Deep foundation pit supporting method

By using high-pressure jet grouting piles to fill the gap between the interlocking cast-in-place piles and steel sheet piles during the construction of deep foundation pits, combined with the construction of prestressed jet grouting anchor cables, the problem of groundwater infiltration is solved, and construction safety and engineering stability are improved. .

CN118727767APending Publication Date: 2024-10-01CHINA ELEVENTH CHEM CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410942170.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

During the construction of deep foundation pits in coastal areas, due to abundant groundwater, the gaps between the cast-in-place piles and steel sheet piles cause groundwater to seep in, increasing construction safety risks.

Method used

High-pressure jet grouting piles are used to support the intersection between the interlocking cast-in-place pile support area and the steel sheet pile support area to fill the gaps and prevent groundwater from infiltrating. Prestressed jet grouting anchor cable construction can be used to enhance the support effect.

Benefits of technology

It effectively reduces the risk of groundwater entering the foundation pit, improves construction safety and project stability, and reduces potential safety hazards.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727767A_ABST
    Figure CN118727767A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of building construction, in particular to a deep foundation pit supporting method which comprises the steps that occluded cast-in-place pile supporting is adopted in a geological hard area to form an occluded cast-in-place pile supporting area; steel sheet pile supporting is adopted in the sludge area to form a steel sheet pile supporting area; and a high-pressure jet grouting pile support is also adopted at the joint of the occluded cast-in-place pile support area and the steel sheet pile support area. The invention aims to provide a deep foundation pit supporting method for at least one technical problem related in the prior art.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of building construction, and in particular to a deep foundation pit support method. Background Art

[0002] With the rapid economic development in coastal areas, super-large infrastructure projects such as nuclear power plants and large water conservancy facilities continue to emerge. An important feature of these projects is the need to build large accident pools to deal with emergencies. However, the geological conditions in coastal areas are complex, and the construction technology of deep foundation pit support is relatively difficult. Therefore, it is of great significance to carry out a technical summary of the "combined support system for deep foundation pits in coastal areas" to improve project safety and efficiency and ensure the stable operation of infrastructure in coastal areas. At present, when constructing the support system, interlocking cast-in-place piles are mostly used in geologically hard areas, and steel sheet piles are mostly used in silt areas. However, due to the abundant groundwater, groundwater often flows into the foundation pit from the gap between the interlocking cast-in-place piles and the steel sheet piles, which brings hidden dangers to the construction. Summary of the invention

[0003] The purpose of this application is to provide a deep foundation pit support method in view of at least one technical problem involved in the background technology.

[0004] In order to achieve the above objectives, this application adopts the following technical solutions:

[0005] The present application provides a deep foundation pit support method, comprising:

[0006] In geologically hard areas, interlocking cast-in-place pile support is used to form interlocking cast-in-place pile support areas;

[0007] Steel sheet pile support is used in the silt area to form a steel sheet pile support area;

[0008] High-pressure jet-jet pile support is also used at the intersection of the interlocking cast-in-place pile support area and the steel sheet pile support area.

[0009] Optionally, the high-pressure jet grouting pile support is also used at the intersection of the occlusal cast-in-place pile support area and the steel sheet pile support area, including:

[0010] Drilling rig positioning;

[0011] preparing cement slurry;

[0012] Intubation;

[0013] Lifting the shotcrete pipe and stirring;

[0014] and, partial treatment of the pile head;

[0015] Among them, the lifting of the shotcrete pipe and stirring include stopping drilling and continuing to rotate after the shotcrete pipe sinks to a preset depth, and after the shotcrete is sprayed for a preset time, lifting the drill rod at a preset lifting speed.

[0016] Optionally, after the pile head portion is processed, the method further comprises:

[0017] Use cement slurry with a water-cement ratio of 0.6 to 1 for supplementary filling.

[0018] Optionally, the deep foundation pit support method further includes using prestressed rotary jet anchor cable construction at the intersection of the interlocking cast-in-place pile support area and the steel sheet pile support area.

[0019] Optionally, the prestressed jet-sprayed anchor cable construction includes:

[0020] to form a hole;

[0021] Anchor cable installation;

[0022] Anchor grouting;

[0023] Waist beam construction;

[0024] and, tensioning and locking;

[0025] Among them, the waist beam construction includes: the waist beam adopts two channel steels connected and welded together with iron plates, and steel concrete anchor piers are used at the joints between the retaining piles and the waist beam to make the waist beam close to the vertical retaining piles. The anchor and the waist beam are separated by steel plate gaskets, and steel plates are used as pads between the waist beam and the anchor, and the pads are welded to the waist beam.

[0026] Optionally, the method of using interlocking cast-in-place piles to support in a geologically hard area to form an interlocking cast-in-place pile support area includes:

[0027] Casing burial;

[0028] The drilling rig is in place;

[0029] and, drilling rigs;

[0030] Wherein, while the drilling rig is drilling, mud wall protection is adopted;

[0031] The mud wall protection comprises: when the mud is injected for the first time, the mud is made to impact vertically downward in the middle of the pile hole.

[0032] Optionally, the step of using steel sheet pile support in the silt area to form a steel sheet pile support area includes:

[0033] Excavation of the first slope of the foundation pit;

[0034] Positioning and laying out of steel sheet piles;

[0035] Driving steel sheet piles;

[0036] Backfilling of foundation pit;

[0037] and, removal of sheet piles;

[0038] Wherein, before the steel sheet piles are driven, the method further includes: applying grease inside the locking mouth of the steel sheet piles.

[0039] Optionally, removing the steel sheet piles comprises:

[0040] First, use a vibrating hammer to vibrate the locking end of the steel sheet pile to reduce soil adhesion, and then pull out the steel sheet pile while vibrating;

[0041] Alternatively, first use a diesel hammer to vibrate the steel sheet pile down a preset distance, and then use the diesel hammer and vibratory hammer to alternately vibrate and pull out the steel sheet pile.

[0042] Optionally, the removing of the steel sheet piles further comprises:

[0043] When the top of the steel sheet pile is higher than the foundation bottom plate, stop pulling out and vibrate the steel sheet pile with a vibrating hammer.

[0044] Optionally, the deep foundation pit support method provided in the present application further includes:

[0045] In the sandy soil area, mesh anchor spraying support is used to form a mesh anchor spraying support area;

[0046] The mesh anchor spraying support area includes a fill bottom layer, a primary spraying surface layer, a steel mesh and a secondary spraying surface layer arranged in sequence from the inside to the outside;

[0047] The hanging mesh anchor spraying support area also includes a drainage pipe, a filter mesh, a metal fence and crushed stone particles. One end of the drainage pipe is a fixed end located in the bottom layer of the fill, and the other end of the drainage pipe passes through the primary spraying surface layer, the steel mesh and the re-spraying surface layer in sequence, and the filter mesh, crushed stone particles and the metal fence are sequentially covered from the outside to the inside at the fixed end.

[0048] The technical solution provided by this application can achieve at least one of the following beneficial effects:

[0049] The deep foundation pit support method provided in the present application adopts high-pressure rotary jet pile support at the intersection of the interlocking cast-in-place pile support area and the steel sheet pile support area to fill the possible gap between the interlocking cast-in-place pile support area and the steel sheet pile support area, so as to achieve the purpose of making it difficult for groundwater to enter the foundation pit, thereby reducing the safety hazards caused thereby.

[0050] The additional technical features and advantages of the present application will be more clearly explained in the following description, or can be understood through the specific practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0051] In order to more clearly illustrate the technical solutions of the specific implementation methods of the present application, the following is a brief introduction to the drawings required for the description of the specific implementation methods. Obviously, the drawings described below are some implementation methods of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work.

