LNG ship tail shaft subsection sheet body folding control method and tail shaft subsection

By introducing auxiliary reference points and total station measurements during the segmented closing process of the LNG ship's stern shaft, the problem of positioning deviation caused by construction site factors was solved, a more efficient closing positioning and construction process was achieved, and costs and risks were reduced.

CN118723004APending Publication Date: 2024-10-01HUDONG ZHONGHUA SHIPBUILDINGGROUP +1
View PDF 8 Cites 0 Cited by

Patent Information

Application Number
CN202410888668.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-04
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

During the segmented closing process of the existing LNG ship's stern shaft, due to the influence of wind direction, scaffolding and other factors on the construction site, the positioning data deviated greatly, requiring multiple measurements and adjustments, resulting in high construction costs, a long cycle, and the risk of poor dimensions.

Method used

By segmenting the stern shaft into piece A and piece B, using auxiliary reference points and total stations for precision measurement and positioning adjustment, and combining the segmented reinforcement layout plan for closing and positioning, the difficulty of closing is reduced and the construction cycle is accelerated.

Benefits of technology

It effectively reduces the difficulty of closing positioning, shortens the construction cycle, reduces the waste of manpower, material and equipment resources, improves positioning accuracy, and avoids positioning inaccuracies caused by on-site factors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118723004A_ABST
    Figure CN118723004A_ABST
Patent Text Reader

Abstract

The invention relates to an LNG ship tail shaft subsection sheet body folding control method and a tail shaft subsection. The method comprises the steps that a sheet body A and a sheet body B are built respectively and then folded; respectively selecting auxiliary reference points on the A sheet body and the B sheet body; determining a correction position, a correction direction and a correction size of the A sheet body according to folding positioning data measured by the total station; calculating the theoretical distance between the auxiliary reference points according to the actual distance between the auxiliary reference points of the A sheet body and the B sheet body and the correction direction and the correction size of the A sheet body; and according to the corrected position, the corrected direction and the corrected size of the A sheet body, combining the theoretical distance between the auxiliary reference points to adjust the folding positioning of the A sheet body, and checking the positioning state of the A sheet body in the adjusting process. According to the method, through introduction of the auxiliary reference points, when the sheet bodies are folded, theoretical folding positioning adjustment is converted into visible data through distance change between the auxiliary reference points, folding positioning of the sheet bodies is facilitated, the folding positioning difficulty is reduced, and the construction period is shortened.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of shipbuilding, and in particular to a LNG ship stern shaft segmentation sheet closing control method and a stern shaft segmentation. Background Art

[0002] At present, the double stern shaft design is widely used in the stern propulsion system of LNG ships. The centerline of the stern shaft hole forms a certain angle with the centerline of the hull. When the stern shaft is constructed in sections, it is necessary to ensure that the stern shaft tube is perpendicular to the horizontal plane during the construction of the sections and make the support plane frame into an inclined surface. When the stern shaft is constructed in sections, it is divided into two pieces A and B for closure. The prior art, such as a method for quickly installing a supporting bracket on a LNG ship stern shaft section and a stern shaft section disclosed in publication number CN115158584A, divides the stern shaft section into A piece and B piece for closure.

[0003] When the A and B sheets are closed, it is necessary to ensure that the base surfaces of the two sheets are on the same inclined plane after closing, and at the same time ensure the verticality and squareness of the box of sheet A. The closing of conventional stern shaft segmented sheets will cause large deviations in on-site confirmation data and analysis data due to interference factors such as wind direction and scaffolding at the construction site. It is necessary to use a total station to perform multiple measurements and software analysis, and combine the construction site ruler and plumb bob to make multiple adjustments to the closing of the sheets. As a result, the entire construction process is costly, the construction period is long, and there are many risks of poor dimensions after segmented molding. Summary of the invention

[0004] In order to reduce the difficulty of on-site closing and positioning and shorten the construction period, the present invention provides a LNG ship stern shaft segmentation piece closing control method and a stern shaft segment;

[0005] The technical objectives of the present invention are achieved through the following technical solutions:

[0006] A method for controlling the closing of segmented sheets of a LNG ship stern shaft, the method comprising the following steps:

[0007] Step 1: Divide the stern shaft into A and B sections, and make the ground wire and the tire frame according to the stern shaft section construction process drawing;

[0008] Step 2, the A sheet and the B sheet are constructed separately, the B sheet is constructed on the tire frame manufactured in step 1 in accordance with the ground line alignment method; the A sheet is constructed on a separate tire frame;

[0009] Step 3: On the basis of qualified accuracy of sheet B, the ground line of the platform plate of sheet A is drawn on the ground with the closing interface of sheet B and sheet A as the reference, and a closing frame of sheet A is made along the platform plate ground line to close sheet A and sheet B;

[0010] Step 4, select auxiliary reference points on the A sheet and the B sheet respectively, and set the auxiliary reference points at the outer plate hard stop close to the segmented reinforcement and the tail shaft casting according to the segmented reinforcement layout diagram; measure the closing positioning accuracy of the A sheet and the B sheet and the position of the auxiliary reference points by a total station, and then install the segmented reinforcement after the auxiliary reference points are measured;

[0011] Step 5: Determine the corrected position, corrected direction and corrected size of sheet A according to the closing positioning data of sheet A and sheet B measured by the total station; calculate the actual distance between the auxiliary reference points of sheet A and sheet B according to the position data of the auxiliary reference points measured by the total station, and calculate the theoretical distance between the auxiliary reference points of sheet A and sheet B according to the actual distance, the corrected direction and corrected size of sheet A;

[0012] Step 6: According to the corrected position, direction and size of sheet A and the theoretical distance between the auxiliary reference points of sheet A and sheet B, adjust the closing position of sheet A, and check the positioning state of sheet A during the adjustment process.

[0013] Furthermore, in step 1, when drawing the ground line, the ground line is drawn with the hull height direction and the hull half-width direction as the center line of the tire frame; the projection of the stern tube is located at the intersection of the center line of the tire frame.

[0014] Furthermore, in step 2, the B sheet is constructed with the first rib of the bow as the base surface; and the A sheet is constructed with the platform plate as the base surface.

[0015] Furthermore, in step 4, when selecting the auxiliary reference point, the following steps are included:

[0016] Step 4.1: Preliminarily select the location of the auxiliary reference point according to the segmented reinforcement layout diagram;

[0017] Step 4.2: After the scaffolding is erected and the position of the total station is determined, the position of the auxiliary reference point is finally determined to ensure that the position of the auxiliary reference point observed by the total station is not affected;

[0018] Step 4.3: After the position of the auxiliary reference point is finally determined, make a Yangchong mark at the position of the auxiliary reference point and post a reflective sheet.

[0019] Furthermore, after the auxiliary reference points are measured, the segmented reinforcement is installed according to the segmented reinforcement layout drawing, and the two ends of the segmented reinforcement are welded to connect the A sheet and the B sheet respectively.

[0020] Furthermore, when measuring data with the help of a total station in step 4, the measurement deviation adjustment of the total station transfer station cannot exceed 0.3 mm, and the measurement coverage angle is controlled at 60°-120°.

[0021] Further, in step 5, the theoretical size between the auxiliary reference points = the actual size between the auxiliary reference points ± the correction value of the platform plate in the Z-axis direction ± the outer plate linear adjustment value + 5mm welding shrinkage anti-deformation value;

[0022] In the hull coordinate system, the Z-axis direction is the upper and lower directions of the stern axis segment in the hull coordinate system, the Y-axis is the half-width direction of the hull, and the X-axis is the bow and stern direction of the hull;

[0023] The correction value of the platform plate in the Z-axis direction is + in the upper direction and - in the lower direction;

[0024] The outer plate linear adjustment value is ±3.5mm for every 10mm in the Y-axis direction and ±2mm for every 10mm in the X-axis direction. The linear adjustment value of the outer plate in the direction of increasing the linear type is - value, and the linear adjustment value of the outer plate in the direction of decreasing the linear type is + value.

[0025] When the deviation of the platform plate in the Z-axis direction is +5mm to +10mm, the +5mm welding shrinkage anti-deformation value is not considered when calculating the theoretical size between the auxiliary reference points.

