Steel mesh reinforced steel-plastic composite pipe, assembly production line and assembly method thereof
By setting up a wire mesh skeleton between the stainless steel pipe and the PE pipe and using hydraulic reaming technology, the problem of insufficient anti-corrosion and water transfer effect of steel mesh reinforced steel-plastic composite pipes in the existing technology is solved, and friction during assembly is reduced , improves the edge sealing quality of the pipe.
Patent Information
- Application Number
- CN202411207200.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2044-08-30
AI Technical Summary
The existing wire mesh reinforced steel-plastic composite pipes have shortcomings in corrosion protection and water transfer effects, and the friction between the inner lined stainless steel pipes and the outer PE pipes during the assembly process is too large, which affects the assembly quality.
The steel wire mesh reinforced steel-plastic composite pipe is used to set the wire mesh skeleton between the stainless steel pipe and the PE pipe, and the water pressure reaming technology makes the inner lined stainless steel pipe tightly fit with the PE pipe, reducing friction, and using laser cutting mechanism Trim the ends of the pipe to ensure edge sealing effect.
It improves the anti-corrosion and water transfer effect of the pipe, reduces damage to the human body, reduces friction problems during assembly, and ensures the edge sealing quality of the pipe.
Smart Images

Figure CN118721821B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of steel wire mesh reinforced steel-plastic composite pipes, and more specifically, to steel wire mesh reinforced steel-plastic composite pipes, an assembly production line and an assembly method thereof. Background Art
[0002] Wire mesh reinforced steel-plastic composite pipe is a high-performance composite pipe that combines the corrosion resistance of stainless steel pipe and the high strength of steel wire reinforcement. Wire mesh reinforced steel-plastic composite pipe provides a high-performance, multi-functional pipe solution through its unique structure and material combination, which is suitable for a variety of industrial and civil fields.
[0003] At present, the existing double PE material for pipelines can achieve anti-corrosion effects, but this type of PE pipeline is not convenient for use in drinking water supply, which affects human health, and the water delivery effect is worse than that of stainless steel pipes. Stainless steel pipes have high resistance to external and internal pressures and are less likely to burst, increasing the pressure resistance level. However, the cost of using stainless steel pipes alone is high and cannot be used over long distances and over large areas.
[0004] In addition, the existing assembly device pushes the inner lining stainless steel pipe into the outer PE pipe, causing the two ends of the inner lining stainless steel pipe to leak out, then bends the exposed parts at both ends of the inner lining stainless steel pipe and fits them with the end faces of the outer PE pipe, and then performs subsequent work of welding the fitting parts; due to the processing problems of the pipes, the uniformity of the inner wall of the pipe cannot be guaranteed. In the process of pushing the inner lining stainless steel pipe, it is also difficult to ensure that the inner lining stainless steel pipe and the outer PE pipe always remain in a centered state, so that when the inner lining stainless steel pipe and the outer PE pipe are nested with each other, the local friction between the two is too large, affecting the assembly quality. Summary of the invention
[0005] In view of the deficiencies in the prior art, the object of the present invention is to provide a steel wire mesh reinforced steel-plastic composite pipe, an assembly production line and an assembly method thereof.
[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solution: a wire mesh reinforced steel-plastic composite pipe, including a pipeline assembly, wherein the pipeline assembly includes a first injection molded tube and a second injection molded tube arranged inside the first injection molded tube, the first injection molded tube and the second injection molded tube are injection molded as one piece, a wire mesh skeleton is arranged between the second injection molded tube and the first injection molded tube, and a stainless steel tube is inserted into the interior of the second injection molded tube.
[0007] The outer diameter of the stainless steel tube is the same as the inner diameter of the second injection tube. Both ends of the stainless steel tube are provided with bending parts, and the diameter of the bending parts is the same as the outer diameter of the first injection tube.
[0008] By adopting the above technical scheme, the stainless steel pipe is combined with the PE pipe, and the stainless steel pipe is placed inside the PE pipe. The composite pipe can play an anti-corrosion role when buried underground. The steel wire mesh in the plastic pipe is used to enhance the compressive strength, and the stainless steel pipe in the composite pipe is used for water delivery. On this basis, the water delivery effect is improved and the damage to the human body is reduced.
[0009] The wire mesh reinforced steel-plastic composite pipe assembly production line includes a stainless steel pipe conveying component, a stainless steel pipe welding component installed on the top of the stainless steel pipe conveying component, a PE pipe conveying component arranged on one side of the stainless steel pipe conveying component, and a clamping component arranged between the stainless steel pipe conveying component and the PE pipe conveying component, wherein the top of the clamping component is slidably connected with a cutting component.
[0010] The stainless steel pipe conveying assembly comprises a workbench and a plurality of auxiliary support blocks which are equidistantly installed on the top of the workbench, and the plurality of auxiliary support blocks are arranged in parallel.
[0011] The stainless steel pipe welding assembly includes an articulated seat installed on the top of the workbench and a swing arm hinged to the top of the articulated seat, the middle part of the bottom surface of the swing arm is hinged to the articulated seat, the end of the swing arm away from the auxiliary support block is hinged with a lifting cylinder, the cylinder body of the lifting cylinder is hinged to the workbench, the end of the swing arm away from the lifting cylinder is installed with a first electric slide rail, and the side wall of the first electric slide rail is installed with a welding head.
[0012] The present invention is further configured as follows: the stainless steel pipe conveying assembly also includes a guide rail installed on the top of the workbench, the top of the guide rail is slidably connected to a transfer trolley, the top of the transfer trolley is installed with a drive motor, and the output end of the drive motor is connected to a swing plate.
[0013] The present invention is further configured as follows: a vertical plate is installed on the top of the workbench, and an electric chuck is rotatably connected to the side of the vertical plate close to the workbench, a through hole is opened in the middle of the electric chuck, and a through hole is opened on the side wall of the vertical plate, and the through hole is connected to the through hole inside the electric chuck; a servo motor is installed on the side of the vertical plate away from the workbench, and the output end of the servo motor passes through the vertical plate and a transmission mechanism is connected to the electric chuck.
[0014] By adopting the above technical solution, the transfer trolley drives the driving motor and the swing plate to move synchronously during the movement, and the swing plate is in contact with the tail end of the stainless steel pipe in the conveying direction. When the transfer trolley moves, the swing plate pushes the stainless steel pipe to move and convey, and the driving motor is used to drive the swing plate to move. That is, when the stainless steel pipe is just placed on the top of the auxiliary support block, the swing plate is driven away by the driving motor to avoid interference with the movement of the stainless steel pipe.
[0015] The transmission mechanism is composed of a driving wheel, a transmission belt and a driven wheel. The output end of the servo motor is connected to the driving wheel, and the electric chuck is connected to the driven wheel. When the servo motor drives the driving wheel to transmit, the transmission belt applies transmission force to the driven wheel and the electric chuck, thereby enabling the electric chuck to rotate synchronously. The electric chuck clamps the stainless steel pipe, and the servo motor drives the electric chuck and the stainless steel pipe to rotate through the transmission mechanism, thereby adjusting the axial angle of the stainless steel pipe.
[0016] The present invention is further configured as follows: the clamping assembly comprises a transfer rail arranged between the workbench and the PE pipe conveying assembly, the top of the transfer rail is slidably connected to two switching mechanisms, and the two switching mechanisms are arranged opposite to each other.