[0052] Figure 1 A schematic diagram of a process for implementing a deep foundation pit support method provided in an embodiment of the present application;

[0053] Figure 2 A structural schematic diagram of an implementation method of deep foundation support provided in an embodiment of the present application;

[0054] Figure 3 A schematic diagram of a process for implementing a steel sheet pile support provided in an embodiment of the present application;

[0055] Figure 4 A schematic diagram of a process for implementing an embodiment of the interlocking cast-in-place pile support provided in the embodiment of the present application;

[0056] Figure 5 A schematic diagram of a process for implementing a high-pressure jet grouting pile support provided in an embodiment of the present application;

[0057] Figure 6 A schematic diagram of a process for implementing the construction of prestressed jet-sprayed anchor cables provided in an embodiment of the present application;

[0058] Figure 7 A schematic diagram of a process for implementing a mesh anchor spraying support provided in an embodiment of the present application;

[0059] Figure 8 A partial cross-sectional diagram of an implementation of the mesh anchor spraying support area provided in an embodiment of the present application. DETAILED DESCRIPTION

[0060] The technical solution of the present application will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are part of the embodiments of the present application, rather than all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present application.

[0061] In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present application. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0062] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0063] like Figures 1 to 7 As shown, the embodiment of the present application provides a deep foundation pit support method, comprising:

[0064] Step 100: using interlocking cast-in-place piles to support the geologically hard area 07 to form an interlocking cast-in-place pile support area 04;

[0065] Step 200: Using steel sheet pile support in the silt area 01 to form a steel sheet pile support area 02;

[0066] Step 300: High-pressure jet grouting pile support is also used at the intersection of the interlocking cast-in-place pile support area 04 and the steel sheet pile support area 02. In the embodiment of the present application, the area using high-pressure jet grouting pile support can be called high-pressure jet grouting pile support area 03.

[0067] The deep foundation pit support method provided by the present application adopts high-pressure jet grouting pile support at the intersection of the interlocking cast-in-place pile support area 04 and the steel sheet pile support area 02 to fill the gap that may exist between the interlocking cast-in-place pile support area 04 and the steel sheet pile support area 02, so as to make it difficult for groundwater to enter the foundation pit, thereby reducing the safety hazards caused by this. The geologically hard area 07 may be a stone dam area.

[0068] Optionally, the step 300 (high-pressure jet grouting pile support is also used at the intersection of the occlusal cast-in-place pile support area 04 and the steel sheet pile support area 02) includes:

[0069] Step 310: Drilling rig positioning;

[0070] Step 320: preparing cement slurry;

[0071] Step 330: intubation;

[0072] Step 340: lifting the spraying pipe and stirring;

[0073] And, step 350: pile head part processing;

[0074] Among them, the step 340 (lifting the shotcrete pipe and stirring) includes stopping drilling and continuing to rotate after the shotcrete pipe sinks to a preset depth, and after the shotcrete is sprayed for a preset time, lifting the drill rod at a preset lifting speed.

[0075] Optionally, after step 350 (processing the pile head part), the method further includes:

[0076] Use cement slurry with a water-cement ratio of 0.6 to 1 for supplementary grouting. After the jet grouting operation, due to the water separation of the slurry, there are generally different degrees of shrinkage, which will cause pits on the top of the solid body. Therefore, it should be supplemented with cement slurry in time, and prevent the entry of soil or debris discharged from other drilling holes.

[0077] Optionally, the deep foundation pit supporting method further comprises:

[0078] Step 400: Prestressed rotary jet anchor cables are also used for construction at the intersection of the interlocking cast-in-place pile support area 04 and the steel sheet pile support area 02.

[0079] Optionally, the prestressed jet-sprayed anchor cable construction includes:

[0080] to form a hole;

[0081] Anchor cable installation;

[0082] Anchor grouting;

[0083] Waist beam construction;

[0084] and, tensioning and locking;

[0085] Among them, the waist beam construction includes: the waist beam adopts two channel steels (Q235-B grade H-shaped steel) connected and welded together with iron plates, and steel concrete anchor piers are used at the joints between the retaining piles and the waist beam to make the waist beam close to the vertical retaining piles. The anchor and the waist beam are separated by steel plate gaskets, and steel plates are used as pads between the waist beam and the anchor, and the pads are welded to the waist beam.

[0086] Optionally, the step 100 (using interlocking cast-in-place pile support in the geologically hard area 07 to form an interlocking cast-in-place pile support area 04) includes:

[0087] Step 110: burying casing;

[0088] Step 120: The drilling rig is in place;

[0089] And, step 130: drilling by a drilling rig;

[0090] Wherein, while performing step 130 (drilling with a drilling rig), mud wall protection is used;

[0091] The mud wall protection includes: when the mud is first injected, the mud is vertically impacted downward in the middle of the pile hole. The drilling by the drilling rig can also be called digging soil (rock) to form a hole.

[0092] Optionally, the step 200 (using steel sheet pile support in the silt area 01 to form a steel sheet pile support area 02) includes:

[0093] Step 210: excavation of the first slope of the foundation pit;

[0094] Step 220: Positioning and laying out the steel sheet piles;

[0095] Step 230: Driving steel sheet piles;

[0096] Step 240: backfilling the foundation pit;

[0097] And, step 250: removing the steel sheet piles;

[0098] Wherein, before the step 230 (driving the steel sheet piles), the method further includes: applying grease to the locking mouth of the steel sheet piles.

[0099] Optionally, the step 250 (removing the steel sheet piles) includes:

[0100] First, use a vibrating hammer to vibrate the locking end of the steel sheet pile to reduce soil adhesion, and then pull out the steel sheet pile while vibrating;

[0101] Alternatively, first use a diesel hammer to vibrate the steel sheet pile down a preset distance (which can be specifically set according to construction needs), and then use a diesel hammer and a vibrating hammer to alternately vibrate and pull out the steel sheet pile.

[0102] Optionally, the step 250 (removing the steel sheet piles) further includes:

[0103] When the top of the steel sheet pile is higher than the foundation bottom plate, stop pulling out and vibrate the steel sheet pile with a vibrating hammer.

[0104] Optionally, the deep foundation pit support method provided in the present application further includes:

[0105] Step 500: using mesh anchor spraying support in the sandy soil area 06 to form a mesh anchor spraying support area 05;

[0106] like Figure 8As shown, the mesh anchor spraying support area 05 includes a fill bottom layer, a primary spraying surface layer, a steel mesh and a secondary spraying surface layer arranged in sequence from the inside to the outside;

[0107] The mesh anchor spraying support area 05 also includes a drainage pipe 08 (passing through the slope 09), a filter screen 11, a metal fence 10 and crushed stone particles 12. One end of the drainage pipe 08 is a fixed end located in the bottom layer of the fill, and the other end of the drainage pipe 08 passes through the primary spraying surface layer, the steel mesh and the re-spraying surface layer in sequence, and the filter screen 11, the crushed stone particles 12 and the metal fence 10 are sequentially coated from the outside to the inside at the fixed end.

[0108] In order to better illustrate the deep foundation pit support method provided by the present application, the present application also provides an application example of the deep foundation pit support method, and the application example is as follows:

[0109] With the rapid economic development in coastal areas, super-large infrastructure projects such as nuclear power plants and large water conservancy facilities are constantly emerging. An important feature of these projects is the need to build large accident pools to deal with emergencies. However, the geological conditions in coastal areas are complex, and the construction technology of deep foundation pit support is difficult. Therefore, the technical summary of "combined support system for deep foundation pits in coastal areas" is of great significance to improving engineering safety and efficiency and ensuring the stable operation of infrastructure in coastal areas.

