Cofferdam type underwater plugging and fishing process

Through the cofferdam-type underwater sealing and salvage process, the cofferdam steel plate and underwater sealing measures are used to solve the problems of low efficiency and high cost of traditional large ship rescue, and realize efficient, safe and environmentally friendly ship floating and salvage.

CN118723019APending Publication Date: 2024-10-01XIAMEN XIAMIN DIVING ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411034266.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

The traditional rescue and salvage of large damaged ships has a long project cycle, high costs, high risks, and is difficult to complete efficiently.

Method used

The cofferdam-type underwater sealing and salvage process is used, and divers measure the damaged parts of the hull. The cofferdam steel plate is prefabricated and installed on the outside of the hull. Underwater sealants and welding measures are combined to ensure sealing. Water pumps are used to pump water to float the hull.

Benefits of technology

Without the need for the support of large salvage engineering ships, the efficiency of sealing and floating of damaged ships is improved, the cost is reduced, the safety and environmental protection of the operation are ensured, it can adapt to various damage situations, and optimize the salvage process .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118723019A_ABST
    Figure CN118723019A_ABST
Patent Text Reader

Abstract

The invention provides a cofferdam type underwater plugging and salvaging process, and relates to the field of ship salvaging and floating, and the cofferdam type underwater plugging and salvaging process specifically comprises the following steps: S1, a diver enters water to detect a damaged ship, determines a damaged part, and then measures the size and shape of the damaged part; according to the method, cofferdam blocking and drainage floating of the large damaged ship are achieved, underwater cofferdam sealing is conducted on the outer portion of a cabin of the damaged ship body, after sealing is achieved through attachment of cofferdam steel plates and the ship body, seawater leaking into the damaged cabin is discharged through a water pump, and the buoyancy of the accident ship is recovered. The damaged ship is blocked and floated on the premise that the support of a large salvage engineering ship is not needed, the efficiency is high, and the cost is low.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of ship salvaging and floating, and in particular to a cofferdam-type underwater plugging and salvaging process. Background Art

[0002] With the development of the country's marine economy and the improvement of marine shipping technology, the size of ships damaged in accidents has gradually increased, and the difficulty and cost of rescue and salvage have also increased accordingly. According to traditional rescue and salvage techniques, large ships that are already damaged or about to sink in the accident area need to be mobilized with large salvage engineering ships. The rescue and salvage project has a long cycle, high cost and great risk, and needs to be optimized and improved. Summary of the invention

[0003] The purpose of the present invention is to solve the technical problems raised in the above background technology.

[0004] The present invention adopts the following technical solution: a cofferdam-type underwater plugging and salvage process, wherein the specific steps of the cofferdam-type underwater plugging and salvage process are as follows: S1: Divers go into the water to explore the damaged ship, identify the damaged part, and then measure the size and shape of the damaged part; S2: Determine the size and shape of the cofferdam steel plate according to the specific location of the damaged ship and the precise size and shape of the damaged part, then prefabricate the cofferdam steel plate and set the lifting lugs at the edge and middle of the cofferdam steel plate; S3: With the help of the crane of the diving operation ship, the prefabricated cofferdam steel plate is hoisted to the outside of the damaged part of the hull. The divers use the chain hoist to put the cofferdam steel plate in place. The divers adjust and check the cofferdam steel plate and the hull to ensure the fit; S4: The diver tightens the lifting lug in the middle of the cofferdam steel plate with a chain hoist to make the cofferdam steel plate close to and fixed to the ship hull; S5: Taking into account the irregularities of the surface of some damaged hulls, in order to ensure the sealing of the cofferdam, when the gap between the edge of the cofferdam steel plate and the hull is less than 2cm, the divers use special underwater sealants to bond the edge of the cofferdam steel plate to the hull. After the underwater sealant is cured, check until the seal is intact; if the gap between the cofferdam steel plate and the hull is between 2cm and 20cm, the divers use the method of driving wooden wedges to fill the gap between the cofferdam steel plate and the hull, and use underwater sealants to seal the edge of the steel plate and the hull; if the gap between the edge of the cofferdam steel plate and the hull is greater than 20cm, the steel plate is welded to the hull, and the steel plate edge is sealed with the hull in combination with underwater sealants; S6: Divers began to use water pumps to drain water from the damaged compartment; S7: As the pumping and drainage operation proceeds, the water level in the cabin drops, and the buoyancy of the internal cabin is gradually formed. When the hull is basically floating and stable, the drainage is stopped and the hull floating and salvage operation is completed; S8: Tow the floated vessel to a nearby shipyard for maintenance and inspection.

[0005] Preferably, the cofferdam steel plates in S2, S3 and S4 are prefabricated and hoisted and fixed. Here, by prefabricating the cofferdam steel plates and setting lifting lugs at the edges and the middle, with the assistance of the crane of the diving operation ship and the precise operation of the divers, the cofferdam steel plates can be installed quickly and accurately.

[0006] Preferably, the sealing of the edge of the cofferdam steel plate is checked in S5 until the sealing is achieved. Here, the sealing of the edge of the cofferdam steel plate is strictly checked until the sealing requirement is met, which can effectively avoid the risk of water leakage during underwater operations.

