Assembly type reinforced concrete foundation pit supporting system convenient to disassemble and disassembling method
By designing a prefabricated reinforced concrete foundation pit support system that is easy to dismantle, and using the design of insertion bars and rope holes, the foundation pit supports can be quickly dismantled, which solves the problem of the long construction and demolition process of cast-in-place reinforced concrete foundation pit supports. , problems of high cost and large environmental impact, and improved resource utilization and construction efficiency.
Patent Information
- Application Number
- CN202411214352.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-31
- Publication Date
- 2024-10-01
AI Technical Summary
The cast-in-place reinforced concrete foundation pit support has problems such as long time, high cost, large environmental impact, and waste of resources during the construction and demolition process. It is especially difficult to dismantle during construction in central urban areas, affecting the environment and economic benefits.
A prefabricated reinforced concrete foundation pit support system is designed that is easy to dismantle. The foundation pit support beam segments and splayed beams are spliced to form an internal support system. Quick dismantling is achieved through preset reinforcement holes and rope threading holes, and wire saws are used for cutting. and machinery to perform low-cost, low-environmental-impact demolition operations.
It shortens the construction time of foundation pit support, achieves efficient recycling, reduces demolition costs and environmental impact, improves resource recycling rate, and reduces construction site occupation and noise and dust pollution.
Smart Images

Figure CN118727775A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of construction engineering, and in particular to an easily dismantled assembled reinforced concrete foundation pit support system and a dismantling method. Background Art
[0002] In large-scale foundation pit projects, reinforced concrete foundation pit support is an important measure to ensure that the foundation pit does not deform or collapse. In the project, large foundation pits mostly use underground continuous walls or support piles in combination with cast-in-place reinforced concrete internal supports to achieve the support purpose. However, cast-in-place reinforced concrete internal supports have many disadvantages: 1. The construction process of reinforced concrete internal supports includes steps such as steel bar binding, formwork installation, concrete pouring and maintenance. These steps require a long construction time, which affects the progress of the project and increases the cost of the project. 2. The construction of reinforced concrete internal supports requires a large site for operations such as steel bar processing, formwork making and concrete pouring, and the construction site requirements are high. In a small construction site or in the central area of the city, construction organization and site layout are difficult. 3. It is difficult to dismantle the reinforced concrete internal support after the project is completed. The dismantling process requires a large amount of mechanical equipment and manual operation, which is time-consuming and costly. At the same time, the dismantling process will generate a large amount of construction waste, which needs to be processed and transported, increasing the construction cost and environmental pressure. 4. Whether it is mechanical demolition or blasting demolition, the noise, dust and construction waste generated by the reinforced concrete internal support during the demolition construction process have a great impact on the surrounding environment. Especially when constructing in the central area of the city, additional environmental protection measures need to be taken, which increases the cost of demolition construction and the difficulty of management. 5. Most of the reinforced concrete waste after demolition has a low reuse value and can only be treated as construction waste, which wastes resources. In order to overcome the above shortcomings of the cast-in-place reinforced concrete foundation pit support system, new foundation pit support technology needs to be developed urgently. Summary of the invention
[0003] The purpose of the present invention is to overcome the shortcomings of the prior art and to provide an easy-to-dismantle assembled reinforced concrete foundation pit support system and a dismantling method. At the beginning of the design, the present invention fully considered the dismantling and recycling of the foundation pit support. By applying assembled foundation pit support beam sections and foundation pit support eight-shaped beams to the foundation pit support, the present invention significantly shortens the construction time of the support in the foundation pit and realizes the efficient recycling of the internal support. In the early stage of the design and construction of the crown beam and the waist beam, the present invention took into account the convenience of dismantling. By pre-setting the rope threading holes for rope saw cutting in the crown beam or the waist beam, it is possible to achieve a drilling-free, low-cost, low-environmental-impact and efficient dismantling effect during rope saw cutting and dismantling.
[0004] The technical solution of the present invention to solve the above technical problems is as follows: The assembled reinforced concrete foundation pit support system which is easy to dismantle comprises an internal support system, a crown beam, a waist beam and a steel lattice column, and is characterized in that: the internal support system is formed by splicing a plurality of foundation pit support beam sections and a plurality of foundation pit support eight-shaped beams, the plurality of foundation pit support beam sections have the same length and cross-sectional dimensions, and the plurality of foundation pit support eight-shaped beams have the same length and cross-sectional dimensions; a beam sleeve is provided on the surface of the foundation pit support beam section, a side steel plate is provided on the beam sleeve, the pipe walls at both ends of a preset transverse embedded pipe are respectively welded to the hole walls of the side steel plates on both sides to form transverse reinforcement holes, end face steel plates are provided at both ends of the foundation pit support beam section, the pipe wall at one end of a preset longitudinal embedded pipe is welded to the inner wall of the hole of the end face steel plate to form a longitudinal reinforcement hole, one end of the foundation pit support eight-shaped beam is a right-angle end, and the other end is an oblique angle end, the surface of the foundation pit support eight-shaped beam is provided with an eight-shaped beam sleeve, and the oblique angle end is provided with an eight-shaped beam reinforcement hole; When two foundation pit support beam sections are axially connected, the end face steel plates of the two foundation pit support beam sections are seamlessly fitted, the longitudinal reinforcement holes of the two foundation pit support beam sections are aligned one by one, and there are connecting steel bars in the longitudinal reinforcement holes; when four foundation pit support beam sections are cross-connected or three foundation pit support beam sections are T-connected, after the two foundation pit support beam sections are axially connected, they are vertically intersected with another one or two foundation pit support beam sections at the axial connection. At the vertical intersection, the longitudinal reinforcement holes of one or two foundation pit support beam sections are aligned one by one with the transverse reinforcement holes at the axial connection of the two foundation pit support beam sections, and there are connecting steel bars in the transverse reinforcement holes; The connection between the foundation pit support beam section and the foundation pit support eight-shaped beam includes that after the two foundation pit support beam sections are axially connected, they are butted with the beveled end of the foundation pit support eight-shaped beam at the axial connection, and at the connection between the foundation pit support beam section and the foundation pit support eight-shaped beam, the eight-shaped beam reinforcement holes are aligned with the transverse reinforcement holes at the axial connection of the two foundation pit support beam sections, and there are connecting steel bars in the transverse reinforcement holes; The foundation pit is provided with a crown beam and a waist beam, and a pedestal and a corbel are provided on the crown beam and the waist beam. The foundation pit supporting beam section at the edge of the internal support system and one end of the foundation pit supporting S-shaped beam are placed on the pedestal, and a jack is arranged between the internal support system and the crown beam or the waist beam, and the jack is placed on the pedestal; a tray is arranged below the connection of the foundation pit supporting beam section, and the bottom of the tray is welded to the steel lattice column.
[0005] Based on the above technical solution, the present invention can also be improved as follows.
[0006] Preferably, the foundation pit support beam section has two rows of longitudinal reinforcement holes and one row of transverse reinforcement holes; the distance between the two rows of longitudinal reinforcement holes is equal to twice the distance between the transverse reinforcement holes and the end steel plate, the vertical spacing between adjacent longitudinal reinforcement holes or transverse reinforcement holes is the same, and the distance between the uppermost longitudinal reinforcement hole and the upper edge of the beam sleeve is equal to the distance between the lowermost transverse reinforcement hole and the lower edge of the beam sleeve; The spacing between the two rows of S-beam rebar holes is equal to twice the distance between the transverse rebar holes and the end steel plate of the foundation pit supporting beam section. The distance from the top S-beam rebar hole to the upper edge of the foundation pit supporting S-beam is equal to the distance from the top transverse rebar hole to the upper edge of the foundation pit supporting beam section. The spacing between vertically adjacent S-beam rebar holes is the same as the spacing between vertically adjacent transverse rebar holes.