[0026] Furthermore, in step 6, during the adjustment process according to the corrected position, corrected direction, and corrected size of sheet A, the actual distance between the auxiliary reference points of sheet A and sheet B is measured, and whether the positioning adjustment of sheet A meets the requirements is determined by the change in the actual distance between the auxiliary reference points of sheet A and sheet B.

[0027] The present invention also provides a LNG ship stern shaft segment, which is a double tail shaft segment, the double tail shaft segments are symmetrically distributed along the center line of the hull, and the single-side stern shaft segment is constructed according to the above method.

[0028] Compared with the prior art, the present invention has the following beneficial effects:

[0029] 1. The LNG ship stern shaft segmented sheet closing control method of the present invention introduces auxiliary reference points. When sheet A is closed to sheet B, the theoretical closing positioning adjustment is converted into visible data through the distance change between the auxiliary reference points, which facilitates the closing positioning of the sheets, reduces the difficulty of closing positioning, speeds up the construction cycle, and reduces the waste of manpower, material resources, and equipment resources.

[0030] 2. The auxiliary reference points of the present invention can also serve as the basis for subsequent inspection of the closing positioning accuracy of sheet A. By directly measuring the distance between the auxiliary reference points and converting the measurement of three-dimensional data into the measurement of two-dimensional data, it is possible to quickly determine whether the positioning state meets the requirements; avoiding the problem of inaccurate positioning caused by factors such as scaffolding, wind direction, and human errors on site. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1It is a schematic diagram of the tire frame center line and the ground line in the present invention.

[0032] Figure 2 It is a schematic diagram of the construction of the B sheet in the present invention.

[0033] Figure 3 It is a schematic diagram of the construction of the A sheet in the present invention.

[0034] Figure 4 It is a schematic diagram of drawing the ground wire of the platform plate in the present invention.

[0035] Figure 5 It is a schematic diagram of the closing of sheet A and sheet B in the present invention.

[0036] Figure 6 It is a schematic diagram of auxiliary reference point selection in the present invention.

[0037] In the figure, 1. center line of the tire frame; 2. platform plate; 3. platform plate ground line; 4. outer plate; 5. A sheet; 6. B sheet; 7. auxiliary reference point; 8. segmented reinforcement; 9. stern tube. DETAILED DESCRIPTION

[0038] The technical solution of the present invention is further described below in conjunction with specific embodiments:

[0039] A method for controlling the closing of a stern shaft segment of an LNG ship is provided. In this embodiment, the construction of a stern shaft segment of a 174,000 cubic meter LNG ship is taken as an example. The stern shaft segment is a double stern shaft segment, and the double stern shafts are symmetrically distributed along the center line of the hull. After the stern shaft segment on one side is built, it is closed to form a double stern shaft segment. In this embodiment, the construction of the stern shaft segment on the port side is taken as an example for explanation. The method comprises the following steps:

[0040] Step 1: Divide the stern shaft into A and B sections, wherein the B section has a stern shaft tube 9, and carry out ground wire production and tire frame construction according to the stern shaft section construction process drawing;

[0041] like Figure 1 As shown, when drawing the ground line, the ground line is drawn with BL.4500 in the hull height direction and CL.8934 in the hull half-width direction as the tire frame center line 1; the projection of the stern tube is located at the intersection of the tire frame center line.

[0042] The tire frame is manufactured according to the following manufacturing standards: support angle steel L100mm×100mm×10mm, tie angle steel L100×100×10mm, support spacing 1000mm×1000mm, and the height difference of the transverse angle steel is 57.6mm per 1m. After the construction is completed, the horizontal reference surface accuracy of the tire frame is required to be controlled within ±2mm, and the ground line accuracy is controlled within ±1mm.

[0043] Step 2, the A sheet and the B sheet are constructed separately, the B sheet is constructed on the tire frame manufactured in step 1 in accordance with the ground line alignment method; the A sheet is constructed on a separate tire frame;

[0044] The B body is constructed with the first rib position of the bow as the base surface. In this embodiment, the first rib position of the bow of the B body is FR19. Figure 2 As shown, the B sheet is constructed with FR19 as the base surface. The B sheet is laid on the tire frame in accordance with the ground line alignment method, and then the secondary marking, component installation, and loose outer plate construction are carried out on the base panel. The main dimension accuracy of the B sheet is controlled within ±2.5mm, the end face accuracy is controlled within ±2.5mm, the main dimension accuracy of the stern tube is controlled within ±10mm, and the verticality and concentricity are controlled within ±1mm.