[0110] Characteristics of the method

[0111] Construction period

[0112] The geological conditions in the pool stone dam area are complex, and interlocking cast-in-place piles are used for support, which shortens the construction period and reduces the accidents caused by the appearance of isolated rocks during the construction process. The sandy area 06 adopts the form of hanging mesh anchor spraying support, which blocks the appearance of quicksand and reduces the probability of slope collapse, thereby reducing the occurrence of repeated slope repairs and shortening the construction period.

[0113] Quality

[0114] The geological survey report provided by the geological survey unit found that there is an original land reclamation rock dam about 200 meters long in the middle of the accident pool from northeast to southwest, and the absolute elevation of the rock dam area is about -2.00 meters to -13.50 meters. Since the geology of the rock dam area is hard and steel sheet pile construction is not possible, the support method in this area is to use interlocking cast-in-place piles. In order to prevent groundwater from flowing into the foundation pit through the gaps at the junction with the steel sheet piles, high-pressure jet grouting piles are selected to fill the gaps. The combination method is "interlocking cast-in-place piles + high-pressure jet grouting piles + steel sheet piles".

[0115] Safety

[0116] The northeast corner of the foundation pit is at the intersection of Yuhua Road 116 and Huanhai Road, and the northwest corner is at the intersection of Yulong Avenue and Yuhua Road 116. Considering that vehicles frequently enter and exit these two places during the construction process, long-term squeezing of the roadbed and uneven force may cause cracks in the road, which in turn affects the stability of the slope, so "steel support + steel sheet pile" is used for support.

[0117] Since the excavation depth of the foundation pit is 5.4 meters to 8.4 meters and the underground soil is mostly sandy, in order to prevent the slope from collapsing during excavation, the entire pool body is supported by "multiple slope reduction + soil nail wall anchor spraying". The fixation of soil nail wall and anchor spraying effectively prevents the occurrence of slope quicksand in the rainy season.

[0118] The total length of the steel sheet pile support is about 753 meters and there is a silt area in the northwest corner of the pool. In order to prevent the soil from exerting lateral pressure on the steel sheet piles and causing them to tilt, a combination of "steel sheet piles and steel waist beams (and anchor cables)" support methods is adopted to effectively ensure the stability of the slope.

[0119] Scope of application

[0120] The support system of "steel sheet pile + steel waist beam + anchor cable + high-pressure jet grouting pile + interlocking cast-in-place pile + anchor spraying net" is suitable for construction areas with various geological conditions, narrow construction working surface, and deep foundation pit construction. During the survey, the groundwater level of Island 2# was measured to be 1.00 to 2.50 meters deep, and the water level elevation was about 0.50m to 0.80m; after the excavation of the foundation pit, the base surface was far below the stable groundwater surface, and the groundwater types were Quaternary pore water, confined water, and bedrock fissure water. The groundwater is relatively abundant and permeable, and the site is close to the sea, with abundant groundwater recharge. Groundwater is an important factor affecting the construction of this project.

[0121] In the middle of the accident pool, there is an original reclamation rock dam about 200 meters long from northeast to southwest, with an elevation of about -2.00 meters to -13.50 meters. Since the geology of the rock dam area is hard and steel sheet piles cannot be constructed, the support method in this area is suitable for construction with interlocking cast-in-place piles. In order to prevent groundwater from flowing into the foundation pit from the gaps in the areas bordering the steel sheet piles, it is suitable to choose high-pressure rotary jet piles for construction to fill the gaps. Since the excavation depth of the foundation pit is 5.4 to 8.4 meters, it is necessary to carry out multiple slope reduction during the excavation of the foundation pit. The soil on site is mostly sandy and has a high water content, so the slope protection is reinforced with wire mesh and anchor spraying. Since the excavation depth exceeds 5 meters and there are structures around the accident pool, in order to prevent the side sliding force of the foundation pit slope protection from causing the steel sheet piles to deform and not play the role of retaining wall, prestressed anchor cables and steel waist beams are selected for reinforcement.

[0122] Principle of Steel Sheet Pile Construction

[0123] Selection and design of steel sheet piles

[0124] According to geological conditions and engineering requirements, select appropriate steel sheet piles and design them. The size and type of steel sheet piles should be determined according to the properties of the soil and load requirements to ensure the strength and stability of the pile body.

[0125] Installation of steel sheet piles

[0126] Insert the steel sheet piles into the soil one by one to form a continuous wall. During installation, vibration pile sinking or driving method can be used, and the appropriate construction method can be selected according to the soil conditions. During the installation process, attention should be paid to the verticality and horizontality of the pile body to ensure the stability and firmness of the pile body.

[0127] Pile connection and support system

[0128] During the construction of steel sheet piles, it is necessary to install the connection between piles and the support system. Adjacent steel sheet piles are connected together through locks to form a continuous wall. At the same time, support systems such as horizontal supports and longitudinal supports are installed as needed to increase the overall rigidity and stability of the pile body.

[0129] Summarize

[0130] The construction principle of Larsen steel sheet piles is based on the principles of soil mechanics and structural mechanics. The key lies in reasonable design and construction technology. Through scientific survey and design, selecting suitable steel sheet piles and performing correct installation and connection, the soil can be effectively supported and fixed. Through reasonable construction and quality control, the safety and stability of the project can be ensured. At the same time, during the construction process, it is necessary to adjust and optimize according to the actual situation to adapt to different geological conditions and engineering requirements.

[0131] Construction principle of bored interlocking cast-in-place piles

[0132] Holes are drilled using rotary drills and impact drills, and the second-order piles are cut between the two existing first-order piles, so that the piles constructed successively are interlocked with each other. The concrete super-slow (more than 60 hours) technology is used to allow the concrete of the piles to solidify into a whole, forming a dense pile wall structure that can bear force together. Therefore, the interlocking piles are also called continuous pile walls.

[0133] Construction principle of high pressure jet grouting pile and jet grouting anchor cable

[0134] Jet-jet piles utilize a drilling rig to place the jet-jet grouting pipe and nozzle at the designed elevation of the pile bottom, and then spray the pre-prepared slurry at high speed through the nozzle on the side of the grouting pipe of the high-pressure generator, forming a liquid flow with highly concentrated energy, which directly destroys the soil. During the spraying process, the drill rod is rotated and lifted at the same time, so that the slurry and soil are fully mixed, forming a columnar consolidation body of a certain diameter in the soil, thereby achieving the effect of foundation reinforcement.

[0135] Anchor spraying network construction principle

[0136] After the excavation of the foundation pit produces an open surface, the side wall soil under the non-support condition will deform under the active earth pressure until it slides and fails. The sprayed anchor mesh support is to use the anchor rods that are deeply fixed outside the soil sliding surface to gradually "sewn up" the cracks of the sliding control surface before the foundation pit side wall has not yet experienced overall sliding and instability, and to closely connect the deformed soil layer medium with the stable medium outside the sliding surface through the anchor rods, the laid steel mesh and the sprayed concrete surface layer, forming an overall self-stabilizing ability. The sprayed anchor mesh support maintains, improves and fully utilizes the inherent mechanical strength of the soil on the side wall of the foundation pit, and changes the soil load into a part of the support structure system, thereby achieving the purpose of safely and economically enclosing the overall stability of the deep foundation pit.

[0137] Steel sheet pile construction plan

[0138] (I) Construction layout and positioning

[0139] 1) Mark the control points in the construction area and effectively protect them after verification.

[0140] 2) Positioning of piles: Mark the specific positions of steel sheet piles in order and mark them with lime lines.