[0017] The present invention is further configured as follows: the two groups of switching mechanisms each include a slide seat slidably connected to the top of the transfer rail, a guide hole is provided on the top of the slide seat, and a three-jaw chuck is installed on the opposite side of the two slide seats, a through hole is provided in the middle of the three-jaw chuck, and the through hole of the three-jaw chuck is connected to the guide hole of the slide seat.
[0018] The present invention is further configured as follows: a second electric slide rail is horizontally installed on one side of the top surface of the slide seat, the top of the second electric slide rail is slidably connected to a bearing seat, the top of the bearing seat is installed with a third electric slide rail, the top of the third electric slide rail is installed with an L-shaped plate, the top of the L-shaped plate is installed with a water pump, and the drainage pipe of the water pump passes through the L-shaped plate and is connected to and installed with a rubber head.
[0019] By adopting the above technical solution, the lined stainless steel pipe and the PE pipe are produced separately, and the lined stainless steel pipe is inserted into the PE pipe, and then the lined stainless steel pipe is expanded by water pressure expansion, so that the lined stainless steel pipe and the PE pipe are squeezed and fitted with each other. This method reduces the problem of excessive friction between the two and affecting the assembly quality.
[0020] The present invention is further configured as follows: the cutting assembly includes a cutting base slidably connected to the top of the transfer rail and a base installed on the top of the cutting base, the top of the base is slidably connected to a base, the top of the base is vertically installed with a fourth electric slide rail, the side wall of the fourth electric slide rail is slidably connected to an L-shaped frame, two laser cutting mechanisms are horizontally installed on the top of the L-shaped frame, and the two laser cutting mechanisms are arranged opposite to each other, a connecting plate is installed on the side wall of the base, a displacement cylinder is horizontally installed on the side of the connecting plate away from the base, the piston rod of the displacement cylinder passes through the connecting plate and is connected to the base, two edge banding motors are staggeredly installed inside the L-shaped frame, the two edge banding motors are arranged opposite to each other, and the output end of each edge banding motor extends to the outside of the L-shaped frame and is connected to an edge banding head.
[0021] By adopting the above technical solution, after the edge sealing of the stainless steel tube is completed, the cutting base is moved to the tail of the stainless steel tube, and then the base is pushed to move on the top of the base by the displacement cylinder, so that the laser cutting mechanism is directed toward the stainless steel tube and the tail of the stainless steel tube. After that, the laser cutting mechanism moves around the outer wall size of the first injection molded tube, so that the tail of the stainless steel tube is cut and trimmed, and the head of the stainless steel tube is cut in the same way. This setting causes the excess corners produced by the edge sealing of the stainless steel tube to be cut, thereby ensuring the edge sealing effect of the stainless steel tube.
[0022] The present invention is further configured as follows: the PE pipe conveying assembly includes a conveyor belt mechanism arranged on the side of the transfer rail away from the workbench and an electric roller transmission-connected to one end of the top of the conveyor belt mechanism, the outer side wall of the electric roller is symmetrically sleeved and connected to two turntables, and the side wall of each turntable is equidistantly provided with four grooves, and the end of the conveyor belt mechanism close to the turntable is equidistantly rotatably connected to multiple conveyor rollers, the angles of the conveyor rollers are staggered with the conveying direction of the conveyor belt mechanism, and the staggered angle is 90 degrees, a fixed plate is installed on the side of the conveyor belt mechanism away from the transfer rail, and a push cylinder is horizontally installed on the side of the fixed plate away from the conveyor belt mechanism, the piston rod of the push cylinder passes through the fixed plate and is connected to a push block, and the push block extends to the top of the conveyor roller.
[0023] By adopting the above technical solution, the injection-molded PE pipe is placed on the top of the conveyor belt mechanism, and the conveyor belt mechanism is transported by a chain, so the conveyor belt mechanism will not slip. When the conveyor belt mechanism transports the PE pipe to the position of the turntable, one of the grooves on the turntable is set toward the PE pipe, and the conveying roller rolls to the inside of the corresponding groove, and then the turntable is driven by the electric roller to rotate and transport. The turntable is driven by the electric roller to rotate, causing the PE pipe to be moved to the top of the conveying roller, and the piston rod of the push cylinder extends and pushes the push block to move. The push block pushes the PE pipe on the top of the conveying roller to be transported in the direction of the stainless steel pipe conveying assembly. The conveying directions of the PE pipe and the stainless steel pipe are opposite, and they are relatively close during transportation to facilitate subsequent docking operations.
[0024] The assembly method of the steel mesh reinforced steel-plastic composite pipe, according to the steel mesh reinforced steel-plastic composite pipe and the steel mesh reinforced steel-plastic composite pipe assembly production line described above, comprises the following steps:
[0025] S1. The staff will weave the wire mesh skeleton on the outer side wall of the second injection molded tube through an external weaving device, and then injection mold the first injection molded tube on the outside of the wire mesh skeleton and the second injection molded tube to finally form a PE tube. Subsequently, the PE tube conveying assembly continuously conveys the PE tube toward the clamping assembly.
[0026] S2. The stainless steel pipe is rolled into a cylinder by an external rolling device and transferred to the top of multiple auxiliary support blocks, and is transported in the direction of the transfer rail through the stainless steel pipe conveying assembly. During this process, the piston rod of the jacking cylinder extends and pushes one end of the swing arm to move upward, and the other end of the swing arm moves downward synchronously and drives the first electric slide rail and the welding head to move downward. The bottom end of the welding head fits into the weld position of the stainless steel pipe, and the stainless steel pipe is gradually welded into shape by the welding head during the conveying process. The conveying directions of the PE pipe and the stainless steel pipe are opposite, and they are relatively close during conveying to facilitate subsequent docking operations.
[0027] S3. The heads of the PE pipe and the stainless steel pipe are respectively passed through the positions of the clamping components and docked, and the length of the PE pipe is shorter than that of the stainless steel pipe, so both ends of the stainless steel pipe are exposed outside the PE pipe.
[0028] After S4, the PE pipe and the stainless steel pipe are connected, two sets of clamping components are used to perform hydraulic hole expansion operations, and then the cutting component is moved to the tail of the stainless steel pipe, and then the tail of the stainless steel pipe is sealed. Then the cutting component is moved to the head of the stainless steel pipe, and then the head of the stainless steel pipe is sealed.
[0029] S5. After the edge sealing is completed, the bending part of the edge sealing position of the stainless steel pipe is laser cut and trimmed by the cutting component.
[0030] In summary, the present application includes at least one of the following beneficial technical effects:
[0031] (1) The stainless steel pipe is combined with the PE pipe. The stainless steel pipe is placed inside the PE pipe. The composite pipe can play an anti-corrosion role when buried underground. The steel wire mesh in the plastic pipe is used to enhance the compressive strength. The stainless steel pipe in the composite pipe is used for water delivery. On this basis, the water delivery effect is improved and the damage to the human body is reduced.
[0032] (2) The lined stainless steel pipe and PE pipe are produced separately, and the lined stainless steel pipe is inserted into the PE pipe. Then the lined stainless steel pipe is expanded by water pressure, so that the lined stainless steel pipe and the PE pipe are squeezed and fitted against each other. This method reduces the problem of excessive friction between the two and affects the assembly quality.