[0045] The A sheet is constructed with the platform plate 2 as the base surface. Figure 3 As shown, during construction, a frame is made outside the A sheet for support, with emphasis on controlling the main dimensions of the outer plate 4 of the A sheet, and the main dimension accuracy of the outer plate 4 of the A sheet is controlled within ±2.5 mm.

[0046] Step 3: On the basis of qualified accuracy of the B sheet, Figure 4 As shown, the platform plate ground line 3 is drawn on the ground with the butt joint interface between the B plate and the A plate as a reference, and the A plate closure frame is made along the platform plate ground line 3 to close the A plate and close the B plate.

[0047] Step 4: Select auxiliary reference points on sheet A and sheet B respectively. The auxiliary reference points are set at the hard stop of the outer plate close to the segmented reinforcement according to the segmented reinforcement layout diagram; measure the closing positioning accuracy of sheet A and sheet B and the position of the auxiliary reference points by using a total station. After the auxiliary reference points are measured, the segmented reinforcement is installed;

[0048] As a preference, when measuring data with the aid of a total station, the measurement deviation adjustment of the total station transfer station shall not exceed 0.3 mm, and the measurement coverage angle shall be controlled at 60°-120°. Figure 6 shown.

[0049] When selecting auxiliary reference points, the following steps are included:

[0050] Step 4.1, preliminarily select the position of the auxiliary reference point according to the segmented reinforcement layout diagram; in this embodiment, the auxiliary reference point 7 is selected at the intersection of the FR12 rib position and the L12 longitudinal girder, the intersection of the FR9 rib position and the L9 longitudinal girder, and the first displacement 1198 of the stern shaft casting. Figure 5 As shown;

[0051] Step 4.2: After the scaffolding is erected and the position of the total station is determined, the position of the auxiliary reference point is finally determined to ensure that the position of the auxiliary reference point observed by the total station is not affected, that is, the auxiliary reference point is not blocked by the total station;

[0052] Step 4.3: After the position of the auxiliary reference point is finally determined, make a Yangchong mark at the position of the auxiliary reference point and post a reflective sheet.

[0053] After the auxiliary reference points are measured, the segmented reinforcement is installed according to the segmented reinforcement layout drawing, and the two ends of the segmented reinforcement are respectively welded to the A sheet 5 and the B sheet 6. In this embodiment, a round steel pipe is selected as the segmented reinforcement 8, and the two ends of the round steel pipe 8 are welded to the A sheet 5 and the B sheet 6 after being cut on site according to the line shape.

[0054] Step 5, determining the corrected position, corrected direction and corrected size of the A sheet 5 according to the closing positioning data of the A sheet 5 and the B sheet 6 measured by the total station; calculating the actual distance between the auxiliary reference points of the A sheet and the B sheet according to the position data of the auxiliary reference points measured by the total station, and calculating the theoretical distance between the auxiliary reference points of the A sheet and the B sheet according to the actual distance, the corrected direction and the corrected size of the A sheet;

[0055] Theoretical size between auxiliary reference points = actual size between auxiliary reference points ± correction value of platform plate in Z-axis direction ± adjustment value of outer plate line type + 5mm welding shrinkage anti-deformation value;

[0056] In the hull coordinate system, the Z-axis direction is the upper and lower directions of the stern axis segment in the hull coordinate system, the Y-axis is the half-width direction of the hull, and the X-axis is the bow and stern direction of the hull; Figure 2 , Figure 3 , Figure 5 , Figure 6 The three-dimensional coordinate direction in is the coordinate axis direction of the hull coordinate.

[0057] The correction value of the platform plate in the Z-axis direction is + in the upper direction and - in the lower direction;

[0058] The outer plate linear adjustment value is ±3.5mm for every 10mm in the Y-axis direction and ±2mm for every 10mm in the X-direction. The outer plate linear adjustment value is - in the direction where the linear type becomes larger, and + in the direction where the linear type becomes smaller. The outer plate linear adjustment value is: in the stern shaft section, in the hull coordinates, the influence of the linear changes in the bow and stern directions of the hull, i.e. the X-axis direction, and the half-width direction, i.e. the Y-axis direction, on the height direction, i.e. the Z direction.