[0141] (II) Lifting and stacking of steel sheet piles

[0142] 1) Lifting of steel sheet piles: Two-point lifting is recommended for loading and unloading of steel sheet piles. When lifting, the number of steel sheet piles lifted each time should not be too many, and care should be taken to protect the lock from damage. There are two lifting methods: bundle lifting and single lifting. Bundle lifting usually uses steel cables for bundling, while single lifting usually uses special lifting equipment.

[0143] 2) Steel sheet pile stacking: The location for steel sheet pile stacking should be selected on a flat and solid site that will not cause significant subsidence and deformation due to weight, and it should be easy to transport to the piling construction site. Pay attention when stacking.

[0144] (III) Steel sheet pile injection

[0145] 1) Before piling, check each steel sheet pile one by one, and remove those with rusted or severely deformed connection locks. Those that fail the test can only be used after repair.

[0146] 2) Before piling, apply grease inside the locking mouth of the steel sheet pile to facilitate driving in and out.

[0147] 3) During the driving process, measure and monitor the slope of each pile at any time to ensure it does not exceed 1%. When the deviation is too large and cannot be adjusted by the pulling method, pull it out and drive it again.

[0148] (IV) Removal of steel sheet piles

[0149] 1) Pile extraction method

[0150] The pile extraction in this project adopts the method of vibratory hammer: the forced vibration generated by the vibratory hammer is used to disturb the soil and destroy the cohesion of the soil around the steel sheet pile to overcome the resistance of pile extraction, and the pile is extracted by relying on the action of additional lifting force.

[0151] 2) Things to note when pulling out piles

[0152] Vibration and pulling: When pulling out piles, you can first use a vibrating hammer to vibrate the locking end of the sheet pile to reduce soil adhesion, and then pull out while vibrating. For sheet piles that are difficult to pull out, you can first use a diesel hammer to vibrate the pile down 100-300mm, and then alternately vibrate and pull out with a vibrating hammer. Sometimes, in order to backfill the soil hole after the pile is pulled out in time, when the sheet pile is pulled out to a height slightly higher than the foundation bottom plate, stop pulling out, vibrate with a vibrating hammer for a few minutes, and try to fill part of the soil hole.

[0153] The crane should be loaded gradually as the vibrating hammer is started. The lifting force is generally slightly smaller than the compression limit of the shock absorber spring.

[0154] The power supply for the vibratory hammer is 1.2-2.0 times the rated power of the vibratory hammer itself.

[0155] For steel sheet piles with large pull-out resistance, the intermittent vibration method is adopted, with each vibration lasting 15 minutes, and the vibration hammer should not exceed 1.5 hours continuously.

[0156] Operation points

[0157] ① Before injecting steel sheet piles, you must be familiar with the conditions of underground pipelines and structures, and carefully lay out the accurate center line of the support piles.

[0158] ② Before piling, check each steel sheet pile one by one, remove those with rust or serious deformation at the connecting lock, and use the unqualified ones only after repair.

[0159] ③ Before piling, apply grease inside the locking mouth of the steel sheet pile to facilitate driving in and out.

[0160] ④ During the driving process, measure and monitor the slope of each pile at any time to ensure it does not exceed 1%. When the deviation is too large and cannot be adjusted by the pulling method, pull up and drive again.

[0161] Bored interlocking piles

[0162] This project adopts The vertical retaining system of bored interlocking cast-in-place piles has an overlap of 250mm between pile A (plain concrete pile) and pile B (reinforced concrete pile). Pile A uses underwater C20 concrete; pile B uses underwater C30 concrete. The thickness of the concrete protective layer of the main reinforcement of pile B is 50mm. The top of the pile enters the ring beam 100mm, and the upper end of the longitudinal reinforcement in the pile is anchored in the ring beam for no less than 35d.

[0163] Construction preparation

[0164] a. Preparation of measuring and setting out equipment

[0165] According to the design drawings, taking into account factors such as construction errors, shotcrete thickness, and enclosure deformation, the interlocking piles were placed 0.15m away. The center coordinates of the bored piles were calculated according to the principle of interval construction, and RTK was used to lay out and arrange the guard piles.

[0166] b. Machine preparation

[0167] Check the electronic control system of the rotary drilling rig, use a plumb line and total station to correct the verticality of the drill rod of the drilling rig, and cross-check with the electronic control system of the drilling rig to ensure that the mechanical properties meet the construction technical indicators.

[0168] c. Mud preparation

[0169] Due to the small construction site and tight construction schedule, the volume of the mud pool for the interlocking piles is based on the requirement that the circulating mud can settle and facilitate the circulation of mud. When the construction of each pile is completed, the waste mud is removed in time and transported to the designated location for discharge at night.

[0170] The mud is made of bentonite and its performance indicators are tested and qualified before use. The mud ratio will be determined according to the geological conditions and the geological requirements during the pile construction process.

[0171] The mud is transported to the construction pile foundation using a horizontal mud pump and a special mud pipeline connected to a hose. During the construction of the rotary drilling rig, the mud carrying slag is pumped out with a mud pump and sent to the sedimentation tank through a hose or a temporary mud drainage ditch. The mud discharged when pouring underwater concrete for the pile foundation and when cleaning the hole and changing the mud is recycled.

[0172] Construction plan

[0173] A. Casing Burial

[0174] The casing is made of 4-8mm thick steel plate. It is generally buried at a depth of 3-4m. The inner diameter is 100-200mm larger than the pile diameter and 0.3m above the ground. First, dig a circular hole 100-200mm larger than the outer diameter of the casing at the pile position. When the geological conditions at the lower end are firm, not sinking, and not seeping water, level and compact the bottom of the pit. Then use the control pile to release the center of the borehole at the bottom of the pit, and then hang the casing into the pit. Use the cross line to determine the center of the casing, and then move the casing. Use the plumb bob to make the center of the casing coincide with the center of the borehole. At the same time, use the plumb bob and level ruler to check and make the casing vertical. It is required that the deviation of the center plane position of the casing along the axis direction is not more than 5cm, the deviation in the vertical axis direction is not more than 3cm, and the inclination deviation is not more than 0.3%. Backfill the area around the casing with clay close to the optimal moisture content. When backfilling, attention should be paid to symmetrical and uniform layered compaction to prevent the casing from tilting.

[0175] B. Drilling rig in place

[0176] The interlocking pile is drilled with a rotary drill and an impact drill. The assembled drilling rig is placed on the hole to be drilled, and the center of the drill bit is precisely aligned with the pile position. The rotary drilling rig uses its own equipment to accurately locate, automatically correct the verticality of the drill hole and automatically measure the depth of the drill hole. During the drilling process, it can control the footage speed and torque according to the changes in the formation. The impact drill uses rtk for line positioning, and after positioning, the drill hammer of the drilling rig is moved to the center of the pile hole.

[0177] C. Drilling

[0178] After the drilling rig is aligned with the pile position, start the mud pump. Drilling can only begin after a certain amount of mud has been input into the hole. Control the drilling speed at the initial stage of drilling, and re-measure the pile position at any time to check the hole diameter, inclination, and stability of the drilling rig to prevent the hole from being skewed. During the drilling process, adjust the drilling speed according to changes in geological conditions and keep drilling records. Different drilling tools are used during rotary drilling construction, and the mud is not circulated. The method of direct excavation is used. The loader receives the soil and then loads it onto the car or transports it to a temporary soil storage yard.

[0179] When encountering a layer prone to collapse, the mud density should be appropriately increased and the drilling speed should be reduced. When drilling to the designed elevation, the hole should be inspected, including the hole position, hole depth, hole diameter and verticality. When drilling, great attention should be paid to mud wall protection, and mud indicators should be adjusted at any time according to geological conditions, and main indicators such as mud density, viscosity and sand content should be measured in a timely manner.