[0007] Preferably, in S5, various sealing measures are taken according to the different sizes of the gap between the edge of the cofferdam steel plate and the hull. Here, different sealing measures are taken to deal with the gaps of different sizes between the edge of the cofferdam steel plate and the hull. This flexibility can ensure that effective sealing can be achieved in various damage situations.

[0008] Preferably, the water pump in S6 can be increased or replaced with a high-power water pump according to the pumping situation. Here, the number of water pumps can be flexibly adjusted or replaced with a high-power water pump according to the pumping situation, which can effectively cope with salvage tasks of different complexities.

[0009] Compared with the prior art, the advantages and positive effects of the present invention are: In the present invention, the cofferdam sealing and drainage and floating of a large damaged ship are realized by setting the present invention. The damaged hull cabin is sealed by underwater cofferdam sealing, and the cofferdam steel plate is fitted with the hull to achieve sealing. Then, the seawater leaked into the damaged cabin is discharged by a water pump to restore the buoyancy of the accident ship. The sealing and floating of the damaged ship is completed without the support of a large-scale salvage engineering ship, and the efficiency is high and the cost is low. BRIEF DESCRIPTION OF THE DRAWINGS

[0010] Figure 1 A schematic diagram of a cofferdam steel plate for a cofferdam-type underwater plugging and salvage process proposed by the present invention; Figure 2 A schematic diagram of water pumping for a cofferdam-type underwater plugging and salvage process proposed by the present invention; Figure 3 A schematic diagram of fixing a cofferdam steel plate on the side of a damaged hull in a cofferdam-type underwater plugging and salvage process proposed by the present invention; Figure 4 The present invention proposes a cofferdam-type underwater plugging and salvage process Figure 3 Side view.

[0011] Legend: 1. Hull; 2. Cofferdam steel plate; 3. Hoist chain; 4. Damaged position of the ship; 5. Water pump. DETAILED DESCRIPTION

[0012] In order to more clearly understand the above-mentioned purpose, features and advantages of the present invention, the present invention is further described below in conjunction with the accompanying drawings and embodiments. It should be noted that the embodiments of the present application and the features in the embodiments can be combined with each other without conflict.

[0013] In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention may also be implemented in other ways than those described herein. Therefore, the present invention is not limited to the specific embodiments of the following disclosure.

[0014] Unless otherwise specified, the reagents, methods and equipment used in the present invention are conventional reagents, methods and equipment in the technical field. Example

[0015] See also Figure 1-4 The present invention provides a technical solution: a cofferdam-type underwater plugging and salvage process, wherein the cofferdam-type underwater plugging and salvage process has the following specific steps: S1: Divers go into the water to explore the damaged ship, identify the damaged part, and then measure the size and shape of the damaged part; S2: Determine the size and shape of the cofferdam steel plate according to the specific location of the damaged ship and the precise size and shape of the damaged part, then prefabricate the cofferdam steel plate and set the lifting lugs at the edge and middle of the cofferdam steel plate; S3: With the help of the crane of the diving operation ship, the prefabricated cofferdam steel plate is hoisted to the outside of the damaged part of the hull. The divers use the chain hoist to put the cofferdam steel plate in place. The divers adjust and check the cofferdam steel plate and the hull to ensure the fit; S4: The diver tightens the lifting lug in the middle of the cofferdam steel plate with a chain hoist to make the cofferdam steel plate close to and fixed to the ship hull; S5: Taking into account the irregularities of the surface of some damaged hulls, in order to ensure the sealing of the cofferdam, when the gap between the edge of the cofferdam steel plate and the hull is less than 2cm, the divers use special underwater sealants to bond the edge of the cofferdam steel plate to the hull. After the underwater sealant is cured, check until the seal is intact; if the gap between the cofferdam steel plate and the hull is between 2cm and 20cm, the divers use the method of driving wooden wedges to fill the gap between the cofferdam steel plate and the hull, and use underwater sealants to seal the edge of the steel plate and the hull; if the gap between the edge of the cofferdam steel plate and the hull is greater than 20cm, the steel plate is welded to the hull, and the steel plate edge is sealed with the hull in combination with underwater sealants; S6: Divers began to use water pumps to drain water from the damaged compartment; S7: As the pumping and drainage operation proceeds, the water level in the cabin drops, and the buoyancy of the internal cabin is gradually formed. When the hull is basically floating and stable, the drainage is stopped and the hull floating and salvage operation is completed; S8: Tow the floated vessel to a nearby shipyard for maintenance and inspection.

[0016] Combining the characteristics of environmental protection, safety, cost-effectiveness and high efficiency, it provides an innovative solution for the field of underwater salvage. Through the precise measurement of divers and the prefabrication and installation of cofferdam steel plates, this method not only protects the marine environment and reduces the risk of pollution, but also significantly improves the safety and efficiency of operations. Its flexible adaptability enables it to effectively respond to various damage situations. The optimized operating procedures and material usage further reduce salvage costs and optimize traditional salvage technology. Under the premise of ensuring environmental protection and safety, efficient and economical salvage operations are achieved.