[0007] Preferably, the diameters of the transverse reinforcing bar insertion holes, the longitudinal reinforcing bar insertion holes and the S-beam reinforcing bar insertion holes are the same.
[0008] Preferably, a first rope threading hole for rope saw cutting is provided on the crown beam, and the first rope threading hole is formed by an L-shaped PVC pipe pre-buried in the crown beam, and both ends of the L-shaped PVC pipe are open, one end opening is located on the side of the crown beam, and the other end opening is located on the top surface of the crown beam; a second rope threading hole for rope saw cutting is provided on the waist beam, and the second rope threading hole is formed by a straight PVC pipe vertically pre-buried in the waist beam, and both ends of the straight PVC pipe are open, one end opening is located on the top surface of the waist beam, and the other end opening is located on the bottom surface of the waist beam, and the straight PVC pipe is pre-buried on the side of the waist beam close to the supporting pile.
[0009] Preferably, the base is formed by welding No. 1 steel plate, No. 2 steel plate, No. 3 steel plate and No. 4 steel plate. The planar shapes of No. 1 steel plate and No. 2 steel plate are rectangular, the planar shapes of No. 3 steel plate and No. 4 steel plate are trapezoidal, and a concave pillow for fixing the jack is welded on No. 2 steel plate.
[0010] Preferably, the No. 1 steel plate used for welding the pedestal is embedded in the crown beam or waist beam, steel bars are welded on the No. 1 steel plate, the steel bars are perpendicular to the plate surface of the No. 1 steel plate, the embedded direction of the steel bars is perpendicular to the side of the crown beam or waist beam, and is fixed to the steel cage of the crown beam or waist beam with steel wire, the corbel is in the shape of a straight triangular prism, the corbel is arranged on the crown beam or waist beam, and a No. 1 steel plate is embedded in the position of the corbel.
[0011] Preferably, the branches of the steel lattice column are angle steels, and the tie materials are steel plates, on which a pallet is welded. The pallet consists of a panel and eight triangular steel plates. No tie materials are welded within a distance above the pallet that is not the first support and is the same height as the foundation pit support beam section, and four branch members in this range are reinforced with four angle steels; the first support is directly placed on the pallet at the top of the steel lattice column, and the non-first support is placed on the pallet after passing through the steel lattice column.
[0012] The method for dismantling the assembled reinforced concrete foundation pit support system which is easy to dismantle comprises the following steps: 1) Prepare the wire saw cutting machine, support frame, crane, grabber and truck; 2) Set up a support frame at the bottom of the lowest support; 3) After the support frame is erected, analyze the pressure of the horizontal foundation pit support beam section and the longitudinal foundation pit support beam section, reduce the pressure of all the jacks in the direction with less pressure, and remove them after the pressure drops to 0. After removing the jacks, use a cutting machine to cut the cap; 4) After the cutting of the cap of the opposite support in the direction with less pressure is completed, the foundation pit support beam sections and the foundation pit support eight-shaped beams at both ends of the opposite support in the direction with less pressure are dismantled by a grab machine; 5) After the foundation pit support beam sections and the foundation pit support S-shaped beams at both ends of the brace in the direction of less pressure are dismantled, the outermost brace in the direction of greater pressure is dismantled, and the jack of the outermost brace in the direction of greater pressure is depressurized and removed after the pressure reaches 0. After removing the jack, use a cutting machine to cut the cap, and use a grab to dismantle the foundation pit support beam sections and the foundation pit support S-shaped beams of the outermost brace in the direction of greater pressure; then use a grab to dismantle the foundation pit support beam sections at both ends of the brace in the direction of less pressure; 6) Repeat the operation in step 5) until the inner support of the bottom support is removed; 7) All dismantled foundation pit support beam sections and foundation pit support beams are hoisted and transported out of the foundation pit and then out of the construction site; the undamaged foundation pit support beam sections and foundation pit support beams are transported back to the factory to wait for the next use, and the damaged foundation pit support beam sections and foundation pit support beams are crushed; 8) Clear the blockages at both ends of the second rope threading hole of the supporting waist beam for rope saw cutting. After the cleaning is completed, pass the rope saw chain through the second rope threading hole, start the rope saw cutting machine to cut the waist beam; the cut waist beam is transported out of the site by crane and truck, and is centrally crushed; 9) Repeat steps 2) to 8) to complete the removal of all non-first supports; 10) Set up a support frame at the bottom of the first support; 11) After the support frame is erected, analyze the pressure borne by the horizontal and longitudinal foundation pit support beam sections, and reduce the pressure of all the jacks supporting the direction with less pressure. After the pressure drops to 0, remove them. After removing the jacks, use a cutting machine to cut the cap; 12) After the cutting of the cap of the opposite support in the direction with less pressure is completed, the foundation pit support beam sections and the foundation pit support S-shaped beams at both ends of the opposite support in the direction with less pressure are dismantled by a grab machine; 13) After the foundation pit support beam sections and the foundation pit support S-shaped beams at both ends of the brace in the direction of less pressure are dismantled, the outermost brace in the direction of greater pressure is dismantled, and the jack of the outermost brace in the direction of greater pressure is depressurized and removed after the pressure reaches 0. After removing the jack, use a cutting machine to cut the cap, and use a grab to dismantle the foundation pit support beam sections and the foundation pit support S-shaped beams of the outermost brace in the direction of greater pressure; then use a grab to dismantle the foundation pit support beam sections at both ends of the brace in the direction of less pressure; 14) Repeat the operation in step 13) until the inner support of the first support is removed; 15) All dismantled foundation pit support beam sections and foundation pit support beams are hoisted and transported out of the foundation pit and then transported out of the construction site; the undamaged foundation pit support beam sections and foundation pit support beams are transported back to the factory to wait for the next use, and the damaged ones are crushed; 16) Clear the obstructions at both ends of the first rope threading hole of the supporting crown beam for rope saw cutting. After the cleaning is completed, pass the rope saw chain through the first rope threading hole, start the rope saw cutting machine to cut the crown beam; the cut crown beam is transported out of the site by crane and truck, and is centrally crushed; 17) After the first support is dismantled, the steel lattice columns are cut using a cutting machine, and the cut lattice columns are lifted out of the foundation pit by a crane.
[0013] Preferably, when removing the connection between the foundation pit supporting beam section and the foundation pit supporting S-shaped beam, the foundation pit supporting S-shaped beam is removed first, and then the foundation pit supporting beam section is removed.
[0014] Preferably, after the crown beam and the waist beam are removed, secondary cutting is performed, and the corbel structures on the crown beam and the waist beam are cut off using a rope saw.
[0015] Beneficial Effects Compared with the prior art, the technical solution of this application has the following beneficial technical effects: (1) The present invention proposes an assembled reinforced concrete foundation pit support system that is easy to dismantle. The foundation pit support beam sections and foundation pit support cross-beams are used as components of the foundation pit internal support. The components are connected by inserting reinforcement bars. When dismantling, it is only necessary to pull the internal support components out of the connecting reinforcement bars, so that the foundation pit support components can be completely recycled. This is a major breakthrough in the circular economy in the field of foundation pit support.
[0016] (2) The present invention provides a method for dismantling an assembled reinforced concrete foundation pit support system that is easy to dismantle. The foundation pit support beam section and the foundation pit support S-beam are completely dismantled by using a grab. The main dismantling operations are completed mechanically, with low labor intensity, fast internal support dismantling speed, high safety, shortening the dismantling period of the foundation pit support and greatly reducing the time cost.