[0180] The drilling operation should be carried out continuously in shifts, paying attention to the changes in soil layers to prevent hole collapse and inclined holes. During the drilling process, the drilling slag should be removed every 2m of drilling or at the place where the soil layers change according to the designed geological data, and detailed records should be made for verification with the designed geological profile.

[0181] D. Lead hole

[0182] If the interlocking pile encounters an underground rock dam during construction, causing the construction to stagnate, it should be reported immediately to the supervisor and the owner, and measures should be taken to guide the hole. A rotary down-the-hole hammer should be used to guide the hole and destroy the underground rock dam obstacle, thereby ensuring the drilling construction of the drilling rig.

[0183] E. One-time hole cleaning

[0184] After the borehole reaches the designed pile bottom elevation, the hole is cleaned once, and the hole is cleaned by high-pressure water jetting. When cleaning the hole, slightly raise the drill hammer to maintain normal circulation of the mud, and press pure mud with a relative density of 1.10 to 1.15 at a medium speed to replace the mud with more suspended drilling debris in the hole, so that the relative density of the mud after cleaning the hole is reduced to 1.15 to 1.20.

[0185] F. Pouring underwater concrete

[0186] The conduit is connected by a threaded conduit that has passed the air tightness test and the pressure bearing test. The conduit length is configured according to the actual measured hole depth, and the connection is ensured to be tight. The conduit (Φ300-400mm) is placed in the center of the pile hole. After the conduit is placed, the hole is cleaned for the second time, and the mud density is controlled at 1.15-1.20. The sediment at the bottom of the hole is checked with a measuring rope to ensure that the sediment thickness is no more than 10cm and meets the pouring standard. The storage hopper uses a conical hopper that matches the conduit, and the volume meets the volume requirements of the first batch of bottom sealing concrete. Before pouring, check the slump of the concrete and re-measure the hole depth. If it meets the requirements, pour the concrete into the storage hopper.

[0187] When the storage hopper is filled with concrete, lift the conduit plug to pour the first batch of concrete. After the first batch of concrete is poured, the buried depth of the conduit shall not be less than 0.8m. The water head in the hole should be maintained during the pouring process. The position of the concrete surface in the hole should be measured frequently according to the volume of poured concrete, and the buried depth of the conduit should be adjusted in time to control the buried depth of the conduit within 2 to 6m. The pouring process should be continuous and uninterrupted, and the final poured concrete should be 0.8 to 1.0m higher than the designed pile top to ensure that the concrete on the pile top is dense.

[0188] When constructing the intermediate reinforced concrete piles, the guide tube is lowered after the steel cage is placed after the hole is cleaned once, and the rest of the process is the same as the plain concrete pile construction.

[0189] G. The interlocking piles should be tested first and the on-site conditions should be analyzed. If the gaps between the cofferdam and the stone dam are large, the length of the casing should be lengthened accordingly to prevent leakage and ensure the pile effect.

[0190] H. The length of the interlocking cast-in-place piles in this project is divided into two types according to the support type:

[0191] The pile bottom elevation is -14.1m, and the pile top elevation is 0.9m (support type: interlocking cast-in-place piles + anchor cables + concrete cap beams).

[0192] The pile bottom elevation is -19.1m, and the pile top elevation is 0.9m (support type: interlocking cast-in-place piles + concrete cap beam).

[0193] After the interlocking cast-in-place pile is dug out, a reinforced concrete crown beam should be constructed on its top, and the steel bars of the interlocking cast-in-place pile should be anchored into the crown beam 5 cm.

[0194] Operation points

[0195] 1. Key points of drilling holes for rotary bored piles

[0196] Static mud ratio

[0197] In rotary drilling, static mud serves as a stabilizing fluid in the drilling process and its main function is to protect the wall.

[0198] The mud can form a thin layer of mud skin on the hole wall, which prevents water from penetrating from the inside to the outside or from the outside to the inside. According to the geological conditions of this project, the mud ratio is dynamically adjusted during construction, the mud specific gravity is controlled, the mud powder quality is improved, the viscosity and lubricity are increased, and the treatment agent is appropriately added to enhance the flocculation ability to ensure the thickness and strength of the wall mud skin. When the mud is injected for the first time, it should be vertically impacted downward in the middle of the pile hole as much as possible to prevent the mud from flowing down along the side wall of the casing and collapsing the root of the casing, causing the base soil at the root of the casing to become soft. Before formal drilling, pour in 2 to 3 bags of bentonite, start the high-speed soil throwing function of the drilling rig, and stir it fully to increase the content of bentonite and increase the thickness of the wall mud skin at the junction of the bottom of the casing and the base soil to prevent leakage and collapse of the hole during drilling.

[0199] Casing burial

[0200] Surveyors should re-measure control points regularly. After the pile position is marked out on site, they should immediately bury the pile guard and casing. Ensure that the center point of the casing coincides with the center point of the pile guard. Use a plumb line to check the verticality of the casing and ensure that it meets the requirements.

[0201] The casing is made of 4-8mm steel plate curled up. The inner diameter of the casing is large and can store enough mud. When the drill rod is pulled out of the pile hole, the water pressure in the casing can be ensured to maintain the stability of the mud skin on the hole wall. The single-side clearance of the casing reaches more than 100mm, which can effectively prevent the collision and scraping of the casing during the lifting process of the rotary bucket and protect the stability of the hole mouth. When the casing is buried, it is buried and compacted in layers to improve the bonding between the casing and the soil, enhance the ability to resist external vibration and impact, prevent water seepage and leakage when grouting or lifting the rotary bucket, and effectively reduce the probability of hole mouth collapse.

[0202] The structure of the rotary bucket

[0203] The rotary bucket adopts a double-bottom rotary bucket, and the side wall is welded with a guide groove to facilitate the guidance in the pile hole and the diversion of mud, reducing the negative pressure in the pile hole. At the same time, the chassis is welded with side teeth to properly control the distance between the rotary bucket and the knife tip to prevent the rotary bucket from damaging the hole wall when it is raised and lowered.

[0204] Drilling rig control

[0205] When drilling, ensure that the position of the rotary drilling rig is stable. If the position of the drilling rig is unstable due to backfilling of the exploration pit or other problems, a 3cm thick steel plate should be laid under the drilling rig to prevent the drilling rig from tilting due to the tilt of the body during the drilling process.

[0206] During the drilling process, the bottom door of the rotary bucket must be kept closed to prevent sand or clay in the rotary bucket from falling into the wall-protecting mud and destroying the mud ratio; the drilling scale must be strictly controlled in each working cycle to avoid drilling accidents; at the same time, the lifting speed of the rotary bucket should be properly controlled, generally maintained at 0.75-0.85m / s. If the lifting speed is too fast, the mud will flow between the rotary bucket and the hole wall at high speed, scouring the hole wall and destroying the mud skin, which is not conducive to the stability of the hole wall and easily causes collapse. During the drilling process, the drilling parameters should be adjusted according to different geological conditions to ensure smooth drilling construction.

[0207] High pressure jet grouting pile

[0208] High-pressure jet grouting piles use double pipes, with a pile diameter of 600 mm, a pile length equal to the length of the underground part of the Larsen steel sheet pile and the interlocking pile, and a center distance of 400 mm. Cement uses PO42.5 ordinary cement, with a water-cement ratio of 1:1, and a cement dosage of no less than 450 kg per cubic meter. The grouting pressure is greater than 28 MPa, the rotation speed is 20 r / min, and the lifting speed is 0.18 m / min.

[0209] Construction preparation

[0210] Site leveling and layout

[0211] The construction site of the mixing pile should be leveled before the machinery and equipment enter the site. When the surface of the site is hard and water injection pre-mixing is required, drainage ditches should be dug around and water collection wells should be set up. The location should not affect the construction of the mixer. Sedimentation and debris should be removed from the drainage ditches and water collection wells regularly to keep the water flowing smoothly.