[0033] (3) By setting a rubber head, the water pump absorbs the water and discharges it into the stainless steel pipe through the drain port and the rubber head. The stainless steel pipe is expanded by water pressure, so that the inner wall of the stainless steel pipe fits tightly with the inner wall of the second injection molded pipe. Then the water inside the stainless steel pipe is discharged, and the stainless steel pipe is expanded by water pressure, so that the stainless steel pipe and the PE pipe are squeezed and fitted with each other. This method reduces the problem of excessive friction between the two and affects the assembly quality.
[0034] (4) By setting up a laser cutting mechanism, after the edge sealing of the stainless steel tube is completed, the cutting base is moved to the tail of the stainless steel tube, and then the base is pushed to move on the top of the base by the displacement cylinder, so that the laser cutting mechanism and the tail of the stainless steel tube are directed toward the stainless steel tube. After that, this laser cutting mechanism moves around the outer wall size of the first injection molded tube, so that the tail of the stainless steel tube is cut and trimmed, and the head of the stainless steel tube is cut in the same way. This setting causes the excess corners generated by the edge sealing of the stainless steel tube to be cut, thereby ensuring the edge sealing effect of the stainless steel tube. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] Figure 1 It is a schematic diagram of the overall structure of the wire mesh reinforced steel-plastic composite pipe assembly production line of the present invention.
[0036] Figure 2 It is a schematic diagram of the structure of the PE pipe conveying assembly in the present invention.
[0037] Figure 3 It is a schematic diagram of the connection structure of the stainless steel pipe conveying assembly and the stainless steel pipe welding assembly in the present invention.
[0038] Figure 4 for Figure 3 Schematic diagram of the side structure.
[0039] Figure 5 It is a schematic diagram of the switching mechanism structure in the present invention.
[0040] Figure 6 for Figure 5 Schematic diagram of the side structure.
[0041] Figure 7 It is a schematic diagram of the cutting component structure in the present invention.
[0042] Figure 8 It is a schematic diagram of the structure of the pipeline assembly in the present invention.
[0043] Fig. 9 It is a schematic diagram of the stainless steel pipe and edge sealing connection structure in the present invention.
[0044] Description of reference numerals: 1. Stainless steel pipe conveying assembly; 11. Workbench; 12. Guide rail; 13. Transfer trolley; 14. Driving motor; 15. Swing plate; 16. Vertical plate; 17. Servo motor; 18. Transmission mechanism; 19. Electric chuck; 101. Auxiliary support block;
[0045] 2. Stainless steel pipe welding assembly; 21. Lifting cylinder; 22. Swing arm; 23. Articulated seat; 24. First electric slide rail; 25. Welding head;
[0046] 3. Clamping assembly; 31. Transfer rail; 32. Switching mechanism; 321. Slide seat; 322. Second electric slide rail; 323. Bearing seat; 324. Third electric slide rail; 325. L-shaped plate; 326. Water pump; 327. Rubber seal head; 328. Three-jaw chuck;
[0047] 4. Cutting assembly; 41. Cutting base; 42. Base; 43. Connecting plate; 44. Displacement cylinder; 45. Fourth electric slide rail; 46. L-shaped frame; 47. Laser cutting mechanism; 48. Edge banding motor; 49. Edge banding head;
[0048] 5. PE pipe conveying assembly; 51. Conveyor belt mechanism; 52. Electric roller; 53. Turntable; 54. Groove; 55. Conveyor roller; 56. Fixed plate; 57. Pushing cylinder; 58. Pushing block;
[0049] 6. Pipeline assembly; 61. First injection-molded tube; 62. Wire mesh skeleton; 63. Second injection-molded tube; 64. Stainless steel tube; 65. Bending portion. DETAILED DESCRIPTION
[0050] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application may be combined with each other. The present invention will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0051] It should be noted that, unless otherwise specified, all technical and scientific terms used in this application have the same meanings as commonly understood by ordinary technicians in the technical field to which this application belongs.
[0052] See also Figure 1-9 , the present invention provides the following technical solutions:
[0053] Example 1, see Figure 8 and Fig. 9 , the steel wire mesh reinforced steel-plastic composite pipe includes a pipe assembly 6, the pipe assembly 6 is a finished pipe after the pipe is composited, and the specific structure of the pipe assembly 6 is as follows:
[0054] The pipeline component 6 includes a first injection molded tube 61 and a second injection molded tube 63 arranged inside the first injection molded tube 61. The first injection molded tube 61 and the second injection molded tube 63 are injection molded as one piece. A wire mesh skeleton 62 is arranged between the second injection molded tube 63 and the first injection molded tube 61. The second injection molded tube 63 is injection molded first, and then the wire mesh skeleton 62 is woven on the outer wall of the second injection molded tube 63. Then, the first injection molded tube 61 is injection molded outside the wire mesh skeleton 62 and the second injection molded tube 63. The first injection molded tube 61, the second injection molded tube 63 and the wire mesh skeleton 62 cooperate to form a PE pipe.
[0055] A stainless steel tube 64 is inserted into the interior of the second injection tube 63. The outer diameter of the stainless steel tube 64 is the same as the inner diameter of the second injection tube 63. Bending portions 65 are provided at both ends of the stainless steel tube 64. The diameter of the bending portion 65 is the same as the outer diameter of the first injection tube 61. The stainless steel tube 64 is inserted into the interior of the second injection tube 63. The first injection tube 61, the second injection tube 63, the wire mesh skeleton 62 and the stainless steel tube 64 form a composite tube. The bending portion 65 is used to seal the composite end.
[0056] The composite pipe can play an anti-corrosion role when buried underground. The steel wire mesh skeleton 62 in the PE pipe is used to enhance the compressive strength. The stainless steel pipe 64 in the composite pipe is used for water delivery. On this basis, the water delivery effect is improved and the damage to the human body is reduced.
[0057] Example 2, see Figure 1 and Figure 3 The wire mesh reinforced steel-plastic composite pipe assembly production line includes a stainless steel pipe conveying assembly 1, which is used to convey the stainless steel pipe 64. The specific structure of the stainless steel pipe conveying assembly 1 is as follows:
[0058] See also Figure 3 and Figure 4 The stainless steel pipe conveying assembly 1 includes a workbench 11 and a plurality of auxiliary support blocks 101 equidistantly installed on the top of the workbench 11 . The plurality of auxiliary support blocks 101 are arranged in parallel. The auxiliary support blocks 101 are used to provide auxiliary support to the stainless steel pipe 64 , thereby limiting the conveying angle of the stainless steel pipe 64 .
[0059] See also Figure 3 and Figure 4 In this embodiment, the stainless steel pipe conveying assembly 1 also includes a guide rail 12 installed on the top of the workbench 11, and a transfer trolley 13 is slidably connected to the top of the guide rail 12. An electric wheel is installed inside the transfer trolley 13. The transfer trolley 13 is driven by the electric wheel to move on the top of the guide rail 12. A driving motor 14 is installed on the top of the transfer trolley 13. The output end of the driving motor 14 is connected to a swing plate 15. The transfer trolley 13 drives the driving motor 14 and the swing plate 15 to move synchronously during the movement. The swing plate 15 is in contact with the tail end of the conveying direction of the stainless steel pipe 64. When the transfer trolley 13 moves, the swing plate 15 pushes the stainless steel pipe 64 to move and convey. The driving motor 14 is used to drive the swing plate 15 to move, that is, when the stainless steel pipe 64 is just placed on the top of the auxiliary support block 101, the swing plate 15 is driven away by the driving motor 14 to avoid interference of the swing plate 15 with the movement of the stainless steel pipe 64.