[0017] (3) The cross-sectional dimensions of the foundation pit support beam section and the foundation pit support cross-shaped beam of the present invention are the same, which realizes the standardization of the foundation pit support beam section and the foundation pit support cross-shaped beam, making the foundation pit support beam section and the foundation pit support cross-shaped beam not only convenient to dismantle and transport, but also capable of better reuse.
[0018] (4) The present invention adopts a full-life design concept. By arranging rope holes for rope saw cutting in the crown beam or waist beam, it realizes drilling-free on-site rope saw cutting, avoids drilling holes in the crown beam or waist beam with dense steel bars, saves drilling costs and time, and reduces dust pollution. It is a successful implementation of the green demolition concept in the field of foundation pit support and demolition.
[0019] (5) The present invention places a jack as a supporting medium between the inner support and the crown beam or the waist beam. The installation position of the jack provides sufficient gap for the assembly of beam sections, which is convenient for the beam sections to be assembled into a whole through the insertion of reinforcement. After the jack is lifted, the installation gap can be quickly eliminated, so that the support beam is quickly stressed. Multiple jacks can be adjusted together to make the stress and deformation of the support beam close to each other, avoiding excessive local stress and deformation, and achieving visualization of the stress on the support. The pressure of the jack can be adjusted at any time. When dismantling, the jack can be directly removed and recycled after the pressure is reduced to 0. The jack can be reused, which reduces the cost of foundation pit support and speeds up the dismantling of the support in the foundation pit, with good economic benefits.
[0020] (6) The surface of the foundation pit supporting beam section used in the present invention is protected by a beam sleeve, and the surface of the foundation pit supporting cross-shaped beam is protected by a cross-shaped beam sleeve, which prolongs the service life of the foundation pit supporting beam section and the foundation pit supporting cross-shaped beam, reduces the damage rate of the foundation pit supporting beam section and the foundation pit supporting cross-shaped beam, improves the durability of the foundation pit supporting beam section and the foundation pit supporting cross-shaped beam, increases the number of recycling times of the beam section, reduces the cost of a single foundation pit support, and has good economic benefits and environmental protection value. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] Figure 1 It is a schematic diagram of the overall structure of the assembled reinforced concrete foundation pit support system that is easy to dismantle; Figure 2 This is a schematic diagram of the reinforcement structure of the foundation pit support beam section; Figure 3 This is a schematic diagram of the reinforcement structure of the eight-shaped beam supporting the foundation pit; Figure 4 The schematic diagram of the beam sleeve structure of the foundation pit supporting beam section; Figure 5 A schematic diagram of the structure of the splayed beam sleeve for supporting the splayed beam in the foundation pit; Figure 6 It is a schematic diagram of the first support edge structure of the prefabricated reinforced concrete foundation pit support system that is easy to dismantle; Figure 7 It is a schematic diagram of the location of the crown beam cap of the prefabricated reinforced concrete foundation pit support system that is easy to dismantle; Figure 8 It is a schematic diagram of the lower support edge structure of the assembled reinforced concrete foundation pit support system that is easy to dismantle; Fig. 9 It is a schematic diagram of the location of the waist beam cap of the prefabricated reinforced concrete foundation pit support system that is easy to dismantle; Fig.10 It is a schematic diagram of the structural node of the first support inside the prefabricated reinforced concrete foundation pit support system that is easy to dismantle; Fig.11 It is a schematic diagram of the structure of the lower support and inner support node of the assembled reinforced concrete foundation pit support system that is easy to dismantle; Fig.12 is a schematic diagram of the support plane layout in the foundation pit of Example 1; Fig.13 is a schematic diagram of the support plane layout in the foundation pit of Example 2; Fig.14 This is a schematic diagram of the support plane layout in the foundation pit of Example 3.
[0022] In the figure: 1- foundation pit supporting beam section; 101- longitudinal reinforcement hole; 102- transverse reinforcement hole; 103- beam sleeve; 103-1- side steel plate; 103-2- end steel plate; 2- foundation pit supporting eight-shaped beam; 201- eight-shaped beam reinforcement hole; 202- eight-shaped beam sleeve; 3-1- first rope threading hole; 3-2- second rope threading hole; 4- jack; 5- cap; 501- No. 1 steel plate; 502- reinforcement; 503- No. 2 steel plate; 504- No. 3 steel plate; 505- No. 4 steel plate; 506- concave pillow; 6- waist beam; 7- corbel; 8- crown beam; 9- steel lattice column; 10- tray; 10-1- panel; 10-2- triangular steel plate; 11- rope saw chain; 12- connecting reinforcement; 13- support pile. DETAILED DESCRIPTION
[0023] The following will clearly and completely describe the technical solutions in the embodiments of the present invention in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention (the top support is the first support, and the second support, the third support, and the bottom support of the bottom layer are sequentially obtained).
[0024] In the embodiment, Figure 1-14Provided is an assembled reinforced concrete foundation pit support system that is easy to dismantle, wherein the inner support is in the form of an orthogonal bracing arrangement, and the assembled reinforced concrete foundation pit support system that is easy to dismantle comprises an inner support system, a crown beam 8, a waist beam 6 and a steel lattice column 9, and is characterized in that: the inner support system is formed by splicing a plurality of foundation pit support beam sections 1 and a plurality of foundation pit support eight-shaped beams 2, wherein the plurality of foundation pit support beam sections 1 have the same length and cross-sectional dimensions, and the plurality of foundation pit support eight-shaped beams 2 have the same length and cross-sectional dimensions; a beam sleeve 103 is provided on the surface of the foundation pit support beam section 1, and a Side steel plate 103-1, the tube walls of both ends of the preset transverse embedded pipe are respectively welded on the hole walls of the side steel plates 103-1 on both sides to form transverse inserted steel bar holes 102, both ends of the foundation pit support beam section 1 are provided with end face steel plates 103-2, one end of the preset longitudinal embedded pipe is welded on the inner wall of the hole of the end face steel plate 103-2 to form a longitudinal inserted steel bar hole 101, one end of the foundation pit support eight-shaped beam 2 is a right-angle end, and the other end is an oblique angle end, the surface of the foundation pit support eight-shaped beam 2 is provided with an eight-shaped beam sleeve 202, and the oblique angle end is provided with an eight-shaped beam inserted steel bar hole 201; When two foundation pit support beam segments 1 are axially connected, the end face steel plates 103-2 of the two foundation pit support beam segments 1 are seamlessly fitted, the longitudinal reinforcing bar holes 101 of the two foundation pit support beam segments 1 are aligned one by one, and there are connecting steel bars 12 in the longitudinal reinforcing bar holes 101; when four foundation pit support beam segments 1 are cross-connected or three foundation pit support beam segments 1 are T-connected, after two foundation pit support beam segments 1 are axially connected, they are vertically intersected with another one or two foundation pit support beam segments 1 at the axial connection, and at the vertical intersection, the longitudinal reinforcing bar holes 101 of one or two foundation pit support beam segments 1 are aligned one by one with the transverse reinforcing bar holes 102 at the axial connection of the two foundation pit support beam segments 1, and there are connecting steel bars 12 in the transverse reinforcing bar holes 102; The connection between the foundation pit support beam section 1 and the foundation pit support cross-shaped beam 2 includes that after the two foundation pit support beam sections 1 are axially connected, they are butted with the beveled ends of the foundation pit support cross-shaped beam 2 at the axial connection, at the connection between the foundation pit support beam section 1 and the foundation pit support cross-shaped beam 2, the cross-shaped beam reinforcement holes 201 are aligned one by one with the transverse reinforcement holes 102 at the axial connection of the two foundation pit support beam sections 1, and there are connecting steel bars 12 in the transverse reinforcement holes 102; The foundation pit is provided with a crown beam 8 and a waist beam 6, and a pedestal 5 and a corbel 7 are provided on the crown beam 8 and the waist beam 6. The foundation pit supporting beam section 1 at the edge of the internal support system and one end of the foundation pit supporting S-shaped beam 2 are placed on the pedestal 5. A jack 4 is arranged between the internal support system and the crown beam 8 or the waist beam 6, and the jack 4 is placed on the pedestal 5; a tray 10 is arranged below the connection of the foundation pit supporting beam section 1, and the tray 10 is welded to the steel lattice column 9 below.
