time to achieve the first shock absorption and reduce the initial impact force generated when the component 1 is placed. At the same time, due to the change in the height of the operating table 505, the position between the two connecting plates 507 also changes accordingly, resulting in a change in the inclination angle of the connecting rod 509. Through this tilting action, the connecting rod 509 The push slider 510 moves under the restriction of the fixed frame 514, and the force is further transmitted to the damper 1 511. The damper 1 511 performs a second shock absorption at this time to further reduce and absorb the remaining impact force, thereby ensuring the stability and integrity of the component 1. This shock absorption process takes effect simultaneously when the flip fixture 6 performs the flipping operation. When the flip fixture 6 performs the clamping and placement operation on the component 1, the two-stage shock absorption function of the shock absorption system works together to effectively prevent the impact force generated during the assembly operation from causing any damage to the component 1. In this way, through the design of the two-stage shock absorption system, the first shock absorption is completed by the damper 2 513, and the second shock absorption is achieved by the damper 1 511. This double shock absorption design fully absorbs and dissipates the impact force generated during the placement and operation process, thereby ensuring the safety and stability of the component 1.
[0039] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An integrated metal sound barrier assembly device, comprising a component assembly (1), It is characterized in that A storage platform (2) is arranged on the top of the component assembly (1), a traveling frame (3) is arranged on the top of the storage platform (2), a lifting fixture (4) is arranged inside the traveling frame (3), an assembly operating table (5) is arranged on one side of the component assembly (1), a turning fixture (6) is fixedly connected to the top of the assembly operating table (5), and a finished product sample (7) is arranged on one side of the assembly operating table (5).
2. An integrated metal sound barrier assembly device according to claim 1, It is characterized in that The traveling frame (3) comprises a plurality of supporting legs (301), each of which is slidably connected to an inner support rod (302), each of which is fixedly connected to a rack (303) inside the supporting legs (301) on one side, each of which is rotatably connected to a rotating column (304) inside the inner support rod (302) on one side, each of which is fixedly connected to a cylindrical gear (306) on the outer wall of the rotating column (304), each of which is meshed with the cylindrical gear (306), and each of which is provided with an electric push rod (318) inside the supporting legs (301) on the other side, and each of which has an output end fixedly connected to the bottom of the inner support rod (302).
3. An integrated metal sound barrier assembly device according to claim 2, It is characterized in that The outer wall of the rotating column 1 (304) is fixedly connected with a driving wheel 1 (305), the inner support rod (302) is rotatably connected with the rotating column 2 (308), the outer wall of the rotating column 2 (308) is fixedly connected with a driven wheel 1 (309), a belt 1 (307) is arranged between the driving wheel 1 (305) and the driven wheel 1 (309), the outer wall of the rotating column 2 (308) is fixedly connected with a bevel gear 1 (310), the inner support rod (302) is rotatably connected with a bevel gear 2 (311), and the bevel gear 1 (310) is meshed with the bevel gear 2 (311).
4. The integrated metal sound barrier assembly device according to claim 3, It is characterized in that One side of the bevel gear 2 (311) is fixedly connected with a driving wheel 2 (312), the inner support rod (302) is rotatably connected with a driven wheel 2 (314), a belt 2 (313) is provided between the driving wheel 2 (312) and the driven wheel 2 (314), the bottom of the driven wheel 2 (314) is fixedly connected with a rotating column 3 (315), the inner support rod (302) is provided with an illuminating lamp (317), the top of the rotating column 3 (315) is provided with a knob (316), and the bottom of the rotating column 3 (315) is fixedly connected to the top of the knob (316).
5. The integrated metal sound barrier assembly device according to claim 1, It is characterized in that The assembly workbench (5) comprises a support column (501), a slide rod (504) is slidably connected inside the support column (501), a fixed column (502) is slidably connected inside the slide rod (504), a spring (503) is sleeved on the outer wall of the fixed column (502), one end of the fixed column (502) is fixedly connected inside the support column (501), and the other end of the fixed column (502) is fixedly connected to the bottom of the slide rod (504).
6. The integrated metal sound barrier assembly device according to claim 5, It is characterized in that A fixing plate (506) is fixedly connected to the outer wall of the support column (501), and an operating table (505) is fixedly connected to the top of the sliding rod (504).
7. The integrated metal sound barrier assembly device according to claim 6, It is characterized in that The sliding rod (504) and one side of the operating table (505) are fixedly connected with a connecting plate (507), and a connecting rod (509) is rotatably connected inside the connecting plate (507). The multiple connecting rods (509) are symmetrically distributed up and down, and one end of the upper connecting rod (509) is rotatably connected to one end of the lower connecting rod (509), and one end of each connecting rod (509) is rotatably connected to a sliding block (510).
8. The integrated metal sound barrier assembly device according to claim 7, It is characterized in that The outer wall of the slider (510) is slidably connected to a fixed frame (514), a limit frame (512) is fixedly connected between the fixed frames (514), a damper 1 (511) is arranged inside the fixed frame (514), and an output end of the damper 1 (511) is fixedly connected to one side of the slider (510).
9. The integrated metal sound barrier assembly device according to claim 7, It is characterized in that One side of the connection plate (507) is fixedly connected to a fixing block (508), and the fixing block (508) is slidably connected inside the limiting frame (512).
10. An integrated metal sound barrier assembly device according to claim 9, It is characterized in that A second damper (513) is arranged between the fixed blocks (508), and the second damper (513) is arranged on the top of the bottom fixed block (508), and the output end of the second damper (513) is fixedly connected to the bottom of the top connecting plate (507).