[0060] See also Figure 3 and Figure 4In this embodiment, a vertical plate 16 is installed on the top of the workbench 11, and an electric chuck 19 is rotatably connected to the side of the vertical plate 16 close to the workbench 11. A through hole is opened in the middle of the electric chuck 19, and a through hole is opened on the side wall of the vertical plate 16, which is connected to the through hole inside the electric chuck 19. A servo motor 17 is installed on the side of the vertical plate 16 away from the workbench 11. The output end of the servo motor 17 passes through the vertical plate 16 and a transmission mechanism 18 is connected between the servo motor 17 and the electric chuck 19. The transmission mechanism 18 is composed of a driving wheel, a transmission belt and a driven wheel. The output end of the servo motor 17 is connected to the driving wheel, and the electric chuck 19 is connected to the driven wheel. When the servo motor 17 drives the driving wheel to transmit, the transmission belt applies the transmission force to the driven wheel and the electric chuck 19, so that the electric chuck 19 can rotate synchronously. The electric chuck 19 clamps the stainless steel pipe 64, and the servo motor 17 drives the electric chuck 19 and the stainless steel pipe 64 to rotate through the transmission mechanism 18, thereby adjusting the axial angle of the stainless steel pipe 64.
[0061] See also Figure 3 and Figure 4 A stainless steel pipe welding assembly 2 is installed on the top of the stainless steel pipe conveying assembly 1. The stainless steel pipe welding assembly 2 is used to continuously weld the conveyed stainless steel pipe 64. The specific structure of the stainless steel pipe welding assembly 2 is as follows:
[0062] See also Figure 3 and Figure 4 The stainless steel pipe welding assembly 2 includes an articulated seat 23 installed on the top of the workbench 11 and a swing arm 22 hinged to the top of the articulated seat 23. The middle part of the bottom surface of the swing arm 22 is hinged to the articulated seat 23. The end of the swing arm 22 away from the auxiliary support block 101 is hinged with a lifting cylinder 21. The cylinder body of the lifting cylinder 21 is hinged to the workbench 11. The end of the swing arm 22 away from the lifting cylinder 21 is installed with a first electric slide rail 24. The side wall of the first electric slide rail 24 is installed with a welding head 25. The first electric slide rail 24 can be a stepper motor linear slide rail slide module, that is, a stepper motor is used to drive the screw in the linear guide rail to rotate, and the slide is threadedly connected to the screw. When the screw rotates, the slide moves along the extension direction of the screw. The welding head 25 is installed on the slide. When the slide moves, the welding head 25 follows the displacement of the slide to adjust the position.
[0063] Specifically, the stainless steel pipe 64 is rolled into a cylinder by an external rolling device and transferred to the top of multiple auxiliary support blocks 101, and is transported in the direction of the transfer rail 31 through the stainless steel pipe conveying assembly 1. During this process, the piston rod of the lifting cylinder 21 extends and pushes one end of the swing arm 22 to move upward, and the other end of the swing arm 22 moves downward synchronously and drives the first electric slide rail 24 and the welding head 25 to move downward. The bottom end of the welding head 25 is attached to the weld position of the stainless steel pipe 64, and the stainless steel pipe 64 is gradually welded into shape by the welding head 25 during the conveying process. After that, the welded stainless steel pipe 64 is conveyed through the electric chuck 19.
[0064] See also Figure 1 and Figure 2 A PE pipe conveying assembly 5 is installed on one side of the stainless steel pipe conveying assembly 1. The PE pipe conveying assembly 5 is used to convey the PE pipe composed of the first injection molding pipe 61, the second injection molding pipe 63 and the wire mesh skeleton 62. The specific structure of the PE pipe conveying assembly 5 is as follows:
[0065] See also Figure 1 and Figure 2 The PE pipe conveying assembly 5 includes a conveyor belt mechanism 51 arranged on the side of the transfer rail 31 away from the workbench 11 and a motorized roller 52 drivingly connected to one end of the top of the conveyor belt mechanism 51. The outer wall of the motorized roller 52 is symmetrically sleeved and connected to two turntables 53. The side wall of each turntable 53 is equidistantly provided with four grooves 54. The injection-molded PE pipe is placed on the top of the conveyor belt mechanism 51, and the conveyor belt mechanism 51 is conveyed by a chain, so the conveyor belt mechanism 51 will not slip. When the conveyor belt mechanism 51 conveys the PE pipe to the position of the turntable 53, one of the grooves 54 on the turntable 53 is set toward the PE pipe, and the conveyor roller 55 rolls into the corresponding groove 54, and then the turntable 53 is driven by the motorized roller 52 to rotate and transport.
[0066] See also Figure 1 and Figure 2 The conveyor belt mechanism 51 has a plurality of conveyor rollers 55 equidistantly connected to one end of the conveyor belt mechanism 51 close to the turntable 53. The angle of the conveyor rollers 55 is staggered with the conveying direction of the conveyor belt mechanism 51, and the staggered angle is 90 degrees. A fixed plate 56 is installed on the side of the conveyor belt mechanism 51 away from the transfer rail 31. A push cylinder 57 is horizontally installed on the side of the fixed plate 56 away from the conveyor belt mechanism 51. The piston rod of the push cylinder 57 penetrates the fixed plate 56 and is connected to a push block 58. The push block 58 extends to the top of the conveyor roller 55, and the turntable 53 is driven to rotate by the electric roller 52, so that the PE pipe is transferred to the top of the conveyor roller 55. The piston rod of the push cylinder 57 is extended and pushes the push block 58 to move. The push block 58 pushes the PE pipe on the top of the conveyor roller 55 to be transported in the direction of the stainless steel pipe conveying assembly 1. The conveying directions of the PE pipe and the stainless steel pipe 64 are opposite, and they are relatively close to each other during transportation to facilitate subsequent docking operations.
[0067] See also Figure 1 A clamping assembly 3 is provided between the workbench 11 and the conveyor belt mechanism 51. The clamping assembly 3 is used to coaxially clamp the PE pipe and the stainless steel pipe 64 being transported, and the PE pipe and the stainless steel pipe 64 are spliced and composited by the clamping assembly 3. The specific structure of the clamping assembly 3 is as follows:
[0068] See also Figure 1 , Figure 5 and Figure 6The clamping assembly 3 includes a transfer rail 31 disposed between the workbench 11 and the conveyor belt mechanism 51. The top of the transfer rail 31 is slidably connected to two switching mechanisms 32. The two switching mechanisms 32 are arranged opposite to each other. The transfer rail 31 is used to drive the two switching mechanisms 32 to move, and the two switching mechanisms 32 correspond to the PE pipe and the stainless steel pipe 64 respectively. The switching mechanism 32 coaxially clamps and positions the corresponding PE pipe and stainless steel pipe 64, and drives the PE pipe and the stainless steel pipe 64 to approach each other for docking. The specific structure of the switching mechanism 32 is as follows:
[0069] See also Figure 5 and Figure 6 The two sets of switching mechanisms 32 both include a slide seat 321 slidably connected to the top of the transfer rail 31. A guide hole is provided on the top of the slide seat 321. Three-jaw chucks 328 are installed on the opposite sides of the two slide seats 321. A through hole is provided in the middle of the three-jaw chuck 328. The through hole of the three-jaw chuck 328 is connected to the guide hole of the slide seat 321. During the transportation process, the PE pipe and the stainless steel pipe 64 pass through the corresponding slide seat 321 and the three-jaw chuck 328 respectively. The three-jaw chuck 328 is used to clamp the corresponding PE pipe or stainless steel pipe 64. Then, the two slide seats 321 move closer to each other on the transfer rail 31, so that the PE pipe and the stainless steel pipe 64 are close to each other for insertion.