[0059] When the deviation of the platform plate in the Z-axis direction is +5mm to +10mm, the deviation of the platform plate in the Z-axis direction is within the normal range due to welding shrinkage after welding, and 5mm anti-deformation is not required. Therefore, the +5mm welding shrinkage anti-deformation value is not considered when calculating the theoretical size between the auxiliary reference points.

[0060] Step 6: According to the corrected position, direction and size of sheet A and the theoretical distance between the auxiliary reference points of sheet A and sheet B, adjust the closing position of sheet A, and check the positioning state of sheet A during the adjustment process.

[0061] Specifically, during the adjustment of sheet A, the two auxiliary reference points on sheet A will change synchronously with sheet A. Even if the closing and positioning adjustment state of sheet A cannot be directly seen, the distance between the two auxiliary reference points on sheet A and the auxiliary reference points on sheet B can be measured intuitively.

[0062] Several detection points are arranged on the A sheet, and the detection points are arranged at key positions of the A sheet, including but not limited to the upper position, the lower position, and both sides of the Y-axis direction; by collecting three-dimensional data at key positions and converting them into hull coordinates, the closing positioning of the A sheet is judged, so that the deviation position, deviation direction and deviation size of the current position of the A sheet compared with the theoretical position can be calculated, the deviation position corresponds to the correction position, the deviation direction corresponds to the correction direction, and the deviation size corresponds to the correction size.

[0063] Correction is performed according to the correction position, correction direction and correction size. Since the structure of film A is relatively large, it is difficult to make an intuitive judgment during the actual operation. The two auxiliary reference points on film A will also be moved synchronously during the correction process. In this way, the auxiliary reference for adjusting film A is realized by using the change in the distance between the two auxiliary reference points on film A and the auxiliary reference points on film B.

[0064] Since the corrected size of sheet A is a theoretical value, the theoretical distance between the auxiliary reference points of sheet A and the auxiliary reference points of sheet B should be inferred based on the actual distance between the auxiliary reference points of sheet A and sheet B; sheet A should be adjusted according to the corrected data, and the actual distance between the auxiliary reference points of sheet A and sheet B should be measured during the adjustment process to determine the corrected size and whether the corrected distance meets the requirements.

[0065] This embodiment is only a further explanation of the present invention, not a limitation of the present invention. After reading this specification, those skilled in the art may make non-creative modifications to this embodiment as needed, but as long as it is within the scope of the claims of the present invention, it will be protected by the patent law.

Claims

1. A method for controlling the closing of segmented pieces of a LNG ship stern shaft, the method The following steps are involved: Step 1: Divide the stern shaft into A and B sections, and make the ground wire and the tire frame according to the stern shaft section construction process drawing; Step 2, the A sheet and the B sheet are constructed separately, the B sheet is constructed on the tire frame manufactured in step 1 in accordance with the ground line alignment method; the A sheet is constructed on a separate tire frame; Step 3: On the basis of qualified accuracy of sheet B, the ground line of the platform plate of sheet A is drawn on the ground with the closing interface of sheet B and sheet A as the reference, and a closing frame of sheet A is made along the platform plate ground line to close sheet A and sheet B; Step 4, select auxiliary reference points on the A sheet and the B sheet respectively, and set the auxiliary reference points at the outer plate hard stop close to the segmented reinforcement and the tail shaft casting according to the segmented reinforcement layout diagram; measure the closing positioning accuracy of the A sheet and the B sheet and the position of the auxiliary reference points by a total station, and then install the segmented reinforcement after the auxiliary reference points are measured; Step 5: Determine the corrected position, corrected direction and corrected size of sheet A according to the closing positioning data of sheet A and sheet B measured by the total station; calculate the actual distance between the auxiliary reference points of sheet A and sheet B according to the position data of the auxiliary reference points measured by the total station, and calculate the theoretical distance between the auxiliary reference points of sheet A and sheet B according to the actual distance, the corrected direction and the corrected size of sheet A; Step 6: According to the corrected position, direction and size of sheet A and the theoretical distance between the auxiliary reference points of sheet A and sheet B, adjust the closing position of sheet A, and check the positioning state of sheet A during the adjustment process.