[0212] When the ground is too soft to be conducive to the movement of the mixer, a coarse sand or fine stone cushion layer should be laid, and coarse-grained gravel should not be used for paving.

[0213] The mortar preparation shed should have sufficient area and be located so that the horizontal pumping distance of the mortar can be controlled within 50m.

[0214] Pile position measurement and positioning

[0215] According to the coordinate points provided by the construction unit and the enclosure design drawings, the axis of the cement mixing pile is laid out and the pile position is located. The stakes are driven into the soil at each stakeout base point. The stakes are surrounded by bricks to form a square, filled with concrete, and the base points are marked on the stakes, nailed with iron nails, and painted red. The stakes in the field are laid out according to the base points, and the center points of each stake are driven into the soil with steel bars painted with red paint. After the stake position is laid out, a second re-measurement is carried out. After it is accurate, please have the representatives of Party A and the supervision party inspect and accept it and keep the measurement and layout records.

[0216] Cement mixing pile technical parameters and process trial pile

[0217] A. Most of the water-stop curtains in this project are made of Φ600 ordinary cement mixing piles and #425 ordinary Portland cement. The cement consumption of the water-stop curtain is 450kg / m3, and the water-cement ratio is 0.5.

[0218] B. The purpose of trial pile driving is to calibrate various construction technical parameters, including: the drilling depth of the mixer, the elevation of the pile bottom, the elevation of the pile top or the mortar stopping surface; the water-cement ratio of the mortar, the formula of the admixture; the rotation speed and lifting speed of the mixer; the pressure of the mortar pump; the mortar delivery per meter of pile length or each pile, and the time it takes for the mortar to reach the spraying port through the mortar delivery pipe; whether re-mixing and re-spraying is required and its location and depth, etc.

[0219] Construction technology

[0220] (1) Positioning the drilling rig. Move the jet grouting machine to the designated pile position, align the drill bit with the center of the hole, and level the drilling rig, placing it stable and horizontally, with the verticality deviation of the drill rod no greater than 1% to 1.5%. After positioning, first conduct a low-pressure (0.5MPa) water jet test to check whether the nozzle is unobstructed and the pressure is normal.

[0221] (2) Prepare cement slurry. When the pile driver is moved, start mixing cement slurry according to the designed mix ratio. First, add water into the bucket, then pour in cement and admixtures, start the mixer and stir for 10 to 20 minutes, then unscrew the valve at the bottom of the mixing bucket, put in the first screen (pore size 0.8mm), filter it into the slurry pool, and then pump it into the second filter (pore size 0.8mm) through the mud pump. After the second filtration, it flows into the slurry bucket and is ready for use when grouting.

[0222] (3) Insertion (double pipe method). When using rotary jet grouting pipe for drilling, the two processes of drilling and inserting can be combined into one. When the first stage is penetrated into the soil, it can be penetrated by the jet or vibration of the jet pipe itself. The process is: start the drilling rig, and at the same time start the high-pressure mud pump to deliver cement slurry at low pressure, so that the drill rod vibrates along the guide frame and sinks by jetting into holes; until the pile bottom is designed elevation, observe that the working current should not be greater than the rated value.

[0223] (4) Lift the grouting pipe and stir. After the grouting pipe sinks to the designed depth, stop drilling and keep rotating. The pressure of the high-pressure mud pump increases to the construction design value (20-40MPa). After 30 seconds of bottom spraying, spray and rotate at the same time. At the same time, lift the drill rod strictly according to the lifting speed determined by the design and test pile (set according to specific needs). If it is a double-tube method or triple-tube method, after reaching the designed depth, connect the high-pressure water pipe and air compressor pipe, start the high-pressure clean water pump, mud pump, air compressor and drilling rig to rotate, and use instruments to control the pressure, flow and air volume. When they reach the predetermined values, start lifting, continue to spray and lift until the expected reinforcement height is reached and stop.

[0224] (5) Treatment of the pile head. When the jet spray pipe is lifted close to the pile top, it should be lifted slowly from 1.0m below the pile top, and the jet spray should be continued for a few seconds, then slowly lifted upward by 0.5m until the grouting surface at the pile top stops. The head of the interlocking cast-in-place pile is reinforced with a C30 concrete cap beam to increase its integrity.

[0225] (6) If gravel is encountered, spraying and mixing can be repeated to ensure the pile diameter: repeat the spraying and mixing according to the above steps 4 to 6 until the spraying pipe is lifted to the stop surface, turn off the high-pressure mud pump (clean water pump, air compressor), stop the delivery of cement slurry (water, air), rotate the rotary spraying pipe and lift it out of the ground, and turn off the drilling rig.

[0226] (7) Cleaning. Pour an appropriate amount of clean water into the slurry tank, turn on the high-pressure pump, and clean the remaining cement slurry in all pipelines until they are basically clean. Also clean the soil adhering to the spraying pipe head.

[0227] (8) Shifting: Move the pile driver to construct the next pile.

[0228] Operation points

[0229] When the drilling rig or rotary jet machine is in place, the seat should be stable, the vertical shaft or turntable should be aligned with the hole position, and the inclination angle should not exceed 0.5° compared with the design error.

[0230] Before jet grouting, the high-pressure equipment and pipeline system must be checked. The pressure and displacement of the equipment must meet the design requirements. The sealing ring of the pipeline system must be in good condition. There must be no debris in each channel and nozzle.

[0231] When spraying grouting, you must pay attention to preparation, start the grouting pump, and wait until the front of the cement slurry is estimated to have flowed out of the nozzle before starting to lift the grouting pipe. Spray grouting from bottom to top.

[0232] When jet grouting, the start-up sequence must also comply with the provisions of Article 3. At the same time, the hole section where the jet grouting hole is started should overlap with the previous section by 0.1m to prevent the consolidation body from being disconnected.

[0233] After the jet grouting operation, due to the water separation effect of the slurry, there is generally varying degrees of shrinkage, resulting in pits on the top of the solid body. Therefore, it is necessary to promptly use cement slurry with a water-cement ratio of 0.6 to 1 for supplementary grouting, and prevent the entry of soil or debris discharged from other boreholes.

[0234] In order to increase the size of the consolidated body, or to avoid the reduction of the size of the consolidated body in deep hard soil, measures such as increasing the injection pressure, pump volume or reducing the rotation and lifting speed can be adopted, and the double injection process can also be used.

[0235] Prestressed jet grouting anchor cable construction

[0236] Construction method

[0237] A special drilling rig is used to drill holes for jet grouting anchor cables. The hole diameter is based on the design drawings. Anchor reinforcement construction should be closely coordinated with excavation. Before formal construction, the excavation depth should be 30cm higher than the reinforcement pile elevation and the width should be no less than 6 meters.

[0238] The construction process of jet-sprayed anchor cable is to form piles by drilling, reinforcing bars, and mixing and grouting. Cement slurry is jetted inward from the hollow hole of the drill rod, with a cement content of 20%, a water-cement ratio of 0.7 (adjustable according to the on-site soil conditions), and a pressure of 25-30MPa (determined by test piles); through the hollow channel of the drill rod, the steel strand and anchor head structure are brought to the designed depth while drilling.