[0070] In the initial state, the diameter of the stainless steel tube 64 is smaller than the inner diameter of the second injection molding tube 63, so the two are directly plugged in, and then the PE tube remains stationary, the three-jaw chuck 328 corresponding to the stainless steel tube 64 cancels the clamping, the slide 321 corresponding to the stainless steel tube 64 retreats and the corresponding three-jaw chuck 328 moves along the outer wall of the stainless steel tube 64, and when the three-jaw chuck 328 corresponding to the stainless steel tube 64 retreats to the extreme position, the stainless steel tube 64 is clamped again, and then the slide 321 corresponding to the stainless steel tube 64 moves again in the direction of the other slide 321, causing the stainless steel tube 64 to continue to be plugged into the inside of the PE tube, and this reciprocating process is repeated until most of the stainless steel tube 64 is inserted into the PE tube.
[0071] Afterwards, the PE tube continues to remain stationary, the slide 321 corresponding to the stainless steel tube 64 retreats and the corresponding three-jaw chuck 328 retreats to the tail of the stainless steel tube 64, and the three-jaw chuck 328 corresponding to the stainless steel tube 64 is completely retracted and through the displacement of the corresponding slide 321, the three-jaw chuck 328 corresponding to the stainless steel tube 64 is inserted into the interior of the stainless steel tube 64 and stretched on the inner wall of the tail of the stainless steel tube 64, and then the slide 321 corresponding to the stainless steel tube 64 moves again in the direction of the other slide 321, causing the stainless steel tube 64 to continue to be plugged into the interior of the PE tube until the stainless steel tube 64 is inserted into the PE tube, and the length of the PE tube is less than the length of the stainless steel tube 64, so the two ends of the stainless steel tube 64 are exposed to the outside of the PE tube.
[0072] Embodiment three, the existing assembly device pushes the lined stainless steel pipe into the outer PE pipe, so that the two ends of the lined stainless steel pipe leak out, and then bends the exposed parts at both ends of the lined stainless steel pipe and fits them with the end faces of the outer PE pipe, and then performs the subsequent work of welding at the fitting parts; due to the processing problems of the pipe, the uniformity of the inner wall of the pipe cannot be guaranteed. In the process of pushing the lined stainless steel pipe, it is also difficult to ensure that the lined stainless steel pipe and the outer PE pipe always remain in a centered state, so that the local friction between the lined stainless steel pipe and the outer PE pipe is too large when they are nested with each other, affecting the assembly quality.
[0073] For this purpose, see Figure 5 and Figure 6 A second electric slide rail 322 is horizontally installed on one side of the top surface of the slide seat 321, and a bearing seat 323 is slidably connected to the top of the second electric slide rail 322, and a third electric slide rail 324 is installed on the top of the bearing seat 323. An L-shaped plate 325 is installed on the top of the third electric slide rail 324, and a water pump 326 is installed on the top of the L-shaped plate 325. The drainage pipe of the water pump 326 passes through the L-shaped plate 325 and is connected to a rubber head 327. The second electric slide rail 322 and the third electric slide rail 324 can both be stepper motor linear slide rail slide table modules, that is, a stepper motor is used to drive the screw in the linear guide rail to rotate, and the slide table is threadedly connected to the screw rod. When the screw rod rotates, the slide table moves along the extension direction of the screw rod. The third electric slide rail 324 is installed on the slide table of the second electric slide rail 322, and the L-shaped plate 325 is installed on the slide seat of the third electric slide rail 324.
[0074] Specifically, after the PE tube and the stainless steel tube 64 are connected, the second electric slide rail 322 drives the bearing seat 323 to slide horizontally, so that the third electric slide rail 324, the L-shaped plate 325 and the water pump 326 move to the position of the through hole of the slide seat 321, and the third electric slide rail 324 drives the L-shaped plate 325, the water pump 326 and the rubber seal 327 to approach the through hole of the slide seat 321, and the rubber seal 327 seals the through hole on the slide seat 321, and the end of the stainless steel tube 64 is inserted into the through hole of the slide seat 321 and is connected to the rubber seal 327 fits together, and the water pump 326 is connected to the external water supply equipment. The water pump 326 absorbs the water and discharges it to the inside of the stainless steel pipe 64 through the drain port and the rubber cap 327. The stainless steel pipe 64 is expanded by water pressure, so that the inner wall of the stainless steel pipe 64 fits closely with the inner wall of the second injection molding pipe 63, and then the water inside the stainless steel pipe 64 is discharged. The stainless steel pipe 64 is expanded by water pressure, so that the stainless steel pipe 64 and the PE pipe are squeezed and fitted with each other. This method reduces the problem of excessive friction between the two and affecting the assembly quality.
[0075] In addition, during the process of compounding the stainless steel pipe 64 with the PE pipe, glue may be applied to the outer wall of the stainless steel pipe 64 and then the two are compounded to increase the composite strength.
[0076] In the fourth embodiment, after the pipe is composited, the pipe end is generally sealed by an edge sealing mechanism. The edge sealing process can protect the pipe end from environmental factors (such as corrosion and wear), thereby extending the service life of the pipe. However, during the edge sealing process, the compression and extension of the edge sealing material in the axial range are different, so part of the edge sealing material will exceed the original pipe diameter, resulting in uneven edge sealing at the pipe end.
[0077] For this purpose, see Figure 1 and Figure 7 A cutting assembly 4 is slidably connected to the top of the clamping assembly 3. The cutting assembly 4 is used to bend the stainless steel tube 64 exposed at both ends of the PE tube, so that the ends of the stainless steel tube 64 seal the two ends of the PE tube. Then, the cutting assembly 4 cuts the excess part during the bending. The specific structure of the cutting assembly 4 is as follows;
[0078] See also Figure 7 In this embodiment, the cutting assembly 4 includes a cutting base 41 slidably connected to the top of the transfer rail 31 and a base 42 installed on the top of the cutting base 41. The top of the base 42 is slidably connected to a base, and a fourth electric slide rail 45 is vertically installed on the top of the base. The side wall of the fourth electric slide rail 45 is slidably connected to an L-shaped frame 46. The fourth electric slide rail 45 can be a stepper motor linear slide rail slide table module, that is, a stepper motor is used to drive the screw in the linear guide rail to rotate, and the slide table is threadedly connected to the screw rod. When the screw rod rotates, the slide table moves along the extension direction of the screw rod, and the L-shaped frame 46 is connected to the slide table of the fourth electric slide rail 45, that is, the L-shaped frame 46 can adjust the height through the fourth electric slide rail 45.