[0025] There are two rows of longitudinal rebar holes 101 and one row of transverse rebar holes at the end of the foundation pit supporting beam section 1; the distance between the two rows of longitudinal rebar holes 101 is equal to twice the distance between the transverse rebar holes 102 and the end steel plate 103-2, the vertical spacing between adjacent longitudinal rebar holes 101 or transverse rebar holes 102 is the same, and the distance between the uppermost longitudinal rebar hole 101 and the upper edge of the beam sleeve 103 is equal to the distance between the lowermost transverse rebar hole 102 and the lower edge of the beam sleeve 103.
[0026] The spacing between the two rows of S-beam rebar insertion holes 201 is equal to twice the distance between the transverse rebar insertion holes 102 and the end steel plate 103-2 of the foundation pit supporting beam section 1, the distance from the top S-beam rebar insertion hole 201 to the upper edge of the foundation pit supporting S-beam 2 is equal to the distance from the top transverse rebar insertion hole 102 to the upper edge of the foundation pit supporting beam section 1, and the spacing between vertically adjacent S-beam rebar insertion holes 201 is the same as the spacing between vertically adjacent transverse rebar insertion holes 102.
[0027] The diameters of the transverse reinforcing bar insertion holes 102, the longitudinal reinforcing bar insertion holes 101 and the cross-beam reinforcing bar insertion holes 201 are the same.
[0028] Preferably, the crown beam 8 is provided with a first rope threading hole 3-1 for rope saw cutting, and the first rope threading hole 3-1 is formed by an L-shaped PVC pipe pre-buried in the crown beam 8, and both ends of the L-shaped PVC pipe are open, one end opening is located on the side of the crown beam 8, and the other end opening is located on the top surface of the crown beam 8; the waist beam 6 is provided with a second rope threading hole 3-2 for rope saw cutting, and the second rope threading hole 3-2 is formed by a straight PVC pipe vertically pre-buried in the waist beam 6, and both ends of the straight PVC pipe are open, one end opening is located on the top surface of the waist beam 6, and the other end opening is located on the bottom surface of the waist beam 6, and the straight PVC pipe is pre-buried on the side of the waist beam 6 close to the supporting pile 13.
[0029] The diameters of the first and second rope holes 3-1 and 3-2 for rope saw cutting are 15 mm-20 mm; the first rope hole 3-1 is set on the crown beam 8 and the waist beam 6 starting from 2.5 m-5 m away from the corner point of the foundation pit, and a second rope hole 3-2 for rope saw cutting is set every 2.5 m-5 m.
[0030] The base 5 is formed by welding No. 1 steel plate 501, No. 2 steel plate 503, No. 3 steel plate 504, and No. 4 steel plate 505. The planar shapes of No. 1 steel plate 501 and No. 2 steel plate 503 are rectangular, the planar shapes of No. 3 steel plate 504 and No. 4 steel plate 505 are trapezoidal, and a concave pillow 506 for fixing the jack 4 is welded on No. 2 steel plate 503.
[0031] The No. 1 steel plate 501 used for welding the base 5 is embedded in the crown beam 8 or the waist beam 6, and the steel bar 502 is welded on the No. 1 steel plate 501. The steel bar 502 is perpendicular to the plate surface of the No. 1 steel plate 501. The embedded direction of the steel bar 502 is perpendicular to the side of the crown beam 8 or the waist beam 6, and is fixed to the steel cage of the crown beam 8 or the waist beam 6 with steel wire. The corbel 7 is in the shape of a straight triangular prism, and the corbel 7 is arranged on the crown beam 8 or the waist beam 6. The No. 1 steel plate 501 is embedded in the position of the corbel 7.
[0032] The branches of the steel lattice column 9 are angle steels, and the tie materials are steel plates, on which a pallet 10 is welded. The pallet 10 is composed of a panel 10-1 and eight triangular steel plates 10-2. No tie materials are welded within a distance above the pallet that is not the first support and at the same height as the foundation pit support beam section 1, and four angle steels are used to reinforce the four branches in this range; the first support is directly placed on the pallet 10 at the top of the steel lattice column 9, and the non-first support is placed on the pallet 10 after passing through the steel lattice column 9.
[0033] The method for dismantling the assembled reinforced concrete foundation pit support system which is easy to dismantle comprises the following steps: 1) Prepare the wire saw cutting machine, support frame, crane, grabber and truck; 2) Set up a support frame at the bottom of the lowest support; 3) After the support frame is erected, analyze the pressure borne by the horizontal foundation pit support beam section 1 and the longitudinal foundation pit support beam section 1, reduce the pressure of all the jacks 4 in the direction with less pressure, and remove them after the pressure drops to 0. After removing the jacks 4, use a cutting machine to cut the cap 5; 4) After the cap 5 of the opposite support in the direction with less pressure is cut, the foundation pit support beam sections 1 and the foundation pit support cross beams 2 at both ends of the opposite support in the direction with less pressure are dismantled by a grab machine; 5) After the foundation pit support beam sections 1 and the foundation pit support S-shaped beams 2 at both ends of the brace in the direction of less pressure are dismantled, the outermost brace in the direction of greater pressure is dismantled, and the jack 4 of the outermost brace in the direction of greater pressure is depressurized and removed after the pressure reaches 0. After the jack 4 is removed, the cap 5 is cut with a cutting machine, and the foundation pit support beam sections 1 and the foundation pit support S-shaped beams 2 of the outermost brace in the direction of greater pressure are dismantled with a grab; then the foundation pit support beam sections 1 at both ends of the brace in the direction of less pressure are dismantled with a grab; 6) Repeat the operation in step 5) until the inner support of the bottom support is removed; 7) All dismantled foundation pit support beam sections 1 and foundation pit support cross-shaped beams 2 are hoisted and transported out of the foundation pit and then out of the construction site; the undamaged foundation pit support beam sections 1 and foundation pit support cross-shaped beams 2 are transported back to the factory to wait for the next use, and the damaged foundation pit support beam sections 1 and foundation pit support cross-shaped beams 2 are crushed; 8) Clear the obstructions at both ends of the second rope threading hole 3-2 of the supporting waist beam 6 for rope saw cutting. After the cleaning is completed, the rope saw chain 11 is passed through the second rope threading hole 3-2, and the rope saw cutting machine is started to cut the waist beam 6; the cut waist beam 6 is transported out of the site by crane and truck, and is centrally crushed; 9) Repeat steps 2) to 8) to complete the removal of all non-first supports; 10) Set up a support frame at the bottom of the first support; 11) After the support frame is erected, analyze the pressure borne by the horizontal foundation pit support beam section 1 and the longitudinal foundation pit support beam section 1, reduce the pressure of all the jacks 4 in the direction with less pressure, and remove them after the pressure drops to 0. After removing the jacks 4, use a cutting machine to cut the cap 5; 12) After the cutting of the cap 5 of the opposite support in the direction with less pressure is completed, the foundation pit support beam sections 1 and the foundation pit support cross beam 2 at both ends of the opposite support in the direction with less pressure are dismantled by a grab machine; 13) After the foundation pit support beam sections 1 and the foundation pit support S-shaped beams 2 at both ends of the brace in the direction of less pressure are dismantled, the outermost brace in the direction of greater pressure is dismantled, and the jack 4 of the outermost brace in the direction of greater pressure is depressurized and removed after the pressure reaches 0. After the jack 4 is removed, the cap 5 is cut with a cutting machine, and the foundation pit support beam sections 1 and the foundation pit support S-shaped beams 2 of the outermost brace in the direction of greater pressure are dismantled with a grab; then the foundation pit support beam sections 1 at both ends of the brace in the direction of less pressure are dismantled with a grab; 14) Repeat the operation in step 13) until the inner support of the first support is removed; 15) All dismantled foundation pit support beam sections 1 and foundation pit support cross-shaped beams 2 are hoisted and transported out of the foundation pit and then out of the construction site; the undamaged foundation pit support beam sections 1 and foundation pit support cross-shaped beams 2 are transported back to the factory to wait for the next use, and the damaged ones are crushed; 16) Clear the obstructions at both ends of the first rope threading hole 3-1 of the supporting crown beam 8 for rope saw cutting. After the cleaning is completed, the rope saw chain 11 is passed through the first rope threading hole 3-1, and the rope saw cutting machine is started to cut the crown beam 8; the cut crown beam 8 is transported out of the site by crane and truck, and is centrally crushed; 17) After the first support is dismantled, the steel lattice column 9 is cut using a cutting machine, and the cut lattice column 9 is lifted out of the foundation pit by a crane.