[0239] Before constructing the purlin, the PVC hose should be tied on the steel strand. The lower part of the PVC hose should be inserted into the cement soil pile for 200mm. Each steel strand is made of 7 steel wires, and the length of 700mm exposed outside the steel pad is convenient for tensioning. The steel strand should pass through the steel pad of the purlin to form a 90-degree angle with it. It is required to open 3 16mm round holes at the corresponding positions of the steel pad, lead the steel strands out of the round holes, and lock the steel strands with anchors after the strength of the top beam and the stiffening pile reaches 75% of the design strength. The tensioning adopts a high-pressure oil pump and a 100-ton through-hole jack. Before formal tensioning, pre-tension it twice with 20% locking load, then tension it in stages with 50% and 100% locking loads, and then tension it to 110% design load. Keep it under the over-tension load for 5 minutes, and lock the load again after observing that there is no displacement of the anchor head. The locking tension is 60% of the internal design value, and the locking tension of the upper anchor pile can be appropriately increased.

[0240] During the earthwork excavation process, collision with the steel strands must be prevented. The reinforced cement soil pile anchor construction must be excavated in sections and layers, and the section length should not be greater than 20m. When the lower layer of earthwork is excavated, the upper layer of the inclined anchor pile must have a curing time of more than 14 days and be tensioned and locked. The excavation depth of each layer should not exceed 300mm below the anchor pile.

[0241] The waist beam is made of double-jointed channel steel and several flat irons. When the waist beam is butt-welded, the distance between the connecting welds of the two channel steels should not be greater than 2mm.

[0242] According to the different sites and geology, anchor cable construction can be divided into three categories:

[0243] The first type of anchor cable is located in section 1: anchor cable spacing is 1.6m, steel strand length is 20m, inclination angle is 40°, tensile strength is 291KN, and free end length is 6.5m.

[0244] The second type of anchor cable is located in section 1A: anchor cable spacing is 2m, steel strand length is 25m, inclination angle is 35°, tensile strength is 308KN, and free end length is 6.5m.

[0245] The third type of anchor cable is located in section 4: anchor cable spacing is 1.5m, steel strand length is 25m, inclination angle is 35°, tensile strength is 268KN, and free end length is 7.5m.

[0246] Construction technology

[0247] (1) Positioning

[0248] After the trench is excavated, the elevation should be measured and the retaining piles should be marked with a line. The drilling rig should be positioned accurately, the base should be leveled, and the inclination angle of the drill rod should be checked with a compass. The angle deviation should not exceed 3 degrees and the height difference should not exceed 5 cm. Drainage ditches and circulating slurry pools should be dug on site before drilling to avoid affecting construction due to random discharge of slurry.

[0249] (2) Anchor cable cutting

[0250] The anchor cable uses φ15.2 steel strands. During construction, the steel strands must be straightened first, and then cut according to the anchor cable length L=L1+0.7m (L1 is the final hole length). The steel strands must be cut with a cutting machine, and electric or gas welding is not allowed to avoid damaging the steel strands.

[0251] (3) Anchor reinforcement production

[0252] Carry out strict quality inspection on the steel strands that have been derusted and degreased. If they meet the requirements, measure the lengths of the anchor section and the tensioning section according to the design, mark them and group them. Set an isolation centering bracket every meter on the anchor section. The centering bracket should ensure that the thickness of the grouting cover layer of the anchor body at its location is ≥10mm, and the surface of the centering bracket is basically smooth to avoid damaging the steel strands. In soft formations, in order to prevent the centering bracket from sinking into the hole wall and increase the contact area between the bracket and the hole wall, the two centering brackets are tied tightly with wire. Evenly apply butter on the surface of the tensioning section anchor as a rust inhibitor, then wrap it tightly with asphalt hemp tendons, put it into a Ф500mm PVC casing, plug the two ends with asphalt cotton yarn and seal it with tape. Finally, install the guide cap on the anchor head.

[0253] (4) Hole formation

[0254] Drilling is a key process to control the construction period in anchor cable construction. To ensure the drilling efficiency and quality, the MD50 anchor cable drilling rig is used for drilling. When the drilling rig is drilling, the drill rods required for drilling are neatly arranged according to the designed length of the anchor cable. When the drill rods are used up, the hole depth is just right. The drilling depth should exceed the designed length of the anchor cable by about 0.5m. After the drilling is completed, the drill rods and drilling tools are pulled out one by one, and the impactor is cleaned and ready for use.

[0255] (5) Anchor cable installation

[0256] The assembled anchor cable is manually lifted to the site. Before installing the anchor cable body, the anchor hole number is carefully checked again. After confirmation, the hole is blown with high-pressure air, and the anchor cable body is slowly placed into the hole. The length of the steel strand exposed outside the hole is measured with a steel ruler, and the length of the anchor cable in the hole is calculated (the error is controlled within 50mm) to ensure the anchoring length. The grouting pipe is installed at the same time as the anchor cable, passing through the central steel pipe of the isolation bracket, with the pipe mouth 30 to 50cm away from the bottom of the hole.

[0257] (6) Anchor grouting

[0258] The anchor grouting method adopts the exhaust grouting method. For the downward-inclined hole, the grouting pipe is inserted to the bottom of the hole, the mortar is injected from the bottom of the hole, and the air is discharged from the anchor hole; for the upward-inclined and horizontal holes, the mortar is injected from the hole mouth, the air is pressed to the bottom of the hole, and the air enters the exhaust pipe from the bottom of the hole and is discharged out of the hole (for horizontal anchor cables, the air enters the exhaust pipe through the slurry limiting ring). During the grouting process of the upward-inclined and horizontal anchor cable holes, when the exhaust pipe is no longer exhausted and thin cement slurry is pressed out of the exhaust pipe, it means that the grouting is full. For the downward-inclined anchor cable grouting, the mortar position indicator is used to control the grouting position. The anchor cable hole grouting adopts a grouting machine, and the grouting pressure is maintained at 0.3-0.6MPa.

[0259] (7) Waist beam construction

[0260] The waist beam of this project adopts two 25a channel steels, which are connected and welded together with steel plates. Steel concrete anchor piers are used at the joints between the retaining piles and the waist beam to ensure that the waist beam is close to the vertical retaining piles. 150×176×20 steel plate gaskets are used between the anchor and the waist beam; 300×300×20 steel plates are used as pads between the waist beam and the anchor, which are welded to the channel steel waist beam.

[0261] (8) Tensioning and locking

[0262] The anchor bar tensioning and locking is tensioned after the anchor bar reaches 75% of the design strength. The anchor is a QVM series anchor, which is locked with a YC-100 core-through jack and an electric oil pump. The locking and tensioning equipment is calibrated in advance, and the reading of the oil pressure gauge is converted into tensioning pressure for control. Before formal tensioning, pre-tensioning is performed once with a 20% locking load, and then tensioning is performed in stages with 50% and 100% locking loads, and then over-tensioning is performed to 110% locking load, and maintained for 5 minutes under the over-tensioning load. After observing that there is no displacement of the anchor head, it is locked at 65% of the locking load. If the requirements are not met, piles should be added nearby.

[0263] Operation points

[0264] a. Before drilling, lay out the holes according to the construction drawing and make marks;

[0265] b. The selection of drilling tools should meet the design parameter requirements of the support design;

[0266] c. The reinforcement of the jet-sprayed anchor pile adopts Φ15.2 steel strands, and the drilling angle is in accordance with the design requirements. The construction is strictly carried out in accordance with the drilling angle, pile length and pile diameter required by the design;

[0267] d. The tendons should be placed in the center of the pile;

[0268] e. Anchor bars should be locked on the purlin;

[0269] f. The grouting material shall be 42.5 grade ordinary Portland cement paste with a water-cement ratio of 0.7; the cement paste shall be mixed evenly with a dosage of 20% and used immediately after mixing. The cement paste mixed once shall be used up before initial setting;

[0270] g. Spin-jet stirring pressure: 25-30 MPa;

[0271] (7) Construction parameters of jet grouting anchor piles;

[0272] a. The diameter of the construction pile shall not be less than the design requirements; the length of the construction pile shall not be less than the design requirements;

[0273] b. The drilling speed of the drill pipe is 0.3-0.5m / min, the lifting speed is 0.5-0.6m / min, and the error is ±10cm / min; the drill pipe speed is 20-50r / min; the pump pressure is 25-30Mpa. The specific parameters need to be determined according to the field test.