[0079] See also Figure 7A connecting plate 43 is installed on the side wall of the base 42, and a displacement cylinder 44 is installed horizontally on the side of the connecting plate 43 away from the base 42. The piston rod of the displacement cylinder 44 penetrates the connecting plate 43 and is connected to the base. Two edge banding motors 48 are installed in an offset manner inside the L-shaped frame 46. The two edge banding motors 48 are set away from each other. The output end of each edge banding motor 48 extends to the outside of the L-shaped frame 46 and is connected to an edge banding head 49. The cutting base 41 moves to the tail of the stainless steel pipe 64 in the feeding direction, and then the base is pushed to move on the top of the base 42 by the displacement cylinder 44, so that the edge banding head 49 facing the stainless steel pipe 64 is docked with the tail of the stainless steel pipe 64. Afterwards, the corresponding edge sealing head 49 is driven to rotate by the corresponding edge sealing motor 48, and the cutting base 41 moves toward the tail of the stainless steel tube 64, so that the position of the stainless steel tube 64 is edge sealed, and the slide seat 321 corresponding to the tail of the stainless steel tube 64 moves, so that the three-jaw chuck 328 corresponding to the tail of the stainless steel tube 64 clamps the stainless steel tube 64, and the three-jaw chuck 328 corresponding to the head of the stainless steel tube 64 cancels the clamping and moves away from the stainless steel tube 64, and then the cutting base 41 moves to the head of the stainless steel tube 64, and the head of the stainless steel tube 64 is edge sealed by another edge sealing head 49 corresponding to the head of the stainless steel tube 64 and the edge sealing motor 48.
[0080] See also Figure 7 Two laser cutting mechanisms 47 are horizontally installed at the top of the L-shaped frame 46, and the two laser cutting mechanisms 47 are set in opposite directions. After the edge sealing is completed, the cutting base 41 moves to the tail of the stainless steel tube 64, and then the base is pushed to move on the top of the base 42 by the displacement cylinder 44, so that the laser cutting mechanism 47 facing the stainless steel tube 64 and the tail of the stainless steel tube 64, and then this laser cutting mechanism 47 uses the fourth electric slide rail 45 and the displacement cylinder 44 to provide driving force for the L-shaped frame 46, so that the laser cutting mechanism 47 can move around the outer wall size of the first injection tube 61, so that the tail of the stainless steel tube 64 is cut and trimmed.
[0081] See also Figure 7 , then the slide 321 corresponding to the tail of the stainless steel tube 64 moves, causing the three-jaw chuck 328 corresponding to the tail of the stainless steel tube 64 to clamp the stainless steel tube 64, while the three-jaw chuck 328 corresponding to the head of the stainless steel tube 64 cancels the clamping and moves away from the stainless steel tube 64, and then the cutting base 41 moves to the head of the stainless steel tube 64, and the head of the stainless steel tube 64 is trimmed by another laser cutting mechanism 47 corresponding to the head of the stainless steel tube 64. Through the trimming, the redundant corners generated by the edge sealing of the stainless steel tube 64 are cut off, thereby ensuring the edge sealing effect of the stainless steel tube 64.
[0082] Embodiment 5, a method for assembling a steel mesh reinforced steel-plastic composite pipe, according to the above-mentioned steel mesh reinforced steel-plastic composite pipe and steel mesh reinforced steel-plastic composite pipe assembly production line, comprises the following steps:
[0083] S1. The staff will weave the wire mesh skeleton 62 on the outer wall of the second injection molding tube 63 through an external weaving device, and then injection mold the first injection molding tube 61 on the outside of the wire mesh skeleton 62 and the second injection molding tube 63 to finally form a PE tube. Subsequently, the PE tube conveying assembly 5 continuously conveys the PE tube to the direction of the clamping assembly 3.
[0084] More specific steps are:
[0085] S11. The injection-molded PE tube is placed on the top of the conveyor belt mechanism 51, and the conveyor belt mechanism 51 is transported by a chain, so the conveyor belt mechanism 51 will not slip. When the conveyor belt mechanism 51 transports the PE tube to the position of the turntable 53, one of the grooves 54 on the turntable 53 is set toward the PE tube, and the PE tube rolls into the inside of the corresponding groove 54, and then the turntable 53 is driven to rotate by the electric roller 52, so that the PE tube is moved to the top of the conveying roller 55.
[0086] S12, then the piston rod of the pushing cylinder 57 extends and pushes the pushing block 58 to move, and the pushing block 58 pushes the PE pipe on the top of the conveying roller 55 to be conveyed in the direction of the transfer rail 31.
[0087] S2, the stainless steel pipe 64 is rolled into a cylinder by an external rolling device and transferred to the top of multiple auxiliary support blocks 101, and is transported in the direction of the transfer rail 31 through the stainless steel pipe conveying assembly 1. During this process, the piston rod of the jacking cylinder 21 extends and pushes one end of the swing arm 22 to move upward, and the other end of the swing arm 22 moves downward synchronously and drives the first electric slide rail 24 and the welding head 25 to move downward. The bottom end of the welding head 25 fits into the weld position of the stainless steel pipe 64, and the stainless steel pipe 64 is gradually welded into shape by the welding head 25 during the conveying process. The conveying directions of the PE pipe and the stainless steel pipe 64 are opposite, and they are relatively close during conveying to facilitate subsequent docking operations.
[0088] More specific steps are:
[0089] S21, the stainless steel tube 64 is rolled into a cylinder by an external rolling device and transferred to the top of multiple auxiliary support blocks 101, and one end of the swing plate 15 is in contact with the end of the stainless steel tube 64 away from the electric chuck 19, and then the transfer trolley 13 drives the drive motor 14 and the swing plate 15 to move, causing the stainless steel tube 64 to be transported in the direction of the electric chuck 19.
[0090] S22. During this process, the piston rod of the lifting cylinder 21 extends and pushes one end of the swing arm 22 upward, and the other end of the swing arm 22 moves downward synchronously and drives the first electric slide rail 24 and the welding head 25 to move downward. The bottom end of the welding head 25 fits the weld position of the stainless steel pipe 64, and the stainless steel pipe 64 is gradually welded into shape by the welding head 25 during the transportation process. After the welding of the stainless steel pipe 64 is completed, the welding head 25 is reset, and then the electric chuck 19 continues to push the stainless steel pipe 64 to move, causing the tail of the stainless steel pipe 64 to reach the position of the electric chuck 19. The electric chuck 19 clamps the stainless steel pipe 64, and the servo motor 17 drives the electric chuck 19 and the stainless steel pipe 64 to rotate through the transmission mechanism 18, thereby adjusting the axial angle of the stainless steel pipe 64. The conveying directions of the PE pipe and the stainless steel pipe 64 are opposite, and they are relatively close during transportation to facilitate subsequent docking operations.
[0091] S3, the head of the PE pipe and the head of the stainless steel pipe 64 are respectively inserted into the position of the clamping assembly 3 and docked, and the length of the PE pipe is smaller than the length of the stainless steel pipe 64, so the two ends of the stainless steel pipe 64 are exposed outside the PE pipe.