[0034] Preferably, when removing the connection between the foundation pit supporting beam section 1 and the foundation pit supporting cross-shaped beam 2, the foundation pit supporting cross-shaped beam 2 is removed first, and then the foundation pit supporting beam section 1 is removed.
[0035] Preferably, after the crown beam 8 and the waist beam 6 are removed, secondary cutting is performed, and the corbel 7 structures on the crown beam 8 and the waist beam 6 are cut and removed using a rope saw.
[0036] Example 1 like Fig.12 As shown in the figure, a rectangular foundation pit has a size of 148 m long and 80 m wide. The internal support adopts a tic-tac-toe arrangement, with 4 horizontal braces and 8 vertical braces. The end faces of the foundation pit support beam sections of the vertical braces are seamlessly fitted. The foundation pit is designed to have 4 layers of internal support. The sizes of the foundation pit support beam sections are all the same. The cross-sectional dimensions of the foundation pit support beam sections are 1000 mm wide and 800 mm high. The length of the foundation pit support beam sections is 5000 mm. The sizes of the foundation pit support eight-shaped beams are all the same. The cross-sectional dimensions of the foundation pit support eight-shaped beams are 1000 mm wide and 800 mm high. The angle of the bevel end is 45° and the length is 6.98 m. The cross-sectional dimensions of the crown beam are 1.2 m×1 m. A L-shaped rope threading hole with a diameter of 20 mm is set every 3 m in the crown beam. The cross-sectional dimensions of the waist beam are 1 m×1 m. A rope threading hole with a diameter of 20 mm is set every 3 m in the waist beam.
[0037] When removing the foundation pit support, the steps are: 1) Prepare wire saw cutting machine, support frame, crane, grabber (Yonggong YGZ360), truck and other machines, and arrange the location and access channels of the machines according to the site environment.
[0038] 2) Set up a support frame under the fourth support.
[0039] 3) All the lateral supporting jacks are depressurized and removed after the pressure drops to 0. After removing the jacks, use a cutting machine to cut the base.
[0040] 4) After cutting, the foundation pit support beam sections and the foundation pit support S-beams at both ends of the transverse support are grabbed by a grabber and the connecting steel bars are pulled out.
[0041] 5) After the dismantling of both ends of the transverse support is completed, the two outermost rows of longitudinal supports are dismantled. The jacks of the two outermost rows of longitudinal supports are depressurized and removed after the pressure is reduced to 0. After removing the jacks, use a cutting machine to cut the base, and use a grab to pull out the foundation pit support beam sections and foundation pit support S-shaped beams of the two outermost rows of longitudinal supports until the foundation pit support beam sections and foundation pit support S-shaped beams of these two rows of longitudinal supports are completely dismantled; then use a grab to remove the foundation pit support beam sections at both ends of the current transverse support.
[0042] 6) Repeat step 5) to complete the removal of the fourth support.
[0043] 7) All dismantled foundation pit support beam sections and foundation pit support cross-beams are transported out of the foundation pit by crane and then transported out of the construction site by truck; the undamaged foundation pit support beam sections and foundation pit support cross-beams are transported back to the factory to wait for the next use, and the damaged ones are crushed.
[0044] 8) Set up a support frame under the waist beam of the fourth support, remove the sealing plaster from the rope hole of the waist beam of the fourth support, pass the chain of the rope saw cutting machine through the rope hole, turn on the rope saw cutting machine, and start rope saw cutting of the waist beam. First cut vertically along the axis of the waist beam, and then cut parallel to the axis of the waist beam. Multiple points can be cut simultaneously until the waist beam of the fourth support beam is completely removed. After removal, the waist beam section is cut for the second time in the foundation pit, and the top beam block of the waist beam is removed by rope saw cutting or cutting machine, so that it can be transported out of the site by truck for centralized crushing.
[0045] 9) After the fourth support is removed, repeat steps 2) to 8) to complete the removal of the second and third supports; 10) Set up a support frame under the first support.
[0046] 11) All the lateral supporting jacks are depressurized and removed after the pressure drops to 0. After removing the jacks, use a cutting machine to cut the base.
[0047] 12) After cutting, the foundation pit support beam sections and the foundation pit support S-beams at both ends of the transverse support are grabbed by a grabber and the connecting steel bars are pulled out.
[0048] 13) After the dismantling of both ends of the transverse support is completed, the two outermost rows of longitudinal supports are dismantled. The jacks of the two outermost rows of longitudinal supports are depressurized and removed after the pressure is reduced to 0. After removing the jacks, use a cutting machine to cut the base, and use a grab to pull out the foundation pit support beam sections and foundation pit support S-beams of the two outermost rows of longitudinal supports until the foundation pit support beam sections and foundation pit support S-beams of these two rows of longitudinal supports are completely dismantled; then use a grab to remove the foundation pit support beam sections at both ends of the current transverse support.
[0049] 14) Repeat step 13) to complete the removal of the first support.
[0050] 15) All dismantled foundation pit support beam sections and foundation pit support cross-beams are transported out of the foundation pit by crane and then transported out of the construction site by truck; the undamaged foundation pit support beam sections and foundation pit support cross-beams are transported back to the factory to wait for the next use, and the damaged ones are crushed.
[0051] 16) Remove the sealing plaster from the rope threading hole of the crown beam of the first support, pass the chain of the rope saw cutting machine through the rope threading hole, turn on the rope saw cutting machine, and start rope saw cutting of the crown beam. First cut vertically along the axis of the crown beam, and then cut parallel to the axis of the crown beam. Multiple points can be cut simultaneously until the crown beam of the first support beam is completely removed. After removal, the crown beam section is cut for the second time in the foundation pit, and the top beam block of the crown beam is removed by rope saw, so that it can be transported out of the site by truck for centralized crushing and processing.
[0052] 17) Use a cutting machine to cut the steel lattice columns. The cut steel lattice columns are lifted out of the foundation pit by a crane and transported out of the construction site by truck.