[0017] The cofferdam steel plates in S2, S3 and S4 are prefabricated and hoisted and fixed. In S5, the sealing of the cofferdam steel plate edges is checked until they are sealed. In S5, various sealing measures are taken according to the different sizes of the gap between the cofferdam steel plate edges and the hull. In S6, a high-power water pump can be added or replaced according to the pumping situation. The cofferdam steel plates are prefabricated and the lifting lugs are set at the edges and the middle. With the assistance of the crane of the diving operation ship and the precise operation of the divers, the rapid and accurate installation of the cofferdam steel plates can be ensured. This not only shortens the preparation time before salvage, but also improves the operation efficiency, ensures that the cofferdam steel plates fit closely with the damaged hull, and lays a solid foundation for the subsequent sealing and pumping operations. The sealing of the cofferdam steel plate edges is checked. Strict inspection until the sealing requirements are met can effectively avoid the risk of water leakage during underwater operations. This step ensures the quality of the plugging and ensures that the entire plugging structure can withstand the external water pressure during the pumping process, thereby improving the safety and success rate of the salvage operation. Different sealing measures are taken to deal with the gaps of different sizes between the edge of the cofferdam steel plate and the hull. This flexibility can ensure effective sealing in various damaged situations. This not only improves the adaptability and flexibility of the operation, but also allows the most appropriate sealing method to be selected according to the actual situation, optimize resource utilization, and ensure the quality of the operation. The number of water pumps can be flexibly adjusted or high-power water pumps can be replaced according to the pumping situation, which can effectively respond to salvage tasks of different complexities. This flexible response strategy ensures the speed and efficiency of pumping, and the pumping strategy can be adjusted in time according to the water accumulation in the cabin, speeding up the salvage progress and reducing the risk of complex salvage tasks.

[0018] The above description is only a preferred embodiment of the present invention and does not limit the present invention in other forms. Any technician familiar with the profession may use the technical content disclosed above to change or modify it into an equivalent embodiment with equivalent changes and apply it to other fields. However, any simple modification, equivalent change and modification made to the above embodiment based on the technical essence of the present invention without departing from the content of the technical solution of the present invention still falls within the protection scope of the technical solution of the present invention.

Claims

1. A cofferdam-type underwater plugging and salvage process, characterized in that: The specific steps of the cofferdam-type underwater plugging and salvage process are as follows: S1: Divers go into the water to explore the damaged ship, identify the damaged part, and then measure the size and shape of the damaged part; S2: Determine the size and shape of the cofferdam steel plate according to the specific location of the damaged ship and the precise size and shape of the damaged part, then prefabricate the cofferdam steel plate and set the lifting lugs at the edge and middle of the cofferdam steel plate; S3: With the help of the crane of the diving operation ship, the prefabricated cofferdam steel plate is hoisted to the outside of the damaged part of the hull. The divers use the chain hoist to put the cofferdam steel plate in place. The divers adjust and check the cofferdam steel plate and the hull to ensure the fit; S4: The diver tightens the lifting lug in the middle of the cofferdam steel plate with a chain hoist to make the cofferdam steel plate close to and fixed to the ship hull; S5: Taking into account the irregularities of the surface of some damaged hulls, in order to ensure the sealing of the cofferdam, when the gap between the edge of the cofferdam steel plate and the hull is less than 2cm, the divers use special underwater sealants to bond the edge of the cofferdam steel plate to the hull. After the underwater sealant is cured, check until the seal is intact; if the gap between the cofferdam steel plate and the hull is between 2cm and 20cm, the divers use the method of driving wooden wedges to fill the gap between the cofferdam steel plate and the hull, and use underwater sealants to seal the edge of the steel plate and the hull; if the gap between the edge of the cofferdam steel plate and the hull is greater than 20cm, the divers use steel plate welding to seal the edge of the steel plate and the hull, and use underwater sealants to seal the edge of the steel plate and the hull; S6: Divers began to use water pumps to drain water from the damaged compartment; S7: As the pumping and drainage operation proceeds, the water level in the cabin drops, and the buoyancy of the internal cabin is gradually formed. When the hull is basically floating and stable, the drainage is stopped and the hull floating and salvage operation is completed; S8: Tow the floated vessel to a nearby shipyard for maintenance and inspection.

2. The cofferdam-type underwater plugging and salvage process according to claim 1 is characterized in that: The cofferdam steel plates in S2, S3 and S4 are prefabricated and hoisted and fixed.

3. The cofferdam-type underwater plugging and salvage process according to claim 1 is characterized in that: In S5, the sealing performance of the edge of the cofferdam steel plate is checked until sealing is achieved.

4. The cofferdam-type underwater plugging and salvage process according to claim 1 is characterized in that: In S5, various sealing measures are provided according to the different sizes of the gap between the edge of the cofferdam steel plate and the hull.

5. The cofferdam-type underwater plugging and salvage process according to claim 1 is characterized in that: The water pump in S6 can be increased or replaced with a high-power water pump according to the pumping situation.