[0092] More specific steps are:
[0093] S31, the head of the PE pipe and the head of the stainless steel pipe 64 pass through the corresponding rubber head 327 and the three-jaw chuck 328 respectively. The three-jaw chuck 328 clamps the corresponding stainless steel pipe 64 and PE pipe, and both are kept in a horizontal state. Then the two slides 321 move close to each other on the transfer rail 31, causing the PE pipe and the stainless steel pipe 64 to be close to each other for insertion.
[0094] S32. In the initial state, the diameter of the stainless steel tube 64 is smaller than the inner diameter of the second injection molding tube 63, so the two are directly plugged in, and then the PE tube remains stationary, the three-jaw chuck 328 corresponding to the stainless steel tube 64 cancels the clamping, the slide 321 corresponding to the stainless steel tube 64 retreats and the corresponding three-jaw chuck 328 moves along the outer wall of the stainless steel tube 64, and when the three-jaw chuck 328 corresponding to the stainless steel tube 64 retreats to the extreme position, the stainless steel tube 64 is clamped again, and then the slide 321 corresponding to the stainless steel tube 64 moves again in the direction of the other slide 321, causing the stainless steel tube 64 to continue to be plugged into the inside of the PE tube, and this reciprocating process is repeated until most of the stainless steel tube 64 is inserted into the PE tube.
[0095] S33, then the PE tube continues to remain stationary, the slide 321 corresponding to the stainless steel tube 64 retreats and the corresponding three-jaw chuck 328 retreats to the tail of the stainless steel tube 64, the three-jaw chuck 328 corresponding to the stainless steel tube 64 is completely retracted and through the displacement of the corresponding slide 321, the three-jaw chuck 328 corresponding to the stainless steel tube 64 is inserted into the interior of the stainless steel tube 64 and stretched on the inner wall of the tail of the stainless steel tube 64, and then the slide 321 corresponding to the stainless steel tube 64 moves again in the direction of the other slide 321, causing the stainless steel tube 64 to continue to be plugged into the interior of the PE tube until the stainless steel tube 64 is inserted into the PE tube, and the length of the PE tube is less than the length of the stainless steel tube 64, so the two ends of the stainless steel tube 64 are exposed to the outside of the PE tube.
[0096] After S4, the PE pipe and the stainless steel pipe 64 are connected, two sets of clamping components 3 are used to perform hydraulic hole expansion operations, and then the cutting component 4 is moved to the tail of the stainless steel pipe 64, and then the tail of the stainless steel pipe 64 is sealed. Then the cutting component 4 is moved to the head of the stainless steel pipe 64, and then the head of the stainless steel pipe 64 is sealed.
[0097] More specific steps are:
[0098] After S41, the PE pipe and the stainless steel pipe 64 are connected, the second electric slide rail 322 drives the bearing seat 323 to slide horizontally, causing the third electric slide rail 324, the L-shaped plate 325 and the water pump 326 to move to the position of the through hole of the slide seat 321, and the third electric slide rail 324 drives the L-shaped plate 325, the water pump 326 and the rubber head 327 to approach the through hole of the slide seat 321, and the rubber head 327 blocks the through hole on the slide seat 321, and the end of the stainless steel pipe 64 is inserted into the through hole of the slide seat 321 and fits with the rubber head 327, the water pump 326 is connected with the external water supply equipment, the water pump 326 absorbs the water and discharges it into the interior of the stainless steel pipe 64 through the drain port and the rubber head 327, the stainless steel pipe 64 is expanded by water pressure, so that the inner wall of the stainless steel pipe 64 is closely fitted with the inner wall of the second injection molding pipe 63, and then the water inside the stainless steel pipe 64 is discharged.
[0099] S42, then the cutting base 41 moves to the tail of the stainless steel tube 64, and then the base is pushed to move on the top of the base 42 by the displacement cylinder 44, so that the edge sealing head 49 facing the stainless steel tube 64 is docked with the tail of the stainless steel tube 64, and then the corresponding edge sealing head 49 is driven to rotate by the corresponding edge sealing motor 48, and the cutting base 41 moves to the tail of the stainless steel tube 64, so that the position of the stainless steel tube 64 is edge sealed.
[0100] S43, then the slide 321 corresponding to the tail of the stainless steel tube 64 moves, causing the three-jaw chuck 328 corresponding to the tail of the stainless steel tube 64 to clamp the stainless steel tube 64, while the three-jaw chuck 328 corresponding to the head of the stainless steel tube 64 cancels the clamping and moves away from the stainless steel tube 64, and then the cutting base 41 moves to the head of the stainless steel tube 64, and the head of the stainless steel tube 64 is sealed by another edge sealing head 49 corresponding to the head of the stainless steel tube 64 and the edge sealing motor 48.
[0101] S5 , after the edge sealing is completed, the bending portion 65 at the edge sealing position of the stainless steel tube 64 is laser cut and trimmed by the cutting assembly 4 .
[0102] More specific steps are:
[0103] S51. After the edge sealing is completed, the cutting base 41 moves to the tail of the stainless steel tube 64, and then the base is pushed to move on the top of the base 42 by the displacement cylinder 44, so that the laser cutting mechanism 47 and the tail of the stainless steel tube 64 are directed toward the stainless steel tube 64. After that, the laser cutting mechanism 47 moves around the outer wall size of the first injection tube 61, so that the tail of the stainless steel tube 64 is cut and trimmed.
[0104] S52, then the slide 321 corresponding to the tail of the stainless steel tube 64 moves, causing the three-jaw chuck 328 corresponding to the tail of the stainless steel tube 64 to clamp the stainless steel tube 64, while the three-jaw chuck 328 corresponding to the head of the stainless steel tube 64 cancels the clamping and moves away from the stainless steel tube 64, and then the cutting base 41 moves to the head of the stainless steel tube 64, and the head of the stainless steel tube 64 is trimmed by another laser cutting mechanism 47 corresponding to the head of the stainless steel tube 64.
[0105] Obviously, the above-described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present invention.