[0053] Example 2 like Fig.13 As shown in the figure, an L-shaped foundation pit has an upper length of 165 m, an upper length of 79 m on the left, a lower length of 40 m on the left, a right length of 119 m, a lower length of 106 m on the left, and a lower length of 59 m on the right. The inner support of the foundation pit adopts a tic-tac-toe arrangement, with 6 horizontal braces and 9 vertical braces. The end faces of the foundation pit support beam sections of the vertical braces are seamlessly fitted. The design of the foundation pit internal support is 2 layers. The dimensions of the foundation pit support beam sections are all the same. The cross-sectional dimensions of the foundation pit support beam sections in the standard area are 1000 mm wide and 800 mm high. The length of the foundation pit support beam sections is 5000 mm. The dimensions of the foundation pit support eight-shaped beams are all the same. The cross-sectional dimensions of the foundation pit support eight-shaped beams are 1000 mm wide and 800 mm high. The angle of the bevel end is 45° and the length is 6.98 m. The cross-sectional dimensions of the crown beam are 1.2 m×1 m. An L-shaped rope threading hole with a diameter of 20 mm is set every 3 m in the crown beam. The cross-sectional dimensions of the waist beam are 0.8 m×0.8 m, and a rope threading hole with a diameter of 15 mm is set every 4 m in the waist beam.
[0054] When removing the foundation pit support, the steps are: 1) Prepare wire saw cutting machine, support frame, crane, truck, grabber (Yonggong YGZ360) and other machines and tools, and arrange the location and access channels of the machines and tools according to the site environment.
[0055] 2) Set up a support frame under the second support.
[0056] 3) All the lateral supporting jacks are depressurized and removed after the pressure drops to 0. After removing the jacks, use a cutting machine to cut the base.
[0057] 4) After cutting, the foundation pit support beam sections and the foundation pit support S-beams at both ends of the transverse support are grabbed by a grabber and the connecting steel bars are pulled out.
[0058] 5) After the dismantling of both ends of the transverse support is completed, the two outermost rows of longitudinal supports are dismantled. The jacks of the two outermost rows of longitudinal supports are depressurized and removed after the pressure is reduced to 0. After removing the jacks, use a cutting machine to cut the base, and use a grab to pull out the foundation pit support beam sections and foundation pit support S-shaped beams of the two outermost rows of longitudinal supports until the foundation pit support beam sections and foundation pit support S-shaped beams of these two rows of longitudinal supports are completely dismantled; then use a grab to remove the foundation pit support beam sections at both ends of the current transverse support.
[0059] 6) Repeat step 5) to complete the removal of the second support.
[0060] 7) All dismantled foundation pit support beam sections and foundation pit support cross-beams are transported out of the foundation pit by crane and then transported out of the construction site by truck; the undamaged foundation pit support beam sections and foundation pit support cross-beams are transported back to the factory to wait for the next use, and the damaged ones are crushed.
[0061] 8) Set up a support frame under the waist beam of the second support, remove the sealing plaster from the rope hole of the waist beam of the second support, pass the chain of the rope saw cutting machine through the rope hole, turn on the rope saw cutting machine, and start rope saw cutting of the waist beam. First cut vertically along the axis of the waist beam, and then cut parallel to the axis of the waist beam. Multiple points can be cut simultaneously until the waist beam of the second support beam is completely removed. After removal, the waist beam section is cut for the second time in the foundation pit. Use rope saw cutting or cutting machine cutting to remove the top beam block of the waist beam, so that it can be transported out of the site by truck for centralized crushing and processing.
[0062] 9) Set up a support frame under the first support.
[0063] 10) All the lateral supporting jacks are depressurized and removed after the pressure drops to 0. After removing the jacks, use a cutting machine to cut the base.
[0064] 11) After cutting, the foundation pit support beam sections and the foundation pit support S-beams at both ends of the transverse support are grabbed by a grabber and the connecting steel bars are pulled out.
[0065] 12) After the dismantling of both ends of the transverse support is completed, the two outermost rows of longitudinal supports are dismantled. The jacks of the two outermost rows of longitudinal supports are depressurized and removed after the pressure is reduced to 0. After removing the jacks, use a cutting machine to cut the base, and use a grab to pull out the foundation pit support beam sections and foundation pit support S-beams of the two outermost rows of longitudinal supports until the foundation pit support beam sections and foundation pit support S-beams of these two rows of longitudinal supports are completely dismantled; then use a grab to remove the foundation pit support beam sections at both ends of the current transverse support.
[0066] 13) Repeat step 12) to complete the removal of the first support.
[0067] 14) All dismantled foundation pit support beam sections and foundation pit support cross-beams are transported out of the foundation pit by crane and then transported out of the construction site by truck; the undamaged foundation pit support beam sections and foundation pit support cross-beams are transported back to the factory to wait for the next use, and the damaged ones are crushed.
[0068] 15) Remove the sealing plaster from the rope threading hole of the crown beam of the first support, pass the chain of the rope saw cutting machine through the rope threading hole, turn on the rope saw cutting machine, and start rope saw cutting of the crown beam. First cut vertically along the axis of the crown beam, and then cut parallel to the axis of the crown beam. Multiple points can be cut simultaneously until the crown beam of the first support beam is completely removed. After removal, the crown beam section is cut for the second time in the foundation pit, and the top beam block of the crown beam is removed by rope saw, so that it can be transported out of the site by truck for centralized crushing and processing.
[0069] 16) Use a cutting machine to cut the steel lattice columns. The cut steel lattice columns are lifted out of the foundation pit by a crane and transported out of the construction site by truck.
[0070] Example 3 like Fig.14 As shown in the figure, a rectangular foundation pit has a size of 110 m long and 58 m wide. The internal support adopts a tic-tac-toe arrangement, with 3 horizontal braces and 6 vertical braces. The end faces of the foundation pit support beam sections of the horizontal braces are seamlessly fitted. The foundation pit is designed to have two layers of internal support. The sizes of the foundation pit support beam sections are all the same. The cross-sectional dimensions of the foundation pit support beam sections are 1000 mm wide and 800 mm high. The length of the foundation pit support beam sections is 5000 mm. The sizes of the foundation pit support eight-shaped beams are all the same. The cross-sectional dimensions of the foundation pit support eight-shaped beams are 1000 mm wide and 800 mm high. The angle of the bevel end is 45° and the length is 6.98 m. The cross-sectional dimensions of the crown beam are 1.2 m×1 m. A 20 mm diameter L-shaped rope threading hole is set every 4 m in the crown beam. The cross-sectional dimensions of the waist beam are 1 m×1 m. A 15 mm diameter rope threading hole is set every 4 m in the waist beam.
[0071] When removing the foundation pit support, the steps are: 1) Prepare wire saw cutting machine, support frame, crane, grabber (Yonggong YGZ360), truck and other machines, and arrange the location and access channels of the machines according to the site environment.
[0072] 2) Set up a support frame under the second support.
[0073] 3) All longitudinal supporting jacks are depressurized and removed after the pressure drops to 0. After removing the jacks, use a cutting machine to cut the base.
[0074] 4) After cutting, the foundation pit support beam sections and the foundation pit support S-beams at both ends of the longitudinal support are grabbed by a grabber and the connecting steel bars are pulled out.
[0075] 5) After the dismantling of both ends of the longitudinal supports is completed, the two outermost rows of horizontal supports are dismantled. The jacks of the two outermost rows of horizontal supports are depressurized and removed after the pressure is reduced to 0. After removing the jacks, use a cutting machine to cut the base, and use a grab to pull out the foundation pit support beam sections and foundation pit support S-beams of the two outermost rows of longitudinal supports, until the foundation pit support beam sections and foundation pit support S-beams of these two rows of horizontal supports are completely dismantled; then use a grab to remove the foundation pit support beam sections at both ends of the current horizontal supports.