[0274] Hanging mesh anchor spraying construction

[0275] Construction technology

[0276] Layered excavation: Carry out layered excavation and slope according to the requirements of the drawings.

[0277] Slope repair: Remove isolated rocks and loose soil on the slope to keep it relatively flat.

[0278] Initial spraying of concrete: Before spraying concrete, the drainage holes must be protected to ensure smooth drainage after spraying. Before spraying, signs to control the spraying thickness must be set up on the sprayed surface. The spraying should be carried out in sections and pieces from bottom to top, first concave and then convex, and no leaks should be allowed.

[0279] Laying steel mesh: The specifications of the steel mesh are φ4×100×200.

[0280] The surface layer is sprayed with 40mm concrete and the concrete strength is C20.

[0281] Operation points

[0282] When excavating the soil, it should be done in layers and sections. After the shotcrete surface layer reaches 70% of the design strength, the lower soil and the lower soil nails can be excavated. The excavation depth of each layer shall not exceed 0.5m of the soil nails. The horizontal section length can be selected from 10m to 20m according to the construction capacity. When encountering right angles, try to dig into rounded corners to prevent stress concentration.

[0283] Sprayed concrete operations shall comply with the following provisions:

[0284] 1) The spraying operation should be carried out in sections. The spraying sequence in the same section should be from bottom to top, and the thickness of one spraying should be 40mm;

[0285] 2) When spraying concrete, the nozzle should be kept vertical to the sprayed surface, and the distance should be 0.6 to 1.0m;

[0286] 3) After 2 hours of final setting, the shotcrete should be sprayed with water for curing. The curing time is determined according to the temperature and should be 3 to 7 hours.

[0287] The laying of steel mesh in the shotcrete surface layer shall comply with the following provisions:

[0288] 1) The steel mesh should be laid after the first layer of concrete is sprayed, and the surface steel mesh should be arranged in a steel mesh grid.

[0289] 2) The steel mesh and the short steel bars of the soil nails should be firmly connected.

[0290] 3) During construction, bricks can be placed behind the steel mesh or short steel bars can be inserted for fixing. The overlap length of the mesh connection should not be less than 200mm.

[0291] After the soil excavation is completed, the next process should be implemented immediately to shorten the exposure time of the pit wall as much as possible. The exposure time should not exceed 24 hours. The last layer of excavation should be reserved for 0.3m and removed manually to prevent the original soil from being damaged.

[0292] The concrete surface layer is 80mm thick, with a mix ratio of cement: gravel: sand = 1:2:2. The required strength is C20, and appropriate amounts of admixtures are added to facilitate on-site construction and ensure that the strength after 3 days is not less than 6MPa.

[0293] A horizontal drainage pipe should be installed at an appropriate position on the back of the soil nail spraying surface layer. The pipe diameter should not be less than 50mm, and a wrapped filter screen should be installed to drain the accumulated water behind the concrete surface layer, mainly the 1st layer of fill.

[0294] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present application, rather than to limit it. Although the present application has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present application.

Claims

1. Deep foundation pit support method, It is characterized in that include: In geologically hard areas, interlocking cast-in-place pile support is used to form interlocking cast-in-place pile support areas; Steel sheet pile support is used in the silt area to form a steel sheet pile support area; High-pressure jet-jet pile support is also used at the intersection of the interlocking cast-in-place pile support area and the steel sheet pile support area.

2. The deep foundation pit supporting method according to claim 1, It is characterized in that The high-pressure jet grouting pile support is also used at the intersection of the interlocking cast-in-place pile support area and the steel sheet pile support area, including: Drilling rig positioning; preparing cement slurry; Intubation; Lifting the shotcrete pipe and stirring; and, partial treatment of the pile head; Among them, the lifting of the shotcrete pipe and stirring include stopping drilling and continuing to rotate after the shotcrete pipe sinks to a preset depth, and after the shotcrete is sprayed for a preset time, lifting the drill rod at a preset lifting speed.

3. The deep foundation pit supporting method according to claim 2, It is characterized in that After the pile head is processed, the method further comprises: Use cement slurry with a water-cement ratio of 0.6 to 1 for supplementary filling.

4. The deep foundation pit supporting method according to claim 1, It is characterized in that It also includes the use of prestressed rotary jet anchor cables for construction at the intersection of the interlocking cast-in-place pile support area and the steel sheet pile support area.

5. The deep foundation pit supporting method according to claim 4, It is characterized in that The prestressed jet-sprayed anchor cable construction includes: to form a hole; Anchor cable installation; Anchor grouting; Waist beam construction; and, tensioning and locking; Among them, the waist beam construction includes: the waist beam adopts two channel steels connected and welded together with iron plates, and steel concrete anchor piers are used at the joints between the retaining piles and the waist beam to make the waist beam close to the vertical retaining piles. The anchor and the waist beam are separated by steel plate gaskets, and steel plates are used as pads between the waist beam and the anchor, and the pads are welded to the waist beam.

6. The deep foundation pit supporting method according to any one of claims 1 to 5, It is characterized in that The method of using interlocking cast-in-place piles to support in a geologically hard area to form an interlocking cast-in-place pile support area includes: Casing burial; The drilling rig is in place; and, drilling rigs; Wherein, while the drilling rig is drilling, mud wall protection is adopted; The mud wall protection comprises: when the mud is injected for the first time, the mud is made to impact vertically downward in the middle of the pile hole.

7. The deep foundation pit supporting method according to any one of claims 1 to 5, It is characterized in that The method of using steel sheet pile support in the silt area to form a steel sheet pile support area includes: Excavation of the first slope of the foundation pit; Positioning and laying out of steel sheet piles; Driving steel sheet piles; Backfilling of foundation pit; and, removal of sheet piles; Wherein, before the steel sheet piles are driven, the method further includes: applying grease inside the locking mouth of the steel sheet piles.

8. The deep foundation pit supporting method according to claim 7, It is characterized in that The removal of the steel sheet piles comprises: First, use a vibrating hammer to vibrate the locking end of the steel sheet pile to reduce soil adhesion, and then pull out the steel sheet pile while vibrating; Alternatively, first use a diesel hammer to vibrate the steel sheet pile down a preset distance, and then use the diesel hammer and vibratory hammer to alternately vibrate and pull out the steel sheet pile.

9. The deep foundation pit supporting method according to claim 7, It is characterized in that The removing of the steel sheet piles further comprises: When the top of the steel sheet pile is higher than the foundation bottom plate, stop pulling out and vibrate the steel sheet pile with a vibrating hammer.

10. The deep foundation pit supporting method according to any one of claims 1 to 5, It is characterized in that Also includes: In the sandy soil area, mesh anchor spraying support is used to form a mesh anchor spraying support area; The mesh anchor spraying support area includes a fill bottom layer, a primary spraying surface layer, a steel mesh and a secondary spraying surface layer arranged in sequence from the inside to the outside; The hanging mesh anchor spraying support area also includes a drainage pipe, a filter mesh, a metal fence and crushed stone particles. One end of the drainage pipe is a fixed end located in the bottom layer of the fill, and the other end of the drainage pipe passes through the primary spraying surface layer, the steel mesh and the re-spraying surface layer in sequence, and the filter mesh, crushed stone particles and the metal fence are sequentially covered from the outside to the inside at the fixed end.