Claims
1. A wire mesh reinforced steel-plastic composite pipe assembly production line, comprising a wire mesh reinforced steel-plastic composite pipe, the wire mesh reinforced steel-plastic composite pipe comprising a pipe assembly (6), the pipe assembly (6) comprising a first injection molding pipe (61) and a second injection molding pipe (63) arranged inside the first injection molding pipe (61), the first injection molding pipe (61) and the second injection molding pipe (63) being injection molded as one piece, a wire mesh skeleton (62) being arranged between the second injection molding pipe (63) and the first injection molding pipe (61), a stainless steel pipe (64) being inserted inside the second injection molding pipe (63); the outer diameter of the stainless steel pipe (64) being the same as the inner diameter of the second injection molding pipe (63), both ends of the stainless steel pipe (64) being provided with a bending portion (65), the diameter of the bending portion (65) being the same as the outer diameter of the first injection molding pipe (61), characterized in that: It also comprises a stainless steel pipe conveying assembly (1), a stainless steel pipe welding assembly (2) mounted on the top of the stainless steel pipe conveying assembly (1), a PE pipe conveying assembly (5) arranged on one side of the stainless steel pipe conveying assembly (1), and a clamping assembly (3) arranged between the stainless steel pipe conveying assembly (1) and the PE pipe conveying assembly (5), wherein the top of the clamping assembly (3) is slidably connected to a cutting assembly (4); The stainless steel pipe conveying assembly (1) comprises a workbench (11) and a plurality of auxiliary support blocks (101) installed at equal intervals on the top of the workbench (11), wherein the plurality of auxiliary support blocks (101) are arranged in parallel; The stainless steel pipe welding assembly (2) comprises an articulated seat (23) mounted on the top of the workbench (11) and a swing arm (22) hinged to the top of the articulated seat (23); the middle portion of the bottom surface of the swing arm (22) is hinged to the articulated seat (23); an end of the swing arm (22) away from the auxiliary support block (101) is hinged to a lifting cylinder (21); a cylinder body of the lifting cylinder (21) is hinged to the workbench (11); an end of the swing arm (22) away from the lifting cylinder (21) is mounted with a first electric slide rail (24); and a welding head (25) is mounted on a side wall of the first electric slide rail (24); The clamping assembly (3) comprises a transfer rail (31) arranged between the workbench (11) and the PE pipe conveying assembly (5), the top of the transfer rail (31) being slidably connected to two switching mechanisms (32), the two switching mechanisms (32) being arranged opposite to each other; The two sets of switching mechanisms (32) each comprise a slide seat (321) slidably connected to the top of the transfer rail (31), a guide hole being provided at the top of the slide seat (321), and a three-jaw chuck (328) being installed on opposite sides of the two slide seats (321), a through hole being provided in the middle of the three-jaw chuck (328), and the through hole of the three-jaw chuck (328) being connected to the guide hole of the slide seat (321); A second electric slide rail (322) is horizontally mounted on one side of the top surface of the slide seat (321); the top of the second electric slide rail (322) is slidably connected to a bearing seat (323); the top of the bearing seat (323) is mounted with a third electric slide rail (324); the top of the third electric slide rail (324) is mounted with an L-shaped plate (325); the top of the L-shaped plate (325) is mounted with a water pump (326); a drainage pipe of the water pump (326) passes through the L-shaped plate (325) and is connected to and mounted with a rubber seal (327); The cutting assembly (4) comprises a cutting base (41) slidably connected to the top of the transfer rail (31) and a base (42) installed on the top of the cutting base (41); the top of the base (42) is slidably connected to a base platform; the top of the base platform is vertically installed with a fourth electric slide rail (45); the side wall of the fourth electric slide rail (45) is slidably connected to an L-shaped frame (46); the top of the L-shaped frame (46) is horizontally installed with two laser cutting mechanisms (47); the two laser cutting mechanisms (47) are arranged in opposite directions. The base (42) is provided with a connecting plate (43) installed on the side wall thereof, a displacement cylinder (44) is horizontally installed on a side of the connecting plate (43) away from the base (42), a piston rod of the displacement cylinder (44) passes through the connecting plate (43) and is connected to the base, two edge banding motors (48) are staggeredly installed inside the L-shaped frame (46), the two edge banding motors (48) are arranged in opposite directions, and an output end of each edge banding motor (48) extends to the outside of the L-shaped frame (46) and is connected to an edge banding head (49).
2. The wire mesh reinforced steel-plastic composite pipe assembly production line according to claim 1 is characterized by: The stainless steel pipe conveying assembly (1) further comprises a guide rail (12) mounted on the top of the workbench (11); a transfer trolley (13) is slidably connected to the top of the guide rail (12); a drive motor (14) is mounted on the top of the transfer trolley (13); and a swing plate (15) is connected to the output end of the drive motor (14).
3. The wire mesh reinforced steel-plastic composite pipe assembly production line according to claim 2 is characterized by: A vertical plate (16) is installed on the top of the workbench (11), and an electric chuck (19) is rotatably connected to the side of the vertical plate (16) close to the workbench (11). A through hole is opened in the middle of the electric chuck (19), and a through hole is opened on the side wall of the vertical plate (16). The through hole is connected to the through hole inside the electric chuck (19). A servo motor (17) is installed on the side of the vertical plate (16) away from the workbench (11), and the output end of the servo motor (17) passes through the vertical plate (16) and is connected to the electric chuck (19) by a transmission mechanism (18).
4. The wire mesh reinforced steel-plastic composite pipe assembly production line according to claim 1 is characterized by: The PE pipe conveying assembly (5) comprises a conveyor belt mechanism (51) arranged on a side of the transfer rail (31) away from the workbench (11) and a motorized roller (52) drivingly connected to one end of the top of the conveyor belt mechanism (51); two rotating disks (53) are symmetrically sleeved and connected to the outer side wall of the motorized roller (52); four grooves (54) are equidistantly formed on the side wall of each rotating disk (53); and a plurality of conveyor rollers (55) are equidistantly rotatably connected to one end of the conveyor belt mechanism (51) close to the rotating disk (53). The angle of the conveying roller (55) is staggered with the conveying direction of the conveyor belt mechanism (51), and the staggered angle is 90 degrees. A fixed plate (56) is installed on the side of the conveyor belt mechanism (51) away from the transfer rail (31). A push cylinder (57) is horizontally installed on the side of the fixed plate (56) away from the conveyor belt mechanism (51). The piston rod of the push cylinder (57) passes through the fixed plate (56) and is connected to a push block (58). The push block (58) extends to the top of the conveying roller (55).
5. A method for assembling a steel mesh reinforced steel-plastic composite pipe, using the steel mesh reinforced steel-plastic composite pipe assembly production line as claimed in any one of claims 1 to 4, characterized in that: The following steps are involved: S1, a worker weaves a steel mesh frame (62) onto the outer side wall of a second injection molding tube (63) through an external weaving device, and then injection molds a first injection molding tube (61) onto the outside of the steel mesh frame (62) and the second injection molding tube (63), finally forming a PE tube, and then the PE tube conveying assembly (5) continuously conveys the PE tube toward the clamping assembly (3); S2, the stainless steel pipe (64) is rolled into a cylindrical shape by an external rolling device and transferred to the top of the plurality of auxiliary support blocks (101), and is transported in the direction of the transfer rail (31) by the stainless steel pipe conveying assembly (1). During this process, the piston rod of the lifting cylinder (21) extends and pushes one end of the swing arm (22) to move upward, and the other end of the swing arm (22) moves downward synchronously and drives the first electric slide rail (24) and the welding head (25) to move downward. The bottom end of the welding head (25) is attached to the weld position of the stainless steel pipe (64), and the stainless steel pipe (64) is gradually welded into shape by the welding head (25) during the conveying process. The conveying directions of the PE pipe and the stainless steel pipe (64) are opposite, and they are relatively close to each other during the conveying to facilitate the subsequent docking operation; S3, the head of the PE tube and the head of the stainless steel tube (64) are respectively inserted into the position of the clamping assembly (3) and docked, and the length of the PE tube is shorter than the length of the stainless steel tube (64), so that both ends of the stainless steel tube (64) are exposed outside the PE tube; After the S4, PE pipe and stainless steel pipe (64) are connected, two sets of clamping components (3) are used to perform a hydraulic hole expansion operation, and then the cutting component (4) is moved to the tail of the stainless steel pipe (64), and then the tail of the stainless steel pipe (64) is sealed, and then the cutting component (4) is moved to the head of the stainless steel pipe (64), and then the head of the stainless steel pipe (64) is sealed; S5. After the edge sealing is completed, the bending portion (65) at the edge sealing position of the stainless steel tube (64) is laser cut and trimmed by the cutting component (4).