[0076] 6) Repeat step 5) to complete the removal of the second support.
[0077] 7) All dismantled foundation pit support beam sections and foundation pit support cross-beams are transported out of the foundation pit by crane and then transported out of the construction site by truck; the undamaged foundation pit support beam sections and foundation pit support cross-beams are transported back to the factory to wait for the next use, and the damaged ones are crushed.
[0078] 8) Set up a support frame under the waist beam of the second support, remove the sealing plaster of the rope hole of the waist beam of the second support, pass the chain of the rope saw cutting machine through the rope hole, turn on the rope saw cutting machine, and start rope saw cutting of the waist beam. First cut vertically to the axis of the waist beam, and then cut parallel to the axis of the waist beam. Multiple points can be cut simultaneously until the waist beam of the second support beam is completely removed. After removal, the waist beam section is cut for the second time in the foundation pit, and the top beam block of the waist beam is removed by rope saw cutting or cutting machine to facilitate transportation by truck; the site is centrally crushed and processed.
[0079] 9) Set up a support frame under the first support.
[0080] 10) All longitudinal supporting jacks are depressurized and removed after the pressure drops to 0. After removing the jacks, use a cutting machine to cut the base.
[0081] 11) After cutting, the foundation pit support beam sections and the foundation pit support S-beams at both ends of the longitudinal support are grabbed by a grabber and the connecting steel bars are pulled out.
[0082] 12) After the dismantling of both ends of the longitudinal supports is completed, the two outermost rows of transverse supports are dismantled. The jacks of the two outermost rows of transverse supports are depressurized and removed after the pressure is reduced to 0. After removing the jacks, use a cutting machine to cut the base, and use a grab to pull out the foundation pit support beam sections and foundation pit support S-shaped beams of the two outermost transverse longitudinal supports until the foundation pit support beam sections and foundation pit support S-shaped beams of these two rows of transverse supports are completely dismantled; then use a grab to remove the foundation pit support beam sections at both ends of the current longitudinal supports.
[0083] 13) Repeat step 12) to complete the removal of the first support.
[0084] 14) All dismantled foundation pit support beam sections and foundation pit support cross-beams are transported out of the foundation pit by crane and then transported out of the construction site by truck; the undamaged foundation pit support beam sections and foundation pit support cross-beams are transported back to the factory to wait for the next use, and the damaged ones are crushed.
[0085] 15) Remove the sealing plaster from the rope threading hole of the crown beam of the first support, pass the chain of the rope saw cutting machine through the rope threading hole, turn on the rope saw cutting machine, and start rope saw cutting of the crown beam. First cut vertically along the axis of the crown beam, and then cut parallel to the axis of the crown beam. Multiple points can be cut simultaneously until the crown beam of the first support beam is completely removed. After removal, the crown beam section is cut for the second time in the foundation pit, and the top beam block of the crown beam is removed by rope saw, so that it can be transported out of the site by truck for centralized crushing and processing.
[0086] 16) Use a cutting machine to cut the steel lattice columns. The cut steel lattice columns are lifted out of the foundation pit by a crane and transported out of the construction site by truck.
[0087] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the sentence "comprise a ..." do not exclude the existence of other identical elements in the process, method, article or device including the elements.
[0088] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. An assembled reinforced concrete foundation pit support system that is easy to dismantle, comprising an internal support system, a crown beam (8), a waist beam (6) and a steel lattice column (9), characterized in that: The internal support system is formed by splicing a plurality of foundation pit support beam sections (1) and a plurality of foundation pit support cross-shaped beams (2); the plurality of foundation pit support beam sections (1) have the same length and cross-sectional dimensions; the plurality of foundation pit support cross-shaped beams (2) have the same length and cross-sectional dimensions; a beam sleeve (103) is provided on the surface of the foundation pit support beam section (1); a side steel plate (103-1) is provided on the beam sleeve (103); the pipe walls of both ends of the preset transverse embedded pipe are respectively welded to the holes of the side steel plates (103-1) on both sides; A transverse reinforcement hole (102) is formed on the wall, end steel plates (103-2) are provided at both ends of the foundation pit support beam section (1), a pipe wall of one end of a preset longitudinal embedded pipe is welded to the inner wall of the hole of the end steel plate (103-2) to form a longitudinal reinforcement hole (101), one end of the foundation pit support eight-shaped beam (2) is a right-angle end, and the other end is an oblique angle end, an eight-shaped beam sleeve (202) is provided on the surface of the foundation pit support eight-shaped beam (2), and an eight-shaped beam reinforcement hole (201) is provided at the oblique angle end; When two foundation pit support beam segments (1) are axially connected, the end steel plates (103-2) of the two foundation pit support beam segments (1) are seamlessly attached, the longitudinal reinforcement holes (101) of the two foundation pit support beam segments (1) are aligned one by one, and the longitudinal reinforcement holes (101) contain connecting steel bars (12); when four foundation pit support beam segments (1) are connected in a cross shape or three foundation pit support beam segments (1) are connected in a T shape, after the two foundation pit support beam segments (1) are axially connected, they are vertically connected with another one or two foundation pit support beam segments (1) at the axial connection, and at the vertical intersection, the longitudinal reinforcement holes (101) of one or two foundation pit support beam segments (1) are aligned one by one with the transverse reinforcement holes (102) at the axial connection of the two foundation pit support beam segments (1), and the transverse reinforcement holes (102) contain connecting steel bars (12); The connection between the foundation pit support beam section (1) and the foundation pit support cross-beam (2) comprises that after the two foundation pit support beam sections (1) are axially connected, they are butted against the beveled ends of the foundation pit support cross-beam (2) at the axial connection, and at the connection between the foundation pit support beam section (1) and the foundation pit support cross-beam (2), the cross-beam reinforcement holes (201) are aligned one by one with the transverse reinforcement holes (102) at the axial connection of the two foundation pit support beam sections (1), and connecting steel bars (12) are provided in the transverse reinforcement holes (102); The foundation pit is provided with a crown beam (8) and a waist beam (6), and a cap (5) and a corbel (7) are provided on the crown beam (8) and the waist beam (6). The foundation pit support beam section (1) at the edge of the internal support system and one end of the foundation pit support eight-shaped beam (2) are placed on the cap (5), and a jack (4) is provided between the internal support system and the crown beam (8) or the waist beam (6), and the jack (4) is placed on the cap (5); a tray (10) is provided below the connection of the foundation pit support beam section (1), and the tray (10) is welded to the steel lattice column (9) below.
2. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The end of the foundation pit support beam section (1) has two rows of longitudinal reinforcement holes (101) and one row of transverse reinforcement holes; the distance between the two rows of longitudinal reinforcement holes (101) is equal to twice the distance between the transverse reinforcement holes (102) and the end steel plate (103-2); the vertical spacing between adjacent longitudinal reinforcement holes (101) or transverse reinforcement holes (102) is the same; the distance between the uppermost longitudinal reinforcement hole (101) and the upper edge of the beam sleeve (103) is equal to the distance between the lowermost transverse reinforcement hole (102) and the lower edge of the beam sleeve (103); The spacing between the two rows of bar insertion holes (201) of the splayed beams is equal to twice the distance between the transverse bar insertion holes (102) and the end surface steel plate (103-2) of the foundation pit support beam section (1); the distance between the uppermost bar insertion hole (201) of the splayed beam and the upper edge of the foundation pit support splayed beam (2) is equal to the distance between the uppermost transverse bar insertion hole (102) and the upper edge of the foundation pit support beam section (1); and the spacing between the vertically adjacent bar insertion holes (201) and the vertically adjacent transverse bar insertion holes (102) are the same.
3. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The diameters of the transverse reinforcement insertion holes (102), the longitudinal reinforcement insertion holes (101) and the cross-beam reinforcement insertion holes (201) are the same.
4. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The crown beam (8) is provided with a first rope threading hole (3-1) for rope saw cutting. The first rope threading hole (3-1) is formed by an L-shaped PVC pipe pre-buried in the crown beam (8). The L-shaped PVC pipe has openings at both ends, one end of which is located on the side of the crown beam (8) and the other end of which is located on the top surface of the crown beam (8). The waist beam (6) is provided with a second rope threading hole (3-2) for rope saw cutting. The second rope threading hole (3-2) is formed by a straight PVC pipe pre-buried vertically in the waist beam (6). The straight PVC pipe has openings at both ends, one end of which is located on the top surface of the waist beam (6) and the other end of which is located on the bottom surface of the waist beam (6). The straight PVC pipe is pre-buried on one side of the waist beam (6) close to the supporting pile (13).
5. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The support platform (5) is formed by welding a first steel plate (501), a second steel plate (503), a third steel plate (504), and a fourth steel plate (505); the first steel plate (501) and the second steel plate (503) are rectangular in plan view, the third steel plate (504) and the fourth steel plate (505) are trapezoidal in plan view, and a concave pillow (506) for fixing the jack (4) is welded on the second steel plate (503).
6. The easily dismantled assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The No. 1 steel plate (501) used for welding the cap (5) is embedded in the crown beam (8) or the waist beam (6), and the steel bars (502) are welded on the No. 1 steel plate (501). The steel bars (502) are perpendicular to the plate surface of the No. 1 steel plate (501). The embedding direction of the steel bars (502) is perpendicular to the side of the crown beam (8) or the waist beam (6), and the steel bars (502) are fixed to the steel cage of the crown beam (8) or the waist beam (6) with steel wires. The corbel (7) is in the shape of a straight triangular prism. The corbel (7) is arranged on the crown beam (8) or the waist beam (6), and the No. 1 steel plate (501) is embedded in the position of the corbel (7).
7. The assembled reinforced concrete foundation pit support system according to claim 1 is characterized in that: The branch members of the steel lattice column (9) are angle steels, and the tie members are steel plates, on which a tray (10) is welded. The tray (10) is composed of a panel (10-1) and eight triangular steel plates (10-2). No tie members are welded within a distance equal to the height of the foundation pit support beam section (1) above the tray that is not the first support, and four angle steels are used to reinforce the four branch members in this range. The first support is directly placed on the tray (10) at the top of the steel lattice column (9), and the non-first support passes through the steel lattice column (9) and is placed on the tray (10).
8. The method for dismantling the easily dismantled assembled reinforced concrete foundation pit support system according to any one of claims 1 to 7, characterized in that: The following steps are involved: 1) Prepare the wire saw cutting machine, support frame, crane, grabber and truck; 2) Set up a support frame at the bottom of the lowest support; 3) After the support frame is erected, the pressure borne by the transverse foundation pit support beam section (1) and the longitudinal foundation pit support beam section (1) is analyzed, and the pressure of the jacks (4) supporting the direction with less pressure is reduced. After the pressure drops to 0, they are removed. After the jacks (4) are removed, the cap (5) is cut using a cutting machine; 4) After the cap (5) of the opposite support in the direction bearing less pressure is cut, the foundation pit support beam sections (1) at both ends of the opposite support in the direction bearing less pressure and the foundation pit support cross beam (2) are dismantled by a grab machine; 5) After the foundation pit support beam sections (1) and the foundation pit support cross-beam (2) at both ends of the support in the direction of less pressure are dismantled, the outermost support in the direction of greater pressure is dismantled, and the jack (4) of the outermost support in the direction of greater pressure is depressurized and removed after the pressure reaches 0. After the jack (4) is removed, the cap (5) is cut using a cutting machine, and the foundation pit support beam sections (1) and the foundation pit support cross-beam (2) of the outermost support in the direction of greater pressure are dismantled using a grabbing machine; and then the foundation pit support beam sections (1) at both ends of the support in the direction of less pressure are dismantled using a grabbing machine; 6) Repeat the operation in step 5) until the inner support of the bottom support is removed; 7) All the removed foundation pit support beam sections (1) and foundation pit support cross beams (2) are hoisted and transported out of the foundation pit and then out of the construction site; the undamaged foundation pit support beam sections (1) and foundation pit support cross beams (2) are transported back to the factory to wait for the next use, and the damaged foundation pit support beam sections (1) and foundation pit support cross beams (2) are crushed; 8) clearing the obstructions at both ends of the second rope threading hole (3-2) of the supporting waist beam (6) for rope saw cutting. After the cleaning is completed, the rope saw chain (11) is passed through the second rope threading hole (3-2), and the rope saw cutting machine is started to cut the waist beam (6); the cut waist beam (6) is transported out of the site by crane and truck, and is centrally crushed; 9) Repeat steps 2) to 8) to complete the removal of all non-first supports; 10) Set up a support frame at the bottom of the first support; 11) After the support frame is erected, the pressure borne by the transverse foundation pit support beam section (1) and the longitudinal foundation pit support beam section (1) is analyzed, and the pressure of the jacks (4) supporting the direction with less pressure is reduced. After the pressure drops to 0, they are removed. After the jacks (4) are removed, the cap (5) is cut using a cutting machine; 12) After the cap (5) of the opposite support in the direction bearing less pressure is cut, the foundation pit support beam sections (1) at both ends of the opposite support in the direction bearing less pressure and the foundation pit support cross beam (2) are dismantled by a grab machine; 13) After the foundation pit support beam sections (1) and the foundation pit support cross-beam (2) at both ends of the support in the direction of less pressure are dismantled, the outermost support in the direction of greater pressure is dismantled, the jack (4) of the outermost support in the direction of greater pressure is depressurized and removed after the pressure reaches 0, after the jack (4) is removed, the cap (5) is cut using a cutting machine, and the foundation pit support beam sections (1) and the foundation pit support cross-beam (2) of the outermost support in the direction of greater pressure are dismantled using a grab; and then the foundation pit support beam sections (1) at both ends of the support in the direction of less pressure are dismantled using a grab; 14) Repeat the operation in step 13) until the inner support of the first support is removed; 15) All the removed foundation pit support beam sections (1) and foundation pit support cross beams (2) are hoisted and transported out of the foundation pit and then out of the construction site; the undamaged foundation pit support beam sections (1) and foundation pit support cross beams (2) are transported back to the factory to wait for the next use, and the damaged ones are crushed; 16) clearing the obstructions at both ends of the first rope threading hole (3-1) of the supporting crown beam (8) for rope saw cutting. After the cleaning is completed, the rope saw chain (11) is passed through the first rope threading hole (3-1), and the rope saw cutting machine is started to cut the crown beam (8); the cut crown beam (8) is transported out of the site by crane and truck, and is centrally crushed; 17) After the first support is dismantled, the steel lattice column (9) is cut using a cutting machine, and the cut lattice column (9) is lifted out of the foundation pit by a crane.
9. The method for dismantling the easily dismantled assembled reinforced concrete foundation pit support system according to claim 8, characterized in that: When removing the connection between the foundation pit support beam section (1) and the foundation pit support cross-beam (2), the foundation pit support cross-beam (2) is first removed, and then the foundation pit support beam section (1) is removed.
10. The method for dismantling the easily dismantled assembled reinforced concrete foundation pit support system according to claim 8, characterized in that: After the crown beam (8) and the waist beam (6) are removed, a secondary cutting is performed, using a rope saw to cut and remove the bracket (7) structure on the crown beam (8) and the waist beam (6).