2. A method for controlling the closing of segmented pieces of a LNG ship stern shaft according to claim 1, It is characterized in that In step 1, the ground line is drawn as the center line of the tire frame in the direction of the hull height and the direction of the half-width of the hull; the projection of the stern tube is located at the intersection of the center line of the tire frame.

3. A method for controlling the closing of segmented pieces of a LNG ship stern shaft according to claim 2, It is characterized in that In step 2, the B sheet is constructed with the first rib of the bow as the base surface; the A sheet is constructed with the platform plate as the base surface.

4. A method for controlling the closing of segmented pieces of a LNG ship stern shaft according to claim 1, It is characterized in that In step 4, when selecting the auxiliary reference point, the following steps are included: Step 4.1: Preliminarily select the location of the auxiliary reference point according to the segmented reinforcement layout diagram; Step 4.2: After the scaffolding is erected and the position of the total station is determined, the position of the auxiliary reference point is finally determined to ensure that the position of the auxiliary reference point observed by the total station is not affected; Step 4.3: After the position of the auxiliary reference point is finally determined, make a foreign mark at the position of the auxiliary reference point and post a reflective sheet.

5. According to claim 1, a method for controlling the closing of segmented pieces of a LNG ship stern shaft, It is characterized in that After measuring the auxiliary reference points, the segmented reinforcement is installed according to the segmented reinforcement layout drawing, and the two ends of the segmented reinforcement are welded to connect the A sheet and the B sheet respectively.

6. A method for controlling the closing of segmented pieces of a LNG ship stern shaft according to claim 1, It is characterized in that When measuring data with the help of a total station in step 4, the measurement deviation adjustment of the total station transfer station cannot exceed 0.3 mm, and the measurement coverage angle is controlled at 60°-120°.

7. A method for controlling the closing of segmented pieces of a LNG ship stern shaft according to claim 3, It is characterized in that In step 5, the theoretical size between the auxiliary reference points = the actual size between the auxiliary reference points ± the correction value of the platform plate in the Z-axis direction ± the linear ratio influence value + 5mm welding shrinkage anti-deformation value; In the hull coordinate system, the Z-axis direction is the upper and lower directions of the stern axis segment in the hull coordinate system, the Y-axis is the half-width direction of the hull, and the X-axis is the bow and stern direction of the hull; The correction value of the platform plate in the Z-axis direction is + in the upper direction and - in the lower direction; The outer plate linear adjustment value is ±3.5mm for every 10mm in the Y-axis direction and ±2mm for every 10mm in the X-axis direction. The linear adjustment value of the outer plate in the direction of increasing the linear type is - value, and the linear adjustment value of the outer plate in the direction of decreasing the linear type is + value. When the deviation of the platform plate in the Z-axis direction is +5mm to +10mm, the +5mm welding shrinkage anti-deformation value is not considered when calculating the theoretical size between the auxiliary reference points.

8. A method for controlling the closing of segmented pieces of a LNG ship stern shaft according to claim 1, It is characterized in that In step 6, during the adjustment process according to the corrected position, corrected direction, and corrected size of sheet A, the actual distance between the auxiliary reference points of sheet A and sheet B is measured, and whether the positioning adjustment of sheet A meets the requirements is judged by the change in the actual distance between the auxiliary reference points of sheet A and sheet B.

9. A LNG ship stern shaft segment, It is characterized in that The stern shaft segment is a double tail shaft segment, the double tail shaft segments are symmetrically distributed along the center line of the hull, and the single-side stern shaft segment is constructed according to the method described in any one of claims 1-8.

Citation Information

Patent Citations

  • Method for rapidly detecting accuracy of position seaming in shipbuilding process

    CN101195403A

  • Laser tracking measurement apparatus multi-target measuring method and apparatus based on inertia guiding

    CN106646507A

  • Chemical tanker U-shaped block assembly and carrying precision control method

    CN111703554A

  • Segmented construction method for double tail fins of LNG ship

    CN112550621A

  • Method for quickly installing supporting bracket on LNG ship tail shaft section and tail shaft section

    CN115158584A